Seg2510 – Management Principles for Engineering Managers
Lecture 5
Present-Worth Analysis
Department of Systems Engineering and Engineering Management
The Chinese University of Hong Kong
1
Part I – Review of the Last Lecture
2
Some Terminologies
•
•
•
•
•
•
•
•
Consumer Price Index (CPI)
Average inflation rate
General inflation rate
Actual dollars
Constant dollars
Market interest rate (i)
Inflation-free interest rate (i’)
Present worth of actual dollars:
– Deflation method
– Adjusted-discount method
i = i '+ f + i ' f
Pn =
=
An
[(1 + f )(1 + i ' )]n
An
(1 + i ) n
3
Part II – Alternatives Analysis
4
Measures of investment worth
•
•
Screening projects to ensure the right investments are made
Financial evaluations of investment proposals
– Present-worth analysis
– Annual cash flow analysis
– Rate-of-return analysis
•
•
•
Use equivalence techniques to measure economic worth
To compare alternatives on an equal basis
To select the wisest alternative from an economic standpoint
Note:
•
Assumptions:
– We will focused on before-tax situations.
•
•
–
–
net cash flows can be viewed as before-tax values or after-tax values
Before-tax situation is common for organizations not subjected to tax (e.g. government and
nonprofit organizations).
Cash flows are in actual dollars.
Interest rates are market interest rates.
5
Loan versus Project Cash Flows
•
Loan cash flow
– interest plus repayment of the principal
•
Project cash flow
• Future earnings, capital expenditures and annual expenses
6
Initial Project Screening Methods
•
To screen capital investments before progressing to other analysis
– Whether & when the money invested can be recovered
•
Payback method
– How long it takes for the net receipts to equal investment outlays
•
Payback period
– Determined by adding the expected cash flows for each year until the sum
is equal to, or greater than, zero.
• Payback point
– The cumulative cash flow equals zero
» Cash inflows exactly match or pay back the cash outflows
– Conventional-payback method
• Ignoring time-value-of-money
– Discounted-payback method
• Including time-value-of-money
– A project does not merit consideration unless its payback period is shorter
than some specified period of time.
•
If the payback period is within the acceptable range, a formal project
evaluation may begin.
7
Payback Method – An Example
•
Find Conventional-payback period
8
Payback Screening
•
Benefits
– Simplicity
– Reduces the information search by focusing on that time at which the firm expects
to recover the initial investment
– Reducing the need to make further analysis efforts on those eliminated alternatives
•
Drawbacks
– Fails to measure profitability
• It assumes that no profit is made during payback period
– Fails to recognize the difference between the present and future value of money
• It ignores differences in the timing of cash flows
– It does not allow for the possible advantages of a project with a longer economic
life
• It ignores all proceeds after the payback period
9
An Example
n
Project 1
Project 2
0
-$10,000
-$10,000
1
$1,000
$9,000
2
$9,000
$1,000
3
$1,000
$1,000
Payback period
2 years
2 years
10
Discounted-Payback Period
•
Consider the time value of money
–
•
Cost of funds (interest) used to support the project
Discounted-payback period
–
The number of years required to recover the investment from
discounted cash flows
11
An Example
•
Assuming the firm’s cost of funds to be 15%, find the discounted-payback
period
Period
Cash Flow
0
-$85,000
1
$15,000
2
$25,000
3
$35,000
4
$45,000
5
$45,000
6
$35,000
Cost of Funds (15%) (unrecovered
beginning balance x interest rate)
Cumulative Cash
Flow
$76,778
12
Present-Worth Analysis
13
Present-Worth Analysis
• Discounted cash flow techniques (DCFs)
– Net-present-worth (PW) method
• PW criterion
– The present worth of all cash inflows associated with an investment
project is compared with the present worth of all cash outflows associated
with the project.
– Net Present Worth (PW)
• The difference between the present worths
• Determines if a project is an acceptable investment
• Select the best project by comparing the PW figures
14
Net-Present-Worth Criterion –
Evaluation of a Single Project
• Step 1:
– Determine the interest rate the firm wishes to earn on its investments
• The rate at which the firm can always invest the money in its investment pool
• Required rate of return or Minimum attractive rate of return (MARR)
– Assume single rate of interest over the life of a project when calculating PW
• Step 2:
– Estimate the service life of the project
• Step 3:
– Estimate the cash inflow for each period over the service life
• Step 4:
– Estimate the cash outflow for each period over the service life
• Step 5:
– Determine the net cash flows for each period
• Net cash flow = cash inflow – cash outflow
15
Net-Present-Worth Criterion –
Evaluation of a Single Project (cont’d)
•
Step 6:
– Find the present worth of each net cash flow at the MARR.
– The project’s PW
• Sum of the present-worths
PW (i ) =
A0
A1
A2
AN
+
+
+
+
...
(1 + i ) 0 (1 + i )1 (1 + i ) 2
(1 + i ) N
N
An
n
n = 0 (1 + i )
=∑
N
= ∑ An ( P / F , i, n)
n=0
• Where
–
–
–
–
PW(i) = PW calculated at i,
An = net cash flow at the end of period n,
i = MARR (or cost of capital), and
n = service life of the project
– An will be positive if the period has a net cash inflow, and negative if the period has
a net cash outflow.
16
Net-Present-Worth Criterion –
Evaluation of a Single Project (cont’d)
• Step 7:
– Decision rule
• If PW(i) > 0, accept the investment.
• If PW(i) = 0, remain indifferent.
• If PW(i) < 0, reject the investment.
17
Net-Present-Worth Criterion –
Comparing More Than One Alternative
• Guidelines
– For selecting the best alternative, select the one with the highest PW (if all
have the same service lives)
– Perform cost-only basis for comparison of mutually exclusive alternatives
with the same revenues
• Accept the project with the smallest PW of costs, or the least negative PW
(minimizing costs)
18
An Example
•
•
Tiger Machine Tool Company is
considering the acquisition of a
new metal-cutting machine. The
cash flows for a three-year project
are:
What is the economic merit of the
acquisition?
End of Year
Net Cash Flow
0
-$75,000
1
$24,000
2
$27,340
3
$55,760
Answer: $3,553
19
Selecting a MARR
• The decision to accept or reject an investment is influenced by the
choice of MARR, so it is crucial to estimate the MARR correctly.
• Return
– To evaluate how investments in financial assets or projects are doing in
relation to each other and to the performance of investments in general.
• Rate of return
– Function of the following components:
• Risk-free real return
• Inflation factor
• Risk premium(s)
20
Selecting a MARR
21
Net Present Worth
• Investment-Pool Concept
– A firm’s treasury
• Funds in this investment pool can earn interest at the MARR
• Borrowed-Funds Concept
22
Investment-Pool Concept – An Example
•
Tiger Machine Tool Company is
considering the acquisition of a
new metal-cutting machine. The
cash flows for a three-year project
are:
End of Year
Net Cash Flow
0
-$75,000
1
$24,000
2
$27,340
3
$55,760
– If a firm did not invest in the project & left the $75,000 in the investment
pool for 3 years, the fund will have grown to:
$75,000( F / P,15%,3) = $114,066
23
Investment-Pool Concept – An Example
– If a firm did invest in the project, the cash inflows can return to the
investment pool to earn interest at a rate of 15%.
– The returns after reinvestment are:
$24,000( F / P,15%,2) = $32,269
$27,340( F / P,15%,1) = $31,441
$55,760( F / P,15%,0) = $55,760
Total = $119,470
– The additional cash accumulation after 3 years from investing in the project
is:
$119,470 − $114,066 = $5,404
24
Borrowed-Funds Concept – An Example
•
•
Assume a firm borrows all its capital from a bank at an interest rate of 15%, and
invests in the project and uses the proceeds from the investment to pay off the
principal & interest on the bank loan.
How much is left over at the end of the project period?
N
0
1
2
3
Beginning Balance
-$75,000
-$61,850
-$43,788
Interest (15%)
-$11,250
-$9,278
-$6,568
Payment Received
-$75,000
+$24,400
+$27,340
+$55,760
Project Balance
-$75,000
-$61,850
-$43,788
$5,404
(net future worth)
PW(15%) = $5,404(P/F, 15%, 3)=$3,553
25
Comparing Mutually Exclusive Alternatives
• Mutually exclusive alternatives:
– Any one of the alternatives will fulfill the same need
– The selection of one alternative implies that the others will be excluded
• A fundamental principle
– Mutually exclusive alternatives must be compared over an equal time span
• Case 1
– Analysis period equals project lives
• Case 2
– Analysis period differs from project lives
26
Do-nothing alternative
•
If project aims to replace an existing asset or system or is a new endeavor, a
do-nothing may alternative exist.
– If none of the proposals are feasible, then do nothing.
•
For the option of retaining an existing asset or system
– Generate cash flows of the new proposals relative to those of the do-nothing
alternative
– Find the incremental costs relative to those of the do-nothing alternative
•
For the replacement problem
– Incremental cash flows
• Subtracting the do-nothing cash flows from those of each new alternative
•
For new endeavors
– Incremental cash flows
• Absolute amounts associated with each alternative (since the do-nothing values are all
zero)
•
Note: otherwise stated, it is assumed that doing nothing is not an option.
27
Service Projects versus Revenue Projects
• Service projects
– Projects that generate revenues that do not depend on the choice of
project, but must produce the same amount of output (revenue).
– Minimize expenditures
• PW criterion
– Choose an alternative with the lower present-value production cost over
the service life
• Revenue projects
– Projects that generate revenues that depend on the choice of
alternative
– Select the alternative with the largest net gains (output-input)
• PW criterion
– Select the one that bring in the largest net present worth
28
Analysis Period Equals Project Lives
•
•
Compute the PW for each project
Select the one with the highest PW
29
An Example
• Ansell, Inc., a medical-device manufacturer, has two options in
addressing the problem of the leaks in the current system. The leaks
cause the compressor to run 70% of the time, and hence requires
excessive usage of 260 kWh of electricity at a rate of $0.05/kWh (the
plant runs 250 days a year, 24 hours a day).
– Option 1: Continue current operation
• The compressor’s run time will increase by 7% per year for the next 5 years.
• After 5 years, the system has to be replaced.
– Option 2: Replace old piping now
• Cost $28,570
• The compressor will run for the same number of days, but run 23% less.
– The interest rate is 12% compounded annually, is it worth fixing the
system now?
Answer: Option 2
30
Analysis Period Differs from Project Lives
• Case 1
– Project’s life is longer than analysis period
• Analyze each project only for as long as the required service period
• Unused portion of the equipment – Salvage value
• Salvage value
– The amount of money for which the equipment could be sold after its service to the
project has been rendered or the dollar measure of its remaining usefulness
• Case 2
– Project’s life is shorter than analysis period
• Consider how, at the end of the project lives, the rest of the required service
period can be satisfied
• Replacement projects may be needed
– Additional projects to be implemented when the initial project has reached the
limits of its useful life
31
Case 1: An Example
•
Waste Management Company (WMC) has won a contract of two years.
There are two possible models of machines that WMC could purchase to
perform the task.
– Model A costs $300,000, and will be operable for three years, and at the end of
that time, the salvage value will be $50,000.
• Operating cost: $80,000 per year
– Model B costs $480,000, and will be operable for 6 years. The estimated
salvage at the end of year 6 is $60,000.
• Operating cost: $45,000 per year
– After two years, the model A could be sold for $90,000, and model B for
$250,000.
– Assuming the firm’s MARR is 15%. Which option is acceptable.
Answer: Model A
32
Case 2: An Example
•
The Smith Novelty Company, a mail-order firm, wants to install an
automatic mailing system. The firm has a choice between two machines.
– Model A costs $12,500 and will last 3 years.
– Model B costs $15,000 and will last 4 years.
Neither of the models may be able to handle the
Expanded volume of business at the end
Of year 5.
At MARR=15%, which model should the firm
select?
N
Model A
Model B
0
-$12,500
-$15,000
1
-$5,000
-$4,000
2
-$5,500
-$4,500
3
-$6,000
+$2,000
-$5,000
4
-$5,500
+$1,500
Suppose the remaining of required service period 5
can be met by leasing comparable equipment
that has an annual lease payment of $5,000, with operating cost of $6,500.
Answer: Model B
33
•
References
– Chan S. Park, Fundamentals of Engineering Economics. Prentice Hall
– Lecture 9: Inflation, by Gabriel Fung