WORLDWIDE DIESEL ENGINE SERVICES
WARTSILA 6L34DF AUXILIARY
ENGINE No.2 & No.4 MAJOR
OVERHAUL
Goltens Singapore had recently completed two
auxiliary
engine No.2 & No.4 Major Overhaul, job
E
carry out repairing at Admiralty Yard, Singapore.
PROJECT FACTS : Major Overhaul
Client
Vessel Name
Equipment maker
Model
Engine no.
Location
: “K” Line LNG Shipping (UK) Ltd
: KINISIS
: WARTSILA
: 6L34DF
: PAAE296742 & PAAE296744
: Admiralty Yard
REPAIR CONSISTED OF:
•
•
•
•
•
•
•
•
•
•
Cylinder head, fuel injection pump, fuel injector,
piston, con-rod, liner, air distributor, main start valve,
rocker arm tappet roller, FIP lifter, rocker arm, ,
charge air cooler and lube oil module removed and
send to Goltens Singapore workshop overhaul.
All unit crankpin journal polishing.
Removed camshaft section and camshaft bearing
journal for bearing inspection.
Checked FIP lifter X-value and fuel timing.
Foundation resilient mounting inspection.
Installed liner, water jacket, con-rod, piston, valve
tappet roller, FIP lifter, cylinder head, rocker arm,
cylinder head accessories, fuel injection pump, fuel
injector, charge air cooler, air distributor, main start
valve and attached pipe with fitting.
Pilot fuel pump renewal for DG#2.
Adjusted valve tappet clearance according engine
manual procedure.
Carried out engine testing follow by engine manual
running in procedure.
Hot condition crankshaft deflection and hot condition
coupling laser alignment checked were done after
engine stop for 80% load. Reading with normal
working condition and witness with engine Maker &
3rd engineer.
AE#2 & AE#4
Removing piston
Crankpin polishing
RESULTS:
- Running In program and load test carried out as
per the instruction manual.
- Engine tested up to 80% load as requested by
Wartsila Maker & Owner for AE#2 & AE#4.
Goltens turned over the fully operation engine to
the Chief Engineer with all in order.
Installing liner
Coupling laser alignment
Cam section removal
Installing cam section
Removing pilot fuel pump
WORLDWIDE DIESEL ENGINE SERVICES
Tightening counter weight
Installing cylinder head
Installing LOC
Installing CAC
Installing FIP lifter
Monitoring while engine on load
Governor gear inspection
Tightening big end bearing
Adjusting valve tappet clearance
Checking fuel timing
Low LO trip simulation test.
Alignment witness with Maker & 3rd
engineer.