city council presentation

advertisement
Pasadena Water and Power
GLENARM POWER PLANT
REPOWERING PROJECT WORKSHOP
Pasadena City Council
February 4, 2013
Item 13
Glenarm Repowering Project
Pasadena Water and Power
• Build a new combined cycle electric generation unit (68 MW net, 71 MW gross)
• Decommission existing B3 electric generation unit (65 MW net, 71 MW gross)
• Close State Street cul-de-sac off of Fair Oaks Avenue
• Construct control room, instrument shop and offices
• Modify existing Pump Building as Maintenance shop
2
Aerial View of Power Plant
Pasadena Water and Power
B3
Gold Line
Glenarm Bldg.
New
Plant
State
St.
3
Pump
Bldg.
Why Repower ?
Pasadena Water and Power
City’s Electrical System Must Stay Reliable
• Need dependable local generation to back up single energy import location
• B3 can’t be depended on for too long …47 years old, spare parts problems
• Other alternatives (i.e. another import connection) not feasible
• Reduced operations cost
• New efficient unit is necessary to reduce dependence on coal
• Flexible generation with quick start enables wind and solar power integration
• Approximately same cost over 20 years to maintain B3 vs. new unit
The City Council approved 2009 Energy IRP on 3/16/2009
•
Replace existing B3 unit with equivalent size combined cycle unit by 2015
4
Project Phases and Timeline
Pasadena Water and Power
Description
Consultants
• Selection of technology, configuration,
preliminary engineering, specifications, etc.
Power Engineers
• CEQA/EIR
PCR
Hearing by Planning Commission … 3/13/13
City Council consideration … 4/8/13
• Air permits for General Electric and Rolls Royce
Worley Parsons
Application submitted …6/12; permit expected 5/13
• Environmental & geotechnical site assessment
• Others for chemical risk management, noise
study, asbestos/lead assessment, etc.
5
Hydrolouge, Inc.
Project Phases and Timeline
Pasadena Water and Power
• Bid Specifications for major equipment i.e. gas
turbine, once through steam generator, steam
turbine and generator (Power Island)
Issued 6/2012
Contract by 7/2013
$ 45million approx.
• Bid specification for final design, rest of the
equipment and construction (Balance of Plant)
Contract by 2/2014
$ 51million approx.
• Design and construction of control room, etc.
Contract by 2/2014
• Request for proposal for Project Manager and
Construction Manager
Contract by 9/2013
These contracts would need the City Council approval
6
Visual Simulations
Pasadena Water and Power – Repowering Project
Looking West From Broadway Plant (Existing)
7
Visual Simulations (Cont.)
Pasadena Water and Power – Repowering Project
Looking West From Broadway Plant…General Electric LM6000 Option
8
Visual Simulations (Cont.)
Pasadena Water and Power – Repowering Project
Looking West From Broadway Plant (Rolls Royce Trent Option)
9
CEQA / EIR- Major Focus Areas
Pasadena Water and Power
• Significantly high greenhouse gas emissions
 CEQA compares emissions from new unit operating entire year at full capacity with
B3’s actual recent operation i.e. 4% of full capacity
 On MWh basis new unit emits ≈30% less
•
•
•
•
•
Exemption for height of structures…125 ft. stack
Cultural Resources – Historical resources (Glenarm Building)
Land Use and Planning – Consistency with South Fair Oaks Specific Plan
Noise – Noise Element of General Plan & Noise Ordinance
Project Labor Agreement…. Discussion with CURE underway, emphasis on local
hiring and apprenticeship
Substantial comments received on draft EIR
10
Project Management and Oversight
Pasadena Water and Power
PWP – GM
PWP – AGM OFFICE
POWER SUPPLY
POWER PLANT
SUPERINTENDENT
REPOWERING PM
TBD
OWNER’S ENGR.
POWER
POWER PLANT
ENGINEERING
OTHER PWP DEPT.
OTHER AGENCIES
CONST. MGR.
TBD
BOP/construction
CONTRACTOR
TBD
Power Island
CONTRACTOR
TBD
Note : Project Manager and Construction Manager may be from the same firm and/or hired under the same contract.
Staff to determine best value arrangement for the project following review of proposals for PM/CM services.
11
Potential Financing Alternatives
Pasadena Water and Power
Funding Sources
Power Fund
Bond Proceeds
100% Revenue Bonds
$0
$115 million
15% Equity Financing
$17 million
$98 million
Financing Impacts*
100% Financing
85% Financing
Annual Debt Service
$8 million
$7 million
Impact per kilowatt hour (kWh)
$0.0071
$0.0063
Monthly bill impact (500 kWh)
$3.55
$3.15
Sources of Equity Financing:
• $15 million to $20 million from Power Fund (working capital)
*All impacts estimated, actual debt service and kWh impact may vary
12
Next Steps and Issues
Pasadena Water and Power
Next Steps
•
•
•
•
•
•
EIR approval
Air Permit (contingent upon EIR approval)
Financing (Reimbursement resolution for City Council approval on 2/25/2013)
Contracts for major equipment, construction and Project/Construction Managers
Construction and Commissioning
Training for Power Plant staff
Major Issues
•
•
•
•
•
•
Air permit conditions and fee increase
EIR
Project Labor Agreement
Future plan for Broadway site and Glenarm building
Future plan for Gas Turbines 1 and 2
Some elements of project and milestones continue to change due to regulatory
and market information
13
Back Up Slides
Pasadena Water and Power
BACK UP SLIDES TO FOLLOW
Another View of Power Plant
Pasadena Water and Power
15
Primary Project Responsibilities
Pasadena Water and Power
• Repowering Project
Manager
• Repowering Construction
Manager
> Overall project responsibility
> Reports to PWP AGM
> Responsible for high-level
decision making and
integration and execution of
project controls
> Full time role, Attends PWP
and City management
meetings, provides status
updates as needed
> On-site management of
construction contract
> Reports to Project Manager and
Owner’s Engineer
> Responsible for: site meetings,
document control, inspections,
const. schedule, billings, change
management
> Coordinates between equipment
supplier and BOP contractor
16
Contracting Strategy
Pasadena Water and Power
• Contract directly for Power Island (15 Major Equipment)
≈ $45M
• BOP Contract for detail design & installation of Power Island ≈ $51M
• Contract design & construction of control room/offices
17
≈ $12M
Project Cash Flow
Pasadena Water and Power
Project Total : $115.4M
FY 2013: $1.2M
FY 2014: $44.7M
FY 2015: $46.2M
FY 2016: $23.3M
18
Project Key Dates/Milestones
Pasadena Water and Power
Environmental Impact Report…
•
•
•
•
•
Issued NOP-------Issued Draft EIR-------Public Meeting Held on Draft EIR---PC Hearing for Draft Final EIR--Council Certification of EIR---
10/6/11
11/5/12
12/12/12
3/13/13
4/8/13
Air Permit (SCAQMD/EPA)…
•
4/8/13
5/13/13
Submitted applications for GE and RR---6/6/12
Power Island Contract (gas turbine, steam and electric generators)…
Balance of Plant Construction Contract…
Glenarm Building Contract…
Demo/Construction Start
Commercial Operation…
19
7/23/13
2/28/14
2/28/14
3/3/14
8/10/15
Estimated Impact of 100% Bond Financing
Pasadena Water and Power
•
•
•
•
$100 million of tax exempt revenue bonds
Estimated pricing date June 1, 2013
30 year, level debt service, estimated 4.0% true interest cost
Annual debt service approximately $7 million
$100 Million Tax-Exempt Financing
Aggregate Debt Service
$25
($Millions)
$20
$15
$10
$5
$0
Existing Debt Service
•
Series 2013
Impact of additional debt service may be reduced by offsetting revenues from ancillary
services, wholesale energy transactions and reduced operating expenses due to
increased efficiencies
20
Download