Shah Gas Development Project Presentation on

advertisement
SOGAT 2012
The Shah Gas Development Project
A Lifecycle Approach to the HSEIA Process
Abu Dhabi Gas Development Company Ltd.
CONFIDENTIAL
Page
Page‹#›
1
HSE Impact Assessment
What is an HSEIA & Its Importance
•
An HSEIA is systematic approach to evaluating the potential effect of a project
on health, safety and the environment
•
A living document that considers the full lifecycle of the project (FEED, EPC,
Operations, Decommissioning & Abandonment)
•
ADNOC Requires HSEIAs to be undertaken for all project phases
•
Key function is to identify, assess, mitigate to ALARP and monitor on a
continuous basis all material risk that can adversely impact health, safety, and
environment
•
Residual impacts and hazards managed by the operator’s HSE Management
System (HSEMS)
Abu Dhabi Gas Development Company Ltd.
CONFIDENTIAL
Page
Page‹#›
2
A Lifecycle Approach to the HSEIA Process
Introduction to the Approach
• A streamlined, risk-based and quality-focused methodology based on current
industry best practice for HSE Case development
• A systematic and gated verification and review process that provides for the
management of major accident hazards through the lifecycle of the Shah Gas
Development (SGD) Programme
• Greater emphasis is placed on HSE Critical Equipment and Systems (HSECES)
integrity that provides significant safety and efficiency benefits to the end user
• Developed in close cooperation with the ADNOC EHS Division
• Demonstrates the safe systems of work and organisation required to effectively
identify, manage and maintain risks to a tolerable and As Low As Reasonably
Practicable (ALARP) level
• Based on the detailed assessment of the proposed SGD activities and the outputs
from HSEIA studies, management plans and procedures
Abu Dhabi Gas Development Company Ltd.
CONFIDENTIAL
Page
Page‹#›
3
A Lifecycle Approach to the HSEIA Process
How it is Different from Traditional HSEIA Approaches
The Al Hosn Gas HSEIA approach is a departure from traditional HSEIAs process in
the following ways:
• Process based method compared to the traditional prescriptive methodology of
HSEIA report development
• Is overarching and not limited to providing a ‘snap-shot’ in time of HSE risk i.e.
lifecycle philosophy
• Systematic and gated verification and review process provide tangible barriers
from allowing the development to proceed to the next stage until a strategy to
manage HSE risks to ALARP can be put in place
• Reduces unnecessary duplication of HSE studies/reviews; and
• Reduces the turnaround time for obtaining approvals from ADNOC EHS Division.
• Inter-linkages between quality management and procurement thus effectively
integrating supply chain logistics in the lifecycle and improving operational
efficiency
Abu Dhabi Gas Development Company Ltd.
CONFIDENTIAL
Page
Page‹#›
4
A Lifecycle Approach to the HSEIA Process
How it is Different from Traditional HSEIA Approaches
The following slides contain diagrams and process flows for the following:
1. ADNOC HSEIA report process (slide 6)
2. Overview of the Al Hosn Gas lifecycle HSEIA approach developed for the
Phase II SGD Programme – well operations and well testing (slide 7)
3. The 8 step elements of the Al Hosn Gas lifecycle HSEIA approach developed for
the Phase II SGD Programme – well operations and well testing (slides 8 – 15)
Abu Dhabi Gas Development Company Ltd.
CONFIDENTIAL
Page
Page‹#›
5
A Lifecycle Approach to the HSEIA Process
Traditional ADNOC HSEIA Report Components
ADNOC HSE Impact
Assessment Report
ADNOC and
SPC as
regulator
require HSEIA
for O&G
Projects
Hazard & Effects Register
For Risk categories:
People, Environment, Assets &
Reputation
Environmental
Impact Statement
COMAH Report
OHRA Report
• Identify and assess material Risk
• Mitigate risk to ALARP
• Provide control measures and monitoring
Manage medium/low risk through Operator’s HSE Management System
Abu Dhabi Gas Development Company Ltd.
CONFIDENTIAL
Page
Page‹#›
6
Al Hosn Gas Lifecycle HSEIA Approach
SGD Phase II – Drilling, Well Testing & Cleanup Phase
8
1
Project
Initiation &
Control
Well Testing &
Handover
2
Gates
Review
7
Evergreen Process
MAH & HSECES
Identification
3
Gates
Review
6
Drilling
Operations
HSE Critical
Positions & Tasks
Gates
Review
Quality
Management
4
Detailed Well &
Well Test Design
& Engineering
Abu Dhabi Gas Development Company Ltd.
5
Procurement,
Inspection &
Testing
CONFIDENTIAL
Page
Page‹#›
7
SGD Phase II – Drilling, Well Testing & Cleanup Phase
Project Initiation &
Element 1
Control
1.1
Baseline
Documentation
Design Codes, Standards and Guidelines established by
Drilling Development Division for the Drilling
Contractors.
1.2
Change Control
in Design
Abu Dhabi Gas Development Company Ltd.
Robust Change Control procedures in place for review,
approval & documentation of design changes.
Change Management supported by an integrated
(Company/Contractor) multi-discipline technical
authority community (approved terms of reference)
CONFIDENTIAL
Page
Page‹#›
8
SGD Phase II – Drilling, Well Testing & Cleanup Phase
MAH & HSECES
Element 2
Identification
2.1
HEMP Studies
HAZID/ENVID/OHRA etc., to identify Major Accident
Hazards (MAHs) & Initial identification of HSECES.
ISO17776 Standard for Hazard Reference Codes with
additional hazards identified for Al Hosn Gas
2.2
Risk Registers
2.3
Bowtie Analysis
Standard Hazards, Effects & Aspects Register format used
by Company and Contractors
Developed via multi-discipline technical authority
community workshops using BowTieXP.
Company Bowtie Analysis Standard establishes unique
hazard and barrier referencing system that will carry
through from design to operations bowties
2.4
HSECES
Identification
Abu Dhabi Gas Development Company Ltd.
HSECES are identified and confirmed by discipline
technical authorities during bowtie analysis workshops.
Controlled HSECES Register
CONFIDENTIAL
Page
Page‹#›
9
SGD Phase II – Drilling, Well Testing & Cleanup Phase
HSE Critical
Element 3 Positions
& Tasks
• HSE Critical Positions & Tasks identified
for all HSECES for the Drilling & Well
Testing Phase.
• Unique barrier referencing system
facilitates efficient assurance activities
i.e., barrier verification audits.
Abu Dhabi Gas Development Company Ltd.
CONFIDENTIAL
Page
Page ‹#›
10
SGD Phase II – Drilling, Well Testing & Cleanup Phase
Well & Well Test
Element 4 Detailed
Design & Engineering
4.1
Well & Well Test
Design
Execution plans and assignment of competent resources
4.2
Design Inputs &
Outputs
Quality plans, codes/specs/standards and HSE criteria
Design programs and calculation sheets
4.3
Well Design &
Development
Review
Integrated multi-discipline design reviews conducted
4.4
HSE Embedded
into Process
Specific safety studies and reviews in line with the HSE
plans
4.5
Design &
Development
Validation
Abu Dhabi Gas Development Company Ltd.
Independent Verification Process for HSECES
CONFIDENTIAL
Page
Page ‹#›
11
SGD Phase II – Drilling, Well Testing & Cleanup Phase
Procurement,
Element 5
Inspection & Testing
5.1
Purchase
Information
HSECES Design Performance Standards Operating
Envelope Criteria
5.2
Verification of
Purchased Products
HSECES inspection and test plans
Independent Verification Process for HSECES
5.3
Inspection &
Testing
Inspection and testing plans prior to operation
5.4
Inspection &
Disposition Reports
Abu Dhabi Gas Development Company Ltd.
Verification of inspection reports
Third Party Inspection monitoring
Change Control procedures
CONFIDENTIAL
Page
Page ‹#›
12
SGD Phase II – Drilling, Well Testing & Cleanup Phase
Drilling Operations
Element 6
6.1
Testing Well Integrity
Drilling logs.
Cement quality and casing integrity testing.
6.2
Validation Processes
Pre-mobilization audits of HSECES.
Technical audits to check critical equipment.
6.3
Identification &
Traceability
Abu Dhabi Gas Development Company Ltd.
Quality plans
Identification procedures
Non-conformance procedures
CONFIDENTIAL
Page
Page ‹#›
13
SGD Phase II – Drilling, Well Testing & Cleanup Phase
Quality
Element 7
Management
7.1
Measurement
Inspection, testing and examination against design
performance standards
7.2
Non-conformance
Non-conformance control procedure
Non-conformance reports & follow up
7.3
Analysis
Abu Dhabi Gas Development Company Ltd.
Monthly quality reports
Independent Verification Body (IVB) compliance
reports
CONFIDENTIAL
Page
Page ‹#›
14
SGD Phase II – Drilling, Well Testing & Cleanup Phase
Well Testing &
Element 8
Handover
8.1
Stimulation &
Cleanout & Testing
Defined Test Objectives – optimised well test programme
Well integrity assurance – standards verification
Wellsite HSE management plan (BAT & ALARP principles)
Management of change
8.2
Air Quality
Flaring Management
Dispersion Modeling
Real time data monitoring – model verification
8.3
Operation
Validation
8.4
Handover
Abu Dhabi Gas Development Company Ltd.
Validation of testing contractors QA/QC via
ADNOC standards & audit
Competence assurance
Nitrogen purging of service lines
Permit to work compliance
Well start up procedure
Endorsed well handover document
CONFIDENTIAL
Page
Page ‹#›
15
A Lifecycle Approach to the HSEIA Process
The Benefits
• The HSEIA approach provides tangible performance enhancement benefits in the
following ways:
• A greater focus on MAHs and HSECES integrity thus significantly reducing the
overall risk picture;
• Greater flexibility for managing HSEIA process associated with multipackage/multi-rig operations thus providing optimum efficiency
• Minimizing overall lifecycle costs through procurement of HSECES against
approved performance standards i.e., QA/QC of HSECES from day one
• Reduction of turnaround in ADNOC/SPC approval process i.e., SGD Program
HSEIA Phase II approvals have been achieved approximately 14 days from
submittal
• The approach is fully integrated with ADNOC & COMPANY HSEMS
• The iterative and evergreen nature of the approach provides the opportunity for
continuous improvement
Abu Dhabi Gas Development Company Ltd.
CONFIDENTIAL
Page
Page ‹#›
16