September 2013

advertisement
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Monthly Progress Report
on
NTDCL Development Projects
for
September, 2013
PLANNING POWER
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
ACTIVITIES
 Ongoing Development Projects
 Projects Ready for Implementation
 Cross Border Interconnection Projects
PLANNING POWER
1
Ongoing Projects of NTDC
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Sr.
No.
1-
Name of the
Projects
220 kV GIS
Bandala
Scope of work
220 kV substation with
two 220/132 kV 160 MVA
T/Fs along with allied
equipment.
In/Out of 220 kV GattiKSK Transmission Line at
Bandala (5+5 km)
Approved
Cost
(MRs/
MUS$)
1,950
32
Date of
Approval by
ECNEC
30-11-2006
Financing
ADB
Tranche-I
220 kV substation with
two 220/132 kV 250 MVA
T/Fs and allied equipment
Project
Status
Overall
Progress
Expected
Commissioning
Civil &
electrical
works in
progress.
90 %
October, 2013
T/L
Completed.
100 %
Commissioned on
16-05-2012
Civil and
electrical
works in
progress.
86 %
October, 2013
T/Ls
Completed.
100 %
Commissioned in
June, 2012
220 kV Dharki-Rohri New
D/C T/L (115 km)
2-
220 kV Rohri
220kV D/C Rohri NewShikarpur T/L (50km)
4,847
78
06-02-2008
ADB
Tranche-II
220kV D/C T/L for In/Out
of Fauji Mari-Rohri New
at Engro Chemical CCPP
(5+5km)
PLANNING POWER
3
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Sr. No.
3-
Name of the
Projects
220 kV Khuzdar &
220kV DaduKhuzdar D/C T/L
Scope of work
220 kV substation with two
220/132 kV 160 MVA T/Fs
and allied equipment
220 kV Dadu-Khuzdar D/C
T/L (274 km)
Lot-I= 135 KM
Lot-II=139 KM
220 kV substation with two
220/132 kV 160 MVA T/Fs
and allied equipment
4-
5-
220 kV Kassowal
220 kV GIS
Shalamar
Two 220 kV D/C T/L for
In/out of 220 kV VehariYousafwala D/C T/L at
Kassowal (45+45km)
220 kV gas insulated
substation with three
220/132 kV 160 MVA T/Fs
and allied equipment
220 kV D/C T/L for In/Out
of one circuit of 220 kV
Ravi-KSK T/L at Shalamar
(9 km) and under ground
cable (3+3 km)
Approved
Cost
(MRs/
MUS$)
2,900
50
2,067
36
3,617
59
Date of
Approval by
ECNEC
27-07-2004
02-02-2005
22-10-2007
Financing
JICA
World Bank
Project
Status
Overall
Progress
Civil and
electrical
works in
progress.
82 %
December, 2013
Erection and
stringing work
in progress.
Lot-I=97%
Lot-II=79%
December, 2013
Civil and
electrical
works in
progress.
67 %
March, 2014
T/L
Completed.
100 %
T/L commissioned
on 06-08-2012
Civil and
electrical
works in
progress.
80 %
October, 2013
100 %
T/L commissioned
on 20-11-2012
JICA
T/L
Completed.
PLANNING POWER
Expected
Commissioning
4
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Sr.
No.
6-
Name of
the
Projects
220 kV
Okara
Scope of work
220 kV substation with
three 220/132 kV 250 MVA
T/Fs and allied equipment
Approved
Cost
(MRs/ MUS$)
1,884
31
Date of
Approval by
ECNEC
06-02-2008
Project
Status
Overall
Progress
Expected
Commissioning
Civil and
electrical
works in
progress.
90 %
October, 2013
T/L
Completed.
100 %
T/L Commissioned on
26.05.2012
.
ADB Tranche-II
Installation in
progress.
92 %
NTDC own
resources
Civil works
completed.
Erection and
Stringing in
progress
Financing
ADB Tranche-II
In/out of 220 kV Yousaf
Wala-Sarfraz Nagar D/C
T/L at Okara (5+5 km)
220 kV substation with
three 220/132 kV 250 MVA
T/Fs and allied equipment
7-
220 kV
T.T. Singh
In/Out of 220 kV
Faisalabad-Multan D/C T/L
at T.T Singh (1+1 km)
1,759
29
06-02-2008
PLANNING POWER
October, 2013
92 %
5
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Sr.
No.
Name of the
Projects
Scope of work
Approved
Cost
(MRs/ MUS$)
Date of
Approval by
ECNEC
220 kV substation with
two 220/132 kV 250 MVA
T/Fs and allied
equipment
8-
220 kV
Loralai
5,088
83
9-
500 kV
Rahim Yar
Khan
Project
Status
Overall
Progress
ADB Tranche-II
Civil and
electrical
works in
progress.
84 %
06-02-2008
220 kV D.G Khan-Loralai
D/C T/L (200 km)
500 kV substation with
two 500/220 kV 600 MVA
& two 220/132 kV
250 MVA T/Fs and allied
equipment
Financing
December, 2013
ADB Tranche-I
4,936
81
22-10-2007
Expected
Commissioning
Erection and
stringing in
progress.
94 %
Civil and
electrical
works in
progress.
65 %
JICA
500 kV S/C T/L for In/Out
of 500 kV Guddu-Multan
3rd Circuit at R.Y Khan
(30+30 km)
December, 2013
Civil and
Electrical
works in
progress.
PLANNING POWER
59.95 %
6
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Sr.
No.
Name of
the
Projects
10-
Ext. at
500 kV
Ghazi
Barotha
Scope of work
Addition of one 500/220 kV 600MVA
T/F with allied equipment.
Approved
Cost
(MRs/
MUS$)
Date of
Approval by
ECNEC
Financing
Project Status
Overall
Progress
Expected
Commissioning
1,654
27
06-02-2008
ADB
Tranche-II
Civil works in
progress.
65 %
December, 2013
JICA
Construction of
boundary wall is in
progress and
contractor is
preparing design
submittals for
approval.
5%
KfW
Bidding
documents vetted
by M/S Lahmayer
and sent to KfW
for concurrence.
Land acquired.
5%
December, 2014
Korean Exim
Bank
T/Ls ready for
commissioning
100 %
Work completed
and ready for
commissioning
220 kV substation with three 220/132
kV 250 MVA T/Fs with allied
equipment.
11-
12-
220 kV
Gujrat
220 kV
Ghazi
Road,
Lahore
220 kV D/C T/L for In/Out of 220kV
Mangla-Ghakkar D/C T/L at Gujrat
(2+2 km)
1,966
32
22-10-2007
220 kV substation with three 220/132
kV 160 MVA T/Fs and allied
equipment.
220 kV D/C T/L for In/Out of 220 kV
NKLP-S/Nagar S/C at Ghazi Road
(30 km)
220 kV D/C T/L for In/Out of 220 kV
Ravi-KSK S/C at Ghazi Road (50 km)
2,592
43
25-02-2005
PLANNING POWER
July, 2015
7
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Sr.
No.
Name of the
Projects
Scope of work
Approved
Cost
(MRs/
MUS$)
Date of
Approval by
ECNEC
Financing
220 kV substation with two
220/132 kV 250 MVA T/Fs
and allied equipment
13-
220 kV
Chishtian
2,633
43
22-10-2007
500 kV D.G
Khan
Civil work in
progress.
49%
Civil and
erection works
in progress.
4,467
73
06-02-2008
51%
49%
39.09 %
ADB
Tranche-II
December, 2013
Erection and
stringing in
progress
In/Out of 500 kV GudduMultan 2nd Circuit at D.G
Khan (20+20 km)
PLANNING POWER
Expected
Commissioning
December, 2013
Civil and
Erection work
in progress.
Extension at 220 kV Vehari
Grid Station
14-
Overall
Progress
JICA
220 kV Chishtian-Vehari
D/C T/L (65 km)
500 kV substation with two
500/220 kV 600 MVA & two
220/132 kV 250 MVA T/Fs
and allied equipment
Project Status
78.37 %
8
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Sr.
No
15-
Name of the
Projects
Augmentation
of existing
Grid Stations
Approved
Cost
(MRs/
MUS$)
Scope of work
Name of
Grid
Stations
No.
of
T/Fs
Voltage
(kV)
Capacity
(MVA)
500 kV
Rewat
1
500/220
750
500 kV
Sheikh
Muhammadi
4
220/132
250
220 kV
Mardan
2
220/132
250
220 kV
Burhan
4
220/132
250
220kV Bund
Road
4
220/132
250
220 kV
Bahawalpur
2
220/132
250
220 kV
Quetta
Industrial
2
220/132
250
3,900
46
Date of
Approval
by ECNEC
21-01-2010
PLANNING POWER
Financing
Project Status
Expected
Commissioning
ADB Tranche-II
i) Contract
agreement for 13
T/Fs has been
signed with M/S
SUNIR and are
expected to be
delivered in
December 2013.
ii)Bidding
document for 5
T/Fs has been
sent to ADB for
concurrence.
December, 2013
9
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Sr.
No.
16-
Name of the
Projects
SVC at NKLP
Scope of work
Static Var Compensators
with T/F of 450 MVA
Capacity
Approved
Cost
(MRs/
MUS$)
2,087
34
220 kV substation with
220/132 kV 1x160 MVA &
1x100 MVA T/Fs and allied
equipment
17-
220 kV Dera
Murad Jamali
880
11
220 kV D/C single
conductor T/L for In/Out of
220 kV Uch-Guddu S/C at
Dera Murad Jamali (5 km)
Date of
Approval by
ECNEC
30-11-2006
PC-I approved
by CDWP on
07-04-2011
Financing
Project Status
Overall
Progress
Expected
Commissioning
ADB
Tranche-I
Basic design
has been
agreed upon
and project will
be completed
on schedule.
26 %
May, 2014
Contractor
mobilized and
civil works in
progress.
10 %
NTDC own
resources
PLANNING POWER
December, 2014
Re-survey
work in
progress.
5%
10
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Sr.
No.
Name of
the
Projects
Scope of work
Approved
Cost
(MRs/ MUS$)
Date of
Approval
by ECNEC
Financing
500 kV substation with two
500/220 kV 750 MVA T/Fs and
allied equipment
Project Status
Overall
Progress
Expected
Commissioning
5%
2014-15
Work is
delayed due to
non availability
of land.
Two 500 kV S/C T/Ls for In/Out
of 500 kV Sahiwal-Lahore S/C
at Lahore New (15+15km)
18-
500 kV
Lahore
New
Two 500 kV S/C T/Ls for In/Out
of 500 kV Lahore – Gujranwala
S/C at Lahore New
(50+50 km)
12,664
147
09-12-10
220 kV D/C T/L for In/Out of
220 kV NKLP- Ghazi Road S/C
at Lahore New (50km)
JICA
T/L route
survey is in
progress.
220kV D/C T/L for In/Out of 220
kV NKLP- Wapda Town S/C at
Lahore New (45 km)
PLANNING POWER
11
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Sr.
No.
Name of
the
Projects
19-
Installation of
SVS at
220/132 kV
Quetta
Industrial
Scope of work
Approved
Cost
(MRs/ MUS$)
Date of
Approval
by ECNEC
Financing
Project
Status
Overall
Progress
Expected
Commissioning
SVS (SVC of -50/+300 MVAR
& MSC of 300 MVAR)
2,087
34
06-02-08
ADB Tranche-II
Not yet
started.
NIL
December, 2014
500 kV substation with two
500/220 kV 600 MVA T/Fs
and allied equipment
20-
500 kV
Shikarpur
Two 500 kV S/C T/Ls for
In/out of 500 kV Dadu Guddu Cct # 1 (20+20 km)
Two 500 kV S/C T/Ls for
In/out of 500 kV Dadu –
Guddu Cct # 2 (22+22 km)
21.25 %
8,085
94
09-12-10
JICA
Contract
agreement
signed, L/C
opened and
contractor
mobilized.
Land
acquired.
1.25%
August, 2014
June, 2015
220 kV D/C T/L for In/out of
220 kV Guddu – Sibbi S/C
at Shikarpur (50 km)
PLANNING POWER
12
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Sr.
No.
Name of
the
Projects
Scope of work
Approved
Cost
(MRs/ MUS$)
Date of
Approval by
ECNEC
Financing
Project Status
Buyer’s
Credit
Basis
Tender opened on
08.10.2012 evaluated
and sent to BOD for
approval.
Deposit
work of
GENCO-II
Civil works in progress.
Overall
Progress
Expected
Completion
500kV Guddu-Muzaffargarh S/C T/L
(256 km)
21-
Power
Dispersal
from
747 MW
CCPP
Guddu
500 kV T/L for In/Out of 500 kV D.G
Khan-Multan S/C T/L at 500 kV
Muzaffargarh (10 +10 km)
Three 500 kV line bays at Muzaffargarh
substation
7,856
91
29.07.2011
500 kV T/L for In/Out of existing GudduMultan (R.Y.Khan) T/L at 500 kV Guddu
New substation (2+2 km)
220 kV Uch-II – Sibbi D/C T/L (125km)
22-
Power
Dispersal
from
Uch-II
Extension at 220kV Sibbi substation
2,508
30
16.08.2012
220 kV D/C T/L for In/Out of 220kV
existing Uch-I to Shikarpur New S/C T/L
at Uch-II (0.5 km)
Reconductoring of 220kV T/L Uch-I to
Uch-II (1 km)
PLANNING POWER
ADB
Tranche-III
2014-15
NIL
Dec. 2013
Bid evaluation report
finalized. ADB has been
requested for allowing
price negotiation with
single bidder. Response
from ADB is awaited.
5%
Dec. 2014
Work in progress from
NTDC own resources.
50%
April, 2014
Reconductoring of 1km
T/L and In/Out of 0.5km
completed.
100 %
Commissioned
on 25.04.2013
13
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Sr.
No.
Name of the
Projects
Scope of work
Approved
Cost
(MRs/
MUS$)
Date of
Approval by
ECNEC
Financing
Project
Status
Overall
Progress
Expected
Completion
NIL
2015-16
90 %
Oct. 2013
(Subject to
clearance of
ROW problems
from Tower No.
2 to 10 during
Jirga Meeting
on 18.08.2013)
Package-I
500 kV D/C T/L from Neelum
Jhelum to Gujranwala (270km)
23-
Power Dispersal
from Neelum
Jhelum HPP
500 kV D/C T/L for In/out of 500
kV Neelum Jhelum Gujranwala
S/C at Azad Pattan (5km)
500 kV D/C T/L for In/out of 500
kV Neelum Jhelum Gujranwala
S/C at Karot (5 km)
22,582
251
Approved by
ECNEC on
26.08.2013
Buyer’s
Credit
Basis
Package- II
Extension at 500 kV
Gujranwala
24-
Power Dispersal
Arrangements
from Duber
Khwar Power
House
220 kV D/C T/Line from Duber
Khwar to Khan Khwar Power
House (33km)
LOA issued
on
12.09.2013.
Bidding not
yet initiated
2494
28
(For Lot-I &
II)
Approved
under PC-I of
Hydel Power
Project
PLANNING POWER
Deposit
work of
G.M
(Hydel)
Erection and
stringing work
in progress.
14
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Sr.
No.
25-
26-
Name of the
Projects
Dispersal of
power from
2x50MW Wind
Power Plants at
Mirpur Sakro
Interconnection
arrangement for
dispersal of
power from TGF
& WPP#4 at
Jhimpir
Approved
Cost
(MRS/MUS$)
Scope of work
Date of
Approval
by ECNEC
Financing
132kV D/C T/L on Greeley
conductor from WPP#1 to 132kV
Thatta G/S (64km)
Construction of two 132kV line
bays each at Thatta G/S
816
14
22-04-2006
NTDC own
resources
_
NTDC own
resources
Project
Status
Overall
Progress
Expected
Completion
Tender
opened,
evaluated and
case is being
prepared for
getting
approval of
competent
authority for
award of work
NIL
June 2014
Procurement
of material
initiated.
NIL
2014-15
132kV D/C T/L for looping I/O of
nd
Jhimpir-Nooriabad 2 132kV at
TGF & WPP#4 at Jhimpir (7 km)
Conversion of 2 Nos. 132kV iso
bays to line bays at Nooriabad
substation for Kalu Kahar and
Jamshoro old S/C T/Ls.
207
2
132kV T/L approx 4km from
Nooriabad to the nearby JamshoroKDA T/L
Total
108,526
1,479
PLANNING POWER
15
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Summary of Ongoing 500kV Projects
Sr. No.
Description
Addition in T/L & T/F Capacity
1-
500 kV S/C Transmission Lines Length
1150 km
2-
500/220 kV Transformation Capacity
(New Projects)
5100 MVA
3-
500/220 kV Transformation Capacity
(Extension)
600 MVA
4-
500/220 kV Transformation Capacity
(Augmentation)
300 MVA
500/220 kV Transformation Capacity
(Grand Total)
PLANNING POWER
6000 MVA
16
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Summary of Ongoing 220kV Projects
Sr. No.
Description
Addition in T/L & T/F Capacity
1-
220 kV D/C Transmission Line
1227.5 km
2-
220/132 kV Transformation Capacity
(New Projects)
6930 MVA
3-
220/132 kV Transformation Capacity
(Extension)
----
4-
220/132 kV Transformation Capacity
(Augmentation)
1620 MVA
220/132 kV Transformation Capacity
(Grand Total)
PLANNING POWER
8550 MVA
18
Projects Ready for Implementation
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
NTDC Development Projects Ready for Implementation
Sr.
No.
Name of the
Projects
1-
3rd Circuit from
Jamshoro to
Rahim Yar Khan
(For power
evacuation from
2x660 MW Coal
Power Plant at
Jamshoro &
WPPs)
Scope of work
Est. Cost
(MRs/
MUS$)
Date of
Approval by
ECNEC
Financing
Project Status
Expected
Completion
24,214
269
Approved by
ECNEC on
26.08.2013
ADB
Tranche-III
Rebidding in
process.
2015-16
3,103
35
Approved by
ECNEC on
26.08.2013
Proposed
under ADB
Tranche-IV
Route under
checking.
2015-16
500 kV Jamshoro-Moro-R.Y.K
S/C T/L (535 km)
500 kV Moro-Dadu S/C T/L
(55 km)
500 kV Switching Station at
Moro
Extension at 500 kV Jamshoro,
Dadu & R.Y.K Grid Stations.
220 kV Chashma Nuclear –
Bannu D/C T/L (125 km)
2-
Power Dispersal
from Chashma
Nuclear
(C3 & C4)
220kV D/C T/L for In/Out of
existing C1 &C2 at C3 & C4
(2 km)
Extension at 220kV Bannu
PLANNING POWER
20
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
NTDC Development Projects Ready for Implementation
Sr.
No.
Name of the
Projects
Est. Cost
(MRs/
MUS$)
Scope of work
Date of
Approval by
ECNEC
Financing
Project
Status
Expected
Completion
JICA has
shown interest
to fund the
project.
T/L Plan and
Profile
Drawings
completed.
Execution is
linked with
installation of
Coal Fired
Power Plants
at Thar.
2015-16
Proposed in
ADB
Tranche-IV
Site for Grid
Station
selected.
Acquisition of
land in
progress.
2015-16
500 kV Thar – Matiari D/C T/L
(250 km)
3-
Power
Dispersal from
1200 MW Thar
Coal Based
Power Plant
500 kV Switching Station at Matiari
22,306
237
16.08.2012
220kV sub station with 220/132kV
3x250 MVA T/Fs along with allied
equipment
4-
220 kV
Nowshera
In/Out of 220 kV Ghazi Barotha –
Shahi Bagh D/C T/L at Nowshera
(5+5 km)
1,876
31
06.02.2008
PLANNING POWER
21
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
NTDC Development Projects Ready for Implementation
Sr.
No.
Name of the
Projects
Scope of work
Est. Cost
(MRs/
MUS$)
Date of
Approval by
ECNEC
220kV sub station with
220/132kV 3x250 MVA T/Fs
along with allied equipment
5-
220 kV
Lalian New
In/Out of 220 kV Gatti –
Ludewala D/C T/L at Lalian
New (4+4 km)
1,581
18
11.11.2011
Financing
Project Status
Expected
Completion
Proposed in
ADB
Tranche-IV
Hiring of project
preparatory
consultants in
process.
Land not yet
acquired
2015-16
ADB
Tranche-III
Bids opened on
26-02-2013
evaluated & sent to
competent authority
for approval.
Land acquired.
2015-16
220kV sub station with
220/132kV 2x250 MVA T/Fs
along with allied equipment
6-
220 kV
Mansehra
Two 220 kV D/C T/L for
In/Out of 220 kV Alai
Khawar – Islamabad
Peshawar Road D/C at
Mansehra (0.5+0.5 km)
905
11
07.04.2011
PLANNING POWER
22
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
NTDC Development Projects Ready for Implementation
Sr.
No.
Name of the
Projects
Est. Cost
(MRs/
MUS$)
Scope of work
Date of approval
by
ECNEC
Financing
Project Status
09.12.2010
Proposed
in ADB
Tranche-IV
Land for G/S
acquired.
Boundary wall
completed.
220kV sub station with
220/132kV 2x250 MVA T/Fs
along with allied equipment
7-
220/132 kV
D.I.Khan
220 kV D/C T/L for In/Out of
220 kV Chashma NuclearLudewala S/C T/L at
D.I Khan (100km)
Total
3,779
44
Expected
Completion
2015-16
57,764
645
PLANNING POWER
23
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Summary of Projects Ready for Implementation
Sr. No.
Description
Addition in T/L & T/F Capacity
1-
500kV S/C Transmission Lines Length
1090 km
2-
220kV Transmission Line
246 km
3-
220/132 kV Transformation Capacity
PLANNING POWER
2500 MVA
24
Cross Border Interconnection
Projects
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Cross Border Interconnection Projects
Sr.
No.
Name of the
Projects
Scope of work
Est. Cost
(MUS$)
Work of profile &
plan tabling is in
progress.
220 kV Pak Iran Border-Gwadar D/C T/L
(100km)
1-
Import of
100MW Power
from Iran.
Project Status
44
220 kV GIS at Gwadar with 2x160MVA
T/Fs
Work awarded to
contractor and
contractor
mobilized.
Financing
Expected
Completion
70% by
Export
Development
Bank of Iran
and 30% by
NTDC.
August, 2014
Not yet
committed
2015-16
500 kV HVDC Bipolar Transmission Line
from Pak - Iran Border to Quetta (585km).
2-
Import of
1000MW Power
from Iran.
500 kV Convertor Station at Quetta.
220 kV Quetta-Quetta Ind.D/C T/L (5 km)
220 kV Quetta-Loralai D/C T/L (170km)
508
MoU signed
between Pakistan &
Iran on 31.05. 2012
to implement the
project.
220 kV Quetta-Mastung D/C T/L (50km)
26
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Cross Border Interconnection Projects
Sr.
No.
3-
Name of the
Projects
Import of
1000MW Power
from Tajikistan
(CASA-1000)
Scope of work
Est. Cost
(MUS$)
Project Status
Financing
Expected
Completion
200
Feasibility Study
completed.
Positive
response from
World Bank
and IDB
2015-16
-
World Bank has
offered to sponsor
pre-feasibility study
for the project
Positive
response from
World Bank
-
500 kV HVDC Bipolar Transmission line
from Pak-Afghan Border to Peshawar
(71km).
500 kV Converter Station at Peshawar
220 kV D/C T/L for interconnection of
220 kV Peshawar- ShahiBagh (10 km)
500 kV D/C T/L for interconnection of
500 kV Peshawar- Tarbela (5 km)
4-
Import of 200-500
MW Power from
India.
Different options for Interconnection are
under study.
Total
752
27
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Report Prepared by:
Designation
Maqsood Ahmad Qureshi
Manager
Projects Planning
0347-4447720
042-99202609
Fahmeeda Shafi
Dy. Manager Projects
Planning
042-99202609
PLANNING POWER
Contact No.
28