University of Saskatchewan Geological Engineering GEOE 498.3 Introduction to Mineral Engineering Lecture # 3 Production Rate Productivity Stope Production Mine Production U/G Infrastructure Productivity vs. Production Productivity is the rate at which a task is completed or ore is produced. In mining it is usually reported in units per machine or man hour. Drilling: metres per drill - Hour Mucking: Tonnes per LHD - Hour Development: metres per man-shift. Production is the total amount produced. In mining it is usually the total production per day, week, month or year. Determining Productivity and Production Rule’s of Thumb Benchmarking Historical Data Equipment Specifications First Principle Calculations Rule of Thumb Rule of Thumb – An easy to remember guide that falls somewhere between an engineered solution and an experienced or educated guess. Are the Rules always correct? Absolutely no. Can they provide a quick answer or a starting place? Absolutely yes. The primary usage of Rules of Thumb should be in the development of conceptual designs and feasibility studies or, when a quick decision is required in the solution of an operating problem. When the time arrives for final design and actual construction, Rules of Thumb are no substitute for sound engineering practices. Productivity - Rule’s of Thumb Activity Measurement Sink timber shaft Sink bald concrete shaft Sink equipped concrete shaft Equip concrete shaft Cut shaft stations - slusher Cut shaft stations – LHD Drive raw raises up to 10 m Drive timbered raises Drive alimak raises Raise bore drill Set up Drill Pilot Ream Track drift Trackless Drift Ramp Drill and Install Rock Bolts (stoper) Drill and Install Rock Bolts (mobile) Drill Jack Leg Drill Stoper Drill Jumbo Drill Tophammer (small diameter < 76mm) Drill Tophammer (large diameter > 105mm) Drill ITH m/day m/day m/day m/day cu m/day Productivity m/m-sh m/m-sh m/m-sh 2 - 2.8 3-4 2.4 - 3.6 10 - 15 50 - 65 65 - 95 0.5 - 0.7 0.45 - 0.6 0.75 - 1.0 days m/day m/day m/m-sh m/m-sh m/m-sh m/m-sh m/m-sh m/m-sh m/m-sh m/m-sh m/machine-shift m/machine-shift m/machine-shift 2-5 20 - 25 7 - 10 0.5 - 0.75 0.65 - 1.0 0.55 - 0.8 45 - 60 100 - 125 10 - 15 8 - 12 75 - 100 75 - 120 25 - 50 25 - 50 Mucking Productivity Productivity - Drilling Productivity - Drilling Mucking Productivity - Trucking Mucking Productivity Large Scoop Benchmarking Gathering information and statistically analyzing how other similar operation are performing. Production Productivity Cost Safety Information is not always readily available. Must ensure that orebody, skill of labour, work organization, consumable costs, etc. are in fact similar. Benchmarking First Principle Calculations Zero based calculations where the production or productivity estimate is created by the mine engineer. Typically used at the detailed design stage. Equipment specifications, quotations, detailed drawings, established engineering practices form the bases. Equipment Manufacturer Equipment Manufacturers have detailed specifications for their equipment that will provide data on: Productivity Energy consumption Water Consumption Compressed Air Size of Openings Weights Equipment Manufacturer The specifications are typically derived under ideal conditions. The mine engineer must factor in site specific conditions such as: Skill of work force Environment (heat, depth, humidity) Condition of openings Hardness of rock Maintenance Availability and Utilization Play LHD Video First Principle Shotcrete Calculation Input Data Arch back is assumed. Roughage Factor Rebound Factor Overlap Factor Drift width Drift height Round length Shotcrete thickness Shotcrete Height from Floor 20% 20% 20% 0.5 4.5 4.5 3.2 3.0 1.5 m m m m in m Calculated Data Shoulder Height Back Arc Length ... Perimeter Coverage of Shotcrete Shotcrete thickness 3.60 m 4.97 m 9.2 m 0.0762 m Results Theoretical volume Actual volume considering overlap, surface roughness and rebound 2.58 m^3 3.72 m^3 Productivity Mucking Equipment Mucking Productivity - Trucking Productivity Drill Equipment Tunneling Equipment Historical Data Usually applies to existing operations and is used to forecast production and create annual operating budgets. If a site does things the way they always did, can expect the same results. Data gathered from time studies. May also be used when estimating productivity, production and costs for an expansion. Summary In most estimating situations a combination of history, benchmarking, rule of thumb and first principle calculations are used. CAUTION: in mining “stuff happens” It is important to build efficiency factors and reality into the estimate. Types of Delays: • Gas Check • Equipment down • Ground Conditions • No Materials • Surveying • Air, water, vent, power • Travel and Breaks Equipment Availability Availability (Operational Availability) It is the probability that an item will operate satisfactorily at a given point in time when used in an actual or realistic operating environment. Includes all sources of downtime, (administrative, logistic as well as actual time to repair) Operational availability is used to isolate the effectiveness and efficiency of maintenance operations. Operational availability can be calculated on a calendar basis or on a scheduled work basis. Uptime Equipment is available to the operators Total Time Based on 24-7, i.e. 168 hours in a week Scheduled Time Based on work schedule, i.e. 2x10hr shifts per day 7 days per week = 140 hours /week AOT = Total Operational Availability = uptime/total time AOE = Effective Operational Availability = uptime/scheduled time Rule of Thumb - New and/or well maintained equipment will have 8090% effective availability Equipment Utilization Utilization Utilization is defined as the percentage of time in which equipment is in production. In other words production is not prevented by equipment malfunction, operating delays, or scheduled downtimes. Utilization is used to isolate the effectiveness and efficiency of mine operations. UT = Total Utilization = equipment operating time/total time US = Effective Utilization = equipment operating time/scheduled time UA = Actual Utilization = equipment operating time/uptime Rule of Thumb - New and/or well maintained equipment should have 60-70% effective utilization Equipment Reliability Reliability: is the probability that a piece of equipment or system will perform its required function under stated conditions for a stated period of time. MTBF: Mean Time Between Failures – how long a piece of equipment or system will operate before it fails. TTR : Time to repair Preventative Maintenance : routinely schedule equipment for service and inspection of key components Predictive Maintenance : Schedule changeout of key components and major overhauls or rebuilds prior to equipment failure. Example 1 Estimate development advance and metres per manshift in a typical development Assumptions: RMR : Very Strong 2 man Crew, 2 boom Jumbo, stoper for ground support, med sized scoop Round size is 5x5x3.5 Drill pattern requires 65 holes Bolting pattern is 1.5x1.5 and 2m long bolts Example 1 Estimating Mine Production Taylor’s Rule is a means of estimating Mine Life and Daily Production. It has been calibrated against many mines over several years and is adequate for pre-feasibility level estimates. L=0.2T0.25 PR=T/(LxDPY) Where L=Mine Life T=Resource (inc. Dilution and Recovery) PR=Daily Production DPY=Scheduled Days Per Year Example 2 Orebody A is 2 000 000 t The expected Recovery is 90% and dilution is estimated at 20%, therefore the Resource = 2mt x .9 x 1.2 = 2.16 mt L=0.2T0.25 L = 0.2 x (2 160 000)0.25 L = 7.7 years If the mine is scheduled to operate 350 days per year, then the daily production is PR=T/(LxDPY) PR=2 160 000/(7.7 x 350) PR ~ 800 tpd Example 3 Orebody B is 20 000 000 t The expected Recovery is 80% and dilution is estimated at 10%, therefore the Resource = 20mt x 0.8 x 1.1 = 17.6 mt L=0.2T0.25 L = 0.2 x (17 600 000)0.25 L = 12.95 years If the mine is scheduled to operate 350 days per year, then the daily production is PR=T/(LxDPY) PR=17 600 000/(12.95 x 350) PR ~ 3900 tpd Example 4 Orebody A is a nearly vertical quartz vein containing 0.25 oz gold per tonne (insitu). It is a tabular, deposit that measures 215 metres on strike, 240 m high and 15m thick. It has a strong ore and f/w and a week h/w. The top of the orebody is 200 metres below surface and the bottom is 440 metres below surface. Both ore and waste have a SG of 2.6 t/m3 The chosen mining method is Transverse Mechanized Cut and Fill. Stope dimensions Have been established as 7m wide x 24m high x 15 m long Example 4 Determine: Average tonnes per day per stope of ore and waste. Number of stopes required to meet daily production target. The truck fleet size. Example 5 Orebody B is a thick, tabular steeply dipping Nickel deposit with a diluted grade of 3% Ni. It averages 330 metres on strike, 400 m high and 40m thick. It has a strong ore and h/w and a moderate f/w. The top of the orebody is 100 metres below surface and the bottom is 500 metres below surface. The recovered ore has an S.G. of 3.8 and the waste has an SG of 2.6 t/m3 The chosen mining method blasthole stoping with paste fill Stope dimensions Have been established as 15m wide x 32.5m high x 20m long Example 5 Determine: Average tonnes per day per stope of ore Number of stopes required to meet daily production target. If 30 metres of development is required to access each stope, calculate tonnes of waste per day Sequencing Once the number of stopes are determined, they need to be sequenced Considerations: Stress Voids Fill Cure Time Logistics (congestion on a level) Ventilation Capital or access developement Chevron & Primary/Secondary Mining 17 Primary Stopes Secondary Stopes 6 8 2 778 42 12 15 9 3 13 14 1 11 5 10 16 Mining Sequence 1 Sill level P S P S P Sill level Mining Sequence 2 1 Sill level P S P S P Sill level Mining Sequence 2 3 Sill level P 1 S P 3 S P Sill level Mining Sequence 4 2 3 Sill level P 1 S P 3 S P Sill level Mining Sequence 4 Sill level 5 2 5 3 1 3 P S P S P Sill level Mining Sequence 4 2 5 Sill level 5 3 6 1 6 3 P S P S P Sill level Sequencing 144 143 143 127 126 124 123 125 123 121 125 123 122 121 122 121 123 121 107 106 105 106 105 104 101 104 103 102 101 087 086 085 086 085 084 083 080 084 083 082 068 067 066 068 067 066 060 067 064 049 045 044 043 048 047 046 043 041 049 047 045 043 041 105 103 102 101 085 084 082 081 080 066 065 064 063 062 103 084 083 081 064 063 061 044 043 063 061 044 043 041 101 103 101 083 081 045 044 043 122 102 082 062 042 120 100 080 060 040 029 028 009 008 025 029 006 005 009 008 023 022 029 028 027 026 023 003 009 008 007 006 003 028 027 023 008 007 026 006 007 025 024 021 025 022 005 004 002 001 006 005 002 001 989 988 984 989 988 987 989 988 987 986 988 987 985 984 981 987 986 984 983 985 984 983 982 981 986 985 982 981 969 968 967 969 968 962 969 967 966 965 968 967 965 964 961 967 966 964 963 961 965 964 963 962 961 966 965 962 961 949 948 947 946 945 S27 948 947 946 945 S26 S57 S47 S27 949 947 946 945 948 947 946 945 941 946 944 943 941 945 944 943 942 941 946 945 942 941 S27 926 925 921 924 923 925 922 S36 S16 S06 S25 S26 S05 S06 905 902 S58 S49 S28 S18 S29 S19 S09 S49 S39 S29 S19 S09 S49 S39 S29 S19 S09 S48 S38 S28 S18 S08 S48 S38 S28 S18 S08 S47 S27 S17 S07 S48 S28 S18 S08 S37 S27 S17 S07 S38 S28 S18 S27 S17 S07 S49 S39 S29 S49 S39 S29 2006 2007 2008 2009 2010 2011 Mine D - Schematic Longitudinal Section Panels 112 110 108 106 104 102 100 98 96 94 92 90 88 86 84 82 80 78 GW1 GW2 GW3 GW4 GW5 GW6 GW7 GW8 GW9 Levels 68 primary primary primary 886 944 927 926 904 903 883 69 944 943 Block 1 903 902 926 70 981 71 981 944 943 942 961 943 942 73 101 882 961 981 961 primary 924 901 887 886 885 881 927 906 902 901 887 886 885 868 867 866 865 906 905 887 886 885 868 866 865 925 primary 829 828 827 822 821 829 828 827 826 825 867 848 865 844 864 843 863 842 866/867 849 864 847/848 863 845/846 862 843 861 841/842 849 868 848 866/867 847 863/864 846 861/862 845 primary 808 807 806 805 809 68-SL4 68-SL3 68-SL2 68-SL1 68-GW1b 68-GW1a 788 S37 S38 GW1 GW2 GW3 GW4 GW5 GW6 S47 S48 GW1 GW2 GW3 GW4 GW5 GW6 785 S45 S46 805 828 827 826 825 S44 848 847 846 S33 S23 S13 825 S45 GW1 GW2 GW3 GW4 GW5 GW6 GW7 S34 GW2 GW3 GW4 GW5 GW6 GW7 H1 2007 943 942 941 NIR 961 927 926 846 S31 S32 S22 74 055 015 993 976 919 918 917 957 956 937 936 938 937 936 918 917 917 918 S33 S23 S13 H2 2007 GW2 GW5 GW6 GW7 GW8 H1 2008 H2 2008 906 905 897 896 S55 877 S45 857 S36 S35 S26 S25 S16 S15 S05 S55 877 S45 857 H1 2009 S35 S25 S15 S05 S45 S35 S26 S25 S15 S05 GW5 GW6 GW7 GW8 GW9 75 015 055 014 012 994 993 992 977 976 975 957 956 995 994 993 977 976 957 956 938 937 936 977 976 958 957 956 939 938 937 936 977 976 957 956 977 976 957 898 897 GW5 GW6 GW7 GW8 GW9 77 033 093 074 055 054 015 014 78 055 093 075 053 033 017 015 014 013 994 993 992 012 011 997 994 993 79 074 073 072 071 093 092 034 033 032 031 035 034 032 031 030 035 80 113 074 073 072 071 070 093 092 82 111 109 126 107 105 106 83 105 106 107 104 105 106 107 84 055 083 084 085 086 087 085 086 087 015 012 011 994 993 105 103 101 99 062 043 004 063 044 005 085 064 046 006 086 065/066 048 007 067/068 049 009/10 061/062 043 023/024 003/4 063 044 025 006 064 045 026 007 067 048 029 009 068 049 0210 0010 044 024 045 025 005 066 008 067 029 009 97 989 9810 986 969 9610 989 9810 969 9610 988 989 968 969 93 947 948 949 9410 946 947 948 949 9410 946 947 948 949 897 S55 S45 S46 S36 S35 S25 S15 S05 897 S55 S56 S46 S45 S35 S25 S15 S05 917 916 915 S65 S55 S56 S46 S45 S35 S25 S15 S05 91 89 87 917 916 915 937 936 935 934 95 877 917 916 938 937 936 935 956 897 898 946 927 928 929 S0A 103 104 105 082 083 084 085 086 080 082 083 084 085 87 88 12A 10A 100 101 103 081 082 083 90 12A 10A 120 101 066 049 041 066 048 065 066 082 083 04B 04A 041 047 048 04A 110 108 005 028 029 023 026 027 028 029 008 009 003 006 007 008 009 021 022 025 026 027 005 006 007 008 026 027 102 004 005 006 007 100 041 91 112 023 043 106 104 986 987 988 989 966 967 968 969 965 966 967 968 969 984 964 986 987 988 966 967 968 989 988 987 986 98 964 965 966 967 96 987 988 989 S0H 948 947 946 948 947 946 945 94 S0E S0X S0F S0Y 0 1 2 3 4 Block 2 GW6 GW7 GW8 GW9 GW6 GW7 GW8 GW9 GW5 GW6 GW7 GW8 GW4 GW8 GW7 GW3 GW4 GW5 GW6 GW6B S13 S23 946 947 945 946 947 S0J/S0B S0I 86 103 104 105 106 GW6 GW7 GW8 GW9 923 924 925 926 924 925 923 924 S12 S00 SA S01 S02 S12 S22 S00 SA S01 S10 S02 S12 S22 S32 90 88 S14 S15 S25 S35 S43/S53 s44/54 S45/S55 S03 S13 S14 S15 S23 s24 S25 s34 S35 S43 s44/54 S45/S55 S03 S13 S14 S23 s24 s34 s44 S45 S03 S13 S14 S23 s24 S33 s34 s44 S13 S23 S33 S43 H1 2007 H2 2007 H1 2008 H2 2008 H1 2009 92 86 84 GW4 GW5 GW6 Block 3 GW4 GW5 GW6 GW4 GW5 GW4 Block 4a