LFT_FCS_Presentation.potx - nc

advertisement

Brookfield Avenue Landfill

Closure and Post-Closure Use Project

NC SWANA

2014 Fall Conference

Wrightsville Beach

Martin Sanford, PE

October 14, 2014

Outline

• Project Summary

• Closure Design Components

• End Use Plan

– Public Use

– Ecological restoration

• Lessons Learned

Brookfield Ave Landfill Project

Project Summary

• 132-acre New York City MSW landfill on Staten Island

– Operated from 1966 to 1980

– Classified as Class 2 Inactive Hazardous Waste Disposal Site in 1986

• Existing utility infrastructure on the property

– 48” Interceptor sewer and pump station

– Triple reinforced concrete stormwater culvert

– Water and gas lines

• Project Schedule

– Construction started in 2010

– Project currently in the two year contractor maintenance phase

Brookfield Ave Landfill Project

Richmond Creek

Salt Marsh

West Cell

East Cell

Wetlands

Wetlands

Pump Station

Pre Construction Aerial Photo

Brookfield Ave Landfill Project

Design Summary

• Complexity of final cover, remediation, and wetlands construction

– Extensive Grading and Shaping

– Standard Subtitle D Landfill Cap

– Geotechnical Slurry Barrier Wall

– Active Gas Collection System and Flare Station

– Leachate Collection System

• Extensive Landscaping Improvement

• Wetland Restoration

• Maintain access to existing infrastructure

Brookfield Ave Landfill Project

2010 Aerial after Tree Clearing

Brookfield Ave Landfill Project

Typical Landfill Cap

132 Acres of Landfill Cap

6”- 36” TOPSOIL LAYER

12” BARRIER PROTECTION LAYER

GEOCOMPOSITE DRAINAGE NET

40 mil LLDPE GEOMEMBRANE

GEOCOMPOSITE DRAINAGE NET

(GAS COLLECTION LAYER)

MIN 12” INTERMEDIATE COVER/

GRADING LAYER

NORTH

Landfill Cap

Brookfield Avenue Landfill

Landfill Cap

East Cell

Landfill Cap

West Cell

Enclosed Gas Flare

Legend

Groundwater Barrier Wall

Leachate Collection Trench

Typical slurry barrier wall construction

Wetland Restoration – East Cell Over Cap

• Wetland Restoration – Wetlands constructed over cap

Brookfield Ave Landfill Project

End Use Plan – Public Use Park and Recreational

Areas

• Public Use

– “Ecological Restoration”

– Total site 272 Acres

– 15 Acres ACTIVE Recreation – Three Future Multi-Purpose

Sports Fields

– 257 Acres of protection and restoration for PASSIVE recreation

• Park and Recreation Elements

– Access and Parking

– Pedestrian Pathways and Trails

– ADA Considerations

Brookfield Ave Landfill Project

Post Closure “End Use Plan”

Brookfield Ave Landfill Project

NYCDEP End Use Plan – Ecological Restoration

• Ecological Restoration

– Re-introduce Native Plant Materials

– Re-introduce Wetland Areas

– Restore Salt Marsh

– Provide Wildlife Habitat

– Minimize Irrigation, Fertilizing and

Herbicides

– Improve Water Quality and Reduce

Future Soil Erosion

Brookfield Ave Landfill Project

2014 Aerial during Maintenance Period

Brookfield Ave Landfill Project

Lessons Learned

• Drainage Flaps

• Planting Berms

• Swale Crossings

• Pipe Crossings

• Site Access – Construction and End Use

• Protection from Public Access and Deer

Brookfield Ave Landfill Project

Drainage Flaps

Problem:

• Landfill side slopes were flat

• Drainage flaps were long, 100 to 150 feet in some cases.

– Future settlement of the flap could cause drainage issues.

Solution

• Extended completely under the road to the embankment to discharge offsite.

Brookfield Ave Landfill Project

Planting Berms

Design

• 36” topsoil for trees and shrubs

– Mounds built on top of the landfill cap.

• Problem

– Berms blocked stormwater sheet flow.

– Caused ponding and erosion.

• Solution

– Erosion gullies filled with filter fabric and riprap.

– Install small basins and piping.

Brookfield Ave Landfill Project

Swale Crossings

Design

• Pedestrian and bike paths tied into the perimeter maintenance road and concrete swale

Problem

• No mechanism for people or bike riders to cross the swale

Solution

• Purchase grates, chip out the concrete, and install grates in place

Brookfield Ave Landfill Project

Pipe Crossings

Design

• Drop inlets placed at low points to convey stormwater.

• 15” CPP pipes drained were installed under road.

Problem

• Clearance for CPP pipe during active construction.

Solution

• Pipes changed to 12” Ductile

Iron Pipe.

Brookfield Ave Landfill Project

Site Access During Construction and End-Use

• Construction site entrance through residential areas.

– Concern with daily trucks access through the neighborhood.

• Public park access

– One access for both vehicles and pedestrians.

– Additional parking and pedestrian entrances added.

• Local FDNY input

– 30 foot wide access to the flare.

– Secondary access for emergencies.

Brookfield Ave Landfill Project

Protection from Public Access and Deer

• Leachate collection system with nine pumping chambers.

– Control panel located near pedestrian and bike paths.

– Panels were exposed to tampering by the public.

– Panels placed inside lockable cabinets to prevent park users from turning the pumps on and off.

• Protection of 17,000 trees and shrubs.

– Deer was observed eating the new plantings, which had to be replaced.

– 10,000 feet of deer fence added to protect the newly planted landscaping.

Brookfield Ave Landfill Project

Other Keys to Project Success

• Hauling of 2.4 million tons of soil materials

– Common Fill – 927,000

– Protective Cover – 798,000

– Wetland Topsoil – 125,000

– Topsoil – 554,000

• Stakeholder Engagement

– Citizen Advisory Committee

– State and local government

• Remaining Project Schedule

– Contractor Maintenance Phase

– Park areas scheduled to open in 2017

Brookfield Ave Landfill Project

Thank You!

QUESTIONS?

Download