Pavement Performance Specifications Research Florida Department of Transportation Asphalt Pavement Facts • FDOT: 5 million tons asphalt per year – Approximately $500 million – 300 construction projects • 96% of pavements in Florida are asphalt – 93% of pavements in US are asphalt • It’s 100% recyclable (RAP) • Typical life-span in Florida is 17 years Florida Department of Transportation Statewide Pavement Performance Section 334.046 of Florida Statutes: “Ensuring that 80% of the pavement on the SHS meets Department Standards” Florida Department of Transportation Statewide Pavement Performance 28% Crack Ride Rut 26% 24% 22% % Deficient 20% 18% 16% 14% 12% 10% 8% 6% 4% 2% 0% Florida Department of Transportation Deficient Roadways Florida Department of Transportation Asphalt Specifications Update January 2013 – July 2014 Florida Department of Transportation January 2013 Workbook • Section 300 – Prime and Tack Coats – Approved NTSS-1hm (trackless tack) as prime coat – Tack all asphalt layers (clarification) Florida Department of Transportation January 2013 Workbook • Section 320 – Hot Mix Asphalt – Plant Methods and Equipment – No more viscosity testing of RAP every 5000 tons (Materials Memo 01-13) – Can use loaded aggregate trucks for scale checks. – Modified wording related to release agents; banning petroleum based products, not just “diesel fuel” Florida Department of Transportation January 2013 Workbook • Section 330 – Hot Mix Asphalt - General Construction Requirements – Eliminated mandatory requirement to perform QC rolling straightedge testing on friction course if final acceptance is by laser profiler – Can only mill out high straightedge deficiencies. No milling of “two highs” to fix a low deficiency Florida Department of Transportation January 2013 Workbook • Section 334 – Superpave Asphalt Concrete – Lowered minimum overbuild thickness for SP-12.5 to ½” Table 334-2 Asphalt Binder Grade for Mixes Containing RAP Percent RAP Asphalt Binder Grade 0 - 15 PG 67-22 16 - 30 PG 58-22 >30 PG 52-28 – Removed Ninitial requirements Florida Department of Transportation January 2013 Workbook • Section 334 – Superpave Asphalt Concrete – No density testing if less than 50 tons of “density mix” in a sublot – No more pro-rating LOT pay factors by density required/no density required areas. Entire LOT gets pay factor unless entire LOT is no density required Florida Department of Transportation January 2013 Workbook • Section 916 – Bituminous Materials – Elimination of RA viscosity graded binders. Now all binders are PG graded – Removed RA-500, RA-750, RA-1000, RA-1500 and replaced with PG 52-28 and PG 58-22 – No longer using PG 64-22 for HMA – Eliminated net total of three binders – Materials Memo 11-26 issued to allow use on contracts let prior to January 2013 Florida Department of Transportation July 2013 Workbook • Section 234 – Superpave Asphalt Base – Can substitute a SP-12.5 Traffic Level D or E mixture in lieu of a Type B-12.5 mixture, not to exceed 500 tons for a project, at no extra cost to the Department, in limited situations if approved by the Engineer • Section 320 – Hot Mix Asphalt – Plant Methods and Equipment – Cover and tie down all loads of friction course Florida Department of Transportation July 2013 Workbook • Section 330 – Hot Mix Asphalt - General Construction Requirements – Moved FC-5 temperature requirements from 337 to 330 Florida Department of Transportation July 2013 Workbook • Section 334 – Superpave Asphalt Concrete – Variable thickness overbuild layers constructed using a Type SP-9.5 or SP-12.5 mixtures may be tapered to zero thickness provided a minimum of 1-1/2 inches of dense-graded mix is placed over the variable thickness overbuild layer – Pavement Composition Report changed to Pavement Coring Report Florida Department of Transportation July 2013 Workbook • Section 336 – Asphalt Rubber Binder – Eliminated ARB-5 and ARB-12 • Section 916 – Bituminous Materials – Addition of “PG 76-22 (ARB)” to replace ARB-5 and ARB-12 – Requirements for “PG 76-22 (ARB)”: • • • • Minimum 7% GTR. Certification Optional polymer modification, if needed Must meet the requirements for PG 76-22 Additional “separation” requirement to minimize settlement Florida Department of Transportation July 2013 Workbook • Section 916 – Bituminous Materials – Previous PG 76-22 with SBS polymer renamed to PG 76-22 (PMA) – PG 82-22 (PMA) added to standard specification – Implementation of Multiple Stress Creep Recovery (MSCR) tests for modified binders only – Polyphosphoric acid (PPA) may be used as a modifier not exceeding 1.25% by weight of asphalt binder Florida Department of Transportation July 2013 Workbook • Section 919 – Ground Tire Rubber – Modified gradation requirements (only max particle size; 98% passing no. 30 sieve) – Removed mandatory ambient grinding requirement – Changed maximum Rubber Hydrocarbon Content from 55% to 60% to reflect modern day tires Florida Department of Transportation January 2014 Workbook • Section 320 – Hot Mix Asphalt – Plant Methods and Equipment – Allows the first five loads of WMA to be produced at HMA temperature for purposes of heating the paver. Mix temperature not to exceed 330°F • Section 330 – Hot Mix Asphalt - General Construction Requirements – Do not use diesel fuel or other petroleum based solvents contained in an open container for cleaning purposes on the paver Florida Department of Transportation January 2014 Workbook • Section 334 – Superpave Asphalt Concrete – Removed coarse graded mixtures – Increased maximum lift thickness of fine graded SP-19.0 mix type from 3" to 3-1/2" because coarse graded mixtures were removed • Section 337 – Asphalt Concrete Friction Courses – Increased maximum possible design AC content for granite FC-5 mixtures from 7.0 to 7.5% Florida Department of Transportation January 2014 Workbook • Section 916 – Bituminous Materials – Added a statement that excess PG 76-22 (ARB) could be mixed with unmodified binder under the conditions outlined in the specification Florida Department of Transportation July 2014 Workbook • Section 300 - Prime and Tack Coats – Removed cut-back prime coats and emulsion grades not being used any more – Added two new trackless tack products • Section 320 – Hot Mix Asphalt – Plant Methods and Equipment – Added language "For warm mix asphalt, the Contractor may produce the first five loads of the production day and at other times when approved by the Engineer, at a hot mix asphalt temperature not to exceed 330°F for purposes of heating the asphalt paver Florida Department of Transportation July 2014 Workbook • Section 334 – Superpave Asphalt Concrete – Added clarification for SP-19.0 mixtures: "Type SP-19.0 - May not be used in the final (top) structural layer below FC-5 mixtures. Type SP-19.0 mixtures are permissible in the layer directly below FC-9.5 and FC-12.5 mixtures." – Set time limit of 60 days for how long a LOT can be left open. Florida Department of Transportation July 2014 Workbook • Section 916 – Bituminous Materials – Removed cut-backs, some emulsions, and added trackless tacks – Emulsions now approved and monitored like binders. Added to the QPL. – For PG 76-22 (ARB), provide a certification statement on the product evaluation application and in the Quality Control Program that a minimum of 7.0% GTR is used in the formulation of the binder. Florida Department of Transportation Hot Topics & Research Notables Florida Department of Transportation NCAT Test Track • 20” of asphalt base insures all failures are in the top 4” asphalt structural layers. • One truck = six fully loaded 18wheelers (152,000 lbs.) • Five trucks are operational at one time. ≈ 45 mph. • Load 5 AM to 11 PM. Two shifts per day. 340 miles per driver per day. 6 days per week. • 3 year research cycle – 10 million ESALs applied over two years. (10.36 ESALs per pass) – Forensics and reconstruction on 3rd year. Florida Department of Transportation NCAT Test Track • 2000-2003 – Fine vs. Coarse (PG 6722) • 2003-2006 – Continuation of 2000 cycle – PG 76-22 vs. PG 76-22 • Validation of SMO HVS • 2006-2009 – Validation of Energy Ratio Florida Department of Transportation • 2009-2012 – Bonded Friction Course • 2012-2015 – Thick tack coats – Polymer vs. Rubber – High RAP vs. Shingles Pavement Preservation • Traditionally FDOT has focused on milling and resurfacing • Higher traffic volume roadways • Goal: Get in, get out, stay out… Florida Department of Transportation FDOT LOOKING AT ALTERNATIVES… Hot-In-Place Recycling Microsurfacing Crack Sealing Fog Seal Florida Department of Transportation HOT IN-PLACE RECYCLING • 12 projects* constructed to date: – 11 as “Reworked Asphalt” – 1 as “Repaved Asphalt” • Every district except for Turnpike • Earliest project* 2001 • Four projects completed in 2012 * “Modern” Era Florida Department of Transportation MICROSURFACING • First FDOT microsurfacing project: – US-319 Leon County – 2010 • Worked with several Contractors & Suppliers on specification – Based on ISSA requirements • ISSA Type II mixture gradation • Spread rate 20 – 26 lbs/sy – Single course • Required crack sealing Florida Department of Transportation Crack Sealing • Five Crack Seal Test Decks were placed in March 2012 – Leon, Baker, Sumter, DeSoto, and Miami-Dade Counties • Several materials and construction techniques evaluated • Performance will be monitored for three to five years Florida Department of Transportation Fog Sealing Test Sections • Placed in 2013 • US-27 & US-17 Polk County • Placed on OGFC – Attempt to reduce raveling & top-down cracking – Age: 4 years old – Good condition • Multiple Test Sections • Multiple Products Florida Department of Transportation Pavement Preservation Test Sections • US-98 Gulf County – Constructed 2012 • Ten Test Sections: 1. 2. 3. 4. 5. 6. 7. 8. 9. Control Section Micro-surfacing (Double course) 1/2” HMA overlays with 4.75 mm mix 3/4” HMA overlays with 4.75 mm mix 1” HMA overlay with 9.5 mm mix Hot-in-place recycling Bonded open graded friction course Mill and resurface 1.0” with 9.5 mm mix Mill and resurface 1.5” with 12.5 mm mix 10. Control section Florida Department of Transportation Recycling Program Florida Department of Transportation RAP Data Conditions FY 10/11 FY 11/12 FY 12/13 FY 13/14 Average 25% 26% 25% 25% Maximum 40% 38% 39% 41% Average 17% 18% 16% 15% Maximum 20% 20% 20% 20% Unrestricted (No Maximum Limit) Restricted (Maximum 20%) Florida Department of Transportation RAS • • • • Florida Department of Transportation National Hot Topic FDOT pilot projects 0.85 Binder Availability Issues with the unknown NCAT: HIGH RAP VERSUS RAP/RAS PG 76-22 (PMA) with 25% RAP PG 76-22 (PMA) with 20% RAP & 5% RAS Florida Department of Transportation Pavement Segregation • January 2012 specification • Texture Meter • Pave-IR System Florida Department of Transportation Pave-IR Demo • Oct. 2013 / Turnpike, Palm Beach • Equipment: MOBA Pave-IR • To detect Thermal Segregation Florida Department of Transportation Bonded Friction Course Conventional Trackless UltraFuse eTac Florida Department of Transportation Other Research • New Flow Number (FN) Test: iRLPD • Hydrated Lime Study • Binder Rejuvenators • Optimization of FC-5 characteristics • Volumetric refinement • Field test method to detect Polymer and/or GTR • Alternative technique(s) to mitigate reflective cracking • Performance Specification for Tack – Bond Strength • RAP with Dense-graded FC • FC-5 image analysis for • Evaluation of FL mixes for determination of optimum crack resistance using Overlay binder content Tester • Understanding mechanisms of OGFC raveling Florida Department of Transportation QUESTIONS/ COMMENTS? THANK YOU! Florida Department of Transportation