PICTURE OF (SITE) CAPSTONE TEAM WHO WE ARE (MEMBERS SKILLS) MAQUIGR TEAM BEYOND SHOWS FRACTURED ROCKS PICTURES DISPLAYED RETAINING WALL DESIGN S LO P E S TA B I L I T Y O N U S - 1 8 9 MAQUIGR ENGINEERING Matthew Hakes, Quinton Taylor, Greg Hanks Site Evaluation SITE 1 IS FEATURED ON TOP SITE 2 ON BOTTOM Site 1 NOTICE: WATER LOCATION Site 2 TEMPORARY SOLUTIONS LOADS CAUSED BY ROAD Considered Solutions SHEET PILE PROS RAPID CONSTRUCTION CONS SHALLOW ROCK MAKES IT IMPOSSIBLE TO DIG IN DEEP ENOUGH TO GET MOMENT Gabion Tieback Sheetpile Tieback Shotcrete Soil Nail Analysis with SnailPlus Assumptions made: Two different soil types • Gravel/Sand • Bedrock Loading • Temporary Max: 700 psf from construction • Permanent Max: 200 psf from traffic Morgenstern-Price • General limit equilibrium (Moment-force) FHWA factors of safety used Analysis with SnailPlus Under construction loading conditions Design section No. 4 No. 3 Calculation Calculation successful Calculation successful FS Slope Fmax Nails (k) Fmax Nails at Head (k) 1.347 17.3 17.3 0.296 0.89 0.286 2.155 6.8 6.8 0.117 0.353 0.113 FS Slope Fmax Nails (k) Fmax Nails at Head (k) 1.579 14.9 14.9 0.257 0.856 0.275 3.07 5.5 5.5 0.094 0.331 0.09 STR Check Nails STR Check Plates STR Check Facing Under normal traffic loads Design section No. 4 No. 3 Calculation Calculation successful Calculation successful STR Check Nails STR Check Plates STR Check Facing Final Design INITIAL CONCEPTION OF WALL SHAPE CREATED SLOPE IN AUTO CAD • 10ft from road edge • Average height, 6ft • 120ft in length • Max height, 13ft • 17 Total Soil Nails UNIFIED DESIGN 1/2 THE DISTANCE FOLLOW SLOPE OR WHAT OPTIMIZED FOR CONSTRUCTION Phase 1 Site Preparation •Conducted during low traffic flow •Close southbound lane •Flaggers to direct flow of traffic through single lane Environmental Impact Reduction (3 lines of defense) •Excavated 5ft bench •1ft silt fence installed 20ft below excavation line •Exposed Shoreline Phase 2 Excavation Slope Preparation •5ft bench approximately 10ft out from edge of the road •Excavation of 1,000 cubic feet •Soil relocated to holding site Phase 3 Soil Nail Installation •Williams Geo-Drill Injection Anchor System with rotary percussive drilling •In case of hitting hard rock, a Polyester Resin Rock Anchor System may be used Phase 4 Prefabrication of Rebar Cages Phase 4: •Constructed offsite due to limited space •75 year design life, hot-dip galvanizing Phase 5 •Challenge will be mobility and visibility of excavator •Guided into place by multiple workers located on bench Installing Rebar Cages The key to the project was contstruction speed 8 in mat Number 6 rebar Tied together Bring in on flat bead and then drop in excavator secure them in place Phase 6 Shotcrete •Two step process using wire mesh as backstop for shotcrete •First day application spraying towards the road, second day other side is applied A problem (wall needs concrete) solution we could pump it with shotcrete Bench was created for workers to stand on No wall – wire mesh 2 sided Phase 7 Installing Drainage System Phase 5: •Composite Drainage system •Drainage system includes: geosythetic filtered fabric and molded plastic core Phase 8 Anchor to wall Attachments •Bearing plate, hardened washers, hex nut, and Geo-Drill Injection Anchor •75 year design life, galvanizing bearing plate and hardened washers and capped with a steel tube filled with cement grout Phase 9 Backfill •Using the soil from the excavation, backfill at 8-12in lifts •Compact soil with plate compactor attachment while avoiding soil nails •Increased bar size to improve bending strength in the case of accidental contact with compactor Phase 10 Phase 11 Capping Cleanup Phase 10: •Last 4-6in of backfill will be filled with cement to cap off the retaining system •Reduce permeability of surface and prevent corrosion Phase 11: •Remove silt fencing and any loose material •Add soil to bench to create a more natural slope •Application of hydroseed to slope to promote vegetation growth Time and Cost Estimates Days Plans & Surveying Permits & Fees Construction Loans COST 17 For this Project we will assume that Planning and Surveying, Permits and Fees and Construction Loans are taken Care of at this point. The Schedule will be 17 Days 1 1 2 Phase 1 Staging area Silt Fencing Moving Baricades Traffic Control Laying gravel Construction Signage 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 THE FEDERAL HIGHWAY ADMINISTRATION CHARCTERISTICS THAT COST $$$ Phase 2 Staking Excavation Soil Removal Phase 3 Marking Soil Nail Instalation drilling add section grouting capping LOCATION, MATERIAL, NIGHT TIME ECT Phase 4 Delivery Rebar, Ties Cutting Bending rebar tieing rebar Installing wire mesh loading for transit SCHEDULE Phase 5 Drainage Fabric Drainage Piping Phase 6 Marking Location Leveling Compacting base delivering from staging dropping in place In place fabrication securing soil nails Phase 7 Shotcreting walls Phase 8 Attachmen plates Phase 9 Load for backfill Transport backfill Place Backfill Compact 10" lifts HOW WE CAME UP INTEGRATING PHASES TO OPOMIZE TIME Phase 10 Form for concrete cap Pour concrete Phase 11 Cleanup Removing Traffic devices •Cost estimates are based on the FHWA pricing graph and scheduling was created in 11 phases Conclusion A soil nail retaining system is the best option for this project •Adaptable – Depending on what is encountered during construction this design can easily be modified to meet the needs of the project •Cost Effective – With little excavation near the road, a temporary wall will be unnecessary •75 Design Life – Simple methods that can be implicated to increase design life