Tullamarine Rehabilitated Landfill > 26 February 2014 Tullamarine Landfill Rehabilitation Landfill Update > Light Non Aqueous Phase Liquid (LNAPL) Trial Progress > Flare Installation Progress > Buffer Land Environmental Audit Completed > 2014 Groundwater Review Commencing 2 LNAPL Trial Commencing Early 2014 Reminder of Stage 1 Testing > Wells tested by removing 100 to 200 litres of LNAPL > Recovery (recharge) in each well measured over a period of approximately 4 weeks > Results reported back to Tullamarine Community May 2014 > LNAPL destruction LNAPL Distribution Prepared by URS, 2013 4 LNAPL Stage 1 Testing Sealed Area Enclosed Well Head Assembly Vapour Flared Tank (1 m3) Cap GACs 2x Leachate Well Leachate Well Perforations LNAPL LNAPL thicker in well Leachate Pump (intake positioned in LNAPL) LNAPL Trial (Completed Tasks) Waste Disposal Approval from EPA Independent Panel Review Engaged Remediation Contractor [EHS Support] Design Review by EHS Support 2 Planning Days with Contractors Well head works to allow connections Well Integrity Testing Commenced Procurement & Fabrication Commenced LNAPL Trial (Upcoming Tasks) > Factory Testing & Commissioning (2 weeks) > Connect Equipment to the Wells and Run through Protocols and Procedures (Mar) > Test Run LNAPL Transfer to a Double Skinned Sealed and Secure Tank (Mar) LNAPL Trial (Upcoming Tasks) > > > > Well Testing & Field Monitoring (Commences 24th Mar) Data Analysis & Reporting (Apr 2014) LNAPL Destruction at Laverton Facility On track to report the results at next meeting May 2014 Environmental Control Vapour / landfill gas > Sealed well heads during extraction; > System connected to landfill gas system and GAC vessels, 2 in series. Spillage control > Double walled LNAPL collection/storage tanks; > Sealed work area around well head; > Secondary contained transfer hosing; Environmental Control Noise > Operations during business hours so no change to current noise profile. Monitoring: > Portable Landfill Gas and Trace Gas monitors > Samples of LNAPL, leachate & vapour obtained & analysed by laboratories Environmental Control - Details > Robust Health, Safety and Environment Plan > Key HSEP monitoring equipment for all work includes : 1. 2. 3. 4. 5. Photo Ionisation Detector (PID), Lower Explosive Limit Detector (LEL), Landfill Gas Meter (LGM), Flame Ionisation Detector (FID) & Fuel/oil spill kit placed within work zone. Environmental Control - Details > Daily Set Up & Pre Start Protocols 1. 2. 3. 4. 5. 6. 7. Daily toolbox meeting at start of day, Check, inspect and test equipment using probes Check all lines Tank placed onto bunded area Bunding & spill mat installed Connect vacuum lines and GAC drum lines to the tank Monitor vacuum in lines. Environmental Control - Details > Monitoring 1. 2. 3. 4. 5. Continuous monitoring of vapours in the work area. Trigger thresholds based on unprotected worker exposure. PPE includes face shields & respirators. Response to trigger = monitor, locate & isolate source, shut down. Workers protected = Community protected. Independent Review Panel > Purpose : 1. Verify field work was completed according to plan 2. Review the data 3. Assist with decision making during the trial 4. Review the LNAPL Trial report prepared by EHS Support 5. Provide a statement to the EPA on the trial report LNAPL Trial Summary > Field trials planning and equipment build is completed and field works are commencing with first well test planned mid March > The results will be reported to the community in May 2014 > The project includes LNAPL destruction trials Enclosed Flare Proposal Design Report Complete Flare Emissions Model Complete Design signed off by Auditor 15 January > On track for flare installation Flare Outline Design Environmental Audit Four Studies completed by Golder and Kleinfelder. Soil (Golder, 2012a & Kleinfelder, 2013) Vapour (Golder, 2012b & Kleinfelder, 2013) Groundwater (Kleinfelder, 2013) Landfill Gas (Kleinfelder, 2013) Auditor review & statement completed and issued 17th Feb. Environmental Audit Statement allows commercial landuse Two conditions -Groundwater sample locations must be accessible -Groundwater restricted use zone Environmental Audit Questions -Audit report to be uploaded to Transpacific’s community website www.transpacific.com.au/tullamarine - TPI has arranged for the Engineer (Kleinfelder) & Auditor to present to the community: 12 March at Mantra Hotel, 7pm 2014 Technical Review (Commencing) > Involves review of all surface water and groundwater data collected since last review (mid 2011) > Golder prepared the 2011 review & Auditor completed his report July 2012 > Kleinfelder will be preparing the 2014 review > Objective (i) to compare monitoring against management plan requirements and (ii) to determine if the current monitoring arrangements adequate Prepared by Golder, 2012 Disclaimer This document has been prepared by Transpacific Industries Pty Ltd (ABN 40 010 745 383) (“Transpacific”) for the purposes of providing the recipient with an update on the status of rehabilitation works at Tullamarine landfill site. This document has been prepared on the condition that it is for the exclusive information and use of the recipient. This document may not be reproduced, distributed or published by any person for any purpose. No part of this document may be quoted or referred to in any other document. With the exception of information provided by external sources, Transpacific retains all applicable intellectual property rights which arise from the creation of this document. This document is subject to the limitations, assumptions and qualifications referred to in it. In addition to any other rights available to them, Transpacific or any related party (“Transpacific Parties”) herein expressly advise that they: 1. make no representation or warranty, express or implied, as to the accuracy, currency, reliability or completeness of any statements, estimates, opinions or other information contained in this document; and 2. to the maximum extent permitted at law, the Transpacific Parties are not responsible or liable in any way whatsoever for any claim, loss, damage, cost or expense, whether direct, indirect, consequential or otherwise, arising (whether in negligence or otherwise) out of use or reliance on this document, its contents or any omissions from it. Transpacific Parties means Transpacific, its related bodies corporate, directors, officers, employees, representatives, consultants and agents; and a Transpacific Party means any of them. Thank you for your time