Overview of January 6 EEA Event Chad Thompson Manager, Operations Support ROS ERCOT Public March 6, 2014 Event Summary – January 6, 2014 • At 6:52, ERCOT declared Level 1 of its Energy Emergency Alert (EEA) and declared EEA Level 2 at 7:01, primarily due to the loss of a number of generating units • Non-Spin Reserve Service (NSRS), Load Resources (LR) and Emergency Response Service (ERS) were deployed, but firm load shed was not required • ERCOT moved from EEA2 to EEA1 at 7:51 and resumed normal operations at 9:12 • Generation outages & derates peaked at 9355 MW just before 07:00, with 3541 MW due to weather • Hourly peak demand was 55,487 MW for HE08 and instantaneous peak demand was 56,478 MW at 07:08:24 2 Timeline – January 6, 2014 EEA ERCOT issued EEA Level 1 for PRC below 2300 MW ERCOT issued EEA Level 2 for PRC below 1750 MW Watch issued due to PRC below 2500 MW 06:37 AM 06:42 AM 06:52 AM 06:42 AM 06:52 AM 07:01 AM 07:51 AM ERCOT recalled EEA Level 2. EEA Level 1 remains in effect 07:56 AM ERCOT recalled 30 minute ERS 07:58 AM ERCOT recalled 10 minute ERS. 06:57 AM 07:02 AM ERCOT deployed Non-Spin for 187 MW ERCOT deployed Group 1 RRS for 546.36 MW ERCOT deployed RRS to Generators for frequency below 59.91 Hz ERCOT deployed Group 2 RRS for 536.24 MW ERCOT deployed 30 minute ERS for 111.68 MW 07:05 AM 07:43 AM ERCOT deployed 10 minute ERS for 508.72 MW 07:13 AM ERCOT recalled all RRS from Generators due to frequency above 59.91 Hz ERCOT recalled all Group 2 RRS 07:50 AM ERCOT recalled all Group 1 RRS EEA Level 1 cancelled. Watch remains in effect. Watch terminated as PRC was above 3000 MW 09:12 AM 09:55 AM 08:10 :36 AM ERCOT recalled all NonSpin 08:10:48 AM ERCOT deployed RRS to Generators for frequency below 59.91 Hz 08:17 AM ERCOT recalled all RRS from Generators due to frequency above 59.91 Hz 3 EEA Steps EEA procedure in the ERCOT Protocols defined by levels 1 Maintain 2,300 MW of on-line reserves 2 Maintain 1,750 MW of on-line reserves. Interrupt loads providing Responsive Reserve Service. Interrupt loads providing Emergency Response Service (ERS). 3 Maintain System frequency at or above 59.8 Hz and instruct TSPs and DSPs to shed firm load in rotating blocks. 4 Event Highlights • Weather was warmer than February 2 2011 • Load and Wind Forecast error were within acceptable margins • 9355 MW forced out/derated/failed to start by HE07; 3541 MW due to weather, and 2468 MW planned out & 2938 MW forced out going into the operating day (14,761 MW) • 97 units experienced forced outages/derates, or failure to start from 00:00 to 23:59 on 1/6/14 • 1 unit committed in DRUC, no units committed in HRUC • Responsive Reserve from generation was deployed in response to low frequency events • Load Resource performance was 94 % • SCED was able to manage congestion 5 Forecast Comparison • Weather was warmer than February 2, 2011, and cooler than January 7 when the load was higher (57,277 MW) • MTLF MAPE was 2.29 % for the day (metric is 3.5-4%) • WPF Error was 8.1 % for the day (2013 average was 8.3%) Dallas Temp 2-Feb-11 6-Jan-14 EEA2 56,031 MW Load HE20 7-Jan-14 13/14 Winter Peak 57,277 MW Load HE08 5AM 6AM 7AM 8AM 5AM 6AM 7AM 8AM 5AM 6AM 7AM 8AM Houston Austin San Antonio Brownsville Midland Wind Temp Wind Temp Wind Temp Wind Temp Wind Temp Wind 14 17 22 10 18 20 20 13 34 18 9 17 14 15 21 14 19 17 20 20 33 13 8 15 14 20 21 16 19 18 20 17 33 20 7 16 13 20 22 18 19 18 20 16 33 16 7 16 2 7 6 -8 7 3 11 -2 10 3 7 4 2 2 7 1 5 2 10 4 10 -2 8 2 1 12 6 0 3 3 8 3 9 6 7 3 4 11 5 9 3 5 7 1 9 -1 7 4 8 8 1 5 0 20 5 13 5 9 11 17 8 6 3 14 -4 13 4 20 7 5 12 9 7 11 3 16 -3 18 4 17 8 12 14 9 8 11 1 14 -4 18 4 16 9 9 14 10 Temperature values shown indicate degrees warmer at this time than same time on 2/2/2011 Wind values shown indicate MPH higher wind on 2/1/2011 than at this time 6 Generation Outages Note: This does not include outages which occurred before midnight on January 6 7 Generation Outages Note: This does not include outages which occurred before midnight on January 6 8 Reserves 9 6000 60.1 5000 60.05 4000 60 3000 59.95 2000 59.9 1000 59.85 0 06:00 06:30 07:00 07:30 08:00 08:30 09:00 09:30 Frequency (Hz) Pyhsical Responsive Capability (MW) Frequency & Physical Responsive Capability 59.8 10:00 Operating Hour Physical Responsive Capability Frequency 10 Ancillary Services • ERCOT manually deployed Non-Spin from 6:42 to 8:10 • Load Resources were manually deployed with a 94 % overall performance • Responsive Reserve from generation was deployed form 6:37 to 7:13 and again from 8:10 to 8:17 • one unit (319 MW) was committed in HRUC 11 Congestion • There were as many as 17 constraints active in SCED between 05:00 and 12:00 on January 6 • SCED was operational and able to manage congestion during this event Operating Day January 6 2014 Constraint Contingency Description D_NBCBY5 : HB_TWG66_A Northbelt - King / Cedar Bayou 345 kV Double-Circiut DNAVLEG5 : 40__A Navarro - Limestone 345 kV Double-Circuit DSAMTHS5 : WHTNY_FMR2 Sam Switch - Tradinghouse 345 kV Double-Circuit DTRSTRC5 : TRSES_MR6L Trinidad - Watermill / Tricorner 345 kV Double-Circuit DWH_STP5 : BONIVI_RINCON1_1 White Point - Lon Hill / STP 345 kV Double-Circuit DWLV89N8 : 3410__A West Levee - 800/900 Network 138 kV Double-Circuit SCOLPAW5 : COLETO_KENEDS1_1 Coleto Creek - Pawnee 345 kV Single-Circuit SDQNB8 : HB_TWG66_A Drilco - Northbelt 138 kV Single-Circuit SI_DI_38 : I_DUPP_I_DUPS1_1 Ingleside Dupont Switch - Dupont PP1 138 kV Single-Circuit SKOCNU28 : GILA_HIWAY_2_1 Gila - Koch Up River 138 kV Single-Circuit SLAQLOB8 : BRUNI_69_1 Lobo - La Quinta 138 kV Single-Circuit SORNLON8 : LON_HI_SMITH1_1 Lon Hill - Orange Grove 138 kV Single-Circuit SPAWCAL5 : COLETO_KENEDS1_1 Calaveras - Pawnee 345 kV Single-Circuit SSALSK28 : 6146__A Skywest - Salt Flat 138 kV Single-Circuit SSHBMLS5 : ELKTN_SD1_1 Martin Lake - Shamburger Switch 345 kV Single-Circuit STRSWTR5 : TRSES_MR6L Watermill Switch - Trinidad 345 kV Single-Circuit XLY2T58 : LYTTON_S_AT1H Lytton Springs 345/138 kV Autotransformer # 2 Constrained Element Humble - Treaschwig 138 kV Line Big Brown - Jewett 345 KV Line Whitney 138/69 kV Autotransformer # 2 Trinidad 345/138 kV Autotransformer Bonnieview - Rincon 69 kV Line East Levee Switch - Reagan Street 138 kV Line Coleto Creek - Kenedy Switch 138 kV Line Humble - Treaschwig 138 kV Line Ingleside Dupont Switch - Dupont PP1 Ingleside 138 kV Line Gila - Hiway 9 138 kV Line Bruni 138/69 kV Autotransformer Lon Hill - Smith 69 kV Line Coleto Creek - Kenedy Switch 138 kV Line East Midland - Midland East 138 kV Line Elkton Series Reactor 138 kV # 1 Trinidad 345/138 kV Autotransformer Lytton Springs 345/138 kV Autotransformer # 1 12 Next Steps • ERCOT and Texas RE requested additional information from generators on causes of generator trips and derates on January 6 • This additional information resulted in outaged/derated MWs changing since the TAC report on Jan 28 • ERCOT has (re)visited 4 of the units who initially reported weatherrelated issues on January 6 to review winterization plans • ERCOT had already requested data to improve accuracy of wind forecast during icing and cold weather from wind generators due to November 2013 cold spell; need to add temperature limits to RARF • Enhance procedures to directly consider increased generating capacity unavailability for unit commitment during severe cold weather events • Reassess outage calculations used for future SARA reports to ensure derates are appropriately included • Improve means to get updated information on generation derates and startup failures to ERCOT in near-real time 13 Next Steps Questions 14