Method Of Statement info@gtek.com.sa Save Energy Live Green www.gtek.com.sa Methodology Site Planning & Preparation Methodology 1-Site Planning & Preparation Before installation takes place, the following pre-installation task is essential: Identify and ensure that pertinent documents (e.g. shop/coordination drawings, Method Statement for Solar Panel) are latest and approved. *Conduct site safety briefing prior to commencement of work. Identify and obtain appropriate installation tools and equipment. Determine the staffing required and assign tasks to team members. Secure the working area and set up signs (where applicable) to alert anyone of danger in the area. Notify appropriate personnel that work is to begin. During the nighttime, working areas should be marked prominently with lights and there should be an arrangement to ensure the uninterrupted operation of these lights throughout the darkness. 2-Handling of Materials. During all the transportation, please make sure there is no strenuous vibration on the module. Because it may cause cell micro cracks or damage the module. Upon receiving the materials, all must be inspected and ensured that there are no manufacturing defects or delivery damages. The materials shall be handled with care and shall be stored in designated areas. The manufacturer’s operational control procedure manual for handling installations should be followed as much as possible. info@gtek.com.sa Save Energy Live Green www.gtek.com.sa 3-Methodology Procedure Site Planning & Preparation Methodology Put on the necessary PPE and slowly unpack the solar panels and hardware The framework, solar panels, and fixings will all be mechanically raised to the installation location. 1-Site Planning & Preparation Before installation takes theoffollowing pre-installation task is essential: Measure and draw out theplace, position the framework. Always adhere to the manufacturer’s installation instructions and any site-specific drawings. Identify and ensure that pertinent documents (e.g. shop/coordination drawings, Method Statement for Solar Panel) latestof and Survey the area for the exactare position theapproved. solar panel location. Prepared railing and framework for construction. ite ertky,bth riefin gapcreioirt to mm ment of work. t tohned“uYc”t frsa msa ewfo n pl onctohe greonucned. Lif*C do taac in eapp opr e et ine st.allation tools and equipment. inbpl witrh coiantcr SId etetn htif e ypoalnes e estteaffi reiqeudi/rfierdmaendduap,ssi ginldtathseksroo to fite WDheetnerm theinceotnhcr hansg dr bu na gm ormce am nobpeyrs. structure on top of the “Y” frame. g lianrgeatoatnhe d se p ysig w.here applicable) to alert anyone of danger in FiSxetcu here frathmeeworkinrai catnuop ornsro(of the area. wgork is bl toebtreegninch. . Nothtiefyelaepcptrriocparliat coenpneercstioonnne ploith na t,tdi a ca To e rnsi,gihntvtier mteer , sw,or kin alraetaorss.should be marked prominently with lights and there SD etuuripngmtehte an d giso should be an arrangement to ensure the uninterrupted operation of these lights throughout the darkness. Put solar panels on the railing. Installation Battery Box. 2-Handling of Materials. During all the transportation, please make sure there is no strenuous vibration on the module. Because it may cause cell micro cracks or damage the module. All DC cables should be marked “DANGER Live DC.” Upon receiving the materials, all must be inspected and ensured that there are no manufacturing defects or delivery damages. mlaetseri ao lsulsdhal enhfarn d ewpita hncel as’ re baanck d s hto allthbee csatoblre dtrin de DT Chceab sh bel bru odle m th enc hs. ignated areas. The manufacturer’s operational control procedure manual for handling installations should be followed as much as possible. According to the plans, install wires and conduits inside the trench. 3-Procedure. Before connecting to the supply, use an electrical test meter to make sure it is dead. All electrical parts and warning signals should be labeled. info@gtek.com.sa www.gtek.com.sa Affix AC cables to the equipment’s terminal boxes for the isolator, meter, and inverter. Complete all cable connections, both DC and AC. Verify the security and integrity of all cables and connections. All non-live testing will be done before the system is restarted. 3-Testing process -Make sure that all string is connected perfectly. -Disconnect the string from the inverter side. -Do the Voc test by AVO Meter to ensure that all string’s voltage is in the accepted range. -Connect the I-V device at the end of the strings. -Check the Voc, Isc, and the insulation of cables. -Compare the ideal with the actual measurement. -Check the string polarity. -Disconnect the device cables after finishing the test. info@gtek.com.sa Save Energy Live Green www.gtek.com.sa