Homework 5 Solutions
th
Homework Solutions for Engineering Economic Analysis, 13 Edition
Newnan, Lavelle, Eschenbach
5-73
Using the PW Method the study period is a common multiple of the lives of the
alternatives. Thus we use 12 years and assume repeatability of the cash flows.
Alternative A
$1,000
$6,000
0
2
4
6
8
10
12
$10,000
NPW = -$10,000 + $6,000 (P/A, 15%, 12) + $1,000 (P/F, 15%, 12)
[(P/F, 15%, 2) + (P/F, 15%, 4) + (P/F, 15%, 6) +
(P/F, 15%, 8) + (P/F, 15%, 10)]
= -$10,000 + $32,526 + $187
1,009 = $1,704
Alternative B
$10,000
0
3
6
9
12
$2,000
$15,000
$2,000
NPW = -$15,000 + $10,000 (P/A, 15
$2,000 (P/F, 15%, 12)
($15,000 + $2,000)[(P/F, 15%, 3) + (P/F, 15%, 6) + (P/F, 15%, 9)]
+ $54,210
4 $23,360 = $15,477
156