Midwest Energy, Inc. Transmission Planning and Expansion Southwest Power Pool Sub-Regional Planning – Area 1 Nathan McNeil Transmission Planning Engineer Introduction to Midwest system • Member-owned cooperative serving 48,000 electric customers in 41 counties of central and western Kansas. • Also serve 41,000 natural gas customers. • 2008 peak load of 330MW total retail and wholesale/municipal load. • 2009 peak of 331MW total load. SPP.org Mwenergy.com 2 Trans Map – Kansas view SPP.org Mwenergy.com 3 Transmission/Generation System Overview • • Assets classified as transmission, pursuant to Attachment AI and as approved by KCC. 230kV: ~ 128 miles 115kV: ~ 457 miles 69kV: ~ 262 miles 34kV: ~ 826 miles Generation totaling 101MW Goodman Energy Center: 75MW Older internal combustion and CTs: 26MW SPP.org Mwenergy.com 4 Key Load Areas • Hays area: commercial, oil field, residential; minimal load growth in most sectors, though oil field load has grown more significantly. • Colby area: Irrigation load has grown rapidly of late due to conversion from natural gas and diesel; other loads in the area are steady. • Great Bend area: Oil field load is growing, as is commercial load; irrigation load is showing minimal growth. SPP.org Mwenergy.com 5 Recently Completed Projects • • City of Larned – Temporary upgrade Interconnection limited by transformer size; necessitated City generate most of the summer. City has been considering construction of new interconnection. Needed additional transformer capacity to avoid running local generation; built temporary interconnection. Storm Damage Repair Over last three years incurred ~$145M in damages from tornadoes and ice storms. Lots of damage to 34kV facilities, and some damage to 115 kV as well. SPP.org Mwenergy.com 6 Large map showing 34kV rebuilds SPP.org Mwenergy.com 7 Recently Completed Projects • Replacement of 115/34kV autotransformer at Rice Co. substation. • Complete replacement of protective relays at Lyons 115kV and Colby 115kV substations. SPP.org Mwenergy.com 8 2009 STEP Projects • • Add capacitors at Kinsley and Pawnee – 2011 Intended to address summer season voltage concerns. Alternate to locating 10MVAR at St. John 115kV sub. HEC to Huntsville 115 kV Rebuild – 2013 • 21.1 miles owned by MIDW, 7.7 miles owned by Westar Huntsville to St. John 115 kV Rebuild – 2014 26.5 miles SPP.org Mwenergy.com 9 SPP.org Mwenergy.com 10 Other Projects • • City of Ellinwood – 2010 Load is currently served from Rice County 115/34.5 kV substation. Will be moved to new 69/34.5 kV substation. 69/34.5 kV transformer delivered. Substation and 34.5 kV line construction underway. Hadley Range 34.5 kV Line Rebuild – 2010 Improved ROW access and increased line capacity. Line serves primarily oil field load northeast of Hays. SPP.org Mwenergy.com 11 Other Projects • • Great Bend to Great Bend North 69kV – 2010 Line already in place; operated normally open. Breakers have been installed, and relaying is being finished to allow normally closed operation. Will help alleviate voltage issues at Hitschmann for contingencies. Improves reliability for substations on radial line. Heizer to Mullergren 115 kV Tie – 2011 Addresses multiple voltage concerns and transformer loading issues. SPP.org Mwenergy.com 12 Other Projects • Spearville – Post Rock (Knoll) – Axtell 345kV Included in SPP Balanced Portfolio NTC’s issued to Sunflower, Midwest, and NPPD ITC Great Plains will construct and own Kansas portion of the 345 kV line and Post Rock 345/230 kV transformer. 345/230 kV transformer sizing and reactive compensation studies are complete. Spearville to Post Rock will be in service by 2012 and Post Rock to Axtell by 2013. SPP.org Mwenergy.com 13 Map showing 345 line SPP.org Mwenergy.com 14 Projects Under Consideration • South Hays – Hays Plant – Vine 115kV May be necessary to avert overloads for loss of either the Knoll 230/115kV XFMR, or the South Hays-Knoll 230kV line. Could be part of a larger project to upgrade distribution in southern part of Hays, requiring re-route of transmission line. SPP.org Mwenergy.com 15 Detail map of Hays transmission SPP.org Mwenergy.com 16 Projects Under Consideration • St. John/Kinsley area Capacitors planned at Pawnee and Kinsley for voltage support on long radial 115 kV line as short-term solution. Multiple looping alternatives being considered for long-term support to the area. Requires significant additional study. Estimated cost $6M $7M+, depending on solution deemed most appropriate and amount of rebuild required. SPP.org Mwenergy.com 17 Projects Under Consideration • Hitschmann area Considering looping Hitschmann 69kV down to North Ellinwood. This solves the voltage issue at Hitschmann for the loss of the Heizer-Great Bend North 69kV line. Requires construction of ~20 miles of 69kV terminating at North Ellinwood. This would also loop the system for customers served from Hitschmann, Bunker Hill and Susank substations on a long radial 69kV line. SPP.org Mwenergy.com 18 Map of 69kv system SPP.org Mwenergy.com 19 Projects Under Consideration • Rebuild/relocate Rice Co. Substation • Substation prone to flooding. At a minimum, need to replace control house to keep out of flood water. Would also require modification of substation equipment to increase elevation above grade. Relays need to be replaced and updated. Considering relocation of substation. City of Larned Work with City on construction of new permanent interconnection. SPP.org Mwenergy.com 20 System Planning - General • As a transmission-owning member of SPP, we participate in the SPP regional planning processes, including model development cycles, STEP processes, etc. • Submit planning data to SPP as required, including EIA411 data for loads and resources. • Also conduct internal studies of local area issues. • Combined distribution and transmission long range plan in progress. SPP.org Mwenergy.com 21 Load & Resource Forecasting • We renew load forecasts for our retail load and firm wholesale loads annually. • Load growth has been modest (approximately 0.7%) annual growth in peak load. • Midwest has traditionally purchased most of its energy resources. Construction of new plant has changed that. SPP.org Mwenergy.com 22 System Modeling • Midwest provides data to SPP and/or updates existing data through MOD: Resources and transactions Transmission topology, ratings, transformers, devices, etc. Generation and Loads • Loads have been separated into owner components for municipals, other utility deliveries, etc. • Reviewing and updating system data, particularly for short circuit modeling SPP.org Mwenergy.com 23 System Planning Contacts • New Interconnections: • Wholesale Services: • System Modeling • Transmission Planning • Engineering & Design SPP.org Mwenergy.com Bill Dowling 785-625-1432 bdowling@mwenergy.com Nathan McNeil 785-650-2551 nmcneil@mwenergy.com Ray Harold 785-650-2552 rharold@mwenergy.com 24 Questions? SPP.org Mwenergy.com 25