13_CM at Risk Delivery Method by Steve Skabla

advertisement

Click to edit Master title style

Facilities Institute

Houston, Texas

Understanding the

Construction Manager at Risk

Project Delivery Method

Presented by

Steve Skabla, Vice President

Chief Estimator/Preconstruction Manager

Facilities Institute

July 9 - 12, 2012

Houston, Texas

Presentation Overview

• Overview of Various Project Delivery Methods o Traditional (Lump Sum) Bid o Competitive Sealed Proposals o Design/Build o Job Order Contracting o Construction Manager at Risk

• Explanation of Construction Manager at Risk o Definition o Characteristics o Pros/Cons o Project Examples o Lessons Learned

• How to Evaluate Best Value

What is a “Project Delivery Method”

The process of how a project will be planned, designed and built

OR

Procurement strategy for designing and constructing a facility

OR

Means of contractually communicating expectations and basis of reimbursement

OR

The process of managing how a project will be planned, designed and built

Overview of Delivery Methods

Traditional & CSP Design/Build

Owner

General

Contractor

A/E

S u b c o n t r a c t o r s

Design Bid Construct

Traditional

Price only

CSP

Price and

Technical

Qualifications

Job Order Contract

Owner

Design/Builder

Owner

A/E or

Consultant

JOC

Contractor

S u b c o n t r a c t o r s

Self-

Perform

Select Design Construct

S u b c o n t r a c t o r s o r

E m p l o y e e C r e w s

Select Design Construct

Price & Technical

Qualifications

Price & Technical

Qualifications

Overview of Delivery Methods

Construction Manager at Risk

Owner

Sub

CM

Sub Sub

A/E

Sub Sub

Select Design

Construct

Fees, general conditions and qualifications

Construction Manager at Risk (CM at Risk)

• What to Expect from Your CM o Provide constructability reviews o Provide detailed cost estimates at Schematic Design, Design

Development and at Guaranteed Maximum Price (GMP) o Deliver GMP prior to completion of Construction Documents o Begin construction before design is 100% complete o Bring best subcontractors and best prices to the project o Control costs/budget o Take a business risk o Provide financial guarantees o Act in the Client’s best interest

Preconstruction (Not Just an Estimate & Schedule)

Budgeting

Solicitation

& Pre-

Qualification

Process

Bid Package

Development

GMP

Development

Value

Engineering

Options

Purchasing

Process

Scheduling

Site Logistics

Over-the-

Coordination &

Shoulder

Design

3D Collision

Comprehensive

Planning &

Monthly

Reporting

Process

FF&E

Coordination &

Management

Constructability

Review &

Site

Management

Planning

Budgets

& Schedules

Meeting Life-Cycle

Management Analysis

Team

Communication

Protocols

Job Hazard

Analysis

OCIP/CCIP

Plan

Severe Weather

Preparedness

Testing &

Commissioning

Process

Occupancy

Planning

Quality

Management

Process

Planning for

Service After

Completion

CM at Risk

PROS

• Flexibility in selecting a builder

• CM provides preconstruction services and works in team concept with A/E & Owner

• Usually brought on early in design (program/SD)

• Constructability reviews at each stage of documents

• Opportunity to phase/fast track

• Better opportunity to maximize

HUB/MBE subcontractor participation through bid package strategic initiatives

Facilities Institute

July 9 - 12, 2012

Houston, Texas

• Opportunity for bid strategies on inflationary materials

• Reduces the risk of proprietary specifications

• Change flexibility

CONS

• Price is not guaranteed at time of selection

• Owner must have more involvement in the process

• Difficult to evaluate actual cost between CM at Risk candidates

Lowest Cost vs. Best Value

Best qualified firm will give you the most value for the 91%.

Project Candidates for CM at Risk

Best Suited

• Large new or renovation projects

• Schedule sensitive

• Difficult to define

• Subject to change

Least Suited

• Small or simple projects

Facilities Institute

July 9 - 12, 2012

Houston, Texas

Example: South Texas Research Facility

Texas A&M Univ., Veterinary Imaging & Cancer Treatment Center

CM at Risk Lessons Learned

• The best performers at CM at Risk are the same best performers at CSP and hard bid.

• State procurement laws may vary the process.

o Example: For Texas, 100% CDs and public subcontractor proposals on each package are required prior to any real work.

o It is more work, not less for the Architect and Contractor.

• Allow adequate time for review and approval of the

Guaranteed Maximum Price (GMP).

• Allow adequate time for the subcontractor selection process by the CM and Owner approval

CM at Risk Lessons Learned

• Agree on the subcontractor selection criteria and process early.

• The project design must be sufficiently advanced to have accurate general conditions proposals in the RFP.

• Clearly define what is to be included and excluded from “general conditions” in the RFP.

• Lump sum general conditions - not cost plus.

o The most issues/problems.

o 90% of contract administrator or Owner’s representative’s time on

5% of cost.

CM at Risk Lessons Learned

• Draft a total project schedule, not just a construction schedule.

• Give the CM the entire project budget. Tell the

CM what parts it is responsible for.

• Add example schedule, decision milestones

Benefits of CM at Risk Delivery

Example: 1 Million GSF

Public Hospital

• 4-year project duration

• Items bought early

• Potential cost savings

Pick the Right Delivery Method

• Before starting the selection process, determine which delivery method will provide “best value”

• Factors to consider ( add more ): o Project size and complexity o Time allocated for the construction o Competitiveness of the current/local construction market o Desired flexibility o Availability of contractors and subcontractors in the local market

• After deciding on key factors, evaluate the various delivery methods and formally adopt the method you deem “best value.”

Hand-out

Thank You

Steve Skabla

713.243.8301

steves@vaughnconstruction.com

Facilities Institute

July 9 - 12, 2012

Houston, Texas

Download