Infrastructure Delivery Management Toolkit: 2010 Edition Delivery Process 1: Portfolio Management Infrastructure Planning: The U-AMP Sonny Schmidt 1 cidb development through partnership The IDMS DP1: Portfolio Management Prov Infr Strat DP1-1 Infrastructure Planning Develop U-AMP Develop C-AMP (including prioritised (including work plans) MTEF works list) DP1-2 Programme Management Dev Proc Strat G1(a) PF1. 3 G1(b) PF1. 4 P C1 PF2. 1 Develop/review IPMP G2 PF2. 2 PF5 Manage Implementation PF2. 3 PF3 PF4 DP2: Project Management DP2-1 Planning (Develop IPIP) Package definitio n Package prep P C2 G3 PF1. 3 Works plannin g G4 DP2-3 Works DP2-2 Design Design develop t. P P C4 C3 a PF1. 4 G5 P C5 MFC Info G6(a) T1 PF2. 1 PF5 Con/Del works G6(b) P C4 b PF2. 2 DP2-4 Close Out Handovr works G7 Project Close Out Update Asset Register G8 T2 PF2. 3 PF3 PF4 DP3: Operations & Maintenance DP3-1 Recognise & accept assets G8 PF1. 3 DP3-2 Mobilisation for Facilities Mgt PF1. 4 DP3-3 Operations PF2. 1 PF5 DP3-4 Maintenance PF2. 2 PF2. 3 DP3-5 Demobilise Facilities Mgt PF3 PF4 User and Custodian Portfolio Management Outputs User organisations Custodian organisations U-AMP Construction procurement strategy IPMP Organisation and Support plan Monitoring reports Recommended actions C-AMP Work Plans Organisation and Support plan Monitoring reports Recommended actions 3 Infrastructure Planning Methodology • What infrastructure / organisational capacity is needed to comply with the organisation’s strategic plan and to support delivery? • What options does the organisaton have for providing the required infrastructure / organisational capacity? • What are the plans (long, medium and short term) for providing the infrastructure / organisational capacity defined in the documented and agreed options. Needs Supply Gap Determine Options • What infrastructure / organisational capacity does the organisation have? • What infrastructure / organisational capacity is required? Alternative Solutions • What alternatives to physical infrastructure / internal organisational capacity can the organisation use / develop? Plans 6 Basic 3 Gaps to be determined: • Space Gaps • Utilisation Gaps • Functional Gaps • Condition Gaps • Efficiency Gaps Other Gaps: • Capacity gaps • Funding Gaps Project Cost Estimating & Budgeting SCOA: Category of Expenditure: – Capital: • • • • Acquisition (new, additions) Upgrading, Alterations, Conversions Renovation, Refurbishment (Rehabilitation) Disposal – Current: • Routine maintenance • Staff, systems Based on Life Cycle Costing 8 Life Cycle Costing (1) • All costs (estimated & actual) over the life cycle of an asset are taken into consideration in order to make future decisions about the asset. • Includes: – capital e.g. initial acquisition cost and future upgrades, – rehabilitations – operations and maintenance 9 Life Cycle Costing (2) 10 Estimate for new infrastructure asset Cost Category Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Infrastructue Asset A 9 000 23 600 42 000 27 400 3 060 3 060 3 060 3 060 3 060 7 140 3 060 3 060 3 060 3 060 7 140 3 060 3 060 3 000 3 000 3 000 3 000 3 000 3 000 3 000 3 000 3 000 3 000 3 000 3 000 3 000 Maintenance Current - - - - Rehabilitation Capital - - - - Acquisition Capital Extension Capital - - - - Upgrading Capital - - - - - - - - - - - - - Disposal Capital - - - - - - - - - - - - - Organisation & Support Current 500 500 500 500 8 500 23 100 41 500 26 900 Acquire/ Develop asset - - - - - 4 000 Capital estimate for - development - of Infrastructure amounts - Asset - A showing required in each financial year 60 60 60 60 60 140 - - - - 4 000 - - Estimate for annualmaintenance - Capital- estimate - for - - - rehabilitation after 5 years of use - - - - - - - - - - - 60 60 60 60 140 - 60 60 Use asset to deliver services 11 Portfolio Budget build up Cos t Ca tegory Infrastructue Asset A Yea r 1 Yea r 2 Yea r 3 Yea r 4 Yea r 5 Yea r 6 Yea r 7 9 000 23 600 42 000 27 400 3 060 3 060 3 060 3 060 7 140 3 060 3 060 3 060 3 060 7 140 3 060 3 060 3 000 3 000 3 000 3 000 3 000 3 000 3 000 3 000 3 000 3 000 3 000 3 000 3 000 Ma i ntena nce Current - - - - Reha bi l i ta ti on Ca pi ta l - - - - Acqui s i ti on Ca pi ta l Extens i on Ca pi ta l - - - - - Upgra di ng Ca pi ta l - - - - - Di s pos a l Ca pi ta l - - - - - Orga ni s a ti on & Support Current 500 500 500 500 60 1 835 1 020 Infrastructue Asset B - 8 500 23 100 41 500 26 900 1 835 1 835 1 835 Yea r 8 Yea r 9 Yea r 10 Yea r 11 Yea r 12 Yea r 13 Yea r 14 Yea r 15 Yea r 16 Yea r 17 3 060 - - - - Capital estimate for - of Infrastructure development Asset - A - - - - - - 60 60 0 0 - 60 60 0 - Current 1 800 1 800 1 800 1 800 - Reha bi l i ta ti on Ca pi ta l - - - - - Acqui s i ti on Ca pi ta l - - - - - Extens i on Ca pi ta l - - - - - - - - - Upgra di ng Ca pi ta l - - - - - - - - Di s pos a l Ca pi ta l - - - - 1 000 - - - Orga ni s a ti on & Support Current - - - 35 35 35 20 820 820 2 450 820 2 560 8 920 11 380 - - - - - - - - - - - - - - - - - 140 0 - 60 0 800 - - 1 600 Acqui s i ti on Ca pi ta l - - - - - - - - Extens i on Ca pi ta l - - - - 1 700 7 940 10 360 - Upgra di ng Ca pi ta l - - - - - Di s pos a l Ca pi ta l - Orga ni s a ti on & Support Current - - - - - - - - 140 0 60 0 60 0 0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1 200 800 - - - - 1 200 800 - - - 1 200 800 1 600 0 - - 1 200 800 - 60 - - 1 200 800 - 60 0 4 000 - 1 230 800 - - Rehabilitation now includes the extension - - - - - - 3 260 1 230 1 230 1 230 1 230 1 200 1 200 1 200 1 200 1 200 - 2 000 - - - - - - - - - - - - - - - - - - - - - - - - - - 20 20 50 20 60 180 220 50 30 30 30 30 60 30 30 30 30 Organisation & Support - Portfolio Management 450 450 450 450 450 450 450 450 450 450 450 450 450 450 450 450 450 Pers onnel Current 250 250 250 250 250 250 250 250 250 250 250 250 250 250 250 250 250 Sys tems Current 200 200 200 200 200 200 200 200 200 200 200 200 200 200 200 200 200 Estimate for organisational Portfolio Management function. This is in addition to identifiable management / supervision of work at specific assets - 60 1 230 Ca pi ta l - - 1 230 Current - - 1 230 Reha bi l i ta ti on - - 2 850 Ma i ntena nce - - - example - B is maintained In this Asset until-Asset A- is operational -after which the organisation disposes of Asset B 35 Asset C is extended in- year 5- - 0 Ma i ntena nce Infrastructue Asset C - - 4 000 - - - 12 “Programme View” of Budget Cost Category Year 1 12 105 Total Infrastructure Estimate Year 2 26 705 Year 3 46 735 Year 4 30 505 Maintenance Current 2 600 2 600 2 600 2 600 Rehabilitation Capital - - 1 600 - Acquisition Capital Extension Capital Upgrading Disposal Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 9 Year 8 Year 7 Year 6 Year 5 7 090 12 430 14 890 6 360 4 740 8 820 4 740 4 740 6 770 4 740 8 820 4 740 4 740 3 800 3 800 3 800 4 200 4 200 4 200 4 200 4 200 4 200 4 200 4 200 4 200 4 200 - - - 1 600 - 7 940 10 360 - - - - 2 000 - - - - - - 4 000 - - - - - 4 000 23 100 41 500 26 900 1 700 - - - - - - - - - - - - - - - - - Capital - - - - - - - - - - - - - - - - - Capital - - - - 1 000 - - - - - - - - - - - - Programme xx yy - - - - - - - - - - - - - - - - - Programme xx yy - - - - - - - - - - - - - - - - - etc. etc - - - - - - - - - - - - - - - - - Organisation & Support Current 8 500 1 005 1 005 1 035 1 005 590 690 730 560 540 620 540 540 570 540 620 540 540 Infrastructure programmes managedby the organisation. Programmes match reporting requirements which are linked to goals and priorities 13 The Need for Budget Revision Project Budget – The “Control” Budget? Financial Year Budget: Demand for work exceeds available fund: – Re-schedule work – Apply robust Prioritisation Criteria – Document prioritisation decisions 14 Budget Revision due to Progressive Improvement of Cost Estimates Cost estimating through the Project Life Cost Estimate Name Gateway Process stage Conceptual Infrastructure Planning Pre-feasibility Package Preparation Preliminary (Feasibility) Design Development Tender Design Documentation Definitive Works Final Close Out 15 Alignment of Budget and Infrastructure Planning Cycles (1) • Expenditure characterised by spike (hockey stick!) • Resulting in: – Roll over of funds – Over expenditure – Value not achieved – Incorrect services procured • Cabinet approved framework (2007) – Allows for due process to take place 16 Alignment of Infrastructure Planning and Budgeting (1) Alignment of the Infrastructure Delivery Cycle & the Budget Cycle Year -2 Year -1 Year 0 Year 1 Year 2 A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J MTEF Budget Cycle Budget Preparation Process The improved Infrastructure Delivery Cycle now facilitates the alignment of the Infrastructure Delivery Cycle with the Budget Cycle. The budget preparation process can now be strengthened by actual projects identified during Infrastructure Planning. Implement Budget Closure Processes Previously Infrastructure Planning was undertaken too late to facilitate effective alignment of the Infrastructure Delivery Cycle with the Budget Cycle. Previous Infrastructure Delivery Cycle Infrastructure Planning Project Design Project Tender Project Implementation Rolled Over Unspent Budget Improved Infrastructure Delivery Cycle U-AMP C-AMP Proc IPMP IPIP update update Strategy O&S Plan O&S Plan O&S PlanO&S Plan Project Project Project Planning Procurement Design Project Works Planned Multi-year Project Works Monitoring & Reporting 19 17 Summary: Infrastructure Planning • User: U-AMP (G1a) Consider service delivery mandate Infrastructure required (“Gaps”) Life cycle costs Collaboration with custodian 18 Thank you cidb 19