Content of Today

Introduction of Claudius Peters

Aerated Distribution System for

Potroom Feeding (ADS) – Basics

Claudius Peters - Outlook for 2015

Introduction of Qatalum

Startup and Tuning - Results

Summary and Outlook 2015

Outlook TMS 2013 for

2014

• FLUIDCON: Attrition factor testing

• ADS: Results of Qatalum Smelter

• AS – System: Commissioning of Boguchany and Results

Introduction – Claudius Peters

Claudius Peters

• Worldwide acting Engineering Company (born 1906)

• Main Business Areas:

Aluminium, Cement, Steel, Gypsum, Power

• More than 550 employees worldwide

• Deliverer for AIRBUS Industries

• Turnover 150 Mio €

• Offices in Germany, USA, France, China, Brazil

UK, Spain, Italy, Romania, Singapore, India

4

The ADS Principle

5

The ADS Principle

6

The ADS Principle

7

Introduction - Who are we?

Qatalum

8

Introduction Qatalum: Our Milestones

2004

December

Heads of agreement

2006

March

Joint venture agreement and approval of feasibility

2007

January

Site p repa ration start-up

July

Final approval

November

Construction commences

October

Investment decision

2009

April

Power from grid

October

First raw material ship

November

Commissioning of cast house

December 18

First Metal from potline

First Export of PFA

2010

January

First EI Export

Fuel gas for power plant gas turbines

Initial power available from power plant

2011

March

Project completion

​September 21

Qatalum achieved full production of

585,000 tonnes

Qatalum: About Us

39 Nationalities at Qatalum

6

2

2

1

1

1

16

239

3

21

34

3 5

1

50

1

1

1

1

15

11

3

9

3

30

1

357

3

98

1

3

172

47

7

Reduction (Potlines) - Qatalum

Designed for low specific energy consumption, high labour productivity, low emissions, no SPL landfill

• Delete text box and insert

Picture/Photo/Figure here

1.2 km

Qatalum

• Delete text box and insert

Picture/Photo/Figure here

Aerated Distribution System in operation since 2009

Qatalum Pot Line Design Parameters

Design Parameter (704 pots)

Name Template

Capacity

Amperage

Number of

Pots

Design 585,000 t/y 300 kA 704

Present Day + 605,000 t/y 314 kA 704

Qatalum ADS Design Parameters

ADS desgin parameters

Design

Present Day

Distribution

Air slide

Inclination Cell Airslide Inclination

50 t/h

100 t/h

1 °

1 °

10 [t/h]

10 t/h

0.5

0.5

°

°

CHALLENGES

Constant Flow into System with varying Material Properties

Silo fluidisation

Silo aeration timing

Material overflow from Silo to Coarse Particle Separator (CPS)

Coarse Particle Separator (CPS) Accessibility & Performance

Air supply nozzles (blockages)

De-aeration of transport system

Fine tuning of operational settings

16

Modifications carried out

• Modification CPS for accessibility

• Repositioning of Level switches

• Conversion of level switches to adjustable types.

• Installation of additional manual valves on 750t secondary alumina silo

• Filling time optimization

Provision of continous venting (2015)

Coarse Particle Separator

Improvements

• Baffle plates for flow control

• Vibrator design

• Silo fluidisation adjustment

• Aeration nozzle size repositioning

• Easier access for daily inspections

18

Coarse Particle Separator- Improvement Results

15

10

5

0

Weekly Count of Coarse Particle Separator (CPS) Failures Causing Material Spills



0

Week

Month

Jul-12

Aug-12

Sep-12

Oct-12

Nov-12

Dec-12

Jan-13

Feb-13

Mar-13

Apr-13

May-13

Jun-13

Jul-13

Aug-13

Sep-13

Oct-13

Nov-13

Dec-13

2

5

4

30

11

5

No. of CPS overflows

26

32

34

28

29

3

3

5

13

0

5

2

19

Other Modifications Carried Out

Modification of CPS for accessibility Repositioning of Level switches on airslides

Installation of adjustable level switches Additional manual valves on alumina silo

20

Verification of Improvements

How the improvements were measured

Alumina spills on CPS

Maintenance cost

- No significant wear can be seen on the airslide fabric

- Spare / Wear parts consumption is extremely low

Timing of aeration system

(Small increaments of 10s resulted in more consistent filling)

21

ADS – Results & Advantages

NO RISK for Potline – Easy catch up after stoppage.

Easy maintenance. Low manpower.

2013 Maintenance cost = 0.126 USD/ton of alumina

Operational activities: Cleaning of CPS and visual inspections!

System availibility is more than 98%;

The buffer silosensures constant material supply to pots.

Dust free system (environmentally friendly)

No accumulation of coarse particles in the system, as material is screened out in the beginning.

Little variations in alumina grain size distribution during conveying

Variations in alumina grain size distribution during conveying

Longest Conveying distance = 280m

100%

80%

60%

40%

20%

0%

Alumina Grain Size Distribution During Conveying (Lab analysis)

-45

+150

-0.020

-0.045 +0.020

-0.075 +0.045

-0.106- +0.075

-0.150 +0.106

-0.200 +0.150

-0.300 +0.200

+0.300

Particle Size Distribution/ Check

Ø 8,1% < 45µm

Ø 8,21% < 45µm

Ø 8,3% < 45µm

Ø 7,9% < 45µm

No Effect on PSD and Anode effect distribution

Material

Number of AE

ADS Maintenance

• No significant wear has been seen on the airslide fabric since the plant startup

• Spare / Wear parts consumption is extremely low

0,25

0,2

0,15

0,1

0,05

0

ADS Annual Maintenance & Operational Cost/ton of Alumina

0,223

0,142

0,126

Dec-09 2010 2011 2012 2013

No Scaling

• No build-up of scales inside

Airslides

• No Coarse particle accumulation.

Lessons Learned

Material Flow from silo

Control of alumina flow out of silo / inlet box by optimization of aeration air.

Coarse particle seperator upgrade

Quality of aeration air/Aeration nozzles

Flushing of the air system before start-up is helpful

Selection of air filtration system for compressed air

Stability of deaeration pressure is crucial for the system operation

Thank you for your attention