Installation Practices at Mines - Moranbah North

advertisement
EXPERIENCES FROM THE USE
OF IN CYCLE TENDON
SUPPORT
Richard Campbell
Principal Geotechnical Engineer
Blackrock Mining Solutions
Metallurgical Coal
1
AGENDA
• Context
• Installing long tendon support on advance
• What the operators see as the risks in the process
• Opportunities to minimise the risks
• Geotechnical considerations
2
Metallurgical Coal
CONTEXT
As coal miners we are all aware we have two masters, two things that rule
our business;
1. Safety of our operators & operations
2. Longwall Float or Continuous LW Production
 = sustainable & profitable business
3
Metallurgical Coal
CONTEXT
Sustainable business.
Everyone in this room will appreciate the current and ongoing battle between
Development meters V’s Longwall retreat metres
= LONGWALL FLOAT
Increasingly the trend we are seeing is Development is losing the race.
The current push for more LW cutting hours, we are seeing across the various major
companies is increasing the gap between LW and Development.
Perceived delays of any sort in the Development process is coming under intense
scrutiny – installing long tendons in cycle is a target
4
Metallurgical Coal
CONTEXT
Changing Conditions
With Australian Longwall mines facing increased geotechnical challenges,
poorer conditions – perhaps needing tendons on advance in code GREEN
TARP conditions just to maintain safe working conditions and the on going
need to increase development rates the need to install long tendon support
on advance is becoming increasing topical and the focus of optimisation.
Also coal mining in Australia is going through a series of changes is the
quest for more coal at lower costs, and recovering coal in new & some
times difficult deposits.
All mines seem to want to go to longer and wider LW panels (6km now,
8km soon).
– Not many 300-400m wide x 6km or 8km blocks exist in nature with
5
no structure or zones of poor strata conditions.
Metallurgical Coal
6 Km +
CONTEXT
6
Metallurgical Coal
ASK THE OPERATORS
When asked “what would make it safer and easier to do?”
Installing long tendon support on advance in the development cycle is a potential
hazard to our operators – some operations do not allow post groutable bolts to be
installed off the CM.
A review of tendon installation related injuries and discussions with operators identifies
the following issues:
•Physically demanding tasks, in a
confined work area of the bolting
platforms on a CM
•Repetition, multiple drill rods to get to
4m, 6m, 8m up to 14m
•Pushing resin to the back of the hole
Metallurgical Coal
7
ASK THE OPERATORS
When asked “what would make it safer and easier to do?”
 Inserting the bolt into the hole, stiff cables need to be bent around the drilling
masts & manually pushing them up the hole, getting the bolt into the chuck.
 Attaching the jewellery
 Using the tensioning device,
• Typically heavy & needs to be lifted above shoulder height
• High pressure hydraulic lines
Crush and laceration of fingers & hands
type injuries
Strains and sprains, backs & shoulders –
heavy lifting, positioning of people
Hydraulic injection from the tensioning unit
Tensioner getting stuck on the bolt
Metallurgical Coal
8
ASK THE OPERATORS
When asked “what would make it safer and easier to do?”
 Reinstalls at the last moment in the bolt install process
 The cable end gets jammed in the dolly, splits the welds, cant get the tensioner on
the bolt……………….
 START AGAIN – re install,
 This is a cause of a great deal of grief & rework with the crews.
Two causes identified.
1. In the dollies cable spline is not robust, various type/brands on the market none
are human proof.
2. The drill pots rotate as the drill motor & mast are dropped, if the dolly is attached
this causes the welds to split.
Needs to be fixed for optimal install process.
9
Metallurgical Coal
OPPORTUNITIES
When asked “what would make it safer and easier to do?”
The following were identified as opportunities
 Remove the need for a tensioner – torque tensionable bolts
 Can we get enough tension on them, is 15+t needed?
 Optimise drilling tips to the actual strata conditions, faster drilling
 Cable feeders to do the grunt work of getting the bolt in the hole.
 Resin insertion – not fool proof
 Grouting –
 Is cement type material the best product to use
 Replace it with something quicker and faster setting.
 If on TARP red is it 24 mins, 24 hrs 48 hrs or 7 days before the grout is
hard enough to work under?
Metallurgical Coal
10
OPPORTUNITIES
When asked “what would make it safer and easier to do?”
 The following were identified as opportunities
 TARP related support plans that use point anchored tendons (say 6m long),
then if triggers are reached the next level uses post grouted tendons (say 8m
long) – can one bolt do both? The difference in 2m of drilling is not an issue,
pulling back the CM or stopping to put them in with an air track is an issue.
 Capacity of the bolts
 Grout tubes – how to ensure they survive
 Are cables the right tool? Extendable self drilling steel bolts (kind of like the old
“coupled bolt”)
 In hard rock they use a continuous roll of cable, automated feed and length cut off
at the hole – why don’t we?
11
Metallurgical Coal
GEOTECHNICAL
Its always a battle between not enough & too much
Metallurgical Coal
12
GEOTECHNICAL
13
Metallurgical Coal
GEOTECHNICAL
Are tendons the right tool for the job.
– Point anchored tendons v’s fully encapsulated
• Can we fully resin encapsulate a 6m or 6m long flexi bolt off a CM?
– How stiff are they,
• How far can they stretch?
• What’s acceptable strain/deformation on a tendon?
– Pretension
• How much is enough/to much
Are tendons on advance really there just to slow the movement down?
– Secondary support next to follow?
– Or are they the final fix?
14
Metallurgical Coal
Download