Update on Löfstedt Review and Red Tape Challenge

advertisement
Health
Healthand
andSafety
Safety
Executive
Executive
Update on Löfstedt
Review and Red Tape
Challenge
Anthony Lees
HSE Construction Policy Unit
Better regulation policy
•
•
•
Government better regulation strategy
•
•
•
February 2011 – Ministerial Statement
June 2010 – Lord Young review
October 2010 – ‘Common Sense,
Common Safety’
May 2011 – Löfstedt – call for evidence
November 2011 – Report and
Government response
Better regulation policy
•
•
•
•
•
April 2011 – Red Tape Challenge
Health and Safety theme
July 2011 – ‘spotlight’ period
2012 – ‘Star Chamber’ process
Lofstedt and RTC implementation: 20112015?
Löfstedt Report - themes
•
Specific revocations and consideration of
further consolidation
•
•
•
•
Review of all ACoPs
•
Influencing Europe to ensure legislation is
risk-based
Self-employed exemption
Civil liability and strict liability regulations
Improving quality and consistency of local
authority enforcement
Löfstedt recommendations –
observations
•
•
•
•
•
HSE welcomes the report
Opportunity to improve regulation
Impact limited on higher risk sectors
Does not dilute standards
Some uncertainty over implications of
future work
Specific Revocations
•
•
Two tranches of specific revocations
•
2nd tranche – 14 Statutory instruments consultation opens early April
•
Three construction-specific Regulations
– Construction (Head Protection) Regulations
1989
– Notification of Conventional Tower Cranes
Regulations 2010 + amendment
1st tranche – 7 Statutory Instruments consultation closed
Construction (Head Protection)
Regulations 1989 - rationale
•
Regulations have largely delivered what
they set out to
•
Head protection culturally-embedded in
industry practice
•
Equivalent protection offered under PPE
Regulations
•
•
Behaviours unlikely to change
Existing exemption retained
Notification of Conventional Tower
Cranes Regulations 2010 - rationale
•
•
Rationale for introduction
•
Existing legislation provides adequate
framework for assurance of integrity
•
Non-regulatory work has improved
standards
•
•
Have not delivered expected benefits
Target public assurance, not health and
safety
Costs substantially higher than expected
Specific revocations - process
•
•
Standard 12 week public consultation
•
Subject to committee scrutiny and
Ministerial approval
•
•
Any revocations expected later this year
Backed by impact assessments (form part
of consultative document)
Need to publicise revocations and
implications – industry support welcome
Review of ACoPs
•
•
ACoPs have basis in Robens Report
•
Wide support for ACoPs, but concerns
over length and complexity
•
Focus should be on assisting SMEs
Intended to add precision in the context of
goal-setting legislation
Review of ACoPs
•
Review willl determine whhether each
ACoP:
– Is still required
– Gives unambiguous guidance about
what is required
– Is up to date
– Is presented in the most apropriate
way
•
•
CDM ACoP outwith
Timings
Self-employed exemption
•
•
Specific recommendation in Löfstedt
•
•
Intended to apply to low-risk activities
Cannot apply to construction work due to
Directive basis of CDM
Explicitly will not apply to construction
Civil liability and strict liability
requirements
•
Löfsted concern over extent of right of civil action
under regulations: fear of civil action provides a
perverse incentive to employers
– Pre-action protocols (‘Woolf lists’)
– Strict liability
•
Use of pre-disclosure lists to be restated and
clarified
•
Strict liability to be examined and either
tempered by SFAIRP, or right to civil action
restricted
Other specific recommendations
•
•
•
CDM
Challenge Panel(s)
Work at Height Regulations 2005
Löfstedt: CDM 2007 recommendation
•
Löfstedt said little about CDM – he was
aware of the review
•
Effectively recommended that HSE
should now publish the CDM evaluation
report
Challenge Panels
•
Recommended an independent panel to
allow challenge of decisions
•
HSE will form two panels
– January 2012 – Independent
Regulatory Challenge Panel
– Later 2012 – ‘wider’ challenge panel
Work at Height Regulations
•
Löfstedt recommended review of WAHR
– Regulations are risk based, but poorly
understood and applied – the ‘2m rule
dilemma’
– Particularly an issue for SMEs
– Elements of gold plating – eg
stepladders
•
Ministerial interest in how WAHR is
misapplied or burdensome
•
Construction fully played into review
Red Tape Challenge
•
Comments made to RTC were
considered by Löfstedt
•
Significant amount of discussion between
departments and Ministers – ‘Star
Chambers’
•
•
Process described on RTC website
3 meetings so far, more planned
Download