Design Process-4 (concept selection)

advertisement

EML4550 - Engineering Design Methods

Concept Selection

Settling on one or more promising ideas to pursue to final design

Hyman: Chapter 9, Sec. 9.1 & 9.2

Ulrich and Eppinger: Chapters 5 and 6

Dym and Little: Sections 6.1 – 6.3

EML4550 2007 1

Concept Development Diagram

Identify

Customer

Needs

Establish

Target

Specs

Generate

Product

Concepts

Select

Product

Concept

Refine

Specs

Mission

Statement

Analyze

Competitive

Products

Perform

Economic

Analysis

Plan

Design/

Development

Project

EML4550

Action

Plan

1-07-2

Concept Selection

 The ‘Concept Generation’ phase spawned many ideas (good and bad) and potential solutions to the problem at hand

 How do we select from all these competing concepts?

 A ‘method’ is needed to systematically weed out poor concepts and select the best one to proceed with to Final

Design

EML4550 1-07-3

Concept Selection Methods

 External decision (customers, consultants, etc.)

 Product “Champion” (strong personal decision)

 Intuition (no rational method)

 Pros and Cons (systematic but subjective)

 Prototype and test (hardware, expensive and timeconsuming)

 Decision matrices (match characteristics vs. pre-specified and weighted criteria)

EML4550 1-07-4

Concept Selection Methods (Cont.)

 Although all methods are used in practice, most of the

‘subjective’ methods are very case-specific

 Decision matrices represent the most ‘rational’ approach to concept selection

 We will focus this section on the Decision Matrix method

EML4550 1-07-5

Concept Selection: Why a Structured Approach?

 A customer-focused product (use the needs as guidelines)

 A competitive design (do not overlook competing designs)

 Better product-process coordination (forces manufacturing issues into the trade-off)

 Reduced time to market (accelerated ‘downselect’)

 Effective group decision-making (minimize ‘arbitrary’ decisions and maximize team exposure)

 Documentation of decision process (not lost in someone’s ‘memory’)

EML4550 1-07-6

Concept Selection: Why a Structured Approach? (Cont.)

 Need to balance:

 Desire to have an expedient ‘downselect’

 Expediency: proceed to design sooner

 Faster time-to market

 Less cost of ‘carrying’ many concepts forward

 Desire ‘to know more’ before deciding

 Risk of making a mistake (pick a loser)

 Risk of avoiding a concept because it is new (potential big winner)

 Engineers tend to be conservative

EML4550 1-07-7

Decision Matrix Method

 Stage 1: Concept Screening

 Apply an initial ‘filter’ to ‘weed out’ bad concepts and determine likely ‘winners’. Apply some elements of ‘scoring’ for the purposes of ranking only

 Stage 2: Concept Scoring

 Apply weighted criteria to the concepts and proceed with a quantitative ‘scoring’ system to pick a winner (or winners)

EML4550 1-07-8

Decision Matrix Method (Cont.)

 Each Stage has 6 steps:

 Prepare the selection matrix

 Rate the concepts

 Rank the concepts

 Combine and improve the concepts

 Select one or more concepts

 Reflect on the results of the process

EML4550 1-07-9

Concept Screening

Selection Criteria

Criterion 1

Criterion 2

Criterion 3

Sum “+”

Sum “0”

Sum “-“

Net Score

Rank

EML4550

A B C

1-07-10

Screening: Step 1 - Prepare Selection Matrix

 Develop a set of criteria

 Customer needs (condensed into criteria)

 Corporate needs (cost, manufacturing, liability, image, etc.)

 Give equal weight to all criteria

EML4550 1-07-11

Screening: Step 2 - Rate the Concepts

 Give +, -, or neutral rating to each concept based on criteria

 Use general notions (no need to get ‘specific’)

 Use team consensus (or majority vote)

 Refine or split criteria if team consensus is hard to reach

EML4550 1-07-12

Screening: Step 3 - Rank Concepts

 Add scores and build a ranking

 Identify a “benchmark” concept (from ranking or from external products - competition)

 Group the concepts into three categories: “possible winners”, “neutral”, and “losers”

EML4550 1-07-13

Screening: Step 4 - Combine and Improve Concepts

 Are we throwing away as ‘loser’ a ‘good’ concept because it has one or two negatives? Can they be neutralized?

 Can two concepts be combined to preserve ‘better than’ qualities while neutralizing ‘worse than’ items? Can we derive a concept that takes the ‘best of both worlds’?

EML4550 1-07-14

Screening: Step 5 - Select one or more concepts

 If there is a ‘clear’ winner, then select it and proceed with it

 MISSION ACCOMPLISHED

 However, usually more than one concept will survive the screening

 Number of concepts to carry forward will depend on resources and time available

EML4550 1-07-15

Screening: Step 6 - Reflect on the Process

 Did we achieve consensus?

 Were all the team members treated equally? No trampling?

 Did we avoid personal agendas? Department politics?

It is very disruptive to team spirit to ‘drop’ a concept that someone was championing. Grudges linger for a long time within a team

EML4550 1-07-16

Concept Screening

Selection Criteria

Criterion 1

Criterion 2

Criterion 3

Sum “+”

Sum “0”

Sum “-“

Net Score

Rank

EML4550

An example

A B C

1

2

1

2

0

+ 0 +

0 +

0 + 0

1

1

1

2

1

0

0

3

2

1

1-07-17

From Screening to Scoring (quantitative)

Selection Criteria

Criterion 1

Criterion 2

Criterion 3

Score

Rank

Proceed?

R = Rank, S = Score

A A B B C C

% R S R S R S

EML4550 1-07-18

Scoring: Step 1 - Prepare Selection Matrix

 Using the same selection criteria used in screening give relative weight to each (must add to 100%)

 It is possible to slightly modify the criteria in light of the surviving concepts

 Weights to each criterion are given by team consensus or related to customer needs

An example

EML4550 1-07-19

Scoring: Step 2 - Rate the Concepts

 As with screening, give a ‘score’ to each concept based on a

‘quantitative’ (yet still subjective) numbering scale as follows:

Relative Performance

1 - Much worse than reference concept

2 - Worse than reference concept

3 - Same as reference concept

4 - Better than reference concept

5 - Much better than reference concept

EML4550 1-07-20

Scoring: Step 3 - Rank the Concepts

 Compute score for each concept

s

j

 i n 

1

w

i

r

ij

score

_

of s

j

_

concept

_

n

number

_

of w

i

weight

_

of r

ij

rating

_

of

_

_

criteria criterion

_

concept

_

j j

_

on

_

criterion

_

i

EML4550 1-07-21

From Screening to Scoring

Selection Criteria

Criterion 1

Criterion 2

Criterion 3

Score

Rank

Proceed?

R = Rank, S = Score

A A B B C C

% R S R S R S

10 4 .4

2 .2

5 .5

30 2 .6

1 .3

3 .9

60 4 2.4 3 1.8 3 1.8

3.4

1

Y

2.3

3

N

3.2

2

Y

EML4550 1-07-22

Scoring: Step 4 - Combine and Improve Concepts

 As before, can concepts be combined to arrive at a better solution?

 Looking at the concepts in the new light of ‘scoring’ can encourage the team to improve on the initial ideas

EML4550 1-07-23

Scoring: Step 5 - Select One or More Concepts

 The final selection is never easy

 Do ‘parametric’ studies by assigning different weight distributions and see which concepts come on top on each try

EML4550 1-07-24

Scoring: Step 6 - Reflect on the Process

 Are we ready to proceed with the ‘winning’ concept?

 Did the method facilitate the selection?

 Can the method be improved?

EML4550 1-07-25

Concept Selection: Caveats!

 Decomposition of product quality

 Failure to capture relationship among criteria

 Subjective criteria

 Methodical, but still high content of subjectivity

 Where to include cost

 Derived from customer needs, but how about ‘manufacturing’ the product, not all parameters known

 Selecting elements of complex systems

 Can a complex concept be reduced to a set of simpler concepts?

How about interactions between sub-concepts?

 Applying concept selection throughout the development process

 The same approach can apply to the selection of concepts within a design effort when developing sub-systems of a larger system

EML4550 1-07-26

Concept Selection: Implications to Project

 If many concepts are considered, perform a screening

 Record results of screening (and criteria used)

 Decision matrix for the selection and scores for each concept

 Presentation of the ‘winning’ concept

EML4550 1-07-27

Download