MTS Working Group San Francisco F2F Agenda Dec. 9, 2014 Agenda 9:00-9:05a Introductions 9:05-9:30a Summary of Prior Discussions & Objectives for Meeting 9:30-12:00n Optimal Locational Benefits • Presentation 1: Ryan Hanley • Presentation 2: Aram Shumavon 12:00-12:30n Lunch break 12:30-1:30p Optimal Location Benefits 1:30-2:30p Distribution Process Planning Alignment • Presentation 3: Lorenzo Kristov 2:30-3:30p Integration Capacity Planning • Erik Takayesu 3:30-4:00p Wrap-up & Next Steps Morning & afternoon breaks as needed 2 2 Optimal Location Benefits Methodology 3 3 Context: AB327 Distribution Resources Plan • Identifies optimal locations for the deployment of Distributed Energy Resources (DERs) • DERs include distributed renewable generation, energy efficiency, energy storage, electric vehicles, and demand response • Evaluates locational benefits and costs of DERs based on reductions or increases in local generation capacity needs, avoided or increased investments in distribution infrastructure, safety benefits, reliability benefits, and any other savings DERs provide to the grid or costs to ratepayers • Proposes or identifies standard tariffs, contracts, or other mechanisms for deployment of cost-effective DERs that satisfy distribution planning objectives • Proposes cost-effective methods of effectively coordinating existing commissionapproved programs, incentives, and tariffs to maximize the locational benefits and minimize the incremental costs of DERs • Identifies additional utility spending necessary to integrate cost-effective DERs into distribution planning • Identifies barriers to the deployment of DERs, including, but not limited to, safety standards related to technology or operation of the distribution circuit in a manner that ensures reliable service 4 4 Optimal Analysis Optimal analysis based on cost minimization of: • Planning objectives • • • • • Reliability Environmental Policy goals Safety Load serving capacity • • • • • Asset utilization Affordability and cost objectives Resiliency and cyber security Customer choice Streamlined interconnection processes • Societal objectives • Environmental • GHG and local area emissions • Water-energy nexus • Environmental Justice • Low income access to reliable power • • • • • Resiliency impacts Ease of access Job Creation Transportation electrification Regulatory certainty • • • • • • • • • System stability Limits of steady-state analysis Inability to account for uncertainty Protection Power Quality (voltage, etc) • System Constraints Thermal Limits Existing system capacity Operating flexibility Assets and their depreciation/age • Institutional constraints • Technology constraints 5 5 Evolution of DRP Optimal Location Benefits Analysis • What are the immediate benefit categories that can reasonably be evaluated within the next 3 months for the first DRP? No. of Benefit Categories & Sophistication of Analysis • What are the next logical set (and data and tools needed) for systemwide DRPs? Run Jog Walk 2015-1H 2016 Systemwide DRPs incl. Locational Societal Benefits Systemwide DRP including LTPP & TPP locational benefits Visibility & Initial DPA Locational Benefits 2H 2016-2019 2020+ 6 6 Objectives for Discussion • Define avoided cost/benefit buckets to include in July 2015 Utility DRP optimal location analyses • Identify methodology for calculating each avoided cost/benefit bucket • Leverage/adapt existing CA methods where possible • Identify data required for each analysis and its source & availability • Identify linkage to existing CA planning processes 7 7 Avoided Cost Approach for Optimal Location Analysis Ryan Hanley Objectives for July 2015 Optimal Location Analysis • What does this analysis intend to accomplish? • Identify optimal locations for DER deployment • Consider mutually exclusive, collectively exhaustive locational avoided costs and benefits • Illustrate a quantitative spread in DER locational value by utility planning area/substation • What does this analysis NOT intend to accomplish? • Completely replicate the CPUC/RMI/E3 avoided cost methodology • Accurately account for the full value of DER assets (some value components do not differ by location, and so will not be included in this analysis) • Consider only one DER technology type (this analysis is focused on the potential benefits of all/any DER, not a specified technology) • Directly inform pricing for any DER tariffs / markets (tariffs and/or markets may be derived from the insights of this analysis, but this analysis is not a tariff pricing exercise). 9 9 DRAFT Analysis Process (Proposed) Perform Planning Analyses Calculate Potential Avoided Costs $14 Potential Avoided Costs Rank Substations by Avoided Cost $14 $12 $12 $10 $10 $8 $8 Millions Millions Identify DPA & Substations $6 $6 $4 $4 $2 $2 $- Avoided Cost / Substation $- Substation 1 10 10 Background: Avoided Cost/Benefits Studies Reviewed • E3 – Net Benefits of NEM in California (2013) • Rocky Mountain Institute – A Review of Solar PV benefit and Cost Studies, 2nd Edition (2014) • Integral Analytics – Distributed Marginal Price (2014) • Brattle – Value of Distributed Electricity Storage in Texas (Nov 2014) • PG&E – Distribution Planning and Investment and Distributed Generation – 2014 GRC Testimony – Appendix C (2013) • New York – Benefits and Costs (Nov 2014) • Regulatory Assistance Project – US Experience with Efficiency as a Transmission and Distribution Resource (2012) • Regulatory Assistance Project – Big Changes Ahead: Impacts of a Changing Utility Environment (2014) • Regulatory Assistance Project - Designing Distributed Generation Tariffs Well (2014) 11 11 Potential Avoided Cost Approach for DRPs Calculate potential avoided costs/benefits in 6 categories Component Current Granularity Potential DRP Approach Generation Energy + Losses Zonal (utility-specific for losses) Exclude in initial DRP, since system-wide benefit Generation Capacity System value (no use of LRA values) Add Incremental Local RA Wholesale Ancillary Services Statewide Exclude in initial DRP, since system-wide benefit CO2 Emissions Statewide Exclude in initial DRP, since system-wide benefit Avoided RPS Statewide Exclude in initial DRP, since system-wide benefit Transmission Capacity Utility (this is only for Transmission downstream of the CAISO) Exclude in initial DRP, since system-wide benefit 2 Distribution Capacity Capacity Upgrades Utility (SCE, SDGE), climate zone (PGE), substation data was included in NEM report, but data was not made public Use substation-specific planned capacity projects (10 year horizon) 3 Power Quality Voltage Regulation, etc -- Use substation-specific power quality investments 4 Reliability Routine Outages -- Use substation-specific reliability investments 5 Resiliency Major Event Outages -- Use substation-specific resiliency investments 6 Emissions Health Impacts -- Use EPA estimates and industry assumptions by local area Fuel Price Hedge physical hedge -- Exclude in initial DRP, since system-wide benefit Market-Price Suppression reduced wholesale energy prices -- Exclude in initial DRP, since system-wide benefit Societal jobs, etc -- Exclude in initial DRP, since system-wide benefit E3 Framework 1 For WG Consideration DRAFT 12 12 1 Generation Capacity: Incremental Local RA DRAFT • Definition • Avoidable incremental costs incurred to procure Resource Adequacy in CAISO-identified load pockets (i.e. Local Areas) • Cost Calculation Approach • Use latest CAISO local capacity requirements to identify incremental capacity needs beyond utility-owned generation and identify deficient sub-areas. • Examples • Local RA Procurement • PG&E: Needs to purchase Bay Area Local RA at a premium in area to fulfill Local RA requirements 13 13 2 DRAFT Distribution Capacity • Definition • Avoidable costs incurred to increase circuit and/or substation capacity to ensure system can accommodate forecasted load growth • Cost Calculation Approach • Use existing utility capacity 10-year plan by substation, and/or • Perform load forecasting vs. capacity analysis to forecast needed capacity upgrades • Examples • Substation upgrades • Transformer upgrades • Circuit reconductoring 14 14 3 DRAFT Power Quality • Definition • Avoidable costs incurred to ensure power delivered is within required operating specifications (i.e. voltage, flicker, etc) • Cost Calculation Approach • Use existing utility power quality investment plan by substation, or • Allocate systemwide power quality investment plan according to power quality statistics (i.e. customer complaints, voltage excursions, etc) by substation/local area • Examples • Voltage regulation investments • Capacitor banks • Load Tap Changers / Line Regulators • Sensing equipment • Line sensors / relays 15 15 4 Reliability (Routine outages) DRAFT • Definition • Avoidable costs incurred to proactively prevent and mitigate routine outages, and • Avoidable costs incurred in responding to routine outages • Cost Calculation Approach • Use existing utility reliability investment plan by substation, or • Allocate systemwide reliability investment plan according to reliability statistics (i.e. SAIDI, CAIDI, SAIFI) by substation/local area • Examples • Investments / expenses • Distribution Automation (FLISR, etc) • Outage Restoration • Tree Trimming 16 16 5 Resiliency (Major Events) DRAFT • Definition • Avoidable costs incurred to proactively harden the system in order to prevent or mitigate major or catastrophic events (e.g. earthquakes, hurricanes, flooding), and • Avoidable costs incurred in responding to major or catastrophic events • Risk of costs due to Local Capacity Deficiencies in local areas • Cost Calculation Approach • Use existing utility resiliency investment plan by substation, or • Allocate systemwide resiliency investment plan according to societal lost productivity statistics by substation/local area • Identify Sub-Area Local Capacity Deficiencies (according to CAISO) and attribute cost of risk to customers • Examples • Investments / expenses • Hardening (e.g. walls) • Redundant infrastructure • Major Event Response • Sub-Area Local Capacity Deficiency • CAISO identified that the West Park Sub-area in the Kern local area has a 26 MW of deficiency of local generation in the case of a Category B contingency 17 17 6 DRAFT Local Health/Emissions • Definition • Societal healthcare costs caused due to local pollution • Cost Calculation Approach • Use forecasts of local emissions and EPA Societal Cost methodology for health impacts by local area • Examples • Avoided Criteria Pollutant Emissions • • • • • • Nox emissions SO2 Mercury VOC PM 2.5 PM 10 18 18 Next Steps • Define avoided cost/benefit buckets to include in July 2015 Utility DRP optimal location analyses • Develop methodology for calculating each avoided cost/benefit bucket • Identify and share (as needed) data required for each analysis • Develop end-to-end illustrative calculation to serve as model for utility calculations 19 19 Optimal Location Analysis Adaptation of E3 Aram Shumavon Distribution Planning Process Alignment to IOU GRC and State Planning Processes Lorenzo Kristov Bi-annual DPP Alignment w/CA Planning • DRP Scenarios • Use DER adoption scenarios to stress-test existing integration capacity and investment requests in GRC, Smart Grid Roadmaps & EPIC funding requests • DRP Scenarios could show shifting RPS, bulk power, and wholesale generation to DG, and its impacts on the larger system. • 3 scenarios using a) variant of LTPP “Trajectory” case, b) “High DER” customer adoption, and c) expanded policy driven preferred resources case • Time horizons: • 10 years at DPA level regarding scenario driven system-wide locational benefits analysis • Locational benefits conducted at the distribution substation level • Feeder level is too granular as the engineering options are considered at the distribution substation level for time periods >2 years • Net benefit of deferral of traditional capital investment • Net benefit of DER provided operational services (voltage, reactive power, etc.) • Planning assumptions linked to CPUC/CEC inputs to IEPR/LTPP/TPP for consistency, but: • Data and forecasts need to be more granular and linked to distribution infrastructure locations (perhaps a more local forecast required to provide data between the DPP and CEC) • RA contribution from DER • DER considerations for Transmission deliverability analysis • Bi-annual DPP Process timing aligned with CA Joint Agency planning schedules to inform process • Adapt Joint Agency planning process map elements to identify DPP and GRC linkages 22 22 DPP Process Alignment for CPUC, CAISO, CEC • The new DPP should align with the LTPP-TPP-IEPR timeline • Main points to consider: • When is it optimal to have a new DRP, i.e., the final result of the biennial DPP, to feed into the other processes? That is, where on the alignment timeline do we want the DPP to conclude? • What are the key process steps of the DPP, what is the sequence in which they must be performed, and what inputs do they require from other processes? • Currently, first DRP due in July 2015. If July 2017 is the next deadline then: • DRP would provide useful and timely input to the IEPR demand forecast, which is planned to be released in draft form in September 2017 and finalized by December 2017. • Likely that July 2015 DPR will not be as informative for the 2015 IEPR, still we should consider to what extent it will inform that forecast. • CPUC, CECS, and CAISO will collaborate between SeptemberDecember 2017 to develop “assumptions and scenarios” for TPP and LTPP for cycles beginning in January 2018. Developed in consultation with Lorenzo Kristov (CAISO) 23 23 Potential DPP Alignment Map for CPUC, CAISO, CEC Refer to Lorenzo’s Handout 24 24 Integration Capacity Analysis (hosting capacity) Erik Takayesu Back-up Materials 26 Distribution Planning Analyses (summary of prior discussions) 27 27 Distribution Planning Process (DPP) • Two step approach given the short time between ruling and statutory deadline of July 1, 2015 • Focus 2015 Distribution Resource Plan (DRP) on: • Identifying current DER1 “integration” capacity based on existing and near-term planned (i.e., already authorized investments) • Integration capacity is not a single value, but a range of values, it varies with type of DER, level of granularity, and by location. • Comparison of current integration capacity with anticipated DER growth • Prototyping locational benefits analysis for one (1) Distribution Planning Area within each IOU • Refine stakeholder engagement model • Ongoing DPP • Annual distribution system DER integration capacity updates via revised RAM maps • Bi-annual DRP to include system-wide Location Benefits analysis at the substation level that could serve as input into General Rate Cases and inform IEPR/LTTP/TPP processes (Note: the DPP and LTPP/IEPR/TPP have significantly different inputs and outputs but one can inform the other) 1 Term DER includes all forms of Distributed Generation, Demand Response, Energy Storage, Electric Vehicles and Energy Efficiency 28 28 2015 DRP • System-wide DER integration “integration” capacity assessment • Substation level DER integration capacity (minimum level) • • • Engineering analysis based on specific locational (load/DER/feeder) information, not “15% rule” heuristics, recognizing that the unique characteristics of each feeder will determine the integration capacity to integrate DER Comparison of existing & near-term changes to integration capacity to anticipated DER growth Continue to use existing distribution system planning criteria and guidelines, including capacity to support “1-in-10” year heat event and enable adjacent circuit load carrying in the event of circuit outage • Revise Renewable Auction Mechanism (RAM) maps to convey distribution system capacity for DER integration • • Modified RAM maps are convenient means to communicate integration capacity availability Current maps use the static 15% rule, which is no longer appropriate and will require more complete engineering analysis largely completed by IOUs • Locational benefits analysis for one (1) Distribution Planning Area (DPA) as defined uniquely by each IOU • 10 year scenarios (3) driven DPA locational benefits analysis • • • More granular “Trajectory” scenario High DER growth based on customer adoption greater than trajectory Preferred resources growth based on increased use of DER to address bulk power and resource adequacy needs • Locational benefits conducted at the distribution substation level • Results will be used to: • • • Validate scenario and optimal location methodology and processes Use as prototype for biennial DRP process Use to prototype stakeholder feedback on process and results 29 29 Ongoing DPP • Annual updates to feeder level DER integration capacity • IOUs can provide annual updates to feeder capacity and publish via modified RAM maps • Compare existing integration capacity to anticipated DER growth • As in 2015, the engineering analysis will be more sophisticated and will not be based on the static 15% Rule • Bi-annual DRP aligned with GRCs & broader CA planning • • • • • 10 year scenario driven system-wide locational benefits analysis Locational benefits conducted at the distribution substation level DRPs done by each IOU concurrently starting in 2017 Planning assumptions linked to CPUC/CEC inputs to IEPR/LTPP/TPP Bi-annual DPP Process timing aligned with GRC process and CA Joint Agency planning schedules 30 30 Distribution Resource Plan Analyses Analysis Action Scope Granularity Timing Data Req’d Integration Capacity • Existing, available distribution capacity for DER interconnections • 2yr Snapshot-in-time view that also reflects IOU investment plans • Power flow analysis per feeder • Utility to communicate via modified RAM maps 2015 & Ongoing: • All distribution feeders • Feeder level • 2yr outlook • Every year • Tbd by WG Optimal Locations • 10yr Scenario driven analysis • Trajectory • High DER • Preferred Resources • Based on distribution capacity & operational services, transmission capacity, generation capacity & energy, BPS ancillary services, environmental, and other avoided costs/benefits • Planning assumptions linked with CPUC/CEC/IEPR/LTPP/TPP planning • Utility investment plans in GRCs and other reflect DER alternatives based on scenario driven locational benefits analysis • Consider customer DER growth rates independent of central planning • Utility to procure DER services via programs, tariffs, RFOs, etc. • Utility to identify optimal locations via RAM type maps 2015: • One (1) Distribution Planning Area • Substation level by DPA • 10 yr outlook • Every 2 years • Tbd by WG Ongoing: • System-wide beginning in 2017 31 31 Optimal Location Benefits (Discussion slides from 11/18/14 F2F discussion) 32 32 Optimal Locational Benefits Methods IOU Planning for Distributed Energy Resources Discussion led by Will Speer, Erik Takayesu & Manho Yeung 33 Overview • • • • • • Distribution Resource Plan Deployment of Distributed Resources Planning Process Optimal Locations Enhanced Tools and Communication Enabling Infrastructure 34 34 Deployment of Distributed Resources Locational targeting DERs can accomplish two objectives: 1. Maximize reliability benefits and defer capital upgrades 2. Minimize costs and impacts of interconnection Integrating DERs into Planning Process • Distributed energy resources have impacts at each stage of the planning process • Existing methods minimally incorporate DERs • Objective to optimize the use of DERs while maintaining safety and reliability 36 36 Analysis of Recorded Loads Improve ability to disaggregate demand from DER impacts when analyzing recorded loads 37 37 Determine Dependability Evaluate dependability of DERs based on statistical analysis and combinations of DERs 38 38 Develop Forecast Enhance forecasting sophistication by looking at profiles of load and DERs; enabled through new forecasting tools 39 39 Optimization Optimize ability to meet forecast through coordination of DERs with infrastructure upgrades and load transfers 40 40 Optimization Coordinate DER planning with infrastructure upgrades and system reconfiguration • Short term • Evaluate feasibility of DER to meet distribution planning needs beyond the 5 year window • Incorporate optimization by matching the profiles of DER with the peak capacity profile at a substation level • Incorporate optimal locations analysis to target locations projected to require load relief • Longer term – • Evaluate tool capabilities for incorporation DER profiles into project planning, and optimized operational performance • Forecasting of DER penetration / targets • Impact on sub-transmission and transmission grid 41 41 Identifying Optimal Locations Strategically-sited Distributed Energy Resources can provide additional value to the grid. AB 327 requires submittal of a distribution resource plan proposal to identify optimal locations for the deployment of distributed resources Existing public interconnection maps (Fig. 1) will be refined and expanded to better facilitate strategic project siting New layers may provide data on potential system benefits, future projects to alleviate constrained areas, etc. A formal process for updating and maintaining data based on interconnection and planning processes will be established Customer • Enable choice Grid Developer • Maximize DER benefit • Low-cost interconnection Optimal Locations Figure 1: Interconnection Map Overview 42 42 Priority 4 • PV benefit is low • Energy storage benefit is high • No project(s) in 10 year plan • High utilization Priority 2 Priority 3 Priority 1 (Most Optimal Locations) • • • • • • • • • • PV benefit is low Energy storage benefit is high Project(s) identified in 10 year plan (Low) COST (High) Optimal Locations PV benefit is high Energy storage benefit is moderate No project(s) in 10 year plan High utilization (Low) PV benefit is high Energy store benefit is moderate Project(s) identified in 10 year plan BENEFIT (High) Priority 5 (No tangible grid benefit) • PV and energy storage benefits are low • Maximum utilization is less than 80% over the 10-year plan 43 43 Improved Tools • • • • • Enhanced Interconnection Maps Distribution Planning Interconnection Application Processing Distribution Circuit Modeling Grid Management System 44 44 Modernizing the Grid for Safety and Reliability • Enhanced protection capabilities • Decreased loading on assets reduces risk of catastrophic failure • Increased situational awareness allowing for quicker response to outages and system events • Increased ability to remotely operate devices allowing for improved response time 45 45 Grid Modernization Framework Grid Infrastructure Monitor & Control • Grid Management System • DVVC Distribution Modeling DG Interconnection Communications Grid Capabilities 2 - 5 Year • Distribution Planning Planning Software • Demand Side Management Increased Monitoring & Awareness • Fiber Optic Cable Advanced Automation • Licensed/Private Spectrum • Enhanced Wireless Equipment High Speed Radios Field Area Network Advanced Voltage Regulation Expanded Grid Communications Grid Devices Intelligent Grid Ops Management 5-10 Year • Enhanced System Data • Enhanced Field Telemetry Self Healing System RFI External Grid Component Control RCS Capacitor Banks Real-time Grid Assessment 46 • Substation Automation • SLIMS • Distributed Intelligence • DER 46 Optimal Locational Benefits Methods Adaptation of Avoided Cost Framework for Distribution Resource Plans Discussion led by Ryan Hanley & Aram Shumavon 47 47 CPUC Avoided Cost Framework – Background • Framework developed by Energy and Environmental Economics (E3) and adopted by the CPUC • Originally adopted to evaluate cost-effectiveness of energy efficiency by the CPUC in 2004 (Rulemaking 04-04-025) • Subsequently, a Distributed Generation Cost-Effectiveness Framework was adopted by the Commission (D. 09-08-026) • Demand Response Cost-Effectiveness Framework was adopted in 2010 • Periodic updates on all three frameworks since 2010 • Most recent methodology described in October 2013 study “California Net Energy Metering Ratepayer Impacts Evaluation” 48 48 CPUC Avoided Cost Framework – Component Definitions Source: CA NEM Ratepayer Impacts Evaluation, Oct 2013 (E3) 49 49 Hourly Forecast of Avoided Cost by Component 50 Monthly Forecast of Avoided Cost by Component Source: CA NEM Ratepayer Impacts Evaluation, Oct 2013 (E3) 51 51 Ranked Hourly Avoided Costs (Nominal $ over 20 years) Source: CA NEM Ratepayer Impacts Evaluation, Oct 2013 (E3) 52 52 Annual Forecast of Avoided Cost by Component Source: CA NEM Ratepayer Impacts Evaluation, Oct 2013 (E3) 53 53 Total Avoided Cost by Feeder/Substation (20-year NPV) $4,250 20-year NPV of Electricity ($ /MWh) $4,000 $3,750 $3,500 $3,250 $3,000 $2,750 $2,500 Source: CA NEM Ratepayer Impacts Evaluation, Oct 2013 (E3) 54 54 For WG Consideration E3 Framework Potential Adoption Approach for DRPs Component Current Granularity Potential DRP Approach Generation Energy + Losses Zonal (utility-specific for losses) Use CPUC model assumptions System Capacity System value (no use of LRA values) Use CPUC model assumptions Ancillary Services Statewide Use CPUC model assumptions CO2 Emissions Statewide Use CPUC model assumptions Avoided RPS Statewide Use CPUC model assumptions Transmission Capacity Utility (this is only for Transmission downstream of the CAISO) Use CPUC model assumptions Distribution Capacity Utility (SCE, SDGE), climate zone (PGE), substation data was included in NEM report, but data was not made public Use Utility Capacity Projects (5-10 Yr Plans) plus CPUC assumption on Yr 10+ planning Additional A/S Volt/VAr, etc -- Use industry assumptions (i.e. Sandia National Labs) Fuel Price Hedge physical hedge -- Use NREL assumptions Market-Price Suppression reduced wholesale energy prices -- Use NREL assumptions Reliability Routine Outages -- Use utility SAIDI statistics + Value of Service assumptions (Brattle Report, etc) Resiliency Major Event Outages -- Use industry assumptions (i.e. Department of Energy) Emissions Health impacts -- Use industry assumptions Societal jobs, etc -- Use industry assumptions 55 55 Methodology for Avoided Cost Component Forecasts Source: CA NEM Ratepayer Impacts Evaluation, Oct 2013 (E3) 56 56 Analysis for Integrated DER Avoided Cost study Source: Methods for analyzing the benefits and costs of distributed PV, Sept 2014, NREL 57 Optimal Locational Benefits Methods Integral Analytics Approach Discussion led by Dave Erickson 58 58 Integration of Average Costs (E3) & Local Granular Costs for an Optimal DRP Detailed Usage & Service Transformer Analytics Local “penalty” reverse flow, granular supply cost to serve Overnight Reconciliation AMI KW KVAR Customer DER Savings Shapes Local Customer/ Vendor Response Rational price response yields optimal DRP. If not, next annual DRP DMCs adjust price signals. Last resort, mandate locations for DER types. Fixed DMC/ Yr Variable DMC CYMEDist (by bank) Losses, Voltage, PF Limiting Factors Other Costs Acre Level Load Forecast snaps to CYME “node” or circuit section Sharing of DER vendor plans ? Local DMCs or DMPs Shadow price of the optimization/ DRP per bank for customer/ acre Sub-5 Minute DER Smart Inverters Zigbee HAN Storage Thermal Inertias, etc. Intra Hour Forecasting Optimal DER mix 10 Year Sub-hourly Modeling 20 Year Congestion Forecast (update LMPs) Existing Averaged Avoided Costs (E3) “Global” Anchors the local granular avoided costs Supply/Grid Used to “center” the granular DMC detail and distributions. Blending occurs at banks in most cases. Source of “dotted line box” is More Than Smart Working Group: Methods for analyzing the benefits and costs of distributed PV, Sept 2014, NREL 59 Geo-Spatial Forecasts (acre, circuit, bank) Only a geo-spatial view with econometric methods is able to forecast local, granular needs & new resources. New DERs, Commuter Rail, EV, or anything where change or locale is not in past data history. Data Types and Sharing Process 60 60 Proposed Data Types Parties EDF ` Basic demographics Populations of electricity using equipment EV and communical charging station populations BUG populations and characteristics Relevant generation production characterisitcs Distribution peak and load characteristics SDG&E x x x x x x PGE SCE x Cal SEIA Customer class-level load patterns and expenditures CESA Solar City x CAISO Petra x x x x List of distribution system expenditures Data Type NRG x DMP and DPC (Distribution Marginal price & cost) analysis by feeder x x x x DG Interconnection process information Local Capacity requirements from the annual TPP Planning forecasts: Identifying capacity constraints x DER data - Relating to its penetration, functionality, and performance x x Optimal Location Maps x x x x x x x x x Solar PV RAM Map x Real-time customer electric meter data Source: CPUC (http://www.cpuc.ca.gov/PUC/energy/Distribution_Resources_Plan_Comments.htm) 61 61 Proposed Data Types Available Today Available Over Time Inputs • • • • • Basic Demographics Populations of Electricity Using Equipment BUG population and characteristics List of distribution system expenditures DG interconnection process information • • • • • EV and communication charging stations Relevant generation production characteristics Distribution peak and load characteristics Customer class level load pattern and expenditures DER data—relating to its penetration, functionality, and performance Outputs • Local capacity requirements from the annual TPP Solar PV RAM map • DMP and DPC (Distributed Marginal Price and Cost) analysis by feeder Planning forecasts (identifying capacity constraints) Real-time customer electric meter data Optimal location maps • • • • Source: CPUC (http://www.cpuc.ca.gov/PUC/energy/Distribution_Resources_Plan_Comments.htm) 62 62