IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau The role of BAT conclusions and BREFs in the Industrial Emissions Directive (IED) Conference on Implementation and Enforcement of Environmental legislation 01 – 04 October 2013 Floriana, Malta Serge Roudier European Commission, Joint Research Centre 1 1 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau IPTS in the context of the Joint Research Centre (JRC) European IPPC Bureau (EIPPCB) ~22 staff within the Sustainable Production and Consumption (SPC) Unit of the Institute for Prospective Technological Studies (IPTS) 2 2 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau Outline of this presentation 1 - The Industrial Emissions Directive (IED) 2 - The Sevilla process 3 - Challenges for the review of BREFs under the IED 3 3 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau 1 - The Industrial Emissions Directive (2010/75/EU) 4 4 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau Industrial Emissions Directive 2010/75/EU (IED) Key instrument for minimising consumption and the emissions of industrial activities in Europe General framework: prevent and, if not feasible, reduce pollution high level of protection for the environment as a whole permit based on Best Available Techniques (BAT) BAT are determined by a Technical Working Group steered by the JRC (EIPPCB) and documented in BREFs ‘BAT conclusions’ are secondary legislation 5 5 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau Annex I to IPPC and IED Directive Wide range of industrial activities listed: • Energy industries • Production and processing of metals • Mineral industries cement, lime, glass, ceramics • Production of chemicals • Waste management industries Several recovery or disposal operations Incineration • ‘Other’ industries: Pulp and paper, textile processing Tanning of hides and skins Intensive farming of pigs and poultry, slaughterhouses and animal by-product processing, food drink and milk processing, surface treatment using solvents ~ 50 000 IPPC installations in Europe 6 6 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau Environmental scope of the IED emissions to air prevention and control of accidents emissions to water waste prevention and recovery vibration noise heat energy & water use odour 7 7 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau Definition of BAT in the IED Best Available Techniques Most effective in achieving a high general level of protection of the environment as a whole Developed on a scale which allows implementation in the relevant industrial sector, under economically and technically viable conditions Both the technology used and the way in which the installation is designed, built, maintained, operated and decommissioned Note: in determining BAT, special consideration should be given to the criteria listed in Annex III of the IED8 8 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau Role of BAT conclusions in IED permitting BAT conclusions are the reference for setting permit conditions Permits to contain emission limit values (ELVs) to ensure that, under normal operating conditions, emissions do not exceed BAT-associated emission levels (BAT-AELs) Derogation from BAT-AELs is only allowed in specific and justified cases • Need to demonstrate that costs are disproportionately higher than benefits due to local/installation-specific situations • Member States report to the public/Commission on use of derogations 9 9 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau Reconsidering / updating permit conditions (IED Article 21) • "Within four years of publication of decisions on BAT conclusions in accordance with Article 13(5) relating to the main activity of an installation, the competent authority shall ensure that: (a) all the permit conditions for the installation concerned are reconsidered and, if necessary, updated to ensure compliance with this Directive [the IED]; (b) the installation complies with those permit conditions. • The reconsideration shall take into account all the new or updated BAT conclusions applicable to the installation and adopted since the permit was granted or last reconsidered." 10 10 10 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau 2 - The Sevilla process A complex consensus-building exchange of information with numerous stakeholders and underpinned by sound techno-economic information that has been enshrined into law by: Commission Implementing Decision 2012/119/EU 11 11 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau The legal basis for the exchange of information on BAT Article 13(1) of the Industrial Emissions Directive 2010/75/EC: ‘In order to draw up, review and, where necessary, update BAT reference documents, the Commission shall organise an exchange of information between Member States, the industries concerned, non-governmental organisations promoting environmental protection and the Commission’ The exchange of information should address: the performance of installations and techniques in terms of emissions and consumptions, etc. the techniques used, associated monitoring, economic and technical viability, etc. best available techniques and emerging techniques identified after considering all the issues concerned 12 12 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau Exchange of information on BAT: actors EU Member States Committee (IED Article 75) ‘Forum’ (IED Article 13) lead by the Commission: industry, Member States, environmental NGOs European IPPC Bureau (EIPPCB) GLS I&S WT (Glass) (Iron and Steel) (Waste Treatment) • Industry • Member States • NGOs • Commission • Industry • Member States • NGOs • Commission • Industry • Member States • NGOs • Commission 35 Technical Working Groups (TWGs) Members of the Committee: • vote the BAT conclusions Forum members: • guidance to COM • nominate in TWGs • formal opinion on BREFs BREF authors team: • lead TWGs • validate/check information • draft BREFs • present BREF to Forum TWG members: • research information • peer review draft BREFs 13 13 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau The ‘Sevilla process’ TWG Industry kick-off meeting EU Member States + EFTA and Accession Countries Draft 1 (D1) Bulk of info. needed (incl. questionnaires) Comments Draft 2 (D2) * Final TWG meeting * D2 optional Total duration: • 24 – 29 months (without D2) • 29 – 39 months (with D2) Final draft BREF BAT conclusions • Forum opinion on BREF • Adoption of BAT conclusions through the IED Art. 75 Committee BAT 14 conclusions 14 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau Exchange of information on BAT: BREFs Standard BREF structure: • Preface • General information about the sector …… Chapter • Process/techniques used……………………… Chapter • Consumption and emission levels………… Chapter • Candidate BAT …………………………………… Chapter • BAT conclusions ………………………………… Chapter • Emerging techniques…………………………… Chapter • Concluding remarks and recommendation for future works (including suggestions for R&D) 1 2 3 4 5 6 200 to 1000 pages 15 15 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau Data collection step is crucial for determining BAT The information on key environmental issues is obtained through plant-specific questionnaires covering: emissions to air and water generation of solid by-products, residues and wastes efficient energy use techniques that are potential BAT candidates Importance of contextual information: details on the techniques used (characteristics, historical data) other than normal operating conditions link between the fuel characteristics and generated pollutants consumptions (e.g. raw water, energy, chemicals) 16 16 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau BAT is about real plant performance TSS concentration in the influent and effluent of central WWTPs (detail) BAT-AEL: 10 – 20 mg/l (monthly average) #36: MBR: <detection limit for TSS 39 60 Lag.+Sed.2 Sed.2 49 Air+flot. 37 46 #48: LVOC, Direct Pretreatment: Settling+bio. treat. 44 Flot.1 50 Sed.2+Filt. 63 Meca.+OWS+Sed.1+Sed.2 38 27 Sed.2+Flot.2 09 041 43 62 Sed.2+Pond/lag. 19 OWS+Sed.1+Sed.2+Filt. 64 OWS+Air+flot.+Flot.1 41 CMAS_MBR 35 Meca.+OWS+Sed.1+Flot.2 54 Sed.1+Sed.2 32 Sed.+Air_flot. 40 33 Air_flot. 07 59 Air_flot. 02 Sed.1 67 Sed.1 Sed.1+Sed.2 61 Filt.+Pond/lag. 01 Sed.1+Sed.2+Filt. 0 34 Meca.+Flot.1+Filt. 0 042 69 Meca.+Sed. 10 03 Filt. <5 Sed.1+Sed.2 20 53 Sed.1+Filt. 45 Meca. 30 Meca.+OWS+Sed.1+Sed.2 40 65 Sed.2 50 Sed.1+Sed.2 60 30 Meca.+Sed.2 #40: OFC+POL, Direct Pretreatment: floc+filtration TSS (mg/l) 70 17 Sed.1+Sed.2 29 80 Sed.2 48 90 Flot.2 51 OWS+Air+flot. 100 influent 20-430 40 Number of central WWTPs Only part of the effluent passes through the MBR - Data from 2007, in 2009 <10 mg/l #08: MBR: 1.1 mg/l (average of 150 measurements) 17 17 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau BREFs are available to the world http://eippcb.jrc.ec.europa.eu/reference/ 18 18 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau Progress on the review of BREFs under the IED 4 BAT conclusions already adopted: Iron and Steel; Glass; Tanning of Hides and Skins; Cement, Lime and Magnesium Oxide 3 BAT conclusions soon to be adopted: Chlor-Alkali; Pulp, Paper and Board; Refining of Mineral Oil and Gas 9 (B)REFs being worked upon: Common Waste Water/Waste Gas; Non-Ferrous Metals; Intensive Rearing of Poultry and Pigs; Large Volume Organic Chemicals; Large Combustion Plants; Wood-Based Panels; Waste Treatments; Food, Drink and Milk; Monitoring Work on 3 more BREFs to start in 2014: Waste Incineration; Surface Treatment using Organic Solvents; 19 Wood-Preservation with Chemicals 19 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau 3 - Challenges for the review of BREFs under the IED 20 20 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau 35 BREFs 8-year review cycle 21 21 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau Challenges and constraints of a BREF review The delivery of BREFs and BAT conclusions is a prerequisite for the updating of IPPC permits time is a critical factor in the implementation of the IED, there is now the need to speed up the Sevilla process The time allowed for a BREF review is 2-3 years maximum Resources are scarce among stakeholders involved in the Sevilla process, including the EIPPCB Increased importance of BREFs/BATC requires the acquisition of better and more data (contextual information, applicability, monitoring, costs), which may 22 not be readily available 22 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau General strategy to shorten the time to delivery Adopt a more focused approach (shorter BREFs, focus on BAT conclusions, target key environmental issues) Anticipate further and prepare input before the BREF review starts: anticipation of the structure of the BAT and identification of the data needs are crucial to devise appropriate questionnaires ‘single draft’ route is the standard for BREF reviews not involving major changes in the scope Possibilities for e.g. extending commenting periods and holding additional TWG or subgroup meetings are necessarily limited Deliver the best quality with (limited) available time and resources 23 23 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau Conditions to reach useful BAT conclusions All stakeholders should contribute to the exchange of information, including representatives from institutions/associations who are not directly represented in the TWG (e.g. competent authorities, equipment suppliers, representatives of industrial installations) The applicability of the identified BAT and any potential restrictions need to be carefully assessed A transparent exchange of information needs to be ensured BAT conclusions are based on clear facts and sound techno-economic information 24 24 IMPEL Conference Malta Role of BAT and BREFs in new IED 3 October 2013 European IPPC Bureau Thank you for your attention Serge Roudier Head of the European IPPC Bureau Serge.Roudier@ec.europa.eu +34 954 488 308 http://eippcb.jrc.ec.europa.eu/ 25 25