Earned Value Management How to apply Earned Value Management to measure the Performance of your Project alphaPM Inc. www.alphaPM.com Project Performance Tracking (Project Dashboard) PROJECT MILESTONES Develop Strategy and Vision Establish Readiness and Blueprint Identify Business and User Goals Document Project Scope Prepare Detailed Requirements Build and Test Launch 2 Planned Date Planned Date Notes Project Issues/Risks Mitigating Actions To Be Taken How To Earned Value Management Overview Earned Value Management (EVM) is a management methodology for integrating scope, schedule and resources, and for objectively measuring project performance and progress. Performance is measured by determining the budgeted cost of work performed (i.e. earned value) and comparing it to the actual cost of work performed (i.e. actual cost). Progress is measured by comparing the earned value to the planned value. Source: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Third Edition 2004 Example: Project Budget: $400K Project Schedule: 4 months (= Baseline Duration) At the 3 month checkpoint: Spent: $200K Work completed: $100K Earned Value Management helps you to report how the project is doing in terms of cost and schedule? Earned Value Management Terms and Formulas Terms and Formulas Alternative Definition Example: Project Budget: $400K Project Schedule: 4 months At the 3 month checkpoint: Spent: $200K Work completed: $100K Example Earned Value (EV) Budgeted Cost of Work Performed (BCWP) i.e. the budgeted cost to date x % complete $100K Actual Cost (AC) Actual Cost of Work Performed (ACWP) i.e. actual cost of work performed to date $200K Planned Value (PV) Budgeted Cost of Work Scheduled (BCWS) i.e. the estimated value of work to be performed $300K Cost Variance (CV) = EV - AC Budgeted Cost of Work Performed (BCWP) - Actual Cost of Work Performed (ACWP) $100K – $200K = ($100K) Schedule Variance (SV) = EV - PV Budgeted Cost of Work Performed (BCWP) - Budgeted Cost of Work Scheduled (BCWS) $100K - $300K = ($200K) Cost Performance Index (CPI) = EV/AC Budgeted Cost of Work Performed (BCWP)/ Actual Cost of Work Performed (ACWP) $100K/$200K = 0.5 i.e. 50% Schedule Performance Index (SPI) = EV/PV Budgeted Cost of Work Performed (BCWP)/ Budgeted Cost of Work Scheduled (BCWS) $100K/$300K = 0.33 i.e 33% Revised Total Duration Baseline Duration/Schedule Performance Index 4/0.33 = 12 months Example: Project Budget: $400K Project Schedule: 4 months At the 3 month checkpoint: Spent: $200K Work completed: $100K Earned Value Management Chart for project example 800 3 Month Checkpoint 700 CV = EV – AC = (100K) SV = EV – PV = (200K) CPI = EV/AC = (50%) SPI = EV/PV = (33%) 600 500 400 Budget PV 300 200 Actual Cost 100 Earned Value 0 J F M A M J J A S O Revised Total Duration = Baseline Duration/SPI = 4/0.33 = 12 months N D How To Activities Prepare Plan Exercise Owner Planned Effort (Days) Budget Actual Effort Actual Cost (Planned Value) $ (As of Day 10) $ (As of Day 10) Status (As of Day 10) John 2 $2,000 4 $4,000 Completed Design Solution Susan 4 $4,000 3 $3,000 Completed Code Programs Jim 10 $10,000 5 $5,000 30% of all work completed Test Programs Debbie 2 $2,000 Not started Brad 2 $2,000 Not started 20 $20,000 Deploy into Production Total Report the Performance for the Project at the 10 day point. (Assume a labour rate of $1,000/day) Step 1: Determine the value of the three variables needed to measure the project performance at the 10 day point (all activities are sequential) Planned Value: Planned Value: Earned Value: Earned Value: Actual Cost Actual Cost: PV = Click+ here when yousince Jim should have PV = $10,000 {2,000 4,000+ 4,000 have your answer completed 4 days of coding at the 10 day point} EV = EV = $9,000 {2,000 + 4,000 + 3,000 since Jim is only 30% complete} AC = AC = $12,000 (4,000 + 3,000 + 5,000 since that is the actual amount that all have spent} How To Activities Prepare Plan Exercise (continued) Owner Planned Effort (Days) Budget Actual Effort Actual Cost (Planned Value) $ (As of Day 10) $ (As of Day 10) Status (As of Day 10) John 2 $2,000 4 $4,000 Completed Design Solution Susan 4 $4,000 3 $3,000 Completed Code Programs Jim 10 $10,000 5 $5,000 30% of all work completed Test Programs Debbie 2 $2,000 Not started Brad 2 $2,000 Not started 20 $20,000 Deploy into Production Total Report the Performance for the Project at the 10 day point. (Assume a labour rate of $1,000/day) We now know that Planned Value (PV) = $10,000 Earned Value (EV) = $ 9,000 Actual Cost (AC) = $12,000 Step 2: Calculate the Earned Value Performance Indices Cost Performance Index (CPI): Cost Performance Index (CPI): Schedule Performance Index (SPI): CPI = EV/AC Click here when you CPI = EV/AC = $9.000/$12,000 0.75 or 75% have your=answer SPI = EV/PV Schedule Performance Index (SPI): SPI = EV/PV = $9,000/10,000 = 0.90 or 90% Project Performance Tracking (Project Dashboard) PROJECT MILESTONES Develop Strategy and Vision Establish Readiness and Blueprint Identify Business and User Goals Document Project Scope Prepare Detailed Requirements Build and Test Launch 8 Planned Date Planned Date Notes Project Issues/Risks Mitigating Actions To Be Taken An Easy Way to Remember the Formulas Four Formulas Three Variables: EV PV AC S C S C An Easy Way to Remember the Formulas Four Formulas Three Variables: EV PV AC SV = EV - P CV = EV - A SPI = EV / P CPI = EV / A An Easy Way to Remember the Formulas Four Formulas Three Variables: EV PV AC SV = EV - PV CV = EV - AC SPI = EV / PV CPI = EV / AC Earned Value Management How to apply Earned Value Management to measure the Performance of your Project alphaPM Inc. www.alphaPM.com