Engineering Standard 01 February 2022 SAES-A-114 Excavation and Backfill Document Responsibility: Geotechnical Standards Committee Previous Revision: 18 April 2019 Contact: (SPYROPEX) Next Revision: 18 April 2024 Page 1 of 29 © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill Contents Summary of Changes...................................................................................................... 3 1 Scope ....................................................................................................................... 4 2 Conflicts and Deviations ........................................................................................... 4 3 References ............................................................................................................... 4 4 Terminology .............................................................................................................. 6 5. General ..................................................................................................................... 8 6. Fill and Backfill Requirements ................................................................................ 14 7. Excavation .............................................................................................................. 23 8 Non-Metallic Applications ....................................................................................... 26 Document History .......................................................................................................... 27 Appendix Summary of Fill Placement and Compaction Requirements ......................... 28 © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 2 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill Summary of Changes Paragraph Number Previous Revision Current Revision (18 April 2019) (01 February 2022) N/A N/A Change Type (Addition, Modification, Deletion, New) N/A © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Technical Change(s) Editorial revision to extend the next revision date. Page 3 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 1 SAES-A-114 Excavation and Backfill Scope This engineering standard defines the requirements for excavation, placement, compaction, inspection, and management of earth and rock materials during construction and/or maintenance. 2 Conflicts and Deviations Any conflicts between this document and other applicable Mandatory Saudi Aramco Engineering Requirements (MSAERs) shall be addressed to the EK&RD Coordinator. Any deviation from the requirements herein shall follow internal company procedure SAEP-302. 3 References All referenced specifications, standards, codes, drawings, and similar material are considered part of this engineering standard to the extent specified, applying the latest version, unless otherwise stated. 3.1 Saudi Aramco References Saudi Aramco Engineering Procedures (SAEP) SAEP-302 Waiver of a Mandatory Saudi Aramco Engineering Requirement Saudi Aramco Engineering Standards (SAES) SAES-A-100 Survey Coordinates, Datum, and Data Formats SAES-A-113 Onshore Geotechnical Engineering Requirements SAES-L-450 Construction of on-Land and Near-Shore Pipelines SAES-L-460 Pipeline Crossings under Roads and Railroads SAES-L-470 Trenchless Pipelines Construction Requirements SAES-Q-001 Criteria for Design and Construction of Concrete Structures SAES-Q-006 Asphalt and Sulfur Extended Asphalt Concrete Paving SAES-S-070 Installation of Utility Piping Systems Saudi Aramco General Instructions GI-1021.000 Street and Road Closure: Excavation, Reinstatement, and Traffic Controls Saudi Aramco Manuals Construction Safety Manual Blasting Manual © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 4 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill Saudi Aramco Safety Management Guide Guide No. 06-002-2008 3.2 Excavations and Shoring Industry Codes and Standards American Concrete Institute (ACI) ACI 229R Controlled Low-Strength Materials American Society for Testing and Materials ASTM C136 Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates ASTM D422 Standard Test Method for Particle-Size Analysis of Soils ASTM D1140 Standard Test Method for Amount of Material in Soils Finer than the No. 200 (75-um) Sieve ASTM D1556 Standard Test Method for Density and Unit Weight of Soil in Place by the Sand-Cone Method ASTM D1557 Standard Test Method for Laboratory Compaction Characteristics of Soil Using Modified Effort 56,000 ft-lbf/ft³ (2,700 KN- M/M³) ASTM D2167 Standard Test Method for Density and Unit Weight of Soil in Place by the Rubber Balloon Method ASTM D2487 Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System) ASTM D2937 Standard Test Method for Density of Soil in Place by the Drive-Cylinder Method ASTM D4253 Standard Test Method for Maximum Index Density and Unit Weight of Soils Using a Vibratory Table ASTM D4254 Standard Test Method for Minimum Index Density and Unit Weight of Soils and Calculation of Relative Density ASTM D4318 Standard Test Method for Liquid Limit, Plastic Limit and Plasticity Index of Soils ASTM D5777 Standard Guide for Using the Seismic Refraction Method for Subsurface Investigation © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 5 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 ASTM D5778 SAES-A-114 Excavation and Backfill Standard Test Method for Electronic Friction Cone and Piezocone Penetration Testing of Soils ASTM D6938 Standard Test Methods for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth) ASTM D7380 Standard Test Method for Soil Compaction Determination at Shallow Depths Using 5-lb (2.3 kg) Dynamic Cone Penetrometer ASTM D7698 Standard Test Method for In-Place Estimation of Density and Water Content of Soil and Aggregate by Correlation with Complex Impedance Method ASTM D7830/ Standard Test Method for In-Place Density D7830M (Unit Weight) and Water Content of Soil Using an Electromagnetic Soil Density Gauge Process Industry Practices (PIP) PIP CVS02100 4 Terminology 4.1 Acronyms 4.2 Site Preparation, Excavation and Backfill Specification CSD Consulting Services Department FEL Front End Loading Definitions Brackish Water: Water with Total Dissolved Solids of 10,000 ppm or more. Clean Sand: Soil meeting the following gradation containing less than 3% weight of organic material or clay: Sieve Size Percent Passing ¼ in (6.25 mm) 100 No. 10 (2.00 mm) 90 - 100 No. 200 (0.075 mm) 10 or less © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 6 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill Company Representative: Saudi Aramco's authorized representative with overall authority and responsibility for the project. Contract or Contract Documents: Any and all documents, including design drawings, which Saudi Aramco has transmitted or otherwise communicated, either by incorporation or by reference, and made part of the legal contract or purchase order agreement between Saudi Aramco and the Contractor. Contractor: The party responsible for performing excavation and backfill, including work executed through the use of sub-contractors. Controlled Low Strength Material (CLSM): A flowable, self-compacting, cementitious material used primarily as a backfill in place of compacted fill. Dune Sand: Wind-deposited sand consisting of relatively single-sized particles generally passing the No. 16 sieve (1.18 mm) and usually containing less than 10% soil particles passing the No. 200 sieve (0.074 mm). Fill Material: See General Fill Material. General Fill Material: Inorganic soil or rock meeting the requirements in Section 6.1.1. Hard Rock: Rock that cannot be excavated using typical excavation equipment. See Rock Excavation, Section 7.5. Marl: A wide variety of calcareous soil materials found in Saudi Arabia which may vary from clay to gravel sizes and often include cobble and boulder sized pieces. Rock: “Rock” may refer to anything from boulder-size individual pieces to hard, intact bedrock. See Section 7.5 for classification of rock by excavation methods. Sabkha: A saline (generally coastal) deposit generally consisting of saturated, loose silty sand and possibly clay. Select Fill Material: Gravel, sand, clay, or silt, or a mixture of these constituents meeting the requirements in Section 6.1.2. Soft Rock: Weak and fractured rock formations that can be excavated using typical excavation equipment. See Normal Excavation, Section 7.5. Stable Rock: Natural solid mineral matter that can be excavated with vertical sides and remain intact while exposed. It is usually identified by a rock name such as limestone or sandstone. Structural Fill: Select Fill Material as per Section 6.1.2. Vibrating or Heavy Machinery: Centrifugal rotating machinery greater than 500 horsepower, reciprocating machinery greater than 200 horsepower, and all table-top special purpose equipment. PIP CVS02100: Site Preparation, Excavation and Backfill Specification © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 7 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 5. General 5.1 Quality Control SAES-A-114 Excavation and Backfill The Contractor shall institute a quality control program that will verify or ensure that the work performed under the Contract meets the requirements of this Standard and the Contract Documents. Saudi Aramco shall have access to all facilities and records of the Contractor for the purpose of conducting performance inspection/audits. During the audit, any inspection, test reports, and/or engineering analyses and calculations associated with the scope of work shall be furnished upon request. Inspection and Testing Agency 5.1.1 The Contractor's quality control testing requirements shall be performed by either a Saudi Aramco-approved independent testing agency or by the Contractor's own laboratory, approved by the Saudi Aramco Inspection Department. 5.1.2 All required laboratory and field acceptance tests required in Section 6.4 and all seismic refraction testing required in Section 7.5 shall be performed by a Saudi Aramco-approved independent testing agency. 5.1.3 If testing and/or inspection is done by Saudi Aramco, this does not relieve the Contractor of the responsibility to meet all requirements of this Standard. Should it be later found that some work has been completed not in compliance with this standard, it shall remain the Contractor's responsibility to repair or reconstruct deficient work until specifications are met at no cost to Saudi Aramco. 5.2 Submittals The Contractor shall be responsible for transmitting the following submittals to the Saudi Aramco Company Representative: 5.2.1 Compaction Test Reports, including all laboratory and field test logs and comments. Field test reports shall include density and moisture content test logs indicating location by coordinates and elevation as per SAES-A-100. Reports shall be submitted as follows: 5.2.1.1 Daily “pass” or “fail” reports. 5.2.1.2 A summary report with test logs shall be submitted weekly or as © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 8 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill required by Saudi Aramco. 5.2.1.3 A complete record of all test logs and comments for permanent project records shall be submitted at earthwork completion. 5.2.2 Fill Materials and Water Test Reports. Sources and test results of all fill materials and compaction water shall be submitted to Company Representative for approval from Project Inspection Department prior to beginning fill operations. Compaction water shall be tested for Total Dissolved Solids, Chloride (Cl-) and Sulfate (SO4) contents according to SAES-Q-001. 5.2.3 Controlled Low Strength Material (CLSM) mix design and 28-day compressive strength shall be submitted to Company Representative for CSD review and acceptance prior to use on the site. 5.2.4 Excavation Plan, including a Pre-Excavation checklist, as per the Saudi Aramco Construction Safety Manual and Safety Management Guide 06-002-2008 shall be submitted prior to beginning excavation. Consulting Services Department review of the Excavation Plan is required if excavation depth is greater than 6 m or if the Plan includes support or protection for existing structures, foundations or underground utilities. Note: A geotechnical investigation as per SAES-A-113/paragraph 6.1 is required. All excavations, including shoring and sheeting materials and systems shall meet the minimum requirements established by the Construction Safety Manual and Saudi Aramco Safety Management Guide 06-0022008. If an Excavation Plan is required and shoring is used, the Contractor’s Excavation Plan shall: a) Describe the materials and shoring system to be used. b) Indicate whether or not any components will remain after filling or backfilling. c) Provide plans, sketches and/or detail along with calculations. d) Indicate the sequence and method of shoring installation and removal. © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 9 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill 5.2.5 Dewatering Plan. If dewatering of an excavation is required, the Contractor shall submit proposed methods and details to the Saudi Aramco Company Representative for review and approval, before beginning dewatering and excavation. 5.3 Environmental 5.3.1 Contaminated Soils Known contaminated soils within the construction limits shall be managed in accordance with a contaminated soil management plan provided by Saudi Aramco prior to the start of excavation. If unexpected soil contamination is encountered during the work, the Contractor shall stop work and notify the Saudi Aramco Company Representative immediately. 5.3.2 Erosion/Sediment Control The Contractor shall ensure that all slopes and other areas subject to erosion shall be maintained using temporary erosion and sediment control measures during construction or until relieved by the Saudi Aramco Company Representative or until permanent measures are completed and functioning in a satisfactory manner. 5.3.3 Dust Control The Contractor shall employ dust control measures during construction. The adequacy of the dust control shall be determined by the Saudi Aramco Company Representative. 5.4 Drainage and Dewatering A Dewatering Plan shall be submitted to the Saudi Aramco Company Representative as per Section 5.2.5 5.4.1 All temporary drainage and dewatering methods and disposal of water are subject to approval by Saudi Aramco. 5.4.2 The Contractor shall employ temporary drainage measures during construction. Ponding of water on placed fill or within excavations shall not be allowed. 5.4.3 Surface water shall be prevented from flowing into excavations by ditching, trenching, forming protective swales, pumping, or other approved measures. 5.4.4 Based on the Geotechnical report, prior to excavation, an approved © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 10 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill dewatering system shall be installed and operated when necessary to lower the groundwater. 5.4.5 All diverted and pumped water shall flow to specified collection areas and shall be disposed of as directed by the Saudi Aramco Company Representative. Excavations for foundations and other underground installations shall not be used as temporary drainage ditches. 5.4.6 Disposal of drainage water and groundwater contaminated with oil, gasoline, diesel, solvents and/or other chemicals shall be approved by the Environmental Protection Department. 5.5 Safety and Protection The Contractor shall place and maintain in good condition temporary fences, guardrails, barricades, lights, shoring, bracing, and other protective measures required for the safety of personnel and the premises as described in the Saudi Aramco Construction Safety Manual. 5.5.1 Required Permits and Procedures 5.5.1.1 All necessary permits must be obtained from Saudi Aramco prior to performing any earthwork. 5.5.1.2 All rock blasting shall follow the procedures in the Saudi Aramco Blasting Manual. 5.5.2 Excavation Safety An Excavation Plan shall be submitted to the Saudi Aramco Company Representative as per Section 5.2.4. All excavation and trenching shall be done in accordance with Saudi Aramco safety requirements including, but not limited to, the Saudi Aramco Construction Safety Manual and Safety Management Guide 06-002-2008, including: • Provision of safe entry and exit. • Precautions for Hazardous Atmospheres and Confined Spaces. • Provision and maintenance of edge protection, clearances, barricades, and fixed lighting. • Protection of underground utilities and installations. • Protection against sidewall cave-in. Shoring shall be installed or the sides shall be sloped or benched when any excavation or © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 11 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill trench reaches a depth of 1.2 m or when soil banks are greater than 1.5 m. Note: Specific requirements are given in Saudi Aramco Safety Management Guide 06-002-2008. • Provision of proper inspection frequency. • Proper backfilling and removal of shoring. Shoring may be left in-place if so indicated in the approved Excavation Plan. 5.5.3 Hazard Mitigation 5.5.3.1 Whenever Saudi Aramco determines that any excavation or embankment or fill which was created by a Contractor and which is a hazard to life and limb, or endangers property, or adversely affects the safety, use or stability of a roadway or drainage channel, the responsible Contractor shall immediately repair or eliminate such excavation or embankment so as to eliminate the hazard. 5.5.3.2 Any construction or maintenance work which restricts the full use of a pedestrian or vehicular roadway shall comply with GI-1021.000, Street and Road Closure: Excavation, Reinstatement and Traffic Controls. 5.5.4 Protection of Existing Facilities 5.5.4.1 The Contractor shall be responsible for avoiding damage to all existing facilities. Unless otherwise specified, any damage by the Contractor during performance of the work shall be repaired or replaced by the Contractor to the satisfaction of the Saudi Aramco Company Representative at no cost to Saudi Aramco. 5.5.4.2 No excavation is permitted under existing foundations. Excavations are not allowed to intersect a 45-degree plane extending downward from the bottom edge of existing foundations unless an engineered support system, approved as part of the Excavation Plan, is in place prior to the start of work or the excavation is in stable rock. 5.5.4.3 Excavations adjacent to existing underground installations (e.g., piping, manholes, electrical and duct banks) or sidewalks shall use bracing and shoring to protect those installations during construction. In general, protection is required if the excavation will intersect a 45-degree plane extending downward from the bottom of the structure or utility to be protected. © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 12 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill 5.5.4.4 Structures that require passive soil pressure for stability (e.g., light poles or tower foundations) shall be properly braced whenever an excavation is within the passive pressure zone (generally a distance of 1.5 times the embedment depth of the foundation). Fill or backfill of the excavation must meet the compaction requirements in sections 6.3.6.1 or 6.3.6.2 as applicable. 5.5.4.5 All reference points, property markers, bench marks, monuments, etc., shall be carefully maintained during excavation, backfilling, compaction and earthwork. Unless otherwise specified, damage to a reference point by the Contractor during performance of the work shall be reported to Saudi Aramco and repaired or replaced by the Contractor to the satisfaction of the Saudi Aramco Company Representative at no cost to Saudi Aramco. 5.5.4.6 The Contractor shall be responsible for preserving and avoiding damage to trees, shrubs, and all other vegetation in the areas beyond the designated excavation area. 5.5.5 Trenching through Roads and Pavements Reinstatement of roads and pavements after trenching shall comply with SAES-Q-006 and GI-1021.000, Street and Road Closure: Excavation, Reinstatement and Traffic Controls. 5.5.6 Clean Up 5.5.6.1 Soil that is spilled or washed onto paved areas or streets shall be removed daily or as directed by the Saudi Aramco Company Representative. 5.5.6.2 Soil that is spilled or washed into drains, pipes, gutters, or ditches or onto adjacent sites shall be removed daily. The Contractor shall provide measures to prevent recurrence. © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 13 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 6. Fill and Backfill Requirements 6.1 Fill and Backfill Materials SAES-A-114 Excavation and Backfill Fill and backfill materials shall conform to the criteria in sections 6.1.1, 6.1.2, 6.1.3, and 6.1.4 below or as recommended by a geotechnical report as per SAES-A-113. All sources of supply shall be approved by Saudi Aramco. Stockpiles shall be placed, graded, and shaped for proper drainage. Storage or stockpiling of material shall not be permitted on a completed subgrade. Stockpiles of cohesive soil shall be protected from freezing. Soils shall be classified per ASTM D2487. 6.1.1 General Fill Material 6.1.1.1 General Fill Material shall consist of gravel, sand and/or marl. The maximum size of the fill material shall be one-half the lift thickness or 75 mm (3 inches), whichever is less. 6.1.1.2 Fill material shall be free of frozen lumps, organic matter, trash, chunks of highly plastic clay (classified as CH as determined by ASTM D2487) or other unsatisfactory material. 6.1.2 Select Fill Material 6.1.2.1 Select Fill or ‘Structural Fill’ shall be composed only of inorganic material and shall have 100% passing the 5 cm (2 in) sieve and from 0 to 20% passing the No. 200 sieve. 6.1.2.2 The portion of Select Fill material passing the No. 40 sieve shall have a maximum liquid limit of 35 and a maximum plasticity index of 12 per ASTM D4318. Liquid limit and plastic limit tests are not required for select fill material with less than 15% passing the No. 200 sieve. Notes: Clean sand and dune sand may be used as Fill or Select Fill Material. If sand is used as fill material, see paragraphs 6.3.3.5 and 6.3.8. Cohesionless materials (sand or gravel) are recommended for Fill or Select Fill Material below the highest natural groundwater level. 6.1.3 Controlled Low-Strength Material (CLSM) 6.1.3.1 CLSM or “flowable fill” may be substituted for either Select Fill Material or general Fill Material, where approved by the Chairman, Civil © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 14 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill Standards Committee. CLSM is recommended where traditional compaction is difficult (i.e., narrow or congested excavation backfill). 6.1.3.2 Unless otherwise specified, CLSM shall be in accordance with ACI 229R. 6.1.3.3 The mix design shall be proportioned to produce a 28-day compressive strength between 0.7 and 1.4 MPa (100 and 200 psi), pretested using the actual raw materials and approved by the Chairman, Civil Standards Committee before use on the project. Compressive strengths above or below this range may be approved by the Chairman, Civil Standards Committee based on future excavation requirements. Note: Per ACI 229R: The ability to excavate CLSM is an important consideration on many projects. In general, CLSM with a compressive strength of 0.3 MPa (50 psi) or less can be excavated manually. Mechanical equipment, such as backhoes, are used for compressive strengths of 0.7 to 1.4 MPa (100 to 200 psi). Mixtures using high quantities of coarse aggregate can be difficult to remove by hand, even at low strengths. Mixtures using fine sand or only fly ash as the aggregate filler has been excavated with a backhoe up to strengths of 2.1 MPa (300 psi). 6.1.3.4 Unless otherwise specified, witness inspection only shall be required for field testing of CLSM. 6.1.3.5 CLSM shall be allowed to harden a minimum of 6 hours prior to proceeding with construction over the CSLM. 6.1.4 Other fill materials (e.g., rock fill, lean concrete, etc.) may be used with the approval of the Chairman, Geotechnical Standards Committee. 6.1.5 Compaction Water 6.1.5.1 Water used for compaction of fill material shall be reasonably free of salts, oil, acid, alkalis, organic matter, or other deleterious substances. 6.1.5.2 Use of water with Total Dissolved Solids of 10,000 ppm or more (i.e., brackish water, seawater or water obtained from ground pits such as sabkha water) shall align with environmental exposure requirements set in Tables 1 and 2 of SAES-Q-001. © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 15 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 6.2 SAES-A-114 Excavation and Backfill Preparation of Areas to Receive Fill, Pavement or Loads 6.2.1 Areas to receive fill, foundations, or pavement shall be free of organic material, trash, or other unsuitable material. 6.2.2 Proper drainage shall be maintained at all time so that the site is free of standing water. Any soil that becomes saturated shall be removed completely or as specified by the Company Representative. 6.2.3 Areas, in horizontal plane or side slope, shall be prepared for fill or loading as follows: 6.2.3.1 The site shall be proof-rolled and inspected for soft spots or loose zones. Proof roll may be defined as crossing the area with a heavy (minimum 10ton weight) rubber-tire or steel-wheel roller. 6.2.3.2 All observed soft spots or loose zones shall be compacted in-place or excavated to firm soil and replaced with fill material compacted to the specifications in Section 6.3.6. 6.2.3.3 Top 150 mm scarified and re-compacted. The density of the top 150 mm in these areas shall not be less than 90% of the maximum Modified Proctor density (ASTM D1557) or 70% relative density (ASTM D4253 and ASTM D4254) for cohesionless freely draining soil. 6.3 Fill Placement and Compaction Note: A summary of fill placement and compaction requirements is included as an Appendix to this standard. 6.3.1 Select Fill Material shall be specified: 6.3.1.1 Within 0.6 m of the bottom elevation of foundations, spread footings, slabs-on-grade and pavements when fill is required to achieve final grade. In general, Select Fill Material shall be specified for entire lifts and not interspersed with General Fill Material within the same lift. Note: Foundations may be constructed directly on undisturbed soil. Excavation of undisturbed soil and replacement with Select Fill Material shall not be performed except as noted in 6.2.3.2 or 7.2.2 or as recommended in a geotechnical report as per SAES-A-113. 6.3.1.2 For backfill which will be in contact with concrete or steel structures. © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 16 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill 6.3.1.3 All other areas not designated above or otherwise specified in as Select Fill Material in the design drawings may be filled or backfilled using General Fill Material. 6.3.2 Before placement of fill, the area to receive the fill shall be prepared in accordance with Section 6.2. In addition: 6.3.2.1 In no case shall compaction be allowed on slopes greater than 1 (V) to 5 (H). A series of horizontal benches, steps, or terraces, at least 1 compactor width, should be cut into existing and natural slopes prior to adding new fill to key the new fill into the underlying soil. 6.3.2.2 Construction of new slopes shall be accomplished by compacting horizontal fill layers at least 1 compactor width beyond the design edge of the slope and then trimming back to achieve the final slope dimensions. 6.3.3 Fill material shall be placed in uniform loose lifts not exceeding the following criteria, provided that the specified compaction is achieved for the full depth. 6.3.3.1 Select Fill Material shall be placed in lifts of 200 mm maximum in loose depth. 6.3.3.2 General Fill Material shall be placed in lifts of 300 mm maximum in loose depth. 6.3.3.3 General Fill Material and Select Fill Material shall be placed in lifts of 100 mm maximum in loose depth for hand-operated compaction equipment. 6.3.3.4 Other lift thicknesses may be approved by the appropriate Saudi Aramco Inspection Representative based on a field test section using the intended compaction equipment and verification that compaction was achieved for the full depth. Notes: Impact rollers can compact soils in lifts exceeding 1 m. Rapid Impact Compaction (sometimes referred to as shallow dynamic compaction or rapid dynamic compaction) can compact soils in lifts up to 4 m provided the following: • Presence of non-cohesive (sandy) materials. • Particles finer than No. 200 sieve shall not exceed 15%. • Trials to be undertaken (prior of the main production works) for verifying the suitability of such method and the parameters to be utilized. © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 17 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 • SAES-A-114 Excavation and Backfill In-situ Cone Penetration Tests (CPT) should be used for verifying compliance to project specifications (acceptance criteria are related to the requirements of Relative Density as per Section 6.3.6). Such tests should be undertaken on treated ground between Rapid Impact Compaction points as per ASTM D5778. See Section 6.4.2.6 for use of a method statement for compaction procedure with reduced testing requirements. 6.3.3.5 If clean sand or dune sand is used for fill, the compacted sand shall be kept wet until the next layer is placed. Note: Sand that has been allowed to dry out will uncompact under vehicle or pedestrian traffic. Continuous watering is required to maintain compaction until the next lift is in-place. 6.3.4 Compacting shall begin only after the fill or backfill has been properly placed and the material to be compacted is at the proper moisture content. 6.3.4.1 The moisture content of the material being compacted shall be within 3%, plus or minus, of the optimum moisture content as determined by ASTM D1557. © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 18 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill 6.3.4.2 For cohesionless freely draining soils when ASTM D4253/ ASTM D4254 are the appropriate test procedures, there is no applicable optimum moisture content. 6.3.5 Compaction shall be performed with equipment compatible with soil type. 6.3.5.1 Fill and backfill adjacent to structures such as retaining walls, pits, and basements shall not be compacted with heavy equipment, but shall be compacted with hand-operated equipment to a distance of 1.2 meters or greater beyond the sides of the structures. Every effort shall be made to place backfill materials symmetrically and in uniform layers to prevent unnecessary eccentric loading on a structure or foundation. 6.3.5.2 Compaction by water jetting or flooding is not permitted for most fill material. However, flooding with positive drainage may be used if the fill material is cohesionless freely draining sand. Density requirements as provided within 6.3.6 shall be followed. Note: Water flooding with positive drainage may be the most effective compaction technique for poorly graded and single-size sands, as these sands are difficult to compact with mechanical compactors . 6.3.6 Fill and backfill layers shall be uniformly compacted in accordance with the following density requirements: 6.3.6.1 All Select Fill Material and any fill beneath and/or adjacent to foundations, grade beams, mats, buildings, lined slopes or drainage channels, and process areas: • At least 90% of the maximum Modified Proctor density as determined by ASTM D1557, or • At least 70% Relative Density as determined by ASTM D4253 and ASTM D4254 for cohesionless granular soils that do not exhibit well-defined moisture density relationship. 6.3.6.2 Select Fill Material beneath and/or adjacent to foundations with static loads over 320 kPa and foundations for vibrating or heavy machinery: • At least 95% of the maximum Modified Proctor density as determined by ASTM D1557, or © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 19 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 • SAES-A-114 Excavation and Backfill At least 85% Relative Density as determined by ASTM D4253 and ASTM D4254 for cohesionless granular soils that do not exhibit well-defined moisture density relationship. 6.3.6.3 Asphalt and concrete pavement subgrades: • At least 95% of the maximum Modified Proctor density as determined by ASTM D1557, or • At least 85% Relative Density as determined by ASTM D4253 and ASTM D4254 for cohesionless granular soils that do not exhibit well-defined moisture density relationship. 6.3.6.4 General Fill Material for areas not designated as open or landscaped: • At least 90% of the maximum Modified Proctor density as determined by ASTM D1557, or • At least 70% Relative Density as determined by ASTM D4253 and ASTM D4254 for cohesionless granular soils that do not exhibit well-defined moisture density relationship. 6.3.6.5 General Fill Material for areas designated as open or landscaped: • At least 85% of the maximum Modified Proctor density as determined by ASTM D1557, or • At least 65% Relative Density as determined by ASTM D4253 and ASTM D4254 for cohesionless granular soils that do not exhibit well-defined moisture density relationship. 6.3.6.6 Working platforms for compaction on sabkha deposits shall be compacted as necessary to achieve a stable base. Sabkha working platforms must be indicated as such and accounted for in the design. Compaction testing of working platforms is not required. Notes: Compaction to the required densities indicated in Section 6.3 are virtually impossible to achieve in the first layer placed directly on sabkha and similar very weak soils. A working platform to provide a stable base is often required. A 500 mm thick layer of fill material placed directly on the sabkha compacted as well as possible is usually sufficient. Stripping of the sabkha “crust” prior to fill placement is not recommended. A geotextile layer between the sabkha and the working platform provides a capillary break and improves both short-term (construction) and long-term performance of the engineered fill. © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 20 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill 6.3.6.7 Topsoil identified as “for planting purposes” is exempted from compaction requirements. 6.3.7 Compacted surfaces of fill and backfill shall be finish graded to the cross sections, lines, grades, and elevations as indicated on the drawings. 6.3.8 Surficial erosion protection, as approved by the Company Representative, shall be provided when: 6.3.8.1 Clean sand or dune sand is used for fill, or 6.3.8.2 Final slopes are steeper than 1 (V) to 5 (H). Note: Typical surficial erosion protection (when clean sand or dune sand is used for fill) includes select fill material (where required as per Section 6.3.1), cohesive marl minimum 150 mm thick (classified as SC, ML, or CL as determined by ASTM D2487, compacted as per Section 6.3.6), soil-cement (minimum 5% cement by weight). For slopes steeper than 1 (V) to 5 (H) surficial erosion protection includes chemical polymer or geocells. For channels or wadis riprap or asphalt/concrete surfacing may be used. 6.4 Testing and Inspection Requirements 6.4.1 Laboratory Control Tests 6.4.1.1 Tests of gradation, plasticity, density, and moisture content shall be performed for each type of fill material. These tests shall include the following: Required tests for cohesive soils: • Sieve analysis (ASTM C136, ASTM D422, or ASTM D1140) • Plasticity Index determination (ASTM D4318) • Modified Proctor Test (ASTM D1557) with corresponding Proctor curve. Required tests for cohesionless soils: • Sieve analysis (ASTM C136, ASTM D422, or ASTM D1140) • Relative Density determination (ASTM D4253 and ASTM D4254). When the backfill material cannot clearly be classified as cohesive or cohesionless both Relative Density and Proctor density tests must be © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 21 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill performed per the above paragraph. The backfill shall then be compacted to the greater density. 6.4.1.2 Laboratory Control Test Frequency • The control tests specified in Section 6.4.1.1 shall be conducted at a minimum for every 10,000 m3 where the fill material is uniform or for every change of source or material type. • Every effort should be made to ensure that the fill material is uniform. However, in situations when the fill is (1) from a single borrow area but non-uniform in composition, or (2) a stockpile from multiple sources, the tests in Section 6.4.1.1 shall be conducted at a minimum for every 5,000 m3 using a combined sample of four random samples of the fill material. 6.4.2 Field Control Tests 6.4.2.1 In-place density and moisture content of soils shall be determined by the following methods: • Sand-cone method in accordance with ASTM D1556 • Nuclear method in accordance with ASTM D6938 • Rubber balloon method in accordance with ASTM D2167 • Drive-cylinder method in accordance with ASTM D2937. The drivecylinder method per ASTM D2937 may only be used if the compacted layer is only 15 cm or less. 6.4.2.2 Other methods for in-place density of compacted fills, such as Electromagnetic Soil Density Gauge (ASTM D7830/D7830M), Electrical Soil Density Gauge (ASTM D7698) or Dynamic Cone Penetration (ASTM D7380), may be approved by the Saudi Aramco Inspection Representative based © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 22 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill on a field test which proves the accuracy of the method for the given fill material and compaction method. 6.4.2.3 Testing shall be performed at the following frequencies: • Select Fill Material under all foundations, buildings and process areas - one test every 100 m² of each lift. • Select Fill Material under roadways, railroads, area pavement and parking areas, and lined slopes or drainage channels - one test every 200 m² of each lift. • General Fill Material - one test every 500 m² of each lift. • Backfill of trenches - one test for every 15 linear meter of each lift. 6.4.2.4 As a minimum, at least one in-place density test must be performed on every lift of fill and further placement shall not be allowed until the required density has been achieved. 6.4.2.5 The number of tests shall be increased if a visual inspection determines that the moisture content is not uniform or if the compacting effort is variable and not considered sufficient to attain the specified density. 6.4.2.6 The Project Inspection Representative may approve a decrease in the number of tests once a compaction procedure has proven to meet compaction requirements. In such cases, a method statement for the compaction procedure and testing frequency shall be submitted to the Saudi Aramco representative and approved by Project Inspection. The method statement must include the equipment type, serial numbers, lift thicknesses, and the number of passes required to achieve the required density. 7. Excavation 7.1 General Excavation General excavation shall be performed after clearing and stripped of organic material, trash, or other unsuitable material. 7.2 Structural Excavation Structural excavation shall include excavations for footings, grade beams, pits, basements, retaining walls, man holes, catch basins, pipeline thrust anchors, etc. 7.2.1 Excavation shall be performed as required by the design drawings to the dimensions, grades, and elevations as noted and as required for formwork © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 23 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill and allowance for compaction equipment. 7.2.2 When soft or compressible soil is encountered at footing grades as shown on the drawings, such soil shall be removed and replaced with compacted Select Fill as specified in sections 6.2 and 6.3, CLSM, or lean (1,000 psi minimum 28-day compressive strength) concrete. 7.2.3 Over-excavation at footings shall be backfilled with compacted Select Fill as specified in sections 6.2 and 6.3, CLSM, or lean (1,000 psi minimum 28-day compressive strength) concrete. 7.3 Earthen Structures Earthen structures include permanent work items such as ponds, canals, ditches, etc. Excavation for such work shall be made to the lines, grades, and cross sections as shown on the drawings. 7.3.1 Side slopes of excavations shall be cut true and straight and shall be graded to the design cross section. Unstable soil in the slopes shall be removed and the slopes properly prepared as described in Section 6.3.2. The bottoms of excavations shall be graded to the elevations and configurations as shown on the drawings. 7.3.2 Over excavation shall be backfilled with suitable material compacted in accordance with Section 6.3, CLSM, or lean (1,000 psi minimum 28-day compressive strength) concrete. 7.4 Trenching Trenching for pipelines and underground utilities shall conform to SAES-L-450, SAES-L-460, SAES-L-470 or SAES-S-070 as appropriate. Reinstatement of roads and pavements after trenching shall comply with SAESQ-006 and GI-1021.000, Street and Road Closure: Excavation, Reinstatement, and Traffic Controls. 7.5 Rock Excavation Seismic velocities will be the sole factor in determining the appropriate category for the excavation of rock. Excavation of rock will fall into the following categories, based on the excavation type and the seismic compression (P) wave © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 24 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill velocities measured in the field prior to excavation by refraction seismic testing as per ASTM D5777. Table 1 – Excavation Categories Excavation Type Seismic Velocity from Shallow Refraction Tests (m/s) Vp < 1,530 Small/linear Mass grading Normal Excavation Normal Excavation 1,530 < Vp < 2,300 Vp >2,300 Rock Excavation Rock Excavation Normal Excavation Rock Excavation Where: Normal Excavation: Excavation that can be accomplished using rippers (mass grading) and/or excavators/backhoes (linear and isolated small excavations,) operated in accordance with good construction practice. Normal excavation includes all soils and also includes soft, weathered and/or fractured rock. Rock Excavation: Excavation that cannot be accomplished using rippers and/or excavators/backhoes and which requires blasting or pneumatic rock breakers to facilitate excavation. Small/linear: Isolated small excavations and linear excavations (trenches, road cuts) where limitations to ripping are present, verified by the Company Representative. Such limitations may include ripping direction and/or travel distance. Mass grading: Large, open area excavation where no limitations to ripping are present. Vp: Seismic compression (P) wave velocity. Notes: The detailed geotechnical report (FEL 3) shall incorporate rock and soil quantification based on the seismic refraction tests (ASTM D5777) especially for projects require major excavations (e.g., site preparation cut and fill projects, linear projects such as underground pipelines, projects including foundations by means of raft, etc.). Layout and final grades should be known at FEL 3 stage. After the excavation contract award the Contractor shall undertake their own field assessment for verification of the rock and soil quantities included within the detailed geotechnical report which has been utilized within the bidding process. Any variations in the quantities of material shall be confirmed by means of additional surface refraction tests prior of commencing the excavation works. If variations in ground conditions (compared to the detailed geotechnical report) are found © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 25 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill during the actual excavations the matter shall be referred back to CSD for further evaluation. 7.6 Disposal of Materials All excavated materials that are unsatisfactory for use as fill or backfill or that are surplus to that needed for backfilling shall immediately be disposed of at a location designated by the Saudi Aramco Company Representative. 8 Non-Metallic Applications 8.1 Geotextile Filters The geotextiles are permeable fabrics which used in association with soil and have the ability to separate, filter, reinforce, protect or drain. The geotextiles shall be used as separation and filtration layer under riprap for shoreline protection within marine applications (e.g. breakwaters, quay wall, and revetments) and shall replace traditionally used graded aggregate filters. 8.2 Geo-grids The geo-grids having the objective to act as a working platform whereas separating the engineering backfill from the weak soils at road construction schemes. The geo-grids provide increased bearing capacity over weak soil formations and improve design life prospect, while reduce the expected construction time. The geo-grids shall replace traditionally soil treatment of the weak formations upon which road construction takes place subject to design confirmation. 8.3 Geo-cells and Chemical Polymer Agents for Slope Protection The chemical polymer agent is a water-based liquid that can be sprayed on the sand and as the water evaporates, the polymer forms a matrix in the sand that bonds the sands particles together forming hard crust. The material is ecofriendly and easy to apply using standard equipment. Chemical Polymer shall be used for slope protection from erosion. The geo-cell protection scheme including a cellular confinement system applied on the slopes shall be another option for slope protection. These materials (chemical polymer and geo-cells) shall replace traditional erosion protection systems such as grass/vegetation, cohesive marl, soil-cement, riprap either grouted (usual) or un-grouted, asphalt/concrete surfacing. Chemical polymer shall also be used in sand berms covering pipelines. 8.4 Geo-nets Geo-nets provide efficient drainage solutions since they slow down the surface runoff and decrease erosion potential of water. In addition, geo-nets break the © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 26 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill capillary action of the water. The geo-nets shall replace traditional aggregate capillary break layers at road construction schemes. 8.5 Expanded Polystyrene (EPS) Geofoam use for Geotechnical Application The EPS geofoam is a closed cell and rigid foam that is formed by exposing polystyrene resin beads, containing a hydrocarbon blowing agent, to steam which is then expanded and formed in molds to required shape and form. The Polystyrene resin beads are a byproduct from petroleum processing and refining. The application of EPS includes but not limited to the following: road construction over poor soils & road widening, bridge abutment & bridge underfill, slope stabilization, retaining & buried wall backfill, rail embankment, airport runway/taxiway, and landscaping & vegetative green roofs. Document History 01 February 2022 18 April 2019 Editorial revision to extend the next revision date. Major revision. The majority of the geo-composites (geotextiles, geo-grids, geo-nets, geo-cells and chemical polymers) are mandated by slightly altering the language. 13 December 2018 Major revision. The changes are summarized below: o As part of Engineering Services (ES) commitment toward deployment of high value non-metallic technologies, Consulting Services Department (CSD) recommends placement of geo-composites of various functions which also may have cost and time schedule enhancements when compared to the traditional mitigation approaches. 1 January 2018 Editorial revision to Section 2, Conflicts and Deviations. 11 December 2017 Major revision. The changes are summarized below: o An additional compaction method (Rapid Impact Compaction) and its applicability has been included. This technology method has been successfully implemented. Having completed the implementation, it is technically concluded that for given soil conditions the Rapid Impact Compaction approach can be utilized (for soil depths up to 4 m) as a substitute to the traditional backfilling operations where fill lifts and roller compaction are used. Furthermore, cost and time simulations by using both methods Rapid Impact Compaction and Roller Compaction has been undertaken. This analysis has proven that the Rapid Impact Compaction method considerably cuts down on time and schedule, by more than 50%, allowing an early start of construction activities and at the same time reduces the cost of site preparation activities by almost 50%. o At contracts where, major excavations are anticipated requirements of the surface refraction tests have been included. More specifically, the detailed geotechnical report (FEL 3) shall incorporate rock and soil quantification. Layout and final grades should be known at FEL 3 stage geotechnical report. Moreover, the awarded Contractor shall undertake their own field assessment for verification of the geotechnical data/quantities provided. Any variations in the quantities of material shall be confirmed by means of additional surface refraction tests prior of commencing the excavation works. If variations in ground conditions are found during the actual excavations the matter shall be referred back to CSD for further evaluation. Unjustifiable change orders and claims shall not be entitled to any compensation. © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 27 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 SAES-A-114 Excavation and Backfill APPENDIX Summary of Fill Placement and Compaction Requirements Area/Region Compaction Requirement Site preparation of areas to receive fill, pavement or loads. The density of the top 150 mm in these areas shall not be less than: 90% of the maximum Modified Proctor density (ASTM D1557) or 70% relative density (ASTM D4253 and ASTM D4254) for cohesionless free draining soil All Select Fill Material or any fill beneath and/or adjacent to grade beams, mats, buildings, lined slopes or drainage channels, and process areas. Compacted to at least: Select Fill Material beneath and/or adjacent to foundations with static loads over 320 kPa and foundations for vibrating or heavy machinery. Asphalt and concrete pavement subgrades (roads and parking areas). Compacted to at least: General Fill Material not designated as open or landscaped. Compacted to at least: General Fill Material for areas designated as open or landscaped. Compacted to at least: 90% of the maximum Modified Proctor density (ASTM D1557) or 70% Relative Density (ASTM D4253 and ASTM D4254) for cohesionless granular soils that do not exhibit well-defined moisture density relationship. 95% of the maximum Modified Proctor density (ASTM D1557). or 85% relative density (ASTM D4253 and ASTM D4254) for cohesionless granular soils that do not exhibit well-defined moisture density relationship. Comments Site preparation • Areas shall be free of organic material, trash or other unsuitable material. • Proper drainage so that the site is free of standing water all the time. • In-situ soil proof rolled and inspected for soft spots or loose zones. Proof roll may be defined as crossing the area with a heavy (minimum 10-ton weight) rubber-tire or steel-wheel roller. • All observed soft spots or loose zones shall be compacted in-place or excavated to firm soil and replaced with properly compacted fill. • Top 6 inches (150 mm) scarified and recompacted. Fill material shall be placed in uniform loose lifts not exceeding the following criteria, provided that the specified compaction is achieved for the full depth. • Select Fill Material shall be placed in lifts of 200 mm maximum in loose depth. • General Fill Material shall be placed in lifts of 300 mm maximum in loose depth. • General Fill Material and Select Fill Material shall be placed in lifts of 100 mm maximum in loose depth for hand-operated compaction equipment. • Other lift thicknesses may be approved by the appropriate Saudi Aramco Inspection Representative based on a field test section using the intended compaction equipment. (Impact rollers can compact soils in lifts exceeding 1 m). 90% of the maximum Modified Proctor density (ASTM D1557) or 70% Relative Density (ASTM D4253 and ASTM D4254) for cohesionless granular soils that do not exhibit well-defined moisture density relationship. 85% of the maximum Modified Proctor density (ASTM D1557) or 65% Relative Density (ASTM D4253 and ASTM D4254) for cohesionless granular © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Page 28 of 29 Document Responsibility: Geotechnical Standards Committee Issue Date: 01 February 2022 Next Revision: 18 April 2024 Area/Region Compaction Requirement SAES-A-114 Excavation and Backfill Comments soils that do not exhibit well-defined moisture density relationship. Topsoil identified as “for planting purposes.” Exempted from compaction requirements. Working platforms for compaction on sabkha deposits. A 500 mm thick layer of fill material placed directly on the sabkha compacted as well as possible is usually sufficient. Stripping of the sabkha “crust” prior to fill placement is not recommended. A geotextile layer between the sabkha and the working platform provides a capillary break and improves both short-term (construction) and long-term performance of the engineered fill. Compaction testing of working platforms is not required. Pavement Reconstruction after Trenching Reinstatement of roads and pavements after trenching shall comply with shall comply with SAES-Q-006 and GI-1021.000. © Saudi Arabian Oil Company, 2022 Saudi Aramco: Company General Use Working platforms for compaction on sabkha deposits shall be compacted as necessary to achieve a stable base. Sabkha working platforms must be indicated as such and accounted for in the design. Compaction to the required densities indicated in Section 6.3 are virtually impossible to achieve in the first layer placed directly on sabkha and similar very weak soils. A working platform to provide a stable base is often required. Controlled Low Strength Material (CLSM), a flowable, self-compacting fill, is recommended for backfill of trenches crossing roads and pavements. Page 29 of 29