Project Management Notes
1. Estimates should include a normal level of contingency is NOT one of the recommended guidelines for
developing useful work package estimates.
2. The requirement for a freshly poured foundation to cure before beginning construction is an example of a Finish
to Start type of lag.
3. Labor, materials and equipment would best represent direct project costs.
4. The forward pass in project network calculations determines all of the following except the critical path.
5. In practice, estimating processes are frequently classified as top down or bottom up.
6. Interrelationships is provided by both the project network and the work breakdown structure.
7. Learning curve is NOT one of the bottom-up approaches to estimating project time and cost.
8. Planning horizon is the factor a project manager is recognizing when she notices that projects that took months or
longer to complete were noticeably more off the estimates.
9. Organization culture is the factor illustrated when a project leader increases his estimates because management
typically insists on reducing forecasts by 20 percent.
10. A node represents an activity on an activity-on-node (AON) project network.
11. Profit is NOT one of the factors that need to be considered to improve the quality of estimates for project times
and costs.
12. Information to develop a project network is collected from the work breakdown structure.
13. An activity that has more than one dependency arrow flowing into it is termed a merge activity.
14. Sensitivity is the likelihood the original critical path(s) will change once the project is initiated.
15. Estimating is the process of forecasting or approximating the time and cost of completing project deliverables.
16. Past experience is a good starting point for developing time and cost estimates.
17. Conditional statements are allowed but looping statements are not allowed is NOT one of the basic rules to
follow when developing project networks.
18. General and administrative overhead would be an example of accounting as a type of cost typically found in a
project.
19. The critical path in a project network is the longest path through the network.
20. A(n) burst activity has more than one dependency arrow flowing from it.