NGB - The British University in Dubai

advertisement

The FIDIC Contracts & Construction Law

A presentation to

The British University in Dubai by

Nael G. Bunni,

BSc, MSc, PhD, CEng, FICE, FIEI,

FIStructE, FCIArb, FIAE, RConsEI .

Chartered Engineer, Conciliator/Mediator and Registered Chartered Arbitrator

Part 1

1 of 37 BUiD’FIDIC’01

1 st April 2011

Copyright NGB

Synopsis

 The FIDIC identity;

 A survey of the FIDIC Forms of Contract and their distinguishing features and characteristics;

 The role of the Engineer and how it compares with the term “Project Manager”;

 The framework of contractual and legal arrangements on a FIDIC Construction Contract;

 The role of insurance in the construction contract;

 The unique feature of seeking to provide for a specific remedy in the event of any breach of the terms of the Contract; &

 The procedure set for claims and dispute resolution.

2 of 37 BUiD’FIDIC’01 Copyright NGB

The FIDIC identity

 FIDIC - Federation Internationale des

Ingenieurs - Conseils

 Founded in 1913 in Ghent , Belgium by the national associations of consulting engineers of Belgium, France & Switzerland

 Has grown to represent associations from over 84 countries worldwide

 Secretariat is located in Geneva, Switzerland

Contd./2

3 of 37 BUiD’FIDIC’01 Copyright NGB

The FIDIC identity

(Contd/2)

 One of the first committees established in 1913 was the Contract Documents Committee.

 Its Terms of Reference were:

– To monitor contract documents of interest to consulting engineers regarding:

» construction of objects or works;

» erection and installation of works;

» maintenance of installations in operation; and

» supply of materials

To inform contractors, suppliers and officials concerning contract documents recommended by FIDIC

Contd./3

4 of 37 BUiD’FIDIC’01 Copyright NGB

The FIDIC identity

(Contd/3)

 First standard form of contract published in

1957

It was the first edition of the Red Book for civil engineering works in the international field

Since then FIDIC has become known outside the engineering profession for its standard forms of contract

 The Red Book was followed by the Yellow

Book for Electrical and Mechanical Works including erection on site

Contd./4

5 of 37 BUiD’FIDIC’01 Copyright NGB

The FIDIC identity

(Contd/4)

Standard Forms & Associated Documentation

Conditions of Contract for Works of Civil Engineering

Construction (Red Book), 4th Edition, 1987; updated in 88 & 92

– Conditions of Contract for Electrical and Mechanical Works including erection on site (Yellow Book), 3rd Edition, 1987

Conditions of Contract for Design-Build and Turnkey (Orange

Book), 1st Edition, 1995

Conditions of Sub-contract for Works of Civil Engineering

Construction, 1st Edition, 1994

Tendering Procedure, 2nd Edition, 1994

Client/Consultant - model services Agreement (White Book), 3rd

Edition, 1998; 4 th Ed. 2006

Joint Venture (Consortium) - Agreement, 1st Edition, 1992

Sub-consultancy Agreement, 1st Edition, 1992

– Dredging & Reclamation Form of Contract, 1st Edition, 2006

6 of 37 BUiD’FIDIC’01 Copyright NGB

The FIDIC identity

(Contd/5)

 First Edition of the Green Book – Short Form of

Contract – Agreement, General Conditions, Rules for Adjudication and Notes for Guidance;

 The 1999 Red Book – Conditions of Contract for

Construction, (for Building and Engineering Works,

Designed by the Employer) – General Conditions,

Guidance for the Preparation of the Particular

Conditions, Forms of Tender, Contract Agreement, and Dispute Adjudication Agreement, 29,775 words;

7 of 37 BUiD’FIDIC’01 Copyright NGB

The FIDIC identity

(Contd/6)

 First Edition of a new Yellow Book: Conditions of

Contract for Plant and Design-Build for Electrical and Mechanical Plant, and for Building and

Engineering Works, Designed by the Contractor –

General Conditions, Guidance for the Preparation of the

Particular Conditions, Forms of Tender, Contract Agreement and Dispute Adjudication Agreement, 30,408 words; and

 First Edition of the Silver Book: Conditions of

Contract for EPC turnkey Projects – General

Conditions, Guidance for the Preparation of the Particular

Conditions, Forms of Tender, Contract Agreement and

Dispute Adjudication Agreement, 26,792 words.

8 of 37 BUiD’FIDIC’01 Copyright NGB

Other Developments since 1999

The Harmonised Multilateral

Development Banks Form of Contract,

1 st Ed. 2005, 3 rd Ed. 2010

The Dredging & Reclamation Works, 1 st

Ed. in 2006

The most important development is the introduction of the “Gold Book” in 2009

The Test Ed. of The Subcontract Form for the 1999 Red Book, published in

December 09

9 of 37 BUiD’FIDIC’01 Copyright NGB

The Harmonised MDB Form

MDB: The Harmonised Multilateral

Development Banks Form of Contract, 2005;

Intended for MDB funded projects;

FIDIC retains copyright & Management;

Based on the 1999 Red Book, which remains

FIDIC’s recommended Form, but amended shifting many risks to the Contractor, including the reduced Authority of Engineer;

The 3 rd Ed. was issued in 2010

Many changes: for example. Cl. 20.

10 of 37 BUiD’FIDIC’01 Copyright NGB

The DBO Form:

Design, Build & Operate

The Gold Book deals with:

Design, Build and Operate (DBO) Projects.

It is based on and developed from the 1999 Yellow

Book.

It is intended for projects where the employer wishes the contractor not only to design and construct a facility, but also to continue and operate and maintain that facility for a long number of years.

Examples of Projects: Water treatment plants,

Power generation plants and manufacturing or process facilities, and motorways/highway projects .

11 of 37 BUiD’FIDIC’01 Copyright NGB

Comparison of the 1999 Forms with previous major forms

Form of Contract Equivalent in the New Forms

Red Book, 4 th Ed. 1992

Red Book, 4 th Ed. With

Suppl. 1996

New Red where the DAB is Adhoc & the

Engineer acts as the DAB

New Red where the DAB is Standing & the

Board is Independent & Impartial

New Yellow, 1999 Yellow Book, 3 rd Ed.

1988

Orange Book, 1 st Ed.

1995

Newly developed

Forms

New Yellow, 1999

Silver Book & Green

Book, 1999

12 of 37 BUiD’FIDIC’01 Copyright NGB

Usual contractual arrangements in a construction project

Employer or Owner

Engineer

Contractor

Sub-contractors

Other

Consultants

Suppliers

Manufacturers

13 of 37

Direct contract

Indirect relationship

BUiD’FIDIC’01 Copyright NGB

Aspects to consider when choosing standard form:

 The allocation of the essential functions found in the project and particularly the design function;

 The allocation of the risks inherent in the projects;

 The allocation of the management role; and

 The method and timing of remuneration for the contractor.

14 of 37 BUiD’FIDIC’01 Copyright NGB

15 of 37

1. The allocation of the essential functions found in the project and particularly the design function

BUiD’FIDIC’01 Copyright NGB

The Allocation of Functions

 The following functions must be allocated to certain parties:

Promoter : Initiator of project or Employer/Owner

Financier and his role as:

»

Self financing

» A simple lender

»

A lender in Build - Transfer

» A lender in Build - Own - Transfer BOT

»

A lender in Build - Own - Transfer and Operate BOOT

»

A lender in Build - Own - Operate BOO

»

A lender in Build - Rent - Transfer BRT

»

BLT in leasing rather than renting

Contd./2

16 of 37 BUiD’FIDIC’01 Copyright NGB

The Allocation of Functions (cont.)

Designer

»

Sketch design

»

Preliminary design

»

Final design

Manager and coordinator of various design functions

Contractor

Sub-contractor, supplier and manufacturer

Project Manager** & Safety Controller

Supervisor

Certifier

Adjudicator

Operator

17 of 37 BUiD’FIDIC’01 Copyright NGB

Roles under FIDIC Standard Forms

 Promoter/Employer

Finance and operation of project

 Engineer

Design in the Red Book, New & Old

– Supervision

Certification

– Adjudication in the Old Red & Yellow Books, but with the DAB elsewhere

 Contractor

– Construction

– Design in the New Yellow Book, partly in the Old

Yellow; the Orange Book & the Silver Book

18 of 37 BUiD’FIDIC’01 Copyright NGB

The Role & Functions of the Engineer

(a) The Completion of a skilful design incl.:

– preparation of drawings;

– drafting specification for materials & workmanship;

– preparation of a bill of quantities .

(b) The preparation of tender & contract documents and advising on the selection of a contractor.

(c) The supervision & quality control of work on site.

(d) The administration of the contract & evaluation

& certification of the work carried out .

(e) Adjudication of disputes .

19 of 37 BUiD’FIDIC’01 Copyright NGB

The different roles Red Book 1992

 Pre - construction Stage [ Steps (a) & (b) ] :

The Engineer acts as an advisor & consultant.

 Construction Stage [ Steps (c) & (d) ] :

The Engineer acts as an Agent of the Owner.

 Construction Stage [ Step (e) ] :

The Engineer acts as an independent , impartial & neutral professional. (under the

1999 Red Book: only when specifically stated)

20 of 37 BUiD’FIDIC’01 Copyright NGB

The Engineer as a designer

 The shape, form and dimensions of the project

 The function & performance

 The selection of the materials & workmanship

 The production of documents

 Projection of cost

 Establishing timing & sequence of construction

21 of 37 BUiD’FIDIC’01 Copyright NGB

The Engineer as the Employer’s Agent

 Implementing & augmenting the design

 Quality control

 Administration and management

Pro-active duties

Re-active duties

Passive duties

 Cost accountancy & certification

22 of 37 BUiD’FIDIC’01 Copyright NGB

The Engineer as a supervisor

To supervise, inspect, oversee, or monitor :

Compliance with specified quality

Progress in accordance with the planned Programme

Budget control as in the cost plan

Compliance with safety & other control requirements

23 of 37 BUiD’FIDIC’01 Copyright NGB

The Engineer as a certifier

 Valuation of work done & Payments to the

Contractor (Cl. 60); (Cl. 12);

 Issue Taking - Over Certificate (Cl. 48); (Cl. 14);

 Date of Completion (Cl. 49); (Cl. 8);

 Payments to nominated sub-contractor (Cl. 59);

(Cl. 5);

 Issue Final Certificate (Cl. 60.8); (Cl. 14.13);

 Defects Liability Certificate (Cl. 62.1); (Cl. 14);

 Valuation of work done, etc. in case of

Termination (Cl. 63.2); (Cl. 15).

24 of 37 BUiD’FIDIC’01 Copyright NGB

The Engineer as an adjudicator under the 1992 Red Book

 Dispute Reference to the Engineer

[84 days for the Engineer to make a decision]

 The Engineer gives notice of his decision in writing

– [70 days for Emp. or Cont. to disagree & give notice of intention to commence arbitration]

 If notice of intention to commence arbitration is given, then attempt amicable settlement (56 days)

[If no settlement, arbitration may then commence. Place, no. of arbitrators & language may be inserted]

 ICC Rules apply unless stated otherwise in Part II

– [ Extreme care must be taken in amending this clause]

25 of 37 BUiD’FIDIC’01 Copyright NGB

Impartial or fair –Red 1992 – Clause 2.6

The Engineer to Act Impartially

2.6 Wherever, under the Contract, the Engineer is required to exercise his discretion by:

(a) giving his decision, opinion or consent,

(b) expressing his satisfaction or approval,

(c) determining value, or

(d) otherwise taking action which may affect the rights and obligations of the

Employer or the Contractor he shall exercise such discretion impartially within the terms of the Contract and having regard to all the circumstances.

…………

26 of 37 BUiD’FIDIC’01 Copyright NGB

Impartial or fair –Red 1999 – 3.1

3.1 Engineer’s Duties and Authority

………….. . The Engineer may exercise (his) authority ……. as specified in or necessarily to be implied from the Contract. ………………..

Except as otherwise stated in these Conditions:

(a) whenever carrying out duties or exercising authority, specified in or implied by the Contract, the Engineer shall be deemed to act for the

Employer;

(b) the Engineer has no authority to relieve either

Party of any duties, obligations or responsibilities under the Contract; and

27 of 37 BUiD’FIDIC’01 Copyright NGB

Impartial or fair –Red 1999 – 3.1

(c) any approval, check, certificate, consent, examination, inspection, instruction, notice, proposal, request, test, or similar act by the Engineer

(including absence of disapproval) shall not relieve the Contractor from any responsibility he has under the

Contract, including responsibility for errors, omissions, discrepancies and non-compliances.

28 of 37 BUiD’FIDIC’01 Copyright NGB

Impartial or fair –Red 1999 – 3.5

Determinations 3.5

Whenever these Conditions provide that the Engineer shall proceed in accordance with this Sub-Clause 3.5 to agree or determine any matter, the Engineer shall consult with each Party in an endeavour to reach agreement. If agreement is not achieved, the Engineer shall make a fair determination in accordance with the

Contract, taking due regard of all relevant circumstances.

29 of 37 BUiD’FIDIC’01 Copyright NGB

2. The allocation of the risks inherent in the project;

30 of 37 BUiD’FIDIC’01 Copyright NGB

The Allocation of Risks &Liability

 Law of contract allocates risks to contracting parties.

 Standard Forms affirm that allocation or re-allocate risks to another contracting part or third party.

 For Civil Engineering Construction the following concepts must be borne in mind:

– The meaning and significance of “Risk”;

Not all undesirable events can be perceived and identified; and

Whilst risks generally imply undesirable consequences, in certain circumstances desirable as well as undesirable consequence may occur

31 of 37 BUiD’FIDIC’01 Copyright NGB

DEFINITIONS:

RISK: ‘ The combined effect of the probability , or frequency, of occurrence of a defined hazard and the magnitude of the consequences of the occurrence. ’

B.S. 4778, 1991.

 Australia/New Zealand Risk Management

Standard AS/NZ 3951: 1995: hazard is replaced by event, which includes positive as well as negative consequences.

32 of 37 BUiD’FIDIC’01 Copyright NGB

DEFINITIONS:

HAZARD: ‘A situation that could occur during the lifetime of a product, system or plant that has the potential for human injury, damage to property, damage to the environment, or economic loss’.

RISK = “Hazard” x Probability of occurrence

33 of 37 BUiD’FIDIC’01 Copyright NGB

34 of 37

3. The allocation of the management role; and

The method and timing of remuneration for the contractor

BUiD’FIDIC’01 Copyright NGB

Management, Timing & Method of Remuneration

 When allocating risks and functions, the promoter or employer should consider:

Management and method of valuing work done and its payment

Is he prepared to share risks with other parties

Extent of such sharing

35 of 37 BUiD’FIDIC’01

Contd./2

Copyright NGB

Management, Timing & Method of

Remuneration

(Contd./3)

 Categories to consider depending on the extent of risk accepted:

Cost-reimbursable contracts

»

May be sub-divided depending on sums to be added

Re-measurement contracts based on unit rates and prices. May be sub-divided into:

Bill of quantities & Schedule of rates

– see next slide

36 of 37 BUiD’FIDIC’01 Copyright NGB

Management, Timing & Method of

Remuneration

(Contd./2)

Lump sum contracts. May be subdivided into:

»

Fixed price

»

No sharing of risks

»

Limited sharing

37 of 37 BUiD’FIDIC’01 Copyright NGB

Download