Registration Management Committee (RMC) AUDITING CUSTOMER REQUIREMENTS Chris Miller EAGLE Registrations Inc. Shannon Craddock Perry Johnson Registrars, Inc. Boston, MA July 21-22, 2011 Company Confidential Auditor Workshop Boston, MA July 21-22, 2011 1 Registration Management Committee (RMC) AGENDA: • Customer Specific Requirements (CSR) General and Process Auditing with CSRs (10 minutes) • Pre-Audit Planning Exercise (20 minutes) • OEM Customer Specific Requirements, Links, Documents and Items to Know (10 minutes) • Case Study (55 minutes) • Questions & Answers (10 minutes) Boston, MA July 21-22, 2011 Company Confidential 2 Registration Management Committee (RMC) Customer Requirements General and Process Auditing with CSRs Chris Miller Boston, MA July 21-22, 2011 Company Confidential 3 Registration Management Committee (RMC) Objectives of AS9100:2009 Audits: • On-time, on-quality performance • See AS9100 paragraphs 5.2, 7.2.1 and 8.2.1 • CSRs mandate specifics targets • Scorecards • Aerospace auditors should be auditing for PERFORMANCE by conducting risk-based, process-based audits. Boston, MA July 21-22, 2011 Company Confidential 4 Registration Management Committee (RMC) Typical Formats For Customer Specific Requirements: • Purchase Order (PO), Long Term Agreement (LTA) and/or Contract • Standard Terms and Conditions with PO • Supplier Manual, Management System Requirements Manual • Engineering Drawings • Specifications (product, special processes, material, BOMs) • Scorecards or performance metrics Boston, MA July 21-22, 2011 Company Confidential 5 Registration Management Committee (RMC) What is the Client’s process for getting their arms around CSRs? • Is this part of a process or defined procedure? • Who is responsible? • How do they know they have all relevant documents and the latest revision level? • The integrity of this procedure/process should be tested by the auditor. Boston, MA July 21-22, 2011 Company Confidential 6 Registration Management Committee (RMC) What is Meant by a Process-Based Audit? • Process-based audits are planned in accordance with the processes defined by the organization. • Customer-specific requirements should be integrated into the process-based audit. • They should not be stand-alone items on the audit plan. Boston, MA July 21-22, 2011 Company Confidential 7 Registration Management Committee (RMC) What is Meant by a Risk-Based Approach? • Customer performance data should be used to prioritize audit trails. • Internal and External Customers • Consider the following tools: • V-Cycle • Check-Act-Plan-Do Approach (CAPDo) Boston, MA July 21-22, 2011 Company Confidential 8 Registration Management Committee (RMC) V-Cycle - Covered in the July 30-31, 2009 RMC meeting • Start and end your audit with top management understanding the customer requirements & measurables Top Management Top Management (Requirements, Objectives, Policies Resources) (Improvement Actions and Strategic Decisions) Process Owners Process Owners (Collect and Analyze Information) (Risk Analysis and Planning) Participants (Operations and Recording) Boston, MA July 21-22, 2011 Company Confidential 9 Registration Management Committee (RMC) Check, Act, Plan, Do - CAPDo Approach • Variation on the Plan-Do-Check-Act Cycle – Check: Begin the audit of a given process by asking questions about performance: » What are the customer and other expectations for the process? AS9100 paragraphs 5.2 & 8.2.1 (Measurable) » What is the actual performance? (Measurables/Trends) – Act: How is performance being improve (Corrective Actions/Continual Improvements Plans) Boston, MA July 21-22, 2011 Company Confidential 10 Registration Management Committee (RMC) CAPDo Approach • Variation on the Plan-Do-Check-Act Cycle (continued) – Plan: How was the process planned? Does the process design allow performance objectives to be met? (Internal Management Resources & Goals) – Do – Is the process being executed as designed? – Do staff & operators understand the (customer) expectations for the process? (Goals, Measurables & Customer Satisfaction) Boston, MA July 21-22, 2011 Company Confidential 11 Registration Management Committee (RMC) AS9101 Pre-Data Planning Exercise: • List what customer specific pre-data will help in planning your audit (10 minutes) • List one audit trail for each piece of data (10 minutes) – Generate at least 2 examples • Example: – Customer-specific pre-data: Customer Scorecard – Trail: Ask Top Management what is being done with these data during management review? Boston, MA July 21-22, 2011 Company Confidential 12 Registration Management Committee (RMC) Groups Report Out: Boston, MA July 21-22, 2011 Company Confidential 13 Registration Management Committee (RMC) OEM Customer Specific Requirements (CSRs), Links, Documents and Items to Know Shannon Craddock Boston, MA July 21-22, 2011 Company Confidential 14 Registration Management Committee (RMC) Basics That Should Be Covered to Understand CSRs: • The purchasing document will detail which CSRs are applicable to an order. • Should request that the supplier access the portal or other methods during the audit activity to verify CSRs and revision status. • Look at the scorecards in the portal or other methods in real time. • Ask if they have any OASIS Feedback from their customers? Verify in the OASIS system. Boston, MA July 21-22, 2011 Company Confidential 15 Registration Management Committee (RMC) The Boeing Company – Boeing’s D6-82479, Boeing Quality Management System Requirements for Suppliers, is available at the following link: » http://www.boeingsuppliers.com/supplier/D6-82479.pdf – The following public website has a BQMS FAQ section and other helpful resources: » http://www.boeingsuppliers.com/supQual.htm Boston, MA July 21-22, 2011 Company Confidential 16 Registration Management Committee (RMC) Cessna – Would expect the following items to be considered for auditing based on a review of the Cessna PO as part of the auditing of customer requirements: » Engineer Drawing Revision Level and Parts List Revision Level » OPSS Revision Level (Outside Production Specification Sheet) Boston, MA July 21-22, 2011 Company Confidential 17 Registration Management Committee (RMC) Cessna – Review of quality notes: This review would, at a minimum, lead the auditor to request a copy of CQRS per quality note 11. • Based on a review of CQRS additional audit trails can be determined. Boston, MA July 21-22, 2011 Company Confidential 18 Registration Management Committee (RMC) Cessna » An auditor should pick up on the link to www.supplier.cessna.com which provides numerous audit trails including: • Revision levels of engineering specifications and standard drawings • List of approved special processors and required special process approvals • Terms and conditions • Description of Cessna’s supplier rating process STARS Boston, MA July 21-22, 2011 Company Confidential 19 Registration Management Committee (RMC) Embraer http://www.embraer.com.br/ftp/pub/qualityrequirements Click Boston, MA July 21-22, 2011 Company Confidential 20 Registration Management Committee (RMC) Ball Aerospace & Technologies Corp. – No on-line link for suppliers – Standard Terms & Conditions for reimbursable government contracts Boston, MA July 21-22, 2011 Company Confidential 21 Registration Management Committee (RMC) GE Aviation Engines: • GE - AVIATION QUALITY SYSTEM REQUIREMENTS FOR SUPPLIERS • SUPPLIER SOURCE SUBSTANTIATION • GE-A SUPPLIER REQUIREMENTS FOR CHARACTERISTIC ACCOUNTABILITY, VERIFICATION, AND QUALITY PLANNING Boston, MA July 21-22, 2011 Company Confidential 22 Registration Management Committee (RMC) Honeywell •Honeywell Aerospace Standard Terms & Conditions and Supplemental Purchase Order Conditions (SPOC) Manual is accessible on the supplier portal website, which is password-protected. •Only want suppliers accessing the portal. •Auditors should request that the supplier access the portal when they are on-site auditing. Boston, MA July 21-22, 2011 Company Confidential 23 Registration Management Committee (RMC) Lockheed Martin – Lockheed Martin Space Systems cannot provide documentation as it is considered proprietary. – The existing and soon to be released Lockheed Martin Aeronautics Supplier Quality Requirements are attached here: Quality System Requirements by Commodity Quality System Requirements by Commodity Draft Boston, MA July 21-22, 2011 Company Confidential 24 Registration Management Committee (RMC) United Technologies Corp. • ASQR-01 – Supplier Quality System Requirements (invokes requirements in addition to AS9100 as well as other the ASQR specifications) • ASQR-07.5 – Software Requirements • ASQR-09.1 – Flight Safety Hardware • ASQR-15.1 – Handling, Storage, Packaging and Delivery Boston, MA July 21-22, 2011 Company Confidential 25 Registration Management Committee (RMC) Spirit Aerospace •Two major procurement sites – Wichita and Tulsa – Each site has a unique set of requirements. – Suppliers have these documents available to them through the Spirit portal (SPN), which is password controlled. Boston, MA July 21-22, 2011 Company Confidential 26 Registration Management Committee (RMC) Spirit Aerospace •Spirit Wichita – Has a set of forms known as Procurement Forms (PF) » PF-550 has a general T&C that go to every supplier and is applicable in total. » PF-515 has product-unique requirements that might apply regardless of customer. » PF-515 with a suffix would indicate notes unique to a specific Spirit customer or program. – The purchasing document will detail which specific notes are applicable to an order. Boston, MA July 21-22, 2011 Company Confidential 27 Registration Management Committee (RMC) Spirit Aerospace •Spirit Tulsa – Has 127 total Flysheets – Work much like the PF note sheets out of Wichita, but each one is much more limited in scope •Attached is a listing of Flysheets relative to quality requirements, and a specific example, Flysheet 100. Boston, MA July 21-22, 2011 Company Confidential 28 Registration Management Committee (RMC) Spirit Aerospace - Expectations – Key for an auditor to ask for a copy of the Spirit purchase document and review the general requirements, which would be called out at the top of each of these documents. – Supplier should have an understanding of either the PF Notesheets or Flysheets, have ready access to the applicable documents and have a documented review process or procedure that would ensure all customer requirements have been reviewed. Boston, MA July 21-22, 2011 Company Confidential 29 Registration Management Committee (RMC) Case Study Exercise Shannon Craddock Boston, MA July 21-22, 2011 Company Confidential 30 Registration Management Committee (RMC) • Thinking of a process-based audit that stresses a riskbased approach to auditing use the information provided in the case study to compile the following: – Cite the higher-risk ABC Aviation CSRs that you would sample during your audit. Be prepared to provide justification for your choices by listing the most critical audit trail. Boston, MA July 21-22, 2011 Company Confidential 31 Registration Management Committee (RMC) • Time for this activity: – Working in your groups (20 minutes) – Report out to the other teams (35 minutes) Boston, MA July 21-22, 2011 Company Confidential 32 Registration Management Committee (RMC) Groups Report Out: Boston, MA July 21-22, 2011 Company Confidential 33 Registration Management Committee (RMC) Questions & Answers Thank You Craddock, Shannon SCraddock@pjr.com Miller, Chris chris.miller@eagleregistrations.com Boston, MA July 21-22, 2011 Company Confidential 34