Baltic NPP Project Specifics and Current Status 2 June 2011 By courtesy of SC Rosatom Baltic NPP Project Project Overview 2 x 1194 MW Units (AES-2006 series) Location in Kaliningrad region of the Russian Federation Operation dates Unit 1 – Oct 2016 Unit 2 – Apr 2018 Site preparatory works ongoing Unique Project First NPP project in the Russian Federation providing opportunity for participation of foreign investors Foreign investors may acquire up to 49% share Cross-border transmission lines developed under separate project with participation of foreign investors Baltic NPP Project Major Stakeholders and Participants State Corporation “Rosatom” – PRINCIPAL OJSC “Concern Rosenergoatom” – DEVELOPER OJSC “SPbAEP” – GENERAL DESIGNER OJSC “Inter RAO UES” – ORGANIZATION OF FINANCING AND ENERGY SALES WorleyParsons – TECHNICAL CONSULTANT Societe Generale – INVESTMENT CONSULTANT Norton Rose – LEGAL CONSULTANT Baltic NPP Project Consultant’s Roles Acting as the Agent of OJSC “Concern Rosenergoatom”, OJSC “Inter RAO UES” have assigned professional consultants for the development of Bankable Feasibility Study Technical Consultant – WorleyParsons Analysis of Baltic NPP technical aspects Analysis of Baltic NPP design compliance to IAEA and EUR requirements CAPEX, OPEX, Basic Financial Model Power Output Scheme Investment Consultant - Societe Generale DCF model preparation Financing sources and structure development Marketing activities Due diligence Legal Consultant - Norton Rose Analysis of the current legal status of the project Integrated legal assessment of the project Risks identification and mitigation strategy development Baltic NPP Project Current Status The project has started in 2008 when a cooperation agreement was signed between State Corporation “Rosatom” and the local government of the Kaliningrad region A site permit for the project was issued in February 2010 At present site preparatory works are ongoing The design documentation have been developed, and a positive opinion of state review body (Glavgosexpertiza) was obtained on 30 Mar 2011 Application for construction license for Unit 1 was submitted Bankable Feasibility Study is under development Baltic NPP Project Current Main Activities on Site Construction and rehabilitation of auto roads Construction of concrete batch plant Construction of reinforcing factory Construction of water intake facilities Construction of temporary electricity supply networks Development of the pit of the main building (soil removal and management, vertical leveling) Arrangement of drainage systems, concrete basement and waterproofing Construction of housing for the construction workforce Baltic NPP Project Project Implementation Schedule Commissioning Unit 1 Construction Unit 1 Commissioning Unit 2 Construction Unit 2 Design and construction of Power Output Scheme Facilities Bankable Feasibility Study Negotiation and Execution of Agreements with Investors Power Purchase Agreements (PPA) Trade Negotiations 2010 7 2011 2012 2013 2014 2015 2016 2017 2018 Baltic NPP Project Negotiations with Potential Investors’ Schedule Sending a teaser Preliminary negotiations with potential investors and conclusion of confidentiality agreements BFS submission Receiving first signs of the potential investors’ interest Potential investors’ shortlist preparation Data room opening and conducting due diligence Management presentations and negotiations Selection of investors for final negotiations May 2011 8 Jun 2011 Jul 2011 Aug 2011 Sep 2011 Oct 2011 Nov 2011 Dec 2011 Baltic NPP Project Strategy of Project Implementation Project Organization Structure during Preparation Phase According to the Russian legislation and other statutory documents, the process of NPP construction is divided into two main phases: preparation phase and construction phase The Operating organization “Concern Rosenergoatom” has established a structural subdivision to perform the functions of Owner/Developer – a branch of «Concern Rosenergoatom», Baltic NPP Construction Directorate. State Customer SC “Rosatom” Owner-Developer OJSC “Concern Rosenergoatom” General Designer “SPBAEP” JSC Preliminary Works Contractor OJSC “Northern Construction Management” Baltic NPP Project Strategy of Project Implementation In order to attract foreign investments, “Concern Rosenergoatom” is the founder and sole shareholder (at present) of OJSC “Baltic NPP” Planned Organization Structure during construction and commissioning phase Owner/Developer OJSC”Baltic NPP” (Joint stock company with participation of foreign capital) A principle decision was made on the readiness to give the foreign investors a stake in the plant up to 49% OJSC “Baltic NPP” shall be Owner/Developer during the construction and commissioning phase General Contractor (selected by tender) General Designer Equipment suppliers Construction & Installation Contractors Start-up & Commissioning Contractors Baltic NPP Project Technical Consultant Feasibility Study Objectives and Content Support the development of BFS substantiating the Project feasibility for potential investors and financial institutions Present Baltic NPP Project Independent analysis for compliance with Technical aspects and solutions Socio-economical aspects Environmental aspects Organization and implementation strategy Financial and economical aspects Grid infrastructure Russian standards and regulations IAEA Safety Standards EUR, Part II requirements Financial and economic evaluation Risks Identification Development of possible power output schemes Baltic NPP Project Feasibility Study Phase 1 Outcomes Baltic NPP Feasibility Study Phase I Technological Process Baltic NPP consists of two reactor units in an AES-2006 standard design configuration, intended to operate under base operational conditions with ICUF above 90% and under transient operation conditions NPP reactor unit has a two-circuit design: The primary circuit is radioactive entailed by Reactor Coolant Piping System. This circuit includes pressurized water reactor of VVER-1200 type, four main circulation loops, one pressurizer, safety systems and primary-related auxiliary systems Secondary circuit is non-radioactive. It entails steam generating portion of SG, steam pipework, steam turbine, condenser units, main condensate system with condensate pumps and low pressure heaters, deaerator, feedwater system with electric feedwater pumps and feedwater high pressure heaters. Turbine condensers are cooled down by circulating water system with heat discharged through wet cooling towers into atmosphere Baltic NPP Feasibility Study Phase I AES-2006 Sectional View Baltic NPP Feasibility Study Phase I Reactor Plant – General Layout Baltic NPP Feasibility Study Phase I High Safety and Performance Indicators COMPARATIVE TABLE OF MAIN TECHNICAL CHARACTERISTICS OF WWER/PWR NUCLEAR TECHNOLOGIES AS-91 (В-428) Tianwan AS-92 Kudankulam AES-2006 BaNPP AP1000 Westinghouse 3000 3000 3200 3415 1060 / 995 1060 / 995 1181 / 1096.5 1154 / 1117 Specific Efficiency Coefficient, net, % 33.5 33.5 34.2 32.7 Availability factor, % ≥90 ≥90.4 92 93 ≤ 10 -6 per year ≤ 10 -6 per year ≤ 10 -6 per year ≤ 10 -7 per year ≤ 10 -7 per year ≤ 10 -7 per year Characteristic Thermal power, MWth Electrical power, gross/net, MWe Probability indices of: 1) cumulative frequency of core damage 2) frequency of limiting emergency release 16 ≤ 5·10 -7 per year ≤ 6·10 -8 per year Baltic NPP Feasibility Study Phase I New Safety Features for DBA and BDBA Active and passive safety systems for prevention and mitigation of Design Basis Accidents and Beyond Design Basis Accidents. A four channels safety systems design is incorporated into the plant design: The active component-based four channel’s safety system design provides the ability to respond to any DBAs scenario and provides a safe status of the reactor plant Design allows a single safety channel to be out of service for maintenance or any other reasons for unlimited period of time during Unit operation. The systems to mitigate BDBAs are designed for long-term heat removal from the containment during beyond design-basis accidents (off-line mode is at least 24 hours without operator’s actions) 17 Baltic NPP Feasibility Study Phase I Protection Against External Impacts Seismic loads NPP is developed with stability to earthquake Aircraft Protection from the fall of an aircraft Wind loads Whirlwind and tornado protection Snow and ice load Extreme snow and ice protection External explosion NPP components responsible for the safety are developed with ensuring the security of percussion coursed by the external explosion. Baltic NPP Feasibility Study Phase I Environmental Impact Assessment The Environmental Impact Assessment (EIA) was developed in 2009 There have been public hearings of EIA report – passed successfully Results and Conclusions Presence of high anthropogenic pressure on the region The hydrological regime of the rivers and lakes in the region will not undergo any changes Non-radioactive releases to the surface waters with concentrations, exceeding the permissible for fishing basins, are prevented by technical solutions Electromagnetic radiation, noise and harmful releases from the NPP facilities are in the range of permissible values and have insignificant off-site impact Non-radioactive industrial and domestic waste will be treated and landfill disposed The liquid radioactive waste are subject of conditioning (solidification). The amount of waste is minimized by the design During normal operation of Baltic NPP the airborne radioactive and chemical releases will have an insignificant impact on the atmospheric air, public and environment. The radiological impact on the public and environment for design basis accidents does not exceed the defined exposure doses for the public and is mitigated during BDBAs The risk of Baltic NPP operation is estimated to be significantly lower than the existing anthropogenic background Baltic NPP Feasibility Study Phase I Analysis of the NPP Design Compliance to the Russian Standards and Regulations All necessary reviews have been performed in accordance with the Russian Legislation Comparative Analysis of Russian Standards and Regulations to IAEA Safety Standards The analysis results indicate that the Russian rules and norms contain appropriate requirements. The observed differences are due mainly to the formulation and terminology being in use Russian documents are significantly more specific than IAEA safety standards, which have mainly conceptual character Analysis of the design against EUR, Part II requirements A preliminary conclusion is that the Design in general will to a great extent comply with the EUR requirements, based on the following: The main target indicators for safety, reliability and efficiency are directly incorporated in the design This is an evolutionary design utilizing the same conceptual approaches, practices and design standards as in the EUR certificated AS-92 design The expected differences will be related to those EUR requirements which differ from the Russian rules and standards Baltic NPP Feasibility Study Phase I Analysis of the NPP Design Spent Fuel Management Strategy Basis Initial storing for a few years in the spent fuel pool; Further transportation out of Kaliningrad Region without using the territory of other states Radioactive Releases and Waste Management Strategy Basis Radioactive releases into the atmosphere - annual effective dose for the public less than 0.01 mSv for Normal Operation (NO) Liquid Radioactive releases – activity of liquid releases is lower than the drinking water intervention level; annual effective dose for the public far bellow 0.01 mSv for NO Liquid Radioactive waste – solidification; Solid waste – Conditioning The RAW storage capacity is calculated for 10 years of operation; Further transportation out of Kaliningrad Region without using the territory of other states Emergency Planning Management Strategy Basis In case of severe accident the radiation impact does not exceed the intervention levels for the population in a distance more than 3 km from the NPP. That is why emergency planning is envisaged only for the NPP personnel Baltic NPP Feasibility Study Phase I Project Implementation – Contractual Approach Contractual approach and possible NPP construction schemes Standard Form of Contract of OJSC "Concern Rosenergoatom" for construction of NPP units is the basis for development of Feasibility Study Phase I Comparative analysis The Standard Form of Contract of OJSC "Concern Rosenergoatom" has been compared with the following internationally recognized contractual approaches: • EPC Lump Sum Turn Key with firm and fixed price • EPC Lump Sum Turn Key with fixed price (subject to escalation) • Split Package (Island) Approach • Multiple Package Approach Comparative Analysis Results Generally, the Standard Form of Contract of OJSC "Concern Rosenergoatom" is comparable with the EPC Lump Sum Turn Key with fixed price (subject to escalation) contractual approach, with some differences, conditioned by the Russian legislation and the established NPP construction practice Baltic NPP Feasibility Study Phase I Project Key Milestones Achieved Milestones “Declaration of Intent” to Invest in the Construction of Power Units 1 & 2 of the Baltic NPP – approved by State Corporation “Rosatom” on 11-Sep-2008; The enactment of the Kaliningrad Region Duma about approval of the “Declaration of Intent to Invest in the construction of NPP 1&2 of the Baltic NPP” on 28-Oct-2008; “AES-2006. Justification of investments in the construction of Baltic NPP”. Prepared by OJSC “SPbAEP” - approved by the Customer (OJSC “Rosenergoatom”) on 14-Dec-2009; The Order No.169-r of the Russian Federation Government of 20-Feb-2010 about location of the Baltic nuclear power plant on the territory of the Neman municipal district of the Kaliningrad region; Development of Design Documentation ongoing. Unit 1 Technical Design Package obtained positive State Examination conclusion on 31-March-2011; Planned Milestones Unit 1 First Concrete (Reactor Building) – 30-Oct-2011; Unit 2 First Concrete (Reactor Building) – 30-Oct-2013; Unit 1 Commercial Operation – Y 2016; Unit 2 Commercial Operation – Y 2018; 23 Baltic NPP Feasibility Study Phase I Power Output Kaliningrad Region Power Sector Diagram of Baltic NPP connection to the network after second unit commissioning Клайпеда Битенай Юрбаркас # Title Voltage/kV/ Length /km/ Crosssection /mm2/ 1 BaNPP-Sovetsk 330 18 2×600 2 BaNPP-Bitenai 330 19 2×300 3 BaNPP-Sovetsk 330 77 2×600 4 BaNPP-Kruoni 330 160 2×300 5 BaNPP-Sovetsk 330 34 2×600 6 BaNPP-PS PT Mamonovo 330 190 2×600 7 BaNPPYurbakas 330 40 2×600 8 BaNPP-Central О-1 330 135 2×600 Круонио ГАЭС Советск-330 Северная-330 Калининградская ГРЭС-2 Балтийская АЭС 2 блока Центральная О-1 Мамоново Baltic NPP Feasibility Study Phase I Power Output Internal Forecasted Demand and Export Potential After the launch of Unit 1 in 2016 and Unit 2 in 2018, a substantial export capacity will arise The excess capacity after meeting initial demand in Kaliningrad Region can be exported to the energy deficit countries of the Baltic Region. Internal Demand & Export Potential 3500 Year 3000 MW 2500 2000 1500 1000 500 0 2011 2017 2020 Year Available Capacity (MW) Optimistic Internal Demand (MW) Minimum Export Potential (MW) 2011 2017 2020 Available Capacity (MW) 950 2050 3280 Optimistic Internal Demand (MW) 660 1000 1400 Minimum Export Potential (MW) 200 1050 1880 Baltic NPP Feasibility Study Phase I Power Output Baltic Region Energy Balance The energy analyses shows a negative balance for the Baltic countries. Baltic NPP Feasibility Study Phase I Financial and Economic Evaluation Capital Cost Estimate Basis of the capital cost estimate Capital Cost Estimate developed by the General Designer (Chapter 11 of TD) • Developed on the basis of Methodology for determination of the cost of construction production in Russian Federation (МДС 81-35.2004) • Reference plant – Leningrad NPP 2 2 x 1194 MW Units Base date 4th Total Installed Costs Quarter of 2010 Currency – Euro Unit 1 COD – 30 October 2016 Base Costs Supplementar y Costs Unit 2 COD – 30 April 2018 Exchange Rate – 40 Russian Ruble / 1 Euro Expected accuracy – ±25% Breakdown as per IAEA accounting system 27 Direct Costs Indirect Costs Owner’s Costs Financial Costs Baltic NPP Feasibility Study Phase I Financial and Economic Evaluation Capital Cost Estimate General Approach to Capital Cost Estimate Analysis of the estimate developed by the General Designer Communications with the Client to clarify unclear items Verification of buildings, structures, systems, etc. against the General Plant Layout (phase B, sheet 2/2) Identify capital costs that are not included in the General Designer estimate on the basis of proprietary check list Add the costs excluded from the General Designer estimate on the basis of in-house database, after appropriate adjustment to reflect the project time, location and specifics for Kaliningrad region Cost distribution by IAEA major account codes Develop Cost Risk Analysis and capital costs possible ranges were identified Contingency Analysis based on the Cost Risk Analysis 28 Develop cash flows on the basis of the project implementation schedule and the standard EPC Contract payment conditions Baltic NPP Feasibility Study Phase I Financial and Economic Evaluation Capital Cost Estimate Analysis of the estimate developed by the General Designer Factoring approach utilized at this stage (Technical Design) of the project Estimating is iterative process – per project phases General Designer experience indicates that increase of the capital costs is expected for the next iteration of the estimate (Detail Design phase of the project) Contingency allowance of approx. 3% is applied on the base estimate on the basis of the adopted methodology (МДС 81-35.2004) The international practice for contingency allowance at this phase of projects and level of project definition recommends over 10% (AACE International) 29 The following costs are not included in the General Designer estimate • First fills and special materials • Utilities during construction (water, electricity, etc.) • First core fuel • Operating personnel (during construction) • Licenses (nuclear regulator) • Escalation • Financial costs Baltic NPP Feasibility Study Phase I Financial and Economic Evaluation Capital Cost Estimate / Results In 90% of the cases the construction of Baltic NPP will require capital costs in the range from € 6.63 Billion to € 8.15 Billion 30 Baltic NPP Feasibility Study Phase I Financial and Economic Evaluation Operating Costs O&M Cost Methodology: O&M costs are determined applying the IAEA accounting system and are presented as personnel and non-personnel expenses Basis for the estimation is client’s data from Balakovo NPP Adjustments of the basic costs were made to reflect the specific conditions of the Baltic NPP Contributions to 3 funds (Decommissioning, Nuclear Safety & Physical protection) have been added to the O&M costs Decommissioning costs Based on the current Rosenergoatom rules (1.3% of revenue); Calculated as annual payments in the Decommissioning fund Fuel costs Fresh fuel costs are estimated based on the prices on the international market Spent fuel costs are based on Balakovo NPP data Baltic NPP Feasibility Study Phase I Financial and Economic Evaluation Operating Costs / Risk Analysis O&M cost risk Reason Range of Consequences Likelihood Ability to influence Fuel costs. International market of energy resources Price of natural uranium could increase, following price increase of other energy resources Low High Low O&M costs for personnel Personnel costs might increase following the inflation processes and approximation of salaries in Russia to EU levels Low High Low O&M costs for repair and maintenance O&M costs for repair and maintenance could be higher than predicted Low Low Low O&M costs for nuclear liability insurance Nuclear liability insurance might become more expensive due to either increased limits or increased premiums Very Low Mid Low CONCLUSIONS • Increase of O&M costs will be mainly due to the inflation and escalation processes. • Risk analysis demonstrates that the risk of O&M and fuel costs increase is low, with low expected impact on LCOE. • There is no significant risk for the plant in terms of operation costs, if it is managed safely and reliably. Baltic NPP Feasibility Study Phase I Financial and Economic Evaluation Basic Financial Model / Technical Inputs Gross Power 1194 MW Nominal Power 1181 MW Net Power 1097 MW Average Availability 92% Lifetime 50 years Construction schedule Unit 1 – commissioning on the 30th October 2016 Unit 2 – commissioning on the 30th April 2018 Baltic NPP Feasibility Study Phase I Financial and Economic Evaluation Basic Financial Model / Major Assumptions Ownership structure 51% Rosenergoatom 49% Strategic Investor Financing structure Base Case – 100% equity (balance sheet financing) Second option – 50% equity & 50% debt financing Discount rate – 6% Electricity sales Russia – 300 MW Baltic region (Lithuania) – 1000 MW Germany and Poland – 1000 MW Electricity Tariff in target markets Presented by the Client Baltic NPP Feasibility Study Phase I Financial and Economic Evaluation Conclusions CAPEX is within international publicly announced price levels At the selected set of assumptions, the project is financially feasible in all scenarios Thank you