Health Healthand andSafety Safety Executive Executive Update on Löfstedt Review and Red Tape Challenge Anthony Lees HSE Construction Policy Unit Better regulation policy • • • Government better regulation strategy • • • February 2011 – Ministerial Statement June 2010 – Lord Young review October 2010 – ‘Common Sense, Common Safety’ May 2011 – Löfstedt – call for evidence November 2011 – Report and Government response Better regulation policy • • • • • April 2011 – Red Tape Challenge Health and Safety theme July 2011 – ‘spotlight’ period 2012 – ‘Star Chamber’ process Lofstedt and RTC implementation: 20112015? Löfstedt Report - themes • Specific revocations and consideration of further consolidation • • • • Review of all ACoPs • Influencing Europe to ensure legislation is risk-based Self-employed exemption Civil liability and strict liability regulations Improving quality and consistency of local authority enforcement Löfstedt recommendations – observations • • • • • HSE welcomes the report Opportunity to improve regulation Impact limited on higher risk sectors Does not dilute standards Some uncertainty over implications of future work Specific Revocations • • Two tranches of specific revocations • 2nd tranche – 14 Statutory instruments consultation opens early April • Three construction-specific Regulations – Construction (Head Protection) Regulations 1989 – Notification of Conventional Tower Cranes Regulations 2010 + amendment 1st tranche – 7 Statutory Instruments consultation closed Construction (Head Protection) Regulations 1989 - rationale • Regulations have largely delivered what they set out to • Head protection culturally-embedded in industry practice • Equivalent protection offered under PPE Regulations • • Behaviours unlikely to change Existing exemption retained Notification of Conventional Tower Cranes Regulations 2010 - rationale • • Rationale for introduction • Existing legislation provides adequate framework for assurance of integrity • Non-regulatory work has improved standards • • Have not delivered expected benefits Target public assurance, not health and safety Costs substantially higher than expected Specific revocations - process • • Standard 12 week public consultation • Subject to committee scrutiny and Ministerial approval • • Any revocations expected later this year Backed by impact assessments (form part of consultative document) Need to publicise revocations and implications – industry support welcome Review of ACoPs • • ACoPs have basis in Robens Report • Wide support for ACoPs, but concerns over length and complexity • Focus should be on assisting SMEs Intended to add precision in the context of goal-setting legislation Review of ACoPs • Review willl determine whhether each ACoP: – Is still required – Gives unambiguous guidance about what is required – Is up to date – Is presented in the most apropriate way • • CDM ACoP outwith Timings Self-employed exemption • • Specific recommendation in Löfstedt • • Intended to apply to low-risk activities Cannot apply to construction work due to Directive basis of CDM Explicitly will not apply to construction Civil liability and strict liability requirements • Löfsted concern over extent of right of civil action under regulations: fear of civil action provides a perverse incentive to employers – Pre-action protocols (‘Woolf lists’) – Strict liability • Use of pre-disclosure lists to be restated and clarified • Strict liability to be examined and either tempered by SFAIRP, or right to civil action restricted Other specific recommendations • • • CDM Challenge Panel(s) Work at Height Regulations 2005 Löfstedt: CDM 2007 recommendation • Löfstedt said little about CDM – he was aware of the review • Effectively recommended that HSE should now publish the CDM evaluation report Challenge Panels • Recommended an independent panel to allow challenge of decisions • HSE will form two panels – January 2012 – Independent Regulatory Challenge Panel – Later 2012 – ‘wider’ challenge panel Work at Height Regulations • Löfstedt recommended review of WAHR – Regulations are risk based, but poorly understood and applied – the ‘2m rule dilemma’ – Particularly an issue for SMEs – Elements of gold plating – eg stepladders • Ministerial interest in how WAHR is misapplied or burdensome • Construction fully played into review Red Tape Challenge • Comments made to RTC were considered by Löfstedt • Significant amount of discussion between departments and Ministers – ‘Star Chambers’ • • Process described on RTC website 3 meetings so far, more planned