ARIBA IMPLEMENTATION IN MED-X Case Team 2: Yusuf Akkoca Tom Bloom Karen Delton Shweta Hire Eric Johnson David Mahzonni Greg Roy Which of the two components are underperforming according to the plan? How do you know this? • Technical Infrastructure is both behind schedule and over budget as indicated by the SPI (94.4%), Control Ratio (< .9) and CPI (91.7%) Schedule Over/Under Estimated Project Duration 184 184*.974 = 11 Days 195 Days Over Budget Under Performing Are the components of the project within budget? How do you know? • Software is within budget, technical is over budget by $85,410 based on EAC. software customization BAC $948,000 EAC $797,819.45 VAC $150,180.55 technical infrastructure BAC $948,000 EAC $1,033,410.50 VAC -$85,410.50 What can you conclude by looking at the combined earned value data for the project? • The projects when combined appear on track to be completed $64k under budget and 6 days early • Viewing as a consolidate projected can distort the true picture. Using this view Terry Baker would easily been led to believe the projects were on budget and on time. What should Martin have done earlier in the project timeline to prevent delays? • Reporting Earned Value and reviewing critical path project tasks independently of the project as a whole, Martin would have visibility to these problems earlier. • With earlier visibility shifting resources from Software to Technical Infrastructure may have been possible. What should Martin do when managing future projects to prevent similar problems from developing? • Tighter monitoring and control of project • Enhanced communication plan • Dedicated Staff (full review of any resource constraints and changes) • Order Hardware Earlier • Begin testing Earlier • Setup system access security up front Thank you! Team 2: Yusuf Akkoca Tom Bloom Karen Delton Shweta Hire Eric Johnson David Mahzonni Greg Roy