PROJECT NETWORK DIAGRAM PREPARED BY : NOR AZAH BINTI AZIZ KOLEJ MATRIKULASI TEKNIKAL KEDAH 1 OBJECTIVES • • • • Define Network Diagram Purpose of Network Diagram Method : Activity On the Node (AON) Identify ES, EF, LS, LF using Forward Pass Calculation and Backward Pass calculation • Identify Critical Path • Identify Slack Time 2 INTRODUCTION • A PND is a pictorial representation of the sequence in which the project work can be done. • The activities and its duration are the basic building blocks needed to construct a graphic picture of the project • Its provide - the earliest time at which work can be begin on every activity that makes up the project - the earliest expected completion date of the project 3 IMPORTANCE OF ND • ND can be used for ; i) Planning : gives a clear graphical picture of the relationship between project activities ii) Implementation : when updating the project file with activity status and estimate to completion data, the ND is then automatically updated and can be printed or viewed iii) control : while updated ND will retain the status of all activities, the best graphical report and controlling project work will be Gantt Chart 4 METHODS I) THE ACTIVITY ON THE NODE ( AON) • • • • Basic unit of analysis in ND is the activity Each activity is represented by a rectangle ( activity node) Arrows represent the predecessor/successor relationship between activities Every activity in the project will have its own activity node ( each rectangle) 5 METHODS I) THE ACTIVITY ON THE NODE ( AON) B D A F C E PDM format of a project network diagram 6 METHODS I) THE ACTIVITY ON THE NODE ( AON) Dependencies A dependency is simply a relationship that exists between pairs of activities 4 types of activity dependencies A B FS : A finishes, B start 7 METHODS I) THE ACTIVITY ON THE NODE ( AON) Dependencies A FF : A finishes, B finish B A A SS : A start, B start 8 METHODS I) THE ACTIVITY ON THE NODE ( AON) Dependencies A B SF : A starts, B finish 9 I) THE ACTIVITY ON THE NODE ( AON) 10 I) THE ACTIVITY ON THE NODE ( AON) Creating an initial project network schedule B Start 3 D 5 A 1 F C 2 E 3 End 2 Forward Pass calculations 11 EST, LST, EFT, LFT • CPM uses the following times for an activity EST LST EFT LFT - Early Start time is the earliest time the activity can begin - Late Start Time is the latest time the activity can begin - still allow the project to be completed on time - Early Finish Time is the latest time the activity can end - Late Finish Time is the latest time the activity can end - still allow the project to be completed on time 12 Forward Pass calculations 13 Backward Pass calculations 14 CRITICAL PATH METHOD (CPM) • An effective way to analyze complex projects • Represent the critical set of activities to complete a project • Help to focus on essential activities which are critical to run the project • Allows the project manager to concentrate on important activities • CP is the longest path on ND and the most important part • Any delays on the CP will lead to delay of the project 15 CRITICAL PATH METHOD (CPM) 16 FLOAT • Also known as slack, total float and path float • Is computed for each task by subtracting EFT from the LFT ( @ the early start from the late start) • Is the amount of time the task can slip without delaying the project finish date. • Free float is the amount of time a task can slip without delaying the early start of any task that immediately follows it. 17 Slack Time calculations 18 EXAMPLE 1. TABLE 1 shows the activities and the durations required to complete a construction project, including the precursor activity. Refering to the TABLE 1: i) draw the project network diagram. ii) state the activities on the critical path. iii) calculate the minimum duration of the project. Activity Precursor Duration (week) A - 7 B A 6 C A 5 D A,B 4 E B,C 3 F D,E 2 19 13 4 17 D 13 0 17 0 0 START 0 0 0 7 7 A 0 0 7 7 6 13 B 7 0 13 7 5 12 ES D EF activity C 17 2 19 14 3 16 E F 17 0 19 19 19 END 19 19 14 1 17 9 2 14 LS F LF project network diagram 20