Remarks

advertisement
1.Wadsa-Armori-Gadchirolli
(49.50 Km. NON - Electrified)
Remarks :-The project report initially submitted in 2001
with ROR of (-) 8.19%. Board instructed to recalculate the
ROR as 50% of project cost is to be borne by Govt. of
Maharastra.Revised report was submitted on 17.01.03 with
ROR of (-) 3.78%.Updated report of RETS submitted on
18.12.08 at the cost of Rs. 186.06 with ROR of (-7.46).
Now fresh updating has been done in July -10 with the cost
of Rs. 232.40 crores & ROR is (-)3.88% & with 50% cost
sharing by State Govt. ROR (-)0.40%
Action Plan :- Further directive yet to receive from
Railway Board.
2.
Raigarh-Mand (63 Km. Electrified)
Remarks :-Survey was completed by outsourcing
and report submitted to board on 27.7.09 @ costof Rs 310.64 Crs ROR- (+)29.58%. As per
announcement in Railway
Budget
2010-11
updating of survery done at the cost of Rs. 344.20
crores & ROR (+) 26.33%
Action Plan :- Further directive yet to receive
from Railway Board.
3.
Raipur-Dhamtari including Abhanpur Rajim Branch line.(67.20 Km Electrified)
Remarks :- The alignment within Raipur Town was
resurveyed as 1995 alignment is not feasible. The
project report was submitted on 8-12-07. Railway
Board advised to conduct fresh survey on 10.11.09.
Project cost Rs 278 crores & ROR (+)14.40% with
sharing 2/3 cost by State Govt. Report is submitted
to Board on 13.07.10
Action Plan :- Further directive yet to receive from
Railway Board.
4. Preliminary Engineering Cum Traffic
Survey for Gauge conversion of
Nagpur-Nagbhir (106.15 km) (Non – Electrified)
Remarks :- Report submitted to Railway Board on
22.12.09. Railway Board has advised to re-examine
the cost. After complying the obsevation, the abstract
estimate report submitted to Rly. Board on 12.11.10.
At the cost of Rs. 376.83 Crores & ROR (+) 1.50%.
Action Plan :- Further directive yet to receive from
Railway Board.
5.
Korba-Lohardaga
new
line
(via
Dharamjaygarh,
Pathalagaon,
Jashpurnagar.) (326 Km. Electrified)
Remarks:- Updating of RET Survey done at the
cost of Rs.2443.74 Crores.& ROR (-) 7.37%.
Report submitted to Railway Board 01.02.11.
Action Plan :- Further directive yet to receive from
Railway Board.
6.
Gevra Road - Pendra Road new line
(via Dipka, Sindurgarh & Pasan.)
(121 Km. Electrified)
Remarks :- Railway Board sanctioned updating
vide letter No.2009/W-1/Genl/sur/09-10 dated
24.06.2010. Updated report submitted on 11.1.11
at the cost of `. 867.03Crores &ROR(+)17.36%.
Action Plan :- Further directive yet to receive
from Railway Board.
7.
Gotegaon-Ramtek
via
Seoni(275Km)
Remarks :- Board has sanctioned updating
vide letter No.2009/W-1/Genl/sur/09-10,dated:24.6.10. Updated abstract estimate vetted by
accounts and ROR under calculation by Optg.
Deptt.
Action Plan :- Further directive yet to receive
from Railway Board.
8.
Raipur-Jharsuguda
via
Bhatgaon
Sarangarh(310Km Electrified) RETS
Remarks :- Railway Board has sanctioned
updating vide letter No.2009/W-1/Genl/sur/09-10
dated:-24.06.2010. Updated report & abstract
estimate submitted to Board on 28.12.10 at the
cost of `.2161.37Crores & ROR(+)16.70 %.
Action Plan :- Further directive yet to receive
from Railway Board.
9.
Updating of Reconnaissance Engineering
cum Traffic Survey for a
new
line
between Barwadih Chirimiri
(Ambikapur) (182 Kms. Electrified)
Remarks :- Railway Board has sanctioned updating
vide letter No.2009/W-1/Genl/sur/09-10, dated:24.6.10 updating done & ROR calculation with Traffic
deptt.
Action Plan :- Report will be submitted shortly after
ROR calculation.
10. Jharsuguda-Durg 4th line (360 km)
Remarks :-To conduct 4th line Survey letter
received from by Railway Board from 02.12.09. Terms
& references yet to be decided. RITES has been
contacted for simulation. They have submitted their
offer. Tender finalized.
11. Dongargarh to Kota (Pendra Road) via
Khairagarh-Chhuikhadan-Gandai
Sahaspur - Lohara-Kawardia Bodh Pendra Road
(220 kms) RETS
Remarks :- Out sourcing contract finalized.
Field work has been commenced from Kota end &
completed as per initial alignment. Railway Board
advised to examine alternative route which is in
process.
12. Durg – Nagpur 3rd line (256 Km.) RETS
Remarks :-
Survey is being conducted through
outsourcing. Tender finalized. Field work of 172 Km
between RJN-BRD done & balance is in progress.