Peak LAN Project Kirk Baringer Meagan Beeman Allison Benton Yolanda Boyd Thomas Guess Project Information •Peak Systems, located in Meridian, Louisiana •Information Systems Consultants •Project: City of Meridian’s social welfare agency •Goal: to build complete Local Area Network (LAN) •Budget $90,000 to be completed in 26 days Project Team Risk •Team Size •Three people •Team Composition •Project Manager and two interns •Is this enough manpower? Project Team Risk •Team Size •Three people •Team Composition •Project Manager and two interns •Is this enough manpower? Project Team Risk •Team Size •Three people •Team Composition •Project Manager and two interns •Is this enough manpower? Budget Risk •Established budget is $90,000 •Do not cut corners •Cheaper Hardware •Hardware and Software compatibility •Hardware reliability •Is this a realistic budget? Timeline Risk •Project complete in one month •Allot of hardware •Hardware •Locating and purchasing •Delivery •Testing •Multiple suppliers •Is this enough time? External Access Risk •Security •Wired always better •Privacy Act information •Wireless less secure •Physical vs. internet based database •Database corruption User Account Risk •List must be accurate •Names, roles, and permissions •Log on problems •Access problems •Earlier enough in project Risk Assessment •Mapping out risks can be beneficial for a project. •Helps prepare a team for what might occur. •Scenario analysis is the most commonly used technique for analyzing risks. Risk Assessment Matrix Risk Event Team Size Budget Availability of hardware and software Secure external/wireless access User priorities & authorizations can’t log on Likelihood Impact Detection Difficulty When Very High High Very Low Continuous High Very High Low Continuous Moderate High Moderate Installation High High High Installation Low Moderate High Start-up Project Team Risk Risk Management Matrix Risk Event Response Contingency Plan Trigger Team size Add personnel Sub-contract if possible and Workload compared to within budget timeline Budget Increase budget or downsize project Negotiate with the City of Meridian At the earliest point it becomes obvious the budget is too small Availability of hardware and Send bids out to several software suppliers See if extras can be placed on standby and returned if unused From the onset of the LAN project if there are shortages Secure external/wireless access Set up tests to ensure this system is working and secure Have alternate ways for At the earliest point this remote employees to access system can be tested and the server doesn’t work. User priorities & authorizations -can’t log on Have a standby system while transitioning to the new LAN or work weekends and off peak hours Have a secondary server system on standby and don’t take the entire LAN down until the new system is running Who is Responsible Peak Project Manager working with City of Meridian City of Meridian And Peak project manager Peak project manager Peak Project manager At the earliest point the LAN Peak Project manager can be tested, run tests periodically throughout the installation to help catch glitches. Team Size Risk Event Team size • • • • Response Add personnel Contingency Plan Trigger Sub-contract if possible and Workload compared to within budget timeline Who is Responsible Peak Project Manager working with City of Meridian Add personnel if needed Sub-contract if within budget Use the workload compared to the timeline as the trigger Responsibility lies with both, Peak and the City of Meridian Team Budget Risk Event Budget • • • • Response Increase budget or downsize project Contingency Plan Negotiate with the City of Meridian Trigger At the earliest point it becomes obvious the budget is too small Who is Responsible City of Meridian And Peak project manager Increase the budget if possible or downsize the scope Negotiate the budget with the city of Meridian When it becomes obvious the budget is too small - trigger Responsibility lies with both, Peak and the City of Meridian Availability of SW & HW Risk Event Response Availability of hardware and Send bids out to several software suppliers • • • • Contingency Plan See if extras can be placed on standby and returned if unused Trigger From the onset of the LAN project if there are shortages Who is Responsible Peak project manager Send our multiple bids to suppliers of needed SW & HW Research whether extras can be ordered and held/returned If there are shortages this is an immediate trigger The Peak project manager is solely responsible for this Secure external/internal access Risk Event Secure external/wireless access • • • • Response Set up tests to ensure this system is working and secure Contingency Plan Trigger Have alternate ways for At the earliest point this remote employees to access system can be tested and the server doesn’t work. Who is Responsible Peak Project manager Frequently test to ensure the system is working and secure Establish alternate ways for remote employees to access Earliest point system is tested and fails - trigger Responsibility lies with Peak project manager Priorities: Authorizations/user log on Risk Event Response User priorities & authorizations -can’t log on Have a standby system while transitioning to the new LAN or work weekends and off peak hours Contingency Plan Have a secondary server system on standby and don’t take the entire LAN down until the new system is running Trigger Who is Responsible At the earliest point the LAN Peak Project manager can be tested, run tests periodically throughout the installation to help catch glitches. • Stand-by system while transitioning to new LAN • Work weekends and during non-peak hours to test • Establish secondary server for temporary back-up • Test LAN early and often; if it fails - trigger • Responsibility lies with Peak project manager Performing Monte Carlo Simulation • A Monte Carlo simulation helps predict risk by using data to predict trends • Performing a risk analysis will assist both PEAK and the City of Meridian in determining if the LAN project can be completed on time and within budget • Having statistical data will allow the project manager to make sound decisions Benefits of Monte Carlo Simulation • Allows for testing of theories before launching the LAN project • Provides statistical validity to the City by measuring probability that the project will meet its stated goals • Reveals trends that can be modified to decrease risk • Assists the project manager in communicating ways that the project can be restructured for enhanced quality, efficiency and cost Steps to Perform • Define the problem to be solved • Can project be completed on time and within budget? • Define the drivers/variables of the problem • What might some of the delays and hidden costs be? Steps Cont. • Define the uncertainty for the variables • Assign best, most likely and worst case estimates to the identified variables • Analyze the model using simulation • Create a model that will compute the assigned formulas to create estimates •End