NMDWS UI Modernization PCC June 20, 2012 Status - 93 Calendar Days left until Go-Live - Everyday is a work day for certain employees - All work in progress - uFACTS UAT VOSS Development IVR Development Transition Planning Communication Planning Phase IV – Program Integrity – Final Coding Stages 2 July 25th 2012 – Go/No Go Decision #1 - Qualifications - UAT Complete Interface Testing Complete Infrastructure Stress Test Complete Converted Data that has fallen out meets Secretary Bussey’s tolerance thresholds and operating procedures for handling those errors have been determined. - Next Steps - Begin Blitz Communication to Legislature, Employers, Claimants, Third Party Administrators, and data sharing partners (HSD, TRD, DFA, USDOL, etc.) - Begin agency line staff training on the system - Clear defect queues. 3 August 17th 2012 – Go/No Go Decision #2 - Qualifications - All blocking/critical defects have been cleared, regression tested, and closed - Agency has successfully completed a two week operability test – can DWS operate uFACTS Sept 1st, (business and IT) - Completed transition planning, operating procedures in place for putting down mid-stream working and picking it up on the other side. - Next Steps - Continue Blitz Communication – Alert Claimants to certify by COB August 27th in preparation for Go-Dark - Continue agency line staff training on the system - Setup War Rooms (developer, infrastructure, business analyst) 4 August 26th 2012 – Go/No Go Decision #3 - Qualifications - Training Complete IVR Complete VOSS Complete uFACTS Complete Transition Complete Communication Complete - Next Steps - Prepare for shut down - Run Final legacy payment batch for processing through Wells Fargo 5 August 31th 2012 – Go/No Go Decision #4 - Qualifications - Has data conversion completed successfully - Have all employer, claimant, and agency accounts been properly moved to the new environment - Have URLs/Firewall Ports/DNS/LDAP been successfully changed - Next Steps - Prepare for Smoke Testing 6 September 1th 2012 – Go/No Go Decision #5 - Qualifications - Smoke Test completed successfully - IVR Integration completed - VOSS Integration completed - Next Steps - Prepare for release to the public - Final Go/No Go Decision Point, once the public begins using the system there is no turning back! - Monitor application, run batches for September 2nd/3rd (offices closed for Holiday weekend) - Prepare for heavy call volume September 4th all hands on telephone calls - War Rooms/Floor Walkers Senior Management monitoring progress, fielding Governor/Media calls 7 Project Certification Change Request - IVR - In order to successfully handle the uFACTS workload additional ports and funcationality will be required in our IVR system. - Project has been scheduled, DWS has been developing a detailed SOW and creating exact specs for Century Link - $172,085 for the initial setup, will increase the monthly cost to ~$75K per month - Discussing future IVR changes with DoIT based on funding availability 8 Request • Requesting release of additional funding $172,085 funding for IVR • Questions? 9