Captive Blocks : Major Bottlenecks – Land, Environment / Forest Clearances 4th Coal Summit 2012 BP Singh Director (Projects), NTPC Ltd. 29 MARCH 2010 19.11.2012 PRESENTATION OUTLINE Power & Coal Sector Scenario Mine Development – The Key Processes Major Issues / Bottlenecks in Mine Development : Land Acquisition, Forest & Environment Clearances Strategies For Dealing with Bottlenecks Power Sector Scenario INSTALLED CAPACITY • All India total generation capacity • Coal Based Generation capacity • Capacity addition achieved during XI Plan • Coal based Capacity addition 2,09,276 MW* 1,20,103 MW (about 57 %) 57,964 MW 48,540 MW (> 83%) PROJECTED CAPACTIY (Figs in GW)# • Terminal Year 2017 8% GDP Growth Rate 306 9% GDP Growth Rate 337 2027 575 685 2022 425 488 2032 778 960 As per Approach Paper for 12th Plan, capacity addition target is 88425 MW, out of which 71228 MW through Thermal, 11897 MW from Hydro & 5300 MW from Nuclear. Dependency on Coal will continue as the primary & most reliable source for power generation in India. *Figures as on 31.10.2012 (Source – CEA Report) # As per Integrated Energy Policy Capacity Addition & Coal Requirement 180000 159294 160000 Installed Capacity (MW) 140000 144389 165954 900 842 800 737 125414 120000 100000 165374 650 572 700 600 500 515 80000 400 60000 300 40000 200 20000 100 0 Coal Requiremnt (Million Tonnes) Capacity addition vis-a-vis coal requirement in 12th plan Installed Capacity (MW) Coal Requirment 0 2012-13 2013-14 2014-15 2015-16 2016-17 YEAR At the end of 12th plan, coal-based installed capacity of 165954 MW envisaged with coal requirement of 842 million tonnes. Coal Demand-Supply Scenario in the Power Sector (Fig in Million Tonnes) S.No Details a) Indigenous coal requirement b) Indigenous coal availability from : 2012-13 2016-17 455 842 i) CIL 347 415 ii) SCCL 35 35 25 100 402 550 iii) Captive mines c) Total availability of indigenous coal d) Shortfall in indigenous coal availability (a-c) 53 242 e) Requirement of imported coal to meet the shortfall in indigenous coal availability 46 168 f) Requirement of imported coal for imported coal based projects 24 40 g) Total requirement of imported coal (e+f) 55 208 More emphasis required on domestic coal production – Thrust on Captive Mines Source: CEA / MOP, GOI Raw Coal Production in India Very nominal increase in production since last 3 years (Almost Stagnant) Source: CIL/ MOC, GOI Captive Coal Block Allocation Govt. of India allocated coal blocks for Captive Mining since 1993 No. of Coal Blocks, allocated till date De-allocated till date 218 29 Bank Guarantee deducted Coal production commenced in about 30 blocks and peak production capacity reached only in 9. ‘Delay in development’ is the reason for de-allocation as cited by MOC. Coal block development schedule of MOC needs a re-look and be made REALISTIC. Source: MOC 5 Mine Development – Key Processes • Detailed exploration and preparation of GR • Mining Plan preparation and approval • Land Acquisition • Obtaining of Statutory Clearances • Infrastructure Development • OB Removal & Coal Production Stages in Development of Coal Mine STAGE - I STAGE - II PLANNING / FEASIBILITY OBTAINING CLEARANCES • Forest Clearance • Exploration / Preparation of Geological Report • Environment Clearance • Surface Master Plan • Conducting Studies - Hydrogeological studies - Socio Economic studies - Transport studies - Environmental studies • Mining Plan - Approval LAND ACQUISITION AND REHABILITATION & RESETTLEMENT OF PAP’s • • • • • Issuance of Notifications Calculation of Compensation Disbursement of Compensation Rehabilitation Action Plan Physical Possession of Land & Rehabilitation of PAP’s CREATION OF INFRASTRUCTURE • Rail Link • Coal Handling Plant • Approach Roads MINE DEVELOPMENT •Removal of OB •Coal Production • Land Requirement • Applications for Clearances STAGE - III APPOINTMENT OF MDO Exploration in India With Regional, Promotional and Detailed Exploration by GSI, CMPDI, SCCL etc., the estimation of coal resources of India reached to 285 Bt. Estimates of coal resources during last 6 years : in Million Tonnes Reserves as on Geological Resources of Coal Proved % Increase Indicated Inferred Total % Increase 1.4.2011 114001 3.8 137471 34389 285862 3.2 1.4.2010 109798 3.7 130654 36358 276810 3.5 1.4.2009 105820 3.9 123470 37920 267210 1.0 1.4.2008 101829 2.7 124216 38490 264535 2.7 1.4.2007 99060 3.3 120177 38144 257381 1.6 1.1.2006 95866 119769 37666 253301 Govt of India may put more thrust on enhancement of rate of exploration. Source: MOC, GOI Detailed Exploration • As per the guidelines for detailed exploration, boreholes to be drilled in 400 meters interval. • In case of detailed exploration in forest area, at present 20 nos. of boreholes allowed in 10 Sq. Km. area. • For meaningful Geological Report, at least about 8 nos. of boreholes per Sq. Km. area required. MOEF may allow drilling of 8-10 nos. of boreholes / Sq. Km. in forest area without requirement of forest permission. Local resistance during exploration - State support is of utmost importance. Main Bottlenecks in Captive Mine Development Huge time being taken in obtaining of - Forest Clearance - Environment Clearance Land Acquisition – problematic Lack of coal transportation infrastructure Forest Clearance – Long Process Forest Clearance – Cumbersome Process 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. Estimation of Land Requirement Application to Nodal Officer/PCCF/DFO for Forest Diversion Survey of forest area, Enumeration of trees and demarcation of Forest land NOC from Village Advisory Committee / Gram Samittee NOC on jungle-jhari land / Revenue forest by State Govt. NOC under FRA-2006 DGPS survey & its authentication by State Bodies like ORSAC (in Odisha) Processing of Forest proposal : DFO - CF - CCF/RCCF - PCCF - Secy (Forest) State Govt - MoEF, New Delhi Site Inspection by Regional office of MOEF – Submission of Report to MOEF, New Delhi Presentation to Forest Advisory Committee of MOEF by AIG (Forest) Approval of FAC recommendation by Hon’ble Minister of Env. & Forests Stage-I forest clearance by MoEF, Delhi Demand note from DFO for NPV of trees & Compensatory Afforestation - Payment by block allocatee, Identification of land for compensatory afforestation Submission of compliance report of Stage-I clearance to DFO - CF - CCF/RCCF - PCCF - Secy (Forest) State Govt - MoEF, New Delhi Processing of Stage-II proposal at MOEF – approval by IG / DG, Forests Stage-II clearance from MoEF Order by DFO/RCCF to start demarcation of forest land, Safety zone and CA areas Approval of State Forest Deptt. to start tree felling and transportation of tree logs MOC schedule stipulates 6 months to complete all these activities – Unrealistic in present scenario Forest Clearance - Factors contributing to Delay Issuance of “No-Objection Certificate” on jungle-jhari by Dist Admn. Issuance of “No-Objection Certificate” on Forest Rights Act by Dist Admn Conductance of Gram Sabhas & certification of its proceedings. Old / not updated land records / forest records, Mismatch of habitants / persons in actual possession of the forest land, wrt available land records. Involvement of number of Central / State Government departments and slow processing of proposal at State Forest Dept. and MOEF. Site inspection & submission of inspection report by Regional Office of MOEF to MOEF, New Delhi. Non-availability of alternate land for compensatory afforestation. NTPC’s experience in forest clearance PakriBarwadih Chatti- Kerandari Bariatu Important Pre-requisites Talaipalli Dulanga * Time taken in months Approval of Mining Plan 7 7 11 4.5 9 NOC on jungle-jhari 26 22 32 28 NA Process Time taken in months Processing of Stage I proposal by State Govt. 5 8 9 7.5 - Site inspection and forwarding of report to MOEF 7 4 7 3 - FAC meeting and Stage I approval 9 4 2 5 - Stage II clearance 4 9 - - - Clearance for tree felling 6 - - - - * NTPC lost 13 months for Dulanga coal block due to ‘No-Go’ area issue. Forest Clearance – Suggested Measures • Regular updation of land and forest records. • Creation of land data bank by Forest Dept. in advance for Compensatory Afforestation. • State Forest Department need to process the proposals within strict timelines. • Process repetition like site inspection by PCCF as well as Regional Office of MOEF, etc. may be avoided. • More number of Forest Advisory Committees (FACs) may be constituted by MOEF. Environment Clearance - Flow Chart Site Clearance / TOR Geological Report Mining plan Submission to SPCB Public Hearing NOC from SPCB Preparation of EIA/EMP Submission of Comprehensive EIA/EMP along with Schedule II Performa to MOEF Approval Engagement of Agency Clearance by Expert Committee Stage I Forest Clearance Environment Clearance MOC schedule stipulates 6 months to complete all these activities – Unrealistic in present scenario NTPC’s experience in environment clearance PakriBarwadih ChattiBariatu Kerandari Talaipalli Key processes causing delays Dulanga Time taken in months Conductance of public hearing and NOC from SPCB 19 6 38 7.5 3 EAC meeting and grant of clearance 21 17 21 10 * 18 * * In-principle clearance accorded – final clearance after Stage-I forest clearance Environment Clearance – Suggested Measures • State Pollution Control Board may act in time-bound manner – • Public Hearing • Report submission • Some sort of environment clearance for cluster of coal blocks may be thought of. • MOEF may consider more number of Expert Appraisal Committees (EACs). Land Acquisition – Factors contributing to Delay • Processing of proposals / issuance of notifications and disbursement of payment by State Govt. / District Admn. • Non-availability of land records / very old records with Dist Admn. • Inadequate manpower at Block / Dist. level. • Slow processing of Govt. land proposals at various level of State Govt. • Absence of Policy for dealing with encroachers of less than 30 yrs. • Approval of R&R Plan by State Govt. • Local resistance - Law & Order situation • Non-standardization of procedures – varying from State to State. Land Acquisition – Suggested Measures • Specialized land acquisition department / agencies by State Governments may facilitate land acquisition process such as IDCO in Odisha, MSIDC in Maharashtra. • Special land acquisition cell at Dist. level. • Uniform R&R Policy for Coal Mining. • Regular updation of land records, digitization. Databank of land for public purposes. Maintenance of comprehensive and intelligent map database. Instant production of Cadastral maps of any scales, themes and sizes. • Processing of land proposals – e-filing. Mining Industry can grow only with active support & involvement of State Govt. Infrastructure Development • Most of the major coalfields not connected with Railway infrastructure. • Development of Railway infrastructure takes huge time – facing with issues like forest clearance, land acquisition, law & order situation, etc. • Support of State Govt. lacks in creation of rail as well as road infrastructure. • Obtaining of non-coal bearing area clearance troublesome. Some suggestions : • Expeditious development of Rail / Road with State support • Dedicated freight / coal corridor • Master Network before allocation of coal blocks with firm plan for Rail corridor. Captive Mining in India to excel To sum up …….. Conclusion • Active support & involvement of respective State Govt. • MOC considering ‘Reserve Price’ for coal blocks – Milestone-based payment to State Govt. • Special thrust of State Govt. for land record updation & digitization. • Expeditious Environment & Forest clearances – Process simplification, Cut short process repetitions, Single-window approach, more nos. of FACs, EACs. • Infrastructure Development : • Expeditious development of Rail / Road with State support • Dedicated freight / coal corridor • Master Network before allocation of coal blocks with firm plan for Rail corridor. • Special Task Force for monitoring the project implementation. • Adoption of latest technology & best practices in Mining (UG & deep OC), deployment of high capacity HEMM, indigenous manufacturing. • Incentive to captive coal mines to maximise production & to allow sale of surplus coal to other power generators after meeting own coal requirement for the life of the project. Thank You