LCLS-II Status

advertisement

LCLS-II Status

LCLS-II Scientific Opportunities Workshops

David Schultz

9-12 February 2015

LCLS-II Concept

Use 1 st km of SLAC linac tunnel for CW SCRF linac

LCLS-II Scientific Opportunities

2

LCLS-II Project Scope

Accelerator

Undulators in existing

LCLS-I Tunnel

Superconducting linac : 4 GeV

New variable gap (north)

New variable gap (south), replaces existing fixed-gap und.

Instruments Re-purpose existing instruments (instrument and detector upgrades needed to fully exploit)

4 GeV SC Linac

In sectors 0-10

North side source:

0.2-1.2 keV ( ≥ 100kHz)

NEH

South side source:

1.0 25 keV (120 Hz, copper” linac )

1.0 - 5 keV ( ≥ 100 kHz, SC Linac)

FEH

LCLS-II Scientific Opportunities

3

Project Collaboration

LCLS-II Scientific Opportunities

• Cryomodule engineering/design

• Cryomodules: ~1/2 of total

• Liquid helium distribution system

• Cryomodules: ~1/2 of total

• Cryoplant design and procurement

• Undulators

• e gun & associated injector systems

• Undulator Vacuum Chamber

• Undulator design: vertical polarization

• Cryomodule R&D, prototype support

• e gun option

4

LCLS-II Cryomodules

35 Cryomodules, 12.6 m long, 1 m diameter

• LCLS-II Cryomodule follows the ILC design (shown)

• 8 SC cavities and a SC quadrupole magnet

LCLS-II Scientific Opportunities

5

Baseline Deliverables

Cu Linac

SC Linac

High Rep Rate

0

Legend

Cu SASE

Cu Self Seeded

High Rep Rate SASE

Self Seeded (Grating)

5

4.0 GeV

10 15

Photon Energy (keV)

20

 Hard X-Ray Source:

 1-5 keV w/ 4 GeV SC linac

 Up to 25 keV with LCLS Cu Linac

 Soft X-Ray Source:

 250 eV-1.2 keV w/ 4 GeV linac

 200 eV requires <4 GeV

25

LCLS-II Scientific Opportunities

6

Project Timeline

• BESAC subcommittee report

• LCLS-II starts a response to the report

• Mission Need Statement signed

• Approval, CD-1

• Purchase niobium materials for cavities

• 4.2K refrigeration plant award

• Prototype accelerating modules test

• Remove copper linac, first km

• All cryomodules at SLAC

• Cryoplant installed

• First Light

• DOE Critical Decision 4 (Level 1)

LCLS-II Scientific Opportunities

July 2013

July 2013

Sep 2013

Jun 2014

Oct 2014

Apr 2015

Dec 2015

Jun 2016

Sep 2018

Dec 2018

Jan 2020

Sep 2021

7

The LCLS-II Project: an extraordinary confluence of

• Institutional core competencies across the collaboration

• Talented, experienced scientists and engineers

• Strong management support at SLAC and the Partner Labs

• Outstanding support from DOE

LCLS-II Scientific Opportunities

8

In Closing

• LCLS-II goals have been changed radically by the reconfiguration of the project

• High average brightness

The change had to come now- or else beyond 2030

• DOE has made a commitment to the long-term future of

SLAC as the home of the nation’s large-scale FEL research facility

• I believe that DOE understands

The scope of LCLS-II and its performance capabilities

• What LCLS ought to be in the long term

• Your input will determine the future capabilities of LCLS-II

LCLS-II Scientific Opportunities

9

Download