February 2014 Scope • Seismic Retrofit of Building • Replacement of three, 40 MW Generating Units • Replacement of all Mechanical and Electrical Systems • Rehabilitation of Tunnels • Regrading Abutment Slope/Road Relocation • Intake Gates/Draft Tube Gate Addition • Architectural Upgrades and Finishes Challenges • Old Facility with Poor Construction Documentation • Confined and Cramped Powerhouse • Operating Powerplant During Construction - Phased Construction 3D Visual Design Aids • 3D Survey – High Definition Survey (Laser Scan) of Powerhouse – TruView – Overlay 3D Point Cloud on Panoramic photo - identify points/ measure distances. • 3D Design – REVIT – 3D Design and Building Information Modeling (BIM) for Powerhouse M&E Design – Navisworks - Clash Detection – Civil 3D – Autodesk 360 – Cloud Rendering High Definition Survey (HDS) - Laser Scan • Triad Associates (Kirkland, WA) – 4 Man Crew • Full Survey - 5 Days • 290 Setups - Inside and Outside • Cost $130,000 • Deliverable- 3D Point Cloud with Leica TruView • 3D Model Generation -$80,000 Benefits • Precision Measurements (± 6 mm) • Full 3D Point Cloud - All Areas • Measurements at your FingertipsFewer Visits to Site • Verification with As Builts - Overlay on Theoretical Model to Identify Discrepancies Powerhouse Point Cloud Fly-Through TruView –Measuring Tool TRUSS IN REVIT MODEL POINTCLOUD • Underwater laser scanner technology by Newton Labs captures as-built measurements with submillimeter precision, as well as being able to quantify cracks, rust, wear, fissures, corrosion, weld deterioration, pitting and other deformities. • Similar in use to air laser scanners, the Newton Underwater Laser Scanner is tuned for the aquatic environment and produces a dense point cloud easily converted into a CAD model using industry standard software. A Model M210UW Underwater Laser Scanner www.newtonlabs.com AUTODESK REVIT (BIM) - 3D Design Tool • • • • • Features & Capabilities I. vs. Parametric Modeling Differences Conventional CAD software Project in aWorkflow single in model I. Minimal inconsistencies views(Views, Schedules, Sheets, …) Benefits II. overEntire Conventional III. and Collaboration II. Worksharing Fully annotatable, understand real world units Use of Features to Aid in Project I.III. Consistent, well-coordinated Design Intelligent objects vs. plain line work Objectdetection oriented, no layer management from user side Clash Cost vs.I.II. Traditional III. II. I.IV. III. II. V. IV. III. Typical Nuisance CADD Issues are handled automatically Visualization Job estimated as conventional design Easy visualization, what you see what you get Phased Construction 3D Design plus training of 4 staff members - met budget Project & data into the model query Extract sortembedded data in a form of database (such as QTO, Future benefits – model available for Contractor use / Plant schedules, sheet index, …) management ELECTRICAL POWER SYSTEM