Enmax Shepherd Power Centre CRAZ AGM 2013

advertisement
Shepard Energy
Centre
Environmental Stewardship
Overview
Nominal 800 MW Natural Gas Combined Cycle
Early 2011 Received Regulatory Approval (Alberta
Utilities Commission and Alberta Environment and
Sustainable Resource Development)
Cost: Approximately 1.35 Billion
Joint Venture with Capital Power
Currently under construction
COD: Early 2015
Technology
Video
Natural Gas Combined Cycle
2 on 1 Mitsubishi 501G gas turbine
4
Environmental Attributes - Low Air Emissions
GHG – Less that 0.4 tonnes/MWh (less than half of the
emissions from Coal)
SOx – Virtually none
NOx – Shepard will only emit between 3 ppm and 6 ppm
PM – virtually none
Mercury – No mercury emissions
We did extensive air dispersion modeling and Shepard has
minimal impact on air quality in the region.
Environmental Attributes - Water Consumption
Plant
MW
ML/y
ML/MW
Keephills
766
16000
20.9
Battle River
663
6019
9.1
More efficient
Shepard
800
3796
4.7
Very efficient due to plant design and uses reclaimed water
Comment
Inefficient
Shepard Site Photos – April 2013
Aerial View Looking South
Shepard Site Photos – April 2013
Fiberglass Cooling Tower Showing End Wall And Louver Installation
Shepard Site Photos – April 2013
HRSG #2 Finger Rack Area
Shepard Site Photos – April 2013
Combustion Turbine #1
Shepard Site Photos – April 2013
Low Pressure Steam Turbine Rotor Insertion