1. I assume you have drawn your own network diagram. Activity Precedes Duration A - 9 B A,D 6 C B 5 D - 6 E D 8 F E 4 G C,F 12 Crash this project to 27 weeks using the lowest amount of money Activity A B C D E F G Normal Duration 9 6 5 6 8 4 12 Crashed Duration 7 5 4 4 6 3 11 Paths: ABCG = 32 ----- (Critical Path) DBCG = 29 DEFG = 30 Crash Cost 720 290 360 320 510 320 650 Normal Cost 560 240 330 240 370 270 590 2600 Cost Slope 80 50 30 40 70 50 60 Time Constraint 2 1 1 2 2 1 1 Step 1: Start from the critical path activities and choose the activity with the lowest cost slope to crash. Remember to consider the allowance. Eg you can only crash C, the lowest slope by 1 week. Crash C by 1 week ABCG = 31 ---- (CP) DBCG = 28 DEFG = 30 Cost = 30 x 1 = 30 Step 2: Focus on the critical path activities and choose the activity with the lowest cost slope to crash Crash B by 1 week ABCG = 30 ---- (CP) DBCG = 27 DEFG = 30------ (CP) Cost = 50 Step 3: Crash D by 2 ABCG = 30 --- (CP) DBCG = 25 DEFG = 28 Cost – 40x2 = 80 Step 4: Crash G by 1 week ABCG = 29 ---- (CP) DBCG = 24 DEFG = 27 Cost = 60 Step 5 Crash A by 2 ABCG = 27 (CP) DBCG = 24 DEFG = 27 (CP) Cost = 80x2 = 160 Remember the potential question of the risk of this set up and how to answer it. Total crash cost = 30 + 50 + 80 + 60 + 160 = 380 Total project cost = 2600+380 = 2980 2. Assume you have drawn your network diagram Activity Precedes Nd Cd Nc A - 9 6 10 B - 8 5 9 C A 5 4 7 D A 8 6 9 E B 7 3 7 F C 5 5 5 G D,E 5 2 8 Activity Dependency Tn (Normal Time) Weeks Tc (Crashed Time) – Weeks A 9 6 Cc (Crashed Cost in Thousand ZAR) 16 Cn Cost (Normal Slope Cost in Thousand ZAR) 10 2 Time Constraint B 8 5 18 9 3 3 3 C A 5 4 8 7 1 1 D A 8 6 19 9 5 2 E B 7 3 15 7 2 4 F C 5 5 5 5 - 0 G D,E 5 2 23 8 Your CEO has instructed that the project be completed in 15 weeks. What is the least costly way to reduce the project to 15 weeks? And how much is the new budget of the project? (Show all your steps and assumptions). ADG – 22; ACF – 19; BEG – 20 Step 1: Reduce A by 2 ADG = 20 ACF = 17 BEG = 20 Amount spent in Step 1 = 2*2 = 4 We now have 2 critical paths Step 2: Reduce A and E by 1 each ADG = 19 ACF = 16 BEG = 19 Amount spent in Step 2 = 2*1 + 2*1 = 4 Step 3: Reduce G by 3 weeks ADG = 16 ACF = 16 BEG = 16 Amount spent in Step 3 = 3*5 = 15 Step 4: Reduce E,D and C by 1 each ADG = 15 ACF = 15 BEG = 15 Amount spent in Step 4 = 2*1 + 5*1 + 1*1 = 8 Amount in total spent to get to 15 weeks= 4+4+15+8 = 31K ZAR The normal cost of the project is 55K. Total spent on project: 55K + 31K = 86K ZAR 5 3