Click here for presentation

advertisement
Preliminary Agreements in
Tendering
Stanislav Roth
www.sourcelegal.com.au
Focus for today
• Overview of contract formation
• Pre-bid and early works agreements in tendering
www.sourcelegal.com.au
• Law on preliminary agreements
2
Innovative legal outsourcing solutions
Contract formation
Offer /
Acceptance
Certainty /
Completeness
Acceptance must
“mirror” offer
Essential terms
must be certain and
complete
Consideration
Each party
gives something
of value
Intention
Determined
objectively from
text of contract
and parties’
conduct
www.sourcelegal.com.au
Contract
Formation
3
What is a preliminary
agreement?
• Memorandum of understanding
• Letter of intent
• Pre-bid agreement
www.sourcelegal.com.au
• Heads of agreement
• Teaming agreement
• Early works agreement
4
Law on preliminary agreements
Three categories - Masters v Cameron (1954) 91 CLR 353
•
Parties agree on all terms but propose to have them restated in more
•
Parties agree on all terms but have made performance of some of them
conditional upon the execution of a formal contract (binding)
•
www.sourcelegal.com.au
detail in a formal contract (binding)
Parties do not intend to be bound unless and until they execute a formal
contract (non-binding)
5
Law on preliminary agreements
! But important fourth category:
Parties intend to be bound by the terms agreed while expecting a further
formal contract in substitution of the first and containing further terms
(binding)
www.sourcelegal.com.au
•
6
•
“Subject to contract” – not decisive but indicative of “non-binding”
•
Terminology (LOI, MOU, HOA…) - not decisive
•
Objective construction of the language and context (pre- and postagreement communications are relevant)
www.sourcelegal.com.au
To bind or not to bind?
7
•
Useful tool for early partnering
•
May enhance tendering capabilities/credibility
•
Typical issues:
•
Binding or non-binding
•
Exclusive or non-exclusive
•
Future contractual structure:
•
Subcontract (back-to-back terms with head contract?)
•
Joint venture/consortium (beware of the Competition and Consumer Act). If JV, “joint and
www.sourcelegal.com.au
Pre-bid agreements
several” liability to customer is likely - need to consider how liability is apportioned
between JV partners
•
Exit provisions, division of scope, key terms of future contract (e.g. limitation of
liability)
8
Early works agreements
•
Convenient for tight schedule projects – early engineering, long lead
•
May give contractor/supplier leverage
•
Typical issues:
•
Binding or non-binding
•
Scope of work under EWA
•
Payment for work under EWA
•
Applicable terms of contract
•
Timeframe for entering into future contract
•
Termination/exit and applicable payment
www.sourcelegal.com.au
delivery equipment
9
•
Often not clear whether binding or not
•
If binding:
•
•
often incomplete/poorly drafted
•
leave many important matters to future agreement
•
fail to have appropriate exit provisions
•
risk of parties failing to follow through with a proper agreement
If non-binding:
•
why do it?
•
work is performed without contract - unlimited liability, no contractual warranties
etc
•
no certainty of recouping start-up or project cancellation costs
www.sourcelegal.com.au
What’s the matter with preliminary
agreements?
10
Checklist
•
Use
preliminary
agreements
selectively.
Avoid
unnecessary
preliminary
agreements.
Use clear words to indicate whether a preliminary agreement should be binding or
non-binding. Draft the preliminary agreement accordingly.
•
Avoid templates. Every preliminary agreement is specific to the needs of the project.
•
Clearly define what the parties are to do in accordance with the preliminary
agreement.
•
www.sourcelegal.com.au
•
Provide for a framework and timetable for entering into a formal contract and cover
any key terms.
•
Outline what should happen if such contract does not eventuate.
11
Download