Using PMPlan® as an EVMS “Earned Value Management System” by AlNik Solutions Copyright 2010-2011 © Agenda for ‘Using PMPlan as an EVMS’ • Project Management for EVMS • Developing the Project Plan • Managing project using Earned Value Methodology – What is EVM and how it is used – Using the EVM features of PMPlan – EVM Reports from PMPlan Using the Earned Value Methodology • For the Earned Value Method to work properly, the project will need to broken-down into measurable units. In PMPlan, that measurable unit is at the activity level, not at an upper level work package. • The recommendation is, that control accounts (where the actual costs are accumulated) be one or two levels above the activities (where the earned value is measured). Agenda for ‘Using PMPlan as an EVMS’ • Project Management for EVMS • Developing the Project Plan • Managing project using Earned Value Methodology – What is EVM and how it is used – Using the EVM features of PMPlan – EVM Reports from PMPlan Good WBS Design Principles for EVMS • The 100% Rule – The WBS defines 100% of the work of the project – Anything that isn’t defined in the WBS is outside the scope of the project. – The work content on any item is the sum of what is included under that work item • The WBS must be consistent with the way the project will be performed and controlled • Upper Levels are planned project outcomes not planned actions, or the work effort • Milestones are the objectives of the work effort, but are not the work effort • Activity Levels are the project work effort, and are where the budget effectiveness (EVM) of the effort is measured Scheduling for EVMS • Scheduling forces the: – Quantification of a discrete work effort – Placement of the work effort in its proper relationship to that of another work effort – Setting the parameters of time by which the work effort can be measured (EVM) Agenda for ‘Using PMPlan as an EVMS’ • Project Management for EVMS • Developing the Project Plan • Managing project using Earned Value Methodology – What is EVM and how it is used – Using the EVM features of PMPlan – EVM Reports from PMPlan An Earned Value Management System • Can: – Provide early (Difficult to ignore) performance problem identification – Improve financial Reporting • Does not: – Recognize Critical Paths • Can not: – Take management action Time-Phased Spend Plan • This shows the time-phased spend plan if the project proceeds as planned. Typical Approach of Tracking of Actual versus Planned • The chart tells us we have spent less than planned to date, but • We cannot tell if we are behind schedule, nor if the cost for work completed matches the actual costs. Measurement Terminology • Budget at Completion (BAC) – The sum of the total budget for a work package, major task, or project. • Planned Value (PV) – The scheduled cost based on the allocation cost items such resources and material during the timeline of an activity – Also called Budgeted Cost for Work Scheduled (BCWS) • Earned Value (EV) – The value of the work performed to-date using any reasonably accurate, mutually acceptable methodology for determining value (i.e.; 0/100%, 50/50%, 30/40/40, ratio of units completed versus total units, manager estimate, level of effort, being some examples). – Also called Budgeted Cost for Work Performed (BCWP) • Actual Cost (AC) – Total incurred costs charged to a work package by the company’s accounting system, which can include labor costs, direct costs (overhead), and indirect costs (material, travel, and etc.) – Also called Actual Cost for Work Performed (ACWP) These values are used to calculate performance. Performance Terminology • Cost Variance (CV) – CV = EV – AC = BCWP – ACWP • Cost Performance Index (CPI) – The cost efficiency ratio of earned value to actual costs (CPI = EV/AC) – In PMPlan, the CPI is used to calculate Estimate at Completion (EAC) (EAC = BAC/CPI) • Schedule Variance (SV) – SV = EV – PV =BCWP – BCWS • Schedule Performance Index (SPI) – The schedule efficiency ratio of earned value accomplished against planned value (SPI = EV/PV). The SPI describes what portion of the planned schedule was actually accomplished. • Variance at Completion (VAC) – The predicted magnitude of possible underrun or overrun at completion of work package, major task, or project (VAC = BAC – EAC) Graphic of the EVM Terminology TAB VAC EAC AC Curve SV EV Curve Time CV Planned Completion PV Curve Forecasted Completion BAC Status Time Cost Management Reserve Review of Earned Value Concept • Will – Describe a simple project and its progress – Define earned value and related terms – Show how earned value defines project performance Note: Sample tables and graphics shown in following slides are from PMPlan Schedule • This shows a sample project schedule Planned Budget • The sample project is loaded with resources which results in an allocated spend plan. Using Earned Value Method • For the Earned Value Method to work well you need to breakdown the project into measurable activities (Note: in PMPlan, Cost Budgeting is done at the activity level not Control Account). • It is recommended that your Control Accounts (where you accumulate actual costs) be one or two levels above the activities. • The following five slides show different performance results of our sample project. Example PMPlan Earned Value Worksheet • • • • • The project manager or task leader enters either an earned percentage or a $ value. Actual Cost is also entered. In this worksheet, actual cost can also include open commitments such as unpaid invoices for material and equipment. The ‘Threshold’ is a percent of the AC to the BAC, which determines when the application uses the CPI to calculate VAC. If AC is less than the ‘Threshold’, the VAC equals CV. Based on the data entered, this project is both behind schedule and over budget. Even though the current CV = -$4,000, the VAC indicates a potential overrun of $5,517. The next slide shows two other views of this data. Project Status with a; Negative SV and CV • In the lower half of the graph, the EV is below both the PV and AC indicating problems with cost and schedule. • The upper half of the graph shows both CPI and SPI relative to a value of 1. It is showing that progress is being made to improve the schedule, but cost problem remains. • The black EV bars in the Gantt schedule at the right shows that the ‘Design’ and ‘Prototype’ activities are behind schedule. Project Status with a; SV and zero (0) CV • The EV and AC are equal, thus actual costs are inline with accomplishments. • Even though the project is behind schedule, the schedule variance trend shows a strong improvement in schedule. Project Status with a; zero (0) SV, + CV • This project is on schedule and should be completed under budget. • The status of the scheduled project tasks show that the earned bars are aligned within the green status line. Why 50% Complete may not be half the schedule status bar! • • • In the above example, all three activities have earned values of 50% of BAC, but the black earned bars are not the same length even though the planned bars are the same. Task A is behind schedule because, instead of 50%, 75% of the budget was scheduled to be spent by end of December. Task B is ahead of schedule because, instead of 50%, only 25% of the budget was scheduled to be spent by end of December. In Summary – an Earned Value System • Can: – Provide early (Difficult to ignore) performance problem identification – Improve financial Reporting • Does not: – Recognize Critical Paths • Will not: – Take management action Agenda for ‘Using PMPlan as an EVMS’ • Project Management for EVMS • Developing the Project Plan • Managing project using Earned Value Methodology – What is EVM and how it is used – Using the EVM features of PMPlan – EVM Reports from PMPlan Project Information Required for EVM Project Information – EVM Related Data Project Title Project Start Date Project Finish Date (Calculated) Project Cost Control Number Contractor Information Project Type Client Information Project Fee Project Contract Number from Client Project Appropriations Management Reserve Fiscal Month PMPlan Tracking Setup Tab Earned Value Set-Up Table Key to CPR Header Information In relation to a row in the Project Information Data 8 12 1 2 22 10&11 3 14 23 25 21 24 Controlling EV Color Codes, ETC Controls calculation of the independent EAC Controls which Control Accounts require analysis Controls Color Codes Agenda for ‘Using PMPlan as an EVMS’ • Project Management for EVMS • Developing the Project Plan • Managing project using Earned Value Methodology – What is EVM and how it is used – Using the EVM features of PMPlan – EVM Reports from PMPlan Status Tab – Performance Reporting Variance Analysis Report - Input Project Information – EVM Related Data Project Title Project Start Date Project Finish Date (Calculated) Project Cost Control Number Contractor Information Project Type Client Information Project Fee Project Contract Number from Client Project Appropriations Management Reserve Fiscal Month Cost/Schedule Status Report Earned Value reporting. Graphic Performance Report The Variance Trend graph provides a better indication of performance issues. CPR Lite Sheet One Slide generated by PMPlan. CPR Format 1 CPR Format 2 CPR Format 3 CPR Format 4 CPR – Format 5 (Cover Sheet) Variance Analysis Report - CPR Sheet 5 Variance Report Baseline, Earned, and Actual Graph SPI and CPI Graph Bull's-eye Chart Estimated Future SPI\CPI PMPlan© “For Project Managers, by Project Managers” Tools for Project and Line Management Questions?