Accelerating the project Edina Nagy Lajos Kiss Szabolcs Hornyák Overview • Introduction • Project acceleration terminology Normal Time, normal cost Crash Time, crash cost Direct Costs Indirect Costs Total Project Cost Optimum Project Duration • Project acceleration principles • References Introduction „When I know all information, only can make a right decisions.” Paulo Coelho Introduction Steps of right decision: Definiate: Time and costs Analysed the possibilities Compare the opportunities Choose the best way Project acceleration terminology Normal Time, normal cost This is the usual time that would be needed to carry out the electrical services work under normal circumstances, estimated at 12 days with a cost of £10.000. Project acceleration terminology Crash Time, crash cost The crash time is the maximum time the operation can be compressed by increasing the resources. Crash time: 8 days Crash cost: £18.000 Project acceleration terminology Cost Slope Project acceleration terminology Activity ranking • Analysed the precedence relationship • Identified the critical activities • Ranking by the cost • Reduce the duration • Define the critical path Project acceleration terminology Direct costs: • Labour • Plants • Materials • Subcontractors • Overheads and profit Project acceleration terminology Indirect costs: • Project supervision • Site hutting and accomodation • Site office telephones, heating and lighting • Vans and site transport Project acceleration terminology Direct costs + Indirect costs Total cost Optimum project duration Project acceleration principles Example – based on a network arrow diagram Project acceleration principles PROJECT DATA Activity Normal Time Normal Cost Crash Time Crash Cost A 6 12 000 4 20 000 B 8 24 000 4 48 000 C 3 18 000 2 20 000 D 6 18 000 4 24 000 E 6 36 000 4 54 000 F 10 10 000 6 50 000 G 5 20 000 3 30 000 H 8 40 000 6 50 000 I 2 20 000 2 20 000 Summation £198 000 Indirect costs £2000 per week Project datas Project acceleration principles Normal time / Normal Cost analysis Project acceleration principles Cost Slope Assessment Activity Normal Time Crash Time Saving in Time Normal Cost (£000) Crash Cost (£000) Increase in Cost (£000) Cost Slope Float Order/ Ranking A 6 4 2 12 20 8 4000 Zero 2nd E 6 4 2 36 54 18 9000 Zero 3rd F 10 6 4 10 50 40 10000 Zero 4th D 6 4 2 18 24 6 3000 Zero 1st B 8 4 4 24 48 24 6000 5 G 5 3 2 20 30 10 5000 3 H 8 6 2 40 50 10 5000 3 I 2 2 0 20 20 0 0 5 C 3 2 1 18 20 2 2000 5 Normal time / Normal Cost analysis Non critical operations Project acceleration principles Revised arrow diagram Project acceleration principles Activity Normal Time (weeks) Crash Time (weeks) D 6 4 2 3000 6000 A 6 4 2 4000 8000 E 6 5 1 9000 9000 Reduction in overall time = Reduction in Time (weeks) Cost slope (£) Increase in direct cost (£) 5 Increase in direct cost due to this reduction in time = 23000 Reduction in project period Total Project Costs at week 23. Direct costs = £198 000 + £23 000 = £221 000 Indirect costs = 23 weeks x £2 000 = £46 000 Total Project Cost £267 000 Therefore, in order to achieve an acceleration of 5 weeks, the project cost will be increased by £13 000, that is: Crash Cost = £267 000 Less Normal Cost = £254 000 Acceleration Cost = £13 000 References - pp. 186-196 Paragraph 9.9 Accelerating the project Thanks…