Pei-Ci Wu
Martin D. F. Wong
DAC’14
Introduction
Preliminaries
Linear Programming Based
Optimization
Bottom-up Buffer Insertion
Experimental Results
Concluding Remarks
Timing closure, which is to satisfy the timing constraints, is a key problem in the physical design
Setup (long-path) constraints
ensure that the signal transitions do not arrive too late hold-time (short-path) constraints
ensure that the signal transitions do not arrive too early
Typically, hold violations are addressed after setup optimization has been performed.
Discrete cell sizes (i.e. discrete buffer sizes for hold optimization) in modern industrial designs
Cell libraries specified for the setup constraints and the hold-time constraints are usually different in modern industrial designs
Negative setup slacks and negative hold slacks indicate setup violations and hold violations
TNS
the absolute value of the total negative setup slacks of all the pins in PO
THS
the absolute value of the total negative hold slacks of all the pins in PO
TNS must not be worsen during holdviolation removal
Given:
a design and a buffer library, find a buffering solution such that:
THS and the cost of buffering (i.e. area and power consumption) are both minimized while
TNS is not worsen.
Inserting delay into wires to remove hold violations
A linear programming formulation
Extend such formulation for the complex timing constraints
Graph-reduction approach
Input
Combinational circuit C* s.t. for any pin p of C* , hold_slack p
< 0 and setup_slack p
> 0
C* can then be represented as a directed acyclic graph G(V,E)
V is the pins of C*
( i, j )
∈ E represents an edge
I : the zero in-degree pins
O : the zero out-degree pins for each pin i in V
three real-value variables, x i
(delays inserted at pin i for hold-time constraints), ha i
, and sa i
Hold-time constraints
For buffer library characterization is necessary in order to get an empirical ratio such that
we assume that the buffer only affects the driver cell and the sink cells of the buffer
Delays introduced by inserting the buffer is
(a)
(b)
Setup constraints
Objective :
The setup constraints limit the delays that can be inserted
r i is only necessary when there is no feasible solution
Some pins with positive setup slacks and positive hold slacks that are not included
Given:
a pin i , hold delay D
H and setup delay D
S
Find a buffering solution at pin i from a buffer library B:
hold delays introduced by the chosen buffers are as close to D
H setup delays introduced by the chosen buffers are not larger than D
S
Minimize the area of the chosen buffers
DP based algorithm
A set of buffering candidates C(L, d h
, d s
, A) is kept during the process
For each buffer in B, we insert it to any of the existing candidates
New buffering candidates
(1) if d′ s
> D
S
, C′ is removed immediately
(2) if d′ h
<= d h
, C′ is removed as well
d′ h
> D
H
+ margin where margin is a parameter, then C′ is removed too
(3) C′ is dominated by any existing candidate
C*(I*, d* h
, d* s
, A*) if d′ h
< d* h and A′ > A*
Chose the candidate that has the largest ratio of d h
/A as the buffering solution
Bottom-up Methodology
process the pins by the bottom-up topological ordering (i.e. from PO to PI)
DP algorithm cannot realize the exact amount of hold delays/setup delays by inserting buffers(extra delays)
Suppose now we are processing pin p , collected extra delays
cur_setup_req p
= setup_req p
− ds_delay
extra delays = cur_setup_req p
– sa p
D s
= x p
+ cur_setup_req p
− sa p
Similarly to get D h
First propose a linear programming based approach that minimizes the number of inserted delays
A bottom-up buffer insertion and the flow of optimizing are presented