15th Tcc / 16th srpc meeting Venue: GOA Date: 29th / 30th April 2011 POWER SYSTEM OPERATION CORPORATION LIMITED SOUTHERN REGIONAL LOAD DESPATCH CENTER BANGALORE 1 NEW PROJECTS OF NTPC, NLC, NPCIL & UMPP SL NO 1 OF TCC NTPC SIMHADRI STAGE - II (2 X 500) SL NO 1.1 OF TCC NTPC SIMHADRI STAGE - II • MoP conveyed the allocation of Power from Simhadri Stage II to beneficiary states. • Units I test synchronised in March 2011 & COD yet to be declared. • Units II likely to be commissioned by June 2011 • Scheduling of Simhadri Stage II will be done by SRLDC w.e.f COD • Data / Speech communication to SRLDC is made operational & under testing • Till the date of COD of Simhadri Stage – II • Simhadri shall regulate infirm power injection as per SRLDC instruction on real time basis NPCIL KUDANKULAM STAGE 1 (2 X 1000) SL NO 1.3 OF TCC NPCIL–KUDANKULAM STAGE I • NPCIL informed that for Kudankulam all equipment's are in place at site and the commissioning activities are in full flow. • Units I & II are likely to be commissioned by June 2011 & March 2012. • In Special TCC held on 3rd Jan 2011. NPCIL Informed Reactor of 1st Unit was likely to go critical by March 2011and generation was expected from April 2011 • SPS & Speech facilities to be provided SRPC TN REPLY - Permission given by TN for placing MUX - SRTS -2 to confirm the status / probable date of completion • SEM & SCADA Data Validation to be done by NPCIL – Observed error of 16kV between Field and Scada data at Kudankulam bus • Commissioning of Bus Reactor at Kudankulam is essential for ensuring availability of reliable start up supply. • The parallel closing of second line between Tirunelvelli – Kudankulam will be at 410 kV and Opened at 425 kV VALLUR JOINT VENTURE BETWEEN NTPC & TNEB ( 3 X 500) SL NO 1.4 OF TCC VALLUR JOINT VENTURE BETWEEN NTPC & TNEB (3X500) • Unit sizes of 500 MW. • TANTRANSO had informed that commissioning of the 1st unit could be delayed by 2-3 months because of issues regarding the coal handling plant. • MoP vide letter dated 28th September 2010 had communicated the allocations to the beneficiaries states as given: Nellore – Allmatty D/C Study Results Nellore – Allmatty D/C Study Report Allocation: AP: 178.8 MW KAR: 111.5 MW KER: 49.9 MW TN: 1040.6 MW Pondy: 6.7 MW Unallocated: 112.5 MW JOINT VENTURE OF NLC& TNEB AT TUTICORN (2 X 500) SL NO 1.5 OF TCC Joint Venture of NLC & TNEB at Tuticorin • NLC had informed that orders had been placed on M/s BHEL and civil works had commenced. • MoP had communicated allocations to the beneficiary States. • NLC had informed that with the action plan given by M/s BHEL, Units I & II were scheduled to be commissioned during August 2012 & October 2012 respectively. KAYAMKULAM 1950 MW/ 1950 MW SL NO 1.6 OF TCC KAYAMKULAM 1950 MW/1050 MW PLANT • Feasibility report for the project had been finalized by NTPC. • Pipeline from Kochi Terminal to Kayamkulam was being developed by M/s GAIL. • GoI had circulated drafts on price pooling mechanism. Price of LNG was linked with prices of crude oil. The unit rate was likely to be Rs. 3.75 - Rs. 4.00 per unit in the present scenario where crude oil prices ranging between $ 70-80/barrel. • Requisition from KPTCL & KSEB received by NTPC. • Conditional consent communicated to NTPC by APTRANSCO. • TANTRANSCO & Puducherry – Presently price pooling mechanism not very clear, would be interested in case tariff was advantageous. NLC NEW THERMAL POWER PROJECT (2X 500) SL NO 1.7 OF TCC Neyveli New Thermal Power Project (2x500 MW) • Director (Power ),NLC had informed that the project was likely to take 40 months after PIB approval and was targeted to be commissioned in 2014. PIB approval was likely in the next six months. • MOP vide letter dated 29th October 2010 had communicated allocation of power from this project • PGCIL informed NLC had applied for connectivity. NLC had been requested to apply for LTA also to take up planning of evacuation scheme • Tamil Nadu had informed that this being a replacement project since Tamil Nadu was loosing 600 MW , entire 1000 MW from the new project to be allocated to them. Neyveli New Thermal Power Project (2x500 MW) • TNEB’s share was 100% in Neyveli Stage 1. • Old plant was commissioned in 1962. • Present Evacuation Plan is at 230/110kV • Designed for evacuating 600MW. • Since 2 x 500MW plant is coming up, inter connection to 400kV is desirable. • Wheeling issue KRISHNAPATTANAM UMPP(3960 MW) SL NO 1.8 OF TCC KRISHNAPATTANAM UMPP(3960 MW) Madugiri KRISHNAPATTINAM UMPP TN UMPP Cochin 400kV D/C QUAD MOOSE 765 KV KRISHNAPATTANAM UMPP(3960 MW) • The unit configuration had been finalized as 6 x 660 MW and CERC had been approached for revised configuration, clearance awaited. • CMD, APTRANSCO had informed that about Rs. 300 Crores had already been invested and progress was their in all the fronts. • Project is being developed by Reliance Power Limited. • The plant may come up beyond 2014. Schedule Date of Commissioning of the Central Sector/JV Projects Station Unit Installed Capacity (MW) Original date of commissioning Revised date of commissioning Simhadri Stage - II I,II 500, 500 11th Plan Mar-11, June-11 Kayamkulam I, II & III 1050/1950 11th Plan 12th Plan Vallur JV with TNEB I II III 500+ 500+ 500+ 11th Plan Oct-11 Dec-11 Dec-12 Neyveli – II (Exp) I II 250 250 2006 – 07 Mar-11 Jun-11 Tuticorin JV with TNEB I II 500 500 11th Plan Aug-12 Oct-12 Sirkalli TPP I,II,III 3 X 660 52 Months, 58 Months, 64 Months from GOI approval Kaiga IV 220 Sep – 07 Nov-10 Kudankulam Stage – I I II 1000 1000 Dec – 07 Dec – 08 Jun-11 Mar-12 Kalpakkam (PFBR) I 500 2010 – 11 Mar-12 Krishnapattanam I VI 4000 11th Plan June 2013 Feb 2015 4000 2015 – 17 2015-17 Cheyyur PAYMENT OF CHARGES OF TNEB OWNED TRANSFORMERS AT SRIPERUMBUDUR & SALEM SL NO 2 OF TCC PAYMENT OF CHARGES OF TNEB OWNED Xmers AT SRIPERUMBUDUR & SALEM 1. Discussed in 13th Commercial Sub-Committee meeting held on 19th July 10 whereas PCKL had agreed to put up a draft computation for the tariff. 2. In the 14th SRPC meeting, it was noted that TCC had agreed that the proposal prepared by PCKL be deliberated in details by the Special Commercial Committee before being put up to TCC/SRPC. 3. Matter was further deliberated in the Special Commercial Sub-Committee meeting held on 29th Sep 10 wherein it was noted that proposal from PCKL was awaited, while APTRANSCO had also submitted their proposal on the issue. 4. Outcome of the 14th commercial Sub – Committee meeting • TNEB would compute the charges for the period from 1.4.1991 to 31.12.2011 in line with norms prevailed during the period and the Commercial Sub-Committee would validate the same for subsequent approval of TCC/SRPC. MAINTENANCE OF MARCONI MAKE SDH EQUIPMENT SL NO 3 OF TCC MAINTENANCE OF MARCONI MAKE SDH EQUIPMENT 1. TN to Expedite Commissioning of their system to Coincide with SR2, PowerGrid Plan Wide band Failure Microwave Details Minutes 12th Jan 10 EXISTING WIDEBAND NETWORK UNDER SOUTHERN REGION ULDC PROJECT Ramagundam Peddapally Durshed Jammikunta Shapur Nagar Warangal Sub-LDC 36 134 Ch. Gutta Vidyut Soudha Hydearbad SLDC 147 (400) 46 Tallapally 99 12 217 63 N’ Sagar PH 17 104 Vijayawada Sub-LDC 66 Kakinada Bommur Bhimadole VTPS Somayajula Pally 76 Gooty 58 Ananthapur 98 Muddanur 57 Chinakam Pally Sub-LDC (Cuddaph) 302 Davanger Sub-LDC Kumbalagodi CHENNAI SLDC Somanhally Sriperabudur B’LORE RSCC 181 Salem 400 Salem 230 30 S.P. Koil Villianur 111 64 Neyveli-I Pondicherry SCC Kozhokode B Panruti 93 Erode Sub-LDC Chidambaram Trichur North 31 140 Ingur Myladuthurai Chalakudy Trichy 230 130 Pongalur Kovilvenni 26 Udumalpet Kalamassery SLDC Thiruvarur Adankottai Orthanadu Vaikkam Thirumayam Pallom Pudukottai Kayamkulam Karaikudi Madurai 400 Kundara Sivaganga Paripally Madurai Sub-LDC Trivandrum North Kannur Sub-LDC 87 Visakapantam SWS 20 Hubli Sub-LDC KPTCL SLDC 147 Ghanapur Srisailam LBPH Srisailam PH Karnool Gazuwaka 11 19 156 Vidyuthi Bhavanam Sub-LDC CORPORATE LD&C DEPT. LEGENDS: RSCC SLDC Sub-LDC/ SCC RTU / Wideband location Repeater Station F. O. Link (ULDC) F. O. Link (APTRANSCO) M.W. Link (ULDC) M.W. Link (TNEB) VSAT link (KPTCL) Colour Code C.S. links (ULDC) Constituents links (ULDC) APTRANSCO links Proposed Solution for replacement of Existing Microwave Links installed under Southern Region ULDC Project Ramagundam Ch. Gutta Durshed Shapur Nagar 147 99 147 12 Srisailam PH 217 Vijayawada Sub-LDC Gooty 58 302 KPTCL SLDC 19 Erode Sub-LDC Ingur 31 130 Udumalpet 26 Kalamassery SLDC Pallom Kayamkulam 30 Salem 400 156 S.P. Koil Pondicherry SCC Neyveli-I 140 Villianur Myladuthurai Trichy 230 Thiruvarur Pudukottai Madurai Sub-LDC Kundara Trivandrum North Vidyuthi Bhavanam Sub-LDC Madurai 400 Total OPGW = 1214kms Total UGFO = 210 kms LEGEND RSCC SLDC Salem 230 64 Chalakudy CHENNAI SLDC 181 B’LORE RSCC 93 Bhimadole VTPS Ananthapur 98 Muddanur 57 Chinakam Pally Sub-LDC (Cuddaph) Somanhally Sriperabudur Trichur North Bommur Somayajula Pally Davanger Sub-LDC Kozhikode B 87 66 Visakapantam SWS Kakinada 20 76 111 N’ Sagar PH 17 104 Hubli Sub-LDC Kannur Sub-LDC 63 Tallapally Srisailam LBPH Karnool 11 Ghanapur 46 Hyderabad SLDC (400) Gazuwaka Warangal SubLDC 134 36 Vidyut Soudha Sub-LDC/ SCC RTU / Wideband location F.O Link (ULDC) F.O. Link (APTRANSCO) OPGW Link (existing) Proposed UGFO link Proposed OPGW link Karaikudi Proposed Radio link VSAT LINK (KPTCL) Constraints In SR System SL NO 4 OF TCC KOODANKULAM NLMNG UNIT 1- JUN 11 UNIT 2- MAR 12 CHITOOR HOODY KOLAR ALMATHI HASSAN SP-BUDUR NLY-2 EXPN S’HALLI HOSUR UNIT1- MAR 11 KALIVENDAPATTU UNIT-2 JUN 11 MYSORE BAHOOR KOZHIKODE SALEM NEYVELI NLY-EXP ARASUR NLY2-EXP PUGALUR THRISSUR UDUMALPET TRICHY KARAIKUDI COCHIN MULTI-CIRCUIT TOWER ON 220 EDAMON KV EDAMONKAYATHAR CORRIDOR EDAMON-TNVL WOULD BE AT 220 KV TO BEGIN WITH MADURAI TIRUNELVELI TRIVANDRUM KOODANKULAM TRANSMISSION SYSTEMS IN SR IN PROGRESS 400 KV D/C MYSORE-KOZHIKODE a) Reduce losses by ~ 8MW b) Enhance margin across constrained S1-S2 corridor. c) Enhanced reliability for N. Kerala (an issue at present) d) Relief for Thrissur(Madakathara) transformer ( Fully loaded) e) Relief on loading of Idukki-LP-Madakathana 220 KV lines g) Enhanced transfer capability to Kerala, opportunity to conserve hydro. 400 KV D/C MYSORE-KOZHIKODE STUDY 1. 2. WITH OUT KOZHIKODE-MYSORE D/C GEN AT IDDUKKI ABOUT 520MW NELAMANGALA MYSORE 173 MWx2 227x2 MW HOOTAGALLY Losses 830.4MW 191 MW 13 MW KADAKOLA KOZHIKODE TK HALLI 104 MW KANIYAMPET 48 MW 72 MW HORAHALLI 105 MW KANAKPURA AREACODE 173 MW 106 MW NALLALAM 139 MW SOMANAHALLI 111 MW TRICHUR KANJIRODE Coal Stock Position SL NO 5 OF TCC DC vs Actual Normative Vs DC Coal Stock Position ( As on 27-Apr-11) DAILY LINKAGE IN 1000 OF TONNES ACTUAL IN 1000 OF TONNES IN DAYS APTRANSCO VTS 26 127 5 KTS 18.9 301 16 RYTPS 16.5 97 6 SIMHADRI 23.1 164 7 KAKATIYA 5.8 109 19 38.1 535 14 52 417 8 ISGS RSTPS TALCHER KPCL RTPS 25.1 404 16 BTPS 8.7 52 6 TNEB ETPS 6.9 14 2 MTPS 13.6 73 5 NCTPS 10.4 59 6 TTPS 18.5 49 3 Issues Related to Transmission Schemes Agreed in Standing Committee SL NO 6 OF TCC HOSUR-ELECTRONIC 400KV D/C D/C TRANSMISSIN HOSUR-ELECTRONIC CITY CITY 400KV TRANSMISSIN LINE LINE 400kV lines 400kV lines In standing committee meeting it is In 28th standing committee meeting it is proposed to Utilise the ROW of 220kV proposed to Utilise the ROW of 220kV Yerandahalli-Hosur line for 400kV Yerandahalli-Hosur line for 400kV Hosur-Electronic City D/C line Hosur-Electronic City D/C line KPTCL Director (Transmission) had stated that KPTCL would examine some alternate transmission system for Electronic city city. to avoid ELECTRONIC CITY ELECTRONIC CITY ROW problems SOMANAHALLI SOMANAHALLI YERANDAHALLI YERANDAHALLI KPTCL had been requested to explore possibility of establishing 400kV S/S at their existing 220kV S/S at Yerandahalli to solve the ROW problem. KOLAR KOLAR HOSUR HOSUR 400 KV D/C HOSUR-ELECTONIC CITY • PGCIL to do joint survey with KPTCL, if necessary latest stringing methodology would be adopted. • KPTCL informed that critical RoW issues existed at two locations. • CE (Trans.) Bangalore had been nominated from KPTCL side for joint survey. • APTRANSCO had requested to furnish cost implication on account of adoption of unconventional technology. Transmission Capability of HVDC Back to Back stations SL NO 7 OF TCC Transmission Capability of HVDC Back to Back stations • In 57th OCCM of SRPC, SRLDC had clarified that it would not be able to certify the past cases as PDO was in service during that period and constituents had to take a decision in this regard ULDC Requirements Beyond 2011 SL NO 8 OF TCC LTSA FOR SR –ULDC SCHEME • Maintenance for comprehensive software and hardware maintenance support for EMS/SCADA system supplied under SR-ULDC scheme with two year extension is going to expire on 31-12-2011. • As the upgradation process will take quite a time, as per the request of constituents SRLDC has obtained the quote from M/s GE for extending the AMC by one year with a provision for one more year for further extension if required. • SRLDC seeks approval of constituents to go ahead with the proposal with negotiation as the rate quoted by M/s. GE was 30% (Approx) higher than the present AMC charges AMC CHARGES OF SR ULDC SCHEME FOR THE PRESENT AND PROPOSED BY M/S GE Sl.No. Constituent Present Total AMC in Rs. Proposed Total AMC in Rs. 1 RSCC 1,67,38,566 2,23,21,282 2 APTRANSCO 1,73,11,346 2,30,81,561 3 TNEB 1,48,71,391 1,98,26,621 4 KPTCL 1,35,55,653 1,80,80,357 5 KSEB 1,47,70,742 1,96,95,948 6 PUDUCHERRY 1,18,34,589 1,57,87,645 Price Break Up Details for AMC OF SR ULDC SCADA PROPOSED AMC COMBINED ON SHORE AND OFF SHORE PRESENT AMC VALUE ONSHORE Sl.No Constituent 1 RSCC Software Support for RSCC Hardware Support for RSCC Sub-Total 2 APTRANSCO Software Support for APSEB Hardware Support for APSEB Sub-Total 3 TNEB Software Support for TNEB Hardware Support for TNEB Sub-Total 4 KPTCL Software Support for KEB Hardware Support for KEB Sub-Total 5 KSEB Software Support for KERALA Hardware Support for KERALA Sub-Total 6 UT PONDY Software Support for UT PONDY Hardware Support for UT PONDY Sub-Total Grand Total (INR) OFFSHORE TOTAL TOTAL Per Annum INR Per Annum INR Per Annum INR Per Annum INR 4,977,295.00 3,979,507.00 8,956,802.00 4,324,307.54 3,457,456.14 7,781,763.68 9,301,602.54 7,436,963.14 16,738,565.68 12,499,918.00 9,821,364.00 22,321,282.00 5,147,620.00 4,115,687.00 9,263,307.00 4,472,299.79 3,575,738.88 8,048,038.67 9,619,919.79 7,691,425.88 17,311,345.67 12,925,674.00 10,155,887.00 23,081,561.00 4,422,084.00 3,535,598.00 7,957,682.00 3,841,967.58 3,071,741.52 6,913,709.10 8,264,051.58 6,607,339.52 14,871,391.10 11,102,908.00 8,723,713.00 19,826,621.00 4,030,841.00 3,222,786.00 7,253,627.00 3,502,020.41 2,800,005.91 6,302,026.32 7,532,861.41 6,022,791.91 13,555,653.32 10,125,000.00 7,955,357.00 18,080,357.00 4,392,152.00 3,511,666.00 7,903,818.00 3,815,960.19 3,050,963.37 6,866,923.56 8,208,112.19 6,562,629.37 14,770,741.56 11,029,731.00 8,666,217.00 19,695,948.00 3,519,072.00 2,813,611.00 6,332,683.00 3,057,395.80 2,444,509.84 5,501,905.64 6,576,467.80 5,258,120.84 11,834,588.64 8,841,081.00 6,946,564.00 15,787,645.00 47,667,919.00 41,414,366.97 89,082,285.97 118,793,414.00 Note : The above prices does not include taxes and duties. Automatic Data Reading (AMR) /Collection SL NO 10 OF TCC Analysis Details IEGC RELATED ISSUES SL NO 11 OF TCC RGMO SL NO 11.1 OF TCC RGMO Description Units Mandated on RGMO as per IEGC Telemetry Status Hydro Thermal total Avaialble Not available Total No of units 194 59 253 231 22 253 Installed capacity 10888 15600 26488 25996 492 26488 No information with RLDC for status Total Status of RGMO in SR Confirmation for participation Excemption/ Extention requested to CERC Offer received from OEM/Implementation Unit Not participating in RGMO as declared by the constituents No of units 9 52 64 36 95 256 Installed capacity 4310 6185 8855 1771 5367 26488 RGMO RGMO analysis: 1.Droop >30% considered as non response for RGMO 2. Ramagundam Unit #5, 6, & 7 generation is in the range of 102 to 105% 2. On all instances Idukki, Varahi, Nagjhari, Lower Sileru, Sharavati, Sengulam, Kundah –I,II,III are responding for immediate increase and decrease. (Units already in FGMO) 3. In adequate response from thermal generating units 4. Mostly hydro generating units responded (which is under FGMO) 5. In adequate response leading to system insecurity Hence petition will be filed by SRLDC to CERC during next month Mandated And Declared Summary Case Study Summary Response Summary Automatic Demand Management Scheme SL NO 11.2 OF TCC Automatic Demand Management Schemes Extracts from IEGC dated 28th April 2010 Clause 5.4.2 (d) Quote: The SLDC through respective State Electricity Boards/Distribution Licensees shall also formulate and implement state-of-the-art demand management schemes for automatic demand management like rotational load shedding, demand response (which may include lower tariff for interruptible loads) etc. before 01.01.2011, to reduce overdrawl in order to comply para 5.4.2 (a) and (b) . A Report detailing the scheme and periodic reports on progress of implementation of the schemes shall be sent to the Central Commission by the concerned SLDC. Unquote: All the Constituents are requested to Operationalize Status Automatic Load Shedding Scheme for Overdrawing Constituents at frequency less than 49.5Hz SL NO 11.3 OF TCC • In the 14th SRPC Meeting held at Cochin, Constituents had agreed to Implement the Load Shedding Scheme for over drawing constituents to avert frequency falling below 49.5 Hz with the following quantum • APTRANSCO had been identified 800 MW and tested for remote tripping. • TANTRANSCO had been identified 647MW and made operational • KSEB had identified 125 -250 MW • KAR had identified 384MW ( Max) • PONDY to furnish the feeder details. Excel Computation • The Quantum of Load relief through Radial feeder is due for revision. Status Arranging Interruptible Loads in four groups SL NO 11.4 OF TCC Extracts from IEGC dated 28th April 2010 Clause 5.4.2 (e) Quote: In order to maintain the frequency within the stipulated band and maintaining the network security, the interruptible loads shall be arranged in four groups of loads, for scheduled power cuts/load shedding, loads for unscheduled load shedding, loads to be shed through under frequency relays/ df/dt relays and loads to be shed under any System Protection Scheme identified at the RPC level. These loads shall be grouped in such a manner that there is no overlapping between different Groups of loads. …………………... Unquote: • AP & Kerala had completed the exercise • KPTCL, Pondicherry & Tamil Nadu had initiated the exercise Status Demand Estimation SL NO 11.5 OF TCC Extracts from IEGC dated 28th April 2010 Clause 5.3 (e) Quote: While the demand estimation for operational purposes is to be done on a daily/weekly/monthly basis initially, mechanisms and facilities at SLDCs shall be created at the earliest but not later than 1.1.2011 to facilitate on-line estimation of demand for daily operational use for each 15 minutes block. Unquote: Constituents are furnishing the block wise forecast Status UFR SL NO 11.6 OF TCC AUFR settings and Quantum Implementation Status • Pondicherry – To confirm the status • UFR Quantum is due for revision Status Pending Field Inputs SL NO 11.7 OF TCC Pending as on 20.04.11 Year wise comparison Constituent Mar2008 Mar2009 Mar2010 Mar2011 APTRANSCO KPTCL KSEB TNEB SR 1 (POWERGRID) SR 2 (POWERGRID) 618 800 0 400 3 205 541 693 0 138 4 411 640 766 25 129 26 729 484 334 18 106 6 173 Apr2011 (20/04/11) 410 332 24 105 17 174 56 16 32 16 22 16 35 16 31 16 40 61 40 61 45 64 61 61 63 37 17 1 2217 13 1 1950 30 1 2493 77 0 1371 57 0 1266 NTPC RSTPS RGCCP(Kylm) NPCIL KAIGA MAPS NLC NLC TS 2 NLC TS 1 EXP TOTAL Details TRANSMISSION SYSTEM FOR EVACUATION OF POWER FROM SIMHADRI-II TPS (2x500 MW) OF NTPC SL NO 12 OF TCC TRANSMISSION SYSTEM FOR EVACUATION OF SIMHADRI-II IN 28TH STANDING COMMITTEE MEETING, IT WAS DECIDED THAT IN STEAD OF NEW 400KV SIMHADRI-GAZUWAKA D/C LINE, 400KV GAZUWAKA-VEMAGIRI D/C LINE LILOed AT SIMHADRI MALKARAM PRESENT 400KV VEMAGIRINUNNA AP LINES WILL BE CONNECTED TO NARSARAOPET BY DISCONNECTING FROM NUNNA GAZUWAKA SIMHADRI NARSARAOPET VEMAGIRI VTS LILO OF 400KV NUNNA-VTS DC LINE AT NARSRAO PET 400KV GAZUWAKA-VEMAGIRI D/C LINE LILO AT SIMHADRI FOR EVACUATION OF SIMHADRI-II (2x500) POWER SIMHADRI – II TPS EVACUATION • APTRANSCO had accorded concurrence for Open Access for a period of 5 years. • Further extension of Open Access would be reviewed w.r.t transmission availability. • APTRANSCO had informed that the charges had been worked out on ARR. The other constituents may like to take up the matter with APERC. • In the 13th & 14th SRPC meeting, it was noted that since the Regulations on the use of intervening system were likely to be notified by CERC, so there may be not be necessary for approaching APERC in the present scenario. • Since Kundankulam & NLC generation has not yet came so if Simhadri II Generation comes up, SR import capability will be reduced to that extent. Allocation: AP: 384.4 MW KAR: 176.4 MW KER: 80.9 MW TN: 197.7 MW Pondy: 10.6 MW Unallocated: 150 MW OPERATION OF TALCHER-KOLAR HVDC TRANSMISSION SYSTEM IN GROUND RETURN MODE SL NO 13 OF TCC PRDC REPORT EXCERPTS • GRM OPERATION IS NOT POSSIBLE WITHOUT BLOCKING DEVICES AT LARGE NUMBER OF LOCATIONS • BLOCKING DEVICES SHIFT THE DC NEUTRAL CURRENT TO A DIFFERENT LOCATION • INVESTIGATE THOROUGHLY ELECTRODE DESIGN AND LOCATION • GRM TO BE LIMITED TO 150 MW • BLOCKING DEVICES TO BE PROVIDED AT KOLAR, DB PURA AND BIAL 220KV STATIONS • TRIP SINGNAL LOGIC NEEDS MODIFICATION? CEA Letter 13.08.09 KPTCL Letter 12.11.09 GRM DETAILS Sudden Flow Reduction due to High ambient temp @ Tal & Low Volt @ Kolar SPS 1000 & 450 APPENDIX-IV PROGRESS OF BUS /LINE REACTORS TO BE COMMISSSIONED IN SR SL NO 14 OF TCC BUS / LINE REACTORS COMMISSIONING BY SR CONSTITUENTS • • • S. No Bus Name Bus / Line Reactor Original Target Revised Target Date 1* Ramagundam Bus Feb-11 Aug-11 2 Simhadri Bus Nov-10 Mar-11 3 Neyveli – Expn. Bus Apr-11 Feb-11 4 Neyveli TS-II Bus Apr-11 Apr-11 5 Raichur TPS Bus Dec-10 Dec-11 6 Talaguppa Bus Jun-10 Mar-12 7 Guttur Bus Jun-10 Mar-12 8 Nelamangala Bus Jun-10 Mar-12 9 Hoody Bus Jun-10 Mar-12 10 Hyderabad Line Apr-11 Jun-11 11 Kurnool Bus Apr-11 Jun-11 12 Vizag Bus Apr-11 Jun-11 Voltages The Bus reactor at NTPC Ramagundam have to be connected to Bus section 1 or 2 instead of Bus section 4 Guttur Line Reactor to be commissioned in addition to Guttur Bus reactor Commissioning of Bus Reactor at Kudankulam is essential for ensuring availability of reliable start up supply IDENTIFICATION OF STRETCHES IN THE STATE SECTOR WHERE INSULATORS ARE TO BE REPLACED DUE TO POLLUTION/FOG/SEA WATER SL NO 16 OF TCC HIGHLY SENSITIVE AREA (FREQUENT TRIPPING DUE TO POLLUTION/FOG/SEA WATER) • Kali Complex in Karnataka. • Tuticorin Area in Tamil Nadu. TTPS • Coastal Area around Kalpaka in Andhra Pradesh. • Tripping in Raichur Switch yard due to tracking of Insulators. RTPS • All Constituents to take up replacement of Insulators in prone area as well as cleaning up of Insulators in Switch yard which are prone to pollution. PCC Meeting OPERATIONALISING OF CHIKKODI-KOLHAPUR 220 KV LINE SL NO 19 OF TCC OPERATIONALISING OF CHIKKODI-KOLHAPUR 220 KV LINE • Any of the planning issues relating to Operationalizing of Chikkodi –Kolhapur 220 kV line like seeking exemption from CERC on Inter Regional ATC computation etc have to be done by SRPC Secretariat directly . SHUT DOWN OF INTER REGIONAL LINKS SL NO 20 OF TCC SHUT DOWN OF INTER REGIONAL LINKS • Talcher – Kolar S/D to be availed only during July – December along with S/D of Talcher Stage II Units • Concurrence of NLDC & the connected region to be taken for planned outage of IR links • Annual Outage Plan of IR links to be concurred by NLDC & Concerned region SHUT DOWN OF 400 KV VIJAYAWADA- NELLORE D/C LINE SL NO 21 OF TCC BEFORE S/D AFTER S/D AP LETTER SCHEDULING OF TALCHER STPS STAGE II SL NO 23 OF TCC Scheduling of Talcher Stg II • Committee recommended that the scheduling of Talcher STPS-II be continued to done by SRLDC, as the clauses in the IEGC allow the same and change is not called for. Scheduling of Talcher stg II Clause 6.4 of IEGC • The national interconnected grid is divided into control areas, like Regional ISTS, States, DVC, etc. where the load dispatch centre or system operator of the respective control area controls its generation and/or load to maintain its interchange schedule with other control areas whenever required to do so and contributes to frequency regulation of the synchronously operating system. The Load Despatch Centre of a control area therefore is responsible for coordinating the scheduling of a generating station, within the control area, real time monitoring the station’s operation, checking that there is no gaming (gaming is an intentional misdeclaration of a parameter related to commercial mechanism in vogue, in order to make an undue commercial gain) in its availability declaration or in any other way revision of availability declaration and injection schedule, switching instructions, metering and energy accounting, issuance of UI accounts within the control area, collections/disbursement of UI payments, outageplaning etc. . Control area definition in IEGC: An electrical system bounded by interconnections (tie lines) , metering and telemetry which controls its generation and/or load to maintain its interchange schedule with other control areas whenever required to do so and contributes to frequency regulation of the synchronously operating system. Why SRLDC ? • Minimal to and fro co-ordination between RLDC’s and SLDc’s in case of scheduling process involving surrender ,recall etc. • Less time in to and fro communication • Right from planning to implementation Talcher II is apart of SR system. Only geographically located in ER system • SR boundary is upto Talcher AC I/C & Jeypore end of Gazuwaka line • In analogy to 6.4.2c(iii) of IEGC and SoR of IEGC 2010 in para 41.13, the control area jurisdiction of Talcher-II shall be with SRLDC as more than 50% share is to SR constituents. • In case of Open Access transaction also the nodal RLDC is that of importing region. On same Anology SRLDC is nodal agency for Talcher-II Continued • It plays a vital role in the LGBR of SR • AOH coordination by SRPC OCC • SPS already in place for eventualities like unit /pole tripping. • Present system is working fine for over 8 years. Extracts from SoR on IEGC dt.18.06.2010 41. Demarcation of responsibilities( Regulation 6.4 of draft grid code regulations) 41.13 This has been done to ensure certainty in the demarcation of responsibilities. The IPP with their business strategy would decide quantum of power to be sold through long term, Medium term and short terms. The connectivity to ISTS and STU system indicates that generator wants to avail this flexibility. As the customer of this type of generator would be in more than one region, RLDC through its communication system would be able to coordinate with more than one regions and also RLDC would be aware of system operating conditions like transmission constraints, Voltage conditions etc and would be in better position to ensure that scheduling to various consumers of the IPP is done optimally on day to day basis. Hence, we have decided that if the host State has more than 50% share of power, then that generating station shall be under the jurisdiction of SLDC, else it shall be under RLDC. Regarding the apprehension of some stakeholders on frequent toggling of control area jurisdiction, it is clarified that the control area jurisdiction is decided on the basis of permanent share of the host State, which will not change frequently, hence frequent toggling would not be there. Moreover, initially when one or two units/ stages of the project will come under commercial operation, the jurisdiction would be more likely with SLDC depending on the share of the host State. On the progressive commissioning of units/ stages, it is more likely that the share of the host State would decrease and become equal to or less than 50%, resulting in shifting of control area jurisdiction from SLDC to RLDC. In future also, when more units are commissioned, it is more likely that the control area jurisdiction will remain with RLDC and there would not be frequent toggling. Regarding the apprehension of some stakeholders about the problem in metering during due to this toggling, it is clarified that the interface meters at CTU and STU interfaces shall be installed as per the CEA regulations on metering. It is further clarified that as switchover of control area would be done expeditiously after the change w.e.f. the next billing period i.e. next week UI accounting there shall not be any problem in energy accounting as anticipated by SLDC, Maharashtra. For inter-State energy accounting, it shall be as per CERC ABT mechanism. LOW FREQUENCY OPERATION SL NO 24.3 OF TCC ABC & 12% SCH VS DRW FLOW GATE VIOLATION FREQUENCY SPECTRUM OF SOUTHERN REGIONAL GRID (APRIL’09 TO 27th APR’11) FREQUENCY (Hz) MONTH Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 MAX MIN AVG < 48.5 HZ 50.93 51.03 50.41 50.48 50.25 50.68 50.85 50.57 50.38 50.47 50.27 50.2 50.56 48.53 48.56 48.97 49.04 48.98 48.82 48.57 48.58 49.2 49.18 49.08 48.78 48.57 49.39 49.72 49.57 49.66 49.52 49.72 49.53 49.77 49.75 49.76 49.59 49.39 49.45 0 0 0 0 0 0 0 0 0 0 0 0 0 MAX MIN AVG < 48.5 HZ 50.88 50.67 50.69 50.54 50.57 50.66 50.97 50.97 50.99 50.93 50.82 50.86 48.58 48.56 48.92 48.7 48.84 49.24 48.88 48.96 49.22 48.83 48.81 48.81 49.84 49.81 49.85 49.81 49.92 49.91 49.99 49.92 49.82 49.7 49.61 49.65 0 0 0 0 0 0 0 0 0 0 0 0.00 % OF TIME WHEN FREQUECY WAS BETWEEN 48.5 TO 49.0 TO 49.2 TO 49.5 TO 50.0 TO 49.0 HZ 49.2 HZ 49.5 HZ 50.0 HZ 50.3 HZ 6.7 13.88 39.66 36.65 3.68 1.86 2.52 18.32 51.31 21.41 1.35 3.8 32.5 51.91 9.64 0.08 0.96 21.11 65.01 11.74 0.77 3.15 34.34 58.18 3.31 0.02 0.32 11.53 69.93 15.82 1.57 4.23 37.14 47.45 8.21 0.06 0.19 4.35 76.25 18.12 0.04 0.15 7.48 70.9 20.7 0.06 0.24 6.34 74.6 17.42 0.46 2.39 20.32 71.33 5.29 2.91 9.07 50.78 35.53 1.59 2.83 7.19 40.91 45.55 3.27 48.5 TO 49.0 HZ 0.28 0.83 0.03 0.04 0.06 0 0.03 0 0 0.07 0.17 0.33 49.0 TO 49.2 HZ 0.25 1.04 0.16 0.17 0.25 0 0.07 0.03 0 0.42 0.78 1.46 49.2 TO 49.5 HZ 2.45 3.88 1.27 3.52 1.33 0.21 0.54 0.75 1.43 7.91 18.27 20.10 49.5 TO 50.0 HZ 71.97 73.81 82.36 77.64 64.25 71.15 55.03 67.24 79.97 85.73 78.63 69.77 50.0 TO 50.2 HZ 19.26 14.52 12.13 13.39 26.49 21.47 28.53 22.33 15.04 4.95 1.77 6.97 > 50.3 HZ 0.44 4.58 0.8 1.1 0.25 2.38 1.4 1.02 0.73 1.34 0.23 0.12 0.24 > 50.2 HZ 5.79 5.92 4.05 5.24 7.62 7.17 15.8 9.65 3.56 0.92 0.38 1.37 HIGH FREQUENCY OPERATION SL NO 24.4 OF TCC GRAPHS & MSGs Staggering of loads in a co-ordinated manner have to be done during change over by Constituents. Staggering to be reviewed Major Events SL NO 24.6 OF TCC MAJOR EVENTS Hydro Availability SL NO 24.7 OF TCC Reservoir Position Full Reservoir Level LEVEL IN MTS Last 9 Years Correspondi ng Monthly Average Level LEVEL LEVEL April 27/Apr/ 2010 27/Apr /2011 Last 9 Years Correspon ding Monthly Average MU's ENERGY ENERGY Shortfall (-ve) / Rise (+ve) IN MU w.r.t Last Year Same Day Shortfall (-ve) / Rise (+ve) w.r.t 9 years Corresponding Monthly Average April 27/Apr/ 2010 27/Apr /2011 MU % MU % JALAPUT 838.40 834.61 822.17 835.24 246 83 402 319 384 156 63 SRISAILAM 270.70 263.65 247.86 247.53 --- --- --- --- --- --- --- N’SAGAR 179.90 164.82 157.34 168.71 --- --- --- --- --- --- --- LINGANMAKKI 554.50 549.29 540.21 541.75 1143 1287 1515 228 18 372 32 SUPA 564.00 546.38 527.89 529.21 788 748 805 57 8 17 2 IDUKKI 732.43 721.53 708.94 713.50 601 595 837 242 41 236 39 KAKKI 969.80 974.23 958.89 959.90 318 333 350 17 5 32 10 NILGIRIS --- --- --- --- 534 491 191 -300 -61 -343 -64 3631 3537 4100 563 16 470 13 TOTAL Reservoir Level Graph Reservoir levels in Mu as on last day of the month for the years 2007-08, 08-09, 09-10,10-11 14000 12000 4100 MU on 27th Apr 2011 Energy in Mu 10000 8000 6000 4000 2000 2007-08 Month 2008-09 2009-10 31st Mar 28th Feb 31st Jan 31st Dec 30th Nov 31st Oct 30th Sep 31st Aug 31st July 30th June 30th Apr 31st May 0 2010-11 Reservoir levels in % as on last day of the month for the years 2007-08, 08-09, 09-10,10-11 100.0 31.99% on 27th Apr 2011 90.0 80.0 60.0 50.0 40.0 30.0 20.0 Month 2007-08 2008-09 2009-10 2010-11 31st Mar 28th Feb 31st Jan 31st Dec 30th Nov 31st Oct 30th Sep 31st Aug 31st July 30th June 31st May 10.0 30th Apr Energy in % 70.0 Grid Voltage SL NO 24.8 OF TCC Voltages Vemagiri MOM Vemagiri Tap Change Installation of Bus reactor at Vemagiri complex may be considered to address the high voltage problem at vemagiri VAR Absorption/Injection by Generators within Capability Limits SL NO 24.9 OF TCC Graphs Operation of Talcher – Kolar HVDC Link in extended mode of operation SL NO 27 OF TCC Report CRISIS MANAGEMENT PLAN SL NO D 2.1 OF TCC PROGRESS Closing of 220/230 kV Inter State Lines Supp Agenda 2 Point 4 OF TCC VARIOUS MEETINGS WHERE ISSUE OF CLOSING AP-TN, AND INTER REGIONA LINKS WERE TAKEN UP Sr.No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Date 06-Jun-08 13-Aug-08 18-Oct-08 11-Nov-08 Meeting 6th TCC 28th OCC 7th TCC 29th OCC Point Discussed RADIALISATION OF CHIKKODI ON N-E-W GRID THROUGH CHIKKODI – KOLHAPUR LINE RADIALISATION OF CHIKKODI ON N-E-W GRID THROUGH CHIKKODI – KOLHAPUR LINE RADIALISATION OF CHIKKODI ON N-E-W GRID THROUGH CHIKKODI – KOLHAPUR LINE STATUS REVIEW ON RADIALISATION OF CHIKKODI ON N-E-W GRID THROUGH CHIKKODI – KOLHAPUR LINE (DISCUSSED IN 28TH OCCM) 10-Dec-08 30th OCC STATUS REVIEW ON RADIALISATION OF CHIKKODI ON N-E-W GRID THROUGH CHIKKODI – KOLHAPUR LINE (DISCUSSED IN 29TH OCCM) 05-Mar-09 8th TCC RADIALISATION OF CHIKKODI ON N-E-W GRID THROUGH CHIKKODI – KOLHAPUR LINE 10-Jul-09 37th OCC OUTAGE OF 220KV CHITTOR - THIRUVALEM LINE SINCE 10TH FEB 09 – PROGRAMME FOR PUTTING LINE BACK INTO SERVICE 10-Jul-09 37th OCC CLOSING OF SULURPET-GUMMDIPOONDI FOR REDUCING OVERLOADING OF NEYVELI - S P BUDUR LINE 09-Sep-09 39th OCC PROLONGED OUTAGE OF CHITTOOR-THIRUVELAM SINCE 10TH FEB 09 15:20 HRS 13-Oct-09 40th OCC PROLONGED OUTAGE OF CHITTOR – THIRUVALEM LINE SINCE 10TH FEB 09 15:20 HRS 12-Nov-09 41st OCC PROLONGED OUTAGE OF CHITTOR – THIRUVALEM LINE SINCE 10TH FEB 09 15:20 HRS 12-Nov-09 41st OCC PROLONGED OUTAGE OF SULURPET –GUMMUDIPOONIDI SINCE 24 /10/09 22:40 HRS 11-Dec-09 42nd OCC TN TO EXPEDITE SYNCHRONISATION OF CHITTOR-THIRUVALEM LINE 11-Dec-09 42nd OCC REVIEW OF SULURPET – GUMMIDIPOONDI O/L TRIPPING SETTINGS 08-Jan-10 43rd OCC TN TO EXPEDITE SYNCHRONISATION OF CHITTOR-THIRUVALEM LINE 08-Jan-10 43rd OCC REVIEW OF SULURPET – GUMMIDIPOONDI O/L TRIPPING SETTINGS 03-Feb-10 8th PCC TN TO EXPEDITE SYNCHRONISATION OF SULURPET – GUMMIDIPOONDI & CHITTORTHIRUVALEM LINE 11-Feb-10 44th OCC TN TO EXPEDITE SYNCHRONISATION OF CHITTOR-THIRUVALEM LINE 11-Feb-10 44th OCC REVIEW OF SULURPET – GUMMIDIPOONDI O/L TRIPPING SETTINGS 09-Mar-10 45th OCC TN TO EXPEDITE SYNCHRONISATION OF CHITTOR-THIRUVALEM LINE 25-Jun-10 48th OCC TN TO EXPEDITE SYNCHRONISATION OF CHITTOR-THIRUVALEM LINE 14-Jul-10 49th OCC CHITTOR-THIRUVALAM LINE CHARGED ON 28.06.10 08-Oct-10 52nd OCC TN TO EXPEDITE SYNCHRONISATION OF SULURPET – GUMMIDIPOONDI LINE 10-Dec-10 54th OCC SYNCHRONISED THE 230 kV SULURPET – GUMMIDIPOONDI LINE ON 04.12.2010 10-Jan-11 55th OCC RESTRICT THE LINE LOADING TO < 100 MW ON SULURPET – GUMMIDIPOONDI LINE 08-Feb-11 56th OCC TN TO EXPEDITE SYNCHRONISATION OF SULURPET – GUMMIDIPOONDI LINE 09-Mar-11 57th OCC TN TO EXPEDITE SYNCHRONISATION OF SULURPET – GUMMIDIPOONDI & CHITTORTHIRUVALEM LINE Operation of 400 kV Lines Upto SIL derived steady State limit Supp Agenda 2 Point 2 OF TCC PPT REPORT Automatic Data Reading (AMR) /Collection • To avoid all the data related delays and fulfill the deadlines set by IEGC, SRLDC had proposed to adopt AMR scheme in SR. In SR, there are about 600 SEMs installed in about 100 locations. Scheme may be implemented by PGCIL at an estimated cost of about Rs. 1.5 Crores which can be recovered through tariff in the same way as the cost of SEMs is being recovered. • Outcome of the 14th commercial Sub – Committee meeting Committee in principle agreed the proposal. SRLDC suggested that cost may be recovered through tariff. Proposal for automatic data reading (AMR) /collection (to be implemented by POWERGRID): To avoid delays in SEM data transmission to SRLDC it is proposed to adopt AMR scheme in SR at an estimated cost of Rs.1.5Crores.Schematic representation of AMR is as below. Hardware required for each location: Modem-1 no, Data Concentrator Unit-1 no Local Computer- 1 no., Remote Computer at SRLDC – 1 no. Cost of Communication on GPRS mode : as per actual. Bill Of Quantities Sl. No. Description Qty. * Unit Rate Rs ** Amount Rs. A For S/S with meters located in Control Room (Aprox. 120 S/S) # 1) All required hardwares i.e. Meter Interfacing Unit/Protocol Comnverter/Optical Probe/ Connectors / Cable for data transfer between meters and Data Concentrator etc. 700 Per SEM 6602 4621400 2) Data Concentrator Unit/Data Accumulator (one No. at each location) 120 No. 22000 2640000 3) GPRS Modem (One No. at each location) 120 No. 6500 780000 B Common for total Scheme 1) Meter Data Acquisition & Analysis software (For all Data Concentrator Units/Data Accumulators (Approx. 120 Nos.) and Servers at SRLDC (2 Nos.). 1 Lumpsu m 1000000 1000000 2) Training to personnel posted at all S/S where scheme will be commisioned and SRLDC. (10 Trainings with a batch of 20-30 participants) 10 No. 3) Installation, Testing & Commissioning/Customization cost 700 Per SEM 2112 1478400 C CENTRAL LOCATION (AT SRLDC & 6 SLDCs) 1) Central server (Including cost of required RDBMS & OS) 7 No. 175000 1225000 2) UPS (2 KVA) 7 No. 30000 210000 3) GPRS/GSM Modems 7 No. 6500 45500 D Wararnty / AMC 1) Warranty for 1 year 2) AMC for 1st year after Warranty 700 Per SEM 806 564480 3) AMC for 2nd year after Warranty 800 Per SEM 853 682667 4) AMC for 3rd year after Warranty 900 Per SEM 894 804414 5) AMC for 4th year after Warranty 1000 Per SEM 929 929032 Total 15180893 200000 NIL Minutes of 14th NRPC meeting reg. AMR scheme implementation Back