PROCESS DATA SHEET DESIGN DATA BRANCHES & INTERNALS 1. Equipment No.: T-1201D/E No. Of: 2 (TWO) 2. Equipment Name: Phosphoric Acid Tanks 3. Type: Fixed Cone Roof (Vertical Cylindrical) 4. Material Handled: Phosphoric Acid1 Sp. Grt.: 1.72 o 5. Vapor Pressure: negligible at 40 C 6. Op. / Design Pressure: Atm. / As per code o 7. Op. / Design Temp.: 40 / 65 C 8. Corrosion Allow. : Nil 2 As per code 9. Design Code: API 650 10. Inside Dia.: 22,000 mm 11. St.Height / Length: 10,500 mm 12. MATERIALS 13. Shell : IS 20623 Lining:Rubber Thk:10/5mm5 3 14. Heads: IS 2062 Jacket: 15. Internal: 16. Nozzles: Carbon Steel with Rubber Lining. 17. Supports: Brackets: 18. Pipes, Internal:SS904L External: 19. Painting, Internals: External: 20. Insulation Type & Thk.:NA 2 21. Gaskets: PTFE 22. Others (List): 23. Remarks: 11FT021/15 1. 2. 3. 4. 5. 32644-11-SE-T1201D/E PAGE 1 OF 1 R2 STORAGE TANK Phosphoric acid contains 54% P2O5, 2-4% Sulphuric Acid & 1-2% Gypsum Solids. Specific gravity varies from 1.63 to 1.7 Mild steel as per IS 2062 Nozzles shall be ASTM A 106 Gr.B 10 mm for bottom & 5 mm for shell/roof SKETCH Tag A1 A2 A3,7 A4 A5,6 B1,2 B3,4 O S1 L1 L2 D1 V M1-5 M6-7 Description Size Inlet nozzle from sump 80 Inlet nozzle from ship 500 Inlet nozzle for circulation line 100 Inlet nozzle for circulation line 200 Inlet nozzle for circulation line 100 Outlet nozzle 250 Outlet nozzle 250 Overflow nozzle 200 Spare nozzle 150 Level indicator (radar) nozzle 100 Level gauge (float) nozzle 250 Drain nozzle 200 Vent nozzle 200 Roof Manhole 600 600X600 Shell Manhole (Cleanout Door) INTERNALS & ACCESSORIES 1. Float and scale arrangement for level measurement 2. Deleted 2 No 1 1 2 3 1 2 2 2 2 1 1 1 3 2 1 1 5 2 3. Ship unloading line nozzle A2 shall be provided with dip pipe of 400 NB size & circulation nozzle A4 shall be provided with dip pipe of 100NB size. Both the dip pipes shall extend up to centre line of overflow nozzle. 2 Breather Valve Flame Arrester Foam Chamber Nominal Capacity: 3480m3(5900MT) Actual Capacity: 3064m3 2 2 Comments Incorporated BV MR KVR 01/07/2020 1 Comments Incorporated BV MR KVR 19/06/2020 0 Issued for Comments GKS AT VKS 10/12/2020 Rev Details By Chkd. Apprd. Date FACT ENGINEERING AND DESIGN ORGANISATION 2 Project: Construction of Additional Phosphoric Acid Storages at Q-10 Berth, WI. Client: M/s. FACT-CD PROCESS DATA SHEET 32644-11-SE-P3202A/B PAGE 1 OF 1 R2 PUMP Equipment No. Equipment Name No. Of Type of Equipment Operating Conditions Fluid Handled Analysis Pumping Temperature, oC Density &Viscosity at Pumping Temperature Vapor Pressure at P.T & pH value Operating Level Units Capacity m3/h Suction Pressure kg/cm2G o Suction Temperature C Discharge Pressure kg/cm2G Differential Pressure kg/cm2 Priming Net Positive Suction Head Duty Drive Capacity Control Location Area Necessity to start against system pressure Material of Construction Casing / Cylinders Impeller / Pistons Shaft Drive Turbine Steam Details Inlet / Outlet Pressure, kg/cm2G Inlet / Outlet Temperature, oC Packing/Mechanical Seal Flashing Arrangements (From Mfr) P-3202A/B Phosphoric Acid Transfer Pumps 1 Working 1 Standby & Centrifugal Reciprocating Phosphoric acid 54% P2O5, 2-4%H2SO4, 1-2% Gypsum solids. 400C 1630 to 1700kg/m3 , 65 cP Negligible Min / Normal / 175 0.07 / 0.07 40 / 40 2 / 4.0 / 3.93 MLC Available:6.511 Continuous / Electric Motor Local / Indoor / Hazardous / Yes 0 Warehouse Standby ………. / / / / / / Maximum 175 40 4.0 3.93 MLC Required (From Mfr.) ……. Intermittent Turbine Using ……….. …………………. 2 Remote / Auto Outdoor Non Hazardous No CD4MCu CD4MCu CD4MCu Normal Minimum Maximum / / / / / / Mechanical Seal 2 Self Flushing As per API Plan No. …………………… Using …………………… at …… kg/cm2G & …..oC 11FT028/15 Minimum Flow Requirements, m3/h (From Mfr.) Shut-off Head (From Mfr.) Remarks: 1. NPSH indicated is minimum considering Tank Pad Elevation as 1m,LLLL as 1.1m& Pump suction nozzle CL elevation as 0.8 m. 2 Issued for Comments BV MR KVR 01.07.2020 0 Issue for Comments BV MR KVR 08.06.2020 1 Rev Issued for Comments Details BV By MR Chkd. KVR 19.06.2020 Apprd. Date FACT ENGINEERING AND DESIGN ORGANISATION Project: Construction of Additional Phosphoric Acid Storage Tanks at Q-10 Berth, WI Client: M/s. FACT-CD PROCESS DATA SHEET 32644-11-SN-L001 PAGE 1 OF 1 R1 LEVEL INSTRUMENTS Sl. No. 1 Tag No. LI-101/2 P&ID No. 32644-11-PD-001 Service / Location Storage Tank, T-1201D/E Type Radar L (Note:2)& P Mounting (L/P) Fluid Phosphoric Acid (54% Conc.) Min. & Max. Level, mm 1,100 & 9,160 Pressure, kg/cm2G Atmospheric Temperature, oC Ambient Density, kg/m3 1630 - 1700 Range, mm 0 – 10,500 Material Of Construction Nozzle Size & Spec. 1 SS 1 100 NB & ASTM A 106 Gr.B with Rubber Lining Remarks 11FT005/15 Notes: 1. Level Instrument shall Indicate, Transmit & Alarm. 2. Local indication shall be available at the ground level. 1 Issued for Comments BV MR KVR 01/07/2020 0 Issued for Comments BV MR KVR 08/06/2020 Rev Details By Chkd. Apprd. Date FACT ENGINEERING AND DESIGN ORGANISATION Project: Construction of Additional Phosphoric Acid Storage Tanks at Q-10 Berth, WI. Client: M/s. FACT – CD PROCESS DATA SHEET 32644-11-SE-P3203 PAGE 1 OF 1 R1 PUMP Equipment No. Equipment Name P-3203A/B 1 Phosphoric Acid Sump Pump 1 1 Standby & 1 Working No. Of Type of Equipment Operating Conditions Fluid Handled Analysis Pumping Temperature, oC Phosphoric acid 54% P2O5, 2-4%H2SO4, 1-2% Gypsum solids. 400C Density &Viscosity at Pumping Temperature Vapor Pressure at P.T & pH value Operating Level Units Capacity m3/h Suction Pressure kg/cm2G o Suction Temperature C 1630 to 1700 kg/m3 , 65 cP Negligible Min / / 0.034 / 40 / Discharge Pressure Differential Pressure Priming Net Positive Suction Head Duty Drive Centrifugal Reciprocating 2 kg/cm G kg/cm2 Normal 25 40 / / MLC Available:6.281 Continuous / Electric Motor Capacity Control Location Area Necessity to start against system pressure Material of Construction Casing / Cylinders 0 Warehouse Standby ………. 4.4 / / / / Maximum 25 / / 4.4 4.36 40 MLC Required (From Mfr.) ……. Intermittent Turbine Using ……….. …………………. Local / Indoor / Hazardous / Yes Remote / Outdoor Non Hazardous No Auto CD4MCu CD4MCu Impeller / Pistons Shaft Drive Turbine Steam Details Inlet / Outlet Pressure, kg/cm2G Inlet / Outlet Temperature, oC Packing/Mechanical Seal CD4MCu Normal / / Mechanical Seal Flashing Arrangements (From Mfr) Minimum / / Maximum / / Self Flushing As per API Plan No. …………………… Using …………………… at …… kg/cm2G & …..oC 11FT028/15 Minimum Flow Requirements, m3/h (From Mfr.) Shut-off Head (From Mfr.) Remarks: 1. NPSH indicated considering minimum submergence level as 200 mm 1 Issue for Comments BV MR KVR 01/07/2020 0 Issue for Comments BV MR KVR 19/06/2020 Rev Details By Chkd. Apprd. Date FACT ENGINEERING AND DESIGN ORGANISATION Project: Construction of Additional Phosphoric Acid Storage Tanks at Q-10 Berth, WI. Client: M/s. FACT-CD PROCESS DATA SHEET 32644-11-SN-L002 PAGE 1 OF 1 R1 LEVEL INSTRUMENTS 1Si. No. 1 Tag No. LS-103 P&ID No. 32644-11-PD-001 Service / Location Phosphoric Acid/Sump Pit (S-1201) Type Float type Mounting (L/P) P Fluid Phosphoric Acid (54% Conc.) 1 Minimum Level, mm NA Pressure, kg/cm2G Atmospheric Temperature, oC Ambient Density, kg/m3 1630 – 1700 350 mm1 from bottom Set point PVC/Equivalent Material Of Construction 1 Remarks Notes: 1. Set point indicated is assuming pump minimum submergence level as 200 mm 1 11FT005/15 Project: Construction of 1 Issued for Comments BV MR KVR 01/07/2020 0 Issued for Comments BV MR KVR 15/06/2020 Rev Details By Chkd. Apprd. Date FACT ENGINEERING AND DESIGN ORGANISATION Additional Phosphoric Acid Storage Tanks at Q10 Berth, WI. Client: M/s. FACT – CD PROCESS DATA SHEET 32644-11-SN-P001 PAGE 1 OF 1 R1 PRESSURE INSTRUMENTS Sl. No. Tag No. P&ID No. Service/Location 1. 2. 3. 4. 5. PG-101 PG-102 PG-103 PG-104 PG-105 32644-11-PD-001 32644-11-PD-001 32644-11-PD-001 32644-11-PD-001 32644-11-PD-002 Liquid/200-PA-013A-1G10-NI Liquid/200-PA-014A-1G10-NI Liquid/80-PA-018C-1G10-NI Liquid/80-PA-018D-1G10-NI Liquid/80-WR-038-1G10-NI Type Mounting (L/P) Pressure kg/cm2G Operating Temperature o C Range kg/cm2G Nozzle/Line Size & Spec. Diaphragm Diaphragm Diaphragm Diaphragm Diaphragm L L L L L 4.0 4.0 4.4 4.4 1 40 40 40 40 40 0 - 10 0 - 10 0-10 0-10 0-5 50 NB & 1G10 50 NB & 1G10 50NB & 1G10 50NB & 1G10 50NB & 1G10 11FT003/15 Remarks: 1. For Sl No.1 to 4, Liquid is 54% Phosphoric acid. 2. For Sl No:5 Liquid is water. 1 Issued for comments BV MR KVR 01/07/2020 0 First Issue BV MR KVR 30/06/2020 Rev Details By Chkd. Apprd. Date FACT ENGINEERING AND DESIGN ORGANISATION Remarks Project: Construction of Additional Phosphoric Acid Storage Tanks at Q-10 Berth, WI Client: M/s. FACT-CD PROCESS DATA SHEET Corrosion Allowance 1.5 mm 32644-11-SP-001 PAGE 1 OF 1 R0 PIPING SPECIFICATION Stream / Fluid Phosphoric Acid 54% Design Pressure, kg/cm2(G) Design Temperature, OC Nominal Pipe Size, NB Piping Class 10.0 Rating 55 150# 50 80 100 150 200 250 300 Wall thickness Pipe Sch.40 Sch.40 Sch.40 Sch.40 Sch.20 Sch.20 Sch.20 mm/Schedule/Class Fittings Sch.40 Sch.40 Sch.40 Sch.40 Sch.20 Sch.20 Sch.20 Part Standard Specification Pipe ANSI B 36.10 API 5L Gr.B SMLS for 50 NB to 200 NB, ERW for 250 NB & above. ANSI B16. 9 ASTM A 234 WPB 50 NB to 200 NB, 3 weld mitre for 250NB & above. Tee ANSI B16. 9 ASTM A 234 WPB 50 NB to 200 NB. Fabricated for 250NB & above. Reducer ANSI B16. 9 ASTM A 234 WPB 50 NB to 200 NB. Fabricated for 250NB & above. ANSI B 16.5 ASTM A 105, FF. Lined with 4mm thk Butyl rubber. ANSI B 16.5 ASTM A 105, FF, 50 NB AND ABOVE IS 1364/4218 STUD BOLT & HEX. NUTS, ASTM A 193 Gr B7/ A 194 Gr.2H ANSI B 16.21 EPDM, FF, 5 mm thk Elbow R=1.5D 1G1O Cap Saddle Blind Flange SW Slip-on Bolts&Nuts Gasket Gate Valve Check Valve SW FLGD SW FLGD Ball Valve FLGD BS 5351 Short pattern, Reduced bore, FF, Body & ball- A 351 Gr.CN7M Diaphragm Valve FLGD BS 5156 Weir type, FF, Body-IS 210 Gr. FG 200, Lining &Diaphragm-Butyl rubber (Tag No: DV 110) Remarks: 1. All pipes and fittings shall have flanged ends. 2. Maximum length of flanged pipe shall be 5500mm. 3. Internal surface and face of flange of each section shall be lined with 5 mm thk. Natural rubber. 4. Rubber lining and testing shall conform to IS 4682 (Part 1) 0 For Comments Rev Details BV MR Process By Piping Process KVR Piping Chkd. Process 19/06/2020 Piping Apprd. FACT ENGINEERING AND DESIGN ORGANISATION Date Project: Construction of Additional Phosphoric Acid Storages at Q-10 Berth, WI. Client: M/s. FACT-CD PROCESS DATA SHEET 32644-11-PC-001 PAGE 1 OF 2 R0 PIPING MATERIAL CLASSIFICATION Designation used for Piping material classification will consists of a four letter code “RBMS” as detailed below: R B M S Code for Rating (See table 1 below) Code for Base Material (See table 2 below) Code forMaterial Standards (See table 2 below) Code forSpecial Requirements (See table 1 below) Table1 Code for Rating Code for Special requirements Code “R” Rating Code “S” 0 125 # O No. special requirements 1 150 # S Seamless 3 300 # J Jacketed 6 600 # B IBR T Tubing -- -- -- -- X Special service (Brick Lining) X Unclassified (Duct) Special requirements Table 2 Code for Base Material Code “B” A B C Code for Material Standards Base Material Carbon Steel Low Alloy Steel Stainless steel Code “B” Material Standards 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 ASTM A106 GR.B ASTM A53 GR.B ASTM A333 GR.1 IS 226 IS 1239 IS 2002 ASTM A516 GR.70 ATSM A204 GR.B ASTM A387 GR.2 ASTM A335 GR.P11 ASTM A335 GR.P22 ASTM A312 TP304 ASTM A312 TP304L ASTM A312 TP316 ASTM A312 TP316L ASTM A312 TP321 ASTM A312 TP321H ASTM A240 TP304 11FT038//15 Project: Construction of Additional Phosphoric Acid Storage Tanks at Q10 Berth, WI 0 Issued For Comments BV MR KVR 19/06/2019 Rev Details By Chkd. Apprd. Date FACT ENGINEERING AND DESIGN ORGANISATION Client: M/S. FACT – CD PROCESS DATA SHEET D Cast iron 1 CHROMIUM C. I. E Galvanised iron 1 IS 1239 GALV. 1 2 3 4 5 6 1 2 3 4 5 6 HDPE PVC FRP F 32644-11-PC-001 PAGE 2 OF 2 R0 PIPING MATERIAL CLASSIFICATION Plastics RUBBER PTFE GLASS LEAD G Lined (Base Material A1O) H Non-ferrous metals 1 COPPER I Graphite 1 IMPERVIOUS GRAPHITE J Glass 1 BOROSILICATE GLASS Remarks 11FT038//15 Project: Construction of Additional Phosphoric Acid Storage Tanks at Q10 Berth, WI 0 Issued For Comments BV MR KVR 19/06/2019 Rev Details By Chkd. Apprd. Date FACT ENGINEERING AND DESIGN ORGANISATION Client: M/S. FACT – CD PROCESS DATA SHEET 32644-11-SE-P3204 PAGE 1 OF 1 R0 PUMP Equipment No. Equipment Name P3204 Rain Water Pit Pump No. Of Type of Equipment Operating Conditions Fluid Handled Analysis Pumping Temperature, oC 1 Working Centrifugal 0 Warehouse Standby ………. Water Water 400C Density &Viscosity at Pumping Temperature Vapor Pressure at P.T & pH value Operating Level Units Capacity m3/h Suction Pressure kg/cm2G o Suction Temperature C Discharge Pressure Differential Pressure Priming Net Positive Suction Head Duty Drive 0Standby & Reciprocating 1000 Kg/m3 0.074Kg/cm2 Min -0.308 40 2 kg/cm G kg/cm2 MLC Available:6.50 Continuous / Electric Motor Capacity Control Location Area Necessity to start against system pressure Material of Construction Casing / Cylinders Local / Indoor / Hazardous / Yes / / / / Normal 25 / / 1 40 / / / / Maximum 25 / / 1 1.308 40 MLC Required (From Mfr.) ……. Intermittent Turbine Using ……….. …………………. Remote / Outdoor Non Hazardous No Auto CD4MCu CD4MCu Impeller / Pistons Shaft Drive Turbine Steam Details Inlet / Outlet Pressure, kg/cm2G Inlet / Outlet Temperature, oC Packing/Mechanical Seal CD4MCu Normal / / Minimum / / Maximum / / Packing Flashing Arrangements (From Mfr) Self Flushing As per API Plan No. …………………… Using …………………… at …… kg/cm2G & …..oC Minimum Flow Requirements, m3/h (From Mfr.) Shut-off Head (From Mfr.) Remarks: 1. Maximum elevation for discharge head is assumed as 5 meters. 11FT028/15 Project: : Construction of Additional Phosphoric Acid Storage Tanks at Q10 Berth, WI. 0 Issue for Comments BV MR KVR 30/06/2020 Rev Details By Chkd. Apprd. Date FACT ENGINEERING AND DESIGN ORGANISATION Client: M/s. FACT-CD PROCESS DATA SHEET 32644-11-SN-L003 PAGE 1 OF 1 R0 LEVEL INSTRUMENTS Si. No. 1 Tag No. LS-104 P&ID No. 32644-11-PD-002 Service / Location Rain Water Sump Pit (S-1202) Type Float type Mounting (L/P) P Fluid Water Minimum Level, mm NA Pressure, kg/cm2G Atmospheric Temperature, oC Ambient Density, kg/m3 1000 350 mm1 from bottom Set point PVC Equivalent Material Of Construction Remarks Notes: 1. Set point indicated is assuming pump minimum submergence level as 200 mm. Project: : Construction of 11FT005/15 Additional Phosphoric Acid Storage Tanks at Q10 Berth, WI. 0 Issued for Comments BV MR KVR 01/07/2020 Rev Details By Chkd. Apprd. Date FACT ENGINEERING AND DESIGN ORGANISATION Client: M/s. FACT – CD TECHNICAL PROCUREMENT SPECIFICATION S.No. 1 PAGE Description Doc. No. 32644-02-PS-001 SW 32644-02-PS-001AT ATTACHMENTS 1 OF 1 R4 Rev. No. with Issue No. of pages 1 2 3 4 5 6 2 A 0 0 0 0 0 Scope of Work - Storage Tanks 2 32644-01-PS-001 SW Scope of Work - Pumps 2 - 0 0 0 0 0 3 32644-02-PS-001 SPL Special Requirement of the Project - Storage Tanks 5 A 0 0 1 1 1 4 32644-01-PS-001 SPL Special Requirement of the Project - Pumps 5 - 0 0 0 0 1 5 32644-02-PS-001 VDR Vendor Data Requirements - Storage Tanks 1 A 0 0 0 0 0 6 32644-01-PS-001 VDR Vendor Data Requirements - Pumps 1 A 0 0 0 0 0 7 32644-01-PS-001 INS Scope of Inspection and Tests - Pumps 1 A 0 0 0 0 0 8 32644-02-PS-001 VDI Vendor Data Index 1 A 0 0 0 0 0 9 32644-02-PS-001 SPR Spares - Storage Tanks 1 A 0 0 0 0 0 10 32644-01-PS-001 SPR Spares - Pumps 1 A 0 0 0 0 1 11 32644-01-PS-001 LD Equipment Lubrication data sheet 1 A 0 0 0 0 0 12 32644-01-PS-001 SV Sub Vendor List 1 A 0 0 0 0 0 DATA SHEET & DRAWINGS 13 32644-01-DA-001 Data Sheet Phosphoric Acid Transfer Pumps 3 - 0 0 1 1 2 14 32644-01-DA-002 Data Sheet Phosphoric Acid Sump Pumps 5 - A A 0 0 1 15 32644-01-DA-003 Data Sheet Rain Water Pit Pump 3 Dwg. for Phosphoric Acid Storage Tank 32644-02-DG-10618 (T-1201 D / E) ENGINEERING SPECIFICATIONS 16 0 1 A 0 1 2 2 3 17 02 ES 001 / 2010 Vendor Data Submission Procedure 4 - - - - - - 18 02 ES 032 / 2010 Storage Tank 11 - - - - - - 19 02 ES 023 / 2010 Painting 13 - - - - - - 20 02 ES 030 / 2010 Rubber Lining 9 - - - - - - 21 02 ES 041 / 2010 Anchor Bolt 2 - - - - - - 22 01ES 010 / 94 Centrifugal Pump for General Purpose 7 - - - - - - 23 01ES067 / 19 Centrifugal Pump for Heavy Duty Service 5 - - - - - - 02 DS 002 / 2010 Anchor Bolt 3 - - - - - - DESIGN STANDARDS 24 25 02 DS 006 / 2010 Earthing Boss 1 - - - - - - 26 02 DS 020 / 2010 Name Plate 3 - - - - - - 27 02 DS 022 / 2010 Platforms 1 0 0 0 0 0 0 28 02 DS 027 / 2010 Spiral Stairway 2 0 0 0 0 0 0 29 02 DS 029 / 2010 Storage Tanks Accessories 5 - - - - - - 30 02 DS 007 / 2010 Float Level Indicator 2 1 1 1 1 1 1 32644-02-PS-001 SIW Schedule of Items of Work - Mechanical 1 A 0 1 1 2 3 32644-02-PS-001 RN Rate of Addition/Deletion of Nozzles 1 A 0 0 1 1 1 PRICE BID 31 32 Note : 1. The receipt of all attachments shall be checked and asertained. 2. All attachments of this TPS shall be retained since only revised sheets, if any, shall be issued. 4 06.07.20 Revised as marked GPG SK AAN 3 24.06.20 Revised as marked GPG SK AAN 2 22.06.20 Revised as marked GPG SK AAN 1 17.06.20 Revised as marked GPG SK AAN 0 10.06.20 Tank capacity revised GPG SK AAN A 05.05.20 For Review GPG SK AAN REV.NO. DATE DESCRIPTION PREPD CHKD APPRD FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION ITEM: 32644-02-PS-001 SW SCOPE OF WORK STORAGE TANK PAGE 1 OF 2 PHOSPHORIC ACID STORAGE TANKS (2 nos.) R0 (space for vendor’s name, signature & seal) EQPT. Nos.: 1 T - 1201 D/E The scope of work for the equipment listed above shall include design, manufacture, supply of material and engineering work as tick marked below. Vendor shall fill in the column marked as “offer from vendor” and return the same along with the offer, without which the offer will be considered as incomplete. Sl. No Reqd. YES YES 23 24 YES 25 YES 26 5 Detailed design Drawing Preparation Submission of documents as per VDR Procurement of materials Fabrication 6 Testing and Inspection YES Equipment components 7 Shop assembly NO 27 Shell 1 2 3 4 Description Reqd. Inspection Third party inspection Drawings for CCE Approval YES NO Calibration YES YES YES Site assembly YES 28 Shell stiffeners YES 9 Equipment erection External surface preparation Painting (CS) Internal Rubber Lining Corrosion inhibitor for internal surface Corrosion inhibitor for external surface YES 29 YES YES 30 YES YES 31 32 Roof Roof Stiffeners / Curb angle. Roof support structure Bottom plate YES YES NO 33 Nozzles YES NO 34 Flanges YES 11 12 13 14 Companion flanges / bolts / nuts / gaskets for nozzles (for Manway & spare nozzles only) Bolts, nuts & gaskets YES 15 Pickling NO 35 16 Passivation NO 36 17 Hydrotest at shop NO 37 Wind girder, if required YES 18 19 Hydrotest at site Pneumatic test at shop YES NO 38 39 Agitator supports Platform & Handrails NO YES 20 Pneumatic test at site YES 40 Ladder NO NO 41 Spiral Stairway YES YES 42 Gauge Hatch NO Packing, marking and forwarding Supply of spares as per spare part list 21 22 Offer from vendor NO 8 10 00FT013/94 00FT013/94 Offer from vendor Sl. No Description YES YES 0 A 09.06.20 05.05.20 Tank capacity revised For Review GPG GPG SK SK AAN AAN REV. NO. DATE DESCRIPTION PRPD CHKD APPRD FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION Sl. No Description 32644-02-PS-001-SW SCOPE OF WORK STORAGE TANK Reqd. 42 Supporting leg/bracket 43 Anchor frame NO 44 Anchor bolts/nuts NO 45 Template for base ring NO 46 Supporting frame for connected equipments. NO 47 Wire mesh NO 48 Demister & supports Internal pipes, flanges, supports, bolts, nuts & gaskets NO Offer from vendor Sl. No PAGE 2 OF 2 Description NO Internals: 49 50 51 NO Baffles NO Internal ladder rungs NO 52 Internal clips / anchors etc. for lining NO 53 Refractory / castable lining NO 54 Insulation clips NO 55 Fire proofing clips NO Platform & ladder clips YES 56 Pipe support clips YES External attachments: 57 58 Support clips & brackets for other eqpt. Manhole/hand hole davit/hinge NO YES 59 Name plate YES 60 Earthing boss YES 62 Tank bottom/drain noz. YES 63 Relief valve / Breather valve with sight glass NO 64 Wind analysis YES 65 Seismic analysis YES 66 Overflow nozzles (As Rqd) YES 67 Flame Arrestor NO 68 Foam Chamber NO 69 Safety Plug NO 70 Float Level Indicator YES FACT ENGINEERING AND DESIGN ORGANISATION Reqd. R0 Offer from vendor TECHNICAL PROCUREMENT SPECIFICATION SCOPE OF WORK (Phosphoric Acid Pump) TPS NO. 32644- ITEM : CENTRIFUGAL PUMP 32644-01-PS-001 SW PAGE 1 OF 2 EQPT. NO. The scope of work for the equipments listed above shall include design,manufacture ,supply of materials and engineering work as detailed below. Sl. Description No Reqd. Remarks X 1.0 Pump 2.0 Auxiliary piping within the confines of the baseplate X X X X Casing drain and vent piping with valve & flanged connection Cooling water piping inlet & outlet valves with flanged connection Self or external flushing piping with flanged connection Quench water or steam piping with flanged connection & traps 3.0 Coupling with nonspark coupling guard IF APPLICABLE IF APPLICABLE For jacketed pumps X Between pump and driver Between pump and gear Between gear and driver 4.0 Base 4.1 Common baseplate X For pump & driver MOC: SS 316 L For pump & gear For pump, gear & driver 4.2 Separate baseplate 4.3 Mounting flange for pump X 5.0 Lube oil system 5.1 Common oil system for pump and gear / driver 5.2 Oil system for pump only 5.3 Complete lube oil system including X As applicable 01FT010/94-R1 Shaft driven main pump Motor driven standby pump 5.4 Interconnecting lube oil piping X Between oil console and pump 6.0 Gear unit 7.0 Inspection and testing X 0 09-06-2020 FOR ENQUIRY LA SK AAN REV.NO. DATE DESCRIPTION PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION Sl. No SCOPE OF WORK (Phosphoric Acid Pump) Description 32644-01-PS-001 SW PAGE Reqd. 2 OF 2 R0 Remarks 8.0 Painting Prime coating only Prime coating and finish paint 9.0 Packing Domestic packing Export packing Rust prevention for long term storage 10.0 Special tools 11.0 Spare parts Construction and commissioning Mandatory Spares Two years operation - ( Purchaser reserves full right to purchase or not to purchase the item fully or partially as per rate quoted by the vendor.) 12.0 Foundation bolts and nuts 13.0 Driver Main electric motor for pump 14.0 Mounting driver Mounting driver on baseplate Mounting driver half coupling Provide shim plates and set bolts for mounting driver 15.0 Miscellaneous Noise attenuation cover X X X X X IF APPLICABLE 6 months IF ANY X X X (Shall not be considered for price bid evaluation) X MoC - SS 316L X X X X * * (If required) X X X X As per VDR Level switch for sump pump Strainer for sump pump suction Minimum flow recirculation valve Mechanical Seal 16.0 Erection 17.0 Commissioning 01FT010/94-R1 18.0 Drawings & documents FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION SPECIAL REQUIREMENTS OF THE PROJECT PHOSPHORIC ACID STORAGE TANKS 32644–02–PS–001-SPL Page 1 of 5 R1 TPS NO. : - ITEM : PHOSPHORIC ACID STORAGE TANK (2 NO’S.) ITEM NO. : T 1201 D / E PROJECT : CONSTRUCTION OF PHOSPHORIC ACID STORAGE TANKS AND ASSOCIATED FACILITIES AT Q10 BERTH, WI. CLIENT : FACT-CD LOCATION : W.ISLAND 1 22-06-2020 Revised as marked GPG SK AAN 0 10-06-2020 Tank capacity revised GPG SK AAN A 08-05-2020 For Review GPG SK AAN REV. DATE DESCRIPTION PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION 1.0 SPECIAL REQUIREMENTS OF THE PROJECT PHOSPHORIC ACID STORAGE TANKS 32644–02–PS–001-SPL Page 2 of 5 R1 GENERAL DESCRIPTION FACT-CD has proposes to install 2 nos. additional Phosphoric Acid Storage Tanks & associated facilities at W. Island adjacent to the existing three tanks for the purpose of improving the Phosphoric Acid handling capability as a part of new NP Plant. 2.0 SCOPE OF WORK The EPC Contractor scope includes but not limited to the following: 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10 2.11 2.12 2.13 2.14 2.15 2.16 2.17 2.17 Design of the equipment based on the data sheet, drawing and specifications listed in the “Attachments” sheet. Detailed Engineering. Submission of mechanical design calculations and fabrication drawings for review by FEDO/FACT-CD Submission of Drawings / Documents as per Vendor Data Requirements (Doc.No. 32644-02PS-001-VDR). Vendor shall do the Wind and Seismic analysis and submit the same for review by FEDO/FACT-CD. Procurement of all materials and bought-out items such as CS plates and structurals, nozzle pipes and flanges, anchor bolts and fasteners, material for Rubber lining, materials for painting, etc. Preparation and obtaining approval of Welding Procedure Specification, Procedure Qualification Record and Welder Performance Qualification. Fabrication and Erection of the equipment at site. Inspection and Testing of the Tanks including Hydro Testing and submission of Testing Procedure for approval by FEDO/FACT-CD. Painting of the storage tank and structurals attached to the tank including supply of materials. Rubber lining of the Storage Tank including supply of materials. Pad plates for fixing brackets, pipe supports etc. Pad plates and cleats required for fixing platforms and stairways. Structurals such as stairway, hand rails and platforms. Calibration of the Tanks. Connected piping including Supply, Fabrication & Erection as per Schedule of Items of Work, Specifications and Drawings attached. Supply of Spare Parts as per Spare parts list (Doc.No. 32644-02- PS- 001-SPR). Any other items covered in Doc. No. 32644-02-PS-001-SW and other documents / drawings attached with the enquiry but not specifically mentioned above. 3.0 3.1 DESIGN APPLICABLE CODES & STANDARDS CODES DESCRIPTION IS 803 : 1976(R2005) Code of Practice for Design Fabrication and Erection of Vertical Mild Steel Cylindrical Welded Oil Storage FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION SPECIAL REQUIREMENTS OF THE PROJECT PHOSPHORIC ACID STORAGE TANKS CODES 32644–02–PS–001-SPL Page 3 of 5 R1 DESCRIPTION Tanks th API 650, 12 Ed. Inc. Add.3 Errata 2 Annex I IS 4682-1 : 1994 IS 875(Part 3) : 2015 Amendment 1 IS 1893 (Part 1) : 2016 IS 1893 (Part 4) : 2015 IS 2062 : 2011 ASME/ANSI 3.2 3.3 3.4 Welded Steel Tanks for Oil Storage Code of Practice for Lining of Vessels and Equipment for Chemical Processes - part 1: Rubber Lining Design loads (Other than Earthquake) for Buildings and structures Part 3 -Wind Loads. Criteria for Earthquake Resistant Design Structures Part 1 – General Provisions and Building. Criteria for Earthquake Resistant Design Structures Part 4 – Industrial structures including Stack like structures. Hot Rolled Steel for Medium and High Tensile Structural Purposes Pipes, Flanges, Fittings and Valves 3.6 3.7 3.8 Tank shall be designed in accordance with IS 803/IS 800 & Good Engineering Practice. Tank bottom plate shall be designed in accordance with Annex I of API 650 Twelfth Ed. The thickness shown in the drawings indicate only the minimum requirements. The EPC Contractor shall check and satisfy the same before quoting. Any additional claim due to increase in thickness / weight while doing the detailed design shall not be entertained. The EPC Contractor shall design roof stiffeners for the tank. The structural for roof stiffeners for tank shall be provided outside the roof, above the roof plates. For wind load and seismic calculation actual specific gravity of the product shall be used. Wind loading in accordance with Indian Standard Code IS: 875 (Part-3) shall be applied. The Seismic Design shall be as per Indian Standard IS 1893 Part 1 & Part 4. 4.0 MATERIALS 4.1 4.2 4.3 EPC Contractor shall furnish complete, item wise MTO in the drawing. Structural steel shall conform to IS 2062 or equivalent of weldable quality. All the materials including CS plates required for shell, roof and bottom of the tank, pipes and flanges required for nozzles, structurals required for roof and shell stiffeners / wind girders, ladder, platforms, anchor bolts & fasteners etc, shall be supplied by Contractor. All internal materials shall be of SS 904L. All materials supplied by the EPC Contractor shall meet the requirements of applicable codes and standards. Test Certificates for the materials shall be submitted for approval by FEDO/FACT-CD. Prior written permission shall be obtained from FEDO/FACT-CD for any change in the material specification. 3.5 4.4 4.5 4.6 5.0 TESTING & INSPECTION 5.1 FEDO/FACT-CD or their representative shall carry out inspection at various stages of fabrication/procurement, including raw material identification. FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION 5.2 SPECIAL REQUIREMENTS OF THE PROJECT PHOSPHORIC ACID STORAGE TANKS 32644–02–PS–001-SPL Page 4 of 5 R1 5.4 EPC Contractor shall submit a detailed Quality Assurance Plan (QAP) and Inspection Test Plan (ITP) for review and approval by M/s FEDO/FACT-CD. Approval of work by M/s FEDO/FACT-CD shall in no way relieve the EPC Contractor of his responsibility in meeting all the provisions of the Enquiry conditions. Testing of Tank shall be as per the relevant sections of Design Code. 6.0 RUBBER LINING 6.1 The entire (shell, bottom plate, roof plate and nozzles) inner surface of tank shall be Rubber Lined. Internal Rubber lining shall be provided for the tank, 5 mm thick rubber lining shall be provided for the walls and roof and 10 mm thick rubber lining shall be provided for the bottom plates and walls up to 1 Metre from bottom. The lining shall be of soft Butyl Rubber. The cured hardness of the rubber lining shall be 650 +/- 50 Shore A. For detailed specification of rubber lining refer FEDO Engineering Specification 02ES030/2010. The tank shall be fabricated in such a manner that it complies with the requirements of IS 4682 – Part 1. 5.3 6.2 6.3 6.4 6.5 7.0 PAINTING. 7.1 7.2 7.2.1 For detailed specification of painting refer FEDO specification for painting 02 ES 023/2010. Tank (Plates and structural sections) shall be painted as follows. Primer – Chlorinated Rubber Based High Build Zinc Phosphate–2 coats of 20 microns each after Shot / Grit blasting. Finish Paint - Chlorinated Rubber Paint - 2 coats of 20 microns each. The bottom side (underside) of the bottom plate is painted as follows. Primer–Chlorinated Rubber Based High Build Zinc Phosphate–2 coats of 20 microns each after Shot/Grit blasting. Finish Paint- Bituminous Paint - 2 coats of 20 microns each. Tank Numbers, Capacities and Name of the products stored shall be painted on the tank at two locations in yellow color, in suitable sizes as per the directions of M/s FEDO/FACT-CD. 7.2.2 7.3 7.3.1 7.3.2 7.4 8.0 GENERAL 8.1 Relevant IS codes shall be followed. Entire work shall be carried out in accordance with relevant standards and accepted codes of practices. All butt welds shall have full penetration. When welding is carried out from both sides of a joint, the root of first side shall be dressed back to sound metal before commencement of weld on second side. Structural items shall not be welded directly to the tank. Pad plates of the same material as the shell plate shall be provided for this purpose. All necessary cleats and pad plates required for platforms and ladders and pipe support cleats are to be provided. Earthing Boss shall be provided on Tank as per FEDO standard 02 DS 006/2010. Name Plates shall be provided on Tank as per FEDO standard 02 DS 020/2010. 8.2 8.3 8.4 8.5 8.6 FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION 8.7 8.8 SPECIAL REQUIREMENTS OF THE PROJECT PHOSPHORIC ACID STORAGE TANKS 32644–02–PS–001-SPL Page 5 of 5 R1 All internal weld joints shall be ground smooth before hydro testing is carried out. Float Level Indicator of Type B shall be provided on Tank as per FEDO Standard 02DS007/2010. Material of construction of Float, Rope & Guide wire shall be SS904L. Level Indicator Nozzle size shall be selected in such a way that float shall be removed & re-installed through the nozzle. Preferred float diameter shall be 200 mm. 8.9 Circumferential Handrail, central walkway, central platform for accessing vent nozzle and Inter-connecting platform between both tanks shall be provided on roof. 9.0 GUARANTEE 9.1 The equipment and parts shall be guaranteed against defects in design, materials, workmanship and performance for a period stipulated in the commercial conditions of this enquiry. 10.0 DOCUMENTS TO BE SUBMITTED ALONG WITH THE OFFER 10.1 Dimensioned sketch of the Tank (General Arrangement drg. with detailed MTO) along with the loading data. 10.2 Quality Assurance Plan. 10.3 Duly filled Scope of Work (Doc. No. 32644-02-PS-001-SW). 10.4 Duly filled Spare Parts List (Doc. No. 32644-02-PS-001-SPR). 10.5 Duly filled Vendor Data Requirements (Doc. No. 32644-02-PS-001-VDR). *********************** FACT ENGINEERING AND DESIGN ORGANISATION 00FT021A/94 Page 1 of 5 TECHNICAL PROCUREMENT SPECIFICATION 32644 -01-SPL-001 SPECIAL REQUIREMENT OF THE PROJECT (PHOSPHORIC ACID PUMPS) Page 1 of 5 R1 1.0 INTRODUCTION 1.1 FACT-CD has proposes to install 2 nos. additional Phosphoric Acid Storage Tanks & associated facilities at W. Island on EPC basis, adjacent to the existing three tanks for the purpose of improving the Phosphoric Acid handling capability as part of new NP Plant. 1.2 Two numbers of Phosphoric acid truck loading pumps (1W+ 1S) with drive motors, two number of Phosphoric acid sump pump (1W+1S) with drive motor, and one number of Rain Water pit pump (1W) with drive motor, with all accessories for these pumps are required as part of aforesaid facility at Q10 Berth, WI. Kochi. 1.3 The scope of work of the EPC contractor shall include the Design, Manufacture, Inspection, Testing, Painting, Insurance, Supply, Erection supervision & Commissioning of the equipment with all accessories, Training of owner’s personnel and Handing over the system to M/s. FACT- Cochin Division as per the Technical Procurement Specification. 2.0 GENERAL 2.1 All documents as detailed in ‘Vendor Data Submission Procedure” & “Vendor Data Requirements” shall be submitted by EPC contractor for review by FEDO. 2.2 All items indicated in “Scope of Work” attached shall be included in the Scope of EPC contractor. Any item required for the safe and efficient operation of the system whether specifically mentioned or not, shall be provided by the EPC contractor without extra cost. 2.3 Inspection / Tests shall be carried out by Vendor as detailed in “Scope of Inspection and Tests”. Witnessing of tests where specified will be done by CLIENT/ FEDO or their authorized representative. 2.4 Data sheets of Pumps are enclosed. EPC contractor shall submit all data sheets duly filled up along with other documents/drawings indicated in “Vendor Data Requirements”, along with the offer. Changes if any required for meeting system /operational requirements shall be indicated along with reasons thereof. 2.5 Bidders or Representative of bidders shall visit the site and familiarize themselves of the site conditions before submitting their bid with prior permission from CLIENT. The bidder shall collect the necessary additional data as well as purchaser’s requirements before quoting so that full coverage of the scope will be ensured in the offer itself. 1 06/07/20 For Enquiry - Revised LA SK AAN 0 09/06/20 Client Review LA SK AAN REV. No. DATE DESCRIPTION PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION 00FT021B/94 TECHNICAL PROCUREMENT SPECIFICATION 32644 -01-SPL-001 SPECIAL REQUIREMENT OF THE PROJECT Page 2 of 5 R1 2.6 First Fill of Lubricant, Mandatory Spares, Start-up and Commissioning spares, spares for two years normal operation and Consumables for Testing, Commissioning and establishing Guarantees shall be included in the scope of the EPC contractor. 2.7 Special tools required if any, for the normal operation and maintenance of the equipment shall be included in the scope of the EPC contractor. Details of such special tools shall be furnished. 2.8 All equipment shall be properly tagged, packed, securely anchored and protected for domestic shipment by rail / truck or suitable for ocean transport as the case may be. Rust inhibitors shall be applied to the equipment to prevent rusting during shipment and site storage for minimum of 6 months. 2.9 EPC contractor shall submit a procedure/methodology for the Performance Guarantee Test Run (PGTR) in the offer stage itself. 2.10 EPC contractor shall submit a Quality Assurance Policy for the system in the offer stage itself. 2.11 The equipment shall be as per the manufacturer’s standard. 2.12 All safety devices to protect the equipment from damage due to conditions of overload shall be incorporated as per standard practice. 2.13 Corrosion allowance on carbon steel parts of equipment shall be 3 mm on thickness unless otherwise specified. 2.14 Bought out items shall be from Sub Vendor list attached. Additional Sub Vendors if required by EPC contractor shall be included only on approval by Purchaser. Any delay due to this shall be to EPC contractor account. 2.15 Deviations if any from the Specifications shall be clearly spelt out in the “Compliance Statement” attached failing which it will be taken to understand that there are no deviations from the Specifications. 3.0 TECHNICAL 3.0.1 Design and documents of the system shall be in accordance with manufacturer’s standard. 3.0.2 Pumps duty shall be continuous. 3.0.3 Pumps shall have stable head / flow rate curves (continuous head rise to shutoff) for all applications. If parallel operation is specified, the head rise from rated point to shutoff shall be at least 10%. Unless otherwise specified, discharge orifice shall not be used to achieve required head rise to shut off in case of parallel operation. 3.0.4 Unless specified otherwise, the maximum permissible sound level shall not exceed 88 dBA measured at one (1) meter from the complete pump unit, when measured in any direction & from any point of any equipment surface located on the equipment skid, for the recommended range of operation. FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION 32644 -01-SPL-001 SPECIAL REQUIREMENT OF THE PROJECT Page 3 of 5 R1 3.0.5 Data sheets of Pumps are enclosed. All the specifications/ parameters specified in the data sheet are the minimum requirements to be established by the EPC contractor, any additional requirements/changes required for the safe and satisfactory functioning of the equipment shall be indicated along with reasons thereof in the offer stage itself. 3.0.6 Pump shut-off pressure should not exceed 20% of rated discharge pressure. 3.0.7 Pumps offered shall have a minimum margin of NPSHA over NPSHR of 0.6 meter. 3.0.8 By changing the impeller it should be possible to attain 5% increase in discharge head over rated discharge head. 3.0.9 Pumps shall be tested at shop with job motor in presence of authorized representative of Client /FEDO. 3.0.10 Base plate shall cover full length of pump and motor. 3.0.11 Pump shall be designed to withstand the external forces and moments calculated in accordance with API 610. 3.0.12 EPC contractor shall indicate Latest ASTM material designation for the parts used for the equipment and accessories, etc. 3.0.13 EPC contractor to include any additional accessory and / or material in their scope of supply required to meet the specified performance and guarantees, for satisfactory operation of equipment, safe and reliable start up, normal shut down and emergency shut down and state the same in specification sheet attached to the technical offer 3.0.14 Equipment shall be with direct drive without gear box. 3.0.15 For Electrics, specification indicated elsewhere in this Tender shall be followed. 3.0.16 Unless otherwise specified, equipment shall be designed to be suitable for outdoor installation without a roof. 00FT021B/94 3.0.17 EPC contractor shall establish all guarantees as specified. Defect or shortfall in performance shall be rectified by the EPC contractor within reasonable time failing which Purchaser (Owner) will make arrangements to rectify the same at the risk and cost of the EPC contractor. All Performance parameters specified in the data sheets, special requirements and engineering specifications including Head and capacity of the pump at rated point without negative tolerance, NPSHR requirements, shut off head, power consumption etc shall be guaranteed. 4.0 SPARE PARTS 4.1 General 4.1.1 The bidder shall include in his scope of supply all the start-up and commissioning spares, mandatory spares and recommended two years operation spares and indicate these in the relevant schedules. The general requirements pertaining to the supply of these spares is given below: FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION 32644 -01-SPL-001 SPECIAL REQUIREMENT OF THE PROJECT Page 4 of 5 R1 4.1.2 The EPC contractor shall also indicate the unit wise population of each item and the service expectancy period for the spare parts under normal operating conditions before order placement. 4.1.3 All spares supplied under this contract shall be strictly interchangeable with the parts for which they are intended for replacements. The spares shall be treated and packed for long storage under the climatic conditions prevailing at the site, e.g. small items shall be packed in sealed transparent plastic bags with dissector packs as necessary. 4.1.4 Each spare part shall be clearly marked or labeled on the outside of the packing with the description. When more than one spare part is packed in single case, a general description of contents shall be on the outside of such case and a detailed list enclosed. All cases, containers and other packages must be suitably marked and numbered for the purpose of identification. 4.1.5 The EPC contractor shall provide the purchaser all the addresses and specification of his subsuppliers while placing the order on vendors for items / components / equipment covered under purchase order and will further ensure with his vendors that the purchaser, if so desires, will have the right to place order for spares directly on them on mutually agreed terms based on offers of such vendors. 4.1.6 No Mandatory spares and recommended spares for 2 years will be used during startup and commissioning of the equipment 4.2 MANDATORY SPARES PARTS 4.2.1 The mandatory spares, which are considered as essential by the purchaser are listed and attached with the TPS. 4.2.2 The ƋŽƵƚĞĚprices ƐŚĂůůďĞŝŶĐůƵƐŝǀĞĐŽƐƚŽĨ mandatory spares indicated by the bidder͘ 4.3 RECOMMENDED SPARES FOR 2 YEARS OPERATION 4.3.1 The Bidders shall submit the list including unit & quantity of recommended spares for two years normal operation & maintenance in un-priced part as per format͘ . 4.3.2 The Purchaser reserves the right to buy any or all recommended spares. 00FT021B/94 . 4.4. START-UP & COMMISSIONING SPARES 4.4.1 Start-up commissioning spares are those spares which may be required during the start-up and commissioning of the equipment/system. All spares used until the system is handed over to the Purchaser shall come under this category. The EPC contractor shall procure and supply spare parts for start-up and commissioning and shall be included in his scope of work without any extra cost to FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION 32644 -01-SPL-001 SPECIAL REQUIREMENT OF THE PROJECT Page 5 of 5 R1 00FT021B/94 purchaser. The quoted price in the price bid (supply) shall be deemed to be inclusive of provision for such spares and additional spares. 5.0 TESTING & INSPECTION: 5.1 Pump testing shall be in accordance with API 610. 5.2 All equipment shall be subjected to inspection by Owner / authorized representative at all stages, before, during and after manufacture. 5.3 Owner or their representative shall have free access to the works of the EPC contractor or his subcontractors (if any) to carry out the inspection of all items covered under the scope of work. EPC contractor shall submit a detailed quality assurance plan for review and approval by FEDO/FACT. 5.4 Equipment shall be tested at shop in the presence of authorized representative of FACT / FEDO. 5.5 Approval of work by FEDO / FACT shall in no way relieve the EPC contractor of his responsibility in meeting all the provisions of the enquiry conditions. 5.6 Bidders shall provide a minimum of 10 days advance notice to Owner to arrange the inspection as per agreed QAP / Inspection Test Plan (ITP). 5.7 The EPC contractor shall operate the equipment initially under his supervision after mechanical erection. Once the system is stabilized / commissioned, the system shall be operated by M/s. FACT in the presence of EPC contractor. The EPC contractor shall impart necessary training and assist the owner to operate the system under his supervision. 6.0 PAINTING & PROTECTION: 6.1 All exposed parts other than SS / Machined surfaces, prior to painting, shall be blast cleaned to SA 2½ in an environment of relative humidity not exceeding 80%. 6.2 After surface preparation the protective painting shall done on all exposed parts other than SS as follows, a) Primer (at shop) : One coat of anti corrosive epoxy primer @ 50 µ DFT (min). b) Intermediate coat (at shop) : One coat of anti corrosive epoxy paint @ 50 µ DFT(min) c) Finish coat ( at site ) : One coat of anti corrosive epoxy paint @ 50 µ DFT(min). 6.3 All exposed machined surfaces and internals shall be protected against rusting, before dispatch, suitable for 6 months of storage. 7.0 ERECTION & COMMISSIONING 7.1 Erection of the new equipment shall be under the scope of EPC Contractor. 7.2 Commissioning of the new equipment shall be under the scope of EPC contractor. ********** FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION VENDOR DATA REQUIREMENTS STORAGE TANK 32644-02-PS-001 VDR PAGE 1 OF 1 PROJECT CONSTRUCTION OF PHOSPHORIC ACID TANKS AND ASSOCIATED ITEM : T 1201 D / E : STORAGE FACILITIES AT Q10 BERTH, WI (2 NO’S) CLIENT : FACT-CD STATUS Sl. No. Grp Code 1 2 3 4 A A A B 5 6 B B 7 8 9 10 11 12 13 B B A A A B B 14 C Legend : - TPS No. X ENQUIRY COMMITMENT Description Drawing Index General Arrangement drawing Foundation loading diagram Detailed fabrication drawing of the following Shell and bottom plate Roof & roof structure Nozzles and flanges Internals, pipes, coils, supports etc. Platforms & ladders External stiffeners, clips, pipe supports Internal rubber lining details Design calculations for the following Shell, bottom plate Roof, roof stiffeners & roof structure Wind girder & wind analysis Earth quake analysis Anchor design Quality Assurance Plan WPS & PQR Bar-chart for anticipated activities Manpower allocation chart for the site work Site erection / assembly procedure Hydrostatic test procedure Rubber Lining application and Test Procedure R0 P.O No. Qty. with offer 1S 1S After Commitment Qty. of final Lead time in weeks docs. (@@ ) Qty. Reqd. Propd @ Agrd 1S 4 4 1S 1S 4 4P+1S 1S 4 1S 1S 6 4 4P+1S 1S 1S 4 4 4P+1S 4P+1S 1S 1S 1S 4 8 8 4P+1S 4P+1S 1S 1S Data folder with the following documents Drawing Index As-built drawings Quality Assurance Plan WPS / PQR Material test certificates Inspection test reports Hydrostatic test report FRV Lining test report Design calculations Rubbing of name plate 4P+1S 4P+1S 4P+1S 4P+1S 4P+1S 4P+1S 4P+1S 4P+1S 4P+1S 4P+1S Group code : A - For review and detailed engineering, B - For review, C - For information and record Document type : R - Reproducible, P - Print, M - Microfilm. or Floppies S- Soft copy in Autocad/ MS word/Adobe Acrobat. Notes : @ Vendor shall fill in proposed lead time if different from the required lead time. @@ Each set of final documents shall be submitted in a folder. Two such folders shall be packed and despatched 00FT017/00 with the equipment. Balance documents shall be forwarded to FEDO. 0 09.06.20 Tank capacity revised A 05.06.20 For Review GPG GPG SK SK AAN AAN REV. DATE DESCRIPTION PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION VENDOR DATA REQUIREMENTS (Phosphoric Acid Pump) PROJECT : Construction of Additional Phosphoric Acid Storage Tanks at Q10 Berth, WI CLIENT : FACT CD STATUS : x Sl. No Grp Code 1.0 2.0 3.0 4.0 5.0 6.0 A A A A A B ENQUIRY COMMITMENT Data sheets Predicted performance curves Dimensioned G. A drawings Foundation plan with load details Foundation bolt details Cross section drawing with list of parts and material of construction B Mechanical seal drawings 7.0 8.0 B Auxiliary piping drawing 9.0 B & C Inspection and test procedure B Spares list for two years normal operation 10.0 11.0 B Spares list Mandatory Spares 12.0 B Coupling drawings 13.0 B Base plate drawing 14.0 A Allowable nozzle forces and moments 15.0 A Utility consumption list 16.0 C Reference list of previous supplies 17.0 C Technical literature and catalogues 18.0 C Lube data sheet 19.0 C Packing list 20.0 C Inspection & test reports and material test certificates 21.0 B & C Installation, operation and maintenance manual ( Routine and preventive ) 22.0 B Compliance statement PAGE 1 OF 1 ITEM : CENTRIFUGAL PUMP TPS No : 32644- PO No : Offer Description 32644-01-PS-001 VDR Qty 1S 1S 1S 1S 1S 1S 1S After Commitment Lead time in weeks Qty Reqd Prop@ Agrd 1S 4 1S 4 1S 4 1S 4 1S 4 1S 4 Final@@ Qty 1S 4 1P+1S 1S 4 1S 1S 1S 1S 6 6 4 6 1S 6 1S 1S 1S 1S 1P+1S 1P+1S 1P+1S 1P+1S 1P+1S 1P+1S 1P+1S before despatch 1P+1S 1P+1S 1P+1S 1S 01FT010B / 94-R1 Legend : Group code : A - For review and detailed Engineering , B - For review , C - For information and record Document type : R - Reproducible , P - Print , S - Soft copy Notes : '@' Vendor shall fill in proposed lead time if different from the required lead time ' @@ ' Each set of final documents shall be submitted in a folder. Two such folders shall be packed and despatched with the equipment. 0 09-06-2020 FOR ENQUIRY LA SK AAN REV NO DATE DESCRIPTION PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION SCOPE OF INSPECTION AND TESTS (Phosphoric Acid Pump) TPS NO. 32644- ITEM : CENTRIFUGAL PUMP 32644-01-PS-001 INS PAGE 1 OF 1 EQPT. NO. The following inspection and test shall be conducted and records submitted. Sl Description No. 1.0 Casing Inspection Non-destructive examination 1.1 Inspn. Witness Reqd. Remarks Reqd. X Magnetic particle or liquid penetrant on cast casing X Magnetic particle or liquid penetrant on repair welds X Magnetic particle or liquid penetrant on weld joints, if any X Spot radiograph on weld joints Magnetic particle on forged casing 1.2 Hydrostatic test 1.3 Air leak test 2.0 Rotor inspection 2.1 Non-destructive examination X X X X Ultrasonic or forging X Magnetic particle or liquid penetrant on shaft X 2.2 Runout test 2.3 Dynamic balance test X 3.0 Performance test with job motor X 4.0 NPSH test X 5.0 Mechanical running test X Sound level test X 6.0 Dismantling inspection X 7.0 Clearance check X 8.0 Appearance and dimensional inspection X 9.0 Material test and chemical analysis X X X X X X Bearing check X X 10.0 Auxiliary Equipment Hydrostatic test 01FT010A/94-R1 Appearance and dimensional inspection 0 09-06-2020 FOR ENQUIRY LA SK AAN REV.NO. DATE DESCRIPTION PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT VENDOR DATA INDEX SPECIFICATION PROJECT: CONSTRUCTION OF PHOSPHORIC ACID STORAGE TANKS AND ASSOCIATED FACILITIES AT Q10 PROJECT NO. : 32644 32644-02-PS-001 VDI PAGE 1 OF 1 R0 VENDOR: BERTH, WI (2 NO’S) ITEM: PHOSPHORIC ACID STORAGE TANKS (T-1201 D/E) Sl. No. Doc. / Drawing No. Description P.O NO.: Rev. 0 Date DATE: Rev. 1 Date ISSUE NO. 00FT020/94 DATE SIGNATURE FACT ENGINEERING AND DESIGN ORGANISATION Rev. 2 Rev. 3 Rev. 4 Rev. 5 Date Date Date Date Relevant to This issue TECHNICAL PROCUREMENT SPECIFICATION 32644-02-PS-001-SPR SPARES STORAGE TANK PAGE 1 OF 1 Sl. No. 1 GASKETS 200% 2 BOLTS, NUTS, WASHERS, CLAMPS 10% Description Quantity Unit Price R0 Total Price ( MINIMUM 2 NOS. OF EACH SIZE) ABOVE SPARES SHALL BE APPLICABLE FOR ALL THE NOZZLES INCLUDING NOZZLES WITH BLIND FLANGES 00FT022 / 94 ‐‐PRICES NOT TO BE FILLED IN HERE‐‐ For Review GPG GPG SK SK AAN AAN DESCRIPTION PREPARED CHECKED APPROVED 0 09-06-20 Tank capacity revised A 08-05-20 REV. DATE FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION SPARES (MANDATORY) 32644-01-PS-001 SPR(M) PAGE 1 OF 1 CENTRIFUGAL PUMPS Sl No Description Quantity (% ) 1 Impeller 2 Impeller nut 3 Mechanical seal ( complete assembly ) Seal parts / kit ( seal faces, secondary 4 seal, gaskets, springs and pins ) 5 Gland Packing Coupling spares ( Flexible elements , 6 bushes, pins, packings, etc 7 Shaft sleeve 8 Impeller wear ring 9 Casing wear ring 10 Bearings Pump Motor 11 Oil Seal 12 Oiler 13 Coupling complete Unit Price Total Price 100 100 100 1 100 200 100 ‐‐PRICES NOT TO BE FILLED IN HERE‐‐ 100 100 100 100 100 100 100 100 01FT010D/94-R1 Note: 1. Spares list shall be furnished separately for each pump. 2. Wherever suggested Quantity is less than 100%, minimum 1 set or 1 No: shall be provided 1 0 06-07-2020 09-06-2020 FOR ENQUIRY - REVISED FOR ENQUIRY LA LA SK SK AAN AAN REV NO DATE DESCRIPTION PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION SPARES (2 Years Operational Spares) 32644-01-PS-001 SPR(OP) PAGE 1 OF 1 CENTRIFUGAL PUMPS Sl No Description 1 Impeller 2 Impeller nut 3 Mechanical seal ( complete assembly ) Seal parts / kit ( seal faces, secondary 4 seal, gaskets, springs and pins ) Coupling spares ( Flexible elements , 5 bushes, pins, packings, etc 6 Gland packing 7 Shaft sleeve 8 Impeller wear ring 9 Casing wear ring 10 Throat bush 11 Description 12 Bearings Pump Motor 13 Oil Seal 14 Oiler 15 Shaft with keys 16 Coupling complete 17 Gland packing Suggested Quantity (% ) Quantity Unit Price Total Price VTA VTA VTA 1 VTA VTA ‐‐PRICES NOT TO BE FILLED IN HERE‐‐ VTA VTA VTA VTA VTA VTA VTA VTA VTA VTA VTA VTA VTA VTA Notes: 1. Spares list shall be furnished separately for each pump. 2 Wherever suggested Quantity is less than 100%, minimum 1 set or 1 No: shall be provided. 3 Purchaser reserves full right to purchase or not to purchase the 2 yrs operational spares fully or partially as per rate quoted by the successful bidder. Quoted rate shall remain firm for 2 yrs from the date of expiry of warrantee period. 4 Price quoted for 2yrs of operational spares shall not be considered for price bid evaluation. 01FT010D/94-R1 * VTA- Vendor to advice 1 0 06-07-2020 09-06-2020 FOR ENQUIRY - REVISED FOR ENQUIRY LA LA SK SK AAN AAN REV No. DATE DESCRIPTION PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION SPARES (Commissioning Spares) 32644-01-PS-001 SPR(CO) PAGE 1 OF 1 HORIZONTAL CENTRIFUGAL PUMPS Sl No Description 1 Impeller 2 Impeller nut 3 Mechanical seal ( complete assembly ) Seal parts / kit ( seal faces, secondary 4 seal, gaskets, springs and pins ) Coupling spares ( Flexible elements , 5 bushes, pins, packings, etc 6 Gland packing 7 Shaft sleeve 8 Impeller wear ring 9 Casing wear ring 10 Throat bush 11 Description 12 Bearings Pump Motor 13 Oil Seal 14 Oiler 15 Shaft with keys 16 Coupling complete 17 Gland Packing Notes: 1 2 3 4 Suggested Quantity (% ) Quantity Unit Price Total Price VTA VTA VTA 1 VTA VTA ‐‐PRICES NOT TO BE FILLED IN HERE‐‐ VTA VTA VTA VTA VTA VTA VTA VTA VTA VTA VTA VTA VTA VTA Spares list shall be furnished separately for each pump. Wherever suggested Quantity is less than 100%, minimum 1 set or 1 No: shall be provided In addition to the vendor listed commissioning spares, vendor binds to provide any additional spare parts required for start-up and commissioning and shall be included in his scope of work without any extra cost to purchaser. Price quoted for commissioning spares shall be considered for price bid evaluation 01FT010D/94-R1 * VTA- Vendor to advice 1 0 06-07-2020 09-06-2020 FOR ENQUIRY - REVISED FOR ENQUIRY LA LA SK SK AAN AAN REV No. DATE DESCRIPTION PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION 32644-01-PS-001 LD EQUIPMENT LUBRICATION DATA PAGE 1 OF PROJECT : Construction of Additional Phosphoric Acid Storage Tanks at Q10 Berth, WI PROJECT NO : 32644 LOCATION : Q10 Berth, WI TPS NO : 32644- VENDOR : CLIENT : FACT CD SL NO DESCRIPTION 1 ITEM NO Type of Lubrication System 1 ( State Grease-Gun, Grease Packed, Drip, Splash, Continuous ) Recommended Lubrication for Break in ( list two 2 Indian alternatives by trade name and number ) 3 4 5 6 7 8 9 Quantity of Lubricant required for initial fill (Litres or Kg ) Recommended Break - in period for Initial application ( Hours ) Recommended Lubrication for normal operation ( List two Indian alternatives by trade name and number ) Refill quantities if different from initial charge ( Litres or Kg ) Quantity of Lubricant shipped with initial order ( Litres or Kg ) Recommended time between changes of Lubricant ( Hours ) Expected annual consumption of Lubricant ( Litres or Kg ) 01FT304/94-R1 Remarks : REV NO DATE DESCRIPTION PREPARED FACT ENGINEERING AND DESIGN ORGANISATION CHECKED APPROVED TECHNICAL PROCUREMENT SPECIFICATION SUB VENDOR LIST (Mechanical) SL. NO. I 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0 17.0 18.0 19.0 20.0 II 1.0 PAGE 1 OF 2 R 0 Vendor Name PUMPS-HORIZONTAL CENTRIFUGALCRITICAL PROCESS SERVICES NUOVO PIGNONE ITALY SAM TURBO INDUSTRY LIMITED COIMBATORE EBARA CORPORATION 144-8510, OHTA-KU OCHSNER & SOHN GmbH & CO GERMANY POMPE GABBIONETA SPA ITALY KSB PUMPS LTD BENGALURU KIRLOSKAR EBARA PUMPS LTD PUNE SULZER PUMPS INDIA LTD CHENNAI SULZER PUMPS AG SWITZERLAND MITSUBISHI HEAVY INDUSTRIES TOKYO AKAY INDUSTRIES LTD BELUR SULZER ESCHER WYSS LTD SWITZERLAND SIHI-HALBERG VERTRIEBSGES GmbH GERMANY BW/IP INTERNATIONAL INC FLORENCE NIIGATA WORTHINGTON CO LTD KAWASAKI GOULDS PUMPS INC NEW YORK UNION PUMP CO SPRINGFIELD GILBERT GILKES & GORDON LTD KENDAL KSB PUMPEN ARMATUREN FRANKENTHAL FLOWSERVE INDIA CONTROLS PVT LTD COIMBATORE PUMPS-VERTICAL CENTRIFUGALPHOSPHORIC ACID APPLICATION 8.0 CHAS-S-LEWIS CO INC ST LOUIS A R WILFLEY INDIA PVT LTD MUMBAI SULZER PUMPS INDIA LTD CHENNAI ENSIVAL MORET BELGIUM S.A BELGIUM PAUL BUNGARTZ GmbH & CO KG GERMANY FRIATEC AKTIENGESELLSCHAFT GERMANY SULZER PUMPS AG SWITZERLAND WILFLEY A R & SONS INC DENVER 0 09-06-2020 FOR ENQUIRY LA SK AAN REV.NO. DATE DESCRIPTION PREPARED CHECKED APPROVED 2.0 3.0 4.0 5.0 6.0 7.0 00FT024/94 32644-01-PS-001 SV FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION SUB VENDOR LIST (Mechanical) SL. NO. III 1.0 PAGE 2 OF 2 R 0 Vendor Name RUBBER LINING OF VESSEL/STORAGE TANKS INCL. SUPPLY OF MATERIALS 9.0 NEO PAINTS & RUBBER INDUSTRIES KOCHI ALPHA LININGS KOCHI ELASTOMER LINING WORKS PUNE K K NAG LTD PUNE MIL INDUSTRIES LTD CHENNAI MINI ENTERPRISES KOCHI O R ELASTOMERS (P) LTD CHENNAI POLY RUBBER PRODUCTS MUMBAI LEBRACS RUBBER LININGS PVT LTD PONDICHERRY 0 09-06-2020 FOR ENQUIRY LA SK AAN REV.NO. DATE DESCRIPTION PREPARED CHECKED APPROVED 2.0 3.0 4.0 5.0 6.0 7.0 8.0 00FT024/94 32644-01-PS-001 SV FACT ENGINEERING AND DESIGN ORGANISATION 32644-01-DA 001 (Mech) CENTRIFUGAL PUMP DATA SHEET 1 OF 3 : 32644 Applicable to : Proposal Site Unit Pump item No. Service No. of pumps reqd Pump mfr. Pump size & type Pump model No. No. of stages Q10 BERTH, WI, FACT CD Motor item No. : : Pump vendor : PHOSPHORIC ACID STORAGE TANK Motor provided by : P3202A/B Motor mounted by Pump vendor : : Phosphoric Acid Transfer Pump No. of turbines reqd : : 2 Turbine item No. : : Turbine provided by : : Horizontal Centrifugal 2 Turbine mounted by : : Service specification:: Remarks : 54% P2O5, 2-4%H2SO4, 1-2% Gypsum solids. : SINGLE By Purchaser By Manufacturer 1 Information to be completed : Notes : X : As built No of electric motors reqd : Purchase 2 Units of measurement SI System 3 VTS- Vendor to specify 4 VTC- Vendor to Confirm. 2 X Metric System 5 VTA Vendor to advice OPERATING CONDITIONS ( TO BE COMPLETED BY PURCHASER ) Liquid : Normal Pumping Minimum temperature Maximum Sp. gravity @ PT Vapor press. @ PT Viscosity @ PT Site temperature Maximum Ambient Minimum Un usual conditions Corrosion/erosion caused by Duty X Continuous Remarks : TPS No PAGE 32644- Job N o Phosphoric Acid 0 40 : C 0 : C 0 : C 1.63 - 1.7 : Negligible : Kg/cm2A 65 : CP 0 : Suct. pressure C 0 C : : : 0 C Intermittent Capacity Control: Remote and Auto NPSH available (NPSHA) pH Value Normal Capacity @ PT Minimum Maximum Discharge pressure Maximum 2 Minimum Normal Differential pressure Differential head Hydraulic KW Indoor Location X Outdoor : : : : : : : 6.51 MLC 175 M3/Hr. 3 M /Hr. M3/Hr. Kg/cm2G 2 Kg/cm G 175 4 0.07 Kg/cm2G : 0.07 : Kg/cm2G 3.93 : Kg/cm2 MLC : : Heated With roof Unheated X Without roof PERFORMANCE ( TO BE COMPLETED BY MANUFACTURER ) Proposal curve No. Minimum Thermal : Speed RPM continuous flow Stable : NPSH reqd. (NPSHR) *note 1 : MLC Rotation ( Viewed CW Rated BHP KW : from coupling end ) Max. BHP with rated impeller KW Suction sp. Speed : Max. head with rated impeller M Efficiency (VTS) : Necessity to start against system pressure: NO Remarks : : : CCW : : M3/Hr M3/Hr % CONSTRUCTION ( TO BE COMPLETED BY PURCHASER & MANUFACTURER ) Casing mount Centerline X Foot Near centerline Vertical (VTS) Casing split (VTS) Bracket Casing type (VTS) Volute Single Diffuser Pressure Balancing: Double Axial Vert. barrel In line Nozzles Size Rating Suction F.F Sump pump Discharge Radial Facing F.F Location 2 Miscellaneous connections Staggered Nozzles Drain Suction Discharge X Vent Pressure gauge X Note 1 : VTS (Margin between NPSHA and NPSHR should be minimum 0.6 meters.) 2 : MLC- Meters of Liquid column 3 : Also refer to Process data sheet 32644-11-SE-P3202A/B and P&ID 32644-11-PD-001. 01FT010C/94-R3 PROJECT 06-07-2020 2 22-06-2020 1 10-06-2020 0 Rev DATE LA LA LA PRPD. SK SK SK CHKD. AAN AAN AAN APPRD. CLIENT P.O No. VENDOR FACT ENGINEERING AND DESIGN ORGANISATION Construction of Additional Phosphoric Acid Storage Tanks at Q10 Berth, WI 2 Maximum 0 Kg/cm G@15 C Bearings 2 Type / No. allowable pr. Kg/cm G@PT Hydro static test pr. Kg/cm2G PAGE Lubrication 3 Thrust Ring oil Flood Type OF Oil mist Pressure Flinger Manufacturer Maximum Coupling Model Overhung Between bearings Closed Semi-open X Open Manufacturer Type Driver half Coupling Manufactured by X Pump manufacturer X Driver manufacturer Purchaser Gland plate taps reqd. Size/No.of rings Single Flexible disc spacer Type Minimum Impeller mount Impeller type 2 Radial Rated Impeller dia. ( mm ) Packing 32644-01-DA 001 (Mech) CENTRIFUGAL PUMP DATA SHEET Tandem X Double Quench Flush Drain Vent Remarks : Manufacturer Mechanical seal Model Manufacturer code API class code Gland type / Material Compatibility of Mechanical seal with respect to Seal Flush/Quench plan (VTC) AUXILARY PIPING ( TO BE COMPLETED BY PURCHASER & MANUFACTURER ) Seal flush piping plan Cooling water piping plan : Tubing Carbon steel Tubing Carbon steel Piping Stainless steel Piping Stainless steel Auxiliary flush plan M3/Hr. Total cooling water reqd. : Tubing Carbon steel Piping Stainless steel Aux.flush liquid Sight flow indicators reqd. : Packing cooling injection reqd. : Kg/cm2G M3/Hr. Seal flush pipng : Threaded Copper Socket welded Flanged Remarks : External seal flush fluid reqd. : Kg/cm2G M3/Hr. MOC X Base plate/ Foundation Bolt(material / type) SS 316L X Casing/Cylinder : CD4MCu Base plate draining arrangement shall be provided to prevent ingress of acid beneath the baseplate X Impeller: CD4MCu X Case/impeller wear rings: CD4MCu API std.610 std. base plate No. Remarks : X Shaft : CD4MCu Other wetted parts : CD4MCu INSPECTION AND TESTS ( TO BE COMPLETED BY PURCHASER ) As per scope insp.& tests Tests Non witnessed Observed Inspection required for nozzle welds Magnetic Particle Hydrostatic Inspection required for castings NPSH Radiographic Shop inspection 01FT010C/94-R3 Witnessed Performance Material certification Dye penetrant Ultrasonic Inspection required for Dismantle and inspect after test Magnetic Particle Dye Penetrant Casting repair procedure approval Radiographic Ultrasonic Remarks : FACT ENGINEERING AND DESIGN ORGANISATION 32644-01-DA 001 (Mech) CENTRIFUGAL PUMP DATA SHEET PAGE 3 MOTOR DRIVER ( TO BE COMPLETED BY PURCHASER & MANUFACTURER ) KW @ OF 3 Manufacturer RPM Service factor Type Frame No. Bearings Volts / phase / hertz Lube 0 Temperature rise Insulation C Full load amps. Enclosure Locked - rotor amps. Remarks: Vertical shaft Hollow Solid Vertical thrust capacity, Kg Up Down VERTICAL PUMPS ( TO BE COMPLETED BY PURCHASER & MANUFACTURER ) (For vertical pumps attach Format No. 01FT010 X) mm Carbon steel Float & rod mm Bronze Pit or sump depth Pump length (mount plate to suction flange) Stainless steel None Float switch mm Minimum submergence reqd. Column pipe Flanged Threaded Line shaft Open Enclosed Guide bushings Guide bushing lube Water Oil Lube fluid Quantity Bowl Line shaft Pr At min. flow thrust, Kg At design flow At run out Up Down Remarks : Grease M3/hr Pump Kg/cm2G WEIGHTS ( TO BE COMPLETED BY PURCHASER & MANUFACTURER ) Weight of pump & base plate Weight of motor Weight of turbine Kg Kg Kg Remarks: PACKING AND SHIPPING Packing type Domestic Export Packing specs. Mfr's standard Purchaser's specs. Packed weight Kg Packing size ( LXBXH ) mm Shipping by Rail Road Ocean Notes: 2 1) Pump shall be capable of running dry for few minutes. 2) Equipment shall be designed to be suitable for outdoor installation without a roof. 3) Bearing must have greasing provision 01FT010C/94-R3 4) The scope of supply include the following items. a) Pumps, b) Drive Motors, c) Mechanical Seals, d) Minimum flow recirculation valve e) Couplings, f) Coupling Guards, g)Base Plate, h) Anchor Bolts with nuts, i) Piping confined to battery limit, j) Mating flanges for suction and dischargenozzles k) Mandatory spares, l) Commissioning spares - VTS, m) First-fill of lubricants - VTS. 5) Flange Rating : Flange rating for pump shall have a minimum requirement, confirm to the dimentional requirement of ISO 7005-1 PN 50 and Equivalent to ANSI/ASME B 16.5 class 150# 6) MAWP: It should be at least the max discharge pressure + 10% of the max differential pressure. 7) Downstream design Pressure is 1.5 Times of Max operating pressure. Maximum Shutoff considering max suction pressure, including all tolerances shall not exceed this value. 8) Corrossion allowance for MOC other than CD4MCu: 3 mm FACT ENGINEERING & DESIGN ORGANISATION DATA SHEET Job No : 32644 Applicable to : Proposal Site Unit Pump item No. Service No. of pumps reqd Pump mfr. Pump size & type Pump model No. No. of stages Q10 BERTH, WI, FACT CD Motor item No. : : PHOSPHORIC ACID STORAGE TANK Motor provided by P 3203A/B Motor mounted by : Phosphoric Acid Sump Pump No. of turbines reqd : 2 (1 Working + 1 Stand by) 1 Turbine item No. : Turbine provided by : * Vertical Centrifugal Turbine mounted by : : * Remarks : : * Notes : 32644-01-DA 002 (Mech) PAGE 1 OF 4 32644- CENTRIFUGAL PUMP 1 2 5 TPS No : As-built No of electric motors reqd : Purchase 2 : * : : : : : : Vendor - Information to be completed : By Purchaser By Manufacturer * Vendor To Specify (VTS) 3. # Vendor To Confirm (VTC) 4. $ Vendor to advise (VTA) Units of measurement SI System x Metric System OPERATING CONDITIONS ( TO BE COMPLETED BY PURCHASER ) Liquid Pumping temperature : Normal Minimum Maximum Density @ PT Vapor press. VP@ PT Dynamic Viscosity (cP) @ PT Site temperature Maximum Ambient Minimum Solids in suspension Un usual conditions Corrosion/erosion caused by Duty X Continuous NPSH available (NPSHA) Phosphoric Acid : 0 40 pH Value : : C 0 40 Normal : : C 0 40 Capacity @ PT Minimum : : C Maximum : : 1630 - 1700 Kg/M3 Negligible : Kg/cm2 A Discharge pressure(Nor/Max) : 65 cP Maximum : : 0 : C 0 : C 0 : C : 54% P2O5, 2-4%H2SO4, : 1-2% Gypsum solids. : Intermittent Priming - Flooded suction Remarks : Suct. pressure Minimum Normal Differential Pressure (Max) Suction temperature Differential head (VTS) Hydraulic KW (VTS) Indoor Location X Outdoor : 6.28 25 M3/Hr. M3/Hr. 25 M3/Hr. 4.4 / 4.4 Kg/cm2G Kg/cm2G 0.034 Kg/cm2G : Kg/cm2G 4.36 : Kg/cm2 0 40 : C MLC : : Heated With roof Unheated X Without roof PERFORMANCE ( TO BE COMPLETED BY MANUFACTURER ) Proposal curve No. Speed NPSH reqd. (NPSHR) *note 1 Rated BHP Max. BHP with rated impeller Max. head with rated impeller Remarks : : : : : : : RPM MLC KW KW M Minimum Thermal continuous flow Stable Rotation ( facing CW coupling end ) Suction sp. Speed Efficiency (VTS) MLC : : CCW : : M3/Hr M3/Hr % CONSTRUCTION (TO BE COMPLETED BY PURCHASER & MANUFACTURER) Centerline Casing mount Foot Bracket Near centerline X Vertical Vert. barrel Casing split Axial Casing type X Volute Single Diffuser Double In line Nozzles Size* Suction X Sump pump Discharge Radial Rating Facing ANSI B 16.5, 150# ANSI B 16.5, 150# F.F F.F Location 1 Miscellaneous connections Staggered Nozzles Drain Vent Pressure gauge Suction Pressure balancing: Line and disc required Cooling water Inlet/outlet * Discharge X Casing Steam Jacket X Not Required X Note 1 : If not specified elsewhere, margin between NPSHA and NPSHR shall be minimum 0.6 MLC 2 : MLC - Meters of Liquid Column 3 : Suction pressure & NPSH available values indicated are calculated considering a minimum submergrnce of 200 mm above pump centre line. 4 : Also refer to Process data sheet 32644-11-SE-P3203 and P&ID 32644-11-PD-001. 01FT010C/15 PROJECT 1 06.07.2020 0 22.06.2020 A 10.06.2020 Rev DATE LA LA LA PRPD. SK SK SK CHKD. AAN AAN AAN APPRD. CLIENT P.O No. Construction of Additional Phosphoric Acid Storage Tanks at Q10 Berth, WI FACT CD VENDOR FACT ENGINEERING AND DESIGN ORGANISATION CENTRIFUGAL PUMP DATA SHEET Maximum allowable pr. Hydro static test pr. * * Kg/cm2 G @150C Bearings* Kg/cm2 G @ PT Type / No. Lubrication* Kg/cm2 G Type * * * * Rated Impeller dia ( mm ) Maximum Minimum Impeller mount Closed Coupling * Overhung X Open Manufacturer Gland Packing Type X Double Driver half coupling to be supplied by Flinger Flexible disc spacer X Pump manufacturer Driver manufacturer Purchaser Gland plate taps reqd. Size/No.of rings Single Oil mist Pressure Model Semi-open Type Packing Ring oil Flood Manufacturer Between bearings Impeller type* Radial 32644-01-DA 002 (Mech) PAGE 2 OF 4 Thrust Tandem Quench Flush Drain Vent Remarks : Mechanical Seal Type: Dry Run Manufacturer Mechanical seal Model Manufacturer code API class code Gland type / Material Compatibility of Mechanical seal with respect to Seal Flush/Quench plan # AUXILARY PIPING (TO BE COMPLETED BY PURCHASER & MANUFACTURER) Seal flush piping plan VTA (If required)$ Cooling water piping plan : VTA (If required)$ Tubing Carbon steel Tubing Carbon steel Piping Stainless steel Piping Stainless steel Auxiliary flush plan Copper M3/Hr. Total cooling water reqd. : Tubing Carbon steel Aux.flush liquid Piping Stainless steel Sight flow indicators reqd. : Packing cooling injection reqd. : Seal flush piping : Threaded Socket welded Flanged ` Remarks : M3/Hr. Kg/cm2G External seal flush fluid reqd. : M3/Hr. Kg/cm2G All interface connection shall be terminated with Flanged Block Valves Size/Rating (ANSI)/Facing Lantern ring Inlet/Outlet * Exit Seal Flush inlet/outlet * Seal Quench Fluid Inlet * Base plate (material / type) X MOC: X Casing/Cylinder : CD4MCu API 610 std. base plate No. X Impeller CD4MCu Base plate Drain Pan Type X Case/impeller wear rings CD4MCu Base plate drain (Only flanged)* X Shaft / sleeve CD4MCu Remarks : INSPECTION AND TESTS ( TO BE COMPLETED BY PURCHASER ) Tests Non witnessed Observed Inspection required for nozzle welds Performance Magnetic Particle Hydrostatic Inspection required for castings NPSH Radiographic Shop inspection 01FT010C/15 Witnessed Material certification Dismantle and inspect after test Casting repair procedure approval As per scope inspection & tests attched Remarks : Dye penetrant Ultrasonic Inspection required for Magnetic Particle Dye Penetrant Radiographic Ultrasonic FACT ENGINEERING AND DESIGN ORGANISATION * 32644-01-DA 002 (Mech) PAGE 3 OF 4 CENTRIFUGAL PUMP DATA SHEET MOTOR DRIVER ( TO BE COMPLETED BY PURCHASER & MANUFACTURER ) KW @ Service factor Frame No. Volts / phase / hertz Temperature rise Full load amps. * * * * * * RPM Manufacturer Type Bearings Lube 0 C Insulation* * * * * Enclosure* Parallel Operation required Locked - rotor amps.* Vertical shaft Remarks: Hollow X Solid Vertical thrust capacity, Kg* Up Down VERTICAL PUMPS ( TO BE COMPLETED BY PURCHASER & MANUFACTURER ) (For vertical pumps attached Format No. 01FT010 97) - Shall be filled by vendor. As per GA attached mm Pit or sump depth Carbon steel Stainless steel Float & rod Pump length mm Bronze None (mount plate to suction flange) Float switch Minimum submergence reqd. mm Column pipe Flanged Threaded Line shaft Open Enclosed Guide bushings Guide bushing lube Water Oil Lube fluid Quantity Bowl Line shaft Pr At min. flow thrust, Kg At design flow At run out Up Down Remarks : Grease M3/hr Pump First dry critical speed of pump in vertical condition(rpm)* Kg/cm2G WEIGHTS ( TO BE COMPLETED BY PURCHASER & MANUFACTURER ) Weight of pump & base plate Weight of motor Weight of coupling Weight of turbine Packing type* * * * * Domestic Packing specs.* Packed weight* Packing size* Shipping by* Mfr's standard Rail Kg Kg Kg Kg Remarks: PACKING AND SHIPPING Export Purchaser's specs. Kg ( LXBXH ) mm Road Ocean NOTES: 1. The scope of supply include the following items. a) Pumps, b) Drive Motors, c) Mechanical Seals, d) Minimum flow recirculation valve e) Couplings, f) Coupling Guards, g) Mounting flanges with gasket, h) Anchor Bolts with nuts, i) Piping confined to battery limit, j) Mating flanges for suction and dischargenozzles k) Mandatory spares, l) Commissioning spares - VTS, m) First-fill of lubricants - VTS. 2. Area classification: Non Hazardous 3. Non sparking coupling guard to be provided. 4. MAWP: It should be at least the max discharge pressure + 10% of the max differential pressure. 5. 6 01FT010C/15 7 8 Downstream design Pressure is 1.5 Times of Max operating pressure. Maximum Shutoff considering max suction pressure, including all tolerances shall not exceed this value. Process min flow shall be equal to Pump MCF (Minimum Continuous flow) Flange Rating : Flange rating for pump shall have a minimum requirement, confirm to the dimentional requirement of ISO 70051 PN 50 and Equivalent to ANSI/ASME B 16.5 class 150# Material of construction for mounting plate shall be minimum IS 2062 Gr. E250C. Material of construction for Mounting fasteners shall be SS 316L. Mounting Plate shall have 5mm thick rubber lining on the underside. (Rubberlining spec identical to Tank lining) FACT ENGINEERING & DESIGN ORGANISATION DATA SHEET CENTRIFUGAL PUMP 32644-01-DA 002 (Mech) PAGE 4 OF 4 9 This pump is to be installed in sump. 10 Pump manufacturer shall furnish dimensional details as per attachement of this data sheet 11 Shaft shall be solid cantilever. Bearings shall be above mounting plate. No intermediate and bottom bearing. 12 Discharge pressure as indicated is at pump discharge flange, bidder shall arrive/calculate the impeller head after accounting for installation depth, frictional loses etc, so as to generate specified discharge pressure at pump discharge flange. 13 Corrossion allowance for MOC other than CD4MCu: 3 mm 14 Studs / Bolts shall be of minimum SS-316 L. 15 Minimum submergence is to be advised by vendor. Indicate minimum submergence value as per attachement of this data sheet. 16 Mounting plate / flanges along with bolts / nuts & gaskets shall be provided by the vendor. 17 The dimensions for the mounting plate, bolting, gaskets etc. shall be as per the following standards. For Sizes ≤ 24 inches: ASME B16.5, For Sizes > 24 inches: ASME B16.47 Series B. Vend or to indicate the mounting plate size. 01FT010C/15 18 The thickness of mounting plate shall be minimum 20mm. FACT ENGINEERING & DESIGN ORGANISATION DATA SHEET ITEM A CENTRIFUGAL PUMP B C D E F PAGE NB 01FT010X/97 1 OF 1 (1) VENDOR SHALL CONFIRM ADEQUACY OF BOTTOM CLEARANCE 01FT010X/97 (2) VENDOR SHALL INDICATE DIMENSIONS A, B, C, D, E, F & NB PROJECT: CONSTRUCTION OF PHOSPHORIC ACID STORAGE TANKS AND ASSOCIATED FACILITIES AT Q10 BERTH, WI (2 NO’S) TITLE: GA Phosphoric Acid Sump Pump P 3203 Rev DATE DESCRIPTION DRAWN CHKD APPD DWG NO: FACT ENGINEERING & DESIGN ORGANISATION 32644-01-DA 003 (Mech) CENTRIFUGAL PUMP DATA SHEET Job N o : 32644 Applicable to : Proposal Site Unit Pump item No. Service No. of pumps reqd Pump mfr. Pump size & type Pump model No. No. of stages Q10 BERTH, WI, FACT CD Motor item No. : : PHOSPHORIC ACID STORAGE TANK Motor provided by P3204 Motor mounted by : STORM WATER No. of turbines reqd : 1 Turbine item No. : Turbine provided by : Horizontal Centrifugal Turbine mounted by : : Remarks : : SINGLE By Purchaser 1 Information to be completed : Notes : X : PAGE 32644- 1 As built No of electric motors reqd : Purchase 2 Units of measurement SI System 3 VTS- Vendor to specify 4 VTC- Vendor to Confirm. OF : Normal Pumping Minimum temperature Maximum Sp. gravity @ PT Vapor press. @ PT Viscosity @ PT Site temperature Maximum Ambient Minimum Un usual conditions Corrosion/erosion caused by Duty X Continuous STORM WATER 0 40 : C 0 : C 0 : C 1 : 0.074 : Kg/cm2A : CP 0 : C 0 : : : : : : : Pump vendor Pump vendor By Manufacturer X Metric System 5 VTA Vendor to advice C : : : 0 C Intermittent Capacity Control: Local NPSH available (NPSHA) pH Value Normal Capacity @ PT Minimum Maximum Discharge pressure Maximum Suct. pressure 3 1 OPERATING CONDITIONS ( TO BE COMPLETED BY PURCHASER ) Liquid Remarks : TPS No Minimum : : : : : : : 6.5 MLC 25 : -0.308 M3/Hr. 3 M /Hr. M3/Hr. Kg/cm2G 2 Kg/cm G 25 1 Kg/cm2G : Kg/cm2G 1.308 : Kg/cm2 MLC : : Heated With roof Unheated X Without roof Normal Differential pressure Differential head Hydraulic KW Indoor Location X Outdoor PERFORMANCE ( TO BE COMPLETED BY MANUFACTURER ) Proposal curve No. Minimum Thermal : Speed RPM continuous flow Stable : NPSH reqd. (NPSHR) *note 1 : MLC Rotation ( Viewed CW Rated BHP KW : from coupling end ) Max. BHP with rated impeller KW Suction sp. Speed : Max. head with rated impeller M Efficiency (VTS) : Necessity to start against system pressure: NO Remarks : : : CCW : : M3/Hr M3/Hr % CONSTRUCTION ( TO BE COMPLETED BY PURCHASER & MANUFACTURER ) Centerline Casing mount X Foot Near centerline Vertical (VTS) Casing split (VTS) Bracket Casing type (VTS) Volute Single Diffuser Pressure Balancing: Double Axial Vert. barrel In line Nozzles Size Rating Suction Location F.F Sump pump Discharge Radial Facing F.F Miscellaneous connections Staggered Nozzles Drain Suction Discharge X Vent Pressure gauge X Note 1 : VTS (Margin between NPSHA and NPSHR should be minimum 0.6 meters.) 2 : MLC- Meters of Liquid column 3 : Also refer to Process data sheet 32644-11-SE-P3204 and P&ID 32644-11-PD-002. 01FT010C/94-R3 PROJECT 06-07-2020 2 22-06-2020 1 10-06-2020 0 Rev DATE LA LA LA PRPD. SK SK SK CHKD. AAN AAN AAN APPRD. CLIENT P.O No. VENDOR FACT ENGINEERING AND DESIGN ORGANISATION Construction of Additional Phosphoric Acid Storage Tanks at Q10 Berth, WI 2 Maximum 0 Kg/cm G@15 C Bearings 2 Type / No. allowable pr. Kg/cm G@PT Hydro static test pr. Kg/cm2G PAGE Lubrication 3 Thrust Ring oil Flood Type OF Oil mist Pressure Flinger Manufacturer Maximum Type Coupling Minimum Impeller mount Impeller type 2 Radial Rated Impeller dia. ( mm ) Between bearings Closed Overhung Semi-open Type X Open Gland Packing Size/No.of rings Single Flexible disc spacer Model Manufacturer Packing 32644-01-DA 003 (Mech) CENTRIFUGAL PUMP DATA SHEET Double Tandem Driver half Coupling Manufactured by X Pump manufacturer X Driver manufacturer Purchaser Gland plate taps reqd. Quench Flush Drain Vent Remarks : Manufacturer Mechanical seal Model Manufacturer code API class code Gland type / Material AUXILARY PIPING ( TO BE COMPLETED BY PURCHASER & MANUFACTURER ) Seal flush piping plan Cooling water piping plan : Tubing Carbon steel Tubing Carbon steel Piping Stainless steel Piping Stainless steel Auxiliary flush plan M3/Hr. Total cooling water reqd. : Tubing Carbon steel Piping Stainless steel Aux.flush liquid Sight flow indicators reqd. : Packing cooling injection reqd. : Kg/cm2G M3/Hr. Seal flush pipng : Threaded Copper Socket welded Flanged Remarks : External seal flush fluid reqd. : Kg/cm2G M3/Hr. MOC X Base plate/ Foundation Bolt(material / type) SS 316L X Casing/Cylinder : CD4MCu Base plate draining arrangement shall be provided to prevent ingress of acid beneath the baseplate X Impeller: CD4MCu X Case/impeller wear rings: CD4MCu API std.610 std. base plate No. Remarks : X Shaft : CD4MCu Other wetted parts : CD4MCu INSPECTION AND TESTS ( TO BE COMPLETED BY PURCHASER ) As per scope insp.& tests Tests Non witnessed Observed Inspection required for nozzle welds Performance Magnetic Particle Hydrostatic Inspection required for castings NPSH Radiographic Shop inspection 01FT010C/94-R3 Witnessed Material certification Dye penetrant Ultrasonic Inspection required for Dismantle and inspect after test Magnetic Particle Dye Penetrant Casting repair procedure approval Radiographic Ultrasonic Remarks : FACT ENGINEERING AND DESIGN ORGANISATION 32644-01-DA 001 (Mech) CENTRIFUGAL PUMP DATA SHEET PAGE 3 MOTOR DRIVER ( TO BE COMPLETED BY PURCHASER & MANUFACTURER ) KW @ RPM OF 3 Manufacturer Service factor Type Frame No. Bearings Volts / phase / hertz Lube 0 Temperature rise Insulation C Full load amps. Enclosure Locked - rotor amps. Remarks: Vertical shaft Hollow Solid Vertical thrust capacity, Kg Up Down VERTICAL PUMPS ( TO BE COMPLETED BY PURCHASER & MANUFACTURER ) (For vertical pumps attach Format No. 01FT010 X) mm Carbon steel Float & rod mm Bronze Pit or sump depth Pump length (mount plate to suction flange) Stainless steel None Float switch Minimum submergence reqd. mm Column pipe Flanged Threaded Line shaft Open Enclosed Guide bushings Guide bushing lube Water Oil Lube fluid Quantity Bowl Line shaft Pr At min. flow thrust, Kg At design flow At run out Up Down Remarks : Grease M3/hr Pump Kg/cm2G WEIGHTS ( TO BE COMPLETED BY PURCHASER & MANUFACTURER ) Weight of pump & base plate Weight of motor Weight of turbine Kg Kg Kg Remarks: PACKING AND SHIPPING Packing type Domestic Export Packing specs. Mfr's standard Purchaser's specs. Packed weight Kg Packing size ( LXBXH ) mm Shipping by Rail Road Ocean Notes: 1) Pump shall be capable of running dry for few minutes. 2) Equipment shall be designed to be suitable for outdoor installation without a roof. 3) Bearing must have greasing provision 01FT010C/94-R3 4) The scope of supply include the following items. a) Pumps, b) Drive Motors, c) Mechanical Seals, d) Minimum flow recirculation valve e) Couplings, f) Coupling Guards, g)Base Plate, h) Anchor Bolts with nuts, i) Piping confined to battery limit, j) Mating flanges for suction and dischargenozzles k) Mandatory spares, l) Commissioning spares - VTS, m) First-fill of lubricants - VTS. 5) Flange Rating : Flange rating for pump shall have a minimum requirement, confirm to the dimentional requirement of ISO 7005-1 PN 50 and Equivalent to ANSI/ASME B 16.5 class 150# 6) MAWP: It should be at least the max discharge pressure + 10% of the max differential pressure. 7) Downstream design Pressure is 1.5 Times of Max operating pressure. Maximum Shutoff considering max suction pressure, including all tolerances shall not exceed this value. 8) Corrossion allowance for MOC other than CD4MCu: 3 mm FACT ENGINEERING & DESIGN ORGANISATION ENGINEERING SPECIFICATION VENDOR DATA SUBMISSION PROCEDURE 00ES001/2010 PAGE 1 OF 4 CONTENTS 1.0.0. SCOPE 2.0.0. VENDOR DATA REQUIREMENTS 3.0.0. CLASSIFICATION OF DOCUMENTS 4.0.0. VENDOR DATA INDEX 5.0.0. QUALITY OF VENDOR DRAWINGS 6.0.0. CONDITIONS OF FEDO REVIEW PRPD.BY:- JC CHKD.BY:-CK APPRD. BY:- JK FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON:-April 2010 ENGINEERING SPECIFICATION VENDOR DATA SUBMISSION PROCEDURE 1.0.0. SCOPE 1.1.0. This document together with “VENDOR DATA REQUIREMENTS (VDR)” defines FEDO’s requirements for vendor drawing and data for any enquiry, work order or purchase order. 1.2.0. Bidders unable to comply with these requirements must detail all exceptions in their proposal. The timely delivery of quality drawings and data is as crucial as delivery of the equipment itself and hence the same shall be strictly adhered to after commitment. 1.3.0. Failure to provide adequate preliminary data / drawing may render a proposal non-responsive and hence may be rejected. After commitment failure to provide documents as per purchase order may delay progressive payments and adversely affect future invitation to bids. 2.0.0 VENDOR DATA REQUIREMENTS (VDR) 2.1.0 FEDO will provide a partially completed VDR form along with each enquiry. This form explains group code of the document, quantity of each document required and lead time for submission. Columns are available for the vendor to fill in his deviations, if any, from FEDO’s requirements. 2.2.0 The vendor shall forward a filled-in VDR form along with his offer, if he has got any deviation from FEDO’s requirements. In the absence of a filled-in VDR form along with the offer, it will be presumed that the vendor is accepting FEDO’s requirements specified in the VDR. 3.0.0. CLASSIFICATION OF DOCUMENTS 00ES001/2010 PAGE 2 OF 4 3.1.0. Documents are classified based on their status and nature of content. 3.1.1. Status of documents: 1. Preliminary documents required along with the offer. 2. Documents to be submitted after commitment. 3. Final documents. 3.2.0. The documents are further classified into Groups A,B and C, depending on the nature of the documents as explained below. 3.2.1. Group A requirements These documents are urgent in nature and contain information that is required for proceeding with the detailed engineering of surrounding / down stream equipments in the plant and hence are to be submitted on priority basis. 3.2.2. Group B requirements These documents are to be reviewed by FEDO for compliance with the purchase order / work order specifications but are not essential for other engineering activities of FEDO. 3.2.3. Group C requirements Documents in this group contains data / information / records which are final in nature and that are required for the equipment user and need not be reviewed by FEDO. 4.0.0. VENDOR DATA INDEX (VDI) 4.1.0. Vendor shall forward a filled up and updated VDI along with each vendor data transmittal. VDI shall list out all documents that are being prepared for the particular order, their current revision status and indicate the documents included in the present transmittal. A blank VDI is attached along with this document, which shall be used for this purpose. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION VENDOR DATA SUBMISSION PROCEDURE 5.0.0. QUALITY OF VENDOR DRAWINGS 5.1.0. Vendor drawing and data shall be supplied in full size drawings, reproducible and CDs as specified in the VDR. 5.2.0. All drawings / documents shall be clear, legible, right reading and made out of originals prepared in black ink. English language and metric units shall be used for the preparation of all documents. 5.3.0. The documents shall be prepared n any of the following standard sizes. 5.3.1. 5.3.2. 5.3.3. 5.3.4. A1: 594 mm x 840 mm A2: 420 mm x 594 mm A3: 297 mm x 420 mm A4; 210 mm x 297 mm 5.4.0. All documents submitted to FEDO shall be folded into A4 size (210 x 297 mm) except originals / reproducible which may be rolled. All reproducible shall be in high quality polyester films. Soft copies shall be furnished in CD for final drawings / documents. 5.5.0. Each drawing / document shall have a title block at the right hand bottom corner with the following information. 5.5.1. 5.5.2. 5.5.3. 5.5.4. 5.5.5. 5.5.6. 5.5.7. Name of Vendor. Drawing title. Name of Project, Owner and location. Name of Consultant: FEDO FEDO Purchase Order Number. Equipment name & Number Drawing number, revision and page number. 5.6.0. All drawings shall be drawn to some standard scales only and the same shall be indicated in the drawing. 5.7.0. The status of the document like “PRELIMINARY, FINAL, FOR REVIEW” etc. shall be stamped on all copies forwarded to FEDO. 00ES001/2010 PAGE 3 OF 4 5.8.0. All documents shall have a block of 100 mm x 100 mm space left vacant for FEDO to put their stamp after review. 5.9.0. All drawing/document shall have a revision block explaining revision number, revision description, data of revision, revision authorization etc. When the revised drawings are submitted all currently revised area shall be clearly demarcated by clouding. Any revisions made on other parts of the documenting will not be reviewed by FEDO. 5.10.0. When drawings are received back from FEDO with comments, vendor shall incorporate all the comments and resubmit the same. If the vendor is not in a position to incorporate certain comment made by FEDO, then the reason for such deviation shall be highlighted in the forwarding letter to FEDO. 5.11.0 The respective engineering specification and other purchase order spec. Will explain the minimum data / details required in various drawings. In the absence of any such information in the purchase order documents, vendor shall follow the standard good engineering practices in detailing the drawing. 6.0.0. CONDITIONS OF FEDO REVIEW 6.1.0. FEDO and / or its client reserve the right to review the vendor documents. FEDO’s REVIEW WITH OR WITHOUT COMMENTS OF THE VENDOR DOCUMENTS SHALL NOT RELIEVE THE VENDOR OF RESPONSIBILITY TO COMPLY WITH ALL PURCHASE ORDER TERMS AND CONDITIONS, including all implied requirements relating to fitness for service and good engineering practices. Approval or acceptance does not imply or infer any determination relating to compliance by the vendor with its full FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION VENDOR DATA SUBMISSION PROCEDURE responsibilities under the purchase order. 6.2.0. FEDO’s comments are limited to identifying requirements within the scope of the purchase order or failure by the vendor to comply with the requirements of purchase order, as revealed by the limited review. Oversights in the above limited review cannot be taken as approval for the vendor to deviate from the purchase order conditions. FEDO reserve the right to point out any such deviations at any stage of the order execution. The vendor shall comply with all such requirements without any price / delivery implications. 6.3.0. FEDO review will be authorized by an official stamp as given below, properly filled and signed by the concerned. Comments if any will be indicated in red ink or clouded in the case of copies of commented drawings. Appropriate comment in the ‘comments’ column and ‘status of review’ column will be marked. Comment As noted No comments Not reviewed 00ES001/2010 PAGE 4 OF 4 Status of Review Revise and resubmit for review Proceed as noted and submit revised docs. For records No further review required Forward final docs. As per P.O. 6.4.0. All documents received in FEDO shall be dispatched after review within 15 days from the date of receipt. Vendor shall notify FEDO of non-receipt of reviewed documents in time immediately, to take corrective actions. 6.5.0. The delivery of the equipment shall in no case be linked with the review of the vendor drawings and data by FEDO. It is the sole responsibility of the vendor to execute the job as per the purchase order conditions. If required the vendor shall depute his technical personnel to FEDO after submission of documents for timely finalisation of documents. *********************** FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION STORAGE TANK 02ES032/2010 PAGE 1 OF 11 CONTENTS 1.0.0 GENERAL 2.0.0 DESIGN 3.0.0 MATERIALS 4.0.0 FABRICATION 5.0.0 PREPARATION & SHOP INSPECTION 6.0.0 PLATE TREATMENT 7.0.0 PAINTING 8.0.0 WELDING 9.0.0 TESTING 10.0.0 VENDOR DOCUMENTS 11.0.0 STATUTORY REQUIREMENTS 12.0.0 GUARANTEE PRPD.BY:- JC CHKD.BY:- CK APPRD. BY:- JK FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON:- April 2010 ENGINEERING SPECIFICATION 1.0.0 GENERAL 1.1.0 SCOPE 1.1.1 02ES032/2010 STORAGE TANK This specification covers the requirements for the design, selection of materials, preparation of drawings, fabrication, erection, inspection, testing, repairing, painting and calibration of the storage tanks. 1.1.2 FEDO means FACT ENGINEERING AND DESIGN ORGANISATION, their authorised representative or their client. 1.2.0. CODES AND STANDARDS 1.2.1. Tanks shall be designed generally in accordance with IS-803 or API-650 (latest) as specified in the respective equipment specification/data sheet. 2.0.0. DESIGN 2.1.0. CALCULATION 2.1.1. The calculations justifying the size and plate thickness of the various items like shell, roof, bottom plates, and accessories like wind girder, roof rafters/ girders, bleeder vents, drains, pipe supports etc. shall be established by the vendor, in conformity with the codes and the same shall be submitted for review by FEDO. 2.1.2. Floating roof design calculations shall be submitted to FEDO for approval along with the quotation. Central deck and pontoon shall be stiffened suitably and calculations for structural stability and strength of the floating roof shall be submitted for FEDO review. 2.1.3 General arrangement drawing of the tank along with an approximate tonnage of plate requirement, thickness wise, shall be furnished along with the quotation for review by FEDO. 3.0.0 MATERIALS PAGE 2 OF 11 spark-proof rings shall conform to material specifications IS-226/ IS-2062 and aluminium. 3.5.0 Reinforcement pads for nozzles, manholes etc. shall conform to same specifications as that of shell plates. 3.6.0 Gaskets for manholes and nozzles fitted with blind flanges shall conform to IS-2712. Thickness of gasket shall be 1.5 mm for nozzles upto 450 NB and 3.2 mm for nozzles above 450 NB. One set of gaskets shall be supplied in addition to the set used during testing at no extra cost to FEDO. 3.7.0 Bolts and Nuts far all nozzles fitted with blind flanges shall conform to A-193 Gr B7, A-194 Gr 2H or equivalent and bolts and nuts for structurals shall conform to IS-1363/1367. 3.8.0 Platforms, stairways and gangways shall all be of gratings. 3.9.0 Floating roof pipe supports and pipe sleeves shall be of carbon steel conforming to A-106/ A-53 seamless / IS1978 seamless or equivalent of Sch-80, unless otherwise specified. 3.10.0 Electrodes used shall meet the minimum requirements of the applicable code and appendix. Vendor shall get approval by FEDO for the list of manufacturers for procurement of electrodes. Test procedure as approved by FEDO shall be carried out by the vendor. 3.11.0 Materials indicated above are to be considered as minimum quality and materials of an equivalent or superior quality may be substituted. No substitution of material is to be made without the written consent of FEDO. 3.12.0 Vendor shall submit manufacturers test certificates for all bought out items, and the same shall be used only after approval by FEDO. 3.1.0 All plates for shell, bottom, roof etc. shall be as specified in the tank drawing. 4.0.0 FABRICATION 3.2.0 4.1.0 BOTTOM PLATE Nozzle neck thickness shall be as per code / tank drawing. Nozzle neck made from rolled and welded plates of similar grade as the shell to which they are attached may also be used for nozzles above 250 NB. 3.3.0 All flanges and couplings should be-as indicated in the drawing. 3.4.0 Pipes for handrails for tank shall conform to IS-1239. Gauge hatches with 4.1.1 Bottom slope of tank shall be as indicted in the drawing. 4.1.2 The plates (except annular plates) shall be lap welded with overlap not less than 5 times the plate thickness of sketch plates. For sketch plate to annular plate overlap shall not be less than 65 mm. Overlaps shall be properly cleaned using steel wire brush before welding. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES032/2010 STORAGE TANK 4.1.3 Annular plate shall be assembled by buttwelding with backing strips and it shall be lap welded to sketch plates. PAGE 3 OF 11 4.2.7 Wind girder shall be designed and provided as per the specified design code. 4.2.8 Fixed roof shall be preferably selfsupporting type. 4.2.9 Supported cone roofs may be provided with internal or external structure supports as specified in the eqpt. spec/data sheet. 4.3.0 FLOATING ROOF 4.3.1 Floating roof shall be of low deck type. Type of deck (single or double) shall be as specified in the eqpt. Spec. 4.3.2 Deck shall have a level surface or be provided with a slope to the centre to avoid stagnation of rainwater. 4.3.3 When floating roof is in the highest position tank shall be capable of holding the designed capacity. 4.3.4 4.1.7 Welding sequence adopted shall be shown in vendors drawing and should give minimum shrinkage and distortion and shall be got reviewed by FEDO. Floating roof design calculation shall be submitted to FEDO for approval along with quotation. 4.3.5 4.1.8 Reinforcement shall be provided to the tank bottom where concentrated loads such as heating coil supports, tank agitator supports etc. are located. 4.3.6. Floating roof shall be annular and centre pontoon with multiple compartment type or Buoy-roof type, liquid proof with minimum requirement of IS 803 /API-650 (latest). Centre deck shall be provided with 2 Nos. man- holes. One of these manholes should be provided with a welded ladder for stepping down to bottom when the roof is in its lowest position. This shall have suitable clearance from tank internals. The other manhole shall allow dismantling of roof drains from the top of the roof. 4.1.4 First course shell plates shall be arranged so that the vertical seams do not coincide with the butt welds of annular plates. Vertical joints of two consecutive shell courses shall not coincide and shall be offset by at least the minimum value for such occurrence specified in the code. The weld seams should not pass through the nozzle openings or reinforcement pads. 4.1.5 Bearing plates shall be centred under each support attached to the tank bottom by a 5 mm continuous fillet weld. Plate shall be minimum 600 mm dia x 20 mm thick. 4.1.6 Datum plate, of the tank shall be welded on the pad plate provided on the bottom vertically below the gauge well pipe after calibration of the tank. 4.2.0 SHELL & ROOF 4.2.1 All vertical and horizontal shell joints shall be full penetration and full fusion welds. 4.2.2 Shell joints shall be double welded butt joints using edge preparation permitted by API-650 latest edition. Details of the weld must be shown in drawings and shall be approved by FEDO. 4.2.3 4.3.7 Access manholes 600 NB dia. shall be provided for entry into each of the pontoon. These shall have waterproof covers. Pontoons shall be numbered serially. Wind girders shall be welded to the tank as shown in the tank drawings. Welding shall be of the same quality as used for the shell. Drain holes shall be provided on the horizontal plates. 4.3.8 Foam dam should be provided along with pontoon. The minimum height of the foam dam shall be 610mm. 4.2.4 Curb angle/stiffening ring welds should not coincide with shell welds. 4.4.0 STAIRWAYS 4.4.1 4.2.5 Vertical plates shall be offset at least one third of each plate length or 1000 mm whichever is higher and the internal weld seams shall be ground smooth and even, to allow proper movement of roof. For access to the top from the ground, spiral stairways may be provided terminating at the top. 4.4.2 For the floating roof tanks, top-landing platform shall be provided for the stairway. The same shall be extended over the roof to permit easy access to roof accessories. 4.2.6 Holes shall not be made in shell plates for erection purposes. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 4.5.0 ROLLING LADDER PAGE 4 OF 11 4.9.2 Sealing system shall exert sufficient sealing pressure in all directions to prevent any evaporation loss and the arrangement shall touch the product during operation. Foam seal should have excellent flexibility and recovery from compression and at the same time permit the roof movement up and down freely with the level of tank contents. 4.9.3 Vendor shall furnish details of seal and seal cover along with catalogue for FEDO review, at the time of quotation. Foam seal cover minimum thickness shall be 3mm. 4.9.4 Guarantee for sealing material for its durability and its life should also be furnished. 4.9.5 The weather shield of the foam seal shall allow entry of foam into the seal space during fire fighting. The rubbing surface of the weather shield shall be coated/covered with resilient material so as to avoid scoring on the oil side of shell. Roof seal angle shall be with galvanised S.S. shunts. 4.5.1 For the floating roof tanks, a rolling ladder shall be provided for access from the platform to the floating roof. Rolling ladder tracks shall permit easy movement of the ladder. 4.5.2 Brass rollers for the rolling ladder shall be provided to prevent sparking. 4.6.0 ROOF VENTS 4.6.1 Roof shall be provided with vents as per eqpt. Spec/drawing. 4.6.2 Floating roof tanks roof shall be provided with automatic bleeder vents designed to open before the roof reaches its lowest position and to close when the roof rises above this point. The contact surface of bearing plate of automatic bleeder vent shall be spark-proof. 4.6.3 Rim vents shall be provided for the floating roof tanks for venting the space between stored liquid and the seal. Pressure-Vacuum vents shall be coupled with rim vents. The peripheral spacing of rim vents shall be about 50m. 4.7.0 GAUGEWELL PIPE 4.7.1 Gauge well pipe shall be of size 250 NB. The gauge well pipe shall facilitate installation of automatic tank gauging system and easy usage of dip rod/tape. 4.7.2 Gauge well pipe shall act as anti-rotation device in floating roof tanks to avoid the rotational movement of the floating roof. 4.8.0 GAUGE HATCH NOZZLE 4.8.1 Gauge hatch nozzle size shall be as indicated in the Eqpt. spec/drawing. 4.8.2 Gauge hatch shall have a quick opening spark- proof cover and shall be fitted with a renewable aluminium guide channel for the dip tape. 4.9.0 02ES032/2010 STORAGE TANK FLOATING ROOF SEAL 4.9.1 The space between the outer rim of roof and shell shall be sealed by an approved sealing device (foam seal). The sealing material shall be resistant to stored product and also durable against friction due to roof movement. 4.10.0 FIXED ROOF SUPPORT 4.10.1 For fixed roof tanks the roofs shall preferably be of the columnless selfsupporting type. 4.10.2 Column and rafter arrangement is acceptable for large diameter tanks. However internally lined tanks shall be provided with rafter or girder supports on the out side of the roof. 4.11.0 FLOATING ROOF SUPPORT 4.11.1 Floating roof supports and pipe sleeves shall be carbon steel pipe with minimum thickness conforming to schedule 80. 4.11.2 The number of supports shall be determined so as to ensure that the roof when it rests on the supports does not deform the tank bottom and/or the roof. 4.11.3 Bearing plates shall be provided beneath the roof legs so as to prevent damage to the bottom during operation of the tank. 4.11.4 Support legs shall permit adjustment of the roof in two positions. The highest position, 1.8 m from the bottom, shall be for inspection maintenance and cleaning the inside of the tank. The lowest operating position shall not interfere with the internal accessories. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION PAGE 5 OF 11 4.12.0 EXTERNAL CLIPS 4.12.1 Extension Plates, brackets, clips and suitable stiffeners for Foam nozzle, Pad Plates for fixing brackets, Pipe supports, supports for Foam & Fire Hydrant system shall be provided. 4.12.2 For Jackup type tank construction, pad plates for fixing hydraulic jacks and other fixtures at various elevations shall be provided earlier. 4.13.0 FLOATING ROOF DRAINS 4.13.1 Water shall be evacuated from the floating roof by means of articulated pipe drains with swivel joints, of approved make and type. 4.13.2 The inlet of each drain shall have a swing type check valve to prevent product from flowing on to the roof if the pipe drain fails. A minimum Clearance of 200 mm between the valve and the sides of the valve chamber shall be maintained. All swivel joints shall be tested to a minimum 2 pressure of 3.5 kg/cm before putting into roof drain assembly. 4.13.3 The valve chamber accessible from roof. shall be 4.13.4 The drains should be so designed as to permit the roof to be lowered upto lowest operating level of roof. 4.13.5 Swivel joints should have double row ball bearings and Viton 'O' ring at both ends. 4.13.6 Sufficient clearance shall be kept between roof drain pipe and roof supports. 4.13.7 The roof drains must cater to the design rainfall intensity with 100% run-off at the lowest level. Flow calculations for the same shall be submitted for FEDO review. 4.13.8 Emergency drains shall be provided in case of failure of drain and also to prevent backflow of the stored product. These drains shall be equipped with water seal sump inside the tank. 4.14.0 EARTHING 4.14.1 02ES032/2010 STORAGE TANK The tank shell shall be earthed as per NEC. 4.14.2 Floating roof shall be provided with wire cables for earthing rolling ladder to track and ladder to shell. 4.15.0 TANK ACCESSORIES 4.15.1 All appurtenances and accessories shown in the tank datasheet/drawing shall be supplied by the vendor unless otherwise noted. 4.15.2 All appurtenances shall be supplied and fitted as per applicable codes. 4.15.3 Additional appurtenances if any required for the satisfactory performance of the tank shall be provided. 4.16.0. SETTLING MARKERS 4.16.1 Markers shall be fitted on the shell 500mm from the bottom, eight in number, to check tank settlement during hydraulic testing. These shall be fitted at 450 equally placed. Markers shall be 50x50x6x100mm long angle. 5.0.0 PREPARATION INSPECTION AND SHOP 5.1.0 PLATES 5.1.1 Edges of the plates shall be preferably sheared or gas cut or m achine cut as per code. All machined surface shall be suitably protected before assembly. Grinding shall be done to the gas cut edges to the satisfaction of FEDO site engineer. 5.1.2 All shaped plates shall be match marked with paint on the concave side with the number shown on the erection drawings. 5.1.3 The ends to be welded shall be properly cleaned to remove paint, oil, grease, rust, oxides, sand, earth and other foreign matter. The ends shall be completely dry before the welding commences. 5.2.0 STRUCTURALS 5.2.1 Structural steel fabrication shall be done by the vendor to the required shapes and sections making up the structure. All items shall be match marked. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES032/2010 STORAGE TANK PAGE 6 OF 11 5.3.0 NOZZLES AND OPENINGS 7.3.0. SPECIFICATION FOR PAINTING 5.3.1 Nozzles shall be provided as per the eqpt. data sheet/drawing. 7.3.1. FEDO reserves the right to change the specifications of paint and approve the quality of paint before painting. All painting materials shall be approved by FEDO site engineer and if in his opinion any tests are to be conducted, the same shall be done by the vendor at his cost. All painting jobs shall be carried out strictly according to the paint manufacturer's application procedure. 5.3.2 Nozzles and manholes may be shop fabricated and assembled at site. 5.3.3 Nozzle reinforcement shall be provided as per the code requirement. 6.0.0 PLATE TREATMENT 6.1.0 All plates shall be thoroughly cleaned and freed from rust, scale and grease and have a good appearance. 6.2.0 It is required that the plates for the shell, roof and external structures and upperside of bottom plate of the tank shall be sand blasted. Plates should have a uniform matt-grey colour. 7.0.0 PAINTING 7.1.0 Tank shall be painted in accordance with the data sheet/Equipment specification and FEDO Engineering specification for painting. 7.2.0 EXTENT OF PAINTING 7.2.1 The areas that are to be painted for any tank shall include all such areas that are made of carbon steel and not in contact with the process fluid. This shall include the following Shell outer surface Roof top and bottom surfaces Bottom side of bottom plate. All structural like roof supports, rafters, and girders Platforms, ladders, stairways and landings Inside of shell above the maximum liquid level or overflow level Nozzles and flanges except flange facing All external clips and pipe supports Top portions of internal column supports above maximum liquid level 7.2.2 For floating roof tanks, the following area are also to be painted. Wind girder Top of deck/ pontoons / buoys Inside of pontoons Portion of shell inside for a height of 900 mm. below curb angle Pontoon outer rim above product level. 7.4.0 SURFACE PREPARATION 7.4.1. Dry Sand Blasting Before sand blasting all greasy substance shall be removed by means of adequate washing. Sand blasted surface shall have a finish of SA 2 ½ grade Swedish and be rough enough to obtain the best condition for moisture, oil. Sand blasting shall be restricted to day time. Sand blasting should be stopped whenever the blasted surface appears to be damp or the relative humidity of the environment exceeds 85%. 7.4.2 Wire Brushing - Where overcoat painting is carried out on the previously painted shell, wire brushing shall be carried out to make the surface sufficiently rough for proper bonding of the new layer of paint. 7.4.3 The primer must be applied on the sand blasted surface the same day before sun-set and in any case before any oxidation takes place. 7.4.4 When weld joints are left without painting till hydro test is completed, sand blasting is to be done along weld joints before painting. 7.5.0 APPLICATION OF PAINTING 7.5.1 No paint shall be applied without the approval of FEDO. A coat or paint can be applied only after the previous one is dry, FEDO reserves the right to ask for the suspension of the work when humidity increases 85% or during rain, fog or dusty environment. The overall thickness of the protective coats after drying shall be checked by FEDO and in case the thickness of the paint is found insufficient, the vendor shall be obliged to give further coat at his own cost. All painting should be done by brush of width not more than 150 mm. 7.5.2 Machined faces of all flanges shall be varnished and protected with wooden discs. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES032/2010 STORAGE TANK PAGE 7 OF 11 the containers shall be kept in ovens at temperatures recommended by the electrode manufacturer. Out of the oven time of electrodes, before they are consumed, shall not exceed the limits recommended by the electrode manufacturer. 8.0.0 WELDING 8.1.0. WELDING PROCESS 8.1.1. Welding of various materials under this specification shall be carried out using one or more of the following processes, with the approval of FEDO. a. Shielded metal arc welding process. b. Automatic submerged arc welding process. 8.1.2 A combination of different welding processes or a combination of electrodes of different class/makes could be employed for a particular joint only after duly qualifying the welding procedures to be adopted and obtaining the approval of FEDO. 8.1.3 All structural items shall not be welded directly on the shell. Pad plate of the same material as the shell shall be provided for this purpose. 8.2.0 FILLER MATERIALS 8.2.1 The electrode/filler wire shall be suitable for the welding process recommended and base metal used. Physical properties of the welds produced by an electrode/filler wire recommended for the welding of a particular base metal shall not be lower than the minimum values specified for the base metal and shall correspond to the physical properties of the class of electrode used. The choice of electrode shall be made after conducting the required tests on the electrodes as per relevant standards and shall be to the satisfaction of FEDO site engineer. 8.2.2 Qualification of electrodes as per ASME Section-II, Part-C is to be carried out for those electrodes, which have not been qualified by FEDO. The relevant sections of the code are given below SFA 5.1 - Carbon steel covered arcwelding electrodes SFA 5.5 - Low alloy steel covered arcwelding electrodes. 8.2.3 The vendor shall submit batch test certificates from the electrode manufacturers giving details of physical and chemical tests carried out by them for each batch of electrodes to be supplied by the vendor. 8.2.4 All electrodes shall be purchased in sealed containers and stored properly to prevent deterioration. The electrodes removed from 8.3.0 WEATHER CONDITION 8.3.1 The parts being welded and the welding personnel should be adequately protected from rain and strong winds. 8.4.0 WELDING TECHNIQUE 8.4.1 On completion of each run, craters, weld irregularities; slags, etc. shall be removed by grinding. 8.4.2 The weld beads shall not be started at the same point in different layers. 8.4.3 The weld shall be free from undercuts and other defects. 8.4.4 Weld identification mark shall be stamped clearly at each joint, just adjacent to the weld. Suitable paint shall be used on thin weld joints for identification instead of stamping. 8.4.5 No painting shall be done until weld-joint has been approved. 8.5.0 WELDING PROCEDURE QUALIFICATION 8.5.1 Shielded metal arc welding, Automatic submerged arc welding or a combination of the two will be used for welding of various joints. Any welding process, combination of welding processes, different classes/makes/combinations of electrodes, can be employed only after qualifying the welding procedure. Procedure qualification is to be carried out as per ASME Section IX and API 650, Chapter 7, vendor has to submit procedure for approval before starting qualification tests. For welds involving high strength materials (group IV, IVA, V & VI of Table 2 - 3 of API 650, procedure qualification shall be carried out as follows 8.5.2 Test to be conducted for plates of each specification and grade to be used in the tank construction. Test plate to be as thick as the plate of same type used for the tank shell. 8.5.3 Test to be carried out for to each position and for each process employed for the tank construction. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES032/2010 STORAGE TANK PAGE 8 OF 11 8.5.4 The positions requiring qualification are 2G and 3G to shell and 1G with backing for annular plates. For nozzle joints procedure qualification may be conducted in 5G position. 8.5.5 No welding shall be taken up without approval of the welding procedure and welder qualification tests by FEDO. 8.5.6 Welding procedure qualification shall be carried out in accordance with the relevant requirements of ASME Sec.IX latest edition or other applicable codes and other job requirements. The vendor shall submit the welding procedure specifications immediately after the receipt of order. 8.6.4 If a welder is found to perform a type of welding or in a position for which he is not qualified, he shall be debarred from doing any further work. All welds performed by an unqualified welder shall be cut and redone by a qualified welder at the expense of the vendor. 8.5.7 FEDO will review, check and approve the welding procedure submitted and shall release the procedure for procedure qualification tests. The procedure qualification test shall be carried out by the vendor at his own expense. A complete set of test results shall be submitted to FEDO for approval, immediately after completing the procedure qualification tests and at least two weeks before commencement of work. It shall be the responsibility of the vendor to carry out all the test required to the satisfaction of FEDO. 8.6.5 Welders engaged by the vendor shall be tested and classified as follows a. 'A' Grade welders 8.6.0 8.6.1 a. b. WELDER QUALIFICATION Performance Qualification All welders employed for the job are to be qualified as per ASME Section IX. Each welder shall be qualified for the particular welding position and the corresponding class of electrode to be employed in the job. All welding including that for temporary fixtures, erection/fit-up at shall be done only by qualified welders. Each welder has to qualify the mechanical tests as per QW 302.1 of ASME Section IX.or other applicable codes. FEDO shall witness the test and certify the qualification of each welder separately. Only those welders who have been approved by FEDO shall be employed for welding. Vendor shall submit the welder qualification reports in the standard format and obtain express approval, before commencement of the work. It shall be the responsibility of the vendor to carry out qualification tests of welders. 8.6.2 The welders shall always have in their possession the identification card and shall produce it on demand by FEDO. It shall be the responsibility of the vendor to issue the identity cards after they have been duly certified by FEDO. 8.6.3 No welder shall be permitted to work without the possession of identity card. They will be permitted to weld shell. The welders will be tested by the FEDO Engineer for horizontal and vertical position butt welds. Another set of welders will be given pipe welders test and will be permitted to weld nozzles, appurtenances and reinforcing pads. b. 'B' Grade welders They will be allowed for fillet welding only. The welders will be tested by the FEDO for fillet weld and butt-welding on down hand position only. The vendor shall make arrangement for such test at his own cost, in the presence of FEDO. 8.7.0 INSPECTION OF WELDS Inspection of welds shall follow the steps given below: a. Conduct welders’ qualification tests and certifies their qualification. b. Verification and development welding procedure. of c. Inspection of welding equipment and electrodes used. d. Supervision and inspection of execution of welds. e. Fixing up location and verification of radio graphs submitted. f. Inspection of hydrostatic, bottom and roof tests and any welding repair. g. Develop and inspect any special tests when those carried out by the vendor are considered insufficient. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES032/2010 STORAGE TANK PAGE 9 OF 11 h. Stamp the weld identification marks after the inspection. i Prepare inspection reports in accordance with relevant procedures. presence of FEDO site engineer and test certificate will be issu ed accordingly. 9.1.5 Liquid penetrant examination and acceptance criteria shall be as per ASME Sec.VIII Div.l latest edition wherever specified in the draw ing/code. 9.1.6 Liquid penetrant test shall be substituted for radiography test for the annular plates. The annular plate butt joint root run shall be 100% dye penetrant tested. 8.8.0 RADIOGRAPHY & INSPECTION OF WELDS 8.8.1 Tank welds shall be radiographed and interpreted as per API 650 (latest) and applicable index. 8.8.2 Quality control shall be progressively through out the job. done 8.8.3 Radiograph film length shall be 10 inches minimum, except if the weld is less than 10 feet long. 8.8.4 Radiograph film shall be of approved quality. 8.8.5 The vendor shall be responsible for taking the radiography by his own equipment at his own cost for the entire job. 8.8.6 Weld areas to be radiographed shall be designated by FEDO. 8.8.7 Radiographs of the welds shall be taken as soon as the welding joint is completed. If repairs are required, they shall be carried out, before continuing the other welds, by the contractor at his own cost. Welds attaching nozzles, manholes etc. shall be inspected as per API-650 latest and applicable appendix. 8.8.9 Welds found faulty as a result of radiographic, visual or other tests must be chipped off to the satisfaction of FEDO or his representative and a re welded as per specifications and instructions. The weld portion shall be retested as per the instructions of FEDO or his representative. No claim for compensation whatsoever shall be entertained by FEDO on this account. 9.2.0 SHELL TESTS 9.2.1 Bottom to shell joint testing shall be a. Inner fillet weld shall be inspected and tested prior to welding the outside fillet weld. The leak testing shall be performed with penetrating oil after removal of slag. Oil shall be removed before welding the outer fillet. b. Examination for inner fillet toe cracks shall be performed using either liquid penetrant or magnetic particle method. 9.2.2 After completion, tanks shall be thoroughly cleaned. All weld lugs and brackets used for erection purposes shall be carefully removed from outside and inside surface of the tank to the entire satisfaction of FEDO or his representative. Parent metal damaged during removal of erection lugs, brackets etc. shall be repaired by filling weld metal and grinding to the satisfaction of FEDO site engineer. 9.2.3 The vendor shall hydrostatically test the tank including filling and emptying. The approved procedure shall be used for the hydro-testing. If salt water is used for testing and will remain in the tank for more than 30 days, an oxygen scavenger and corrosion inhibitor shall be added. After testing, the tank shall be drained and thoroughly rinsed with clean fresh water. Water, silt or other dirt left in the t ank after hydrostatic testing shall be cleaned so that the tank interior is "broom" clean and ready for operation. 9.2.4 The vendor shall furnish, lay and remove all lines required for testing 8.8.8 9.0.0 TESTING 9.1.0 BOTTOM TESTS 9.1.1 The weld joints along the periphery shall be tested before erection and welding of the first shell. 9.1.2 Leak tightness of the bottom will be checked by vacuum box. 9.1.3 A detailed description of the proposed method shall be submitted for FEDO review. 9.1.4 Vendor shall test the tank bottom for the entire weld length in the FACT ENGINEERING AND DESIGN ORGANISATION 02ES032/2010 STORAGE TANK ENGINEERING SPECIFICATION PAGE 10 OF 11 from the water supply source and to the water disposal point. This sh all include all pumps, valves etc. 9.2.5 After completion, thoroughly cleaned. tanks shall 9.2.6 All openings not used for the hydrostatic test or any other test shall be closed by plugs and blind flanges supplied by the vendor. 9.5.0 TEST GAUGES 9.5.1 All pressure and vacuum gauges shall be calibrated and calibration certificates shall be availability for verification before their use on tests. be 9.2.5 After equipment, required for testing, shall be supplied by the vendor. 9.2.6 Vendor shall perform the hydrostatic test in the presence of FEDO on each tank after erection. Any defects observed during the testing shall be repaired by the vendor. 9.2.9 When the tank is full upto the nominal capacity, all welded joints shall be hammered by the vendor in the presence of FEDO. In case of any defect, it shall be repaired and retested by the vendor as per the instructions of FEDO. 9.2.10 Tank shall be emptied at a maximum water level variation rate of 5m per day or as per the instructions of FEDO. 9.2.11 All weld repairs shall be done with water level minimum 300mm below the joint being repaired. 9.3.0 ROOF TESTS 9.3.1 Tank roof shall be tested by vacuum box or applying internal pressure at the option of the FEDO. Vendor has to make arrangements for required tests. 9.3.2 The roof drain is to be pressure tested at 4.0-kg/cm2 gauge pressure. After fixing the roof seal there should not be any clearance between shell and seal at any location for the entire tank height and this is to be verified during hydro-testing. 9.3.3 Pressure - vacuum relief valves are to be tested before installing. 9.3.4 Proof testing of the floating roof simulating the minimum floating roof design requirements as per code requirements shall be done with the floating. 9.4.0 NOZZLE REINFORCING PLATES 9.4.1 These reinforcing plates shall be air pressure tested at 3 Kg/cm2 with soap solution. This test shall be done before hydrostatic testing of tank. 10.0.0 VENDOR DOCUMENTS 10.1.0 Vendor shall furnish documents as listed in the Vendor data requirements form in accordance with the vendor data submission procedure. 10.2.0 Type of documents to be submitted shall include Fabrication drawings. Calculation sheets. Material test certificates Radiographic results Test reports. WPS S PQR Calibration charts. 10.3.0 DRAWINGS 10.3.1 General arrangement drawings of the tank with design data and material specifications are attached with the Enquiry/P.O documents. 10.3.2 Vendor shall forward the general arrangement drawing and plate requirement of the equipment along with the offer, if called for in the enquiry. 10.3.3 On award of contract, vendor shall design the tank and prepare detailed fabrication drawings. 10.3.4 Fabrication drawing of tank include the following details. shall General arrangement with overall dimensions and plate thickness. Detailed fabrication drawing of each component Weld lines, weld profiles and sizes Edge preparation and method employed. Tolerance Quality, brand name. gauge of electrode to be used. Details of reinforcement pads with tell tale holes Nozzle details Details of brackets for supporting pipes, platforms, ladders/staircase, earthing connection etc. Detail of appurtenances Details of internal fixtures FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES032/2010 STORAGE TANK PAGE 11 OF 11 Complete bill of materials indicating supply by FEDO/vendor with item wise weight Total plate requirement 10.4.2 Design calculation of floating roof tank shall also include the following item. Design of Pontoon & structural stability analysis Pontoon support calculation Flotation calculation of floating roof Design and sizing of vent & drains All other information and general and special instructions required as per FEDO drawings Plate cutting diagrams Detail of structure for roof supports Details of stairway, platforms and handrails 11.0.0 STATUTORY REQUIREMENTS Development details of shell, roof, floating roof and bottom WPS and PQR. Catalogues / drawings for bought-out items. 11.1.0 Vendor shall arrange for all necessary statutory clearances like IBR, CCE approval etc. for drawings, fabrication and site work at his own cost, unless other wise specified in the purchase order. 10.3.5 The following details are also required in the case of floating roof tanks. Arrangement drawing and fabrication details of floating roof tanks Pontoon support details Rolling ladder and rack 12.0.0 GUARANTEE 12.1.0 Vendor shall guarantee that all materials used for the equipment have been submitted to regular acceptance procedure and free from any defect regarding quality, form and appearance, 12.2.0 Vessels must be guaranteed for design; materials and workmanship for a period as specified in the Commercial conditions of the Purchase Order. Rim vent, bleeder vent, PV valve, foam bund etc. Centre drain and articulated drain pipe Foam seal and fixing detail Deck nozzles, man ways and other pontoon accessories 12.3.0 Any vessel, or its part not having been submitted to wrong operating service or faulty manipulation and found defective during erection, test or during operation, shall be repaired / replaced by the vendor without delay and free of cost within the guarantee period. 12.4.0 In case of defective equipment FEDO shall have the option to repair / replace the equipment after intimating to the manufacturer, in order to avoid time delay. In such an event, FEDO shall been titled to recover the cost of such repair / replacement from the vendor. 10.4.0 DESIGN CALCULATIONS. 10.4.1 The design calculations shall include design of the following items Shell, roof & bottom plates, Roof structure & supports Wind and earthquake analysis Design of wind girder Design of anchors Stress analysis of agitator mounted nozzles. ****************** FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES023/2010 PAINTING PAGE 1 OF 13 CONTENTS: 1.0.0. SCOPE 2.0.0. MATERIALS 3.0.0. SURFACE PREPARATION 4.0.0. STORAGE OF PAINTING MATERIALS 5.0.0. MIXING AND THINNING 6.0.0. PAINTING 7.0.0. SAFETY 8.0.0. INSPECTION 9.0.0. GUARANTEE 10.0.0. CODIFICATION OF PAINTING MATERIALS 11.0.0. SCHEME OF PAINTING 12.0.0. COLOUR CODING & MATERIAL FOR PIPING TABLES PRPD.BY:- JC CHKD.BY:- CK APPRD. BY:- JK FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON:- April 2010 ENGINEERING SPECIFICATION 1.1.0. This specification covers the requirements for surface preparation, painting and painting materials for equipment, structures and piping (including those painted/primed at shop and those painted at Field/Site. 1.2.0. Requirement of painting for any item shall be as specified in any of the following documents. d) Equipment Data Sheet Piping line schedule Design Basis for package items Painting schedule 1.3.0. The purpose of painting described in this specification is generally for protection against corrosion. 1.4.0. Painting for other reasons shall be as indicated in the respective equipment data sheets or painting schedule. 1.5.0. The following surfaces exposed to atmosphere are covered by this specification, which are not provided by any other form of covering/coating. a) b) c) d) PAGE 2 OF 13 a) 1.0.0. SCOPE a) b) c) 02ES023/2010 PAINTING Pressure vessels, Tanks, Heat Exchangers and other process equipment with Carbon steel and low alloy steel as material of construction. Machinery items including motors. Steel structures Carbon and low alloy steel piping 1.6.0. The following items shall not be painted unless otherwise specifically required by respective equipment Data Sheets/Painting schedule b) c) d) e) f) g) h) i) j) Non ferrous surfaces, stainless steel and High Alloy steel surfaces. Glass, tile or ceramic surfaces Name plates and identification tags Valve stems Machined contact surfaces Galvanised surfaces Insulation covers Plastics Underground / buried piping and equipments which are provided with special type of protective coatings. Surfaces / Items which are excluded from painting due to specific reasons. 1.7.0. This specification also covers painting of “Markings” and color-coding of carbon steel, low/high alloy steel, stainless steel, galvanized iron and insulated pipes. 2.0.0. MATERIALS 2.1.0. All painting materials shall be of good quality as covered by respective IS or other international specifications 2.2.0. Special paints and painting materials shall have proven quality and shall meet the requirements laid down in the respective data sheets for equipment and piping. 2.3.0. All painting materials shall not have passed the date of expiry or shelf life as recommended by manufacturer. 3.0.0 SURFACE PREPARATION 3.1.0 All surfaces to be painted shall be free from rust, oil, grease, dust, stain, moisture or any other foreign material/contamination, as per IS 1477 Part I. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES023/2010 PAINTING PAGE 3 OF 13 3.2.0 Surfaces to be completely dry. be or when the relative humidity of air exceeds 90%. 3.3.0 Oil, grease, stains and other similar contaminants shall be completely removed by using proper solvents and removers, After cleaning, the surfaces shall be free from even traces of contaminants and solvents/removers. 3.9.3. Blasting operations shall not be carried out during rain, snow, or strong winds. 3.4.0 3.5.0 painted shall Dust shall be removed by air blowing or vacuum cleaning. Hard and caked dust, mud, mill scale and rust shall be removed by mechanical means like wire brushing, sand blasting , shot blasting or grit blasting. 3.6.0 Wet surfaces shall be dried by blowing warm air. 3.7.0 All surfaces cleaned by different methods shall be painted immediately with out allowing the clean surfaces togather dust, rust and other external substances. 3.8.0 During the course of painting if it is found that the surfaces are contaminated due to any reason, the same shall be cleaned by any of the methods described earlier, before further proceeding with painting. 3.9.4. Blasting medium viz. Slag, grit, or shot shall be completely dry and shall be free from any sort of contaminants like dust, oil, grease etc. 3.9.5. Blasting air shall be completely dry and shall have minimum pressure of 3.5 kg/cm2. 3.10.0 Surfaces which are not suitable for blast-cleaning or could not be blastcleaned due to practical reasons shall be thoroughly wire brushed to exhibit a pronounced metallic sheen, equivalent to St 3 as per IS 9954. 3.10.1 Absence of compressed air, slag/shot/grit and/or blasting equipment and accessories shall not be a reason for not carrying out blast cleaning. 4.0.0. STORAGE OF PAINTING MATERAILS 4.1.0. Paints, varnishes, thinner, additives and other volatile substances shall be stored in a flame proof enclosure, away from heat. 3.9.0 All surfaces to be painted after sand, grit or shot blasting shall exhibit almost clean white metal and shall have surface finish of SA 2 ½ as per IS 9954. 4.2.0. Fire extinguishers or sand and water for emergency fire fighting operations shall be provided near storage area at easily accessible place for use, in case of fire. 3.9.1 Blast cleaned surfaces shall be primed within 2 hrs, after blasting, before rerusting starts and before contamination. 4.3.0. Warning Boards and signs shall be exhibited around the storage area. 5.0.0. MIXING AND THINNING 3.9.2. Blast cleaning shall not be carried out when temperatures are less than 20C 5.1.0 Mixing and thinning of paints shall be carried out as per manufacturer’s recommendations. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 5.2.0 Mixing and thinning operations shall be carried out in well ventilated rooms. 5.3.0 Only that quantity of paint which is sufficient to cover the required area within the specified painting time, shall be mixed at a time. 5.4.0 Mixed paints shall be used with in the time span as recommended by manufacturer. Mixed paints, for which standing time specified has elapsed, shall not be used. 5.5.0 5.6.0 Ready-mixed paints containers shall be opened only at the time of painting. Containers shall be closed air tight after drawing paint from it. Ready-mixed paints shall be stirred well before drawing from the storage container as well as during painting operations. 5.7.0 Ready-mixed paints shall be thinned only if absolutely necessary by using thinners commended by manufacturer. 5.8.0 Balance of ready-mixed paints shall not be poured back into the main container after use, but shall be kept in a separate air tight container. 6.0.0 PAINTING 6.1.0 General Requirements. 6.1.1 Painting of equipment, piping and structurals shall be carried out at shop or site as prescribed in the respective eqpt. data sheets, piping line schedule or structural detail drawing. . 6.1.2 6.1.3 02ES023/2010 PAINTING Painting shall not be carried out on surfaces not prepared and not meeting the requirements of clause 3.0.0. Painting shall be carried out only under favourable conditions. Painting shall PAGE 4 OF 13 not be carried out in dusty and draught conditions in damp areas and during rainy seasons or cold atmosphere. 6.1.4 During painting, adjacent equipments or surfaces shall be protected from paint sprays, splashes or drips. 6.1.5 Painting shall be carried out only by using brushes, rollers, air/airless spray. 6.1.6 Caution boards indicating ‘wet paint’ shall be posted after painting is over and kept till the curing time is completed. 6.1.7 For painting of multiple coating, each coat shall be applied only after sufficient curing time has elapsed after the previous coat, as recommended by manufacturer. 6.1.8 All painted surfaces shall have a uniform and smooth regular finish. The surfaces shall be free from foreign particles, brush marks, bristles, ridges, waves, laps wrinkles etc. If such surface defects occur, the same shall be removed by using abrasive paper/cloth and re-painted. 6.1.9 Surfaces inaccessible after assembly shall be painted to requirement before assembly. 6.1.10 Any imperfect or damaged layer/coat shall be repaired before subsequent coating. 6.1.11 At places where welding is to be carried out at field after assembly, a space of 100 to 200 mm width shall be left unpainted on both sides of the welding joint. 6.1.12 Field welded areas shall be thoroughly cleaned as required in clause 3.0.0 and painted in the same manner as the remaining area. 6.2.0 Shop Painting/Priming. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 6.2.1 PAINTING Shop painting/priming shall be carried out as specified in the respective data sheets/line schedule etc. and shall meet all the requirements of this specification. 6.3.0 Painting at Field /Site. 6.3.1 Field/site painting shall be carried out as specified in the data sheets/painting schedule and shall meet all the requirements of this specification for painting. 6.3.2 Where equipments/piping/structures have already received shop painting/priming, the painted/primed surfaces shall be thoroughly cleaned and inspected for any damage or defects. Such damages or defects shall be repaired before starting the filed/site painting. 7.0.0. SAFETY 7.1.0. Sufficient safety precautions shall be taken to ensure protection of Personnel, equipments, piping structures and buildings in the vicinity, where painting materials are stored and painting and blasting operations are carried out. 7.2.0. Open flames and exposed elements or sources of ignition of any kind shall be prohibited in the area where painting materials are stored and painting operations are carried out. 7.3.0. ‘Warning’ or ‘Caution’ boards indicating chances of fire shall be displaced around the paint storage and painting areas. 7.4.0 Electrical fittings and appliances shall be spark proof and shall not cause a fire in the painting storage and painting areas. 7.5.0 Cleaning agents with flash point less than 400C shall be used. 02ES023/2010 PAGE 5 OF 13 7.6.0 Adequate ventilation shall be ensured during painting and storage of paints. 7.7.0 Painting workmen shall wear face masks, gloves and protective clothing during painting and mixing operations. In addition, workmen engaged in blasting operations shall be earmuffs also. 7.8.0 Area where painting is carried out, as well as materials are stored shall be clean, After work, the areas shall be cleared of all scaffoldings, balance materials etc. in order to prevent fire hazards and hinder fire fighting operations. 7.9.0 Painting materials shall be stored and painting and blasting operations shall be carried out only in areas where fire fighting equipments/vehicles and personnel evacuation vehicles can have easy access. In areas where such easy access is not available suitable precautions are to be ensured. 8.0.0 INSPECTION 8.1.0. All painting materials and related items shall be inspected to check the suitability of the same for the specified purposes. 8.2.0. Painting surfaces are to be inspected after cleaning operation, to ensure that the surfaces are fit for painting. 8.3.0. Finished surfaces shall be checked for uniformity in colour, finish and appearance as well as for defects. 8.4.0. Thickness of each coat of paint shall be checked after curing time. The total thickness of multiple coats shall be as specified in the data sheets/piping line schedules/painting schedules. 8.5.0. Paint thickness gauge shall be either mechanical or electronic. The gauges FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES023/2010 PAINTING shall be calibrated regularly. Defective gauges shall not be used. 8.6.0. Absence of paint thickness gauge shall not be made for each eqpt/line/structure separately. PAGE 6 OF 13 D.02 10.5.0. Polyurethane Coating. (For low temp. application) E.01 8.7.0. A detailed quality / inspection report shall be made for each eqpt / line / structure separately 9.0.0. GUARANTEE Guarantee shall cover materials and workmanship. 10.0.0. CODIFICATION OF PAINTING MATERIALS 10.1.0. Primers A.01 A.02 A.03 A.04 A.05 A.06 Synthetic Zinc Phosphate Primer Epoxy based Zinc Phosphate Primer Epoxy based Zinc Rich Primer Alkyd High Build Zinc Phosphate Primer Inorganic Zinc Silicate Primer Chlorinated Rubber based High Build Zinc Phosphate Primer 10.2.0. Finish Paints B.01 B.02 B.03 B.04 B.05 Epoxy Resin based Enamel Epoxy Resin based Micaceous Iron Oxide Paint Epoxy Resin based High Build Paint Coal Tar Epoxy Resin based Paint Chlorinated Rubber Paint Single Pack High Temperature Silicon Aluminium Paint (upto 600oC) E.02 Two-Pack Polyurethane Holding Primer High Build Polyurethane Coating 10.6.0. General Purpose Paints F.01 F.02 F.03 Synthetic Resin based Enamel Chemical Resistant Enamel Alkyd, Antiskid Abrasion Resistant Synthetic Floor Paint 10.7.0. Special Applications G.01 G.02 G.03 Bituminous Mastic Coating Asphalt doping as per IS 10987 App-B Thermocolour Paint 10.8.0 As an alternative, in place of one coat of E.01 – Two pack Polyurethane Holding Primer, one coat of Epoxy Zinc Phosphate Primer A02 (20 microns) followed by one coat of High Build Epoxy containing Micaceous Iron oxide-Bo2 (20 microns) shall be applied before applying finish paint E02-High build Polyurethane coating. 11.0.0 SCHEME OF PAINTING 11.1.0. Scheme of painting of equipment, piping, structures and other items shall conform to class 1, class II or class III as specified in the equipment data sheet/ piping line schedule/ painting schedule/ structural drawings. 11.2.0 Representation of painting 10.3.0. Bituminous Coating C.01 Nontoxic Inert Coating for drinking water tanks C.02 Acid Alkali and Heat Resisting Coating 10.4.0. Heat Resistant Paints D.01 Dual Pack Aluminium Paint (upto 250oC) Requirement of painting of an item shall be indicated in respective drawings/ data sheets/ line schedule/ painting schedule as follows. Indicate primer or finish or both as required followed by subclass indicated in Table 1, Table 2 or table 3 as the case may be. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION PAINTING Eg Primer Finish Primer & Finish Primer Primer & finish Primer Finish Primer & Finish Class I (1)L Class I (1)L Class I (2)M Class II (2)O Class II (3)O/P Class III (1) Class III (1) Class III (3) 02ES023/2010 PAGE 7 OF 13 12.0.0 COLOUR CODING AND MARKING FOR PIPING 12.1.0 In addition to the requirements of painting as per 11.0 the finish painting of the piping shall have the specified colors as per Table 4 – Color coding for pipes, for purposes of identification of service. 12.2.0 All pipes and pipe lines covered under 1.7 shall be provided with “Markings” such as color bands, hazard markings, line identification markings, flow arrow markings etc. at specified locations/intervals and dimensions as indicated in Table 5 – Marking of pipes. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES023/2010 PAINTING PAGE 8 OF 13 TABLE 1 – CLASS I – Pressure Vessels, Heat Exchangers, Reactors, Towers, Tanks and Piping Sl. No. SERVICE CONDITIONS OPERAT PAINT ING SUBTEMP. CLASS 1 UN INSULATED NON CORROSSIVE ATMOSPHERE UN INSULATED CORROSSIVE ATMOSPHERE INSULATED CORROSSIVE ATMOSPHERE =/< 15 =/< 65 =/< 125 =/< 400 =/< 15 =/< 65 =/< 125 =/< 400 =/< 15 =/< 65 =/< 125 =/< 400 INSULATED =/< 15 CORROSSIVE =/< 65 ATMOSPHERE =/< 125 =/< 400 SUPPORTS =/< 15 FOR ALL =/< 65 EQPTS.(INSUL =/< 125 ATED/UN =/< 400 INSULATED) EQPT. AND =/< 15 STRUCTRURE =/< 65 S SUBJECTED =/< 125 TO SALINE =/< 400 ATMOSPHERE UN INSULATED 2 3 4 5 6 PRIMER (1) L (1) N (1) M (1) H Type No.of coats E.01 1 A.01 2 D.01 2 D.02 2 (2) L (2) N (2) M (2) H (3) L (3) N (3) M (3) H (4) L (4) N (4) M (4) H (5) L (5) N (5) M (5) H E.1 A.06 A.02 D.02 E.01 A.04 D.01 D.02 E.01 A.06 D.01 D.02 E.01 A.01 D.01 D.02 (6) L (6) N (6) M (6) H E.01 A.06 A.02 D.02 *DFT FINISH 30 20 20 20 Type No.of coats E.02 2 F.01 2 D.01 2 D.02 2 30 20 20 20 1 2 2 2 1 2 2 2 1 1 1 1 1 2 2 2 30 20 20 20 30 25 20 20 30 30 30 30 30 20 20 20 E.02 B.05 B.02 D.02 E.02 F.01 D.01 D.02 2 2 2 2 2 2 2 2 20 20 20 20 30 20 20 20 1 2 2 2 30 20 20 20 E.02 B.05 B.01 D.02 2 2 2 2 30 30 30 20 * DFT – Dry film Thickness per coat microns Notation: L – Low Temperature N – Normal Temperature M – Moderate Temperature H – High Temperature : FACT ENGINEERING AND DESIGN ORGANISATION *DFT ENGINEERING SPECIFICATION 02ES023/2010 PAINTING PAGE 9 OF 13 TABLE 2 – CLASS II – OTHER EQUIPMENTS PRIMER PAINT SUB CLASS Sl. No. TYPE OF ITEM 1 2 3 4 5 6 7 8 9 10 11 Chimneys,Stacks, Furnaces,heaters (fired and unfired)operating Temp upto450oC D.M.Water Storage Tanks Fresh Water/fire Water Storage Tanks Drinking Water Storage Tanks Acid/alkali Storage Tanks Storage Tanks/Vessels for Petroleum Products Floating Roof Tanks:Inside of shell, top of bottom plate,topside and underside of deck, inside of pontoon Underside of Bottom Plate of Tanks Underground Tanks (buried) Below Ground (submersible) Tanks Secondary Reformer&Simila r Eqpt.(Thermo colour paint) *DFT : ** : Notation: FINISH Type No.of coats *DFT Type No.of coats *DFT Outside (1) A.05 2 25 D.02 2 20 Outside Inside Outside (2)O (2)P (3)O A.01 A.03 A.01 2 2 2 20 35 20 F.01 B.03 F.01 2 2 2 25 35 25 Inside Outside Outside (3)P (4)O (4)P A.03 A.01 A.01 2 2 2 35 20 20 B.04 F.01 C.01 2 2 3 75 25 20 Outside (5) A.04 2 30 C.02 3 25 Outside (6)O A.04 2 50 D.01 2 25 Inside (6)P A.02 2 30 B.03 2 75 Outside (7)O A.04 2 50 D.01 2 25 (7)P A.02 2 30 B.03 2 75 (7)Q A.01 2 25 (8) A.01 1 20 G.01 1 80 Outside (9) A.01 1 20 G.02 Outside (10) A.06 2 35 B.05 3 35 (11) G.03 2 ** G.03 1 ** Dry Film Thickness per coat microns As per Manufacturer’s recommendations O- Outside P-Product Side Q-Specified Side FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES023/2010 PAINTING PAGE 10 OF 13 TABLE 3 – CLASS III – MISCELLANEOUS Sl. TYPE OF ITEM No. 1 Steel structures, Platform Supports PAINTING SUB Type CLASS PRIMER No. of *DFT coats FINISH Type No.of coats *DFT (1) A.04 2 20 B.01 2 25 2 Chequered Plate,Floorplanks&Gang ways (2) A.04 2 20 F.03 2 25 3 Handrails Posts,Railings,Ladders and Stairways (3) A.04 2 20 B.01 2 25 * DFT – Dry Film Thickness per coat microns FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES023/2010 PAINTING PAGE 11 OF 13 TABLE 4 – COLOUR CODING FOR PIPES Sl. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 Identification Ground / Finish Colour Instrument Air0 Sky Blue Service Air Sky Blue Plant Air Sky Blue Cooling Water Sea Green Service Water Sea Green Demineralised Water Sea Green Boiler Feed Water Sea Green Steam Condensate Sea Green Boiler Blow Down Sea Green Turbine condensate Sea Green Process Condensate Sea Green Low Pressure Steam Silver Grey Medium Pressure Steam Silver Grey High Pressure Steam Silver Grey Very High Pressure Silver Grey Steam Naphta Liquid Light Brown Naphta Vapour Light Brown Fuel Oil Light Brown Antifoam Solution Black Phosphate Black Hydrazinc Black Waste Water Black Oily Water Black Ammonia Liquid Dark Violet Ammonia Water Dark Violet Ammonia gas Dark Violet MDEA Solution Dark Violet Process Vent Canary Yellow Carbondioxide Canary Yellow Hydrogen Canary Yellow Nitrogen Canary Yellow LPG Canary Yellow Fuel gas Canary Yellow Process Gas Canary Yellow Synthesis Gas Canary Yellow Effluent Black Drinking Water Sea Green Service Colour Band - 1 Colour Band - 2 White Light Brown French Blue French Blue French Blue Light Orange Light Brown White White Black Light Orange Light Brown Signal Red Signal Red Signal Red French Blue Signal red French Blue French Blue French Blue White Sea Green Signal Red Signal Red Sea Green White French Blue French Blue French Blue Black Light Grey Light Grey Signal Red Black French Blue Light Brown Sea green White Sea Green Light Orange White Sea Green Signal Red Sea Green Canary Yellow White Signal Red Signal Red - FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES023/2010 PAINTING PAGE 12 OF 13 TABLE 5 – MARKING FOR PIPES 1.0. GROUND COLOUR UNIT OF MEASUREMENT Insulated Line – all (excludes buried line) 1.1. Un-insulated Lines–Stainless : Ground colour for a length Per Marking as per para 6.0 Steel,GI ,Alloy steels & of 2 meters below including pipe supports Other non-ferrous pipelines (excludes buried line) ___________________________________________________________________________ 1.2. Un-insulated carbon steel : Ground colour applied Run length in Meters along Lines (excluded buried throughout entire length centreline including Markings Lines) as per Para 6.0 below & pipe supports ___________________________________________________________________________ 2.0. COLOUR BANDS MARKINGS 2.1 Colour band(s)and its width,Band 2 downstream of Band 1(ie.after band 1 along the direction of flow) Pipe size NB (D-pipe size in inches) 80 NB and below Above 80 NB(3”) up to 100 NB(4””) Above 100 NB(4”) up to 300 NB(12”) Above 300 NB(12”) 3.0 4.0 5.0 Band 1 mm 75 D x 25 D X 20 D x 15 B and 2 mm ¼ of Band 1 (Rounded to the nearest mm) Diagonal strips of Black and golden Yellow as per IS2379 superimposed on the ground color. If color bands exists, the hazard marking shall be painted downstream of the bands (ie. after bands in the direction of flow) Color shall be Black or White to contrast with the color on which LINE IDENTIFICATION they are painted. It shall consist of Line No., Line size, Fluid code & Pipeline Spec. No. The lettering dimensions shall be as per MARKINGS IS2379. Color shall be Black or White to contrast with the color on which FLOW ARROW they are painted. The dimension of the arrow shall be as follows and MARKINGS is based on the size of the pipeline. HAZARD MARKINGS d a c b a b c d 150NB & below 65 30 95 20 FACT ENGINEERING AND DESIGN ORGANISATION 200NB & above 90 50 125 30 ENGINEERING SPECIFICATION 6.0 02ES023/2010 PAINTING PAGE 13 OF 13 LOCATION OF MARKINGS Marking includes 2M long ground color, color band(s), hazardous marking, Line No. & flow direction arrow which shall be located at the following points with proper visibility as per IS2379. a. Battery Limit Points b. Either side of walls & dyke walls c. For long yard piping – at 30M interval d. Inter-section on pipe bridge e. Any other location indicated by the Engineer-in-charge at site 7.0 PIPE SUPPORTS 7.1 This includes base springs, hanger springs, shoes and trunnions etc. and excludes pipe bridge structures, platform, equipment support structures and such structures which do not actually support the pipeline. The painting of pipe supports forms part of the pipelines and a separate rate will not operate. 7.2 7.3 The painting specification for pipe supports shall be same as that for pipe ground colour. **************** FACT ENGINEERING AND DESIGN ORGANISATION 02ES030/2010 ENGINEERING SPECIFICATION RUBBER LINING PAGE 1 OF CONTENTS PRPD.BY:- JC 1.0.0 SCOPE 2.0.0 GENERAL 3.0.0 DESIGN OF LINING 4.0.0 MATERIAL 5.0.0 SURFACE PREPARATION 6.0.0 APPLICATION 7.0.0 TESTING 8.0.0 INSPECTION 9.0.0 REPAIR 10.0.0 STORAGE 11.0.0 TRANSPORTATION 12.0.0 GUARANTEE CHKD.BY:- CK APPRD. BY:-JK FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON:- April 2010 9 ENGINEERING SPECIFICATION 02ES030/2010 RUBBER LINING PAGE 2 OF 9 1.0.0 SCOPE 2.2.0 SPECIAL REQUIREMENTS 1.1.0 This specification covers the requirements for design, supply of materials, surface preparation, application of rubber lining, curing, inspection, testing and repairs of lining with rubber for vessels, tanks etc. made out of carbon steel material. 2.2.1 Special requirements pertaining to specific application shall be adhered to strictly. 2.2.2 It shall be the responsibility of the vendor to ensure that all aspects of design, fabrication, inspection and testing conform to the requirements of the specified codes, standards and legal requirements. 2.2.3 Conflicts, if any between the eqpt. Datasheet / drawing / this specification / codes and other enquiry / purchase order specifications shall be referred to FEDO for clarification, prior to the work. Changes in price and delivery due to such clarification shall be resolved and settled immediately. In any case the vendor is bound to accept the stringent of the conflicting clauses without any price / delivery change. 2.3.0 STATUTORY APPROVAL 2.3.1 Vendor shall obtain approval from the statutory bodies for equipment falling under such categories. 2.4.0 FEDO DRAWINGS AND SPECIFICATIONS 2.4.1 FEDO will furnish the vendor the drawing which are prepared based on FEDO’s basic design work containing information such as the shape, basic dimension, design conditions and material of construction etc. required by the vendor to do the estimate of the work and to make detailed application drawings. Subsequent revision, if any, in FEDO drawings which will be communicated to the vendor shall also be considered. 1.2.0 Rubber lining shall be provided to the equipment on all portion indicated in the respective data sheet / drg. of the equipment. 1.3.0 The items shall be rubber lined at site or at the vendor’s shop as per the order. 1.4.0 FEDO means FACT ENGINEERING AND DESIGN ORGANISATION, their authorised representative or their client. 2.0.0 GENERAL 2.1.0 CODES AND STANDARDS 2.1.1 The applicable codes, standards and legal regulations shall be as indicated in FEDO drawings, data sheets and specifications. Such codes and standards shall be of latest editions, unless otherwise specified. 2.1.2 The vessel to be rubber lined shall in general confirm to the requirements of Part-I of Indian standards 4682-1968 “Code of practice for lining of vessels and equipments for chemical processes Part1-Rubber lining”. 2.1.3 Vessels and Tanks to be rubber lined shall be fabricated in such a manner that it complies with the requirements of IS4682-Part-I. 2.1.4 The lining shall be as per this specification and confirm to the requirements of IS 4682 Part-I. FACT ENGINEERING AND DESIGN ORGANISATION 02ES030/2010 ENGINEERING SPECIFICATION RUBBER LINING 2.5.0 VENDOR DRAWINGS / DOCUMENTS 2.5.1 The drawing furnished to the vendor generally will not be a detailed application drawing. Hence it is the responsibility of the vendor to furnish detailed application drawings. Refer Vendor Data submission procedure (VDSP), and Vendor Data Requirement (VDR) for FEDO requirement. 3.0.0 DESIGN OF LINING 3.1.0 The selection lining and its method application shall be based on the following information’s supplied by FEDO. 1. Full analysis of operating medium including constituents present in traces. 2. Maximum, operating conditions variation. minimum and normal temp: and pressure including cycle of 3. Cycle of operation, whether batch or continuous process. 4. Details of the amount, particle size and physical characteristics of the suspended matter together with rates of flow. 5. MATERIAL 4.1.0 The quality of the rubber shall be such that it should withstand the chemical and physical conditions specified during its service life. It shall withstand deterioration by prolonged contact with the contents of the vessel. 4.2.0 Thickness and hardness of the lining specified by FEDO is the minimum requirements and for general guidelines only. The vendor is at 9 liberty to change the thickness and also the hardness to suit the service condition specified. Such changes shall be explained in the offer with the reasons for the changes. 4.3.0 Lining shall be designed taking into account the proposed vulcanising method (autoclave vulcanisation / site vulcanisation / and with pressure steam or open steam). 4.4.0 The rubber sheet should be free from blisters and other imperfections which would affect the performance pf the lining. The thickness tolerance of the lining shall not exceed plus or minus 10%. 4.5.0 The lining shall be done with nature rubber which shall be vulcanised thereafter or with pre-vulcanised rubber of suitable grade and hardness of the service mentioned in the enquiry / order. 4.6.0 Only virgin rubber shall be used for the lining and the vendor shall provide an identification number for the approved mix and supply samples of vulcanised sheets for test and reference in case of any dispute which may arise in future. 4.7.0 Alternate materials such as synthetic rubber equal or superior in quality may be offered as an alternative when called for in the enquiry and the properties and suitability of such materials shall be established by the vendor. Such materials shall be used only with the approval of FEDO. 4.8.0 Care should be taken in the manufacture of the sheets to ensure minimum of stress in the material which could cause shrinkage during vulcanisation. 4.9.0 Care should be taken to see that the rubber sheets used on the job are not semi-vulcanised due to exposure to outside temperatures / long storage. Probable anticipated mechanical damage, if any during construction or operation. 4.0.0 PAGE 3 OF FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES030/2010 RUBBER LINING 4.10.0 VULCANISATION 4.10.1 Generally vulcanisation of the lining shall be done by steam curing. This shall be achieved by keeping the lined equipment in autoclaves for the desired duration and temperature. 4.10.2 The equipment itself shall be used as the autoclave by admitting steam directly into the vessel, provided that all parts of the equipment is designed to withstand the applied steam pressure. Vendor shall submit calculation to establish this aspect along with such offer. However this method shall be adopted only with prior approval form FEDO. 4.10.3 When the above two alternatives are impractical and the equipment is larger than 2m diameter prevulcanised (pre-cured) rubber sheets shall be used for lining job. However this aspect shall be mutually agreed upon before placement of order / application. 5.0.0 SURFACE PREPARATION 5.1.0 All surface to be rubber lined shall be thoroughly cleaned using a solvent or with live steam. 5.2.0 The cleaned surface is then sandblasted to SA 2 ½ to remove rust and scale. The sand / grit used for the job shall be 30-40 mesh size 5 to 60 Kgs/cm2 g air pressure shall be used for blasting to prepare the surface fit for lining. The sand used for the job shall have sharp edges and shall be preferably mountain sand. Sand used once shall not be reused. After each days sandblasting is over the surface blasted is cleaned and first coat primer applied immediately to prevent rust formation. 5.3.0 Sharp changes in contours in the surface to be covered shall be avoided wherever possible. Edges formed by the junctions of plates etc in different planes and external angles including misalignment should be welded and finished by grinding to a suitable radius. Internal angles should be fillet welded and ground concave so as to provide adequate radius. The radius should be as great as possible. The minimum radius shall be equal to the thickness of lining vendor shall ensure that all the surface / contour / welds etc are prepared to his satisfaction before taking over the equipment for lining work. 5.4.0 All surfaces which are to be covered with rubber shall be free from pit holes and other physical imperfections. Pittings, corrosion, cavities, depressions, laminations etc shall be filled by welding and ground to a smooth curvature. 4.10.5 Alternate vulcanisation methods shall be employed when called for by the design and overall dimensions of the equipment and depending on the facilities available at site, without risking the performance of the lining to the required service with mutual agreement of vendor and FEDO. 4.10.7 During vulcanisation abrupt increase and decrease of pressure and temperature shall strictly avoided. 4.10.8 The temperature difference between the inside and outside of the shall be limited to less than 10BC during 9 vulcanisation by providing suitable insulation. 4.10.4 In any case during lining by compartments or in parts is not acceptable as the resultant vulcanisation will not be uniform. 4.10.6 If the edges of flanges are blanked off, a satisfactory method shall be resorted to, to avoid under vulcanisation of the flanges faces. PAGE 4 OF FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 5.5.0 02ES030/2010 RUBBER LINING All weld spatters should be removed from surface to be rubber lined. 5.6.0 Any projections that are objectionable to soundness of lining shall be removed by grinding. 5.7.0 An initial sandblasting may be resorted to, if necessary to assess the repairs to be done for the vessel to make it fit for rubber lining. 5.8.0 Only after complete repairs have been carried out and vessel made fit for rubber lining, final sandblasting as mentioned above shall be done and first coat primer applied. 6.0.0 APPLICATION 6.1.0 GENERAL 6.1.1 All the surface of the vessel shall be lined as shown in the data sheets / drawings with rubber sheets of specified thickness secure by bonded to the metal surface. 6.1.2 Before applying the second coat of rubber solution the surface on which the first prime coat has been given after sand blasting shall be cleaned with cloth moistured in petrol or other suitable cleaning agent to remove the possible dust accumulation due to blasting. The surface shall be thoroughly checked for any rust formation also. After cleaning petrol / suitable cleaning agent sufficient time lag shall be given for the vapour to evaporate and to get a dry surface. Subsequent coats of rubber solution shall be applied after the solvent has evaporated from the previous layer. The rubber coatings shall be applied in a thin uniform continuous layer using brush. Care shall be taken not to for air bubbles while applying the coating. Drips or clots if any shall be carefully rubbed into the metal with a brush. The coating film shall be protected against contamination by dust, fibres and hairs from the brush. PAGE 5 OF 9 6.1.3 The calendered rubber sheets shall be made to fit the surface to be lined. The edges of the rubber sheets shall be chamfered with the maximum inclination of the knife to get a proper overlapping joint. That side of the sheet which will be in contact with the adhesive shall be wiped with the rubber solvent to clean its surface and increase its tack. As soon as the solvent evaporates and the surface still retains its tack the sheet shall be applied to the metal. 6.1.4 Any pre-shrinking of the rubber sheet shall be done at shop / site before hand tailoring the sheet to fit the surface to be lined. 6.1.5 The air trapped between the rubber sheets and the metal surface shall then be thoroughly and carefully forced out by using suit able rollers. 6.1.6 Extreme care shall be taken during rolling to avoid air entrapping. In unvulcanised sheets if air bubbles are noticed, the same shall be punctured at a suitable inclination, with a needle / knife dipped in rubber solution and the air pressed out through the hole formed and the puncture / cut rolled with the roller. 6.2.0 JOINING OF SHEETS 6.2.1 Unvulcanised sheets shall be joined by using overlap bevel joints and vulcanised sheets by strapped joints as detailed in IS4682-Part I. 6.2.2 The staggering of the joints of the first and second layer rubber lining shall not be less than 100mm. 6.2.3 Overlap joints shall be made in such a way that the overlap flow the direction of liquid flow. 6.2.4 Joints at corners and at the edge of rings shall be strictly avoided. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES030/2010 RUBBER LINING 6.3.0 SAFETY AND PRECAUTIONARY ASPECTS 6.3.1 All safety precautions as per the Factories Act shall be strictly followed while working inside the vessels. 6.3.2 6.3.3 6.3.4 a. All naked light shall be avoided 24 volts safety lamps shall be used. While applying solution, frequent check shall be conducted with a gas tester to ensure that no inflammable or explosive gasses exist within the limit. The following precautions shall be adhered to while testing for continuity of lining with a spark tester. Remove moisture from inside the tank or other object being tested and from the surface of the rubber so as to prevent electric shock. b. Remove oil, dust, wood, metal etc from the rubber lining surface. c. For vessels, tanks, ducts, pipe lines in open areas sparks test shall not be conducted while it is raining. d. Inflammable objects shall be kept away from the test area. e. Confirmation shall be obtained from the Owner that no flammable or explosive gasses or other materials exist in the test area. 6.3.5 Smoke inside or near the rubber lining area or near the area where the compound adhesive etc and stored shall be strictly forbidden. 6.3.6 Workers of inside the vessel shall be instructed to wear only rubber shoes. There shall not be any nail or other sharp objects in the shoes which can damage the rubber lining. 6.3.7 Metal scaffolding shall be avoided inside the vessel. PAGE 6 OF 9 6.3.8 Bamboo or wooden scaffolding / platforms used shall be sufficiently strong and shall not have sharp edges which may damage the rubber lining. 6.3.9 Ladder used for the job shall have the bottom covered with rubber shoe to prevent any possible damage to the lining. 6.3.10 Any site cutting of the rubber sheets required shall not be allowed inside the vessel. 6.3.11 Knives or sharp objects shall not be allowed inside the vessel except for any repairs of the rubber lining being done. 6.3.12 Care shall be taken to ensure that semi-vulcanised rubber sheets are not used on the job. 6.4.0 SPECIAL REQUIREMENTS FOR LINING OF VACCUM VESSELS 6.4.1 The vendor shall decide the lining material and application procedure only after complete study of the working conditions. 6.4.2 Triplex rubber lining with soft-hardsoft layer is preferred for vacuum service rubber lining. 6.4.3 For vessels which operate under vacuum, pre-vulcanised rubber sheets shall not be used since it has less bond strength. 6.4.4 Since peeling of rubber from metal surface can be due to improper metal surface, surface preparation is one of the most important factors in lining of vacuum vessels. 6.4.5 Wherever possible the rubber lining of vessels under vacuum should be done in the vendor’s shop so that special attention can be given during application, vulcanised in an autoclave. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 6.4.6 02ES030/2010 RUBBER LINING Wherever the rubber lining of vessel under vacuum are done at site the vessel shall be vulcanised by pressure vulcanisation method by using the equipment as an autoclave by sealing openings with blind flanges and taking all design / application precaution. Adequacy of strength of the equipment against the steam pressure and temperature shall be ensured before proceeding this method. 6.4.7 The equipment shall be provided with outside insulation to limit the temperature difference between inside and outside within 10BC. 6.4.8 Each rubber sheet shall be spark tested to detect defects / pinholes before application. Spark testing should be done before and after vulcanisation. 6.4.9 Peel test shall be conducted for each batch of material and only after ensuring that the bond strength is as per IS 4682 Part I the lining job shall be carried out. 6.4.10 Wherever the lining thickness is more than 3mm, lining shall be done in different layers with the maximum thickness of the single layer being 2.5 mm. All vertical and horizontal joints should be staggered and should have proper overlaps. 6.4.11 After completion of the lining, before vulcanisation the lining shall be subjected to positive air pressure (as limited by the design of the equipment), which ensures even bondage between metal surface and rubber. 6.4.12 After completion of the rubber lining, the vessel shall be kept for a period of minimum 2 days for natural drying before being vulcanised. PAGE 7 OF 9 6.4.13 Sample rubber pieces shall be put inside the vessel during vulcanisation and checks shall be made on the sample piece at the end of vulcanisation to ensure that uniform proposed hardness has been obtained. 6.4.14 Care shall be taken to see that the pressure and temperature inside the vessel is raised / lowered slowly at a uniform rate and any abrupt increase / decrease shall be strictly avoided. 6.4.15 Steam traps and drain holes shall be provided at the lowest point of the vessel to drain the condensed water to prevent under vulcanisation of the rubber in those areas. 6.4.16 A hammer test shall be conducted with a wooden mallet to detect any separation of rubber from metal surface. 6.4.17 During testing, if the rubber lined surface shows defects in more than 10% area, the vessel shall be completely relined and retested at free of cost. 7.0.0 TESTING 7.1.0 Inspection and testing of rubber lining shall be carried out at all stages. 7.2.0 The physical properties / composition of the rubber lining shall be tested when specified by FEDO as per the requirements of IS 3400. 7.3.0 Peel test shall be conducted on samples of each batch of compound and adhesive and the values obtained shall be as per IS 4682-Part I. 7.4.0 The vendor shall give test results conducted on samples of hard rubber for bond strength as per ASTM-429 and the values shall be as per IS standards. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 7.5.0 7.6.0 02ES030/2010 RUBBER LINING Continuity of the lining shall be ensured by visual inspection and high frequency spark test as per IS 4682-Part I. Spark test shall be conducted before and after vulcanisation. The voltage used shall be as per IS 4682- Part I. Hammer test with wooden hammer shall be conducted before and after vulcanisation to detect any possible air gaps / separation of sheets from metal surface. 7.7.0 Hardness test shall be conducted on completion of vulcanisation as specified in IS 4682-Part I. 7.8.0 The thickness of the lining shall be checked by direct measurement or by using a thickness metre as the case may be. 7.9.0 A hydraulic test, wherever required at an agreed pressure and for an agreed duration of times shall be conducted in a manner specified by FEDO and there shall be no leakage past the lining. 7.10.0 A vacuum test shall be carried out maintaining the specified vacuum for a period of 8 hour and by an agreed method wherever specified by FEDO. 7.11.0 Wherever contamination of the contents of the equipment by the lining material in detrimental, check shall be conducted on samples of the compound. 8.0.0 INSPECTION 8.1.0 FEDO or its representative shall have free access to the works of the vendor during execution of the job. The vendor shall furnish all facilities to the buyer or his representative to satisfy himself that the materials used and the quality of workmanship are in conformity with this specification. PAGE 8 OF 9 8.2.0 The vendor shall also notify FEDO the test schedule sufficiently in advance as to enable them to witness the tests. 8.3.0 All expenses in connection with taking specimens and samples and subsequent testing shall be borne by the vendor. 9.0.0 REPAIRS 9.1.0 Any minor defects noticed on testing and inspection shall be rectified by the vendor in a manner mutually agreed by the vendor and FEDO. The repair shall be done as per good engineering practice and to the entire satisfaction of FEDO site engineer. 9.2.0 After the repair, the vendor shall conduct further test and satisfy FEDO regarding the suitability of the lining. 9.3.0 After conducting tests, if the lining again shows major defects, the vendor shall replace the complete lining to the satisfaction of FEDO representative. 9.4.0 In case of any dispute regarding the degree of the defect as to major defect or minor defect and the areas to be replaced, the decision of FEDO shall be final. 10.0.0 STORAGE 10.1.0 STORAGE OF LINING MATERIALS 10.1.1 The rubber sheets and adhesives shall be transported from the works of the vendor and stored at site at the required temperatures. 10.1.2 The air conditioned / cold storage facilities provision required at site and during transportation shall be mutually discussed and arranged between the vendor and owner prior to placement of order. However it shall be the responsibility of the vendor to arrange all facilities for the FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES030/2010 RUBBER LINING safe transport and storage of the sheet and adhesives at his own cost. 10.1.3 The vendor shall ensure that the work area is properly protected against unfavourable weather conditions such as rain, wind dust etc. 10.2.0 STORAGE OF LINED VESSELS 10.2.1 The lined vessels shall be kept preferably in cool and dark place. In case of large equipment the outside of the vessel shall be covered to protect from direct sunlight. 10.2.2 The rubber lined vessels may be filled with water until it is commissioned. 10.2.3 The rubber lined equipment shall be kept away from fire. 11.0.0 TRANSPORTATION OF RUBBER LINED EQUIPMENT 11.1.0 Rubber lined equipment shall be properly crated to prevent possible impact and mechanical damage during transportation. 11.2.0 Extreme care shall be taken while loading and unloading of rubber lined equipment to prevent damage. PAGE 9 OF 9 12.0.0 GUARANTEE 12.1.0 Vendor must guarantee that all materials used for the lining have been submitted to regular acceptance procedureand free from any defect regarding composition, strength, quality, form and appearance. 12.2.0 Rubber lining must be guaranteed for design, materials and workmanship for a period as specified in the commercial conditions of the purchase order. 12.3.0 Any vessel lining or part not having been submitted to wrong operating service or faulty manipulation and found defective during test after installation or during operation, shall be repaired / replaced by vendor without delay and free of cost within the guarantee period. 12.4.0 During guarantee period, in case of defective equipment, FEDO shall have the option to repair / replace the equipment after intimating to the vendor, in order to avoid time delay. In such an event, FEDO shall be entitled to recover the cost of such repair / replacement from the vendor. ******************** FACT ENGINEERING AND DESIGN ORGANISATION 02ES041/2010 ENGINEERING SPECIFICATION ANCHOR BOLT PAGE 1 OF 2 CONTENTS PRPD.BY:- JC 1.0.0 SCOPE 2.0.0 CODES AND STANDARDS 3.0.0 MATERIAL 4.0.0 IDENTIFICATION MARKS 5.0.0 INSPECTION 6.0.0 PACKING AND FORWARDING 7.0.0 VENDOR DOCUMENTS 8.0.0 GUARANTEE CHKD.BY:- CK APPRD. BY:- JK FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON:- April 2010 02ES041/2010 ENGINEERING SPECIFICATION ANCHOR BOLT 1.0.0 SCOPE 1.1.0 This specification covers the requirement for manufacture, inspection, testing and supply of anchor bolts for static equipment. 1.2.0 The vendor shall quote for all the items in the anchor bolt schedule. The requirement given in the schedule is indicative only. The purchaser reserves the right to delete/increase/decrease the number of bolts in each category. The quoted rates shall be firm even after such change in scope. The final requirement will be intimated during the time of placing the order. 2.0.0 CODES AND STANDARDS 2.1.0 Bolt shall be Metric sizes as per the anchor bolt schedule and threads shall be as per IS 4218. 2.2.0 The threads shall be 2 pitch series for bolts below M24 size and 3 pitch series of sizes M24 and above. 3.0.0 MATERIAL 3.1.0 The material of construction of bolt shall be as specified in the anchor bolt designation. Anchor bolt designation is as explained below. PAGE 2 OF 2 4.0.0 IDENTIFICATION MARKS 4.1.0 Anchor bolts supplied shall be provided with proper identification marks indicating the bolt designation listed in the schedule. The designation shall be clearly stamped with low impression punching on the shank of each anchor bolt. In addition to this all the anchor bolts shall be individually provided with suitable leather tags with the designation printed on it. 5.0.0 INSPECTIION 5 . 1 . 0 Anchor bolts shall be subjected to inspection / acceptance by FEDO / Purchaser. 6.0.0 PACKING AND FORWARDING 6.1.0 All items shall be properly packed so as to enable easy identification of each type of bolts. The packing shall be done as per the FEDO engineering spec. 02ES022/2010. Threading of bolts and nuts shall be coated with suitable lubricant to prevent galling, before despatch. Eg.M24TP3A 7.0.0 VENDOR DOCUMENTS M24 Size TP3 A Type Material code 3.2.0 Refer FEDO standard 02DS002 for details and dimensions of various types of anchor bolts. Material code shall be as specified below. Bolt Nut A SA 193 B7 SA 194 2H Plates IS-2062 B IS-2062 SA 194 2H C SS-304 SS-304 IS-2062 SS-304 Relevant material test certificates, certificate of manufacturing and inspection shall be forwarded along with supply. 8.0.0 GUARANTEE 8.1.0 Material Part 7.1.0 Vendor shall guarantee against defective materials and faulty workmanship for the period and terms as specified in the commercial conditions of the enquiry/order. ********************** FACT ENGINEERING AND DESIGN ORGANISATION iso2.sty ENGINEERING SPECIFICATION CENTRIFUGAL PUMPS FOR GENERAL PURPOSE SERVICES CONTENTS 1.0.0 2.0.0 3.0.0 4.0.0 5.0.0 6.0.0 7.0.0 SCOPE REFERENCES DEFINITIONS DESIGN AND MANUFACTURE SHOP INSPECTIONS AND TESTS ASSEMBLY & PREPARATION FOR SHIPMENT APPENDICES 1.0.0 SCOPE ———————————— This specification covers the engineering requirements for horizontal and vertical centrifugal pumps for general purpose services. Special requirements of the project. Special requirements of the project attached to this specification cover modifications to this specification, customer’s special or local requirement as well as specific job data pertinent to this specification. Where special requirements of the project are in contradiction to this specification, special requirements of the project shall govern. 1.2.0 2.0.0 REFERENCES The requirements contained in the latest editions (unless otherwise indicated) of the following specification, standards and code shall form part of this specification, in the manner and to the extent indicated herein. 1. ANSI B1.1 : Unified Inch Screw Threads (UN and UNR Thread Form) 2. ANSI B2.1 : Pipe Threads (Except Dryseal) 3. ANSI B4.1 : Preferred Limits and Fits for Cylindrical Parts 4. ANSI B16.5 : Steel Pipe Flanges, Flanged Valves and Fittings 5. ANSI B31.3 : Chemical Plant and Petroleum Refinery Piping 6. ASME Boiler and Pressure Vessel Code a. Section III, Division 1 b. Section V, Nondestructive Examination c. Section VIII, Divisions 1 and 2 7. Hydraulic Institute Standards for Centrifugal , Rotary &Reciprocating Pumps. 8. AFBMA (Anti Friction Bearing Manufacturers’ Association ) Standards for Ball and Roller Bearings and Steel Balls. 9. MSS (Manufacturers Standardisation Society of the valve and fittings industry) Standards. 3.0.0 DEFINITIONS The following terms as used in this specification shall have the meanings denoted: PRPD. BY:B.K CHKD. BY:N.R.N 01ES010 / 94 PAGE 1 OF 7 1. Max. Allowable Casing Working Pressure The greatest discharge pressure at the specified pumping temperature for which the pump casing is designed. Designs shall conform to the requirements of this specification. The pressure shall be equal to or greater than max. discharge pressure. 2. Maximum Discharge Pressure The maximum possible suction pressure to be encountered, plus the maximum differential pressure the pump is able to develop when operating at the specified conditions of speed, specific gravity and pumping temperature with the furnished impeller. For vertical pumps, the pressure shall be referenced to bottom of base plate. 3. Rated Discharge Pressure The discharge pressure of the pump at the guarantee point related to rated capacity, speed, suction pressure and liquid specific gravity. For vertical pumps, the pressure shall be referenced to bottom of base plate. 4. Maximum Suction Pressure The highest suction pressure to which the pump is subjected during operations. For vertical pumps, the pressure shall be referenced to bottom of base plate . 5. Rated Suction Pressure The suction pressure for the operating conditions at the guarantee point. For vertical pumps, the pressure shall be referenced to bottom of base plate. 6. Rated Speed The normal operating speed (in rpm) on which the pump performance ratings and guarantees are based. For motor-driven pumps, rated speed shall be the actual speed of motor based on test report or drawings of the motor. 7. Rated Brake Horsepower The horsepower required by the pump at the specified rated operating conditions, including capacity, pressures, specific gravity and viscosity. 8. Pressure Casing All major stationary pressure containing components of the pump unit, including all attached nozzles and other components, but excluding the shaft and shaft sleeves. 9. Net Positive Suction Head Available NPSHA is determined by the purchaser based on the pumping system requirements. NPSHA is the total suction head in metres of liquid absolute - referred to the pump centerline for horizontal pumps and to the top of the foundation for vertical pumps - minus the vapor pressure of the liquid at pumping temp. in meters absolute. 10. Net Positive Suction Head Required NPSHR i s d e t e r mi n e d b y t h e p u m p manufacturer and is expressed as metres APPRD. BY:A.N.J FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON: MAR ’94 ENGINEERING SPECIFICATION CENTRIFUGAL PUMPS FOR GENERAL PURPOSE SERVICES of liquid (water) required at the pump centerline for horizontal pump or at the top of the foundation for vertical pumps for the specified capacity. 11. Submergence The minimum liquid level above the suction port necessary to prevent vortexing or cavitation. 12. Minimum Flow Based on the fluid characteristics, the lower flow rate at which the pump can continuously operate without danger of failure. 4.0.0 DESIGN AND MANUFACTURE 4.1.0 4.1.1 Pump Selection Pump head - capacity curves shall continuously rise from rated capacity to shutoff unless otherwise approved by the purchaser. The rated capacity point shall be at or to the left of the peak efficiency point on the head - capacity curve for the rated impeller diameter unless otherwise approved by the purchaser. The correction factors given in the 13th edition of the Hydraulic Institute standards shall be used for sizing pumps handling liquids more viscous than water. An NPSH correction factor shall not be used. Turbine-driven pumps shall be designed to operate continuously at 105% of rated speed and, under emergency conditions, at 120% of rated speed (turbine overspeed trip setting). All equipment shall be designed for operation outdoors totally unprotected from the elements. All instruments and valves, including auxiliary systems, shall be securely mounted and supported to avoid damage during shipment, storage, operation and maintenance. For pumps with vertical sumps, the pump manufacturer shall state the minimum submergence required and the minimum clearance from the sump bottom. Pump shall be designed so that the maximum allowable sound levels are not exceeded while operating at specified conditions. Pump selection shall be such that it shall be possible to obtain an increase in differential head to the order of 105% for the rated head by changing the impeller with the same casing. Pumps shall be suitable for continuous duty unless otherwise specified. MECHANICAL DESIGN Pump Casing 1. Pressure casings shall be sufficiently thick to withstand the maximum discharge pressure at pumping temperature and hydrostatic test pressure at ambient temperature. All casings shall have a minimum 3.2mm corrosion allowance unless otherwise specified. 2. The design stress, temperature restrictions and other requirements for materials shall conform to the limitations in the ASME code, Section VIII, Division 1 for similar material. 4.1.2 4.1.3 4.1.4 4.1.5 4.1.6 4.1.7 4.1.8 4.1.9 4.2.0 4.2.1 4.2.2 4.2.3 01ES010 / 94 PAGE 2 OF 7 3. Pressure containing components shall be manufactured in accordance with the ASME c od e, Se ct ion VII I, Divis ion 1. Th e manufacturers’ data report forms and stamping specified in the ASME Code are not required. 4. All vertical and horizontal pumps shall be furnished with flanged suction and discharge nozzles that conform to ANSI standards unless otherwise specified. Pump suction and discharge nozzle of 32NB, 65 NB, 125 NB and 225 NB are not preferred. If the pump manufacturer’s standard design offers a flange thickness and diameter greater than necessary for the specified rating, the heavier flange may be furnished, but it shall be faced and drilled as specified. Flange bolt holes shall straddle the centrelines. 5. Each stage of a pump shall be self venting by arrangement of the nozzles or be provided with a vent connection. All horizontal pumps and vertical in-line pumps shall be provided with a drain connection. Vent and casing drain connections shall be 15NB minimum. 6. Pumps shall be provided with suitable means, such as eyebolts, lugs or jackscrews, to facilitate disassembly of gasketed joints. 7. The casing shall be supported by feet beneath the casing or any other suitable support between the casing and the baseplate. Impellers 1. Impellers shall be of one piece fabrication. Major components of rotating elements, such as the impellers and balancing drums, shall be individually statically balanced. In addition to static balancing, impellers shall be dynamically balanced if the pump is to be operated under any of the following conditions: a. At speeds over 1,800 RPM, where the rated capacity exceeds 60 M3 /hr and the impeller diameter exceeds 152 mm (6 in.) b. At speeds over 1,800 RPM for two or more stages. For pumps with impellers mounted between the bearings, the shaft and impellers shall first be individually balanced and then finally balanced as an assembled unit. After balancing, vibration shall be according to the limits specified in Subsection 4.2.4. 2. Impeller shall be fixed to the shaft using keys. Screwed type fixing is not recommended unless specifically accepted by purchaser. Shafts and Shaft Sleeves 1. Replaceable shaft sleeves are required for all pumps. Shaft sleeves shall extend beyond the outer face of the gland and inward past the throat bushing. 2. The pump shaft or shaft sleeve runout measured by a dial indicator at the stuffing box face shall not exceed 0.05 mm total indicator reading. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 4.2.4 Vibration Peak-to-peak vibration limits shall apply to pumps with anti-friction bearings and sleeve bearings. The limits shall cover rotor vibration during shop and field tests at rated speed and throughout the full operating capacity. Peak-to-peak limits in micrometers are as follows: Anti-Friction Bearings * Sleeve Bearings* 1,800 and below 75 75 1,801 to 3,600 50 50 Rated Speed(RPM) 4.2.5 4.2.6 4.2.7 CENTRIFUGAL PUMPS FOR GENERAL PURPOSE SERVICES * Measured on the bearing housings. Critical speeds shall be at least 20% above or below the normal operating speed for pumps with flexible shafts and at least 20% above the maximum operating speed for pumps with stiff shafts. Mechanical Shaft Seals 1. Mechanical seals shall be as specified in pump data sheets. If mechanical seal manufacturer has any alternate recommendation for seals, same shall be submitted for purchaser’s consideration. 2. Seal end plates shall be of the same material or better as the pump casing, except that carbon steel plates shall be furnished for a cast iron, ductile iron or bronze casing. Seal end plates shall be retained by a minimum of four stud bolts. 3. Mechanical seal flush piping shall conform to Appendix 2. Seal flush piping shall be of 18 Cr- 8 Ni stainless steel material. 4. Heat exchangers used for cooling mechanical seal flushing streams shall have 15NB minimum size tubing for the process liquid. The tube material shall be a continuous fabrication. Material for the product side shall be 18Cr-8Ni stainless steel or as specified. 5. Horizontals pumps with impellers mounted between the bearings and vertical turbine type pumps shall be furnished with cartridge type mechanical seals. Stuffing Boxes for Conventional Packing 1. Stuffing boxes shall have adequate number of rings of packing plus the lantern ring. Lantern rings shall have inlet and outlet liquid connection. 2. Stuffing box glands shall be easily removable and must permit replacement of packing without removal or disassembly of any other part of the pump. Glands shall preferably have complete bolt holes. Slotted holes, open at one side are acceptable only if studs are provided for securing the glands. Drivers 1. Drivers and gears for vertical pumps shall be designed for the maximum up and down thrusts that the pump may develop during starting or stopping or while operating at any capacity. 01ES010 / 94 PAGE 3 OF 7 2. Gear losses and transmission losses shall be added to the pump power consumption before driver rating factors are applied. 3. Motors for pumps covered by this specification shall have horsepower ratings at least equal to the following percentage of pump rated brake horsepower. Motor Nameplate Rating, KW 4.2.8 4.2.9 Percent of Rated BHP 18.5 and less 125 Above 18.5 & below 75 115 75 and above 110 4. Motor or steam turbine drivers that are specified on the individual pump specification sheets as operating in parallel or without discharge control valves shall have a nameplate rating not less than the maximum power required by the pump when furnished with the specified diameter impeller. 5. The rated power of steam turbine drivers shall be 110% of the rated pump power, based on the guaranteed pump efficiency. The steam turbine power rating shall be based on the specified minimum initial steam conditions at the turbine inlet and the maximum exhaust pressure. Couplings 1. Horizontal pumps shall have flexible couplings. Vertical pumps shall have rigid adjustable, spacer-type couplings when the pump thrust load must be carried by the bearings of a solid-shaft motor. Vertical pumps designed with integral thrust bearings shall be supplied with suitable all metal, nonlubricated couplings. (A spacer is required if it is possible to service the mechanical seal without completely disassembling the pump). Couplings for in-line pumps need not be adjustable. 2. The pump manufacturer shall mount the pump half-coupling. Gear and driver half couplings shall be furnished and mounted by the pump manufacturer unless otherwise specified. 3. Couplings shall be mounted on shafts with a cylindrical fit and keyed in place. Cylindrical fits shall conform to ANSI B4.1, Class FN-1. 4. Couplings shall be dynamically balanced when the size-speed relationship is such that balancing is recommended by the coupling manufacturer. 5. Removable all-metal coupling guards are required. They shall be sufficiently rigid to avoid contact with the coupling or shaft due to body contact. 6. Type of couplings shall be as specified in pump data sheet. Bearings 1. Radial bearings shall be the standard available design (ball, roller, sleeve or pivoted shoe) unless otherwise specified by the pur- FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION CENTRIFUGAL PUMPS FOR GENERAL PURPOSE SERVICES chaser. Anti-friction bearings shall be the standard type and selected to give three years (25,000 hrs) minimum (AFBMA) rating life with continuous operation at rated pump conditions and not less than 16,000 hrs at maximum axial and radial loads and rated speed. The rating life is the number of hours at constant speed that 90% of a group of identical bearings will complete or exceed before the first evidence of failure. 2. Horizontal pump bearings shall be arranged for oil lubrication. 3. Thrust bearings for vertical pumps shall not be located in the drivers. 4. Non pressure oil-lubricated bearings shall be equipped with 60 cc (minimum) constant level oilers. Constant level oilers shall be provided with protective wire cages. 5. If a complete lube oil system is required, it will be specified by the purchaser. 4.2.10 Piping Piping shall terminate with a flanged connection. Piping shall be in accordance with ANSI B31.3 and flanges and flanged fittings in accordance with ANSI B16.5. Tapped openings and piping threads shall con form to ANSI B2.1 and B16.5. 1. Cooling Water a. The cooling water systems shall be arranged for flow through the jacket, coolers, and glands specified on the individual pump specification sheet by a letter code from Appendix 3. b. The system inlet and outlet shall be at the edge of the baseplate opposite the driver unless otherwise specified. The system shall be arranged for easy disassembly to permit maintenance and cleaning and shall be properly supported to prevent vibration and damage. Complete drainage is required. Closed sight flow indicators and inlet and outlet shut off valves are required for all closed cooling water systems. c. If cooling water is required for a pump and driver, the pump manufacturer shall provide single inlet and outlet connections for the cooling water piping. d. Cooling water jackets or housings shall be designed for a minimum 5.3 Kg/cm2G working pressure unless otherwise specified. e. Piping shall be 15NB minimum for pumps with discharge openings smaller than 80NB and 20NB minimum for pumps with discharge openings 80NB and larger. Pipe wall thicknesses shall be schedule 80 for nominal pipe sizes 15NB through 50NB and schedule 40 for nominal pipe sizes 80NB and larger. f. Copper tubing conforming to ASTM B88, Type K (soft annealed) and brass fittings may be furnished for cooling water, if specified by purchaser. If copper or its alloy are specified as not suitable for the service, then AISI 316 tubing shall be used. g. Cooling water systems shall be furnished by 01ES010 / 94 PAGE 4 OF 7 the pump manufacturer. They shall be fully assembled and installed on the pumps. Piping shall be thoroughly cleaned before connection to a pump. Piping on vertical pumps may be separately boxed for shipment. 2. Seal Flushing a. Seal flushing systems shall be as specified on the individual pump specification sheet by a numeric code from Appendix 2. Systems shall be arranged for easy disassembly to permit maintenance and cleaning and shall be properly supported to prevent vibration and damage. The temperature and pressure rating of the system shall not be less than the pump casing maximum discharge pressure at the maximum pumping temperature. b. If alloy pump casings are specified, all flushing system components shall be of equal specification or better than the casing material. c. 18Cr-8Ni stainless steel tubing shall be used for flushing fluids to mechanical seals. The minimum size of tubing shall be 15NB. The minimum tubing wall thickness for 15NB and 20NB sizes shall be 1.65mm (0.065 inch). Tubing fittings shall be 18Cr8Ni stainless steel. d. Seal flushing systems, including all accessories such as gauges and valves, shall be furnished by the pump manufacturer. They shall be fully assembled and installed on the pumps. Piping shall be thoroughly cleaned before connection to a pump. Piping on vertical pumps, except in-line pumps, may be separately boxed for shipment. 4.2.11 Auxiliary Connections 1. Tapped openings and threads shall conform to ANSI B2.1 and B16.5. Auxiliary piping connections that are supplied but not piped shall be plugged with solid plugs. Carbon steel plugs shall be used for cast iron castings; otherwise, the materials for the plugs and casing shall be identical. 4.2.12 Baseplates and Mounting 1. All horizontal pumps shall be furnished with s t urdy drai n rim or drai n pan-ty pe baseplates with a raised lip. Baseplates material shall be as specified. They shall extend the full length and width of the pump and driver unit and shall be fully machined to receive pump and driver. 2. Basic requirements for baseplates are as follows: a. Connections for drain shall be tapped 25NB in the raised lip at the pump side and shall be located to effect complete drainage. The pan or upper surface of the baseplate shall be sloped at least 10 mm per meter toward the drain. b. A minimum of two 100 mm grout holes shall be provided in each baseplate. They shall be positioned to allow grouting with all the components in place and have vents to promote even grout distribution. Grout FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION CENTRIFUGAL PUMPS FOR GENERAL PURPOSE SERVICES holes shall have raised lips to prevent liquid accumulating on the exposed grout. 3. The centerlines of pump shafts shall be sufficiently high above baseplates for correct installation of all auxiliary piping connections such as pump drains, steam turbine inlet end drain and leakoff connections. 4. All vertical in-line pumps shall have a flatbottomed casing. 4.2.13 Materials 1. Materials shall be as specified on the individual specification sheet. 2. Casings shall be sound, free from shrinkage holes, blowholes, scale, blisters and other defects. Surfaces shall be cleaned by the pump manufacturer’s standard methods. All casting burrs shall be filed or ground flush with the surface of the casting. 3. Leaks and defects in pressure casings must not be repaired by plastic or cement compounds. When casting repairs are authorized by the material specifications, repair welding shall be according to the applicable ASTM specifications. Welding repairs shall be made with a welding rod that will give the same composition as the deposited material and of the same nominal chemical composition. 4. Cast iron materials are limited to a maximum design temperature of 1210C . 4.2.14 Nameplates and Rotation Arrows 1. A corrosion-resistant nameplate shall be permanently attached to each pump. The nameplate shall be stamped with the following information. a.Equipment number b.Manufacturer’s name c.Serial number of pump d.Model number of pump e.Rated capacity f. Pumping head g.Specific gravity of fluid h.Speed in RPM i. Driver rating. 2. Each pump shall be provided with a cast-in or permanently attached arrow indicating the direction of rotation. 5.0.0 SHOP INSPECTIONS AND TESTS 5.1.0 Test procedures and correction factors shall be agreed by purchaser and manufacturer. For this purpose detailed test procedure write up shall be submitted by manufacturer well in advance of test after placement of order. Typical calculations shall form part of the write up. Nondestructive examinations shall be carried out according to the individual pump specification sheet. All results must be certified by the purchaser’s inspector. Other requirements are as follows. 1. The magnetic particle method shall be used 5.1.1 01ES010 / 94 PAGE 5 OF 7 for superficial examination, if the material is ferromagnetic and the surface is accessible. 2. The liquid penetrant method shall be used for superficial examination, if the material is nonmagnetic or inaccessible for a magnetic particle examination. 3. The procedure and acceptance criteria (as per ASME, except as noted) for the various nondestructive examinations are: Method Procedure Acceptance criteria Radiography Sect V, Art 2 Sect VIII, Div 1 Magnetic particle Sect V, Art 7 Liquid Penetrant Sect V, Art 6 Sect VIII, Div 1, App VI Sect VIII, Div 1, App VIII Welds Castings Radiography ASTM E 94 MSS-SP-54 Magnetic Particle Sect V, Art 7 Liquid Penetrant Sect V, Art 6 Sect VIII, Div 1,App VII Sect VIII, Div 1,App VII Forgings 5.2.0 5.2.1 5.2.2 5.2.3 5.2.4 5.3.0 5.3.1 5.3.2 5.3.3 Magnetic Particle Sect V, Art 7 Liquid Penetrant Sect V, Art 6 Ultrasonic ASTM A 368 Sect III, NB-2545 Sect III, NB-2546 Sect VIII, Div 2, AM 203.2 HYDROSTATIC TEST Each pressure casing shall be hydrostatically tested with water at 160C or above. The minimum test pressure shall be 1 1/2 times the maximum allowable casing working pressure. Cooling water jackets shall be hydrostatically tested at a pressure of 1 1/2 times maximum cooling water system design pressure. Auxiliary piping shall be hydrostatically tested with water at 16 0C or above. The minimum test pressure shall be 1 1/2 times the design pressure of the auxiliary piping or 8.0 Kg/cm2G, whichever is greater. All hydrostatic tests shall be maintained for a minimum of 30 minutes. PERFORMANCE TEST Each pump shall be performance tested with water and job motor. The purchaser’s driver shall not be used for shop running tests if there is any possibility of serious overload. Unless otherwise mutually agreed upon, the test speed of all pumps shall be the rated speed. Allowable deviations are as follows. 1. Normal fluctuations of motor speed. 2. Pumps manufactured for 50 Hz service may be tested at a standard 60 Hz speed and vice versa. The certified test curve shall be corrected to actual speed of the job driver. The performance test shall include a minimum of five test capacities extending from zero flow to at least 125% of capacity at peak efficiency. Capacity test points shall generally be equally FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION spaced and include one capacity not more than + 5% from rated capacity. The complete pump assembly shall be guaranteed for head, capacity, power consumption and water NPSH at the specified rated operating conditions and satisfactory application to all operating conditions specified on the individual pump specification sheet.Permissible deviations from the specified performance ( in percent of rated ) are as follows or as otherwise specified in the specification. 5.3.4 Condition Rated capacity Plus Zero capacity* Minus Plus 6.3.1 6.3.2 6.3.3 Minus Rated differential head 5.3.6 5.3.7 5.4.0 6.0.0 6.1.0 6.2.0 6.2.1 6.2.2 6.3.0 1. 0 to 150M 5 2 10 10 2. 151M & above 3 2 8 8 Power consumption (KW) NPSH required 4 - - - 0 - - - Guaranteed efficiency - 0.5% - - * A minus tolerance on the head-capacity curve at zero capacity (shut off) is allowed only if the continuously rising characteristic is maintained. Each pump shall be checked for acceptable vibration during the shop performance test in accordance with subsection 4.2.4. Mechanical seals shall be used during the shop performance test if so specified, but are not required for the hydrostatic test. Pumps that are dismantled after the shop test solely to machine the impellers and achieve the tolerances for differential head need not be retested unless the reduction in impeller diameter exceeds 5 percent of the original diameter. NPSH TEST An NPSH test is required, if the difference between the NPSH available indicated on the pump specification sheet and the NPSH required by the pump is 1.0 metre or less. 5.3.5 01ES010 / 94 CENTRIFUGAL PUMPS FOR GENERAL PURPOSE SERVICES ASSEMBLY & PREPARATION FOR SHIPMENT GENERAL Assembly and preparation for shipment shall be according to the pump manufacturer’s standard and this specification. The pump manufacturer shall be solely responsible for packing and shipping the pumps. EQUIPMENT TRAIN ASSEMBLY Pumps, drivers and all furnished auxiliaries (except coupling spacers and bolts) shall be shipped fully assembled on the baseplates, except where it is not possible or advisable to ship the pump in fully assembled condition. Coupling spacers and bolts shall be separately boxed and securely attached to the base plate. Metal filter elements and screens shall be cleaned and reinstalled prior to shipment. PAINTING 6.3.4 6.3.5 6.3.6 6.3.7 PAGE 6 OF 7 Unpainted Surfaces Stainless steel surfaces, interiors and finished surfaces such as flange faces, shafts and couplings, shall not be painted. Painted Surfaces The exteriors of pumps, drivers, baseplates, accessories and piping, except where otherwise prescribed in subsection 6.3.1., shall be painted before the equipment is shipped from the pump manufacturer’s shop. Painting shall be carried out under the following conditions. a. Ambient temp. shall be above + 50C. b. Relative humidity shall be below 80%. c. Surface to be painted shall be dry. Painting shall not be done during raining conditions. Surface preparation is to be performed generally in accordance with SSPC standards so as to remove all rust, oil and foreign particle. Painting shall be performed by spray gun. Shop painting requirements. Service conditions Coat Type of Paint Epoxy Extremely Primer based red corrosive oxide environment like splash & spillage of High build acids, urea upto Finish epoxy 1300C based paint Corrosive High build environment like Primer chlorinated exposure to salt zinc dust, acid, acid phosphate fumes etc upto 650C Finish Chlorinated rubber paint Corrosive Epoxy environment like based red exposure to salt Primer oxide / zinc dust, acid, acid chromate fumes /zinc 0 etc 65 to 120 C phosphate Finish Epoxy based paint Corrosive Primer environment like exposure to salt dust, acid, acid Silicon fumes etc 0 Finish based paint above 120 C Ordinary Red oxide environment Primer zinc upto 1200C chromate ( IS2074 ) Synthetic Finish enamel ( IS2952 ) Epoxy Saline based zinc environment Primer chromate / upto 1250C zinc phosp hate primer Finish Epoxy based paint 6.3.8 6.3.9 6.4.0 6.4.1 Dry Film No. of Thk. coats (microns / Coat ) 2 25 2 35 2 25 2 35 2 25 2 35 2 35 2 35 2 25 2 35 2 25 2 35 Colour of finish paint for pumps and accessories shall be sea green shade No. 217 of IS-5. If any of the catogories of paint are not available in seagreen colour, then prime and finish coats can be given in avaiable colours. A final colouring coat of enamel paint in sea green colour shall be given over the finish coats in such cases. Motors shall be painted as specified in motor spec. Other Protection Interiors FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 6.4.2 6.4.3 6.5.0 6.5.1 6.5.2 CENTRIFUGAL PUMPS FOR GENERAL PURPOSE SERVICES 1. Bearings, bearing housings and oil systems shall be thoroughly cleaned and coated with a suitable rust preventive. 2. Surfaces that were in contact with fluids, including the stuffing boxes and flushing piping, shall be thoroughly dried. Surfaces that are susceptible to corrosion shall be coated with a suitable rust preventive. 3. Mechanical seal assemblies shall be fully protected from corrosion and ingress of foreign materials. Exteriors 1. Unpainted exteriors, except stainless steel, but including bolting and flange faces, shall be coated with a suitable rust preventive. 2. Afterwards exposed shafts and shaft coupling shall be wrapped with waterproof moldable waxed cloth or VPI barrier paper. The seams shall be sealed with adhesive tape. Openings 1. All threaded openings shall be plugged with long shank pipe plugs. The plug material shall be equivalent to the material being plugged, except that carbon steel plugs shall be used for openings in cast iron. 2. Flanged openings shall be provided with full flange diameter protective covers. The cover material shall be 4.5mm (minimum) thick metal plate. A full diameter gasket shall be supplied between the flange and the cover. The cover shall be secured to the flange by a minimum of four full diameter bolts and nuts. Identification Markings 1. Each major piece of equipment having an equipment number as per the purchase order or specification sheet shall have a permanently attached nameplate. The nameplate shall comply with the project specifications. 2. Connections furnished on the equipment shall be die-stamped or permanently tagged to agree with the pump manufacturer’s connection table or general arrangement drawing. 3. Each coupling half and spacer shall be electrically etched or die-stamped with the equipment number of the pump for which it is intended. Tags 6.6.0 6.6.1 6.6.2 7.0.0 01ES010 / 94 PAGE 7 OF 7 1. Each pump component shall be identified by its purchase order number and equipment number. Tags shall be corrosion-resistant metal (not aluminum) and die- stamped with the purchase order number and equipment number. 2. Tags shall be attached to each pump component with stainless steel wire (The tags are in addition to the equipment nameplate). Equipments shipped in fully en closed containers shall also have the purchase order number and equipment number marked on the outside of the container. 3. Miscellaneous components shall be tagged or marked with the equipment number of the pump for which they are intended. 4. Equipment containing insulating oils, antifreeze solutions or other fluids shall be prominently tagged at openings to indicate the nature of the contents and shipping and storage precautions. Packing All equipment shall be packed, securely anchored (skid-mounted when required) and protected for domestic shipment by rail or truck. All unmounted components, except drivers, shall be suitably crated and firmly attached to the main pump unit for shipment. Export boxing, if required, shall be mutually agreed upon by purchaser and manufacturer. One complete set of installation, operation and maintenance instructions shall be packed and shipped with the equipment, if required. APPENDIXES Appendix 1: Classification codes for Mechanical seals Appendix 2: Piping for Seals Appendix 3: Cooling Water Piping ********************************* FACT ENGINEERING AND DESIGN ORGANISATION CENTRIFUGAL PUMPS FOR HEAVY DUTY SERVICE ENGINEERING SPECIFICATION 4.0.0 CONTENTS 1.0.0 SCOPE 2.0.0 REFERENCES 3.0.0 DEFINITIONS 4.0.0 MODIFICATIONS TO API STANDARD 610 8TH EDITION 1.0.0 SCOPE ------------------------------------- Reference is made in this section only to those paragraphs of API 610 – 8th Edition where additions or modifications are made and to wholly new paragraphs which are inserted in alphanumeric order in API 610 – 8th Edition. Other paragraphs of API 610 – 8th Edition which are not mentioned in this section are to be followed without change. 4.1.1 The word in parenthesis following the number or title of a paragraph indicates the following: ( Addition ) An addition of a part, section or paragraph referred to. (Modification) An amplification or rewording has been made to a part of the corresponding section or paragraph but not a substitution replacing the entire section or paragraph. (Substitution) A substitution has been made for the corresponding section or paragraph of the standard in its totality. (New) A new section or paragraph having no corresponding section or paragraph in the Standard. (Delete) The paragraph is deleted. 4.2.0 SECTION 1 : GENERAL 1.1.0 This specification covers the engineering requirements for horizontal and vertical centrifugal pumps for heavy duty service. 1.2.0 Special requirements of the project, if attached to this specification, cover modification to this specification, customer’s special or local requirements as well as specific job data pertinent to this specification. Where special job requirements are in contradiction to this specification, special job requirements shall govern. 1.3.0 This specification does not supersede API standard 610 8th Edition, but modifies it as required in following paragraphs. 2.0.0 REFERENCES 2.1.0 The requirements contained in the latest editions (unless otherwise indicated) of following standards shall form part of this specification in the manner and to the extent indicated. Hydraulic Institute Standard - Centrifugal Pump Section. 3.0.0 DEFINITIONS 3.1.0 Following terms as used in this specification shall have the meanings denoted. Heavy duty centrifugal pump a. Multi stage centrifugal pumps (more than 3 stages) b. Single or two stage, horizontal and vertical centrifugal pumps having either of following rated service conditions. 0 0 Temperature : Below -10 C or above+150 C 2 Discharge pr. : 21 Kg/cm G or higher 4.2.1 Para 1.1 Scope (Substitution) 4.2.1.1 Para 1.1.1 The entire paragraph is substituted by paragraph 1.0.0 herein above, excepting the note contained in the para. 4.2.1.2 1.1.3 (Modification) Unless otherwise specified, the pump types listed in Table 1.1 of API shall not be offered. 4.2.2 Para 1.2 Alternative Designs (Deleted) 4.2.3 Para 1.3 Conflicting Requirements (Substitution) All conflicts between this specification, data sheets and specifications/codes/standards referred herein shall be referred to the purchaser for clarification prior to the manufacture of the affected part. 4.2.4 Para 1.5.1 (Modification) The editions of referenced publication that are in effect at the time of inquiry or at a date specified in the inquiry documents shall be applicable. 3 Capacity : 150 M /h or higher Speed : More than 3000RPM 4.3.0 4.3.1 c. Any other centrifugal pump specifically include in 4.3.1.1 the heavy duty classification by Purchaser. PRPD. BY: 01ES067 / 19 PAGE 1 OF 5 MODIFICATIONS TO API STANDARD 610 8TH EDITION Centrifugal pumps shall conform to API 610 – 8th edition, except as modified in this section. CHKD. BY: SECTION 2 : BASIC DESIGN Para 2.1 General Para 2.1.8 (Addition) Pumps where margin between NPSHA and NPSHR from quoted minimum flow to rated flow is less than 0.6 meter are not acceptable. The said NPSHR value shall correspond to the maximum APPRD.BY: FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON: ENGINEERING SPECIFICATION CENTRIFUGAL PUMPS FOR HEAVY DUTY SERVICE 01ES067 / 19 PAGE 2 OF 5 Regions of double-casing and horizontal multistage value of NPSHR from rated flow down to the pumps (pumps with three or more stages) that are recommended minimum continuous stable flow subject only to suction pressure shall also be designed specified by the vendor. However in case of parallel for the maximum allowable working pressure. operation or auto-start against open discharge valve 4.3.2.2 Para 2.2.8 (Substitution) conditions, NPSHR at End of the Curve shall not The pump's pressure casing shall be suitable to exceed specified NPSHA in addition to above margin Withstand twice the forces and moments in Table requirement. Pumps fitted with inducers for reducing 2-1A (2-1B) applied simultaneously to the pump NPSHR are not acceptable. through each nozzle, plus internal pressure, without 4.3.1.2 Para 2.1.10 (Addition) distortion that would impair operation of the pump Refer Performance Correction Chart of or seal. Hydraulic Institute Standard. Correction factors Note: Vendor to note that the above criteria shall be as applicable shall be indicated by the used for design of purchaser's associated piping system. manufacturer on the filled-in data sheet. 4.3.1.3 Para 2.1.11 (Substitution) 4.3.3 Para 2.3 Nozzle & Pressure Casing Connections Pumps shall have stable head/flowrate curves 4.3.3.1 Para 2.3.3.10 (Addition) (continuous head rise to shutoff) for all Casing shall be provided with drain connection with applications. If parallel operation is specified, nipple, threaded and seal welded and provided with a the head rise from rated point to shutoff socket welded gate valve terminated at edge of the shall be at least 10%. Unless otherwise base plate. Gate valve shall be of 800# rating with specified, discharge orifice shall not be used to material of construction (MOC) equal or superior to achieve required head rise to shut off in case of the pump casing. For multistage pumps with more parallel operation. than one drain point, block valves at each drain 4.3.1.4 Para 2.1.12 (Substitution) point shall be provided and the piping shall be Pumps shall have preferred operating region of terminated at edge of the base plate with a flange. 70% to 120% of best efficiency flow rate of the Unless made self venting design, vent connections pump as furnished. Rated flow shall be within shall also be provided with a nipple, threaded and 110% of best efficiency flow rate of the pump as seal welded and terminated with a gate valve. furnished. Vendor shall indicate "Preferred Pressure gauge connection shall not be provided Operating Range" and " Allowable Operating unless specifically required in the inquiry. Nipples Range "on the characteristic curve. shall meet the requirements of 2.3.3.5 & 2.3.3.6. 4.3.1.5 Para 2.1.14 (Substitution) Unless specified otherwise, the maximum 4.3.4 Para 2.6 Wear Rings And Running Clearances permissible sound level shall not exceed 88 dBA 4.3.4.1 Para 2.6.3 (Modification) measured at one (1) meter from the complete The sentence " Other methods including tack pump unit, when measured in any direction & welds, requires purchaser' s approval" stands from any point of any equipment surface located deleted. on the equipment skid, for the recommended 4.3.4.2 Para 2.6.4.1 (Addition) Vendor shall also furnish in the proposal the range of operation. maximum permissible running clearances which in 4.3.1.6 Para 2.1.20 (Modification) Maximum inlet temperature 33°C, maximum no case shall be less than twice the running clearances as specified in this clause. temperature rise 17°C, fouling factor water side maximum allowable 0.0004 m2h°C/Kcal, working pressure 8 kg/cm2g. 4.3.5 Para 2.7 Mechanical Shaft Seals 4.3.1.7 Para 2.1.29 (Modification) 4.3.5.1 Para 2.7.3.19 (Modification) Unless otherwise specified, equipment shall be For the applicable flushing and cooling plans, the designed to be suitable for outdoor installation vendor shall also include in his scope of supply, all without a roof. items marked with an asterisks (*)and shown as 4.3.1. 8 (New) optional items in Appendix D - Mechanical Seal For balancing axial thrust in multi-stage pumps, and Piping Schematics along-with all other only the following arrangements shall be used: specified/ required items. - Opposed arrangements of impellers. 4.3.6 Para 2.8 Dynamics - A balancing piston 4.3.6.1 Para 2.8.2.6 (Modification) Replace the words " when specified" by "If torsional 4.3.2 Para 2.2 Pressure Casings analysis is performed". 4.3.2.1 Para 2.2.4 (Modification) FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION CENTRIFUGAL PUMPS FOR HEAVY DUTY SERVICE 01ES067 / 19 PAGE 3 OF 5 operation shall not be less than the max. BKW 4.3.7 Para 2.9 Bearings & Bearing Housings indicated on pump data sheet (Power at End of the 4.3.7.1 Para 2.9.2.6 (Modification) curve for the rated impeller) and the pump motors Bearing housings shall be equipped with shall be suitable for start-up under open discharge replaceable non contact type bearing isolators valve condition. where shaft passes through the housing. 2. The motor nameplate rating for applications where 4.3.7.2 Para 2.9.2.9 (Modification) Requirement of oil heaters for bearing oil shall be the specific gravity of pumped fluid is less than 1.0 as per vendor's standard practice and shall be shall either be 100% of the BKW of pump at provided by the vendor when the ambient or minimum continuous stable flow with clean cold operating temperature dictates. water of sp. gravity 1.0 or shall have the specified 4.3.7.3 (New) margin as per this clause, whichever is greater. Bearing housing shall be equipped with magnetic 4.4.1.2 Para 3.1.9 (Modification) Unless otherwise specified, steam turbine drivers drain plug. shall be sized to deliver continuously 110% of pump rated power at minimum inlet and maximum 4.3.7 Para 2.11 Materials exhaust steam conditions. The steam turbine rating 4.3.7.1 Para 2.11.1.1 (Modification) (with minimum inlet and maximum exhaust steam The material of construction of pump parts shall be conditions) for pumps under parallel operation or in accordance with the data sheet. for pumps with auto-start operation shall not be less 4.3.7.2 2.11.1.4(c)(Modification) than the max. BKW indicated on pump data sheet Unless specified otherwise, Casing in Cast Iron (maximum power at any point on the pump construction shall not be offered. performance curve from shutoff to end of the curve 4.3.7.3 Para 2.11.1.7 (Modification) for the rated impeller). The turbine shall also be The words ' when specified' stand deleted. suitable for start-up under open discharge valve 4.3.7.4 Para 2.11.1.11 (Modification) condition. In any case, Turbine Rating shall be at Requirements indicated in the referred clause are least equal to the Motor Rating of the standby applicable even if only trace quantity of wet H2S is pump. indicated to be present. 4.3.7.5 2.11.2.5 (Modification) 4.4.2 Para 3.2 Couplings & Guards The words " when specified" stand deleted. 4.4.2.1 Para 3.2.2 (Addition) The coupling service factor shall not be less than 4.4.0 SECTION 3 - ACCESSORIES 1.5 over the driver rating. 4.4.1 Para 3.1 Driver 4.4.2.2 Para 3.2.12 (Addition) 4.4.1.1 Para 3.1.4 (Modification) Coupling guard shall be non-sparking and shall be Electric motor drivers shall have a maximum open at the bottom to permit manual shaft rotation. continuous rating (MCR) (i.e. service factor equal The guard shall be sufficiently rigid to withstand to 1) not lower than the following: deflections as a result of bodily contact of nominally 100 kgs. Motor Name Motor MCR (% of Pump 4.4.2.3 (New) plate Rating Rated BKW) Unless otherwise specified, all couplings required for multistage pump package(s) (greater than two Upto 22 kW To suit maximum BKW stages) shall conform to API standard 671 where indicated on pump data sheet or either the driver rating is greater than 160 kW or 125% of rated pump BKW, the maximum continuous speed is greater than whichever is higher. 3000 rpm. However in case of gear box driven multistage pump units, both low speed and high The electric motor shall be suitable for the speed couplings shall conform to API standard 671 electrical area classification specified on the data if any of the above criteria of speed or power is sheet. satisfied. Note: 1. Over and above the requirements specified in Table 3- 1 and the above modifications, the motor nameplate rating for pumps under parallel FACT ENGINEERING AND DESIGN ORGANISATION ` ENGINEERING SPECIFICATION 01ES067 / 19 CENTRIFUGAL PUMPS FOR HEAVY DUTY SERVICE PAGE 4 OF 5 4.4.3 Para 3.3 Baseplates 4.4.3.1 Para 3.3.6 (Modification) 4.4.5 The vendor shall furnish the results of the pipe load 4.4.5.1 test data for the proposed pump model(s) along with their proposal indicating the shaft deflections at coupling end. 4.4.5.2 - Cables between transmitters and junction box. Para 3.5 Piping & Appurtenances Para 3.5.2.4 (Addition) Auxiliary process fluid piping material shall be SS316 as a minimum. 3.5.2.10.1 (Modification) Flanges are required in places of socket welded 4.4.3.2 Para 3.3.20 (Modification) unions. Anchor bolts & suitable washers shall be furnished 4.4.5.3 (New) by the pump manufacturer. Material for seal flushing liquid cooler shall be as 4.4.3.3 (New) under: Pumps in corrosive service shall have provision to Tube or Coil : Type 316 stainless steel or Monel. collect and drain the leakage from mechanical seal Casing (or Shell): Carbon Steel. or packing, through a drip pan of metallurgy Cooling water shall be on the casing (Shell) side. equivalent or superior to pump casing. Leakages 4.4.5.4 3.5.4.3 (Modification) from drip pan shall be piped to baseplate with a Sight flow indicator shall have ball or flag for easy flanged connection for onward disposal by verification of water flowing through pipes. purchaser. Where the design of bearing prohibits Thermal Relief valves in each isolatable CW circuit provision of drip pan, the material of bearing shall also be provided. bracket shall be suitable for the corrosive service. 4.5.0 SECTION 4 - INSPECTION TESTING AND 4.4.3.4 (New) PREPARATION FOR SHIPMENT Skid layout of pump trains along-with their 4.5.1 Para 4.1 General auxiliary systems (i.e. seal flushing plans) shall be 4.5.1.1 Para 4. 1 .5 (Addition) designed in a manner so as to ensure that there is Prior to start of test, manufacturer shall furnish enough space within the skid for maintenance and the certificate of latest calibration / recalibration operation. Special care shall be taken for pumps of driver and measuring instruments for review provided with seal flushing plans 23 and 52 so that by purchaser' s inspection agency. couplings and seals can be attended for maintenance without disturbing any seal Unless electrical or mechanical failure occurs, piping/cables/other items located on the skid. As driver used for shop testing need not be far as possible, area on motor terminal box side recalibrated and original calibration certificate shall be left clear of all piping and accessories for shall remain valid. ease of maintenance. Duration of recalibration for all measuring 4.4.4 Para 3.4 Instrumentation 4.4.4.1 3.4.3.1 (Modification) The words ' when specified' stand deleted. 4.5.2 4.4.4.2 Para 3.4.3.2 (Modification) 4.5.2.1 The words `when specified' stand deleted. 4.4.4.3 4 (New) Horizontal multistage pumps intended for pumping temperature above 120°C shall be provided with pump casing skin temperature monitoring system consisting of the following: - Four thermocouples along-with yoke mounted temperature transmitters with integral indicator for each thermocouple. - One Junction Box (JB) to be mounted on the pump base-plate. - Cables between the thermocouples and transmitters. instruments shall be as recommendations of HI Standards. per the 4.3 Testing Para 4.3.3.3.3 (Modification) The tolerances for guaranteed characteristics stand modified as under: -Rated Head : Zero negative tolerance @ rated flow rate & rated speed -Shut-off Head Following criteria shall apply: a) Positive tolerance permitted as long as maximum shutoff pressure corresponding to shut-off head (as observed during the shop performance test) and the maximum suction pressure (as specified on pump data sheet), does not exceed the downstream design pressure (as specified on pump data sheet). FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 01ES067 / 19 CENTRIFUGAL PUMPS FOR HEAVY DUTY SERVICE PAGE 5 OF 5 b) Negative tolerance (as per Table 4-2 of API Std. 4.6.2 Para 5.3 Vertically Suspended Pumps 610,8th edition) may be permitted only if test curve 4.6.2.1 5.3.1 PRESSURE CASINGS still shows rising characteristics. 4.6.2.1.1 Para 5.3.1.2 (Addition) c) Negative tolerance is not permitted for pumps Bowls and columns shall be flanged and bolted. required for pumps under parallel operation. [Note: Generally shutoff head should be limited 4.6.2.2 Para 5.3.2 ROTORS within 120% of rated head.] 4.6.2.2.1 Para 5.3.2.3 (Addition) -NPSHR Zero positive tolerance. Multi-piece vertical pump line shaft shall not be -Rated BKW Zero positive tolerance. joined by threaded couplings. 4.5.2.3 Para (New) 4.6.2.3 Para 5.3.5 GUIDE BUSHINGS AND BEARINGS During the performance test, the equipment shall be checked for its sound level at minimum flow, at 4.6.2.3.1 Para 5.3.5.2 (Modification) rated flow, at flow at best efficiency point and at Pump thrust shall not be transferred to driver 120% BEP flow. motor. Vertical pumps shall be provided with their The maximum allowable value shall not exceed the own thrust bearing to carry rotor weight and pump value specified under clause 2.1.14 or as specified generated axial forces. Thrust bearing shall be in the datasheet, whichever is lower, when positively locked on the pump shaft (shouldered measured at one (1) meter from pump surface. shaft) and the bearing housing. Where complete unit test is specified, vendor is required to demonstrate the noise levels within the 4.6.2.4 Para 5.3.6 LUBRICATION maximum permissible sound level for the complete 4.6.2.4.1 (New) For self lubrication pumps, guide bushing shall be unit. Recorded sound levels during shop test shall be taken for reference only & not for final suitable for dry running during startup. acceptance or rejection. However sounds level as 4.6.2.5 Para 5.3.7 ACCESSORIES specified in the inquiry document shall be 4.6.2.5.1Para 5.3.7.1.2 (Modification) guaranteed at site. For vertical pumps, not provided with non-reverse racket, vendor shall describe the precaution taken, 4.5.3 Para 4.4 Preparation for Shipment to prevent damage due to reverse rotation. 4.5.3.1 (New) 4.6.2.6 Para 5.3.9 SINGLE CASE DIFFUSER (VS1) AND Unless otherwise specified, the equipment shall be VOLUTE (VS2) PUMPS protected for a storage of 12 months at site. If any 4.6.2.6.1 Para 5.3.9.7 (Modification) extra precaution is to be taken by the Purchaser for The words " when specified" stand deleted. storage beyond 12 months the same shall be 4.6.2.7 Para 5.3.12 DOUBLE CASING DIFFUSER (VS6) explicitly indicated in the operation and AND VOLUTE (VS7) PUMPS maintenance manuals. 4.6.2.7.1 Para 5.3.12.6 (Modification) The words " when specified" stand deleted. 4.6.0 SECTION 5 - SPECIFIC PUMP TYPES 4.6.1 Para 5.2 Between Bearing Pumps (TYPES BB1 - 4.7.0 SECTION 6 - VENDOR' S DATA BB5) This section is deleted. 4.6.1.1 Para 5.2.8 TESTING 4.6.1.1.1 Para 5.2.8.5 (Modification) Submission of vendor’s data shall be in The words " when specified" stand deleted. accordance with the requirements stipulated in the procurement specification vide documents 4.6.1.2 Para 5.2.9 PREPARATION FOR SHIPMENT VDS & VDR. 4.6.1.2.1 Para 5.2.9.2 (Modification) The words " when specified" stand deleted. ***************************************** FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION 32644-03-PS-001 ATT ATTACHMENTS PAGE 1 OF 1 R0 TPS No. SL. No. Doc. No. No. of Rev. No. with issue Pages 1 2 3 4 Description 1 32644-03-PS-001 VDR VENDOR DATA REQUIREMENT 1 0 2 32644-03-PS-001 SPL SPECIAL REQUIREMENT (PIPING) 3 0 3 03ES001/10 PIPING DESIGN 11 0 4 03ES010/10 PIPING TURNKEY PACKAGE 2 0 5 03ES014/15 RUBBER LINING FOR PIPES& PIPE FITTINGS 14 0 6 03DS003 PIPING SPACING 1 0 7 03DS013 VENTS & DRAINS FOR PIPE LINES 1 0 8 03DS202 PIPING TRUNNION SELECTION 6 0 9 03DS305 TABLE OF BASIC SPANS AND UNIT LIGHT 3 0 WEIGHT WITHIN BATTERY LIMITS 10 02ES023/10 PAINTING 13 0 11 25ES205/10 FABRICATION , ERECTION OF STEEL PIPING 28 0 12 32644-03-PS-001 SV SUB VENDOR LIST 3 0 13 32644-03-OP-00001_Rev.0 OVERALL PLOT PLAN 1 0 1. The receipt of all attachments shall be checked and asertained. Note: 00FT011/10 2. All attachments of this TPS shall be retained since only revised sheets, if any, shall be issued 0 05.06.2020 FOR ENQUIRY AMN JTG KK REV. DATE DESCRIPTION PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION PROJECT VENDOR DATA REQUIREMENTS : CONSTRUCTION OF ADDITIONAL PHOSPHORIC ITEM 32644-03-PS-001 VDR PAGE 1 OF 1 R0 PIPING SYSTEM ACID STORAGE TANKS AT Q10 BERTH, WI CLIENT : M/s. FACT STATUS : √ TPS No ENQUIRY COMMITMENT Sl. No Grp Code 1.0 2.0 3.0 4.0 4.1 4.2 4.3 5.0 5.1 5.2 5.3 6.0 7.0 7.1 7.2 8.0 8.1 8.2 8.3 9.0 9.1 10.0 10.1 10.2 10.3 A Specific plot plan A&C Piping Layout drg. A&C Quality control procedure & plan for piping system. Design data and layout. A&C Design basis A&C Piping material specification A&C Valve material specification ( with filled data sheet) Issued for construction (IFC) Drawing. C Piping GA DRGS. Isometrics C Piping supports, operating platforms drg. C C Material Take-offs Material and Purchase Requisitions Pipes A A Valves Design calculation / Documents. B Pipe stress analysis (CEASAR II ) report A Flexibility Analysis of Piping A Support and load data Vendor Drawings B&C Valves As Built Drgs C Piping GAD’s C Isometrics C All inspection, testing & NDT Records. PO No Offer Description After Commitment Lead time in weeks Final@@ Qty Qty Qty 3P+1S 3P+1S 4 3P+1S 4 3P+1S 3P+1S 4 3P+1S 3P+1S 4 3P+1S 3P+1S 4 3P+1S 3P+1S 4 3P+1S Reqd Prop@ Agrd 3P+1S 4 3P+1S 3P+1S 4 3P+1S 4 3P+1S 3P+1S 4 3P+1S 3P+1S 4 3P+1S 3P+1S 4 3P+1S 3P+1S 4 3P+1S 3P+1S 4 3P+1S 4 1S 4 1S 3P+1S 4 3P+1S 3P+1S 4 3P+1S 3P+1S 4 3P+1S 3P+1S 4 3P+1S 3P+1S 4 3P+1S 4 3P+1S 3P+1S 4 3P+1S 4 3P+1S 03FT044B / 2015 Legend : Group code : A - For review and detailed Engineering , B - For review , C - For information and record Document type : R - Reproducible , P - Print , M - Microfilm, S - Soft Copy Notes : '@' Vendor shall fill in proposed lead time if different from the required lead time ' @@ ' Each set of final documents shall be submitted in a folder. Two such folders shall be packed and despatched with the equipment. 0 05.06.2020 For Enquiry REV No DATE DESCRIPTION AMN PREPARED FACT ENGINEERING AND DESIGN ORGANISATION JTG KK CHECKED APPROVED PIPING DEPARTMENT SPECIAL REQUIREMENTS (PIPING) 32644-03-PS-001 SPL Page 1 of 2 1. Associated piping for the construction of 2nos. of Phosphoric acid (P2O5) sto rage tank each having capacity of 5900 MT at W.Island, FACT CD m ainly consist of inlet line to new tanks, line from new ta nks to pu mp suction, recirculation lines , line to barge, erection of new truck load ing bay and its associated p iping, utility piping etc. Process and Utility pipin g system for this project shall be in a ccordance with Process piping code ASME B 31.3. 2. Piping and its com ponents shall be designed as per the attached engineering specification 03ES001/10 (Piping Design) 3. Bidder shall follow the attach ed engine ering specification 03ES010/10 (Piping turnkey package) for the piping scope, desi gn consideration, battery limits for piping, details of drawing and documents, general requirements etc. 4. Bidder shall submit documents as per attached Vendor Data Requirement. 5. General design, m aterial, procedure, testin g etc. for rubber lining shall be as per attached rubber lining specification 03ES014/15. 6. All piping (Process lin es, Utilities etc.) with in the battery lim its are under the scope of bidder 7. Piping scope includes design, detail engineer ing, procurem ent, testing at vendor' s shop and supply of all piping’s as per the a pproved material classes and specification. 8. Design of piping system shall be as per the relevant codes and regulations specifies in the engineering specifications . 9. Bidder shall furnish drawings & docum ents necessary for approval from statutory bodies and that all m aterials used sh all be accompanied by the necessary certificates as per the applicable codes. 10. Detailed painting specifica tions will be as per 02 ES023/2010 (FEDO). Sand blasting will not be allowed under any circumstances. 11. All lines ter minating at the ba ttery limit shall be provided with a flange and m ating flange, gasket, bolt & nuts. 12. Bidder shall provide break flanges on pipe lines where ever required for m aintenance access. 13. Bidder shall provide temporary piping for blow-out. Blank & spacers’ gaskets etc. for isolation during the line testing and temporary & permanent strainers. 0 REV 05.06.2020 DATE ORIGINAL ISSUE DESCRIPTION FACT ENGINEERING AND DESIGN ORGANISATION AMN PRPD JTG CHKD KK APPRD PIPING SPECIAL REQUIREMENTS DEPARTMENT (PIPING) 32644-03-PS-001 SPL Page 2 of 2 14. For pressure relief valve and safety valve, reaction load calculation shall be carried out and provide adequate supporting. Outlet vent shall be provided to safe height without pockets. 15. If the pipe line at the floor level, bottom of the pipe shall be at the height of 500 mm from the floor level. 16. Piping stress analysis and equipment nozzle loading analysis shall be in accordance with ASME B31.3 and relevant API codes. 17. Nozzle analysis shall follow the guide lines of ASME Section VIII, Division 1, and WRC 297 & 107 (Latest editions). Nozzle stresses shall fall within the allowable as per ASME 18. Bidder shall use latest version of CEASAR II for the pipe stress analysis of critical piping. 19. The procedure and conditions for hydro test will be followed as per the descriptions given in engineering specification 25ES205. Sea water/ saline water shall not be used for hydro testing and contractor shall arrange water for hydro testing at no extra cost. Suitable corrosion inhibiters should be added. 20. All alloy steel and higher alloyed piping material shall be subjected to Positive Material Identification (PMI) inspection. 21. Sufficient number of safety showers & eye wash shall be provided in the ISBL area. FACT ENGINEERING AND DESIGN ORGANISATION iso2.sty ENGINEERING SPECIFICATION PAGE 1 OF 11 CONTENTS 1.0.0 2.0.0 3.0.0 4.0.0 GENERAL DESIGN MATERIALS FABRICATION, HEAT TREATING, INSPECTION AND PRESSURE TESTING ———————————————————— 1.0.0 GENERAL 1.1.0 1.1.1 SCOPE This specification together with the Piping Specification and design data sheets is applicable for the piping located within the Plant Battery limits. No variation shall be permitted unless approved in writing. MODIFICATIONS Piping which is furnished as a regular part of proprietary or standardized equipment shall be in accordance with the equipment manufacturer’s standards for the design conditions. 1.1.2 1.2.0 1.2.1 2.0.0 DESIGN 2.1.0 2.1.1 GENERAL The design of piping shall conform to the requirements of the ASME Process Piping B31.3 except as modified by Paragraph 2.12.4. When a code, rule, or regulation is speciied in the Piping Specification Sheets, the design shall conform to such specified requirements and to such portions of this specification as do not conflict. a. Snubbers shall be furnished as proprietary piping equipment, designed and fabricated in accordance with Section VIII of the ASME Boiler and Pressure Vessel Code. b. Knockout pots and like items shall be furnished as piping equipment designed and fabricated as follows. 1. Sizes 600NB outside diameter and smaller in accordance with ASME B31.3. 2. Sizes greater than 600NB outside dia. in accordance with ASME section VIII c. Piping, snubbers, knockout pots, and like items with design pressures below those covered by the applicable listed code shall be designed and fabricated in accordance with ASME B31.3. Piping connected to power boilers, waste heat boilers, dowtherm boilers or unfired steam generating equipment shall be designed in accordance with section I of the ASME Boiler and Pressure Vessel Code, with all addenda, Power Piping ASME B31.1 and IBR to the extent required thereby. DESIGN PRESSURES & TEMPERATURES 2.1.2 2.2.0 PRPD. BY: 03ES001 / 10 PIPING DESIGN CHKD. BY: 2.2.1 2.2.2 2.2.3 2.2.4 2.3.0 2.3.1 2.3.2 2.3.3 The expected continuous operating conditions shall be specified on the process flow sheets / line schedule. The design pressure and metal temperature shall be in accordance with ASME B31.3 / ASME B31.1 and the following. a. In vacuum service, the normal design pressure shall be the lowest value which the vacuum producing means is capable of attaining. b. Piping circuits on the upstream side of control valve shall be designed for pressures resulting from minimum flow conditions (closed or throttled control valve) and downstream of the control valve shall be designed for the downstream terminal pressure plus friction losses (pressures due to closed or throttled block valves shall not be considered except as short time conditions) and head losses. c. The design metal temperature of the piping conveying fluids with temperatures below 15 deg.C shall be equal to the minimum, normal operating tempera ture of the fluid in the pipe or fluid temperature during normal startup or shutdown. Metal temperatures resulting from emergency conditions caused by equipment failures such as ruptured tubes, etc. or operational errors shall not be considered. The short time design pressure and design metal temperature shall be those of higher value which are expected to occur during starting-up, shutting-down, or in any other short time operating condition. A freezing climate shall be defined as one with a January average temperature of 4 deg.C or lower. LOADS The design for wind and earthquake shall be based on and considered to the extent required by the Bureau of Indian Standards. Piping shall be designed to resist the effects of the following combinations of loads within the limits of stress specified herein. Wind and earthquake loads shall not be assumed to occur simultaneously. a. Operation : The design pressure, the operating dead load, and the maximum operating contents load, combined with or without wind or earthquake load. b. Test : The test pressure, the test dead load, and the fluid test load. c. Short time : The operating condition without wind or earthquake load but modified or supplemented by the changes resulting from the short time conditions defined in 2.2.3. For the design conditions given, the calculated principal stresses for pressure parts shall not exceed the following. a. Operation and short time condition stresses are covered by ASME B31.3/ ASME B31.1. APPRD. BY: ISSUED ON: APR ’10 . FACT ENGINEERING AND DESIGN ORGANISATION CONTROLLED COPY ISO 9001 : 2015 ENGINEERING SPECIFICATION 2.3.4 2.3.5 2.4.0 2.4.1 2.4.2 2.4.3 2.5.0 2.5.1 2.5.2 03ES001 / 10 PIPING DESIGN b. Test: Based on the test thickness and the test temperature, the basic allowable stresses increased by 50%. The basic allowable stresses for non-pressure parts, including attachments (except threaded parts and attachment welds to pressure parts) and devices for supporting or bracing piping, shall be one-third of the ultimate tensile strength, two-thirds of the yield strength, or the stress producing a creep rate of 0.01% in 1000 hours, whichever is lower. a. The maximum allowable tensile stress for carbon steel threaded parts, such as anchor bolts and rods, based on the root area of the thread, shall be 15,000 psi (1055 kg/sq.cm) The calculated principal stresses for non-pressure parts shall not exceed the basic allowable stresses for the operating conditions; the basic allowable stresses increased by 20% for the test or short time conditions; and the basic allowable stresses in creased by 33 1/3% when combined with wind or earthquake. CORROSION ALLOWANCE & THK. OF PIPE The allowance for corrosion or erosion in piping shall be determined by the intended service and material of construction. This shall be added to all surfaces exposed to the flowing medium. In general, beyond that inherent in the thickness of the pipe selected, a minimum allowance of 1.3 mm (0.05 inches) shall be provided for carbon steel in process service and no allowance provided for carbon steel in utility service or for alloy steel and non-ferrous materials. For threaded or grooved pipe the greater of either the corrosion allowance or the threading or grooving allowance, shall be added to the pipe wall thickness. The corrosion allowance may be more than the above based on severity of service. SIZING OF PIPING Piping shall be sized on the basis of the operating conditions and, when required, with an allowance for normal control of approximately 25% of the design friction losses in pipe and equipment, except for the following. a. Pump, compressor, and blower piping shall be sized on the basis of maximum pump, compressor, and blower design capacities (at the equipment normal design speeds) with allowance for control reduced, to zero if necessary. b. Circulating fuel oil systems shall be sized to supply 125% of the specified equipment design requirements with 25% being recirculated. c. Piping in intermittent service (such as starting- up and bypass lines) shall be sized on the basis of the available pressure differentials. d. Inlet and outlet piping at pressure-relieving safety devices shall be sized in accordance with the requirements of 2.6.0. Gravity flow oil-water sewers shall be sized to carry all normally flowing streams plus the maximum rainfall in one hour when running at three PAGE 2 OF 11 2.5.3 2.5.4 2.6.0 2.6.1 - quarters depth of flow or to carry all normally flowing streams plus the maximum expected fire water in the area, with an upper limit of 2840 litres (750 gpm), when running full, whichever results in the larger line size. Sanitary sewers and chemical sewers shall be sized to carry the design quantity when running at three-quarter depth of flow. The minimum nominal size of underground sewer mains shall be 100 NB (4 inches). OVER PRESSURE PROTECTION Over pressure protection (relief valves, safety valves, rupture discs, open vents, and design for maximum pressure) shall be provided for pressure equipment (pressure systems when units are connected without intervening block valves) as outlined in the following paragraphs. These provide the protection required by API RP520 though it is not followed in detail. a. Vessels and heat exchangers shall be protected in accordance with Table 1 when pressures greater than the stamped maximum allowable working pressure of the equipment may be produced by the causes indicated. b. Pumps, compressors, and blowers shall be protected with relief valves or other automatic shut down devices when pressures greater than the casing design pressure may be produced at normal equipment design speeds. c. Steam ends of reciprocating pumps and steam turbines shall be provided with relief valves when the casing design pressure may be exceeded. d. Piping systems shall be protected when pressures may be produced which are greater than 133 1/3% of line equipment (separators, etc.) design pressures or more than 133 1/3% of the service rating of fittings, valves, etc., or when the pressure stress in the pipe may exceed 133 1/3% of the basic allowable stress. e. Vacuum exhaust systems shall be provided with atmospheric relief valves when the system may be over pressured during a loss of vacuum. f. Vents shall be properly sized so that no additional protection need be provided against vacuum caused by emptying water after a hydrostatic test or condensing steam after steaming out the equipment. g. Fired furnace coils shall not be provided with separate over pressure equipment except as required for steam generators and superheaters by Section I of the ASME code. h. Pumps, compressors, blowers, and piping systems shall not be provided with over pressure protection for pressures caused by fire. i. Fixed roof atmospheric tanks shall be provided with open vents or vacuum breakers. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 2.6.3 2.7.0 2.7.1 2.7.2 2.8.0 2.8.1 2.8.2 2.8.3 2.8.4 2.9.0 2.9.1 Airfin condensers and coolers shall be protected by water fog nozzles with a remote, manually operated valve. A means shall be provided for remotely shutting off fan motors. Relief valves may be of the conventional, back pressure, or spring pilot operated type. Relief valves, safety valves, rupture discs and vents shall be sized in accordance with the following. a. For vessels and heat exchangers, the initial and maximum relieving pressures of relief and safety valves and the relieving pressure of rupture discs shall be as specified in Table 1. Values are given as functions of the equipment maximum allowable working pressure, P, stamped on the vessel. b. For pumps, compressors, turbines, and blowers, the initial and maximum relieving pressures shall not exceed the values recommeded by the manufacturer. c. For piping the maximum relieving pressure shall be as determined from 2.6.1.d. with the initial relieving pressure 90% of this value. d. It is mandatory that the nominal size of the inlet and oulet piping be same as, or greater than, the nominal size of the pressure relief valve inlet and outlet connection. Refer Table I and Notes - Page 11 of 11. SUPPORTS Piping sections requiring frequent dismantling such as for removal of burners, etc., shall be provided with permanent supports for the dismantled condition. All piping with insulation, and piping operating at temperatures 343 deg.C (650 F) and higher shall have steel shoes with bearing surfaces outside the insulation. Insulated piping in low temperature service shall have the insulation locally reinforced at the point of support. All other piping may rest directly on the supporting members. Small diameter lines may be supported by, or suspended from larger diameter lines. CLEARANCES The clear headroom over platforms, walkways, passage ways, and working areas shall be at least 2 metres. The clear headroom over outside areas designated for use as truckways shall be at least 3.6 metres. Clear headroom over pump access roads shall be at least 3 metres. The clear headroom over railroads as measured from the top of rails shall be at least 6.7 metres. Walkways shall be at least 750 mm. ARRANGEMENT OF PIPING When located below grade, piping provided with protective heating and piping in acid, caustic, phenol, and similar services requiring inspection and servicing shall be in trenches; other piping shall be buried in earth with at least 300 mm PAGE 3 OF 11 j. 2.6.2 03ES001 / 10 PIPING DESIGN 2.9.2 2.9.3 2.9.4 coverage except that trenches may be used at changes in direction to provide for thermal expansion of hot lines. The center line of underground water lines shall be located below the frost line or furnished with other means to prevent freezing. Minimum cover for water pipelines not in trenches is 900 mm. Burner fuel piping shall conform to the following requirements. a. Valves used to adjust the flame shall be located at the side of low floor - fired furnaces convenient to peep holes, and adja cent to the burners of elevated floor fired furnaces and wall- fired furnaces. b. Fuel oil supply piping shall be arranged as a circulating system for continuous recirculation through the headers. c. Fuel gas supply piping shall be arranged to produce equal distribution of flow to allow condensate drainage. Relief and safety valves shall discharge to a closed system when the valves release lethal vapors, mixtures of hydrocarbon vapors and other vapors (such as steam) with a molecular weight of the mixture greater than 80, or lethal, hazardous, or hydrocarbon liquids; and to atmosphere when they release mixtures of hydro carbon vapors and other vapors (such as steam) with a molecular weight of the mixture of 80 or less, non-hazardous liquids, or non-hazardous vapors. Bonnet vents of back pressure type relief valves may discharge to atmosphere. a. Lethal vapors or liquids shall be defined as poisonous gases or liquids of such a nature that a very small amount of the gas or of the vapor of the liquid mixed or unmixed with air is dangerous to life when inhaled. It is the intent of this specification that the following are not lethal: chlorine, ammonia, natural or manufactured gas, any liquefied petroleum gas (propane, butane, butadiene, etc.), and vapors of any other petroleum products. This corresponds to the definition contained in Paragraph UW-2 of the ASME Code, Section VIII. Relief and safety valve piping shall conform to the following requirements: a. All relief and safety valves on towers shall preferably be located in the overhead line. b. Relief and safety valves discharging vapor to the atmosphere in hydrocarbon service shall have the outlet piping extend to at least 3 metres above the highest working level or building roof within a radius of 12 metres. The requirements of the local pollution control board shall be followed if its more stringent. c. Relief valve header shall not be pocketed. Wherever this requirement cannot be met, a drain line discharging to a knockout pot shall be provided, with the vent from knockout pot connected back to the header. d. There shall be no isolation valves on the inlet lines to pressure safety devices. Isolation valves if provided at inlet lines to pressure safety devices shall be locked open. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 03ES001 / 10 PIPING DESIGN 2.10.0 MAINTENANCE & OPERATION REQUIREMENTS 2.10.1 Means shall be provided in the piping at pump and driver nozzles to permit the removal of the pump or driver without removing the block valves. For this purpose, a flanged valve, fitting, or strainer against the nozzle shall be considered satisfactory. 2.10.2 Piping requiring removal of coke shall be provided with flanged clean out points and bends of a radius suitable for the cleaning tool or with flanged fittings at turns. The run of pipe between clean out points shall be limited as follows. a. Straight runs: Cleaning from one end - 12 metres. Cleaning from both ends - 24 metres. b. Bends: Cleaning from both ends - 12 metres developed length. 2.10.3 All piping equipment requiring frequent attention of the operating personnel shall be readily accessible. Equipment such as automatic control valves preferably shall be grouped at main operating levels. Equipment such as motor operated valves and relief valves shall be accessible from platforms or grade. a. Man ua lly op erat ed val ves requiring manipulation during operation or an emergency shall be located so that hand wheels are convenient to operate from a platform or grade and so that the bottom of the hand wheel is not higher than 2 metres above a platform or grade, otherwise such valves shall be equipped with chain operators or exten sion ste ms. Valves with ch ain operators shall be located or have stems turned so that chains do not hang in passageways. 2.10.4 Driver steam exhaust lines shall be provided with exhaust heads when discharging to the atmosphere. 2.10.5 Funnels and drain lines shall be provided at sampling connections, gauge glasses, level controllers, etc.. 2.10.6 Access shall be provided for heat exchanger tube removal, tower tray removal, catalyst removal and for crane access to compressors. 2.11.0 VALVING 2.11.1 Block valves shall not be provided at vessel nozzles, except as required for operating and process control and for storage vessels containing hazardous or toxic materials. 2.11.2 Block valves shall be provided on the water side of exchanger units as follows: a. Exchangers that are essential for the operation of the unit shall have one valve. b. Exchangers provided with process isolation valves for frequent inspection and cleaning during operation of the unit shall be provided with block valves in the inlet and outlet piping. All water cooled exchangers will have isolating valves on the inlet and PAGE 4 OF 11 outlet water lines. In freezing climates, an antifreeze bypass from the inlet to the outlet piping or other means to prevent freezing shall be furnished. 2.11.3 Block valves shall be provided at the following locations in pump, turbine, and compressor piping. a. In suction and discharge piping to pumps. b. At the equipment in auxiliary piping for gland oil, flushing oil, and cooling water. c. At the header in overhead water supply branches located outdoors in freezing climates and in all auxiliary piping when necessary to allow removal of the equipment during operation of the unit. 2.11.4 Block valves shall be provided at the following locations in steam piping. a. At the steam main: In steam headers serving grouped equipment such as steam drivers located in a pump room. b. At the equipment: In steam piping to steam driven equipment. c. At the steam header: In steam piping to steam driven equipment when the steam pressure exceeds 21 kg/sq.cm g.(300 psig) d. At the equipment: In pressure exhaust steam piping from steam driven equipment. e. Adjacent to the equipment: In vacuum exhaust steam piping from steam driven equipment when the equipment may be shut down for sustained periods during operation of the unit. 2.11.5 Arrangements for block valves at spare equipment that is to be isolated for maintenance and equipment that may be removed from service during the operation of the unit shall conform to the following. a. In chemical and other process liquid services, single block valves shall be used for all pressure temperature ratings up to and including 600 # ANSI. In services of higher ratings, double block valves shall be considered for each individual case. b. In gas or vapor services block valves shall be as indicated in the following table. Pressure Temperature Valve size Selection o Upto 300 NB Single Gate Valve 350 NB and above Single Plug Valve All sizes Single Gate Valve All sizes Single Plug Valve All sizes Double Gate Valve 232 C o Upto and ( 450 F) and including below 300 psig ( 212 kg/cm g ) o Above 232 C ( 450 oF) 232oC ( 450 oF) and Above below 300 psig ( 21 o kg/cm2g ) Above 232 C ( 450 oF) 2.11.6 A block valve shall be provided for the fire steam system. Other utility systems shall be provided with valves at service connections only. 2.11.7 Block valves shall be provided and located as required for bleed and aeration systems. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 03ES001 / 10 PIPING DESIGN PAGE 5 OF 11 2.11.8 A block valve shall be provided in the main line of fuel oil and fuel gas piping to furnaces or fired heaters, be located remote from the equipment, and be accessible for rapid operation in an emergency. 2.11.9 Block valves shall be provided for piping crossing the unit limits as follows. a. In outgoing lines only when required to divert product streams. b. In all steam lines except exhaust steam lines. 2.11.10 Automatic control valves shall be furnished with either block valves for isolating the control valve and a bypass for hand control, the sizes of which shall conform to Table given below,or an auxiliary means for manual operation. Control Valve Size Line Size By-Pass & Block Valve Size 50 NB and smaller 50 NB and smaller Line size 50 NB and smaller 65 NB and larger 50 mm 65 NB and larger 65 NB and larger Control valve size a. All three-way control valves shall be furnished with an auxiliary means for manual operation. b. Control valves in lethal, phenol, and ethanolamine services shall be furnished only with block valves located adjacent to the control valves and an auxiliary means of manual operation. c. Control valves in services containing abrasive solids or viscous material (viscosity at ambient temperature so high that one-half the design flow rate cannot be attained with the pressure available for starting circulation), boiler feed water services, services with a pressure drop across the control valve greater than 14 kg/sq.cm (200 psi), and steam services with a pressure of 5 kg/sq.cm (75 psig) or higher shall be furnished with block and bypass valves except that when control valves are paired (separate control valves furnished for drivers and their standbys) neither block and bypass valves nor auxiliary means of manual operation shall be furnished. d. When the pressure drop across the control valve is over 70 kg/sq.cm (1000 psi) two by-pass valves in series shall be furnished. 2.11.11 Two block valves with a bleeder shall be provided in piping connecting systems in services in which contamination cannot be tolerated. 2.11.12 Two valves shall be provided in connections used during operation for venting, draining, or sampling in liquid hydrocarbon services with a vapor pressure over 4.5 kg/ sq cm-a (65 psia) at 37 deg.C (100 F) for venting or draining in all services with an ANSI rating of 900 # or higher; and for sampling in all services with an ANSI rating of 400 # or higher. 2.11.13 Block valves shall generally be gate valves except as follows. a. Lubricated plug valves shall be used in vacuum and caustic services and in fuel gas piping except burner leads and may be used in gas compressor services and services with an ANSI rating of 600 # and over. b. Non-lubricated mechanical lift plug valves shall generally be used in services containing abrasive solids in a gas or liquid. Branch line block valves, however, shall be of the type required for the branch line service. c. Non-lubricated plug valves shall be used at service air hose connections. d. Globe valves shall be used in furnace blowdown lines, for venting and sampling connections in caustic services and may be used in services with an ANSI rating of 2500 #. e. Butterfly type valves with resilient seats may be used in water services. 2.11.14 Check valves shall be provided for the common discharge of centrifugal and rotary pumps and centrifugal compressors when the pumps or compressors discharge into a system whose pressure or volume is likely to cause backward rotation of the pump or compressor. 2.11.15 Check valves shall be provided in process steam and steaming out services connected to process equipment or lines when such services are subject to contamination from the process equipment or lines. The check valve shall be located between the block valves required by Section II, Part M, Paragraph 11 and adjacent to the valve nearest the process equipment or line. 2.11.16 Hand control valves shall generally be of the type specified in Table below with the following exemptions. a. Globe valves shall be used for all sizes when the operation pressure differential across the valve is greater than 35 kg/sq cm (500 psi). b. Angle type globe valves shall be used for all ratings and sizes in slurry services. c. Gate valves shall be used in services containing abrasive solids in a gas. d. Non-lubricated reducing port plug valves shall be used for regulating fuel oil to burners, gate valves for fuel gas. Valve size NB 150#, 300#, 400# & 600# 900# 1500# & 2500# 150 & larger Gate Gate Gate 100 & larger Globe Gate Gate 80 & larger Globe Globe Gate 65 & smaller Globe Globe Globe 2.11.17 The following flanged and butt welded valves 65 NB and larger shall be bossed, if required, and drilled, tapped and plugged at the locations indicated, in accordance with MSS SP-45, latest revision. a. In water and steam service, all gate valves FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 03ES001 / 10 PIPING DESIGN PAGE 6 OF 11 at locations “A” and “G” and all globe valves at location “C”. b. In services containing abrasive solids, in a gas all gate valves at locations “G” and “H”. c. All ball check valves above the seat and all swing check valves at location “G”. 2.11.18 Steel valves shall have the following construction. a. Flanged and butt welded valves of the gate, globe, and angle type shall have bolted bonnets and glands, and of the check type, bolted bonnets. Threaded and socket welded valves of the gate, globe, and angle type shall have gasketed union bonnets and bolted glands, and of the check type, gasketed union bonnets. Pressure sealed, welded or integral bonnet for threaded and socket welded gate, globe and angle valves may be used for corrosive or high pressure services. b. Gate, globe and angle valves shall be of the outside screw and yoke type. c. Gate valves shall be provided with pressure equalizing by-passes and by-pass valves of the minimum sizes and ratings listed in Table below when a differential pressure approximately equal to the pressure rating of the valve may exist across the closed valve (eg. 600 lb across a 600 lb valve). By-pass and By-pass Valve Size, NB GateValve Size NB 150# 300# 400# 600# 100 - - - - 15 15 15 150 - - - 20 20 20 20 200 - - 20 20 20 20 20 250 - 25 25 25 25 25 25 300 25 25 25 25 25 25 25 350 25 25 25 25 25 25 () 400 25 25 25 25 25 () () 450 25 25 25 25 25 () () 500 25 25 25 25 () () () 600 25 25 25 25 () () () Gate and By-pass Valve Pressure Rating 900# 1500# 2500# d. Globe and angle valves shall be selected for the required sensitivity of control. Specially designed plugs may be used when the operating differential pressure is greater than 35 kg/sq.cm (500 psi). Geared operators shall be furnished for the valves listed in Table below. ANSI Rating Valve size 150# 300 NB and over 300# 200 NB and over 400# & 600# 150 NB and over 900 # 100 NB and over 1500# & 2500# 80 NB and over e. Threaded and socket welded check valves shall be of the ball type. Flanged and butt welded check valves shall be of the swing -non-slam type in sizes 350 NB and over and of the swing type in sizes 300 NB and under except that valves with ANSI ratings of 900 and 1500 # shall be of the ball type in sizes 100 NB and under. f. Lubricated plug valves shall be wrench operated in the sizes listed and gear operated in larger sizes. 125 # ANSI - 250 NB size and smaller 150, 250 and 300 # ANSI - 200 NB size and smaller 400 to 1500 # ANSI - 100 NB size and smaller 2500 lb ANSI - 50 NB size and smaller Such valves shall be fitted with giant button-head lubrication. g. Non-lubricated mechanical lift plug valves for use in services described in Section II, Part M, Paragraph 13 b. shall be of the single operation mechanical lift type, designed to permit sealing the plug and blowing or flushing the seat. Such valves shall be wrench operated in sizes 150 NB and smaller and gear operated in sizes 200 NB and larger except that for chain operation, valves in sizes 150 NB and larger shall be gear operated. h. Control valves shall have flanged or threaded end connections. i. Gate valves in the 150 # and 300 # ANSI ratings may be reduced port. 2.11.19 Cast iron valves shall have the same construction as steel valves except as follows. a. Flanged gate valves used in buried lines shall be of the inside screw non-rising stem type. b. Threaded gate valves shall have a clamp type bonnet and be of the inside screw non-rising stem type. c. Threaded check valves shall have a threaded bonnet and be of the swing type. 2.11.20 Bronze and brass valves shall have threaded end connec tions. Gate, globe and angle valves shall be of the inside screw rising stem type, check valves shall be of the swing type. Plug valves shall be manufacturer’s standard. 2.12.0 PIPES AND BENDS 2.12.1 In general, for all except alloy steel pipe, seamless and fusion welded pipe shall be used. Welded pipe may be used for services with an ANSI rating of 300 # or less, and for utility services with a temperature of 175 deg.C (350 F) or less. For alloy steel pipe, only seamless shall be used. 2.12.2 Pipe, in sizes 32 NB, 65 NB and 125 NB shall not be used. 2.12.3 Changes in direction shall be made with fittings preferably or bends. Bends shall be used for u nlined pipe conveying abrasive solids suspended in gas or liquid. a. One weld miter elbows: atmospheric air FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 03ES001 / 10 PIPING DESIGN co mp re ss or i nt a ke l in es whe n f low straightening vanes are used. Vent lines from compressor and sewer lines. b. Two weld/ three weld miter elbows: process lines larger than 600 NB in diameter with an ANSI rating of 125, 150 or 250 # and all utility (water, steam, air, etc.) and auxiliary (vent, flare, etc.) lines. c. Four weld miter elbows: process lines larger than 600 NB in diameter with an ANSI rating of 300 # and over and internally lined pipe conveying abrasive solids in gas or liquid. 2.12.4 The minimum radius for pipe bends shall be 5 times the nominal pipe size for upto 350 NB inclusive and 6 times the nominal pipe size for pipe over 350 NB size. When bends are required with smaller radius or of any radius in pipe operating at temperatures above 400 deg.C (700 F), the possible thinning in the wall of the outer periphery due to bending shall be taken into account. 2.12.5 Equal size 90 degree intersections, except in low pressure utility piping (ANSI rating of 250 # or less and temperature of 232 deg.C less (450 F)) shall be made with tee fittings. In general, all other intersections and all intersections in low pressure utility piping shall be made by welding. When reinforcement is required for branches, branch welding fittings may be used. 2.13.0 FITTINGS END CONNECTIONS, FLANGE FACINGS AND GASKETS 2.13.1 Fittings and end connections in carbon and alloy steel piping shall be as follows: a. In austenitic steel pipe at service temperatures over 400 deg.C (750 F) butt welded or flanged for sizes 25 NB and larger. Socket welded or threaded in smaller sizes. b. In galvanized steel pipe - flanged in sizes 150NB and larger, threaded in smaller sizes. c. In all other services - butt welded or flanged for sizes 50 NB and larger, threaded or socket welded in 40 NB and smaller. 2.13.2 Threaded connections shall be made up with Teflon taped threads when the temperature is 260 deg.C (500 F) and below. Threaded connections shall be seal welded when the temperature is above 260 deg.C (550 F). When so required in vent, drain, or sample piping discharging to an open system or in instrument leads, seal welding shall be done only to the upstream side of the first block valve. 2.13.3 Except for removable sections of pipe, erection requirements, and piping requiring dismantling for clean ing, the use of flanges in piping shall be limited to connections at flanged equipment. 2.13.4 Raise faced flange shall be used for ANSI ratings of 900 # and below and ring joint flanges for process services with ANSI ratings of 1500 # and higher. All steam systems with ANSI ratings of 150 to 2500 # shall have raised face flanges when flanges are used. 2.13.5 Gaskets for ring joint flanges shall be of the octagonal type. PAGE 7 OF 11 2.14.0 BLANKS 2.14.1 Blanks shall be provided in the piping at the following locations only. a. At inlet and outlet connections of equipment, other than pumps, compressors, and blowers, which must be periodically taken out of service for maintenance, inspection, or alternate operation without interfering with the operation of the unit and when the omission of such blanks would present a hazard to personnel. b. In furnace piping at locations which will permit the simultaneous testing of the furnace and as much of the piping as may be sub ject to the test pressure. c. At the unit limits in utility piping conveying hydrocarbons and in process piping connected to other plant piping which may be in use during a shut down of the unit. 2.14.2 The selection of the type of blank shall be in accord ance with Table VI and the following subparagraph: a. Blanks for piping in service at temperatures below -18 deg C (zero degrees F) shall be of the circular type with spades for rigid connections and without spacers for flexible connections. Nominal size of pipe (NB) Rigidity of connection Rigid Flexible 100 and smaller Figure 8 Circular without spacer 150 and 300 incl. Figure 8 Figure 8 Larger than 300 NB Circular with spacer Circular with spacer 2.14.3 Circular type blanks and spacers shall be provided with attach ments for handling. 2.15.0 UTILITY OUTLETS 2.15.1 Utility steam, air, and water service outlets of 25NB minimum size for hose and fittings shall be provided as required at such locations that working areas at grade, in structures, and in buildings can be reached with 15000 mm length of hose. a. The steam supply to hose connections shall be limited to a pressure of 8.75 kg/sq.cm g (125 psig). b. Service outlets for water shall be located at grade for furnaces and at grade and the lowest main operating level in structures. c. Hose and fittings will not be furnished. 2.16.0 VENTS, DRAINS AND SAMPLE OUTLETS 2.16.1 Valved vent and drain connections shall be furnished on all equipment not self venting or self draining. Connections shall be located on equipment if practicable but may be located in connected piping when there are no valves or blocks between the vent or drain connections and the equipment. Vents and drains for pumps in services containing abrasive solids shall be located in connected piping. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION PIPING DESIGN PAGE 8 OF 11 2.16.2 Valved vent connections shall be furnished for trapped high points of piping 65 NB and larger except that when the connection is used for test purposes only, the valve shall be omitted and a plug substituted. Valved drain connections shall be furnished for the low points of lines located above grade. 2.16.3 Vent connections shall be 20 NB minimum size drain connections and sample outlet connections shall be 20 NB minimum size, except as follows. a. All piping connections from equipment shall be the equipment connection size. b. All connections from piping in services involving abrasive fluids or materials which are of high viscosity when cold shall be 25 NB minimum size. 2.16.4 Vent and drain connections from vessels shall be at least the sizes given in Table given below. Volume of Vessel (liters) 03ES001 / 10 Nominal size of vents and drains (NB) Vents Drains 1400 and smaller 25 25 1400 to 5650 25 40 5650 to 17000 25 50 17000 to 70800 40 80 over 70800 50 80 2.16.5 All single valved vents and drains in process services only shall be provided with plugs or blind flanges except for the following. a. Casing vents and drains for pumps in nonvolatile services shall be piped to the pump base plate or into a gutter or sewer. b. Casing vents for pumps in services handling materials near the auto-ignition point shall be piped to a cooler and from the cooler to a sewer. 2.16.6 Vent and drain connections used during operation in fuel gas supply piping and in services with a vapor pressure over 4.5 kg/sq.cm-g (65 psig) at 37 deg.C (100 F) shall discharge to a closed system or to a sealed and vented sewer inlet. 2.16.7 Sample outlets in piping or equipment in hot services shall be provided with means for cooling the sample. One cooler may be used for grouped sample outlets. 2.16.8 Means shall be provided for clearing sampling lines and coolers with steam in services involving materials which are of high viscosity when cold and in all services when grouped sample outlets use the same cooler. 2.17.0 EMPTYING, STEAMING OUT AND WATER FILLING 2.17.1 Means shall be available for removing the operating liquid contents from all vessels and heat exchange units and the connected piping. Process lines and pumps shall be used for this purpose as far as practicable; or steam or other medium shall be used to remove the liquid by pressure; otherwise, an auxiliary pumping out system shall be provided. 2.17.2 Connections for emptying vessels shall be at least the drain sizes given in table 2.16.4: and on heat exchanger units they shall be 40NB when provided. 2.17.3 When required by the service, means shall be available for purging process equipment with steam or inert gas. Unless steam or inert gas is otherwise available, the following provisions shall be made: a. Vessels of volume from 2832 to 141600 liters (100 to 500 cu.ft.) and all sizes of vessels of low temperature service, shall be provided with a 25NB connection to which a steam hose may be at tached. Other vessels of volume greater than 141600 liters (5000 cu.ft.) shall be serviced by a 40 NB line connected to a source of steam. b. Furnace coils shall be serviced by piping permanently connected to each coil inlet line and to a source of steam. 2.17.4 When required by the service, means shall be available for filling process equipment with water for washing out. a. Vessels requiring frequent maintenance shall be serviced by piping permanently connected to a source of water. b. Vessels not requiring frequent maintenance shall be serviced by hose connected between a service water outlet and the vessel drain connection. 2.18.0 FIRE, SMOTHERING, SERVICE, SNUFFING AND PROTECTIVE HEATING SYSTEM 2.18.1 Smothering system shall be provided to furnace combustion chambers, header boxes, and to the spaces above the furnace arch and shall be controlled by valves remote from the furnace area. 2.18.2 Smothering steam shall be provided to enclosed rooms housing pumps or compressors in flammable liquid or gas service and shall be controlled from outside the building. a. Flammable liquids shall be defined as liquids having a flash point below 93 deg.C (200 F) as determined by ASTM D56-70 or D93- 66. b. Flammable vapors shall be defined as vaporized flammable liquids with molecular weights greater than 80. 2.18.3 Snuffing steam shall be provided to relief valve outlet piping discharging hydrocarbon vapors to the atmosphere and shall be controlled from grade. 2.18.4 The steam supply for fire smothering, fire fighting, snuffing, service hoses and protective heating shall be from a separate steam system connected to the plant steam header on the supply side of the unit limit block valve. a. A separate fire steam header shall not be required if steam is normally available at a pressure 3.5 and 8.75 kg/ sq.cm-g (50 and 125 psig) in the plant steam system. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 03ES001 / 10 PIPING DESIGN 2.19.0 STEAM TRAPS AND SEPARATORS 2.19.1 Steam traps shall be provided for the removal of condensate from collection points in steam system. 2.19.2 Steam traps discharging to the atmosphere shall be provided with upstream block valves. Steam traps discharging to a condensate collecting system shall be provided with upstream block valves and downstream block valves except that steam traps for unit heaters shall be provided with downstream block valves only. 2.19.3 Condensate from vacuum steam systems shall be re-evaporated into the system by means of a condensate flash pot. 2.19.4 A steam separator shall be provided in the steam piping to each group of steam turbines and to each group of steam driven reciprocating compressors. 2.19.5 Drip legs shall be provided on steam headers for collecting condensate. 2.20.0 STRAINERS AND FILTERS 2.20.1 Permanent strainers shall be provided in the piping for the protection of the following equipment when not furnished as part of the equipment. a. All pumps - in suction line. b. Steam turbines and steam jet ejectors - in steam inlet line. c. Pumps and compressors - in sealing, gland, and flushing oil and cooling water supply piping. d. Reciprocating compressors taking suction from process equipment in suction line. e. Burners - in main fuel oil supply piping. f. Hydraulically actuated equipment - in hydraulic oil supply piping. g. Pneumatically actuated equipment - in air supply piping. h. Restriction orifices in bleed gas or air service - in gas or air piping. 2.20.2 In addition to permanent strainers, temporary strainers with a mesh finer than the permanent strainer mesh shall be placed over the permanent strainers, for use in preliminary operation in the suction piping to all pumps. 2.20.3 Reciprocating compressors taking suction from process equipment shall be furnished with temporary strainers. 2.20.4 A filter shall be provided in the air piping upstream of air driers. 2.20.5 Screened intakes shall be provided for air compressors and air blowers. 2.21.0 SEWERS 2.21.1 An underground oil water sewer system shall be provided to collect and convey all oil drainage, waste water, and storm water from paved areas to the unit limits. Sewers, if required for raw sanitary and chemical waste, shall be run separately to the unit limits. Treated chemical and sanitary waste may be conveyed through the oil water sewer system. PAGE 9 OF 11 2.21.2 The oil water sewer system shall conform to the following: a. Paved areas at grade, the bottoms of trenches, and the floors of pumps or compressor rooms shall be provided with drains for the collection of surface drainage except that drains shall not be furnished for concrete floors of elevated open sided com pressor rooms. The floors of control rooms, switch rooms and lavatories shall not be provided with drains. Drains located within enclosed buildings shall be provided with drain fittings of the sealed type. b. All equipment such as pumps, compressors, and vessels shall be provided with sewer inlet receptacles as required.. c. Roof areas upon which process equipment is located shall be connected to the sewer system through the down spouts. d. Sewers discharging from seperately defined areas such as pump rooms, furnaces, and grouped equipment shall connect to the system through sewer boxes having sealed inlets. When it is not prac ticable to connect trench drains individually to sewer boxes, such drains shall be sealed by means of “P” traps. Sewer boxes in hazardous areas, such as around furnaces, shall have sealed covers and be vented to a safe location. 2.22.0 EMERGENCY FIXTURES 2.22.1 Eye wash fountains and emergency showers shall be provided near equipment or pipe manifolds in acid, caustic, phenol service and any other lethal service.The fixtures shall be installed at locations conveniently accessible for emergency use. Emergency showers shall be arranged for overhead delivery of water spray. 2.22.2 Water for eye washing fountains and emergency showers shall be taken from the drinking water system. Self closing valves shall be used. 2.22.3 Eye washing fountains & emergency shower heads shall be as per the relevant IS codes only 3.0.0 MATERIALS 3.1.0 3.1.1 GENERAL The selection of materials for a given piping system shall be based on the fluid conveyed and the design temperature and pressure. The materials of special elements, such as steam traps and separators shall conform to the manufacturer’s standards for the operat ing conditions. The material and corrosion allowance for a particular service will be specified in the design data sheets. Low temperature piping (design metal temperatures below -28.9 deg.C (-20 F) shall have materials for pressure containing parts in accordance with the applicable code. Materials for non- pressure parts shall be as follows. a. Structural attachments which are welded directly to any pressure part and which normally will be subject to dynamic loads while the pipe is at operating temperature such as vacuum stiffener rings, pipe supports, 3.1.2 FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION PIPING DESIGN guides, anchors, platform and ladder clips. b. Structural attachments which are welded directly to any pressure part but which are not normally subject to dynamic loads while the pipe is at operating temperature such as davit clips,. lifting lugs, Nelson studs, insulation clips and rings, etc.. mild carbon steel (not impact tested) for piping of carbon or ferrite alloy steel and AISI Type 304 steel for piping of austentitic alloy steel. Valve body materials shall be steel conforming to the relevant codes / manufacturer’s standards for the valve type and pressure ratings except as follows. Generally all valves 40 NB and below shall be forged and 50 NB and above shall be of cast material. a. For water and low pressure air service, cast iron and bronze or brass shall be used. b. For low pressure steam, cast iron may be used but not within 7.5 metres of furnaces. Bronze and brass shall not be used. c. For corrosive and high temperature service, the material will be comparable to that indicated on the Design Specification Summary Sheet. Valve body material may be ductile iron in 150 # and 300 # ANSI ratings. However, ductile iron shall not be used in compressor piping. Valve trim material shall be as per code or as per the manufac turer’s standards for the service conditions. Bolting and gasket materials shall conform to the relevant code/ IS/ ASTM standards. In selecting materials the following are special considerations. a. When piping systems or equipment are inter- connected by a valve, the valve shall be suitable for the services connected. However should the particular service require the use of alloy valves because of high temperature or corrosion, the block valve located in connected piping which normally is deadened or in which the service temperature is lower may be of carbon steel of the required pressure rating if suitable. b. When a change in pressure or temperature occurs at equipment such as a control valve, a heat exchanger unit, or a trap, the up stream block valve and the by-pass valve (if any) shall be suitable for the u p s t r e a m co n d i t i o n s wh e r e a s t h e downstream block valve need be suitable for the downstream design conditions only. All steel pipe and fittings 100 NB and under for drinking water service and air transmission service to air motor operated valves shall be galvanized. 3.1.3 3.1.4 3.1.5 3.1.6 3.1.7 3.1.8 4.0.0 FABRICATION, HEAT TREATING, INSPECTION AND PRESSURE TESTING 4.1.0 Fabrication, heat treating, inspection and pressure testing shall be as per the specification for Fabrication And Installation of Steel Piping 25ES205. FACT ENGINEERING AND DESIGN ORGANISATION 03ES001 / 10 PAGE 10 OF 11 ENGINEERING SPECIFICATION 03ES001 / 10 PIPING DESIGN PAGE 11 OF 11 TABLE 1 FOR CLAUSE 2.6.0 - OVER PRESSURE PROTECTION FOR EQUIPMENT EQUIPMENT SELECTED Towers, Drums & Kettle Type Evaporators CAUSE OF OVER PRESSURE (NOTE 1) PROTECTIVE DEVICE Open Inlet (Control valve opens wide) Closed Outlet Failure of Cooling Medium Top or Side Stream Reflux Failure Lean Oil Failure to Absorber Failure of Tower Pressure Controller in the Closed Position Driver Electric Failure Steam Power Failure Chemical Reactions Exclusive of Explosions Relief Valve or Safety Valve or Rupture Disc RELIEVINGPRESSURE Initial Maximum 1.00 P 1.10 P External fire (Note 2) Heat Exchanger (Shell & Single Type) 1.20P Thermal Expansion of Liquid when closure of a Single Valve isolates contents or if exchanger can be dispensed with or is spared. Relief Valve ( Min size ) Light hydrocarbon service-blocked inlet & outlet when the pressure exceeds the Design Pressure Safety Valve ( Min size ) External Fire ( Channel Side) Safety Relief Valve ( Min size except when dealing with large exchangers) External Fire ( Shell Side ) 1.00 P 1.20 P Safety Relief Valve or Safety Valve Heat Exchangers Relief Valve or Ruptured Tube ( Note 3 ) Safety Relief Open Inlet (Contro Valve opens wide) Valve or Rupture Closed Outlet Disc Exchangers (Double Pipe ) Thermal Expansion of Liquid when closure of a single valve isolates contents or if Exchanger can be dispensed with or is spared. Relief Valve (Min. Size) 1.10 P 1.00 P P - Maximum available working pressure ( MAWP ) of equipment NOTES: 1. Each cause of overpressure shall be considered individ ually. 2. The heat input shall be calculated in accordance with the formula 0.82 Q= —— FA 21000 3. In which Q = the total heat input to the wetted surface in Btu per hour F = 1.0 for uninsulated vessels and 0.3 for insulated vessels. A = the total wetted surface exposed to fire in square feet. The surfaces of vessels or heat exchangers up to 25 ft. above grade or other fire supporting level shall be considered subject to fire expo sure. Area of rupture assumed equal to the flow area of two tubes. Relieving device will not be required when sufficient quantities of material can be discharged through the low pressure connecting system (with block valves assumed thro’ open) to prevent an overpressure of more than 1.10 P. FACT ENGINEERING AND DESIGN ORGANISATION iso1.sty ENGINEERING SPECIFICATION PIPING TURNKEY PACKAGE PAGE 1 OF 2 and forwarding. e. Insulation of all insulated lines and Painting of all uninsulated CS / AS pipes and ducts shall be as per specification attached. Color coding shall be as per FEDO color coding. f. All piping items covered by Indian Boiler Regulations (IBR) shall be supplied along with IBR certificate g. Any other work related to the completion of the Package. h. All items included in the vendor’s scope may be subjected to inspection by FEDO / Client. The items are to be cleared by the designated inspector before dispatch. i All piping larger than 50 NB shall be prefabricated. Pipes smaller than 50 NB shall be delivered in commercial lengths, properly marked with type and material. 10% excess pipe shall be supplied for all sizes and materials. j. All vents shall be at a safe location and shall include necessary supports. CONTENTS 1.0.0 2.0.0 3.0.0 4.0.0 5.0.0 SCOPE DESIGN CONSIDERATIONS BATTERY LIMITS FOR PIPING DETAILS OF DRAWINGS/ DOCUMENTS GENERAL ———————————— 1.0.0 SCOPE 1.1.0 1.1.1 GENERAL The scope of work includes but is not limited to basic design, detailed engineering, supply, fabrication, erection, testing, painting, insulation, commissioning and guarantee run of the Piping / Ducting on turnkey basis. The supply of hardware and engineering shall be completed as there will be no other supplier other than the vendor within the battery limit indicated. IDENTIFICATION The scope of work includes but not limited to: a. Basic engineering for the piping / ducting for the Package. b. Detailed engineering for piping/ducting within the Package. This includes preparation of plot plan, piping layouts, isometrics, support drawings, bill of materials, procurement, special instructions for storage, special instructions for identification of pipe lines and components, special instructions for erection, special instructions for testing, special instructions for pickling of oil lines if any, blowout procedure etc.. Submission of these drawings to FEDO, incorporating comments made by FEDO and obtaining necessary IBR / Statutory approvals. c. Stress Analysis of all pipe lines and ducts above 100 deg.C, all IBR lines and all lines connected with rotating equipments. These stress analysis reports shall be submitted to FEDO for review and comments. Compensators and spring supports shall be finalized and provided based on the stress analysis reports. All pipe lines shall be anchored at the Battery Limit. Nozzle loads on rotating equipments, viz, turbines, etc., shall comply to API/ NEMA codes and the reports shall be submitted to FEDO for review. d. Supply of all materials based on the piping bill of materials and any additional material required for the satisfactory completion of the system. Supply includes all materials for piping such as pipes & ducts, pipe & duct fittings, flanges, gaskets, bolts and nuts, pipe supports, valves, expansion bellows, spring supports, shut-off plates, safety valves, etc. as per approved piping layouts and P&IDs. Supply inclusive of testing, packing 1.1.2 1.2.0 1.2.1 PRPD. BY: 03ES010 / 10 CHKD. BY: 2.0.0 DESIGN CONSIDERATIONS 2.1.0 Design of all piping systems, except those listed below, shall be as per ANSI / ASME B 31.3. a. All boiler feed water and steam lines shall be as per the latest issue of IBR and ANSI / ASME B31.1. All dimensions and elevations shall be given in metric units. Flange and valve ratings shall be as per class designation in ANSI B16.5 and ANSI B16.34 respectively. 32, 65 & 125 NB pipe sizes shall not be used. Traps & strainers shall be provided wherever necessary. Normally a shut off valve shall be provided ahead of each strainer /trap. Union or flanges shall be provided for removal of traps. The clear headroom over platforms, walkways, passage ways and working areas shall be at least 2.2 m. All pipes shall have a slope of minimum 1 in 1000 and shall be provided with drain line at the lower most point. All equipment location, layout, design and general arrangements shall conform to the relevant statutory requirements. Valves shall be located where there is ease of operation and maintenance. Gear arrangement shall be provided for all valves as per clause 5.5. 2.2.0 2.3.0 2.4.0 2.5.0 2.6.0 2.7.0 2.8.0 2.9.0 3.0.0 BATTERY LIMITS FOR PIPING 3.1.0 All incoming and outgoing lines shall be terminated at the Battery Limits specified in the battery limit list attached. 4.0.0 DETAILS OF DRAWINGS/ DOCUMENTS This is only a general guide line for preparing various drawings / documents, highlighting the APPRD. BY: ISSUED ON: APR ’10 FACT ENGINEERING AND DESIGN ORGANISATION CONTROLLED COPY ISO 9001 : 2015 ENGINEERING SPECIFICATION 03ES010 / 10 PIPING TURNKEY PACKAGE PAGE 2 OF 2 minimum details to be furnished. The vendor is obliged to include any other details found to be wanting in the drawing/document, after review of the same by FEDO. 4.1.0 GENERAL LAYOUT DRAWING 4.1.1 The Layout should be of A1 size and should give the following details using the coordinate system to locate each item. a. Size Location and Point Of Support (POS) elevation of all equipments, location and size of buildings. b. Battery Limits. c. Pipe Bridge Locations. d. Sewer and Drain Details. e. Free area required around equipment / exchangers for maintenance / tube removal. f. Paved area and elevations. g. Plant North. h. The Layout shall also contain a table showing the complete list of equipments with location and point of support details. 4.2.0 PIPING LAYOUT 4.2.1. The Piping Layout shall be drawn on a scale of 3:100. The layout shall give the following details using the coordinate system to locate each equipment and line. 4.2.2. Routing of all pipelines and ducts showing all fittings, valves, strainers, springs, bellows, line Nos., direction of flow, location and elevations, pipe supports etc. 4.2.3. Nozzle schedule of all equipments giving the following details of all nozzles on each equipment. a. Size and Rating b. End Connection c. Orientation d. Elevation e. Standout f. Description 4.2.4 Separate details for lines / areas which cannot be clearly drawn on the layout. 4.2.5 All platforms on vessels and structural platforms. 4.2.6 All instruments, control valves, MOV, PSV, traps, etc. 4.2.7 Any other detail required by FEDO during review. 4.3.0 ISOMETRICS: 4.3.1 Isometrics shall be drawn for all lines irrespective of size, including isolation valves on equipments. The isometric shall include a Bill of Materials showing the complete list of materials and quantity required for fabrication and erection of the line. 4.3.2 4.3.3 4.4.0 4.4.1 4.5.0 4.5.1 4.6.0 4.6.1 4.7.0 4.7.1 The isometric drawings shall indicate the relevant line numbers, flow direction, pipe specification, insulation / painting details, stress analysis requirements, pipe supports like trunnions, line fluid conditions such as pressure, temperature, hydrotesting pressure, etc. Steam tracing isometrics: This shall be produced from the relevant isometrics with details of steam tracing incorporated. However the bill of materials will be that for the steam tracing line. PIPE SUPPORT PLAN This drawing should indicate the location and type of all supports used and should also give the pipe support detail sheet number to be referred for getting details of the support. PIPE SUPPORT DETAIL SHEETS This detail sheet should give all the data required for the fabrication and erection of a particular pipe support. LINE SCHEDULE This document should give all line numbers, the detail of connecting equipment lines, operating conditions, service and insulation details. VALVE SCHEDULE This document should furnish tag numbers, type, pressure rating, size, material of construction and service of all valves. 5.0.0 GENERAL 5.1.0 All piping items shall be procured from the attached sub vendor list of approved vendors for indigenous vendors. For any deviation, prior approval from FEDO shall be obtained before placement of order. Operating spares for valves, steam traps, strainers etc. for two years of trouble free service be included in the offer. A layout shall be included in the package for reference. Bypass, drain and vent connections for valves shall be as specified in MSS-SP 45. Geared Operators for valves shall be provided as per the following table. 5.2.0 5.3.0 5.4.0 5.5.0 ANSI Rating Valve Size 150 # 300 NB and over 300 # 200 NB and over 400 # & 600 # 150 NB and over 900 # 100 NB and over 1500 # & 2500 # 80 NB and Over ————————————————————————- FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 03ES014/15 RUBBER LINING FOR PIPES , DUCTS & PIPE FITTINGS PAGE 1 OF 14 CONTENTS : 1.0.0 2.0.0 3.0.0 4.0.0 5.0.0 6.0.0 7.0.0 8.0.0 SCOPE PIPE AND FITTINGS LINING GUIDELINES 3.1.0 METAL PREPARATION 3.2.0 CEMENTING 3.3.0 LINING THICKNESS 3.4.0 LINING MATERIAL SELECTION LINING PROCEDURE 4.1.0 PREPARATION 4.2.0 LINING PROCEDURE FOR STANDARD FLANGED PIPE 4.2.0 LINING PROCEDURE FOR LARGE DIAMETER PIPE PROTECTING RUBBER LINED PIPES 5.1.0 SOURCES FOR POTENTIAL PROBLEMS 5.2.0 MEANS FOR PROTECTION TESTING AND INSPECTION 6.1.0 ADHESION 6.2.0 VISUAL INSPECTION 6.3.0 SPARK TEST MAINTENANCE REQUIREMENTS FOR RUBBER LINING ANNEXURES: TABLE 1 RECOMMENDED MAXIMUM LINING THICKNESS TABLE 2 CHEMICAL RESISTANCE OF VERIOUS LINING PRPD BY : KR CHKD BY : AMN APPRD BY : KKK FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON : SEPT ' 15 ENGINEERING SPECIFICATION 03ES014/15 RUBBER LINING FOR PIPES , DUCTS & PIPE FITTINGS 1.0.0 SCOPE 1.1.0 This specification covers general requirements for 3.2.4 lining of pipes, ducts. Piping fittings etc. including fabrication, installation and testing. 3.3.0 1.2.0 Shop and field lined pipe are both included. 1.3.0 The thickness of rubber and areas to be covered shall 3.3.1 be in accordance with each data sheet and specifications. 1.4.0 The lining must be resistant to the chemicals shown 3.3.2 under the conditions listed on data sheet and specifications 2.0.0 PIPE AND FITTINGS 2.1.0 Pipes and fittings shall confirm to piping 3.3.3 specifications and to the requirements of this standard. 2.2.0 Pipe is to be seam-welded or seamless steel pipe 3.3.4 unless otherwise specified. Wall gauge is to be specified if not shown or called for on purchase 3.3.5 orders or drawings. 2.3.0 Where welding is used, internal welds shall be ground flush with the parent metal to ensure a continuous smooth surface, all fittings shall be flanged type. 2.4.0 Flanges shall be flat-faced, Class 150 forged steel slip-on, weld neck, or boiler plate. Raised face flanges shall not be used. Class 125 cast-iron flanges 3.4.0 or cast-iron pipe are not recommended for use with 3.4.1 rubber lining. 2.5.0 The weld on the front face shall be continuous and rounded convex to a radius of 3.0 mm or 4.5 mm. 3.4.2 PAGE 2 OF 14 Sufficient drying time between cement coats is required. LINING THICKNESS Lining thickness may vary from ¹∕₈" to ¹∕₄" in (3 to 6 mm). In some very abrasive conditions, up to 1"(25 mm) has been applied. Experience has proved that not only the rate of abrasion must be considered but temperature also. For temperatures greater than 140 F (60 C), ¹∕₄ in (6 mm) thick lining will provide better service. The most commonly used and economical lining thickness is ¹∕₄ in (6 mm). It offers long life for a wide range of applications. Recommended maximum lining thicknesses for different pipe sizes are shown in Table-1. Table-1 show that the smallest pipe size which can be lined is NPS 2 (DN50); however, NPS 1 nozzles can be lined per the following specifications: 1. Maximum length of nozzle is 25mm 2.Maximum thickness of rubber is ¹∕₈" (3 mm) 3.Maximum distance from end of pipe is 450mm 4.Nozzle is attached to a minimum of 150NB pipe LINING MATERIAL SELECTION The most important factor in selecting the right lining material is specific chemical resistance that will be required. In-service testing may be needed to confirm the suitability of the material selected. 3.0.0 LINING GUIDELINES 3.4.3 Table-2 lists some common chemicals and the 3.1.0 METAL PREPARATION general polymer used for a lining. 3.1.1 All metal surfaces to be lined shall be blasted to a white metal finish. White metal blasting is the 4.0.0 LINING PROCEDURE process of removing all foreign matter (such as rust, 4.1.0 Sheets of rubber shall be unrolled and cut to the scale, and paint)by the use of abrasives propelled by desired size and shape on a clean heated table and using 100 psi (690 kPa) of air. The surface finish shall be taken so that the tie gum (sticky) side of the will become a metallic gray-white color, with a lining is facing out for cementing. roughened anchor pattern providing a 1.5 to 3 mil 4.2.0 The edges can be cut with a skive (30 to 45-degree (37.5 to 75 micron) profile. angle) to aid forming the seam. 3.1.2 Other acceptable standards are provided by the Structural Steel Painting Council (SSPC) or 4.1.0 LINING PROCEDURE FOR STANDARD NationalAssociation Corrosion Engineers(NACE). FLANGED PIPE : 4.1.1 A tube shall be formed with lining stock using 3.2.0 CEMENTING longitudinal skived seams by wrapping the lining 3.2.1 Primer shall be applied immediately after removal of stock around a mandrel, using a liner inside the tube, dust and sandblasting to prevent rusting. or any other method to facilitate the making of a 3.2.2 Additional coats of primers and cements may need tube. tobe applied as specified by the lining manufacturer. 4.1.2 The spliced tube’s outside circumference shall be slightly smaller than the inside circumference of the 3.2.3 Primers and cements are normally applied on the pipe to be lined. inside of pipe with a swab, spray, or roller. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 03ES014/15 RUBBER LINING FOR PIPES , DUCTS & PIPE FITTINGS PAGE 3 OF 14 4.1.3 When forming the tube, the seam is formed by using 4.2.2 Large diameter pipes shall be lined in the same steady, firm, and overlapping strokes with a roller and when rolling, always work toward the edges 4.2.3 forcing all the air out from behind the overlapping layers of lining or along the butt skive. 4.1.4 The spliced tube’s length is longer than the pipe’s 4.2.4 length. manner as tanks or ductwork. The stock is flared over the flange face and trimmed or buffed flush after the cure and a covering is applied to the full face of flange. Bleeder strings are used at the applicators option, to facilitate the escape of gases during curing. 4.1.5 Twisted multifilament strings (called bleeder strings) 4.2.5 The I.D. of the flange stock is then skived to slightly are then applied lengthwise to permit proper air venting between pipe and lining. String made from synthetic yarns is not to be used. Stringing is done after cementing the pipe, and the individual strings are spaced equally around the circumference. 4.1.6 Normally, four strings are used on pipe of sizes up to 4.1.7 4.1.8 4.1.9 4.2.0 4.2.1 less than the I.D. or lining and stitched firmly to the tube stock. On larger-sized pipe, the flange stock is lapped into the pipe lining instead of applying the skive technique used on smaller pipe or applying lining to flange first. The lined pipe is cured as specified by the lining manufacturer. and including NPS 6 (DN 150). Larger-sized pipe 4.2.6 After curing, the ends of the pipe are buffed to normally requires the use of additional strings. The remove any excess rubber. This provides a smooth use of strings is optional with applicators fit during installation at the plant site. The tube is enclosed in a liner and a tow rope is 4.2.7 The best cure results will be obtained by using a attached to it. The tube is then pulled into the pipe steam autoclave. with a slow constant pull. One of two methods is used to seal the liner against 5.0.0 PROTECTING RUBBER LINED PIPES 5.1.0 SOURCES FOR POTENTIAL PROBLEMS the inside surface of the pipe. METHOD 1 : The liner is removed and the tube 5.1.1 Ozone from welding: Ozone can and will cause expanded against the pipe wall by using air pressure. severe cracking of natural rubber in linings, and the A mechanical extension and flange arrangement is corrosion barrier may be breached permanently. used to seal the pipe ends and a minimum of 100 psi 5.1.2 Portable generators, power relay stations, and (690 kPa) internal pressure is maintained in the electric motors are a potential source of ozone. expanded tube for at least 5 minutes. If any air blisters are found after the air pressure is removed, 5.1.3 Fumes from generators, such as nitrous oxide, are detrimental to rubber linings. they are punctured, vented, and repaired with a 2 in 5.1.4 Arcing from electrical equipment and hook-ups (50 mm) patch. generate a corona (ozone) environment. METHOD 2 : After the liner is removed, an air bag or balloon is pulled through the pipe, with stops at 5.1.5 Oils and liquids of many types cause softening and intervals where it is alternately inflated and deflated. deterioration of the rubber. Next, the extension is removed, the excess stock 5.1.6 Problems may occur from any one or more of the flared over the flange face, and trimmed flush. A above sources and can occur either inside or outside covering is then applied to the full face of the flange. of the structure being erected. Suitable protection The inside diameter (I.D.) of the flange stock is must be provided. skived to slightly less than the I.D. of the lining and stitched firmly to the tube stock or folded out and 5.2.0 MEANS FOR PROTECTION onto the flange surface. When using hard rubber 5.2.1 Installation of rubber lining should be done as near lining on flanges, it is important that the pipe the end of the construction phase as possible. installer/user understand that soft rubber gaskets are 5.2.2 Openings to rubber-lined equipment should be required over the face lining. closed as much as possible to prevent attack from On pipe sizes larger than NPS 6 (DN 150), the hazards such as those noted. flange stock is lapped onto the lining instead of the 5.2.3 The ends of rubber-lined pipe should be blanked off skive used on smaller sizes. This lapping technique and kept that way until ready for use. Lining on makes a stronger joint and is the preferred method. flanged faces should be protected during shipment or LINING PROCEDURE FOR LARGE storage by covering with plywood or other suitable DIAMETER PIPE material. Piping that is too large to safely line by inflating a 5.2.4 All portable rubber-covered items should be covered tube, but large enough to allow personnel to enter up for protection. will be considered in this section. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 03ES014/15 RUBBER LINING FOR PIPES , DUCTS & PIPE FITTINGS 5.2.5 Each piece should be identified by stamping on a ground area in such a manner that numbers will remain visible. Stencil: ‘‘Rubber Lined—Do Not Cut or Weld.’’ 5.2.6 Additional protective measures are available from rubber lining manufacturer publications. 6.0.0 TESTNG AND INSPECTION 6.1.0 ADHESION 6.1.1 The adhesion of rubber bonded to metal shall be satisfactory strong. 6.2.0 VISUAL INSPECTION 6.2.1 The inspection for visual defects should be carried out over the entire surface in a good light the entire surface shall be free of cracks, traces of bubble, lack of adhesion, hollow spaces etc. 6.3.0 SPARK TEST 6.3.1 A high voltage. High- frequency spark test should be carried out over the entire surface 6.3.2 Surface of the lining should be clean and dry when the test is carried out. 6.3.3 The voltage shall be 5kV/mm thickness to 6kV/mm thickness of lining unless the lining contains considerable amount of carbon black filter in which the voltage shall be 1.5kV/mm thickness. 7.0.0 MAINTENANCE 7.1.0 Rubber-lined pipe can be a large investment for a company. Thus, proper care and maintenance are always recommended. An experienced applicator can offer many detailed suggestions. 7.2.0 Some basic considerations of maintenance are: avoid impact, such as can occur from dropped tools; prevent exposure to sunlight and outdoor weathering; and protect from sudden temperature changes, which may cause thermal stresses that result in cracking, especially in hard rubber linings. 8.0.0 REQUIREMENTS FOR RUBBER LINING 8.1.0 The standards and requirements for rubber lining shall be as per the figures and tables given in this section. 8.2.0 When manufacturers intend not to apply this standard, he shall submit his standard or practices in order to get approval of purchaser. FACT ENGINEERING AND DESIGN ORGANISATION PAGE 4 OF 14 ENGINEERING SPECIFICATION 03ES014/15 RUBBER LINING FOR PIPES , DUCTS & PIPE FITTINGS FACT ENGINEERING AND DESIGN ORGANISATION PAGE 5 OF 14 ENGINEERING SPECIFICATION 03ES014/15 RUBBER LINING FOR PIPES , DUCTS & PIPE FITTINGS FACT ENGINEERING AND DESIGN ORGANISATION PAGE 6 OF 14 ENGINEERING SPECIFICATION 03ES014/15 RUBBER LINING FOR PIPES , DUCTS & PIPE FITTINGS FACT ENGINEERING AND DESIGN ORGANISATION PAGE 7 OF 14 ENGINEERING SPECIFICATION 03ES014/15 RUBBER LINING FOR PIPES , DUCTS & PIPE FITTINGS FACT ENGINEERING AND DESIGN ORGANISATION PAGE 8 OF 14 ENGINEERING SPECIFICATION 03ES014/15 RUBBER LINING FOR PIPES , DUCTS & PIPE FITTINGS FACT ENGINEERING AND DESIGN ORGANISATION PAGE 9 OF 14 ENGINEERING SPECIFICATION 03ES014/15 RUBBER LINING FOR PIPES , DUCTS & PIPE FITTINGS FACT ENGINEERING AND DESIGN ORGANISATION PAGE 10 OF 14 ENGINEERING SPECIFICATION 03ES014/15 RUBBER LINING FOR PIPES , DUCTS & PIPE FITTINGS FACT ENGINEERING AND DESIGN ORGANISATION PAGE 11 OF 14 ENGINEERING SPECIFICATION 03ES014/15 RUBBER LINING FOR PIPES , DUCTS & PIPE FITTINGS PAGE 12 OF 14 ANNEXURES FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 03ES014/15 RUBBER LINING FOR PIPES , DUCTS & PIPE FITTINGS PAGE 13 OF 14 TABLE 1 FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 03ES014/15 RUBBER LINING FOR PIPES , DUCTS & PIPE FITTINGS PAGE 14 OF 14 TABLE 2 FACT ENGINEERING AND DESIGN ORGANISATION CONTROLLED COPY ISO 9001 : 2015 CONTROLLED COPY ISO 9001 : 2015 CONTROLLED COPY ISO 9001 : 2015 CONTROLLED COPY ISO 9001 : 2015 ENGINEERING SPECIFICATION 02ES023/2010 PAINTING PAGE 1 OF 13 CONTENTS: 1.0.0. SCOPE 2.0.0. MATERIALS 3.0.0. SURFACE PREPARATION 4.0.0. STORAGE OF PAINTING MATERIALS 5.0.0. MIXING AND THINNING 6.0.0. PAINTING 7.0.0. SAFETY 8.0.0. INSPECTION 9.0.0. GUARANTEE 10.0.0. CODIFICATION OF PAINTING MATERIALS 11.0.0. SCHEME OF PAINTING 12.0.0. COLOUR CODING & MATERIAL FOR PIPING TABLES PRPD.BY:- JC CHKD.BY:- CK APPRD. BY:- JK FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON:- April 2010 ENGINEERING SPECIFICATION 1.1.0. This specification covers the requirements for surface preparation, painting and painting materials for equipment, structures and piping (including those painted/primed at shop and those painted at Field/Site. 1.2.0. Requirement of painting for any item shall be as specified in any of the following documents. d) Equipment Data Sheet Piping line schedule Design Basis for package items Painting schedule 1.3.0. The purpose of painting described in this specification is generally for protection against corrosion. 1.4.0. Painting for other reasons shall be as indicated in the respective equipment data sheets or painting schedule. 1.5.0. The following surfaces exposed to atmosphere are covered by this specification, which are not provided by any other form of covering/coating. a) b) c) d) PAGE 2 OF 13 a) 1.0.0. SCOPE a) b) c) 02ES023/2010 PAINTING Pressure vessels, Tanks, Heat Exchangers and other process equipment with Carbon steel and low alloy steel as material of construction. Machinery items including motors. Steel structures Carbon and low alloy steel piping 1.6.0. The following items shall not be painted unless otherwise specifically required by respective equipment Data Sheets/Painting schedule b) c) d) e) f) g) h) i) j) Non ferrous surfaces, stainless steel and High Alloy steel surfaces. Glass, tile or ceramic surfaces Name plates and identification tags Valve stems Machined contact surfaces Galvanised surfaces Insulation covers Plastics Underground / buried piping and equipments which are provided with special type of protective coatings. Surfaces / Items which are excluded from painting due to specific reasons. 1.7.0. This specification also covers painting of “Markings” and color-coding of carbon steel, low/high alloy steel, stainless steel, galvanized iron and insulated pipes. 2.0.0. MATERIALS 2.1.0. All painting materials shall be of good quality as covered by respective IS or other international specifications 2.2.0. Special paints and painting materials shall have proven quality and shall meet the requirements laid down in the respective data sheets for equipment and piping. 2.3.0. All painting materials shall not have passed the date of expiry or shelf life as recommended by manufacturer. 3.0.0 SURFACE PREPARATION 3.1.0 All surfaces to be painted shall be free from rust, oil, grease, dust, stain, moisture or any other foreign material/contamination, as per IS 1477 Part I. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES023/2010 PAINTING PAGE 3 OF 13 3.2.0 Surfaces to be painted shall be completely dry. or when the relative humidity of air exceeds 90%. 3.3.0 Oil, grease, stains and other similar contaminants shall be completely removed by using proper solvents and removers, After cleaning, the surfaces shall be free from even traces of contaminants and solvents/removers. 3.9.3. Blasting operations shall not be carried out during rain, snow, or strong winds. 3.4.0 Dust shall be removed by air blowing or vacuum cleaning. 3.5.0 Hard and caked dust, mud, mill scale and rust shall be removed by mechanical means like wire brushing, sand blasting , shot blasting or grit blasting. 3.6.0 Wet surfaces shall be dried by blowing warm air. 3.7.0 All surfaces cleaned by different methods shall be painted immediately with out allowing the clean surfaces togather dust, rust and other external substances. 3.9.4. Blasting medium viz. Slag, grit, or shot shall be completely dry and shall be free from any sort of contaminants like dust, oil, grease etc. 3.9.5. Blasting air shall be completely dry and shall have minimum pressure of 3.5 kg/cm2. 3.10.0 Surfaces which are not suitable for blast-cleaning or could not be blastcleaned due to practical reasons shall be thoroughly wire brushed to exhibit a pronounced metallic sheen, equivalent to St 3 as per IS 9954. 3.10.1 Absence of compressed air, slag/shot/grit and/or blasting equipment and accessories shall not be a reason for not carrying out blast cleaning. 4.0.0. STORAGE OF PAINTING MATERAILS 3.8.0 During the course of painting if it is found that the surfaces are contaminated due to any reason, the same shall be cleaned by any of the methods described earlier, before further proceeding with painting. 4.1.0. Paints, varnishes, thinner, additives and other volatile substances shall be stored in a flame proof enclosure, away from heat. 3.9.0 All surfaces to be painted after sand, grit or shot blasting shall exhibit almost clean white metal and shall have surface finish of SA 2 ½ as per IS 9954. 4.2.0. Fire extinguishers or sand and water for emergency fire fighting operations shall be provided near storage area at easily accessible place for use, in case of fire. 3.9.1 Blast cleaned surfaces shall be primed within 2 hrs, after blasting, before rerusting starts and before contamination. 4.3.0. Warning Boards and signs shall be exhibited around the storage area. 5.0.0. MIXING AND THINNING 3.9.2. Blast cleaning shall not be carried out when temperatures are less than 20°C 5.1.0 Mixing and thinning of paints shall be carried out as per manufacturer’s recommendations. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 5.2.0 Mixing and thinning operations shall be carried out in well ventilated rooms. 5.3.0 Only that quantity of paint which is sufficient to cover the required area within the specified painting time, shall be mixed at a time. 5.4.0 Mixed paints shall be used with in the time span as recommended by manufacturer. Mixed paints, for which standing time specified has elapsed, shall not be used. 5.5.0 Ready-mixed paints containers shall be opened only at the time of painting. Containers shall be closed air tight after drawing paint from it. 5.6.0 Ready-mixed paints shall be stirred well before drawing from the storage container as well as during painting operations. 5.7.0 Ready-mixed paints shall be thinned only if absolutely necessary by using thinners commended by manufacturer. 5.8.0 Balance of ready-mixed paints shall not be poured back into the main container after use, but shall be kept in a separate air tight container. 6.0.0 02ES023/2010 PAINTING PAINTING 6.1.0 General Requirements. 6.1.1 Painting of equipment, piping and structurals shall be carried out at shop or site as prescribed in the respective eqpt. data sheets, piping line schedule or structural detail drawing. . 6.1.2 Painting shall not be carried out on surfaces not prepared and not meeting the requirements of clause 3.0.0. 6.1.3 Painting shall be carried out only under favourable conditions. Painting shall PAGE 4 OF 13 not be carried out in dusty and draught conditions in damp areas and during rainy seasons or cold atmosphere. 6.1.4 During painting, adjacent equipments or surfaces shall be protected from paint sprays, splashes or drips. 6.1.5 Painting shall be carried out only by using brushes, rollers, air/airless spray. 6.1.6 Caution boards indicating ‘wet paint’ shall be posted after painting is over and kept till the curing time is completed. 6.1.7 For painting of multiple coating, each coat shall be applied only after sufficient curing time has elapsed after the previous coat, as recommended by manufacturer. 6.1.8 All painted surfaces shall have a uniform and smooth regular finish. The surfaces shall be free from foreign particles, brush marks, bristles, ridges, waves, laps wrinkles etc. If such surface defects occur, the same shall be removed by using abrasive paper/cloth and re-painted. 6.1.9 Surfaces inaccessible after assembly shall be painted to requirement before assembly. 6.1.10 Any imperfect or damaged layer/coat shall be repaired before subsequent coating. 6.1.11 At places where welding is to be carried out at field after assembly, a space of 100 to 200 mm width shall be left unpainted on both sides of the welding joint. 6.1.12 Field welded areas shall be thoroughly cleaned as required in clause 3.0.0 and painted in the same manner as the remaining area. 6.2.0 Shop Painting/Priming. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION PAINTING 6.2.1 Shop painting/priming shall be carried out as specified in the respective data sheets/line schedule etc. and shall meet all the requirements of this specification. 6.3.0 Painting at Field /Site. 6.3.1 Field/site painting shall be carried out as specified in the data sheets/painting schedule and shall meet all the requirements of this specification for painting. 6.3.2 Where equipments/piping/structures have already received shop painting/priming, the painted/primed surfaces shall be thoroughly cleaned and inspected for any damage or defects. Such damages or defects shall be repaired before starting the filed/site painting. 7.0.0. SAFETY 7.1.0. Sufficient safety precautions shall be taken to ensure protection of Personnel, equipments, piping structures and buildings in the vicinity, where painting materials are stored and painting and blasting operations are carried out. 7.2.0. Open flames and exposed elements or sources of ignition of any kind shall be prohibited in the area where painting materials are stored and painting operations are carried out. 7.3.0. ‘Warning’ or ‘Caution’ boards indicating chances of fire shall be displaced around the paint storage and painting areas. 7.4.0 Electrical fittings and appliances shall be spark proof and shall not cause a fire in the painting storage and painting areas. 7.5.0 Cleaning agents with flash point less than 400C shall be used. 02ES023/2010 PAGE 5 OF 13 7.6.0 Adequate ventilation shall be ensured during painting and storage of paints. 7.7.0 Painting workmen shall wear face masks, gloves and protective clothing during painting and mixing operations. In addition, workmen engaged in blasting operations shall be earmuffs also. 7.8.0 Area where painting is carried out, as well as materials are stored shall be clean, After work, the areas shall be cleared of all scaffoldings, balance materials etc. in order to prevent fire hazards and hinder fire fighting operations. 7.9.0 Painting materials shall be stored and painting and blasting operations shall be carried out only in areas where fire fighting equipments/vehicles and personnel evacuation vehicles can have easy access. In areas where such easy access is not available suitable precautions are to be ensured. 8.0.0 INSPECTION 8.1.0. All painting materials and related items shall be inspected to check the suitability of the same for the specified purposes. 8.2.0. Painting surfaces are to be inspected after cleaning operation, to ensure that the surfaces are fit for painting. 8.3.0. Finished surfaces shall be checked for uniformity in colour, finish and appearance as well as for defects. 8.4.0. Thickness of each coat of paint shall be checked after curing time. The total thickness of multiple coats shall be as specified in the data sheets/piping line schedules/painting schedules. 8.5.0. Paint thickness gauge shall be either mechanical or electronic. The gauges FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES023/2010 PAINTING shall be calibrated regularly. Defective gauges shall not be used. 8.6.0. Absence of paint thickness gauge shall not be made for each eqpt/line/structure separately. PAGE 6 OF 13 D.02 10.5.0. Polyurethane Coating. (For low temp. application) E.01 8.7.0. A detailed quality / inspection report shall be made for each eqpt / line / structure separately 9.0.0. GUARANTEE Guarantee shall cover materials and workmanship. 10.0.0. CODIFICATION OF PAINTING MATERIALS 10.1.0. Primers A.01 A.02 A.03 A.04 A.05 A.06 Synthetic Zinc Phosphate Primer Epoxy based Zinc Phosphate Primer Epoxy based Zinc Rich Primer Alkyd High Build Zinc Phosphate Primer Inorganic Zinc Silicate Primer Chlorinated Rubber based High Build Zinc Phosphate Primer 10.2.0. Finish Paints B.01 B.02 B.03 B.04 B.05 Epoxy Resin based Enamel Epoxy Resin based Micaceous Iron Oxide Paint Epoxy Resin based High Build Paint Coal Tar Epoxy Resin based Paint Chlorinated Rubber Paint Single Pack High Temperature Silicon Aluminium Paint (upto 600oC) E.02 Two-Pack Polyurethane Holding Primer High Build Polyurethane Coating 10.6.0. General Purpose Paints F.01 F.02 F.03 Synthetic Resin based Enamel Chemical Resistant Enamel Alkyd, Antiskid Abrasion Resistant Synthetic Floor Paint 10.7.0. Special Applications G.01 G.02 G.03 Bituminous Mastic Coating Asphalt doping as per IS 10987 App-B Thermocolour Paint 10.8.0 As an alternative, in place of one coat of E.01 – Two pack Polyurethane Holding Primer, one coat of Epoxy Zinc Phosphate Primer A02 (20 microns) followed by one coat of High Build Epoxy containing Micaceous Iron oxide-Bo2 (20 microns) shall be applied before applying finish paint E02-High build Polyurethane coating. 11.0.0 SCHEME OF PAINTING 11.1.0. Scheme of painting of equipment, piping, structures and other items shall conform to class 1, class II or class III as specified in the equipment data sheet/ piping line schedule/ painting schedule/ structural drawings. 11.2.0 Representation of painting 10.3.0. Bituminous Coating C.01 Nontoxic Inert Coating for drinking water tanks C.02 Acid Alkali and Heat Resisting Coating 10.4.0. Heat Resistant Paints D.01 Dual Pack Aluminium Paint (upto 250oC) Requirement of painting of an item shall be indicated in respective drawings/ data sheets/ line schedule/ painting schedule as follows. Indicate primer or finish or both as required followed by subclass indicated in Table 1, Table 2 or table 3 as the case may be. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION PAINTING Eg Primer Finish Primer & Finish Primer Primer & finish Primer Finish Primer & Finish Class I (1)L Class I (1)L Class I (2)M Class II (2)O Class II (3)O/P Class III (1) Class III (1) Class III (3) 02ES023/2010 PAGE 7 OF 13 12.0.0 COLOUR CODING AND MARKING FOR PIPING 12.1.0 In addition to the requirements of painting as per 11.0 the finish painting of the piping shall have the specified colors as per Table 4 – Color coding for pipes, for purposes of identification of service. 12.2.0 All pipes and pipe lines covered under 1.7 shall be provided with “Markings” such as color bands, hazard markings, line identification markings, flow arrow markings etc. at specified locations/intervals and dimensions as indicated in Table 5 – Marking of pipes. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES023/2010 PAINTING PAGE 8 OF 13 TABLE 1 – CLASS I – Pressure Vessels, Heat Exchangers, Reactors, Towers, Tanks and Piping Sl. No. SERVICE CONDITIONS OPERAT PAINT ING SUBTEMP. CLASS 1 UN INSULATED NON CORROSSIVE ATMOSPHERE UN INSULATED CORROSSIVE ATMOSPHERE INSULATED NON CORROSSIVE ATMOSPHERE INSULATED CORROSSIVE ATMOSPHERE =/< 15 =/< 65 =/< 125 =/< 400 =/< 15 =/< 65 =/< 125 =/< 400 =/< 15 =/< 65 =/< 125 =/< 400 =/< 15 =/< 65 =/< 125 =/< 400 SUPPORTS =/< 15 FOR ALL =/< 65 EQPTS.(INSUL =/< 125 ATED/UN =/< 400 INSULATED) EQPT. AND =/< 15 STRUCTRURE =/< 65 S SUBJECTED =/< 125 TO SALINE =/< 400 ATMOSPHERE UN INSULATED 2 3 4 5 6 PRIMER (1) L (1) N (1) M (1) H Type No.of coats E.01 1 A.01 2 D.01 2 D.02 2 (2) L (2) N (2) M (2) H (3) L (3) N (3) M (3) H (4) L (4) N (4) M (4) H (5) L (5) N (5) M (5) H E.1 A.06 A.02 D.02 E.01 A.04 D.01 D.02 E.01 A.06 D.01 D.02 E.01 A.01 D.01 D.02 (6) L (6) N (6) M (6) H E.01 A.06 A.02 D.02 *DFT FINISH 30 20 20 20 Type No.of coats E.02 2 F.01 2 D.01 2 D.02 2 30 20 20 20 1 2 2 2 1 2 2 2 1 1 1 1 1 2 2 2 30 20 20 20 30 25 20 20 30 30 30 30 30 20 20 20 E.02 B.05 B.02 D.02 E.02 F.01 D.01 D.02 2 2 2 2 2 2 2 2 20 20 20 20 30 20 20 20 1 2 2 2 30 20 20 20 E.02 B.05 B.01 D.02 2 2 2 2 30 30 30 20 * DFT – Dry film Thickness per coat microns Notation: L – Low Temperature N – Normal Temperature M – Moderate Temperature H – High Temperature : FACT ENGINEERING AND DESIGN ORGANISATION *DFT ENGINEERING SPECIFICATION 02ES023/2010 PAINTING PAGE 9 OF 13 TABLE 2 – CLASS II – OTHER EQUIPMENTS PRIMER PAINT SUB CLASS Sl. No. TYPE OF ITEM 1 2 3 4 5 6 7 8 9 10 11 Chimneys,Stacks, Furnaces,heaters (fired and unfired)operating Temp upto450oC D.M.Water Storage Tanks Fresh Water/fire Water Storage Tanks Drinking Water Storage Tanks Acid/alkali Storage Tanks Storage Tanks/Vessels for Petroleum Products Floating Roof Tanks:Inside of shell, top of bottom plate,topside and underside of deck, inside of pontoon Underside of Bottom Plate of Tanks Underground Tanks (buried) Below Ground (submersible) Tanks Secondary Reformer& Similar Eqpt.(Thermo colour paint) *DFT : ** : Notation: FINISH Type No.of coats *DFT Type No.of coats *DFT Outside (1) A.05 2 25 D.02 2 20 Outside Inside Outside (2)O (2)P (3)O A.01 A.03 A.01 2 2 2 20 35 20 F.01 B.03 F.01 2 2 2 25 35 25 Inside Outside Outside (3)P (4)O (4)P A.03 A.01 A.01 2 2 2 35 20 20 B.04 F.01 C.01 2 2 3 75 25 20 Outside (5) A.04 2 30 C.02 3 25 Outside (6)O A.04 2 50 D.01 2 25 Inside (6)P A.02 2 30 B.03 2 75 Outside (7)O A.04 2 50 D.01 2 25 (7)P A.02 2 30 B.03 2 75 (7)Q A.01 2 25 (8) A.01 1 20 G.01 1 80 Outside (9) A.01 1 20 G.02 Outside (10) A.06 2 35 B.05 3 35 (11) G.03 2 ** G.03 1 ** Dry Film Thickness per coat microns As per Manufacturer’s recommendations O- Outside P-Product Side Q-Specified Side FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES023/2010 PAINTING PAGE 10 OF 13 TABLE 3 – CLASS III – MISCELLANEOUS Sl. TYPE OF ITEM No. 1 Steel structures, Platform Supports PAINTING SUB Type CLASS PRIMER No. of *DFT coats FINISH Type No.of coats *DFT (1) A.04 2 20 B.01 2 25 2 Chequered Plate,Floorplanks&Gang ways (2) A.04 2 20 F.03 2 25 3 Handrails Posts,Railings,Ladders and Stairways (3) A.04 2 20 B.01 2 25 * DFT – Dry Film Thickness per coat microns FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES023/2010 PAINTING PAGE 11 OF 13 TABLE 4 – COLOUR CODING FOR PIPES Sl. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 Identification Ground / Finish Colour Instrument Air0 Sky Blue Service Air Sky Blue Plant Air Sky Blue Cooling Water Sea Green Service Water Sea Green Demineralised Water Sea Green Boiler Feed Water Sea Green Steam Condensate Sea Green Boiler Blow Down Sea Green Turbine condensate Sea Green Process Condensate Sea Green Low Pressure Steam Silver Grey Medium Pressure Steam Silver Grey High Pressure Steam Silver Grey Very High Pressure Silver Grey Steam Naphta Liquid Light Brown Naphta Vapour Light Brown Fuel Oil Light Brown Antifoam Solution Black Phosphate Black Hydrazinc Black Waste Water Black Oily Water Black Ammonia Liquid Dark Violet Ammonia Water Dark Violet Ammonia gas Dark Violet MDEA Solution Dark Violet Process Vent Canary Yellow Carbondioxide Canary Yellow Hydrogen Canary Yellow Nitrogen Canary Yellow LPG Canary Yellow Fuel gas Canary Yellow Process Gas Canary Yellow Synthesis Gas Canary Yellow Effluent Black Drinking Water Sea Green Service Colour Band - 1 Colour Band - 2 White Light Brown French Blue French Blue French Blue Light Orange Light Brown White White Black Light Orange Light Brown Signal Red Signal Red Signal Red French Blue Signal red French Blue French Blue French Blue White Sea Green Signal Red Signal Red Sea Green White French Blue French Blue French Blue Black Light Grey Light Grey Signal Red Black French Blue Light Brown Sea green White Sea Green Light Orange White Sea Green Signal Red Sea Green Canary Yellow White Signal Red Signal Red - FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 02ES023/2010 PAINTING PAGE 12 OF 13 TABLE 5 – MARKING FOR PIPES 1.0. GROUND COLOUR UNIT OF MEASUREMENT Insulated Line – all (excludes buried line) 1.1. Un-insulated Lines–Stainless : Ground colour for a length Per Marking as per para 6.0 Steel,GI ,Alloy steels & of 2 meters below including pipe supports Other non-ferrous pipelines (excludes buried line) ___________________________________________________________________________ 1.2. Un-insulated carbon steel : Ground colour applied Run length in Meters along Lines (excluded buried throughout entire length centreline including Markings Lines) as per Para 6.0 below & pipe supports ___________________________________________________________________________ 2.0. COLOUR BANDS MARKINGS 2.1 Colour band(s)and its width,Band 2 downstream of Band 1(ie.after band 1 along the direction of flow) Pipe size NB (D-pipe size in inches) 80 NB and below Above 80 NB(3”) up to 100 NB(4””) Above 100 NB(4”) up to 300 NB(12”) Above 300 NB(12”) 3.0 4.0 5.0 Band 1 mm 75 D x 25 D X 20 D x 15 B and 2 mm ¼ of Band 1 (Rounded to the nearest mm) Diagonal strips of Black and golden Yellow as per IS2379 superimposed on the ground color. If color bands exists, the hazard marking shall be painted downstream of the bands (ie. after bands in the direction of flow) Color shall be Black or White to contrast with the color on which LINE IDENTIFICATION they are painted. It shall consist of Line No., Line size, Fluid code & Pipeline Spec. No. The lettering dimensions shall be as per MARKINGS IS2379. Color shall be Black or White to contrast with the color on which FLOW ARROW they are painted. The dimension of the arrow shall be as follows and MARKINGS is based on the size of the pipeline. HAZARD MARKINGS d a c b a b c d 150NB & below 65 30 95 20 FACT ENGINEERING AND DESIGN ORGANISATION 200NB & above 90 50 125 30 ENGINEERING SPECIFICATION 6.0 02ES023/2010 PAINTING PAGE 13 OF 13 LOCATION OF MARKINGS Marking includes 2M long ground color, color band(s), hazardous marking, Line No. & flow direction arrow which shall be located at the following points with proper visibility as per IS2379. a. Battery Limit Points b. Either side of walls & dyke walls c. For long yard piping – at 30M interval d. Inter-section on pipe bridge e. Any other location indicated by the Engineer-in-charge at site 7.0 PIPE SUPPORTS 7.1 This includes base springs, hanger springs, shoes and trunnions etc. and excludes pipe bridge structures, platform, equipment support structures and such structures which do not actually support the pipeline. The painting of pipe supports forms part of the pipelines and a separate rate will not operate. 7.2 7.3 The painting specification for pipe supports shall be same as that for pipe ground colour. **************** FACT ENGINEERING AND DESIGN ORGANISATION iso2.sty ENGINEERING SPECIFICATION FABRICATION & ERECTION OF STEEL PIPING CONTENTS 1.0.0 2.0.0 3.0.0 4.0.0 5.0.0 6.0.0 GENERAL FABRICATION WELDING HEAT TREATMENT THREADED AND FLANGED JOINTS PROTECTION & SIZE OF PREFABRICATED PIPE SPOOLS 7.0.0 INSTALLATION OF PIPE SUPPORTS 8.0.0 PIPING INSTALLATION 9.0.0 TESTING AND INSPECTION 10.0.0 PRESSURE TEST AND OTHERS 11.0.0 APPENDICES ——————————- 1.0.0 GENERAL 1.1.0 1.1.1 SCOPE This specification covers the general requirements for fabrication and installation of steel piping (including carbon steels, low-alloy steels, and stainless steels) within petroleum refineries and chemical plants. When conflict occurs between this specification and the piping drawings or the individual specification, the order of precedence shall be piping drawings, individual specification, and this specification. REFERENCES The requirements contained in the latest editions of the following standards shall form a part of this specification, in the manner and to the extent indicated herein: 1. Indian Boiler Regulation (IBR) 2. ANSI B2.1, Pipe Threads 3. ANSI / ASME B31.3, Chemical Plant and Petroleum Refinery Piping 4. ASME, Boiler and Pressure Vessel Code: Section V- Non-destructive Examination, Se c t i o n VI I I - D i v i s i o n 1 , U W- 5 1 Radiographic Examination of Welded Joint, Section IX- Welding and Brazing Qualifications. DEVIATIONS When piping cannot be fabricated and installed as shown on the piping drawings, or when it is deemed to be more appropriate to fabricate and to install the piping in a manner other than as shown on the drawings, the FEDO Engineer / Representative shall be consulted and the piping shall be fabricated and installed in accordance with his instructions. 1.1.2 1.2.0 1.2.1 1.3.0 1.3.1 2.0.0 FABRICATION 2.1.0 2.1.1 MATERIAL CONTROL Packages of piping materials delivered to the jobsite shall be opened immediately, and the quantities, specifications, sizes, and identifica- PRPD. BY: CHKD. BY: 2.1.2 2.1.3 2.1.4 2.1.5 2.1.6 2.1.7 2.2.0 2.2.1 2.2.2 2.2.3 2.3.0 2.3.1 23.2 2.3.3 25ES205 / 10 PAGE 1 OF 28 tion ( color identification and die stamp ) shall be checked and recorded in the material ledger. The materials shall be stored promptly and neatly in the designated warehouse or storage yard. When the identification is inadequate, the material shall be marked according to the colour identification or an identification mark such as die stamp shall be applied before storing the material. Piping materials shall be issued only upon presentation of Material Issue Slips signed by the FEDO Engineer / Representaive. Piping materials shall be issued only against the relevant isometrics. Issued materials shall be indicated on the drawings or material use charts, etc., to prevent duplication of issues. Any surplus materials found on the job - site shall be returned promptly to the warehouse or storage yard. When more material is needed as a result of faulty fabrication or other similar reasons, the FEDO engineer shall promptly be in formed of the matter so that he can give further directions and advice. Special precautions shall be taken to keep electrodes and gaskets dry during storage. PRECAUTIONS FOR PREPARATI ON & FABRICATION When the location of piping connections by field welding is not shown on the piping drawings, consideration shall be given to preparation and fabrication of piping materials so that the field welding position is flat or horizontal as far as possible. The minimum clearance between the edges of two adjacent welds shall exceed 25mm or 4 t imes the pipe n ominal wall t hickness, whichever is greater. When both welded pipes and piping components having a longitudi nal welded joint are joined at the end, in the girth butt welds the dimension between the longitudinal welded joints shall exceed 5 times the nominal pipe wall thickness of the thicker of those being joined. In unavoidable circumstances when the dimension is less than 5 times, both longitudinal welded joints in the girth butt welds shall be examined by radiography over 100mm. In addition, Section 8.1 (14) shall be considered in the preparation and fabrication. CUTTING Pipes shall be marked accurately and then cut according to the dimensions shown in the piping drawing or the dimensions most suitable for the conditions of field installation. When irregular cutting is required for single and multiple branch connections and for curved and mitred segments of pipe, the cutting shall be performed by using a template. In principle, pipes shall be cut mechanically with a pipe cutter or a high speed cutter. When cutting ss pipe using a high speed cutter, an APPRD. BY: ISSUED ON: JAN 10 FACT ENGINEERING AND DESIGN ORGANISATION CONTROLLED COPY ISO 9001 : 2015 ENGINEERING SPECIFICATION 2.3.4 2.4.0 2.4.1 2.4.2 2.4.3 2.4.4 FABRICATION & ERECTION OF STEEL PIPING abrasive wheel for stainless steel shall be used. When pipe is of a large diameter, or when a pipe cutter or a high speed cutter cannot be used the following methods may be used. a) Carbon Steel Carbon steel pipe may be cut with automatic or manual oxygen- acetylene gas apparatus. However, base metal with a carbon content of more than 0.35% shall not be cut with oxygen-acetylene gas apparatus. b) Low-alloy steel pipe Only when unavoidable, low-alloy steel pipe may be cut with oxygen-acetylene gas apparatus pursuant to Subitem (a) above. c) Stainless steel pipe Only when unavoidable, stainless steel pipe may be cut by plasma arc cutting or arc air gouging. In this case, the pipe shall be coated with spatter deposit prevention paint to avoid adhesion of spatter. END PREPARATION Shape of Grooves 1. In principle, grooves for butt welding ends shall be shaped in accordance with ANSI B16.25 However, the grooves shall be in accordence with the approved Procedure Qalification Records(PQR). 2. Unless otherwise specified, the grooves shall be in accordance with the requirements shown in Table below which conform to ANSI B16.25. PIPE WALL THICKNESS (t) GROOVE 3 mm or less (stainless steel) and 4mm or less (carbon steel and low alloy steel) Square groove or slightly bevelled Over 4mm (but over 3mm for stainless steel ) to 22mm Single v groove asper figure 1a Over 22 mm Double v groove as per figure 1b Shape of Internal Trimming and Misalignment 1. Radial misalignment at the joining ends of piping components shall be such that full penetration can be attained. 2. Where component ends have an internal misalignment over 1.6mm, the thicker component with the wall extending internally shall be trimmed internally to an angle less than 300C as shown in Figure2. However, such trimming shall not result in a finished wall thickness less than the required minimum design thickness plus corrosion and erosion allowances. End Preparation method In principle, the end preparation shall be performed by machine. However, when the preparation is other than by machine, any cracks, flaws, burrs or oxidation scale (rust) shall be removed from the surface with a grinder. Treatment after End Preparation 2.5.0 2.5.1 2.6.0 2.6.1 2.6.2 25ES205 / 10 PAGE 2 OF 28 When carbon or low-alloy steel pipes and piping components with the ends prepared are to be stored for an extended period, a groove face rust preventive that will not damage the welding shall be applied to the ends (Appendix I). The rust preventive shall be removed prior to welding, as far as possible. BENDING In principle, ready-made elbows shall be used for bends of piping. However, when bends of a large radius are required due to fluid characteristics or plant performance, the pipe may be bent to shape.The procedure for bending shall be as follows: 1. In principle, pipe shall be cold bent with a pipe bender. However, when the pipe bender cannot be used because of the large pipe diameter, the pipe may be bent by heating or by high frequency induction.Lowalloy and stainless steel pipes shall not be bent by heating. 2. Pipe bends shall be made of one piece of pipe with no welds at the bend. 3 The pipe shall be smooth on both the exterior and interior, and shall be bent so as not to form any cuts, cracks, wrinkles, dents, etc. 4 Flattening of a bend shall not exceed the requirements shown in Section 2.8 figure 6. 5 The minimum bending radius shall be greater than 1.5 times the nominal diameter of pipe, unless otherwise specified on the piping drawings or the individual specification. 6 Low-alloy and stainless steel pipe shall be heat treated in accordance with the individual specification to relieve residual stress and work hardening of the bend. However, the heat treatment may not be applied to austenitic stainless pipe or to nickel-alloy steel pipe. 7. For carbon steelpipe of 25 NB and smaller, steam tracing, or discharge-end piping of vents, drains, etc., the pipe may be bent to the required angle by heating with an oxygen-acetylene gas torch. However, precautions shall be taken to prevent damage to the pipe by overheating and to ensure that the roundness of the steel pipe is maintained. MITRE BENDS Unless otherwise specified, mitre bends shall be used for piping 350NB and larger. For piping of 300 NB and smaller, ready-made smooth elbows shall be used. Mitre bends shall be fabricated as follows unless otherwise stated in the piping drawings or the individual drawings. 1 Mitre bends to be used at bends greater than 450C shall consist of not less than three segments. The minimum distance (l) between alternate segments of the mitre bend shall be 4 times the pipe nominal wall thickness or 25mm, whichever is greater (Figure3) FACT ENGINEERING AND DESIGN ORGANISATION 25 ES205 / 10 FABRICATION & ERECTION OF STEEL PIPING PAGE 3 OF 28 FIGURE 1 B FIGURE 1 A WHEN t > 22 mm WHEN t - 4mm to 22 mm 33 1/2° ± 2 1/2° R 3.2mm 37° ± 2.5° 19 t 10°± 1° 1.6 ± 0.8 t ENGINEERING SPECIFICATION 1.6 ± 0.8 3.2 ± 0.8 3.2 ± 0.8 FIGURE 2 TRIMMING AND PERMITTED MISALIGNMENT OVER 1.6 mm THIS PORTION SHALL BE FINISHED SMOOTHLY SO AS NOT TO HAVE A SHARP EDGE, WHICH MAY HINDER RADIOGRAPHIC EXAMINATION 30° MAX FIGURE 3 SHAPES OF MITRE BENDS 15° 30° 1.5 D 30° 1.5 D FIGURE 4 ANGLE OF MITRE BENDS FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 2 3 4 FABRICATION & ERECTION OF STEEL PIPING The radius of the mitre bend shall be greater than the nominal diameter of the pipe. The maximum mitre angle (ß of Figure 4) of each segment shall be as follows: When design pressure is 8kgf / cm2G or less : β ≤ 22030’ 2.7.7 When design pressure is 28 kgf / cm2 G or less : β ≤ 15000’ 2.7.8 When design pressure exceeds 28 kgf / cm2G : β ≤ 11 015’ The segments shall be neatly cut so that they will closely fit with each other when assembled. Cutting and end preparation of pipe shall be in accordance with the requirements (Sections 2.3 and 2.4) 5 When designing the shape of a groove, the mitre angle shall be considered and the shape of the groove shall be suitable for the welding process used. 6 When assembling the mitre bend, the segments shall be laid out and tack welded on a surface plate or other flat surface to keep the centers of the segments aligned. 7 After welding is completed, the interior of the pipe shall be inspected and any internal weld protrusions shall be removed. 8 Welding and heat treatment shall be performed in accordance with the requirements specified in Sections 3.0.0 and 4.0.0 of this specification. 2.7.0. BRANCH CONNECTIONS 2.7.1 Branch connections shall be fabricated by assembling the fittings that have dimensions and configurations shown in the piping drawings.Unless otherwise specified, branch connections shall be made in accordance with Figure 5 and as follows: 2.7.2 Branch connections, which are made by providing a hole in the main run pipe and inserting a branch pipe or a coupling, shall be as follows: a The hole provided in the main run pipe shall conform to the requirements of Section 6. b When the main run pipe is welded pipe, the welds of branch connections shall be made so as to avoid the welds of the main run pipe. 2.7.3 Branch connections shall be made by means of fully penetrated groove welds. The groove welds shall be made in accordance with the same welding procedure as for girth butt welds. 2.7.4 In no case shall scraps of metal resulting from making the hole be left inside the pipe. 2.7.5 When making branch connections, a jig or a metal fitting shall be attached to the main run pipe to prevent distortion of the main run pipe or bending of the branch pipe due to welding. The material of the metal fitting shall be similar to the main run pipe. 2.7.5 If reinforcement pads are used, unless otherwise specified, a 3.0mm dia vent hole shall be provided (at the side and not at the crotch) in the reinforcement pad to reveal leakage in the weld 2.8.0 2.8.1 2.8.2 2.9.0 2.9.1 25ES205 / 10 PAGE 4 OF 28 between branch and main run, and to provide vent ing during welding and heat treatment operations. If the reinforcement pad is made in more than one piece, each piece shall be provided with a vent hole. The material of reinforcement pads shall be the same as the main run pipe. An examination of the welds joining reinforcement pad to the branch shall be made by FEDO Engineer/ representative before installing the reinforcement pad. FABRICATION TOLERANCES To avoid misalignment when joining a pipe or fitting to a pipe, the pipe or fitting shall be turned to check for any irregularities and shall be joined correctly. Unless otherwise specified, tolerances for fabrication shall be in accordance with the requirements shown in Figure 6. GALVANISED PIPING Galvanised carbon steel piping shall be completly cold worked so as not to damage galvanised surfaces 3.0.0 WELDING SPECIFICATION 3.1.0 3.1.1 GENERAL This specification shall be adopted to all welded pipe joints of carbon steel, alloy steel and stainless steel piping system. The welded pipe joints are defined as under: 1. All line joints of the longitudinal and circumferential butt welded and socket welded type. 2. Attachments of castings, forgings, flanges and other supporting attachments to pipes. 3. Welded manifold headers and other sub assemblies 4. Welded branch connections with or without reinforcement pads. 5. Manufacture of welded / fabricated piping components. 6. The attachment of smaller connections for vents, drains, drips and other instrument tappings. All welding, and heat treatment, shall be in accordance with the applicable codes and specifications. 3.1.2 3.1.3 a. codes for petroleum refinery piping ANSI B31.3 b. Welding Qualifications. ASME Sec. IX. c. Code of procedure for metal arc welding of mild steel (structural work only) IS : 823 d. The Indian Boiler Regulations IBR All codes referred shall be the latest editions. In adition to the codes mentioned above, other relevant international codes such relating to the work, shall also be applicable. In case of conflicts between different codes or between codes FACT ENGINEERING AND DESIGN ORGANISATION 25ES205 / 10 25ES205 / 10 FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 3.2.0 3.2.1 a. b. c. d. e. f. b. To supervise welding procedure & welders performance qualification tests. c. To ensure that only qualified welders are engaged for welding. d. To check that shop / field welding is in conformity with the relevant specification and codes of practice followed in pipe line construction. g. h. i. j. e. To carry out Non Destructive Examination of welds. 3.2.3 3. Contractor shall intimate sufficiently in advance the commencement of qualification tests and welding work to enable the owner’s inspector to be present to supervise them. Welding procedure qualification Welding procedure qualification shall be carried out in accordence with the job requirements and relevant requirements laid down in the standard ASME Sec. IX and other relevant applicable codes. The contractor shall submit the welding procedures in QW — 482 format given in ASME Sec. IX. immediately on receipt of work order. Owner’s inspector will review, check and approve the welding procedure after conducting the necessary tests. It shall be the responsibility of the contractor to carry out the tests, at his costs. All the necessary arrangements for the procedure qualification i.e. supply of material for assembly welding consumables, welding equipments, preparation of test coupons, welding, heat treatment, machining of test specimen, conducting N.D.T, mechanical & chemical test and maintaining qualification records, shall be by the contractor at his cost. He shall submit the test results to the Engineer-in-charge in QW483 format given in ASME Sec. IX. for approval. Welder’s Qualification 1. Welder’s qualification shall be in accordance with the relevent codes specified in scope of work. Owner’s inspector shall witness the test and certify the qualification of each welder. Contractor shall submit the welder qualification report as per Format before the commencement of work. It shall be the responsibility of the contractor to carry out the qualification tests of welders. PAGE 7 OF 28 For piping covered by Indian Boiler Regulations, welders with valid IBR certificate, qualified by Boiler Inspectors and acceptable to the local Boiler Authority shall only be employed. 2. The welders shall always have in their possession the identification card as per Format and shall produce it whenever demanded by owner’s Inspector. It shall be the responsibility of the contractor to issue the identity cards after duly certified by the Inspector. 3. The identity card shall contain the following minimum details. and tender specifications the more stringent shall be applicable. INSPECTION & TESTING General 1. The owner’s inspector shall have free access to all concerned places, where the actual work is being performed. The contractor shall also provide the owner’s inspector all means and facilities necessary for carrying out inspection. 2. The owner is entitled to depute his own inspector to the field or shop where prefabrication and erection of pipe lines are being done with ( but not limited to ) the following functions : a. To check the quantity, consumables and welding equipments used on the job 3.2.2 25ES205 / 10 FABRICATION & ERECTION OF STEEL PIPING 3.3.0 3.3.1 3.4.0 3.4.1 3.4.2 3.4.3 Name of Contractor Name of welder Stamp No. Address Recent passport size photograph Details of qualifications i Welding process and P numbers ii Range of pipe diameters iii Range of thickness iv Welding positions Date of qualification test Period of validity Signature of manufacturer Signature of Engineer —in—charge 4. No welder shall be permitted to work without the possession of identify card. 5. If a welder is found to perform a type of welding or in a position for which he is not qualified, he shall be debarred from doing any further work. All such welds so performed shall be cut and redone at the expense of the Contractor. 6. Engineer-in-charge reserves the right to ask the contractors to perform requalification test at their cost for welders whose workmanship technique etc. are found unsatisfactory during the execution of the job. SELECTION OF WELDING MATERIALS Selection of welding electrodes shall be as per Appendix - II Table - I : Selection of welding electrodes & rods for joining similar materials except Aluminium Table - II : Selection of welding electrodes & rods for joining dissimilar materials except Aluminium STORAGE AND ISSUE OF ELECTRODES Electrodes shall be stored and issued as follows: Electrodes shall be stored indoors free from moisture as far as possible. Electrodes shall be dried in a heating cabinet in accordance with the manufacturer’s recommendation before welding. Immediately after drying, electrode shall be stored in a portable dryer, or in a heating cabinet at the following temperature, and shall then be used. a. Illumenite FACT ENGINEERING AND DESIGN ORGANISATION : 70 - 1000C ENGINEERING SPECIFICATION b. 3.4.4 3.4.5 3.4.6 3.4.7 3.5.0 3.5.1 3.5.2 3.6.0 3.6.1 3.6.2 Others FABRICATION & ERECTION OF STEEL PIPING : 100 - 1500C During welding, electrodes shall be kept in a portable dryer or equivalent. The electrodes shall not be laid down directly on the ground or any other damp places. Electrodes exposed to the atmosphere for more than 4 hours shall be redried. However, only two redryings are permitted. When the day’s work has been completed, the electrodes shall be collected and stored in a heating cabinet at the temperature specified in 3.3.2 above. Issue of electrodes shall be controlled by the assigned person. SURROUNDING CONDITIONS FOR WELDING Welding shall not be performed under the following climatic conditions. 1. In the rain 2. In winds of 8 m/s or more 3. In snow However, welding may be performed if the area is fully protected from the inclement weather. When the item to be welded is wet with rain or covered with snow or ice, the snow or ice shall be removed and the surface dried completely before welding. GENERAL FOR WELDING Welding shall be performed in accordance with welding procedure specification (WPS), which has been approved by FEDO/Representative. Before welding, the WPS shall be prepared which has been qualified by the welding procedure qualification test based on the specification for welding procedure qualification, according to this specification and ASME Section IX. As a general rule, welding for steel pipes shall be performed as follows. 1. The welding process used shall be SMAW, GTAW, or GMAW (MIG Welding). Any other welding process may be used only when approved by FEDO / Representative. 2. Preferably, the first layer of butt welded joint shall be made by GTAW. For the first layer on 3Cr. and higher low-alloy steel pipe, or stainless steel, GTAW shall be performed with back shielding gas such as argon. 3. The surface to be welded shall be cleaned thoroughly and any paint, rust, scale, oil, dust, moisture, or any other foreign matter that would be detrimental shall be removed at least within the extent of 50mm from the groove end before welding. 4. The welding position shall be performed in flat position as far as possible. 5. Full consideration shall be given to the welding progression to keep distortion to a minimum. 6. In multi-layer welding, before welding the following layer, the surface of each layer 3.7.0 3.7.1 3.7.2 3.7.3 3.7.4 3.7.5 25ES205 / 10 PAGE 8 OF 28 shall be removed of any slag or other foreign matter with a chipping hammer, a grinder, or a wire brush. To prevent spatter adhering to the base metal, a spatter deposit prevention paint may be applied around the outside of the groove. Wire brushes and abrasive wheels shall be distinguished so that those for stainless steel shall not be confused with those for carbon steel or low-alloy steel. Moreover, any arc starts, craters, or inferior beads of each layer shall be removed before the welding is continued. 7. Peening on the welds is prohibited. 8. Unless required, the external surfaces of welds shall not be finished with a grinder or any other tool. However, when finishing the end of weld beads with a grinder, special precautions shall be taken not to reduce the thickness of base metal by over grinding. 9. Arc strike shall not be generated on the pipe surface. Care shall be taken not to lay down the electrode holder or move it around by the electrode. 10. To prevent damage from sparks, care shall be taken to ground the welding equipment by strict use of ground clips and to ground each piece of material. 11. When welding galvanized steel, the coating shall be removed from the surface to be welded, 50mm on either side. 12. For the joints of P-Number 5 materials, when welding is unavoidably interrupted, postheating shall be applied and the welds shall be cooled gradually by the use of insulation or other suitable materials. ( Para 4.3.0 ). BUTT WELDS When welding a pipe to a pipe, fitting, valve, etc., the components shall be placed on a revolv ing stand, aligned accurately within the tolerances specified in Section 2.8. of this specifica- tion by the use of tack weld pieces (fit-up pieces), lineup clamps, etc., and shall then be welded. Backing rings shall not be used unless otherwise specified. The number of tack welds made shall be the minimum required to secure the pipe, and a minimum of three shall be made for pipes of 50 NB and larger. When tack weld pieces are used for pipe materials of stainless steel,the material of the pieces shall be similar to that of the pipe. When the pipe material is low-alloy steel, carbon steel may be used for the pieces unless otherwise specified.The welding for the tack weld pieces shall be performed with electrodes equivalent to those used for the base metal and shall be performed by a welder or welding operator qualified for fillet welds. Tack welds, which are made directly at the root of the joint, shall be made by a qualified welder or welding operator specified in Section 3.2.3 and shall be made by the same welding procedure as the product welding. Tack welds that are cracked or not fused properly shall be removed. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 3.7.6 FABRICATION & ERECTION OF STEEL PIPING Pieces for tack welds shall be removed with a grinder. If a concave surface due to overgrinding, etc., is produced on the pipe, the repair welding shall be performed in accordance with WPS, which has been approved by FEDO Engineer / Representative. Any convex weld beads formed on the pipe surface shall be removed. When defects are found while removing tacks / cleats they shall be fully removed, repaired by welding, and a magnetic particle or liquid penetration examination shall be performed to confirm that there are no defects. 3.7.7. Internal weld protrusions of butt welds for orifice flanges shall be finished smoothly to the pipe inside diameters with a grinder. 3.7.8. The root pass of all buttwelds on pipe of size less than 50NB shall be made in GTAW grove only. 3.8.0 FILLET WELDS 3.8.1 Fillet welding shall be performed as follows: 1. Fillet welds shall be multi-layered and of sufficient strength. 2. Fillet welds shall be as shown in Figures 7A and 7B. 3. Fillet welds for socket welding flanges shall be as shown in figure 7C. 4. Fillet welds for socket welding components shall be as shown in figure 7D. 3.9.0 SEAL WELDS 3.9.1 Seal welding shall be performed as follows: 1. Threaded joints to be seal welded shall not be coated with a compound or covered with a seal. After any oil on the threads has been fully removed, the threads of joint shall be screwed in securely in accordance with Section 5-1.0, and shall then be welded. 2. If threaded joints are seal welded, all exposed threads shall be covered by a seal weld. 3. Seal welding shall be performed by a qualified welder. 4. Electrodes of 3.2 mm dia or less shall be used. 3.10.0 FLANGE ATTACHMENT WELDS Flange attachment welding shall be performed as fol lows: 3.10.1 Unless otherwise shown on the drawings, in principle, flange bolt holes shall straddle the established centerlines. The only exception is at equipment flanges required for matching orientation. 3.10.2 When installing flanges, flange square or other jig shall be used, and the center line of the pipe and the perpendicular of the flange face shall be within the tolerances specified in Section 2.8. 3.10.3 Joining welding neck flanges to the pipe shall be performed in accordance with the requirements of Section 3.7. 3.10.4 Front welding shall be performed on slip-on flange joints except for pipes class less than 50NB (Figure 8). Care shall be taken so that the weld reinforcement does not protrude on to the 25ES205 / 10 PAGE 9 OF 28 gasket contact face and that the gasket contact face is not damaged by welding. If the gasket contact face is damaged,or weld reinforcement protrudes onto the gasket contact face, such defects shall be removed by polishing the gasket contact face. 3.10.5 When welding flange joints, care shall be taken to handle the flanges carefully so that the gasket contact face will not be damaged. The gasket contact face shall not be in direct contact with the ground, and grounding shall not be taken directly from the gasket contact face. 3.10.6 In the case slip-on flanges which are to be heat treated, and also require to be front welded,they shall be provided with a 3mm dia vent hole at the hub as shown in FIG.8. 4.0.0 HEAT TREATMENT 4.1.0 4.1.1 PREHEATING Unless otherwise specified, the preheating applies to gas cutting and welding (all welds including butt welds, fillet welds, socket welds, repair welds, tack welds, and seal welds of thread ed joints ). Preheating shall be performed as follows: 1. Materials to be pre heated and preheating temperature shall be in accordance with relevant codes as a rule, but for steam lines fallen under the purview of IBR, the same shall be followed. 2. If the maximum specified carbon content is more than 0.38, or if the material is under a high degree of restraint (weld-all- around such as pipe shoe), carbon steel shall be preheated to a minimum of 800C and maintained at that temperature for surface welding. 3. When welding dissimilar metals, unless o th er wise sp eci fied , the preh eatin g temperature shall be that for the higher grade steel 4. The width of the heated circumferential band shall be 4 times the pipe nominal wall thickness or 100mm, whichever is greater, extending on both sides of the welds. 5. Heat shall be applied by the use of a gas burner or a heating coil. The use of a gas burner for cutting shall not be permitted since it tends to heat locally. Temperature measurements of preheating, interpass temperature, and postheating shall be performed by a temperature crayon ( tempil stick), thermocouple temperature indicator, etc., and it shall be confirmed that the specified temperature is maintained. INTERPASS TEMPERATURE The following items shall be confirmed for interpass temperature: 1. Interpass temperature of the materials that require to be preheated shall be the same as the preheating temperature and shall be maintained until welding has been completed. 2. Interpass temperature of austenitic stainless steel pipe shall not exceed 1500C. 4.1.6 4.2.0 4.2.1 FACT ENGINEERING AND DESIGN ORGANISATION 25ES205 / 10 FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 4.3.0 4.3.1 4.4.0 4.4.1 25ES205 / 10 FABRICATION & ERECTION OF STEEL PIPING POSTHEATING When postheating is required it shall be carried out for more than 30 minutes within the temperature range of 300 to 4000C, and the material shall be cooled gradually by the use of insulation, etc. However, when post weld heat treatment is performed immediately after welding, post - heating is not necessary. POST WELD HEAT TREATMENT Procedure Unless otherwise specified, post weld heat treatment shall be performed in accordance with the following procedure. However, post weld heat treatment for dissimilar metals shall be in accordance with the individual specification. 1. The requirements for heat treatment shall be in accordance with applicable codes. But for steam lines IBR shall be followed. Heat treatment of welded joints between dissimilar ferritic metals shall be within the temperature ranges for the higher grade steel. 2. Al l th e m ach ine d surf aces sha ll be protected adequately by the use of paint or compound to prevent damage from scaling during heat treatment. 3. In case of furnace heat treatment, all the pipes shall be supported properly during heat treatment to minimize warps and other distortions. 4. In principle, after heat treatment has been completed, neither rewelding nor reheating shall be performed. However, if rewelding is performed because of repairs, etc., heat treatment shall be performed again. 5. If welding is intrrupted before completion or the weldment is allowed to cool prior to heat treatment, adequate heat treatment or controlled rate of cooling shall be applied to ensure that no effects detrimental to the piping shall result. The pre-heat temperature in the welding must be applied before welding is resummed. 6. When heat treatment is performed, the holding temperature, holding time, rate of heating and cooling, and the hardness after heat treatment required shall be recorded and the records shall be submitted to FEDO Engineer / Representative. 7. The measurement of heat treatment temperature shall be performed by measuring the metal temperature by the use of a thermocouple,or by other suitable methods. Ho w e ve r, w he n t he h e at t r ea t me n t temperature is measured by the furnace temperature, the relation between the temperature of metal and furnace shall be considered. 8. A hardness test shall be performed in accordance with Section 9.4.0 to determine if the heat treatment has been performed satisfactorily. 9. Throughout the cycle of heat treatment, the portion out side the heated band shall be suitably wrapped under insulation so as to avoid any harmful temperature gradient at PAGE 11 OF 28 the exposed surface of pipe. For this purpose temperature at the exposed surface of pipe should not be allowed to exceed 4000C. 10. All online pipe item ( eg. Valves, Instruments etc. )within 500mm of the weld which is beingheat treated, shall be dismantled prior to commencement of heat treatment of weld. 11. The no. of thermocouples to be used for the monitoring of tempreature shall be as follows.( HAZ - Heat Affected Zone ) DIA OF PIPE NOS. OrientatIO N(0) LOCATION 15NB & below 2 0 , 180 One on weld & one in HAZ 200 to 500 NB 3 0 , 120 , 240 one on weld & rest in HAZ on either side of weld 600 Nb & above 4 & rest in 0 , 90 , two on weld either side 180 , 270 HAZ on of weld 4.4.2 Heating Methods For heat treatment, application of heat in a furnace is preferable, however, heat may be applied locally by the following methods: 1. Heating by electrical resistance This is a method where a programmed movable automatic heater applies heat by means of nickel-chrome wire applied around the welds. Special attention shall be given to the following items: a. Protective measures shall be taken to prevent damage to the pipe surface or injury to the workers due to a short circuit of the lead wire, and to prevent persons other than the operator entering the work area. b. The width to be heated shall extend 25mm beyond the edges of the weld on each side c. The width to be insulated shall extend at least 150mm on each side of the weld. d. The heating and cooling rates above 3150C shall be determined by the following formula, but in no case shall the rate exceed 2200C per hour. 25 x 220 ( oC ⁄ h) wall thickness (mm) 2. Heating by gas burner a. This is a method where heat is applied by a propane or butane gas burner. This method shall not be used unless specified by FEDO Engineer/ Representative. 5.0.0 THREADED AND FLANGED JOINTS 5.1.0 THREADED JOINTS Threading of joints shall be as follows. Taper pipe threads shall be as per ANSI B2.1, 5.1.1 FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION FABRICATION & ERECTION OF STEEL PIPING ANSI Standard Taper Pipe Thread (NPT). Unless otherwise specified, when threading on pipes of NPS 11/2 or smaller, the pipe thickness shall be Schedule 80. 5.1.3 In principle, all threads shall be cut with a threading machine or lathe. When threading with hand dies such as an oster or reed type, a lubricant shall be used to avoid an irregularity of screw thread or scratches due to coarse machining. 5.1.4 All the threads shall be cleaned thoroughly. 5.1.5 In principle, teflon seal tape shall be used for threaded joints used in services of 1500C and lower. Once the joints are screwed, they shall not be unscrewed. Fillers such as hemp, jute, lead scraps, and white paint shall not be used. 5.1.6 Seal welding of threaded joints shall be in accordance with Section 3.9 5.1.7 In no case shall threaded joints be made with a length of engagement less than specified. 5.1.8 When pipe is screwed into a threaded flange, the pipe end shall not extend beyond the gasket contact face. If the pipe end protrudes even slightly, the pipe end shall be ground off with a grinder or a file so that the gasket contact face is not scratched. 5.1.9 When screwing a pipe into a threaded bronze valve, the pipe shall be gripped by a pipe vice and the valve shall be screwed on by clutching the end of the valve with a wrench. Threading and screwing shall be carried out carefully so that the pipe does not enter the valve too far and damage the valve due to the threads being overcut on the pipe. 5.1.10 Scraps of metal due to threading and oil used for cutting shall be removed before screwing on instrument air piping. 5.1.11 Any compound or lubricant used on the threads shall be suitable for the service conditions, and shall not react unfavourably with either the service fluid or piping material. 5.2.0 FLANGED JOINTS Flanged joints shall be made as follows: 5.2.1 In principle, Class 125 and 250 flanges of valves and other equipment made of gray cast iron shall be of flat face with full contact area gaskets. 5.2.2 Steel to gray cast iron flanged joints shall be assembled with care to prevent damage to the cast iron flange. 5.2.3 Unless otherwise specified, gasket paste shall be applied uniformly on the gasket contact face of the flange when a metal jacketed gasket or a metal gasket is used. However, when the flange material is austenitic stainless steel, the use of gasket paste shall be approved by FEDO Engineer / Representative. As the choice of paste is limited by the fluid handled, the paste shall be suitable for the service fluid. The gasket paste shall be kept in a container with a lid and handled with care to prevent entry of sand, dust or other foreign matter. 5.2.4 For asbestos-sheet gasket, gasket paste may not be applied. 5.2.5 For spiral-wound gaskets or ring-joint gaskets, gasket paste shall not be applied. 5.1.2 25ES205 / 10 PAGE 12 OF 28 5.2.6 The thread and bearing surfaces of bolts and nuts to be used on piping at temperatures of 2500C or higher shall be coated thinly and uniformly with a lubricant to prevent them becoming burnt and stuck. 5.2.7 Lubricant shall not be applied to machine bolts unless other wise specified. 5.2.8 Bolts shall be of material and length as specified. In principle, all the bolts shall extend 2 or 3 threads through their nuts. 5.2.9 Flanges shall be tightened with a wrench or spanner of the specified length and with a hammer if required, or with a torque wrench. Care shall be taken so that the bolt is not tightened excessively or unevenly. 5.2.10 As the tightening force varies according to the flanges, gaskets, and bolts used, the tightness shall be controlled with care. In particular, flanges of piping for low temperature and dangerous services shall be tightened only with a torque wrench. For large diameter bolts, the use of an impact wrench with torque control or a power machine ( hydraulic torque wrench ) is preferred. 5.2.11 Bolts of flanged joints shall be successively and evenly tightened in a symmetrical pattern ( Appendix IV ). 5.2.12 Cast iron flanges of equipment such as pumps, turbines, compressors, or other similar equipment shall be tightened carefully so that the flange does not break. 5.2.13 The flange clearance with connections of pumps, compressors, or other similar equipment, and ring-joint flanges shall be measured by the use of a clearance gauge and the parallelism shall be checked, and then the bolts shall be tightened evenly. 5.2.14 Ring-joint gaskets shall be ground with the groove of the flange for a tight fit prior to installation. The grinding shall be performed by using a compound (coarse, intermediate, or fine), and red paste shall be applied to confirm the roughness of the contact face between the ring and the groove of the flange. The paste shall be removed completely before the ring is installed. 5.2.15 If the gasket contact face of the flange is damaged, the defects shall be removed by polishing evenly the gasket contact face, or the flange shall be replaced. 6.0.0 PROTECTION OF PREFABRICATED PIPE SPOOLS AND SIZE 6.1.0 PROTECTION OF PREFABRICATED PIPE SPOOLS All prefabricated pipe spools that have been inspected shall be protected as follows until they are installed in a plant. 1. All dust, rust, weld slags, or other foreign matter in the pipe shall be removed carefully by brushing or by flushing with compressed air, or by other suitable means. After cleaning, all openings of austenitic stainless steel shall be blanked. 2. Pipe spools to be stored temporarily shall be laid on suitable sleepers and not directly on the ground. 6.1.1 FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 6.1.2 6.1.3 6.2.0 6.2.1 6.2.2 FABRICATION & ERECTION OF STEEL PIPING 3. Pipe spools shall be marked with the area number (major divisions such as offsite, onsite), line number, and piece number. After cleaning the pipe spool surface and applying rust preven tive, it shall be marked clearly with paint by the use of a stencil. When specified, in showing the line number, etc., a color code identification or tag plate (die stamped to the sheet metal) for each area shall be made, and it shall be attached with coated iron wire. However, zinc coated iron wire shall not be used for austenitic stainless steel. 4. If hydrostatic test is performed, the water shall be removed completely. When prefabricated pipe spools are to be stored for a long period of time or are to be shipped, the pipe interior shall be checked to see that it is clean, and the openings of pipe ends shall be protected as follows: 1. When the pipe ends are prepared, the ends shall be coated with rust preventive ( Appendix — 1 ) and covered with a plastic cap, etc. 2. When the pipe ends are flanged, the gasket contact face shall be coated with rust preventive and be protected with a wooden or plastic cover bolted on to the flange. In case of a wooden cover, poly ethylene or other suitable film shall be inserted between the flange and the cover. 3. When the pipe ends are threaded, the threads shall be coated with rust preventive and threaded end connections shall be covered with wooden or plastic plugs or caps. 4. When masking tape is intended to be used instead of the protection mentioned above, it shall be subject to FEDO Engineer’s/ Representative’s approval. However, austenitic stainless steel pipes and prefabricated pipe spools that may be affected by chlorine ions, shall be protected in accordance with the individual specification. SIZE OF PREFABRICATED PIPE SPOOLS The size of prefabricated pipe spools shall be determined by consideration of the conditions of transportation, etc. Consideration shall be given to the conditions of inland transportation, size of the carrier’s hatch, means of transportation, traffic regulations in the country and the economy. The standard size of a package to transport prefabricated pipe spools is limited to 2.5 meters width by 2.5meters height by 13 meters length with a weight of 5 tons per package. 7.0.0 INSTALLATION OF PIPE SUPPORTS 7.1.0 7.1.1 PIPE SUPPORTS Pipe supports whose materials & dimensions conform to fabrication drgs, shall be installed accurately at the positions shown on the drawings prior to piping installation. When installing the pipe supports, pay attention to the following: 1. Each support shall be fabricated and assembled so that piping does not become disengaged from the support by movement of the piping itself due to operation. 7.2.0 7.2.1 7.3.0 7.3.1 7.3.2 7.4.0 7.4.1 7.5.0 7.5.1 25ES205 / 10 PAGE 13 OF 28 2. Stanchions requiring foundations shall have anchor bolts of the correct size, position, projection, etc. 3. Before installing the supports, the finished conditions of the cut ends of all members and welded conditions shall be checked. 4. Pipe supports shall be made level and plumb to facilitate alignment during piping installation. 5. In principle, when the main run pipe is lowalloy steel or ss, either a pad plate or support members of the same material as the main run pipe shall be used, and carbon steel supports shall not be welded directly to these. In this case, when welding the pipe to the support, the same electrodes as applied to the pipe shall be used, and the qualified welder specified in Section 3.1.0 shall perform the welding in accordance with WPS. When the main run pipe requires heat treatment, the welds for attachment of pipe supports shall be heat treated if required,as per ANSI B31.3. 6. Welds for anchor supports shall be doublelayer welds to provide a bond of sufficient strength. 7. When welding dummy pipe to elbows, tees, etc., the welding shall not melt through to their interior. SLIDING SUPPORTS Sliding supports shall be assembled so that the expected movement of the supported piping due to thermal expansion and contraction or other design requirements is possible. SPRING HANGERS The lock-pin or preset-piece of spring hangers shall not be taken off until pressure testing and flushing have been completed, except only when a high temperature fluid such as flushing steam is streamed. Adjustment of spring hangers shall be performed by taking off the lock-pin or preset-piece prior to ini tial operation. It shall be confirmed that spring hangers operate on the expected movement according to temperature increase in the initial operation. ADDITIONAL SUPPORTS If additional supports are required to prevent shaking of piping in the field, they shall be installed in accordance with the instructions of the FEDO Engineer’s / Representative’s Engineer in consideration of the effects due to thermal expansion of the piping. INSULATION SUPPORTS The configuration, material, and installation procedure of support rings for hot or cold insulation of vertical piping shall be in accordance with the individual specification. 8.0.0 PIPING INSTALLATION 8.1.0 GENERAL ITEMS FOR PIPING INSTALLATION The general items for attention relating to piping installation shall be as follows: FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 8.1.1 FABRICATION & ERECTION OF STEEL PIPING Pipes shall be stored in accordance with each category of material, and stacked on sleepers with wedges or stakes provided to prevent the stack from collapsing. 8.1.2 Before installation, pipe spools shall be checked with the piping drawings as to dimensions, material, class, etc. In principle, the installation of pipe spools shall start from elevated lines or larger size lines. The precedence for installation shall be determined after confirming that all equipment has been installed and aligned, and steel structures and pipe racks are ready for installation of the piping. The part which cannot be painted after piping installation shall be painted beforehand. 8.1.3 In principle, underground piping shall be installed before above ground piping. 8.1.4 Before installation, the pipe spool shall be suspended at one end by a crane, etc., and ham mered to remove the dust inside. 8.1.5 Supports such as stanchions shall be checked for the accuracy of position, dimensions, elevation, levelness and plumbness. 8.1.6 When temporary supports are installed unavoidably to the piping, welding shall not be performed on the main run pipe. 8.1.7 Temporary work for piping installation shall be planned in advance, and the necessary equipment and materials shall be selected and prepared in time with the schedule. Moreover, the scaffolding required for field connections shall be checked, and whether the required number of scaffold pipes and boards shall be sufficient. 8.1.8 Scaffolding shall be provided to permit safe operation, and the use of small size piping, pumps, instruments, etc., in lieu of scaffolding shall be prohibited. All scaffold boards shall be securely tied to the scaffold pipes or piping with metal connectors or iron wire. 8.1.9 The primary cards, cables, and grounding wires of all welding equipment shall be of sufficient size, and any conductors with damaged insulation shall not be used. They shall be inspected periodically. 8.1.10 Piping components such as pipe spools and valves shall be lifted with the designated wire rope slings, and the use of iron wire shall be prohibited. 8.1.11 Piping components shall be hauled by mechanical equipments as far as possible. Even for a short haul, the components shall be securely tied to prevent them from falling. 8.1.12 Piping requiring cold spring may become misaligned during field welding, therefore, the dimensions shall be checked thoroughly in accordance with the piping drawings. After it has been confirmed that guides and anchors have been installed at the specified location, the piping shall be installed. Furthermore, when there are flanged joints in the same direction requiring cold spring, a spacer with the same thickness as the dimension of cold spring shall be inserted between the flanges, and when the entire piping system has been assembled, the spacer shall be removed and the flange fastened. 25ES205 / 10 PAGE 14 OF 28 8.1.13 Alignment tolerances of flange connections installed in piping shall be as per Figure 9 ( Page 28 of 28 ). However, alignment tolerances of pipe flanges for the rotational equipment nozzle shall be as per Section 8.3.0 ( Item 6 ). 8.1.14 In principle, the longitudinal welded joint of welded pipe shall be located above the horizontal centerline, if the pipe is installed horizontally. 8.2.0 PIPING AROUND COLUMNS, DRUMS AND HEAT EXCHANGERS The piping installation around columns, drums, and heat exchangers shall be as follows: 8.2.1 Piping for columns shall be installed in the order of the overhead line and the risers, and the installation of instrument take-off nozzles, supports, spring hangers,etc. The levelness and plumbness of piping shall be complete and true. 8.2.2 For piping installed at high elevations at the top of columns, drums, etc., assembly and nondestructive examination and pressure testing shall be performed on the ground, as far as possible, to minimize work at high elevations. When piping installation is unavoidably performed at high elevations, the area below shall be fenced in with a safety rope and “MEN AT WORK ABOVE” signs shall be posted. 8.2.3 When piping components are to be lifted into place at high elevations by means of large cranes, in advance, the work data such as the weight, position of center of gravity, reach of crane, crane boom length, and other vital data shall be ob tained, and they shall be studied sufficiently. 8.2.4 Temporary supports shall not be taken from the shell (body) of equipment. 8.2.5 After the pipe spool has been installed accurately to the nozzle of the equipment, field welding shall be performed. In such cases, blinds shall not be inserted for purposes of pressure testing, etc. 8.3.0 PIPING AROUND PUMPS AND COMPRESSORS The piping installation around pumps and compressors shall be as follows. 8.3.1 All piping except for the connections to the nozzle of rotating machinery shall be assembled on the ground. 8.3.2 Before installation of piping to rotating machinery, the required heat treatment, pressure test ing, interior cleaning, etc., shall be completed. Pressure testing shall not be performed by inserting the blinds directly between the nozzle of rotating machinery and the flange of the connected piping. 8.3.3 The protective cover placed on the nozzle of rotating machinery shall not be removed until the piping is to be connected. 8.3.4 The preset-piece of spring hangers shall be taken off and spring hangers shall be adjusted, so that piping is located accurately. 8.3.5 It shall be confirmed that alignment work of rotating machinery and measurement preparation for inspecting misalignment has been completed. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 8.3.6 8.3.7 8.3.8 8.3.9 8.4.0 8.4.1 8.4.2 8.5.0 8.5.1 8.5.2 FABRICATION & ERECTION OF STEEL PIPING Pipe flanges shall be aligned with all the nozzles of rotating machinery. The alignment shall be performed by the adjustment of pipe supports and flange connections. Unless otherwise speci fied, the misalignment between flanges shall be within the following permissible limits: a. Flange face separation ( space for gasket ) : ± 0.8mm b. Flange face parallelism : 0.2mm c. Rotational offset : 0.8mm d. horizontal and vertical bolt hole offset : 0.8mm If the piping alignment specified in Item (6) above is not within the permissible limits, it shall be corrected. The correction of piping alignment or the adjustment work of supports shall be performed by dismantling piping from rotating machinery. Care shall be taken so that expansion or distortion due to welding, etc., does not have a detrimental influence on the rotating machinery. When connecting piping to a rotating machine, if the machine misalignment is more than the values specified, alignment work of the machine and piping shall be performed again by dismantling the piping from the machine. After piping is connected to rotating machinery, the rearrangement of pipe supports or retightening of flange bolts shall not be performed without permission. PIPING AROUND FIRED HEATERS Piping installation around fired heaters shall be as follows: Since piping around the burner tends to become complicated, piping for one or two burners shall be installed first, and after confirming operability, clearance, safety, and other matters, other piping shall be installed. Drain piping around the burner shall not be placed on the ground or in such a way as to obstruct passage of persons. PIPING ON PIPE RACK Piping installation on pipe rack shall be as follows: Generally, since air cooled heat exchangers are placed on top of the pipe rack, and pumps are placed underneath, the precedence for installing piping shall be determined in consideration of the time of installing such equipment, the number of stages of the pipe rack itself, etc. In principle, piping installation will be performed from the bottom to the top level. When installing piping, a check shall be performed to ensure that the pipe rack beams have been painted. Before connecting piping to other equipment, piping on pipe racks shall be laid down accurately in the places specified beforehand, and then slide shoes and stoppers shall be installed accurately in accordance with the drawings, so that baseline for dimensional adjustments in field installation may be made. However, elbows, tees, etc., required for take-off connections to outside the pipe rack may be left in place temporarily since it may be re quired to perform 8.5.3 8.5.4 8.6.0 8.6.1 8.6.2 8.6.3 8.6.4 8.6.5 8.6.6 8.6.7 8.7.0 8.7.1 8.7.2 8.7.3 8.7.4 8.7.5 25ES205 / 10 PAGE 15 OF 28 adjustments. After the pipe has been laid on the rack, the pipe shall be tied with wire to prevent it from falling off until the weld joints are made. The pipe fittings and welded lines shall be installed so as not to be positioned on the beams. OFFSITE PIPING Installation of offsite piping shall be as follows: Piping installation inside the dike shall be performed after a thorough study of the work schedule has been made, with consideration given to other related work such as the confirma tion of time of tank water filling and of access for handling materials. Pipe sleepers and support footings inside the dike shall be installed after confirming that the levelness of the ground has not been disturbed by the water filling test of the tank. Piping to be connected to the tank nozzle shall be installed after checking that the valve and accessories installed on the tank are in accordance with the specification. Flexible hoses and expansion joints to the tank nozzle shall be installed accurately in accordance with the drawings. When laying pipe on sleepers, the sleepers shall be checked to confirm that they are at the specified elevation, level in line, and painted. Piping on pipe sleepers shall be laid on sleepers that have been marked off. Slide shoes and stoppers shall be installed accurately in accordance with the drawings. The pipe fittings and welded lines shall be installed so as not to be positioned on the sleepers. For piping penetrating an oil dike, the flanged, threaded, or welded joints shall not be embedded in the dyke. INSTALLATION OF VALVES The installation of valves shall be as follows: The valve shall be installed accurately so that its location and the orientation of the handle is in accordance with the piping drawings. However, when the orientation of the handle is deemed inappropriate from the viewpoint of operation or passage, the FEDO engineer shall be contacted for directions. The valve shall be checked for its class, body materials, and trim materials to prevent any misuse. Before installing the valve, the flange faces of the valve and the connected piping shall be checked to see that they are not damaged or dirty, and that they are parallel with each other. Valves shall be installed in the closed position, except for plug valves and ball valves. After being installed, valves shall not be opened except for pressure testing. Especially, welding for installation of the butt weld and socket weld type valves shall be performed in the closed position, to prevent the valve seat being damaged. For lubricant plug valves, the disc shall be left in the open position and the lubricant shall be replenished to prevent loss of the sealant. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 8.7.6 FABRICATION & ERECTION OF STEEL PIPING Globe valves, check valves, control valves, and other similar valves shall be installed in accord ance with the marked direc tion by checking the flow direction. 8.7.7 To prevent the stem threads from rusting, grease shall be applied prior to installation of the valve. 8.8.0 INSTALLATION OF SAFETY VALVES The installation of safety valves shall be as follows: 8.8.1 Until line pressure testing has been completed, in principle, the safety valves shall not be in stalled with the piping. If safety valves are necessary to assemble the piping, a spool of the same face-to face dimension shall be fabricated and installed. For threaded safety valves, the piping shall be capped. However, the safety valve with test gag may be installed with piping and subjected to line pressure testing. 8.8.2 All safety valves shall be installed after the specified set pressure has been tested in the field. 8.8.3 The seal securing the cap to the safety valve body shall not be removed without FEDO / Representative’s approval. 8.8.4 The safety valve with a lever shall be installed with the lever oriented as shown on the drawing. 8.9.0 Installation of expansion joints The installation of expansion joints shall be as follows: 8.9.1 Expansion joints shall be installed accurately and shall be at the location and of the dimensions shown on the piping and detailed drawings, and in a manner so as not to be connected eccen tric with the pipe. 8.9.2 Expansion joints shall be installed after confirming that the line has been completely assembled with all anchors, guides, and stoppers installed in place as shown on the piping drawings. 8.9.3 Expansion joints shall be installed so that no stress except in the direction intended occurs. 8.9.4 After pressure testing and flushing, all shipping bolts and fixtures shall be removed and the joints shall be checked to ensure that nothing obstructs the expansion movement. 8.9.5 Prior to installation, expansion joints with inner sleeves shall be checked to ensure that the sleeve inlet (fixed) is on the upstream side. 8.9.6 Bellows of expansion joints shall be handled with utmost care, so that no objects will be dropped upon it. 8.9.7 Each expansion joint shall be blown free of dust / foreign matter with compressed air or shall be cleaned with a piece of cloth. 8.9.8 For handling and installation of expansion joints, great care shall be taken while aligning. An expansion joint shall never be slinged with bellows corrugations/external shrouds, tie-rods, angles etc. 8.9.9 An expansion joint shall preferably be slinged on the end pipes/flanges or on the middle pipe. 8.9.10 The pipe ends in which the expansion joint is to be installed shall be perfectlyaligned or shall 25ES205 / 10 PAGE 16 OF 28 have specified lateral deflection as noted on the relevent drawings. 8.9.11 The pipe ends / flanges shall be spaced at a distance specified in the drawings. 8.9.12 The Expansion Joint shall be placed between the mating pipe ends/flanges and shall be tack welded/bolted. The mating pipes shall again be checked for correct alignment. 8.9.13 Butt welding shall be carried out at each end of the expansion joint. For flanged Expansion Joint, the mating flange shall be bolted. 8.9.14 After the Expansion Joint is installed the contractor shall ensure that the mating pipes and Expansion Joint are in correct alignment and that the pipes well supported and guided. 8.9.15 The Expansion Joint shall not have any lateral deflection. The contractor shall maintain parallelism of restraining rings or bellows convolutions. 8.10.0 INSTALLATION OF INSTRUMENTS 8.10.1 Kinds of instrument handled 1. The following instruments shall be installed in the scope of piping installation work: a. Flow meters to be installed directly on the line (area type, volume type, magnetic type, etc.). b. Orifice flanges and orifice plates c. Displacer type or ball float type level meters d. Control / self control valves & safety valves e. Other instruments installed directly on the line 2. In addition, instruments up to the first valve or flange in the nozzle take-off connections for the instrument lead piping are included. 8.10.2 General Procedure : General installation procedure for instruments shall be as follows: a. All instruments shall be checked as to instrument number and shall be installed true to level, plumbness, or the specified angle b. The instruments and the associated piping (excluding instrument piping) shall be supported so that problems will not result due to distortion or vibration c. It is preferred to have all the instruments installed after the interior of piping, columns and drums have been cleaned. When instruments are to be installed unavoidably during piping construction, measures shall be taken to prevent the instruments from being damaged and to prevent foreign matter from entering the instruments. Orifice plates shall be installed only after testing and flushing of pipes. d. Flow control valves shall be installed after checking the flow direction mark. 8.10.3 Installation of Flow Meters : The installation of flow meters shall be as follows: a. When installing orifice flanges, the straight lengths of pipe required upstream and downstream shall be checked to see that they comply with the piping drawings. In principle, the upstream straight pipe length shall be of one piece. When there is an unavoidable welded line in the length, the distance between the orifice and the weld FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION FABRICATION & ERECTION OF STEEL PIPING line shall be not less than 14 times the pipe diameter. The straight lengths of pipe shall not be provided with a vent, drain, or other similar branch. b. Jack screws for orifice flanges shall be installed so that they are 180O apart from each other. c. When taps are to be taken off from a pipe, the holes shall be drilled where shown on the drawings, the burrs removed and the holes made smooth. Sockets shall not be embedded in the pipe. d. The orientation for pressure differential taps shall be accurate as shown on the drawings e. Orifice plates shall not be installed until the pipe interior has been cleaned. f. When installing orifice plates, the orifice plate number and the flow direction shall be checked. In general, the handle is pointed upwards and the inlet die stamp mark end is pointed upstream. g. An orifice plate shall be installed with its center coinciding with the center of the pipe and with the gasket not protruding into the pipe. g. An orifice plate shall be installed with its center coinciding with the center of the pipe and with the gasket not protruding into the pipe. h. Installation of flow meters such as area type, column type, and magnetic type shall be in accord ance with the instructions of the FEDO Engineer. 8.10.4 Installation of Control Valves : The installation of control valves shall be as follows: a. Control valves shall be installed by checking the flow direction and, except for special cases, with the diaphragm at the top in a vertical position. b. To prevent internal and external damage and entry of foreign matter during construction, control valves shall be installed during the last stage after pressure testing and flushing of the line. In this case, a spool having the same face-to-face dimension as the control valve shall be inserted to keep the distance during construction. Further more, after the piping around the control valve has been installed, the dimensions shall be checked to confirm that the valve can be fit in place. c. When installing control valves unavoidably during construction, a blind gasket, galvanized iron sheet, or other suitable material of the same thickness as the main gasket shall be inserted to prevent entry of foreign matter. During construction, control valves shall be covered with vinyl sheet or other suitable material, and care shall be taken not to damage the valves. During pressure testing and flushing of the line, the valve shall be removed and the end flanges of the valve shall be covered up. 25ES205 / 10 PAGE 17 OF 28 9.0.0 INSPECTION AND TEST 9.1.0 DOCUMENTS The Contractor shall submit the following inspection records for each items of test and inspection: Non-destructive inspection 9.1.1 9.1.2 9.1.3 9.2.0 9.2.1 a. Record of radiographic inspection b. Record of magnetic particle inspection c. Record of liquid penetrant inspection d. Record of ultrasonic inspection e. Records of stress relieving f. Records of hardness test g. Records of hydrostatic & pneumatic pr. tests Destructive inspection Record of welding procedure qualification test Others specifically instructed Following are to be indicated on the test and inspection record 1. Name of customer 2. Job number and name of work 3. Name of contractor 4. Line number 5. Date of test and inspection 6. Name(s) of attendant (FEDO, Customer, or third party) ITEMS OF INSPECTION AND TEST Prior to, during and after completion of the works, the following tests and inspections shall be performed. ITEMS FOR INSPECTION AND TEST PRIOR TO COMMENCING WORK Checking materials Legal qualification certificate Welding procedure test Welder’s technique qualification test welder’s techniqe qualification certificate Welding rod check PRIOR TO WELDING WORK Edge preparation Angle, Root opening, Thickness of land, Cleanliness Shape of pipe end Out of roundness, Thickness, Uneven thickness Bending Degree of flattening at bent part, Radius of curvature, Thickness reduction at bent part Tack welding Bevelled end misalignment, Root opening Preheating Method of preheating, Temperature of preheating, width of heating, Temperature measurement, Heating temperature, Others FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION Welding rod 25ES205 / 10 FABRICATION & ERECTION OF STEEL PIPING Drying temperature, Drying time DURING WELDING WORK Welding parameters, Flow rate of sealing gas, ProtectWelding condition ing measure for welding, Condition of ambient temperature PAGE 18 OF 28 6 Under cut No under cut is allowed for piping of cold or high temperature service. 7 Over lap 8 Height of reinforcement Inter-layer temperature : Within 0.8mm or 12.5% of thickness whichever smaller : 1.5mm or less Nominal Wall Thk. Re-examination of welder Up to 6.4mm : 1.6mm or less Inside surface misalignment, Outer surface misalignment, Inside surface weld Visual approtrusion, Wave irregularity, pearance inspec- Uneven leg length, Irregular tion height of bead, Undercut, Overlap, Bead centre shift, Height of reinforcement welds Over 6.4mm up to 12.7mm ; 3.2mm or less over 12.7mm up to 24.5mm : 4.0mm or less Over 24.5mm : 4.8mm or less Non-destructive inspection Throat thickness of fillet welds AFTER COMPLETION OF WELDING WORK Radiography, Dye penetrant, Magnetic particle : 70% of thickness of the inner plate or more Stress relieving temperature and method Hardness test DURING OR AFTER COMPLETION OF WELDING WORK Product inspection 9.4.0 9.4.1 Dimension, Condition of connection to equipment, Visual apperance inspection Non-destructive inspection Non-destructive inspection shall be performed according to the grade of inspection stipulated in the next table. (Pressure classes in accordance with ANSI B16.5) Grade of Inspection Treatment of pipe inside Material Thread Seal welding of threaded portion AFTER COMPLETION OF WORK Pneumatic pressure test Carbon steel Removal of temporary supports / scafoldings AT TRIAL OPERATION Appearance inspection 9.3.0 9.3.1 VISUAL APPEARANCE EXAMINATION Following shall be met, checking visually or in using measuring instrument 1 2 3 Inside surface : 1.5mm or less misalignment Outer surface misalignment due to difference of : 3.0mm or less diameter of thickness Inside surface weld protrusion Nominal Wall Thk. Up to 6.4mm : 1.6mm or less Over 6.4mm to 12.7mm : 3.2mm or less Over 12.7 up to 25.4mm : 4.0mm or less Over 25.4mm : 4.8mm or less 4 Wave irregularity ; 2.5mm or less 5 Irregular height of bead : 2.0mm or less II III P - NO: 1 Completion of work w.r.t piping drawings Flushing I Pressure classes - ANSI B16.5 (psig.) Service temp. below 3500C Less than 300 lb 400 lb 1500 lb 2500 lb and above Service temp. 3500C or more - 150 lb 900 lb 1500 lb and above - 150 lb 900lb 1500 lb and above - 150 lb 900 lb 1500 lb and above - 150 lb 900 lb 1500 lb and above A312 Gr. TP304 Less than 150 lb @ 300 lb 600 lb 900 lb and above Other than above - 150 lb 300 lb 400 lb and above Al-killed Steel P - NO: 3, 4, 5 C- 0.5 Mo Steel Cr- Mo Steel P - NO: 9 3.5 Ni steel P - NO: 8 Austenitic stainless steel Note: 9.4.2 @ When A312 Gr. TP304 is used for cold or high temperature service, the grade II of inspection shall be applied even if it is not above 150 lb. Items of non-destructive inspection and number of samples for the random inspection shall be as follows: FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION FABRICATION & ERECTION OF STEEL PIPING ITEM OF INSPECTION R - Radiographic Inspection M - Magnetic particle Inspection L - Liquid PenetrantInspection Object of inspection Material Peri phery Nozzle (1) Soc ket Non pressure part GRADE - I R Carbon steel Less than 150 lb A312 Gr. TP304 - - - - - - 10 % (2) 10 % 10 % 10 % (4) 100 % - - - 9.4.3 10 % GRADE - II R All materials 20 % Carbon steel - M (3) C-0.5 Mo steel Cr-Mo steel Al-killed steel 3.5-Ni steel L (3) Austenitic stainless steel Non-ferrous metals GRADE - III R All materials M (3) All materials except for austenitic stainless steel, non-ferrous metals & non-magnetic metal L (3) Austenitic Stainless steel Non-ferrous metal % 20 % 100 % 100 % 20 (4) Notes (1) In “nozzle welding”, welded parts of reinforcing plate and slip-on flange are included. (2) This inspection shall be performed for the welded parts other than those to which radiographic inspection was applied. (3) Either magnetic particle inspection or liquid penetrant inspection shall be performed. (4) This inspection shall be performed for Cr-Mo steel (A335 Gr. P5 or over grade) and 3.5Ni steel. Remarks 1. Radiographic inspection for peripheral joint shall be performed for pipes of nominal diameter of 2" or more having the same condition. 2. Number of random sampling test shall be at least one, when less than one is obtained in percentage of sampling 3. Number of photographs to be taken for one peripheral joint at radiographic inspection shall be as follows: PIPE SIZE NB NO. OF PHOTOGRAPHS 50 to 80 150 x 2 sheets 100 to 150 300 x 3 sheets 9.4.4 PAGE 19 OF 28 200 to 300 300 x 4 sheets 350 to 400 300 x 5 sheets 450 300 x 6 sheets 500 300 x 7 sheets 600 300 x 8 sheets 650 & above With film overlap of 25mm or more, no of photographs shall be equivalent to peripheral length of the pipe 3% Over 150 lb to 300 10 % lb 25ES205 / 10 Radiographic examination Unless otherwise specified, radiographic examination shall be as follows: 1. Radiographic inspection shall be performed in accordance with Article 2, Section V of the ASME Boiler and pressure vessel code. 2. The welds to be examined shall be selected based on the number of work products of each welder and welding operator engaged in all welding operations. A minimum of one weld per sample shall be examined. 3. All welded joints in a designated lot of piping shall be radiographed over the complete circumference. 4. When a random type examination reveals a defect, additional examination shall be performed in accordance with the requirements of appendix IV. 5. The radiation source shall, in principle, be x-ray or Gama-ray. 6. Film such as Sakura RR, Fuji #100, Kodak AA, or Equivalent shall be used. 7. Identification mark as shown in Figure 10 ( Page 28 of 28 ) shall be marked on every radiograph, and radiographs of repair weld shall be marked with repair mark (R). 8. The image quality indicator (IQI) specified in B UB-51, ASME Section VIII, Division 1, or equivallent shall be used. 9. Limitations on imperfection shall be in accordance with ANSI B31.3 TABLE 327.4.1 (A) for the degree of radiography involved. Magnetic Particle/Liquid Penetrant Examination Liquid penetrant or magnatic particle examination shall be as follows: 1. Liquid penetrant inspection shall be performed in accordance with Article 6, section V of ASME Boiler and pressure vessel code. 2. Limitations on imperfection shall be in accordance with ANSI B31.3 Table 327.4.1 (A) 3. The weld surface, to which liquid penetrant or maganetic particle examination is applied, shall be finished smoothly with a grinder as necessary. 4. If a defect is found in welds, the defect shall be removed, and liquid penetrant examination or maganitic particle examination shall be performed again to confirm that no more defects exist., and then rewelding shall be performed. After rewelding has been completed, liquid penetrant examination or maganetic particle examination shall be FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION FABRICATION & ERECTION OF STEEL PIPING performed again to confirm that the rewelds are sound. a. Magnetic particle inspection shall be performed in accordance with Article 7, Section V of the ASME Boiler & pressure vessel code b. Limitations on imperfection shall be in accordance with ANSI B31.3 Table 327.4.1 (A) 9.5.0 9.5.1 9.5.2 9.6.0 9.6.1 9.6.2 9.6.3 HARDNESS TEST After stress relieving (SR) is performed, hardness shall be tested as follows: 1. If SR is performed by heat coil, the hardness test shall be carried out for all welds. 2. If SR is performed in furnace, hardness test shall be performed for 10% of all welds (at least one-when 10% of all is less than one) 3. Point to be tested shall be finished flat with file before the test. 4. The hardness points shall be tested to weld and to heat affected zone. Hardness test of the heat affected zone shall be made at a point as near as practicable to the edge of the weld. When dissimilar materials are welded, both heat affected zones shall be tested. Hardness limit is given in following table ( Hardness In Brinell Max. ) P-No. MATERIAL HB (MAX) P-3 A335 Gr.P1 (STPA12) 225 P-4 A335 Gr.P12 (STPA22) A335 Gr. P11 (STPA23) 225 P-5 A335 Gr. P22 (STPA24) A335 Gr. P5 (STPA25) 241 PRODUCT INSPECTION Inspection for the finished product shall be performed as follows: Dimension: Right angle, perpendicularity, parallelness, dimension, etc. shall be measured visually and by measuring tools and checked against the drawings. Dimensional tolerances are as follows: 1. Length + 0 ; -3.2mm or less 2. Inclination of flange surface: less than 0.5o against the surface perpendicular to the axis of pipe. (but, not to exceed 2mm at outside circumference of flange). 3. Perpendicularity of vertical line: 2/1000 or less. 4. Horizontality: 2/1000 or less 5. Misalignment between flange center and pipe center: 1.6mm or less 6. Shift of bolt hole center: 1.0mm or less. Inspection of connection to equipment: For those pipings which are connected with pump, compressor, turbine, etc., the above dimensional tolerance shall be submitted by the tolerances required by each of such machinery. Appearance inspection: 1. Correction for jig mark. 9.7.0 9.7.1 25ES205 / 10 PAGE 20 OF 28 2. Removal of spatter and slag 3. Any harmful flaw on the flange face, inner and outer surface of pipe. 4. As-erected condition 5. Shape and size of branches and other attachment shall comply with drawings. Inspection for treatment of pipe inside Inspection shall be performed visually and touching by hand to confirm that no rust, slag, spatter, sand, or other foreign matters are left. Inspector must confirm whether sufficient flushing was performed. 10.0.0 PRESSURE TEST AND OTHERS 10.1.0 GENERAL 10.1.1 Prior to initial operation, the installed piping shall be pressure tested under witness of FEDO Engineer/ Representative. 10.1.2 Prior to the pressure test, a line check shall be performed based on P&I diagrams and the piping draw ings, in accordance with the instructions of the FEDO Engineer/ Representative. 10.1.3 Types of pressure test are as follows, however the test shall be performed in accordance with the individual specification: 1. Pressure tests Hydraulic test (using water or other liquids) Pneumatic test 2. Leak test Overall air tightness test 10.1.4 Before filling it with the test fluid, the entire line to be pressure tested shall be examined in the manner described in Section 9.0.0, and any faults shall be repaired. The piping affected by any repairs or additions made after the pressure test shall be retested. 10.1.5 In principle, piping shall be pressure tested at a metal temperature not less than 20C. However, carbon and alloy-steel piping exceeding 25mm in thickness shall be pressure tested at a temperature not less than 160C. 10.1.6 The following equipment and instruments shall not be connected to the piping before completion of the pressure test: 1. Rotating machinery such as pumps, turbines, and compressors. 2. Pressure relieving devices, such as rupture discs and pressure relief valves. 3. Equipment that has a castable or lining material . 4. Instruments. 5. Piping which is normally open to the atmosphere such as drains, vents, and discharge piping from pressure relieving devices. 6. Any other designated equipment. 10.2.0 TEST FLUID Test fluid shall be as follows: 10.2.1 In principle, the fluid for hydrostatic testing shall be fresh water. Unless otherwise specified, the FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION chlorine ion concentration in the fluid used for austenitic stainless steel piping shall not exceed 30 ppm. After completion of the test, the water shall be drained immediately, and the interior of the pipe shall be dried by an air blower, etc. 10.2.2 For piping systems having strong acids and So2 where water may become corrosive, or piping systems operated at a temperature of 00C or less, kerosene or similar light oils (with a flash point not less than 500C) or air is preferred as the test fluid. 10.2.3 The air to be used for pneumatic testing shall be compressed air from a portable compressor. However, for instrument air lines or where specifically specified, oil-free dry compressed air or inert gas shall be used. For high pressure piping (not less than 100 kgf/cm2G), the use of inert gas is preferable. When pneumatic testing is performed by the use of an air compressor, precautions against combustion shall be taken by blowing clean the oil separator thoroughly so that no lubricant enters the air. 10.3.0 TEST PREPARATION The preparation for pressure test shall be as follows: 10.3.1 All joints (including welds) are to be left uninsulated and exposed for examination during the test. However, joints previously tested in accordance with this standard may be insulated. 10.3.2 When filling water into piping that is designated for vapor, gas, etc., not filled with water during operation, temporary supports or other reinforcements shall be provided beforehand. 10.3.3 Special fittings in piping components, such as expansion joints, filters, and flame arrestors, shall be disconnected from the piping. 10.3.4 Equipment which is not to be subjected to the pressure test shall be either disconnected from the piping or isolated by blinds or other means during the test. 10.3.5 If a pressure test is to be maintained for a certain period and the test liquid in the system is subject to thermal expansion, precautions shall be taken to avoid excessive pressure. In particu lar, for hydrostatic testing, care shall be taken to ensure that the water will not be subject to thermal expansion so that the piping is not damaged during the test. 10.4.0 TEST PRESSURE 10.4.1 Hydraulic Testing of Internally Pressured Piping 1. The test pressure for piping subject to internal pressure shall be as follows: a. Not less than 1.5 times design pressure b. For a design temperature above the test temperature, the minimum test pressure shall be calculated by the following formula. PT = 25ES205 / 10 FABRICATION & ERECTION OF STEEL PIPING 1.5PST S Where PT= minimum hydrostatic pressure in kgf/cm2 G PAGE 21 OF 28 P = internal design pressure in kgf/cm2 G ST= allowable stress in kgf/cm2 at test temperature S = allowable stress in kgf/cm2 at design temperature 3. If the test pressure as defined in Item (2) above produces a stress in excess of the yield strength at the test temperature, the test pressure may be reduced to the maximum pressure that will not exceed the yield strength at test temperature. 10.4.2 Hydrostatic testing piping with vessels as a system 1. Where the test pressure of piping attached to a vessel is the same as or less than the test pressure for the vessel, the piping may be tested with the vessel at the test pressure of the piping. However, the test pressure shall be controlled carefully so as not to exceed the test pressure of the vessel. 2. Where the test pressure of piping exceeds the vessel test pressure, the piping shall be tested by isolating it from the vessel. 10.4.3 Hydrostatic testing of externally pressured piping : The test pressure for piping subjected to external pressure shall be as follows: a. Lines in external pressure service shall be subjected to an internal test pressure of 1.5 times the external differential design pressure, but not less than a pressure of1.0 kg/cm2G (15 psig). b. In jacketed lines, the internal line shall be pressure tested on the basis of the internal or external design pressure, which ever is critical. The jacket shall be pressure tested on the basis of the jacket design pressure unless otherwise specified. 10.4.4 Pneumatic testing 1. In principle, pressure tests shall be performed hydraulically, however, when it is inappropriate to fill piping with water, the test may be performed with air or inert gas. The test pressure shall be 1.1 times the design pressure. 2. Any pneumatic test shall include a preliminary check at not more than 1.75 kgf / cm2G (25 psig) pressure. The pressure shall be increased gradually in steps providing sufficient time to check for leaks. 10.5.0 TESTING METHOD The method of pressure testing shall be in accordance with the instructions of FEDO. However, the general method by using water shall be as follows: 10.5.1 In principle, pressure tests shall be performed for each piping system. However, when design conditions do not permit testing in such a manner, the system may be tested in sections. 10.5.2 Test blinds shall have a handle extending out from the flange. The handle shall be painted in red, to ensure removal of blind after testing. 10.5.3 Installation and removal of blinds shall be performed in accordance with the instructions of FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 25ES205 / 10 FABRICATION & ERECTION OF STEEL PIPING FEDO. The number or all the blinds used and the location of the insertion shall be recorded at all times. 10.5.4 Test pressure gauges with graduations up to two times the prescribed test pressure shall be provided. All the pressure gauges shall be certified by the national authority, and the calibrations shall be checked by periodic inspections. 10.5.5 Two or more pressure gauges shall be installed so that they are easily observed. When the piping system to be tested extends from a low to a high level, pressure gauges shall be installed at both the lowest and the highest points. 10.5.6 For each piping system, an outlet for discharging the pressure in case of emergency shall be designated and marked to that effect. 10.5.7 During pressure testing of piping, operation of valves shall be prohibited and the valves shall be marked to that effect. 10.5.8 Prior to pressure testing, it shall be confirmed that a strainer is provided at a designated location to remove foreign matter. 10.5.9 Vents on piping subjected to hydrostatic testing shall be opened to remove the air when filling the piping with water. 10.5.10 Prior to hydrostatic testing, the piping shall be checked to confirm that it is free from air pockets and if necessary, temporary vents shall be provided to eliminate the air pockets until testing is completed. 10.5.11 For piping systems with a check valve, the pressure shall be applied from upstream of the valve. If this is impractical, the check valve shall either be reversed or shut off with blinds. However, when reversed, the valve shall be reinstalled correctly after testing. 10.5.12 When the test pressure is not less than 50 kgf / cm2G, pressure shall be increased gradually. 10.5.13 The test pressure during a pressure increase shall be read by the pressure gauge installed at the lowest point of the piping in consideration of the water head pressure. 10.5.14 The check for any leaks during the pressure test shall be performed after the prescribed pressure is maintained for a time not less than 10 minutes. All connections and all welded joints shall be inspected thoroughly. 10.5.15 After the completion of pressure testing, the water shall be drained immediately from the line to prevent the piping system from being damaged by freezing or thermal expansion. Also to prevent vacuum forming in the piping, the vents shall be opened when the water is being drained. 10.5.16 On completion of pressure testing, the line shall be checked to see that no residual pressure is present, and the line shall be drained. All blinds shall be removed. 10.5.17 Short pieces of pipe, which must be removed for installing blind plates and blind flanges, shall be tested separately. 10.5.18 All valves, orifice plates, expansion joints, short pieces of pipe, and other items removed or installed for the test, shall be reinstalled with the prescribed gaskets in the correct position. PAGE 22 OF 28 10.6.0 REPAIR OF DEFECTS The repair of defects found during test and inspection of piping systems shall be as follows. In principle, the repair shall be performed under witness of FEDO after the approval of the FEDO Engineer has been given. 10.6.1 Repair of welds a. Repair welding shall be performed after the pressure and liquid remaining in the pipe have been removed. b. The defects to be repair welded shall be removed completley with a grinder, etc. c. The welding, the heat treatment, and the test and inspection shall be the same as required for the initial welding, and performed in accordance with the applicable provisions of this specification. d. In principle, repair welding of the same portion shall not be performed more than twice. 10.6.2 Repair of Threaded Joints All defective threaded joints shall be replaced with complete new ones. 10.6.3 Repair of Flange Joints All defective flange joints shall be replaced with complete new ones, except those which can be repaired in accordance with Section 5.2 (15). 10.7.0 FLUSHING AND CLEANING 10.7.1 Selection of cleaning method Cleaning method shall be selected in the following methods considering kind of fluid, pipe material and condition of internal surface of piping to be cleaned. Cleaning method and extend of cleaning shall be as per specific Project Requirements. a. b. c. d. e. f. Water Flushing Air Blowing Steam Blowing Acid Cleaning Oil Cleaning Others 10.7.2 Procedure of cleaning in general 1. Cleaning of fabricated pipings Inside surface and face of weld of fabricated piping shall be made free from slag, chamfer, scale and other foreign matter, with grinder, chisel, wire brush, etc., and be airblown. After completion of air blowing and checking, ends of the piping shall be covered with vinyl or veneer cap, etc. till the installation in the field. 2. Temporary Strainers Temporary strainers shall be used as follows: a. After installation of piping, and before commencement of flushing/cleaning. b. The temporary strainers shall be installed at pump suction piping, upstream of control valve and other locations as specified. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION FABRICATION & ERECTION OF STEEL PIPING c. Mark plate shall be attached to the temporary strainers to distinguish from other strainers. d. After a constant period of initial operation, all temporary strainers shall be removed, cleaned and reinstalled. 10.8.0 WATER FLUSHING 10.8.1 Cleaning method by water 1. As a rule, pure water, service water, steam condensate, industrial water, etc. shall be used. If there is any requirement about the quality of water to be used, it shall be observed. 2. After flushing, drying by compressed air or natural drying shall be carried out. Drying by superheated steam shall be carried out with agreement between Customer and FEDO. 3. Flushing shall be performed till the water becomes free from foreign matter, scale, etc. This shall be decided by observing turbidity of water taken out ( into beaker or cup). 4. Water flushing shall be performed by the method of running by pressurised water and hammering, or rapid draining with water filled. Hammering shall, however, not be performed for austenitic stainless steel pipe, copper pipe, aluminum pipe. 5. The primary cleaning shall be performed for each assembled piping system including the equipment. 6. Where instruments are included in piping system to be cleaned, the instruments shall, as a rule, be disconnected and spool pipe (distance piece) shall be inserted instead. 7. When cleaning is carried out in the condition that control valve is connected, the procedure shall be as follows: a. Disconnect companion flange at upstream side of the control valve and cover opening of the control valve. b. Clean the piping of upstream side. c. Connect the control valve and the piping of upstream side after cleaning. d. Close the control valve, open by-pass valve, and then clean the piping of down stream side. Where the by-pass valve is not installed, the temperory strainer having austenitic stainless steel screen of No. 50 specified in ASTM E-11 shall be inserted. 10.8.2 Air blowing 1. Air blowing shall be performed by the method of blowing by pressurized air and hammering. Hammering shall, however, not be performed for austenitic stainless steel pipe, copper pipe and aluminum pipe. 2. Blowing shall be performed till there remains no scale in the piping. FEDO personnel in charge shall make judgement of whether the result of the cleaning is statis- 25ES205 / 10 PAGE 23 OF 28 factory or not 3. The primary cleaning shall be performed for each assembled piping. The secondary cleaning shall, as a rule, be performed for piping from eqpt. to adjacent eqpt. Whether or not the equipment is included shall be determined considering shape, internal construction & packing of the eqpt. and according to overall cleaning planning. 10.8.3 Steam blowing 1. Execution of steam blowing Steam blowing shall be executed after completion of pressure test and insulation work. 2. Preparation of steam blowing a. Temporary piping work, countermeasure for safety & confirmation of preparation shall be done according to blowing plan. b. Support shall be attached to exhaust piping to prevent accident caused by the reaction force during blowing. 3. Procedure of steam blowing a. Warm up the piping with cooperation by operator b. Check expansion joints, spring hangers, etc., for expected thermal expansion. c. Steam blowing shall be performed at the temperature near to the operating temperature, considering operating condition of boiler. d. To remove the scale effectively by temperature change, it is required to perform flushing and cooling cyclically, having temperature difference as large as possible between the flushing and cooling. 4. Judgement criteria of steam blowing a. Judgement on result of steam blowing shall generally be done by checking color or quantity of foreign material present in the drain sampled. b. If necessary, especially for suction line of steam turbine etc., result of flushing shall be judged by observing whether scratch was produced or not on the test piece inserted in the line. 10.8.4 Acid cleaning 1. Applicable piping of acid cleaning Unless otherwise specified in specific job requirements, acid cleaning shall apply to oil piping system of rotating machinery. 2. Cleaning method by acid As a rule, acid cleaning procedure shall be as follows: FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 25ES205 / 10 FABRICATION & ERECTION OF STEEL PIPING a. Ten-percent hydrochloric acid solution or Ten-percent sulphuric acid solution with temperature 30 to 400 C shall be used, and piping shall be pickled in the acid solution for 1 to 6 hours. b. After pickling, the piping shall be washed sufficiently to remove the acid solution by water. c. And the piping shall be rinsed for neutralization of the acid solution by sodium hydroxide solution, followed by water flushing. d. The piping shall be well dried by superhaeted steam or dry air and the inside of pipes given a coat of the oil of the same quality as specified to be used in the oil piping. Remarks: Oil piping of stainless steel shall not be acid cleaned. 10.8.5 Oil cleaning 1. Applicable piping of oil cleaning Oil cleaning shall apply to the oil piping system after the acid cleaning specified in par. 10.8.4 has been performed. 2. Cleaning method by oil The procedure shall be as follows: PAGE 24 OF 28 10.10.0Disposition 10.10.1All construction equipment used for the piping work, and all surplus, scrap and debris shall be disposed of in accordance with the instructions of the FEDO Engineer. 10.11.0 Test record 10.11.1 All inspection and test results shall be made into re cords in accordance with the instructions of FEDO. The records shall be submitted for approval to FEDO. 11.0.0 APPENDICES 11.1.0 The following Appendices shall form a part of this manual: TITLE REFER TO: Grove face Rust Preventive APPENDIX I Selection of welding electrodes APPENDIX II Procedure for Flange Bolt up APPENDIX III Additional Random Type Examination for weld defects APPENDIX IV a. Oil to be used shall have good quality suitable for the machinery, and shall be completly replaced with the specified oil after cleaning. b. The cleaning shall be performed by the method of circulation of the oil and hammering. Hammering shall, not be performed for copper pipe. c. After completion of cleaning, it shall be checked that no foreign matter is present in temporary strainer screen of No.200 specified in ASTM E- 11 for oil pipings of centrifugal compressor, and screen of No.100 specified in ASTM E-11 for other oil pipings. 10.8.6 Other cleaning method 1. Cleaning method by pig or cushion ball Cleaning by the use of pig or cushion ball shall confirm to specific job requirements. 2. Cleaning method by sodium hydroxide Cleaning by sodium hydroxide solution shall conform to specific job requirements. 3. Special cleaning Special Cleaning, if specified for special piping components or systems, shall conform to specific job requirements. 10.9.0 Overall airtightness test 10.9.1 When specified, an overall airtightness test shall be performed for the piping of process line by the use of air or inert gas after completion of flushing. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION FABRICATION & ERECTION OF STEEL PIPING APPENDIX — I GROOVE FACE RUST PREVENTIVE Features of Product 1. As rust preventive applied to the groove face, in general, deoxialuminite is used as it is not detrimental to the weld. Deoxialuminite is the brand name of a product of Special Chemical Co., Ltd.of USA. This was first produced in Japan by Nippon Oil & Fats Co., Ltd. and is sold under the brand name of Tasteto Silver. 2. The composition of the product is 40% resin, 50% solvent, 5% pigment, etc., and the percentage of resin in the compound is high to reduce the amount of gas produced during welding. 3. This product is recommended for both marine and overland transportation. The thickness of the applied product shall not be more than 30 microns. 4. The adherent durability is not more than three months. Directions for Use 5. Before applying the rust preventive, it shall be confirmed that the groove face is clean. 6. After the rust preventive has been applied, welding shall not be performed within two weeks. 7. In principle, the application shall be sprayed by maintaining a distance not less than 30 cm from the spray nozzle to the object. Unless otherwise specified, the product shall not be applied with a brush. 25ES205 / 10 PAGE 25 OF 28 Procedure for Bolt Up Procedure for flange bolt up shall be as follows 5. Hand tighten bolts with a short wrench by the procedure shown in Figure 11. 6. Tighten bolts a second time with a spanner wrench and light hammer (about 1 kg), again by the procedure shown in Figure 11. 7. Continue tightening gradually by the procedure shown in Figure 11, using a heavy hammer (about 2 kg) until bolts are completely drawn tight. This may take two or three additional rounds by the same procedure. 8. For bolts larger than 25mm in diameter, a final round or two with a heavier hammer (about 3.5 kg) is recommended to reach the correct bolt tension. Precautions Special precautions shall be taken for the following items for bolt up: 9. Never draw up tight on one or two bolts only. This will cause local gasket crushing or pinching, which will result in leaks. 10. After each round of tightening, the alignment may be checked by measuring the distance between flange faces. 11. The bolts should be gradually and evenly tightened with a wrench and hammer until the hammer begins to “bounce” with a distinct ring. APPENDIX — IV APPENDIX — II SELECTION OF WELDING ELECTRODES & RODS Table - I : Selection of welding electrodes & rods for joining similar materials except Aluminium Table - II : Selection of welding electrodes & rods for joining disimilar materials except Aluminium ( Tables overleaf ) APPENDIX — III PROCEDURE FOR FLANGE BOLT UP Confirmation Prior to Bolt Up The following items shall be confirmed prior to bolt up: 1. The gasket has been inserted and centered. 2. Bolts and nuts have been lubricated. 3. Bolts have been inserted and are finger tight. 4. There are at least two threads extending beyond the nut on either side. ADDITIONAL RANDOM TYPE EXAMINATION FOR WELD DEFECTS (Taken from ANSI / ASME B31.3b-1982, 336.5) When the required examination of a spot or random type reveals a defect requiring repair, two additional examinations of the same type shall be made on the same kind of item (if of a weld, others by the same welder or welding operator). If the second group of items examined is acceptable, all items represented by these additional examinations shall be accepted. For each of the second group of items which reveals defects requiring repair, two additional items shall be examined. If all of the third groups of items examined are acceptable, the items requiring repair shall be repaired or replaced to meet the requirements of the code, and all items represented by the examined items shall be accepted. If any of the third group of items examined reveal defects requiring repair, all comparable items may be replaced or they shall fully examined and repaired as necessary to meet applicable quality requirements. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 25ES205 / 10 FABRICATION & ERECTION OF STEEL PIPING PAGE 26 OF 28 TABLE - I : SELECTION OF WELDING ELECTRODES & RODS FOR SIMILAR MATERIALS EXCEPT ALUMINIUM MATL. NO. BASE MATERIAL 1 UTS UNDER 60,000psi 2 carbon steel COVERED ELECTRODES AWS SPEC PREFERRED ELECTRODE WELDING RODS AWS SPEC. CLASSIFICATION A 5.1 E6010/E6013 (1) (2) (3) (4) — UTS 60,000psi & above A 5.1 E6010/ E7018 (1) (2) (3) (4) — 2a A333 Gr - 1 A 5.1 E7018 -1(5) (5) -- 3 carbon-molybdenum A 5.5 E70XX-A1 (2) (3) (4) — 1 4 2 /4 nickel A 5.5 E80XXC1 (2) — 5 31/2 nickel A 5.5 E80XX-C2 (2) — 6 9 nickel A 5.11 ENi Cr Fe - 3 A5.14 ER Ni Cr -3 7 1 /2Cr–1/2Mo A 5.5 E8015-B2L (2) 0.05C max. 8 1 1Cr– /2Mo A 5.5 E8015-B2L (2) 0.05C max. 9 11/4Cr–1/2Mo A 5.5 E8015-B2L (2) 0.05C max. 2 /4Cr–1Mo A 5.5 E9015-B3L (0.05C max.) (2) 0.05C max. 1 5Cr– /2Mo A 5.4 E502-I5 (0.05C max.) A5.9 ER502(0.05C max) 7Cr–1/2Mo A 5.4 E7Cr-I5 (0.05C max.) (2) (0.05C max.) 10 11 low chromium ferrtic steels 12 1 13 9Cr–1Mo A 5.4 E505-I5 (0.05C max.) A5.9 ER505(0.05C max) 14 AISI Type405 A 5.4 E410-I5 (0.05C max.) A5.9 ER410(0.05C max) AISI Type 410S A 5.4 E410-I5 (0.05C max.) A5.9 ER410(0.05Cmax) 15 16 ferrtic stainless steels AISI Type410 A 5.4 E410-I5 (0.05C max.) A5.9 ER410(0.05C max) 17 AISI Type430 A 5.4 E430-I5 A5.9 ER430 18 AISI Types 304&304H A 5.4 E308-I5 or 16 A5.9 ER308 19 AISI Type 304L A 5.4 E308L-I5 or 16 A5.9 ER308L 20 AISI Types321&321H A 5.4 E347-I5 or 16 A5.9 ER347 AISI Types 347 & 347H A 5.4 E347-I5 or 16 A5.9 ER347 AISI Types 316 & 316H A 5.4 E316-I5 or E 16 -8 -2 A5.9 ER316 AISI Type 316L A 5.4 E316L-I5 or 16 A5.9 ER316L AISI Type309 A 5.4 E309-I5 or 16 A5.9 ER309 21 22 23 austenitic stainless steels 24 25 AISI Type310 A 5.4 E310-I5 or 16 A5.9 ER310 26 Incoloy(32Ni46Fe20Cr) A 5.11 ENi Cr Fe-2 A5.14 ERNiCr -3 27 AluminiumBronze A 5.6 ECu Al-A1 A5.7 RCu Al-A2 28 Phosphor Bronze A 5.6 ECuSn-C A5.7 RCuSn-A 29 Copper A 5.6 ECu A5.7 RCu 30 31 32 non– ferrous metals & alloys 67Ni-30Cu Monel A 5.11 ENiCu-4 A5.14 ERNiCu-7 Hastalloy(60Ni-28Mo-5Fe) A 5.11 ENiMo - 1 A5.14 ERNiMo-4 Inconel(75Ni 15Cr8Fe) A 5.11 ENiCrFe -1 A5.14 ERNiCrFe-5 33 70Cu-30Ni A 5.6 ECuNi A5.7 RCuNi 34 Nickel A 5.11 ENi-1 A5.14 ERNi-3 35 20Cr-29Ni-21/2Mo-3Cu - Alloy 20 Cb - 3 — Alloy 20Cb3 Notes: (1) For materials Nos.1 and 2 (Carbon steel) where SMAW is followed, the root run shall be with E 6010 electrodes. (2) Where no AWS specification exists for base wire, it is acceptable to use wire or rods of the same nominal composition as the base material with substantially neutral flux or inert gas, provided they have been qualified in the procedure test. (3) MIG wire shall conform to AWS A5.18 and A5.20 (4) SAW wire and flux shall conform to AWS A5.17 (5) The root run of butt welds for material No. 2a shall be made in GTAW process using ER70S - 2 wires. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 25ES205 / 10 FABRICATION & ERECTION OF STEEL PIPING PAGE 27 OF 28 TABLE II — SELECTION OF WELDING ELECTRODES & RODS FOR WELDING DISSIMILAR MATERIALS EXCEPT ALUMINIUM Lower base mat’l No. 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 35 1 A A A A A B B B B B B B B B B B C C C C C C D D E C 2 3 4 5 6 7 8 9 Higher base material number A A A A B B B B B B B B B B B C C C C C C D D E C @ @ @ B B B B B B B B B B B C C C C C C D D E C A A @ @ @ @ @ @ @ @ @ @ @ C C C C C C D D E @ A @ @ @ @ @ @ @ @ @ @ @ C C C C C C D @ E @ @ @ @ @ @ @ @ @ @ @ @ E E E E E E E @ E @ A A A A A A A A A A C C C C C C D E C @ A A A A A A A A A C C C C C C D E C @ A A A A A A A A C C C C C C D E C @ A A A A A A A C C C C C C D E C @ A A A A A A C C C C C C D E C @ A A A A A C C C C C C D E @ @ A A A A C C C C C C D E @ @ A A A C C C C C C D E @ @ A A C C C C C C D E @ @ A C C C C C C D E @ @ C C C C C C D E @ @ A A A A A A A A C F F A F F F C A A A A A A C A A A A A C A A A A C A A A C C E C E C 10 11 12 13 14 15 16 17 18 19 F 20 21 22 23 24 25 26 C DESCRIPTION OF CODE LETTERS IN ABOVE TABLE A As specified in table I for material corresponding to either the higher or lower base material number B ASME SFA-5.5, E8015-82L electrode C ASME SFA-5.4, E309 electrode. Acceptable alternatives shall be as specified in table I for the higher base material number D As specify in table I for the material with the higher base material number E ASME SFA-5.11, ENiCrFe-2 electrode and ASME SFA-5.4. ERNiCr-3 rods shall be used where design temperature exceeds 10000F (5380C). ASME SFA-5.4, E310 electrodes are to be used where service temperatures are below 10000F (5380C) and expected to be relatively constant after start up. All rods, excluding alternatives shall require written approval from designated authority. F ASME SFA-5.4, E308 electrode or as specified in table I for the material with the higher base material number @ Welding of these material combinations are not permitted without written approval from designated authority. FACT ENGINEERING AND DESIGN ORGANISATION 25ES205 / 10 TECHNICAL PROCUREMENT SPECIFICATION 32644-03-PS-001 SV SUB VENDOR LIST PAGE 1 OF 3 R 0 A) CS & SS PIPES 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. M/s Surindra Engg. Mumbai M/s Indian Seamless Metal Tubes, Bangalore M/s Ajantha Tubes, N.Delhi M/s Bharat Steel, Mumbai M/s Sreevatsa Tube Corpn, Chennai M/s Sanghvi Metals, Mumbai M/s Nagardas Kanjishah, Mumbai M/s M.J.Patel & Co. Mumbai M/s Maharashtra Seamless, Mumbai M/s Madras Steels & Tubes, Chennai B) CS & AS PIPING FITTINGS 1. 2. 3. 4. 5. 6. 7. 8. M/s Tube Products, Baroda M/s Metal Forge, Mumbai M/s Sivananda Pipe Fittings, Chennai M/s Teekay Tubes, Mumbai M/s Eby Industries, Mumbai M/s Precision Forgings, Mumbai M/s M.J.Industries, Mumbai M/s Tube Weld Engg., Mumbai C) FLANGES 00FT024/94 1. 2. 3. 4. 5. 6. 7. 8. M/s Abassi Engg. Works, Chennai M/s Echjay Industries, Mumbai M/s Metal Forge, Mumbai M/s M.J.Industries, Mumbai M/s Precision Forging Industries, Mumbai M/s Punjab Steel Works, N.Delhi M/s Golden Iron & Steel Works, N.Delhi M/s Britex Engg. Works, Mumbai 0 26.05.2020 REV.NO. DATE FOR ENQUIRY DESCRIPTION AMN JTG KK PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION 32644-03-PS-001 SV SUB VENDOR LIST PAGE 2 OF 3 R 0 D) NON METALLIC PIPES & FITTINGS 1. 2. 3. 4. 5. 6. 7. 8. E) M/s Chemplast, Mumbai M/s Emco General Plastic Industries, Kochi M/s Kodoor Engrs., Kochi M/s Manikya Plastichem,Mysore M/s National Organic Chemical Industries, Mumbai M/s Polyplast, N.Parur, Kochi M/s Sunrise Polymers & Industries, Vadodara M/s Sangir Plastics P.Ltd., Mumbai. DUCTILE IRON PIPES & FITTINGS 1. 2. F) M/s Electrosteel Castings Ltd., Thiruvananthapuram M/s LANCO Industries Ltd., Thiruvananthapuram GATE, GLOBE & CHECK VALVES 1. 2. 3. 4. 5. 6. 7. 8. G) M/s BDK Marketing, Hubli M/s Fouress Engg., Mumbai M/s Intervalve (I), Mumbai M/s Kirloskar Brothers, Pune M/s Larsen & Toubro, Chennai M/s Neco Schubert & Salzer, Nagpur M/s Nitone Valves, Mumbai M/s VIP Valves, Mumbai CAST IRON VALVES 1. 2. 3. 4. 5. 6. 7. M/s H. Sarkar & Co., Calcutta M/s Upadhyaya Valvesmanufacturers, Calcutta M/s Kirloskar Brothers, Pune M/s Ronex Engg.Co., Howrah M/s Geeta Valves, Baroda M/s Intervalve India Pvt. Ltd M/s Ajay Valves, Bhavanagar 00FT024/94 0 26.05.2020 FOR ENQUIRY REV.NO. DATE DESCRIPTION AMN JTG KK PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION 32644-03-PS-001 SV SUB VENDOR LIST PAGE 3 OF 3 R 0 H) BOLTS & NUTS 1. 2. 3. 4. 5. 6. 7. 8. M/s Echjay Industries, Mumbai M/s Fasteners & Allied Products, Hubli M/s Fasteners India Manufacturers, Mumbai M/s Hardwin Fasteners, Mumbai M/s Nagabhushanam Industries, Bangalore M/s Pacific Forgings, Mumbai M/s Vaibhav Industries, Mumbai M/s Fix fit Fasteners, Kolkota I) GASKETS 00FT024/94 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. M/s Industrial Minerals And Mill Store Traders, Calcutta M/s Plastofab, Madras M/s Mechanical Packaging Industries Pvt. Ltd.,Bombay M/s Metro Agencies, Kochi M/s Popular Mill Stores, Cochin M/s Reinz-Talbros Pvt. Ltd. New Delhi M/s Southern Gasket Products, Madras M/s Sealings And Jointings, Kalamassery M/s SUJAYA RUBBER INDUSTRIES,PALAKKAD M/s High Tech Seals (P) Ltd., Aluva M/s Igp Engineers Ltd., Chennai M/s Spiraseal Gaskets Pvt. Ltd., Chennai M/s Unique Industrial Packings, Mumbai M/s Vircap Sealing Tech, Pvt, Ltd, Chennai 0 26.05.2020 REV.NO. DATE FOR ENQUIRY DESCRIPTION AMN JTG KK PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION FOR CIVIL & STRUCTURAL WORKS – CONSTRUCTION OF ADDITIONAL PHOSPOHORIC ACID STORAGE TANKS AT Q10 BERTH, WI TPS NO. 32644-12-PS-003 STATUS ENQUIRY ORIGINATING DEPT. 32644-12-PS-003 PAGE 1 OF 1 R1 COMMITMENT CIVIL P.O / W.O NO. PROJECT CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WILLINGDON ISLAND LOCATION WILLINGDON ISLAND, KOCHI, KERALA CLIENT M/S. FACT-CD PURCHASER M/S. FACT-CD VENDOR 00FT004 / 94 ITEM: CIVIL & STRUCTURAL WORKS 1 0 22-06-2020 09-06-2020 SECOND ISSUE ORIGINAL ISSUE AVR AVR NJ NJ ASOK ASOK REV. DATE DESCRIPTION PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION CIVIL DEPARTMENT S.No. CONTENTS TECHNICAL PROCUREMENTSPECIFICATION FOR CIVIL & STRUCTURAL WORKS – CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI Doc. No. No. of Pages Description 32644-12-PS-003 Page 1 of 1 Rev. No. with Issue 1 2 1.0 TECHNICAL DOCUMENTS 1.1 32644-12-DA-003 Specific Requirements of Work 4 0 1 1.2 32644-12-PS-003-DB Design Philosophy and Basis for Civil & Structural Works 69 0 1 1.3 32644-12-PS-003-SIW_A Schedule of Items of Work (Unpriced) 3 0 1 1.4 12ES001/18 Engineering Specification-Civil & Structural Works 14 0 0 2.0 DRAWINGS 2.1 32644-12-DG-00001 1 0 0 2.2 32644-12-DG-00002 1 0 1 2.3 32644-12-DG-00010 1 0 0 1 0 22-06-2020 09-06-2020 REV. DATE Construction of Phosphoric Acid Storage Tanks at Q10 berth,WI Details Of Dyke Wall, Pipe Rack And Drains Construction of Phosphoric Acid Storage Tanks at Q10 berth,WI Layout And Details Of Pile And Foundation Details Of Phosphoric Acid Tanks Construction of Phosphoric Acid Storage Tanks at Q10 berth,WI Truck Loading Platform-Plan,Elevation And Section SECOND ISSUE ORIGINAL ISSUE DESCRIPTION FACT ENGINEERING AND DESIGN ORGANISATION 3 4 AVR AVR NJ NJ ASOK ASOK PREPARED CHECKED APPROVED CIVIL DEPARTMENT 32644-12-DA-003 R1 PAGE 1 OF 4 SPECIFIC REQUIREMENTS OF WORK CIVIL WORKS FOR THE CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WILLINGDON ISLAND 1. INTRODUCTION FACT Cochin Division proposes to construct additional PhosphoricAcid Storage Tanks and its allied facilities such as dyke wall, drains, pipe supports, stairs and truck loading platforms at Q10 berth in Willingdon Island. The work to be performed under this contract includes Detailed Engineering, preparation of Good for construction drawings, Procurement, Supply and construction activities as defined in this document and prepared with reference to the Tender drawings and design basis (32644-12-PS-003-DB) 2. SCOPE OF WORK As part of the construction of additional Phosphoric Acid Storage Tank, following civil &structural works are in the scope of the contractor: 2.1 Design Engineering and preparation of good for Construction drawings for the various Structure and Foundation as indicated in the scope of this document satisfying the requirements mentioned in Doc-32644-12-PS-003-DB and Tender drawings. 2.2 Demolition of existing sheds like service station, mechanical workshop and light tower inside the dyke enclosed area of proposed tanks. . 2.3 Filling up the area consumed by crossing cable trench inside dyke with red earth as per specification. 2.4 Dismantling of existng drain in dyke enclosed area and rerouting the drain as per 32644-03-OP-00001. 2.5 Arranging and Conducting routine pile load test on Single pile. 2.6 Casting of bored castin-situ concrete piles in appropriate depth and dimension for the proposed tank foundation 2.7 Construction of Pile cap and Grillage beams over the pile cap 2.8 Construction of Dyke wall for the proposed Phosphoric Acid Storage Tank 1 0 REV 22/06/2020 09/06/2020 DATE Second Issue First Issue REVISION DESCRIPTION FACT ENGINEERING AND DESIGN ORGANISATION 12FT011/18 AVR AVR PRPD PT NJ CHKD ASOK ASOK APPRD CIVIL DEPARTMENT 2.9 SPECIFIC REQUIREMENTS OF WORK 32644-12-DA-003 R1 PAGE 2OF 4 Construction of Acid spill drain around tanks and from tank to drain pitwith appropriate length and dimensions along with required drain pipes 2.10 Construction of drain pit inside dyke wall for meeting contingency 2.11 Construction of Pipe rack from tank area to shore side, Truck loading piping, Barge loading piping 2.12 Construction of Pipe sleepers as Utility supports within and around dyke for laying suction lines and unloading lines 2.13 Construction of crossover platforms, approach ladders, stairs for providing access to the tank from outside the dyke wall 2.14 Construction of truck loading platforms and roof All the works mentioned above shall be executed strictly as per detailed, design, specifications & good for construction drawings reviewed and approved by FEDO. The above referred work is not conclusive. Any other items of work as provided in the schedule of items of work and items for the successful completion of the project shall be under the scope of the Contractor. 3. GENERAL CONDITIONS 3.1 All Tools / tackles/ materials/scaffolding /machinery/ manpower, all incidental items not specified but implied necessary for the successful completion of the work etc shall be arranged by the Contractor. 3.2 Tenderers are advised to visit the site and get a clear idea of the work before quoting. The offers shall be, deemed to have been made with full knowledge of all features of the area as well as the procedures to be followed for executing the work. 3.3 All materials shall be subject to approval of Owner / Consultant and if any material is rejected the same shall be removed from site by the Contractor at his own cost. 3.4 The tender purpose drawings enclosed with the tender document are preliminary to indicate the scope of the job and are for tender purpose only which are not complete and final and do not show the full range of the work under the scope of the contract. 3.5 Work shall be carried out only on the basis of drawings marked “Good for Construction” with addition, alteration, modifications, if any made to aforesaid drawings as required from time to time and also according to other drawings that FACT ENGINEERING AND DESIGN ORGANISATION 12FT012/18 CIVIL DEPARTMENT SPECIFIC REQUIREMENTS OF WORK 32644-12-DA-003 R1 PAGE 3OF 4 would be supplied from the contractor side (after getting approval from FEDO), from time to time. 3.6 The schedule of items of work attached indicates the quantities of various items of work and the work shall be executed as per the detailed specification issued for each item of work. 3.7 Tenderer should consider that the entire job has to be carried out in the operating plant and the required safety measures shall be considered so that the work is completed without disturbing the routine operations. 4 TIME OF COMPLETION 4.1 The time of completion for the work shall be as per work order 5 MATERIALS All materials used for construction shall be bought by the contractor with the approval of Engineer in-charge. The contractor shall furnish the product manual with full specification and application methods of materials to the Engineer incharge and obtain his/her approval in writing before commencement of work a. Due to time and space constraints, contractor is advised to use Ready mixed concrete of specified grade for reinforced concrete works. ULTRATECH / ACC / NEPTUNE are the recommended vendors for supply of ready-mix concrete to site. In case of machine mixed concrete, the contractor should get the design mix done through approved agencies/institutions and approval of Engineer-in-charge shall be obtained. b. ULTRATECH / SANKAR / COROMANDAL / MALABAR / ACC / AMBUJA / BIRLA are approved brands of cement. c. SAIL / RINL / TISCON / JINDAL / JSW are the only approved brands for HYSD reinforcement bars of Fe500D grade steel d. SAIL / RINL / TISCON / JINDAL / JSW are the only approved brands for structural steel e. ASIAN / BERGER / JOTUN / ICI DULUX / SHALIMAR are the approved brands of Paint products. Thinner used for the painting work shall conform to the brand specified by the manufacturer in the product literature. FACT ENGINEERING AND DESIGN ORGANISATION 12FT012/18 CIVIL DEPARTMENT f. SPECIFIC REQUIREMENTS OF WORK 32644-12-DA-003 R1 PAGE 4OF 4 FOSROC / ACC / BASF / SIKA / CERA are approved brands for Epoxy bonding agents, Non-shrink grouts& Epoxy based chemical resistant coatings (Acid resistant) g. HILTI is the only approved brand for post installation rebars / bolt anchoring using chemical or mechanical anchoring The contractor shall provide samples of all materials mentioned in the list of makes as required by the Engineer-in- charge. A written approval of these samples shall be sought prior to commencement of any work. Engineer-in-charge reserve the right to enquire the genuineness of any material used at site directly from the manufacturer / Dealer. If the material of approved make is not available in the market, the choice and the approval of the equivalent makes shall be made by Client. 6 GUARANTEE PERIOD 6.1 Guarantee period of the above work shall be as per work order FACT ENGINEERING AND DESIGN ORGANISATION 12FT012/18 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FOR CIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 1 OF 42 TPS No. : 32644-12-PS-003 Item : DESIGN PHILOSOPHY AND BASIS FOR CIVIL& STRUCTURAL WORKS Item No. : 32644-12-PS-003-DB Project : CONSTRUCTION OF ADDITIONAL PHOSPHORIC STORAGE TANKS AT Q10 BERTH, WI Client : M/s. FACT-CD Location : WILLINGDON ISLAND, KOCHI R1 1 Second Issue 22-06-2020 AVR NJ ASOK 0 First Issue 09-06-2020 AVR NJ ASOK Rev. Description Date Prepared Checked Approved FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FOR CIVIL& STRUCTURAL WORKS -CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 2 OF 42 CONTENTS 1. INTRODUCTION 2. SCOPE 3. SITE INFORMATION 4. REFERENCED STANDARDS & PUBLICATIONS 4. 1 Indian Standards – General 4. 2 Indian Standards ­ Foundation 4. 3 Indian Standards ­ RCC 4. 4 Indian Standards – Steel 4. 5 Special Publications 5. CATALOGUE OF STRUCTURES, MOC & STIPULATIONS 6. CATALOGUE OF BUILDING UNITS & ITEMWISE SPECIFICATIONS 7. CATALOGUE OF MATERIALS & STANDARDS 8. DESIGN PHILOSOPHY 8. 1 Site Arrangement 8. 2 Tank foundations 8. 3 Dyke wall & Yard 8. 4 Utility supports / Crossings 8. 5 Drain & pit 8. 6 Truck loading Bay 8. 7 Clearance above Structures 8. 8 Soil Investigation Report 9. UNITS OF MEASUREMENT 10. ORDER OF PRECEDENCE 11. DESIGN LOADS 11. 1 Dead Loads 11. 1. 1 Dead Load on utility/Equipment Supports 11. 2 Imposed loads 11. 2. 1 General 11. 2. 2 Imposed Loads for Piperacks 11. 2. 3 Piping/ Equipment Loads for Foundation 11. 2. 4 Miscellaneous Imposed Loads 11. 3 Wind Loads 11. 3. 1 Dynamic Effects of Wind 11. 4 Seismic Loads 11. 5 Erection Loads 11. 6 Load Combinations 12. ANALYSIS AND DESIGN OF RCC STRUCTURES 12. 1 General 12. 2 Design of RCC Slab 12. 3 Design of RCC Beam 12. 4 Design of RCC Column 12. 5 Design of RCC Foundation 12. 6 Minimum thickness for RCC elements 12. 7 Minimum clear cover to main reinforcement 12. 8 Design of RCC Liquid Retaining Structures 12. 9 Reinforcement Detailing FACT ENGINEERING AND DESIGN ORGANISATION 4 4 4 5 5 6 6 6 7 7 8 10 12 13 13 14 14 15 16 16 17 17 19 19 19 20 21 21 21 23 23 24 25 26 26 27 30 30 30 31 31 31 32 33 33 35 R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 12. 10 Expansion Joints 13. ANALYSIS AND DESIGN OF STEEL STRUCTURES 13. 1 Minimum thickness of steel sections 13. 2 Deflection Control for structural steel members 13. 3 Connections 14. Design – FACTORS OF SAFETY 15. DELIVERABLES ANNEXURE A FACT ENGINEERING AND DESIGN ORGANISATION 32644-12-PS-003-DB PAGE 3 OF 42 35 35 36 36 36 37 38 42 R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 4 OF 42 1. INTRODUCTION FACT Cochin Division proposes to construct an additional Phosphoric Acid Storage Tanks of capacity 5900 MT and its allied components such as dyke wall, drains, pipe supports, stairs and platforms for truck Loading with Roofing at Q10 berth in Willingdon Island. 2. SCOPE This specification summarises the standards, design criteria and practices that shall be taken in to account for detailed structural design, engineering, construction and commissioning of all industrial structures, buildings and foundations for the proposed project of additional phosphoric acid tanks at Q10 berth, WI. The design considerations given hereunder establish the minimum basic requirements of reinforced concrete structures, structural steel works and masonry structures. However, all structures shall be designed for the satisfactory performance of the functions for which the same are to be constructed. 3. SITE INFORMATION Proposed Site for constructing additional Phosphoric Acid Storage Tanks shall be sited within OWNERs existing Ship unloading and Material Storage facility at Q 10 berth, Willingdon Island, FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 5 OF 42 Cochin Division (CD) located at Willingdon Island with in Kochi city limits inErnakulam district of Kerala state. The site is connected with road and inland waterways. Village/ Tehsil : Willingdon Island/ Kochi Nearest Railway Station : ErnakulamJn ­ 8 km approx. Nearest Airport : Cochin International Airport Ltd. Nedumbassery ­ 40 km approx. Nearest Water bodies : Island location within the Cochin backwaters. 4. REFERENCED STANDARDS & PUBLICATIONS The design shall be in accordance with the latest editions and revisions of established codes, sound and economical engineering practices and shall conform to the statutory regulations applicable in India. The main codes, standards and statutory regulations considered as minimum requirements are as follows. Latest revision of these shall be followed. 4. 1Indian Standards – General IS 875 Parts (1 to 4) Design Loads (Other than earthquake) for Buildings and structures – Code of Practice IS 1893Parts (1 to 4) Criteria for Earthquake Resistant Design of Structures IS 816 Code of Practice for use of Metal arc welding for General Construction in mild steel IS:4326 Code of Practice for earthquake resistant design & construction of buildings IS:1172 Code of basic requirements for water supply, drainage & sanitation IS:1742 ­ Code of practice for building drainage IS:1905 Code of practice for structural use of unreinforced masonry IS:2212 Code of practice for brick work FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI IS:2065 Code of practice for water supply in buildings IS: 8835 Guidelines for design of surface drains 32644-12-PS-003-DB PAGE 6 OF 42 4. 2Indian Standards ­ Foundation IS 1904 Code of practice for design and construction of foundations in soils : general requirements IS 2911 (Part 1 to Part Code of Practice for Design and Construction of Pile Foundation 4) IS 2950 (Part 1) IS 2974 Part 5) Code of Practice for design and construction of Raft foundation (Part 1 to Code of Practice for design and construction of Machine Foundations IS 6403 Code of practice for determination of bearing capacity of shallow foundations IS 8009 (Part 1) Code of practice for calculation of settlements of foundations: shallow foundations subjected to symmetrical static vertical loads 4. 3Indian Standards ­ RCC IS 456 Plain and reinforced concrete – Code of Practice IS 1786 Specification for High strength deformed steel bars and wires for concrete reinforcements IS:13920 Code of Practice for ductile detailing of reinforced concrete structures subjected to seismic forces IS:3370 Code of Practice for Concrete Structures for storage of liquids 4. 4Indian Standards – Steel IS 800 General Construction in Steel ­ Code of Practice IS 801 Code of Practice for use of light gauged steel structures IS 2633 Methods for testing uniformity of coating of zinc coated articles IS 2062 Hot rolled medium and high tensile structural steel — Specifications IS 2629 Recommended practice for hot dipped galvanizing on iron and steel IS 4923 Hollow sections for structural use IS 1161 Code of Practice for Circular hollow sections/pipes FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 7 OF 42 4. 5Special Publications SP 6 Parts (1 – 7) Handbook for Structural Engineers SP 7 National Building Code of India: 2005 SP 38 Handbook of Typified Designs for Structures with Steel Roof Trusses SP 34 Handbook on Concrete Reinforcement and Detailing SP 16 Design Aids for Reinforced Concrete to IS: 456 SP 24 Explanatory Handbook on Indian Standard Code of Practice for Plain and Reinforced SP 20 Explanatory Handbook on Masonry Design and Construction 4. 6 Note: The above list is suggestive and not exhaustive. Apart from these basic codes any other related codes shall also be followed wherever required. 5. CATALOGUE OF STRUCTURES, MOC & STIPULATIONS Following are the tentative list of buildings and structures envisaged for the proposed project. Sl. 1 2 3 4 Building / Structure Tank foundations MOC RCC Storm water Drain Requirement Pile foundation, Sizing as per Loading RCC drains on sides of Dyke Minimum depth – 300mm wall in slope 1: 600 Minimum width – 300mm Cable trench / Utility RCC Sizing as per electrical trench requirement Road crossing culverts RCC culverts with precast cover Minimum width 600mm, for drains slab Maximum width 1200mm FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI PAGE 8 OF 42 5 Utility Crossings below RCC Hume pipe ground: encased in concrete 6 Utility Crossings above Structural steel pipe racks on Sizing as per utility requirement ground: RCC foundations 7 8 9 10 11 12 13 14 / 32644-12-PS-003-DB HDPE Sizing as per utility requirement Platforms, Ladders, Structural Steel with FRP Sizing as per utility requirement Crossovers, Stair gratings founded on RCC pedestals and foundation Pipe supports / Overhead Structural Steel with RCC Sizing as per utility requirement cable tray supports footings Pipe sleepers on ground RCC Sizing as per utility requirement Yard inside dyke RCC Equipment foundations RCC Dyke wall RCC Truck Loading bay Reclamation Pit Sizing as per volume to be encased Sizing as per Loading Sizing as per volume to be encased Structural Steel roof with RCC Sizing as per utility requirement footings. Platforms shall be RCC RCC Sizing as per volume to be encased Note: This list is not conclusive and any additional building or structure if required as per the requirement of the contractor/vendor for the successful installation of Acid Storage tank and pumping of Phosphoric acid shall be included with this list and shall be binding to the entire project. 6. CATALOGUE OF BUILDING UNITS & ITEMWISE SPECIFICATIONS Following are the minimum requirements for the building components / elements. For components not mentioned here within, the requirement shall be as per CPWD specifications / best engineering practices for the durability of the structure. Sl. 1 Building Component Requirement Equipment / Tank M30 grade RCC with cement content not less than 330kg/cum FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION 2 3 4 5 6 7 8 9 10 11 12 DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI foundations RCC piles / pile cap 32644-12-PS-003-DB PAGE 9 OF 42 M35 grade RCC with cement content not less than 400kg/cum Underground sump tanks M30 grade RCC with cement content not less than 350kg/cum with waterproofing compound mixed with concrete. Additional water proofing on concrete surface – surface coating / membrane application shall be done to make underground structures water tight. Masonry work below Minimum 230 thick solid cement block (200 thick brick) or First­ ground class bricks plastered on both sides Masonry work in super Minimum 100 thick half brick partition walls. 230 thick walls for structure exterior. 100/150/200thick walls are permitted for interior walls as required. Use of Solid Cement Concrete blocks / Clay bricks are permitted Plastering 15mm thick plaster in CM 1:4 over rough / exterior face of masonry 12mm thick plaster in CM 1:4 over fair / interior face of masonry 6mm thick plaster in CM 1:3 over / under RCC elements Concrete Columns / M30 grade RCC with cement content not less than 330kg/cum beams / slabs/ Lintels / Sunshades Lean concrete Cement concrete mix 1:3:6 with an average thickness of 75mm under foundations / grade beams etc. Cement concrete mix 1:5:10 for site grading / site levelling Handrails In plant buildings / External: MS or FRP Inside building: Stainless steel SS304 grade, brushed finish Anti­termite treatment Pre­construction anti­termite treatment of soil with chemical agents Fire proofing Fire proofing to steel structures wherever required as per Tariff Advisory Committee (TAC) rules and regulations and other Codes / requirements asapplicable. Painting Masonry / RCC work (dry Area) exposed to corrosive environment to be painted with Corrosion resistant epoxy paint. Steel structures in corrosive environment shall be painted as follows: Surface shall be prepared by shot blasting to near white metal grade SA 2.5 as per IS 9954. Two coats of red oxide zinc chromate primer (one shop coat and one coat after fixing /erection) shall be applied. One intermediate coat of Micaceous Iron Oxide epoxy paint of 70­micron DFT. One coat of two pack polyamide cured epoxy finish paint of 40­microns DFT and one coat of aliphatic acrylic polyurethane finish paint of 40­microns DFT. Any parts of structure which are prone to aggressive alkali / acid FACT ENGINEERING AND DESIGN ORGANISATION R1 DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI TECHNICAL PROCUREMENT SPECIFICATION 32644-12-PS-003-DB PAGE 10 OF 42 substances shall be protected by suitable protective membranes or methods (including cathodic protection, if required) Other RCC / Masonry structures to be painted with two coats of acrylic / plastic emulsions over one coat of cement primer Pre­cast Cover slabs 13 Grouting 14 Roofing / Cladding 14 Epoxy Coating 15 Wood work shall be painted with two coats of enamel paint over two coats of wood primer. RCC M25 Non­Shrink cement Grout with minimum strength of 40 N/mm² at 28 days, 25mm thick or as specified by equipment manufacturer for Structural bases of Columns and static equipment Non­Shrink cement Grout with minimum strength of 40 N/mm² at 28 days, 50mmthick or as per vendor’srequirements for Dynamic Equipment, Reactors / Process Columns Non­Asbestos cement sheets / High impact resistant Polypropylene roofing sheets shall be used for roofing/ cladding high build epoxy based chemical resistant coating for outer surface of tank foundation (CERACOTE EP CR of CeraChem or equivalent) with a minimum dry film thickness of 500 microns 7. CATALOGUE OF MATERIALS & STANDARDS Specifications of materials used for construction are as follows: Sl. 1 2 3 4 5 6 7 Specification Material Cement Aggregates OPC 53 grade conforming to IS 12269 or PPC conforming to IS 1489 – Part 1 HYSD bars of grade Fe500 with 14% elongation conforming to IS 1786. Binding wires shall conform to IS 280 Conforming to IS 383 Water Conforming to IS 456 Reinforcement steel Admixtures concrete Structural steel in Structural hollow sections / tubes Conforming to IS 9103 Conforming to IS 2062 (Fe250 Grade A) Minimum thickness of plates 5mm Conforming to IS 4923 / IS 1161 with YST310 grade. Tubes used shall be medium class.Structural pipes shall be either seamless or mild welded. Spiral welded pipe is not acceptable. FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION 8 9 10 11 12 13 14 15 16 17 18 DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 11 OF 42 Stainless steel SS 304 Grade Bitumen Bitumen grade VG – 10 conforming to IS 73 Non­shrink grouts Paints Curing compounds MS anchor bolts, Rungs, metal inserts, grating Hexagonal head bolts, screws and nuts of product Grade C. Plain washers conforming to ASTM C 1107 Plastic emulsion paint Type 1 for interior use and Type 2 for exterior use conforming to IS 15489 ASTM C309­19 Conforming to IS 432 Conforming to IS:1363 Conforming to IS:2016 Steel Chequered Conforming to IS:3502 plates Hexagonal Bolts and Conforming to IS:3138 nuts (M42 to M150) Non­Asbestos Non­asbestos high impact Polypropylene reinforced cement 6 mm Polypropylene sheets thick corrugated sheets conforming to IS: 14871 Note: The materials list is not conclusive and for the materials required and not mentioned in the list shall conform to relevant IS codes / ISO / ASTM / Engineering standards as per nature of use of the material. FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 12 OF 42 8. DESIGN PHILOSOPHY Preparation of detailed design and drawings, sketches, specifications for all civil & structural works, shall be in the scope of contractor’s work. List of various facilities given are only indicative. Therefore, sizing, nos., location etc. of various facilities viz. Tank foundations, Dyke floor and wall sections, Utility supports, drains, etc. shall be in the scope of the bidder, with approval and satisfaction of FACT CD/FEDO. All the facilities shall conform to all Local Rules and Regulations, Factory Inspector Rules, TAC rules, etc. whichever is more stringent. The vendor shall carryout Analysis and Design of the structures required for this document and prepare all the required Civil and Structural drawings needed for correct and accurate construction as per the Design Specifications given in this document. It shall be the responsibility of the vendor to accommodate all the functional requirements such as access, cut outs, clearances, interference etc. while designing / detailing of various structures /facilities. Complete analysis, design and all drawings of each independent structure / facility shall be submitted in one lot so as to facilitate overall systematic review by FEDO. Preparatory and site clearing jobs (as enlisted in Drawing No 32644­03­OP­00001) will be executed by FACT CD, in a span of time organized in such a way that jobs for construction of PA tanks will be executed unhindered. The philosophy for the design of individual structures is as follows: FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 13 OF 42 8. 1Site Arrangement The site arrangement shall conform to applicable laws, regulations, Layout drawings issued from Piping dept. and environmental standards. Utility interconnections will be optimized as much as practical. Spill containment measures shall be provided. The following criteria shall be followed regarding site arrangement: Tank yard and dyke shall be designed to contain spills Storm water drains along the Dyke wall shall be constructed to take out rain water accumulated in the Dyke floor to the nearest drain with control arrangement as per the scheme indicated in the Drg­32644­03­OP­0001 Locations and requirements for piping supports shall conform to piping requirements 8. 2Tank foundations Proposed phosphoric acid tank foundation shall be RCC pile group with a system of grillage and drain above the pilecap ( below the tank base plate), designed for the worst case ofloads and their combinations. The clear Spacing between each grillage beam running below tank plate shall be kept to a max of 300mm, so that the thickness required for bending action of base plate is optmised. Piles of sufficient depth and number shall be accommodated to resist base shear from seismic action or wind, whichever is critical. Portions of pile cap exposed to yard area, or area where chances of acid leak or spill is there, shall be protected with acid proof lining, wherever possible. FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 14 OF 42 8. 3Dyke wall & Yard Dyke wall shall be of RCC. The dyke wall shall be designed as liquid retaining structure in the inside face. Suitable drainage arrangements shall be provided within curbed areas around pumps, for drainage leaks. Finish of 50 thick concrete screed, with non­metallic (Quartz based) hardener topping shall be provided on paving after erection and commissioning of tank is over. Paving within Tank farm& Utility areas for maintenance compatible to crane 200 mm thick, M30 movements / dropout / Loading / Unloading areas / Vehicular movement areas grade RCC Non­vehicular movement areas 150 mm thick M20 grade RCC Under Pipe rack & foot paths 100mm thick PCC 1:3:6 Expansion joints & Contraction joints shall be as per relevant IS codes and standards. 8. 4Utility supports / Crossings For all utility supports 500mmabove Paved level, RCC sleeper supports resting on RCC isolated foundations shall be provided with spacing of 3m c/c for the pipes. For all Supports at 3.5m or 7m or at any specified elevation above paved/Ground level, Structural steel supports shall be raised from RCC pedestals supported on RCC foundation slab, at a spacing of 6 to 18 m c/c depending on the crossings and obstructions enroute. FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 15 OF 42 8. 5 Drain & pit The proper surface drainage of rain water from all parts of the scope area shall be envisaged. All drain work shall be in RCC. The drainage system shall be bygravity. Rain water falling on such portion of paved areas of layout where it is not likely to get contaminated in regular usage other than a tank burst, shall be collected in open rectangular RCC drains provided in floor paving. These drains shall be covered by FRP gratings and shall be generally connected to peripheral storm water drains as per the scheme indicated in the layout drawing No 32644­03­OP­00001. Proposed Project mainly include following different types of drain system: Drain below tank surface towards cleanouts (Coating as indicated in tender drawing) Drain around Tank for accommodating acid leaks, if any (Acid proof lined) Drain from tank to Reclamation pit / Drain pit (Acid proof lined) Drain inside dyke for routing for storm water Grillage beams shall be provided with a minimum height of 900mm and with maximum clear spacing of 300mm below tank base plate for facilitating leakages from the tank bottom, if any. The top of pile cap shall be constructed to be sloping towards the outer corners from the center so that spillage flows towards the surrounding drain. Cleanouts to be kept diametrically opposite corners at minimum 2 locations or as per the Mechanical requirement for the tank cleaning.. These cleanout drainshall be connected to circular drains provided around tank (above pile cap). Spills/ Leaks in thesedrains shall be further routed towards the drain pit. FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 16 OF 42 Runoff from possible chemical contamination areas, such as the acid storage and handling areas, will be contained. Small neutralization pits may be provided near drain around tank to treat floor wash in yard areas as per process requirement. Water from these pits will further be routed to storm water drains. 8. 6Truck loading Bay Truck loading bay with RCC platform for mounting the loading arm shall be provided for acid loading to the trucks. The proposed location of truck loading has been indicated in drawing No 32644­03­Op­0001. The roof shall be with Non Asbestos fibre reinforced corrugated sheets over steel roof truss. The minimum clear height for the loading platform for Phosphoric acid loading shall be 4500 mm from the pavement. An additional bay at +4.0m lvl shall be provided with platform at same level as existing platform as in Sulphuric acid an additional requirement as indicated in the Tender drawing no 32644­12­ DG­00010 8. 7Clearance above Structures Minimum overhead clearances shall be as follows: Above platforms and walkways 2100 mm Clearance below Truck Loading Platform 4500 mm Vertical head room for stairs 2400 mm Safety gauge for ladders 2400 mm Access for forklift trucks 2800 mm Above main roads, crane access and Conveyor crossings 7000 mm FACT ENGINEERING AND DESIGN ORGANISATION R1 DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI TECHNICAL PROCUREMENT SPECIFICATION Above other plant roads and truck access 32644-12-PS-003-DB PAGE 17 OF 42 4200 mm The guidelines of NBC 2005 shall be followed for all offsite buildings. 8. 8Soil Investigation Report The recommendations from the investigation conducted in the nearby area is summarised as follows: The land is previously dredged fill area near the Product Handling Berth(Q10) in Cochin Port area at Willington Island. The soil profile for a considerable depth is marine clay with shallow pockets of decayed wood at random depths. Hence it is advised to found heavy loaded structures at denser strata available at deeper depth. Water table was met at 0.50m to 1.0 m depth below ground level in the bore holes at the time of investigation during April 2014. For heavily loaded structures pile foundation of sufficient depth and number shall be accommodated to resist vertical and uplift load including base shear from seismic / wind, whichever is critical. Piles shall be bored cast in situ DMC type with depth ranging from 60 to 65m resting the pile in the very dense silty sand layer with minimum 2 times the diameter penetration in the layer. Safe load carrying capacity of bored cast in situ piles of depth 65m below cut off level, arrived from the soil investigation conducted nearby area for design are as follows: Pile diameter (mm) Vertical capacity (kN) Shear capacity (kN) Uplift capacity (kN) 750 2350 105 500 900 3400 135 680 FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 1000 4250 155 32644-12-PS-003-DB PAGE 18 OF 42 850 Portions of pile cap exposed to yard area, or area where chances of acid leak or spill are expected, shall be protected with acid proof lining. For lightly loaded structures safe bearing capacity of soil for different size of shallow footings shall be considered as follows: Type of foundation Size of footing Depth of footing below the E.G.L (m) Safe Load carrying capacity (kN/m2) (m x m) Isolated 2x2 2 50 Isolated 3x3 2 40 Isolated 2x2 4 55 For structures with light loading aforementioned Safe bearing pressures can be adopted with due consideration to settlement criteria. The soil Investigation report conducted in the nearby area is enclosed as Annexure­A for information. 9. UNITS OF MEASUREMENT Units of measurement shall be in SI system and shall be as follows: Entity Unit of measurement Elevations millimeter (mm) Dimensions millimeter (mm) Force kilo Newton (kN) FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI Mass kilogram (kg) Moment kilo Newton meter (kNm) Stress Newton/square millimeter (N/mm2) Pressure kilo Newton/ square meter (KN/m2) 32644-12-PS-003-DB PAGE 19 OF 42 10. ORDER OF PRECEDENCE In case of any conflict / deviations amongst various documents, the order of precedence shall be as follows: Statutoryregulations Job specifications Engineering designbasis Standard specification 11. DESIGN LOADS 11. 1Dead Loads Dead load is the vertical load due to actual weight of all permanent structural and non­ structural components of building such as floors, roofs, walls, staircases, fixtures etc. Dead loads shall be estimated for purposes of design using the actual weights of material of construction and finishes on the basis of unit weights given in IS 875­ Part 1. The following unit weightsshall be considered for computation of dead loads: Material Unit weight (kN/m3) Plain concrete 24.00 Reinforced concrete 25.00 Structural Steel 78.50 Soil 18.00 FACT ENGINEERING AND DESIGN ORGANISATION R1 DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI TECHNICAL PROCUREMENT SPECIFICATION Saturated soil 20.00 Water 10.00 Solid Brick masonry 20.00 11. 1. 1 32644-12-PS-003-DB PAGE 20 OF 42 Dead Load on utility/Equipment Supports The following dead loads shall be included in the design of support structures:­ Weights of fixed process equipment and machinery, piping, valves, electrical cable trays, and the contents of these items Fireproofing on structural steel, vessel skirts and equipment.including all internals, refractory linings and hydrotest. Insulation installed on piping and equipment Steel platform framing and floor plate. Weight of platforms, piping and ladders on towers shall be as specified onthe vessel drawings. any other permanent load if applicable. Following super imposed loads shall also be considered (if not stated otherwise) along with dead loads as applicable: Item Loading Cable tray single tier 1.00kN/m2 Cable tray two tier 1.90kN/m2 Piping load (for pipes less than 300mm dia) 1.90 kN/m2 FRP gratings 0.50 kN/m2 FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 21 OF 42 11. 2 11. 3Imposed loads 11. 3. 1 General Imposed loads are the greatest loads assumed to be produced by the intended use of the structure. For the design of each structural element the imposed loads shall be applied in the least favourable pattern. Imposed loads on floors shall be the actual loads when these are known, but shall not be less than the distributed loads given below: Pump and compressor houses 7.5 kN/m2 Warehouses and open storage areas 7.50 kN/m2 Sheeted roofs with access for maintenance only 0.75 kN/m2 Main Access Platforms and Floors 5.0 kN/m2 Platforms subject to storage of heavy equipment 7.0 kN/m2 Walkways and Minor Platforms used for access to equipment only 2.5 kN/m2 Piping load (for pipes less than 300mm dia) 0.75kN/m2 Crane beams and supports for travelling cranes shall be designed in accordance with IS 800/ IS 807/ IS 3177. 11. 3. 2 Imposed Loads for Piperacks Pipe racks shall be designed for live load only if permanent accesses (walkways) are provided. If the width/height of pipe rack is equal or more than 7 m, provide a walkway of min width 0.8m. In such cases, loadings shall be given as follows: Loading for maintenance bay: Min. 1.0 kN/Sqm Loading for Equipment bay : Min. 2.5 kN/Sqm FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 22 OF 42 When individual pipe loads are not available for racks with pipes exceeding 300 mm diameter, but not exceeding 400 mm diameter, the piping shall be considered as a distributed load of not less than 1.2 kN/m2 for the operating condition and 2.5 kN/m2 for the test conditions. Note that piping loads for the operating condition are considered as live loads since they do not represent the “pipe full” condition.Test loads (“pipe full”) may be applied with a reduced load factor equivalent to a dead load.Test loads should not be applied to more than one tier simultaneously. The location and magnitude of anchor forces for all pipes over 400mm diameter shall be established before the design is started. Point loads from pipe supports on piperacks shall be the actual loads when they are known. In the absence of known point loads from pipe supports each piperack member (excluding bracing) shall be checked for a single point load of 4.5 kN in the least favourable position in addition to the distributed loads specified above. A longitudinal thermal force of 10 per cent of the operating load per tier shall be assumed to act uniformly distributed at each bent. The piperack shall be checked when the actual pipe stress anchor forces are known. Transverse anchor or guide forces equivalent to 0.75 kN per metre of rack width per tier shall be assumed to act on each bent, applied as a single force at each tier level. The piperack shall be checked when the actual pipe stress anchor forces are known. When considering the erection load combination, piping shall be considered as a distributed load not greater than 0.5 kN/m2 irrespective of pipe diameter.The piperack structure self weightshall FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 23 OF 42 be considered as a distributed load of 0.5 kN/m2 per tier unless the pipe rack is fireproofed prior to erection, when the actual weight of fireproofing shall be included. 11. 3. 3 Piping/ Equipment Loads for Foundation Consideration shall be given to loads on the foundation from pipework where the configuration, operating loads and operating temperatures may give rise to significant horizontal forces due to friction at supports.Pipe anchor forces and thermal forces on equipment and vessels shall be included under normal operation and test conditions, whichever gives the most severe effects. The contents of equipment shall be considered as live load and shall be applied in the least favourable pattern. Ensure the correct specific gravity is applied when calculating the load.Exchanger and horizontal vessel foundations shall be designed for thermal forces due to vessel expansion. The following coefficients of static friction shall be used to determine forces at sliding surfaces:­ a) Teflon on Teflon 0.10 b) Steel on steel 0.30 c) Steel on concrete 0.45 11. 3. 4 Miscellaneous Imposed Loads Consideration shall be given to loads of a special nature such as piping counterweights, spring hangers, thrusts from expansion joints, expansion loads from horizontal vessels and exchangers, purpose made handling equipment such as counterbalanced crane hooks, and thermal expansion of the structure. FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 24 OF 42 In the absence of any suitable provision for live loads in this specification or relevant IS codes for any particular type of floor or structure, the assumed loading shall be got approved. Apart from the specified live loads, any other equipment load or possible overloading during maintenance/ erection shall also be considered in the design. 11. 4Wind Loads Design wind loading shall be in accordance with IS 875: Part 3­ “Code of practice for design loads for buildings and structures­Wind loads” and as per clause given below. Basic wind speed shall be 39 m/sec for a 50­year return period for structural and equipment design. Wind load design should be done as per IS: 875 (Part 3) ­2015 Design wind pressure, Pd = Kd x Ka x Kc x pz N/m2 Ref Clause 7.2 of IS: 875 Part­3 Where wind pressure pz = 0.6Vz2 Design wind speed, Vz = Vb x k1 x k2 x k3 x k4 Ref IS: 875 Clause 6.3 Basic wind speed, Vb = 39 m/s Probability factor, k1 = 1.0 Risk coefficient Terrain height and k2 Ref. Table 2 of IS: 875 Part­3, based structure size factor on terrain category 2 Topography factor k3 = 1.0 Cyclonic factor k4 = 1.0 The values of Pd, however shall not be taken as less than 0.70 Pz FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 25 OF 42 The effective exposed area of open framed structures which support piping and equipment shall be estimated as a percentage of the gross projected area.Vessels or other large equipment supported on a structure shall be calculated separately and be additive in computing the total wind load. Transverse forces due to wind acting on pipes in racks shall be calculated in accordance with IS 875. The effect of wind on all pipes shall be considered, but the shielding effect shall be taken into account. Wind forces on longitudinal beams shall also be included, but shielding effect shall be neglected. 11. 4. 1 Dynamic Effects of Wind Structures such as, but not limited to, heater stacks, chimneys and tall towers, may be sensitive to wind gust effects and/or vibrations due to vortex shedding. In general, the following guidelines may be used for examining the problems of wind induced oscillations: Building and closed structures with a height to minimum lateral dimension ratio of more than about 5.0, Or Buildings and structures whose natural frequency in the first mode is less than 1.0 Hz. Any building or structure which satisfies either of the above two criteria shall be examined for dynamic effects of wind. If vortex shedding analysis results indicate that unacceptable levels of vibrations can occur, then helical strakes, dynamic vibration absorbers or other means shall be adopted provided prior approval is obtained from Owner.All calculations for gust or vibration analysis on purchased equipment shall be submitted for review prior to release for fabrication. FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 26 OF 42 11. 5Seismic Loads The plant structures must be designed for design basis earthquake (DBE) as per clause no. 7.0 and the design spectra given in IS: 1893 (Part­IV), Annex B for Type­2 medium soil. The design value of horizontal seismic coefficient Ah shall be computed by the following expression: Ah = (Z/2) . (I/R) . (Sa/g) Seismic load on the structures shall be calculated as per IS 1893 by taking Zone factor Z corresponding to Zone III. Response reduction factor “R” shall be taken as per Table 4 Importance factor I should be considered as per Table­3, IS­1893, Part­4 based on the category of structure defined in Table­6 of IS­1893: pt­4). Equipment support structures/ pipe racks/ / storage tanks ­ Category­2, so Importance factor I = 1.5 Sa/g is the average Response acceleration coefficient to be taken from Annex B corresponding to the natural period of the structure. Damping (for DBE) 5% (for concrete) 2% (for steel). Ductile detailing of reinforcement is mandatory for moment resisting RCC frames and hence response reduction factors corresponding to special moment­resisting frame shall be considered. 11. 6Erection Loads All loads to be carried by the structure or any part of it due to storage or positioning of construction material and erection of equipment including all loads due to operation of such equipment shall be considered as erection load. Proper provision shall be made including temporary bracings to take care of stresses due to erection loads. The structure as a whole and FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 27 OF 42 all part of the structure in conjunction with temporary bracings shall be capable of sustaining this erection load without exceeding the permissible stresses subject to the allowable increase of stresses. Dead loads, wind loads and all such parts of live load as would be imposed on the structure during the period of erection shall be taken as acting together with the erection load. 11. 7Load Combinations All buildings, structures, equipment, and foundations shall be investigated for each of the loading combinations given in Table below and the most severe shall determine the final design. LOADING LOADING COMBINATIONS Normal Abnormal Empty DEAD Erection Test Operation Operation Shutdown Structures Include (7) Include Include Include Include Equipment Include (7) Include Include Include Include Internals Include (6) Include (3) Include Include Include linings Include (6) Include Include Include Include Piping Include Include Include Include Include Include Include Include Include Include Internals Floors/ Platforms FACT ENGINEERING AND DESIGN ORGANISATION or R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 28 OF 42 Insulation Include Include Include Include Include Fireproofing Include (6) Include Include Include Include Include Include Include Include Include platforms ­ Modified (4) Include (9) Include Include Normal Fluids ­ ­ Include Maximum(1) ­ Test Fluids ­ Include (5) ­ ­ ­ ­ Modified (4) Include Include Include ­ ­ Include Include ­ ­ ­ Include Include ­ Modified Greater of Modified Greater of wind (2) two wind (2) two Vessel Platforming IMPOSED Floors/ Vessel Platforming Surge (normal contents) Thermal (piping) Wind Earthquake or Greater two of FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 29 OF 42 Construction Equipment IInclude (8) Include (8) ­ ­ Include (8) Notes below refer to numbers in brackets shown in Table :­ (1) Load shall be computed due to faulty unit operation from items such as catalyst or liquid backup. (2) Wind loading shall be based on a wind speed of 0.77 times the design wind speed, but not greater than 39 m/sec. (3) Loads shall be included only if in place during the future test condition. (4) Include only 50% of the platform live load for the test condition. (5) Load for vertical vessels includes only the test fluid as permitted by the vessel design for the hydrostatic field test. (6) Include only if installed in shop or before lift. (7) The erection load shall be calculated in conjunction with the clause of this Specification. (8) The construction equipment load shall only be included if it is greater than the operating load or increases the overturning moment. (9) Live load reduction may be considered as defined in this Specification. Following Load factors in limit state of strength shall be applied for the design: Load cases Dead Erection 1.2 1.2 Live Wind / Seismic Erection / Construction 1.2 1.5 0.6 1.2 1.2 FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 0.9 1.5 Test 1.2 0.5 Operation 1.5 1.5 1.5 1.2 32644-12-PS-003-DB PAGE 30 OF 42 1.0 1.2 1.5 1.2 0.9 1.2 1.5 12. ANALYSIS AND DESIGN OF RCC STRUCTURES 12. 1General Main RCC structures under this scope comprises of Tank Foundation, drains, truck loading bay, dyke wall, drain pits etc. Frame analysis shall be carried out for all structures for all load combinations using structural analysis and design software STAAD Pro.Limit state design shall be adopted for design of all structural elements.However, water retaining structures may be designed using working stress method. While considering earthquake effects, EL shall be substituted in place of WL and appropriate portion of IL shall be considered as stipulated by IS 1893. Ductile detailing of RCC frames shall be done as stipulated in IS 13920 for RCC structures in Zone 3. 12. 2Design of RCC Slab Two­way slabs shall be designed based on the Bending moment coefficients given in annexure D of IS 456. For continuous one­way slabs moment coefficients given in Table 12 of IS 456 shall be used. Deflection check of the slabs as envisaged in IS 456 shall also be done. FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 31 OF 42 12. 3Design of RCC Beam Beam reinforcement steel shall be provided for the required moment of resistance obtained from the analysis of frames. Shear stirrups shall be provided to withstand balance shear after deducting the shear capacity of concrete section based on the percentage steel provided to resist Bending Moment. Spacing of stirrups shall be detailed in accordance with IS 13920. 12. 4Design of RCC Column Columns shall be designed for the combined effect of axial loads and biaxial moments due to frame action obtained from the analysis for the worst load combination and the detailed design output specifying the percentage steel to be provided and the interaction ratios shall be furnished. 12. 5Design of RCC Foundation All foundations shall be designed to suit the existing soil conditions. Where available, drawings showing existing buildings, foundations, underground services and any other information pertinent to the design and construction of foundations shall be used to assist in establishing the foundation design criteria. Information obtained from such drawings shall be verified on site preferably before finalising the new designs. The sizing of foundations & design shall be done as per recommendations given in the soil investigation report. The bearing capacity / safe pile capacity shall satisfy strength as well as settlement criteria. The permissible increase in bearing capacity/ pile capacity in wind and seismic load combinations shall be as per IS 875 ­ part5 and IS 1893 respectively. Foundation design for major structures shall be verified by a Geo Technical expert. While designing foundations at various levels, effect of uplift/ subsoil water table shall also be considered. FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 32 OF 42 All underground pits, sumps, etc. shall be designed to take care of the uplift forces due to buoyancy, if required.If the sub soil is of aggressive nature, suitable precautions are to be taken as recommended in the soil investigation report in respect of type of cement, concrete cover etc. for foundations / underground structures. PCC 1:3:6 is proposed for levelling course for all RCC structures. The thickness of levelling course shall be 80mm and when used as a structural element, the minimum thickness shall be 150mm. 12. 6Minimum thickness for RCC elements Footings (All types, with or without beams) 300 MM (Note : Tapered footings shall not have thickness less than 150mm at the edges, minimum average thickness shall not be less than 300 mm) PileCap 500 MM Basement a) walls 150 MM b) Base Slab with beams 200MM c) Base Slab without beams 300 MM Slab thickness in raft foundations with beam & slab construction 150 MM Floor/Roof Slab, Walkway and CanopySlab 150 MM Cable/ Pipe Trench / Launder Walls & baseSlab 125 MM Parapet 100 MM Louvre /Fin. 100 MM Precast Trench Cover / Precast FloorSlab 125 MM Louvre (in contact withliquid) 125 MM Liquid Retaining / Leak proofStructure a) Walls 150 MM b) Base Slab with beams 200 MM c) Base Slab without beams 300 MM UndergroundPit a) Walls FACT ENGINEERING AND DESIGN ORGANISATION 150 MM R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 33 OF 42 b) Base slab with beams 200 MM c) Base slab without beams 300 MM a) Pedestal / encasements of structural columns in open area 300 MM b) Pedestal / encasements of structural columns in yard area 150 MM c) Pedestal / encasements of equipment in open area 300 MM d) Pedestal / encasements of equipment in yard area 150 MM Pedestals For all other Sleeper supports, corresponding thickness mentioned in drawing shall be used 12. 7Minimum clear cover to main reinforcement As otherwise stated, minimum thickness to main reinforcement for RCC members shall be as follows: STRUCTURAL MEMBER CLEAR COVER Floor / Roof / stair waist 20 mm Grade Slab 40mm Roof beams / Floor beams / Lintels 30mm Columns and pedestals 50mm Basement walls, retaining walls & pit walls 40 mm Water /liquid retaining structure 40mm Foundation slab /plinth beams 75 mm Pile 60mm (Sides), 150mm (Bottom) Pile cap 100 mm (Bottom), 75 mm (Sides) 12. 8Design of RCC Liquid Retaining Structures 1. Design shall conform to IS 3370 Part I to IV. All elements of water retaining structures or similar structures in contact with water shall be designed as uncracked section. 2. M30 grade concrete shall be used. FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 34 OF 42 3. For tanks resting on grounds cement concrete 1:3:6 mix levelling course shall be provided. 4. The provisions regarding expansion joints, contraction joints, construction joints, bitumen sliding layer above levelling course, etc. shall be provided as recommended in the standards. 5. Hydro swelling gasket kept in place by a single component hydro swelling polyurethane sealant for sealing or other approved treatment shall be provided at construction joints in concrete both at vertical and horizontal construction joints of water retaining structures to make it leak proof. 6. For underground storage tanks, pits, trenches etc. where protection against uplift due to buoyancy from subsoil water is to be considered, a min. factor of safety of 1.2 shall be ensured. For purpose of calculating downward load due to overburden, only the mass located vertically over the projected area of the base shall be taken into account. 7. All liquid retaining/ storage structures shall be designed assuming liquid up to the full height of wall irrespective of provision of any overflow arrangement. 8. The walls and base slab of liquid retaining/ storage structure shall be provided with reinforcement on both faces irrespective of any thickness. 9. All embedded parts such as nozzles, pipes, bolts, etc. shall be provided at the time of concreting. 10. Plastering with cement mortar 1:4, 10 mm thick, mixed with integral waterproofing compound like Conplast X4211C of M/s. FOSROC or equivalent shall be provided for inside surface after hydro test. 11. All leaks or wetting noticed during hydro tests shall be rectified as per approved methods, using approved materials. FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 35 OF 42 12. 9Reinforcement Detailing 1. All requirements governing quantum of reinforcement and detailing of reinforcement as per clause 26 of IS 456 and as detailed in SP 34 for detailing of reinforcement shall be adhered to while preparing the construction drawings. 2. The recommendations for detailing for earthquake resistant construction given in IS 13920 shall also be followed. 12. 10Expansion Joints 1. Expansion joints in concrete structures shall be provided as per IS 456/ IS 3414 Code provisions. 2. Bitumen impregnated fibre boards of approved manufacture as per IS 1838 Part 1 shall be used as fillers for expansion joints. 3. The gap between the expansion joints shall be thoroughly cleaned and the bitumen fibre boards placed in position as per manufacturer’s specification and the surface shall be sealed with elastomeric silicone rubber sealants. 4. All expansion/ separation joints in ground floor slabs shall be filled with sand for the full depth of the slab except top 25 mm, which shall be filled with approved mastic sealing compound. 13. ANALYSIS AND DESIGN OF STEEL STRUCTURES Basic consideration of structural framework shall primarily have strength to withstand the various loads mentioned above. Ease of fabrication, erection and overall economy satisfying IS stipulations shall also be a criterion for design. Design shall be done in accordance with IS 800.The deflection limits specified in IS 800 shall also be complied with. FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 36 OF 42 13. 1Minimum thickness of steel sections Trusses, Purlins, side girts & bracings 6mm Columns & beams 7mm For gussets, stiffeners, plate guides, etc. 8mm For base plates 10mm Chequered plates 6mm Grating 5mm The minimum thickness of tubes shall be as specified in IS 1161 for medium class tubes. The minimum thickness for rolled beams and channels shall be mean flange thickness regardless of web thickness. The slenderness limits of sections shall conform to IS 800. 13. 2Deflection Control for structural steel members The permissible vertical and lateral deflection for structural steel members shall be as specified in IS 800:2007.The lateral deflection of Conveyor supporting Trestles shall be as per IS­11592. Permissible deflections of members shall be as follows: Member Purlin Purlin Truss Monorail Column Type of deflection Loading Maximum Deflection Vertical DL+WL Span /180 Lateral DL+WL Span/180 Vertical DL+WL Span/120 Vertical DL+IL+CL Span/500 Lateral DL+WL Height/150 13. 3Connections As far as possible, all the shop connections shall be welded and site connections shall be bolted. Minimum thickness of any structural weld shall be 6mm. Field connections shall be made with black bolts for ladders, hand rails posts, stair stringers, removable members and floor plates, platform forming members 200mm and under in size, purlins, girts and minor pipe support FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 37 OF 42 members that require not more than three bolts per connection. The minimum size of bolts shall be 16mm unless limited by the size of the connected parts. Any connection shall have at least two bolts. Expansion joints in steel structures shall be provided as per the guidelines in IS 800. Roofing over steel trusses shall be with non­Asbestos fibre reinforced cement corrugated sheet (as per IS: 14871) roofing 6 mm thick up to any pitch and fixing with polymer coated J, or L hooks, bolts and nuts 8 mm dia. G.I. plain and bitumen washers or with self­drilling fastener and EPDM. All accessories like flashing, capping, shall be made of the above specified material. The gutter shall be of 180mm dia half round moulded PVC. Roofs shall generally have a slope of 1:3. Rain water gutters and pipes shall be provided for proper roof drainage and collection of rainwater in accordance with SP 35. 14. DESIGN – FACTORS OF SAFETY All structures above ground shall be designed for Limit state of strength and shall be checked for serviceability conditions. In case of foundations, following factor of safety shall be adhered to in different load combinations to establish the most economical design that is compatible with life expectancy and service life of structures. Minimum Factor Of Safety Against Overturning Type Of Structure With Wind Without Or Seismic Wind Seismic Minimum Factor Of Safety Against Sliding With Wind Without Wind Or Or Seismic Or Seismic All structures/Eqpmnt Supports 1.5 2 1.5 1.5 Pipe rack 1.5 2 1.5 1.5 Retaining / Dyke wall 1.5 2 1.5 1.75 FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 38 OF 42 Minimum Factor of safety against UPLIFT shall be 1.2 for all structures. (Note: In case of sumps/pits, lining weight shall not be included) For machine foundation design IS 2974 shall be strictly followed and additional safety checks for frequency and mass ratio shall be performed depending upon the vibration range of machinery above it. In addition to stablitiy ratio check, foundation settlement shall also be restrained to the limits specified in IS 1904. Long­term and differential settlement criteria shall be determined while designing and special consideration shall be given to differential settlement of foundations supporting interconnected, settlement­sensitive equipment or piping systems. 15. DELIVERABLES The CONTRACTOR shall prepare and submit the following: 1. Architectural drawings, Civil & structural design & construction drawings based on the standard accepted practice and guidelines 2. Bar bending schedules 3. Fabrication drawings 4. As­built drawings 5. Design calculations based on the standard accepted practice and guidelines FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 39 OF 42 All design calculations shall be written or typed systematically in MS Excel, legibly and submitted for approval as per standard accepted practice. For structures, analysis and design shall be done on latest version of STAAD.pro software. Detailing / drafting shall be done on latest version of CAD software only. Drawing size used shall be preferably of A1 size only. For foundation layout, drainage plans and paving plans, A0 size drawings can be used if necessary All Drawings shall be in metric units showing dimensions and elevations in millimetres. Drawings shall indicate quantities of concrete grade wise and or nominal mix wise, reinforcement bars diameter wise and structural steel section wise and or thickness wise as detailed therein. The contractor shall submit requisite number of prints (as mentioned elsewhere) of the supporting design calculations along with explanatory notes/ sketches, computer inputs & outputs and Drawings (complete in all respects) to Owner/ Consultant for review and checking purposes. All the above design calculations and Drawings submitted by the Contractor shall be completed in all respects and thoroughly checked, Approved, stamped as "Approved for Construction" and signed by the Contractor's authorised representative (irrespective of the fact that whether the same are prepared in the Contractor's own Design Office or by an Approved Agency to ensure accuracy and correctness) before submission to the Owner/ Consultant. Incomplete, unchecked and unsigned Drawings and design calculations shall not be accepted for review/ checking and will be returnedforthwith. The design calculations and Drawings prepared for this works shall have to be got checked and Approved by the Owner/ Consultant as per mutually agreed time schedule and the Contractor FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 40 OF 42 should strictly adhere to these Approved Drawings and specifications. Construction work shall be carried out only with the Approved Drawings and specifications. Correctness / soundness of the designs/ Drawings and their execution at site shall be the sole responsibility of the Contractor irrespective of the fact whether the same has been Approved by Owner/ Consultant or not. Any defect, observed during construction or during the defect liability period of works, shall be rectified and removed by the Contractor. The contractor shall carry out whatever modification or re­construction is needed for the purpose, to the entire satisfaction of the Engineer­in­Charge / Owner without any extra cost to the Owner. But this will not in any way absolve Contractor of the final responsibility for fulfilment of all Guarantee Clauses specified elsewhere. If due to any un­avoidable reason, the contractor wishes to use any other software, other than mentioned in the Tender, he shall indicate the names of the computer software to be used for drafting and analysis/design work. The Contractor must get the approval of the Owner/ Consultant for the computer software prior to their use. The Contractor shall forward to Consultant four prints of design calculations and Drawings preferably for the whole work at a time along with all the concerned civil scope Drawings and load data sheets. After reviewing the above design calculations and Drawings, Consultant will send comments to the Contractor within four weeks’ time from the date of receiving the above. The Contractor will send their designer, if required, to Consultant's office for clarifications /modifications/ incorporations and to finalize designs/Drawings across the table. The design calculations and Drawings for each independent building/structure along with scope/load data shall be submitted by the Contractor in one lot so as to facilitate systematic review/ checking and approval. The contractor shall start submitting such first set of design calculations and Drawings within thirty days from the date of FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI 32644-12-PS-003-DB PAGE 41 OF 42 issue of Letter of Intent and complete the submission of the same for all the items/ units to Consultant's Office within the period mutually agreed upon depending on the volume of job. Any delay in submission of design calculations and/ or Drawings with complete data and getting the same Approved from Consultant shall not absolve the contractor of their responsibility to complete the work within the completion time. If at a later stage, the contractor feels the necessity for any addition or alteration, prior approval of Owner / Consultant must be taken for effecting the changes. The contractor shall also be bound to incorporate any addition and alteration which Owner/ Consultant may suggest at a later stage. FACT ENGINEERING AND DESIGN ORGANISATION R1 TECHNICAL PROCUREMENT SPECIFICATION DESIGN PHILOSOPHY AND BASIS FORCIVIL& STRUCTURAL WORKS - CONSTRUCTION OF ADDITIONAL PHOSPHORIC ACID STORAGE TANKS AT Q10 BERTH, WI ANNEXURE A FACT ENGINEERING AND DESIGN ORGANISATION 32644-12-PS-003-DB PAGE 42 OF 42 R1 SCHEDULE OF RATES Name of Work: General Notes: Sr. No. A PARTICULARS QTY. UNIT RATE (Rs.) SCHEDULE OF RATES AMOUNT IGST Total Amount (Rs.) (%) (Rs.) DESIGN, DETAIL ENGINEERING, PREPARATION OF DRAWINGS GOOD FOR CONSTRUCTION, SUPPLY, DELIVERY AT SITE, UNLOADING ,FABRICATION, INSTALLATION, THIRD PARTY INSPECTION, TESTING AND COMISSIONING OF INTAKE SCREEN SYSTEM AS PER TECHNICAL SPECIFICATIONS MENTIONED IN THE TENDER DOCUMENT. A Mechanical ERECTION OF TANK 1 Tank 2 PA Pumps SUB TOTAL B PIPING SUB TOTAL C CIVIL 1 2 3 4 5 Demolishing R.C.C. work manually / by mechanical means including cutting and stacking of reinforcement bars and disposal of unserviceable material with in premises of FACT at Q10 as per direction of Engineer in‐charge. Demolishing stone rubble masonry in cement mortar manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within premises of FACT at Q10 as per direction of Engineer in‐charge Dismantling doors, windows and clerestory windows (steel or wood) shutter, of area 3sqm and below, including chowkhats, architrave, holdfasts etc. complete and stacking within premises of FACT at Q10 Dismantling doors, windows and clerestory windows (steel or wood) shutter, of area beyond 3 sq. metres , including chowkhats, architrave, holdfasts etc. complete and stacking with in premises of FACT at Q10 Dismantling steel work manually/ by mechanical means in built up sections without dismembering and stacking within premises of FACT at Q10 as per directions of Engineer in‐ charge. 6 Dismantling Asbestos sheet roofing including ridges, hips, valleys and gutters etc, and stacking the material within premises of FACT at Q10 as directed by Engineer in‐charge. 7 Surface dressing of the ground including removing vegetation and inequalities not exceeding 15cm deep and disposal of rubbish, with in premises of FACT at Q10 and lift up to 1.5m in all kinds of soil Felling trees of girth (Measured at a height of 1m above ground level) including cutting of trunks and branches, removing the roots by uprooting, stacking of serviceable material and disposal of unserviceable material ‐ Beyond 60cm girth up to and including 120cm girth. Felling trees of the girth (measured at a height of 1m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material ‐ Beyond 120cm girth up to and including 240cm girth Disposal of moorum / building rubbish / malba / similar unserviceable, dismantled or waste material by mechanical transport including loading, transporting, unloading to approved municipal dumping ground for lead up to 30km for all lifts, complete as per directions of Engineer in‐charge. Note ‐ Item to be applicable in urban areas having directions for restricted hours for movement/ plying of load carrying motor vehicle of 3.5cum or more. Casting 750mm diameter bored cast in‐situ reinforced cement concrete piles in M35 grade ready mix concrete after boring through Direct mud circulation method as per IS 2911‐ Part 1/sec 2, having minimum cement of 400 kg/cum of concrete, using Portland Pozzolana cement conforming to IS 1489, river sand / manufactured sand conforming to IS 383, 20mm or less size graded hard granite broken stones, admixtures to concrete as per IS 9103, water as per IS 456 and reinforced with High strength deformed bars of 500D grade conforming to IS 1786 for the entire length of piles. All the materials used in the casting of concrete shall be done with the approval of Engineer in‐charge. The rate shall include the cost for all plants, tools, materials labour and other services for boring the piles including mobilisation and de‐mobilisation of piling rigs, boring to the required depth and stabilisation of hole with bentonite slurry or other required material to suit site conditions, making channels in the ground, making service roads and arrangements for transportation and disposal of muck (The muck will be treated as owned by the contractor and it will be the responsibility of the contractor to dispose the muck without causing environment damage with necessary permission from the concerned authority and consultant / client to be informed well in advance on the disposal methodology before starting the work), cleaning the bores with water, lowering the reinforcement cages, concreting, excavating and levelling the ground exposing piles to a depth of 100mm below cut‐off level after curing and gaining sufficient strength. Rate of reinforcement alone shall be paid extra ‐ For piles of length 65m below cut‐off level. (payment shall be made Chipping and removing weak concrete at the top of RCC piles to the cut off level in line and levels carefully, manually / mechanically without damaging the remaining portion of pile and exposing the reinforcement, cleaning the reinforcement off any loose concrete particles and removing the debris to places pointed out within the project premises as directed by the Engineer in‐charge. 8 9 10 11 12 102 Cum 48 Cum 5 Each 5 Each 1678 kg 23 Sqm 2000 Sqm 3 Each 3 Each 206 Cum 8450 Rm 60 Cum 13 Charges for empty boring through various strata to the required diameter of pile specified in the Item above, clearing the area, collecting, conveying and disposal of muck of all types such as liquid, fluid, solid and spoil earth (The muck will be treated as owned by the contractor and it will be the responsibility of the contractor to dispose the muck without causing environment damage with necessary permission from the concerned authority and consultant / client to be informed well in advance on the disposal methodology before starting the work) including hire charges for tools and plants, rigs, cost of labour, etc. complete for all depth. (Payment will be made for abandoned pile due to reasons attributable to owner and for empty boring involved in between ground level at the time of casting the piles and cut‐off level of piles.) 500 mm dia. piles 130 Rm 14 Arranging and conducting routine tests on single pile of diameter 750mm and length up to 65m below cut off level described in Item above as per IS: 2911 (Part‐IV) latest revision including all required arrangements materials, machineries such as test cap, loading platform, hire and labour for kentledges, cost of all materials, tools and plants, instruments for loading and recording settlements with dial gauge / LVDTS (calibrated), and labour charges, submitting reports etc complete as per technical specifications for 750mm dia piles for a maximum load of 3525kN or the load at which the maximum settlement of test loading in position exceeds the permissible value. 1 15 Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains , in all kinds of soil, including dressing of sides and ramming of bottoms, lift up to 1.5m, including getting out the excavated soil and disposal of surplus excavated soil as directed with in premises of FACT at Q10 and close timbering in trenches including strutting, shoring and packing cavities wherever required and bailing out water to keep the excavated trenches suitable for concreting. 16 17 ‐‐PRICES NOT TO BE FILLED IN HERE‐‐ Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering Supplying and filling contractor's own good quality earth to the required levels and grades to level uneven areas at site in layers of 200 mm including watering, ramming, etc complete with all leads and lifts as directed by Engineer in charge (Measurement will be given for consolidated filled volume as per initiasl and final levels as approved and certified by Engineer ‐ in ‐ charge) Charges for conveying the surplus earth to places approximately 30 kms away and dumping at low lying places as directed by the Engineer in‐charge. Note ‐ Item to be applicable in urban areas having directions for restricted hours for movement/ plying of load carrying motor vehicle of 3.5cum or more. Providing hard core layer of required thickness using 40mm Nominal size graded hard granite broken stones after compacting the underlying soil, spreading and levelling the stones and then spreading a layer of 6mm downgraded crushed aggregates on top of the broken metal layer and it shall be watered in order to force the crushed fine aggregates into the void spaces of the broken stone and repeat the process till all the voids are filled with crushed fine aggregates right up to the edges of hard core layer, including cost of all materials and labour charges etc., complete Providing 50mm thick bitumen sand mix with blown type bitumen of penetration 85/25 and clean river sand (120kg. bitumen/cum of sand) over a tack coat (total industrial asphalt to be used at 62.5kg /10sqm of surface (including 2.5 kg/10sq.m. of tack coat) including all charges for cleaning the surfaces, heating bitumen, mixing, laying, consolidating, finishing, etc. complete. Supplying and providing high build epoxy based chemical resistant coating for outer surface of tank foundation (CERACOTE EP CR of Cera Chem or equivalent) as per manufactures specification to achieve a minimum dry film thickness of 500 microns Each 3450 Cum 1039 Cum 9 cum 2411 Cum 345 Cum 1010 Sqm 2600 Sqm 315 Sqm 220 Cum 1308 Cum 25 Providing and laying in position ready mixed M‐35 grade concrete for reinforced cement concrete work, using fly ash and cement content as per approved design mix, and manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for reinforced cement concrete work, including pumping of R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering, finishing and reinforcement, including cost of admixtures in recommended proportions as per IS : 9103 to accelerate / retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer ‐ in ‐ charge. NOTE‐ (1) Cement content considered in this item is @ 350 kg/cum. Excess/ less cement used as per design mix is payable/ recoverable separately.“ (2) Fly ash conforming to grade I of IS 3812 (Part‐1) only be used as part replacement of OPC as per IS : 456. Uniform blending with cement to be ensured in accordance with clauses 5.2 and 5.2.1 of IS:456 ‐2000 in the items of BMC and RMC ‐ All works above plinth level upto and including floor V level 322 Cum 26 Providing and laying in position ready mixed M‐30 grade concrete for reinforced cement concrete work, using fly ash and cement content as per approved design mix, and manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for reinforced cement concrete work, including pumping of R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering, and reinforcement, including cost of admixtures in recommended proportions as per IS : 9103 to accelerate / retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer in ‐ charge. NOTE‐ (1) Minimum Cement content shall be @ 340 kg/cum. Excess/ less cement used as per design mix is payable/ recoverable separately. “(2) Fly ash conforming to grade I of IS 3812 (Part‐1) only be used as part replacement of OPC as per IS: 456. Uniform blending with cement to be ensured in accordance with clauses 5.2 and 5.2.1 of IS:456 in the items of BMC and RMC – for all works up to plinth level except pile cap. Approved make of materials are furnished in Specific requirements of work – 32644‐12‐DA‐003 260 Cu.m 27 Providing and laying in position ready mixed M‐30 grade concrete for reinforced cement concrete work, using fly ash and cement content as per approved design mix, and manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for reinforced cement concrete work, including pumping of R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering and reinforcement, including cost of admixtures in recommended proportions as per IS : 9103 to accelerate / retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer in ‐ charge. NOTE‐ (1) Minimum Cement content shall be @ 340 kg/cum. Excess/ less cement used as per design mix is payable/ recoverable separately. (2) Fly ash conforming to grade I of IS 3812 (Part‐1) only be used as part replacement of OPC as per IS: 456. Uniform blending with cement to be ensured in accordance with clauses 5.2 and 5.2.1 of IS:456 ‐ in the items of BMC and RMC – for all works above plinth level . Approved make of materials are furnished in Specific requirements of work – 32644‐12‐DA‐003 114 Cu.m 18 19 20 21 22 23 24 Acid proof lining after cleaning the cement finished surface well with water and allowing to dry, brushing and removing all dust, apply two coats of approved quality bitumen based primer conforming to IS. 1580 as per manufacture's specification, applying 12 mm thick asphalt membrane with hot melt asphalt free from filler conforming to IS. 1580, then laying acid resistant tiles of class II quality conforming to IS. 4860 over a bed of 6 mm thick potassium based silicate cement mortar conforming to IS. 4832 ‐ part. I & 4441 and joints 5 mm thick, raking the joints to full depth from the top surface, removing the raked‐out mortar and filling the entire depth of joints with Furan base resin cement mortar conforming to IS. 4832 ‐ part. II including acid washing curing etc. complete as per relevant IS. 4443 specifications at all heights. ‐ 230X112X38 mm or nearest size tile Cement concrete work in 1:3:6 mix (1 Portland Pozzolana cement: 3 coarse river sand/manufactured sand: 6 20mm nominal size graded hard granite broken stones) including all charges for mixing concrete, necessary shuttering, laying, consolidating, curing, removal of shutters, cost for bailing out of water, oil, liquid mud etc. from all sources in excavated pits, trenches, etc. complete at all levels as per standard specifications and as directed by the Engineer in‐charge for foundation / levelling course etc. Approved make of materials are furnished in Specific requirements of work – 32644‐12‐DA‐003. Providing and laying in position ready mixed M‐35 grade concrete for reinforced cement concrete work, using fly ash and cement content as per approved design mix, and manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for reinforced cement concrete work, including pumping of R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering, and reinforcement, including cost of admixtures in recommended proportions as per IS : 9103 to accelerate / retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer in ‐ charge. NOTE‐ (1) Minimum Cement content shall be @ 350 kg/cum. Excess/ less cement used as per design mix is payable/ recoverable separately. “(2) Fly ash conforming to grade I of IS 3812 (Part‐1) only be used as part replacement of OPC as per IS: 456. Uniform blending with cement to be ensured in accordance with clauses 5.2 and 5.2.1 of IS:456 in the items of BMC and RMC – for pile caps . Approved make of materials are furnished in Specific requirements of work – 32644‐12 DA‐003 28 Providing and laying in position ready mixed M‐20 grade concrete for reinforced cement concrete work, using fly ash and cement content as per approved design mix, and manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for reinforced cement concrete work, including pumping of R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering, and reinforcement, including cost of admixtures in recommended proportions as per IS : 9103 to accelerate / retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer in ‐ charge. NOTE‐ (1) Minimum Cement content shall be @ 300 kg/cum. Excess/ less cement used as per design mix is payable/ recoverable separately. “(2) Fly ash conforming to grade I of IS 3812 (Part‐1) only be used as part replacement of OPC as per IS: 456. Uniform blending with cement to be ensured in accordance with clauses 5.2 and 5.2.1 of IS:456 in the items of BMC and RMC – for yard concreting, drains, stairs. Approved make of materials are furnished in Specific requirements of work – 32644‐12‐DA‐003 381 Cum 29 Reinforced cement concrete work of M25 grade for precast cover slab using Portland pozzolana cement containing more than 25% of fly ash, river sand / manufactured sand conforming to IS 383 and 20mm nominal size graded hard granite broken stones including all charges for designing the mix, weigh batching, including installation of batching plant at the designated location in the site premises or arranging RMC, mixing concrete, cost of adding concrete admixtures as required, transporting, formwork, laying, vibrating, consolidating, curing with minimal use of potable water subject to provision of IS 456, handling, transporting, loading, unloading, keeping and fixing in position, at all levels etc., complete but excluding cost of providing reinforcements. (Exposed surfaces of pre‐cast elements shall have good finish with no blemish or mark on the finished surfaces) NOTE‐ (1) Minimum Cement content shall be @ 330 kg/cum. Excess/ less cement used as per design mix is payable/ recoverable separately. (2) Fly ash conforming to grade I of IS 3812 (Part‐1) only be used as part replacement of OPC as per IS: 456. Uniform blending with cement to be ensured in accordance with clauses 5.2 and 5.2.1 of IS:456 in the items of BMC and RMC ‐for cover slabs (50mm to 100mm thick) on drain. Approved make of materials are furnished in Specific requirements of work – 32644‐12‐DA‐003. 18 Cum 30 Add for using extra cement in the items of design mix over and above the specified cement content therein. 31 Providing form work to cement concrete and RCC works with necessary plywood / steel sheet, steel joists, runners, struts, posts etc with adjustable spans and telescopic posts, wooden planks for beam sides etc. including removal after completion /curing at all levels ‐ foundation footings, bases of columns and walls. for mass concrete with straight sides 32 158625 kg 635 Sqm Providing form work to cement concrete and RCC works with necessary plywood / steel sheet, steel joists, runners, struts, posts etc with adjustable spans and telescopic posts, wooden planks for beam sides etc. including removal after completion /curing at all levels ‐ foundation footings, pile caps, RCC kerb wall around pile cap, bases of columns and walls. for mass concrete with circular sides 210 Sqm 33 Providing form work to cement concrete and RCC works with necessary plywood/steel sheet, steel joists, runners, struts, posts etc with adjustable spans and telescopic posts, wooden planks for beam sides etc. including removal after completion / curing at all levels – Drain wall (any thickness). 1642 Sqm 34 Providing form work to cement concrete and RCC works with necessary plywood/steel sheet, steel joists, runners, struts, posts etc with adjustable spans and telescopic posts, wooden planks for beam sides etc. including removal after completion /curing at all levels ‐ Suspended floors, roofs, landings, balconies and access platform 50 Sqm 35 Providing form work to cement concrete and RCC works with necessary plywood/steel sheet, steel joists, runners, struts, posts etc with adjustable spans and telescopic posts, wooden planks for beam sides etc. including removal after completion /curing at all levels ‐ Lintels, beams, plinth beams, girders, bressumers and cantilevers 1113 Sqm 36 Providing form work to cement concrete and RCC works with necessary plywood/steel sheet, steel joists, runners, struts, posts etc with adjustable spans and telescopic posts, wooden planks for beam sides etc. including removal after completion / curing at all levels ‐ Columns, Pillars, Piers, Abutments, Posts and Struts 46 Sqm 37 Providing form work to cement concrete and RCC works with necessary plywood / steel sheet, steel joists, runners, struts, posts etc with adjustable spans and telescopic posts, wooden planks for beam sides etc. including removal after completion /curing at all levels ‐ Stairs, (excluding landings) except spiral‐staircases 11 Sqm 38 Supplying , fabricating, conveying and fixing reinforcement to RCC works at all levels with high strength deformed bars Fe500D grade Thermo Mechanically Treated (TMT) bars conforming to IS 1786 including all charges for uncoiling and straightening rods, cutting rods, bending cold, placing in position and supplying & tying with black annealed tying wire of 16 gauge, etc. complete. Approved make of materials are furnished in Specific requirements of work – 32644‐12‐DA‐003 469487 kg 39 Supplying, conveying fabrication and erection of MS single section members such as channels, guard rail, MS angle hand rails verticals, etc. with fixtures such as end stops, clamps, bolts and nuts etc. including charges for cutting, splicing, drilling holes as required, fixing to lines and levels and cleaning thoroughly with power tools and painting with two coats of red oxide zinc chromate primer ( one shop coat and one coat after fixing / erection) Approved make of materials are furnished in Specific requirements of work – 32644‐12‐DA‐003, Refer painting specs for applying priming coats 99377 kg 40 Supplying and fixing MS inserts of all types fabricated out of MS plates, angles, channels, flats, rods, fabricated pieces, etc. in RCC / masonry works at all levels including all charges for cutting, welding, fixing to lines and levels and painting the exposed surfaces with two coats of chemical resistant enamel paint of approved quality and colour over two coats of red oxide zinc chromate primer, etc. complete Approved make of materials are furnished in Specific requirements of work – 32644‐12‐DA‐003, Refer painting specs for applying priming coats 1337 kg 41 Providing and fixing mild steel round holding down bolts with nuts and washer plates complete to all lines and levels and applying petroleum jelly / grease after erection on exposed surface of bolts to prevent corrosion 190 kg 42 Painting of structural steel work over priming coats (paid with the steel supply item) as follows: a) One intermediate coat of Micaceous Iron Oxide epoxy paint of 70‐micron DFT b) One coat of two pack polyamide cured epoxy finish paint of 40‐microns DFT 2778 Sqm 43 Supplying and fixing pultruded GRP gratings made of Isophthalic polyester resin containing glass fibre content not less than 60% and having fire retardant characteristics, of 38mm height with I bar spacing not exceeding 40mm c/c and crossbars not exceeding 90 mm c/c, suitable for imposed load of 500kg/sqm of colour grey and designed for a max support span of 1300mm over cable trenches / drains / stairs with bonded grit antiskid surface including fixing to the existing structural steel frames / RCC walls by means of SS hold down clamps, locking arrangement etc. For step ladders, gratings have to be fabricated as per site measurement and shall be rigidly fixed to the existing structural by suitable locking arrangement. 2 Piece locking system of size 700 wide (I‐bar) x 1mtr (Cross Rod) Length. The GRP material shall be fire retardant meeting ASTM E84 Class A with Flame Spread less than or equal to 25 & Smoke Density ±200 and UV resistant meeting ASTM G154 with flexural strength not reducing by more than 7% on accelerated UV radiation exposure. Approved make of materials are furnished in Specific requirements of work – 32644‐12‐DA‐003. 183 Sqm 44 Supplying and grouting pockets, base plates, etc. at all levels for static equipment / structural steel supports using non‐shrink grouts. Approved make of materials are furnished in Specific requirements of work – 32644‐12‐DA‐0032. 2 Cum 45 Civil & Structural Design,Detailed Engineering and preparation of Good for Construction Civil & Structural drawings for the Phospohoric Acid tanks and Allied facilities as per the Design philosophy and Design Basis for Civil & Structural Works and Tender Specifications. 1 LS ‐‐PRICES NOT TO BE FILLED IN HERE‐‐ SUB TOTAL D Elecrtical SUB TOTAL E Instrumentation SUB TOTAL SUB TOTAL TOTAL PROJECT COST QUALITY MANAGEMENT SYSTEM 12ES001/18 CIVIL & STRUCTURAL WORKS PAGE 1 OF 14 1.0.0 2.0.0 3.0.0 4.0.0 5.0.0 6.0.0 7.0.0 8.0.0 9.0.0 10.0.0 11.0.0 12.0.0 13.0.0 14.0.0 15.0.0 16.0.0 17.0.0 CONTENTS SCOPE CLASSIFICATION OF BUILDING AND GENERAL REQUIREMENTS CODES AND DESIGN LOADS SITE CLEARING, EARTH WOK, BACK FILLING FOUNDATIONS CONCRETE WORK STRUCTURAL STEEL WORK MASONRY WOK ROOFING AND ROOFING TREATEMENT DOORS, WINDOWS, VENTILATORS FLOORING AND FLOORING FINISHES FINISHING WORK PROTECTIVE LINING SANITARY AND WATER SUPPLY ROADS DRAINAGE SYSTEM AND CABLE TRENCHES LIQUID RETAINING STRUCTURES 1.0.0 SCOPE 1.1.0 This document gives the engineering specification pertaining to Civil Engineering works. This document is meant for attaching along with the turn key package for various works in order to get uniform bid from the bidders to the extent possible. These specifications give the general requirements for design and material classification for different works. 1.1.1 The specifications given are not conclusive an additions required in the specifications shall be supplemented to suit to be project require meant by bidder mentioning the deviations and additions in separate statement to be attached along with the bids. 1.2.0 1.3.1 1.3.2 1.3.3 1.3.4 1.3.5 1.3.6 1.3.7 1.3.8 1.3.9 1.3.10 1.3.11 1.3.12 1.3.13 1.3.14 1.3.15 The engineering specifications covered in this document are listed below. Classifications of buildings and general requirements Codes and design loads Site clearing earth work, back filling Foundations Concrete works Structural steel works Masonry works Roofing and Roofing treatment Doors, Windows, Ventilators Flooring and Flooring finishes Finishing work Protective lining Sanitary and water Roads Drainage system and cable trenches 0 REV 01/09/2018 DATE Revised & Issued for ISO 9001:2015 REVISION DESCRIPTION FACT ENGINEERING AND DESIGN ORGANISATION HOD (C) PRPD GM (E) CHKD GM (F) APPRD QUALITY MANAGEMENT SYSTEM CIVIL & STRUCTURAL WORKS 12ES001/18 PAGE 2 OF 14 1.3.16 Liquid retaining structures 1.4.0 The contractor shall be responsible for the complete design of all civil structures of the project mentioned in the bid document. Issue these specifications do not absolve responsibility of the contractor with respect of the structural stability a suitable adoption of the engineering specifications. 1.5.0 A brief specialization of the work along the approximate bill of quantities of major items of work viz. RCC, Brick and rubble masonry and concreting ,doors and windows etc are to be submitted by the bidder along with the offer. 1.6.0 Whenever civil scope drawings are issued along with these specifications all designs shall be carried out to suit the civil scope drawing in addition to the engineering specification 1.7.0 In case civil scope drawing details and engineering specifications differ the details given in the civil scope drawings shall be followed for the design. 1.8.0 The specification for different work / structures pertaining to a particular project shall be provided in the data sheet “civil and structural works” (Ref. format No.12FT018) and shall attached. 2.0.0 2.1.0 2.1.1 CLASSIFICATION OF BUILDING AND GENERAL REQUIREMENTS CLASSIFICATIONS OF BUILDING Type A RCC Framed structure with masonry walls 2.1.2 Type B Building with RCC floor /roof supported on load bearing wall 2.1.3 Type C Building with steel column steel roof trusses with AC sheet roofing Masonry walls etc. 2.1.4 Type D As per Type a but with AC sheet cladding. 2.1.5 Type E As per Type C but with RCC columns 2.1.6 Type F As per Type C but with AC sheet cladding. 2.2.0 GENERAL REQUIREMENTS FOR BUILDINGS 2.2.1 The clear height of building shall not be less than 2.75 m generally. The size of a building shall not be less than 9.50m² where there is only one room and where there are two rooms one shall not be smaller than 9.50m² and other not less 7.50m². Minimum width shall be 2.4m. 2.2.2 The size of bath rooms shall not be less than 1.5m x1.20 or 1.8m² the combined bath room and water closet shall have a floor area of not less than 2.80m² with a minimum width of 1.2 m a water closet area of 1.1 m². The height of bath room or water closet shall not be less than 2.2 m. 2.2.3 Every bath room or water closet shall have at least one wall open to external air and shall not open in to a kitchen by a door or any other opening. 2.2.4 Rooms used as control rooms, MCC, compressor rooms etc. shall be provided with two doors 2.2.5 Minimum width of stairs shall be 1 m 2.2.6 The minimum width of treads without nosing shall be 25 cm for internal stairs. 2.2.7 Minimum rise for stairs shall be15cm for stairs of public building and residential building and 18 cm for stairs of plant buildings. 2.2.8 Minimum treads of stairs shall 30cm for public buildings and 25cm for plant buildings 2.2.9 The minimum clear head room in a passage under a stair case landing and the minimum clear head room in stair case shall be 2.20m. 2.2.10 Hand rails shall be provided with in a minimum height of 100cm and shall be firmly supported 2.2.11 Sump, Tank, Pit, or openings in ground or in a floor shall be covered or fenced securely. FACT ENGINEERING AND DESIGN ORGANISATION 12FT012/18 QUALITY MANAGEMENT SYSTEM CIVIL & STRUCTURAL WORKS 12ES001/18 PAGE 3 OF 14 2.2.12 2.2.13 2.2.14 2.2.15 Minimum width of steel ladder shall be 45 cm. Maximum spacing of rungs for steel ladder shall be 200 mm. where the height of steel ladder exceeds 2.4m cages shall be provided. all rails on which a travelling crane moves shall be of proper size and adequate strength. The rail shall have an even running surface .Every such rail or track shall be properly laid and adequately supported. 2.2.16 General requirements of building are not conclusive and shall satisfy the prevalent municipal/statutory bodies’. 3.0.0 3.1.0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 3.2.0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 CODES AND DESIGN LOADS The design of structures foundations, etc. shall be as per latest relevant IS codes. Items not covered in the IS codes can be designed based on other international codes like BS codes American codes etc. or other accepted engineering practices some of the relevant IS codes for designs are listed below. Structural safety of buildings loading standards IS 875(Part I to IV) Earthquake resistant design of buildings IS1893 Plain and Reinforced Concrete IS 456 Concrete structures for storage of liquid IS 3370(Part I to IV) Design of reinforced concrete shell structures and folded plates IS 2210 Designs of reinforced concrete chimneys IS 4998 Design of reinforced concrete bins (silos) for Bulk food grain storage IS 4995 Structural safety of buildings masonry walls IS 1905 Structural safety of building foundations IS 1904 Design and construction of spread o foundation IS 1080 Design and construction of machine foundation IS 2974(Part I to V) Design and construction of raft foundation IS 2950 Design and construction of pile foundation IS 2911 (Part I to IV) Basic requirement of water supply, drainage and sanitation IS 1172 Water supply in buildings IS 2065 Design and construction of septic tanks IS 2470 Building drainage IS 1742 Structural steel in general building construction IS 801 The materials used, construction practices, testing procedures etc. shall also conform relevant IS codes. Only tested quality material shall be used. Some of the relevant codes for commonly used materials and construction practices are listed below. earthquake resistant construction of building IS 4326 Cold twisted steel bars IS 1786 Mild steel and medium steel bar for reinforcement IS 432(Part I) Fabric for concrete reinforcement IS 1556 Structural steel IS 226 Burnt clay building bricks IS 3495(Part I to IV) Hollow light weight concrete block IS 2185(Part I) Specifications for concrete masonry unit IS 2185 (Part II) Construction of stone masonry IS 1597(Part I & V) Brick work IS 2212 Preparation and use of masonry mortars IS 2572 Construction of hollow concrete bock masonry IS 2572 Plastic pipe work for water supply IS 7634(part I to III) LDPE pipe for portable water supply IS 3076 HDPE pipe for portable water supply IS 4984 FACT ENGINEERING AND DESIGN ORGANISATION 12FT012/18 QUALITY MANAGEMENT SYSTEM 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 3.30 3.4.0 3.4.1 3.4.2 3.4.3 3.4.4 3.4.5 3.4.6 CIVIL & STRUCTURAL WORKS 12ES001/18 PAGE 4 OF 14 Unplasticised PVC pipes for portable water supply IS 4985 Construction of refuse duct for malty storied Building IS 6924 Cement and cement lime plastic finishes IS 1661 Painting concrete masonry and plastered surface IS 2395(Part I & II) Painting in ferrous metals in buildings IS 1477(Part I&II) White washing & colour washing IS 6278 Laying in situ concrete flooring IS 2571 Selection of industrial floor finishes IS 4971 Aluminium doors, windows and ventilators IS 1948 Aluminium doors for industrial building IS 1949 Steel door, windows and ventilators IS 1038 Steel windows for industrial building IS 1361 Timber door, windows and ventilators frame IS 4021 Timber panelled and glazed shutters IS 1003 (Part I&II) Acid resistant bricks IS 4860 Chemical resistant mortars IS 4832(Part I to II) The list of given is not conclusive. Related codes and other relevant codes published by the Burro of Indian standards shall be used along with the engineering specifications. DESIGN LOADS Design loads In addition to dead ,live, wind or earth quake loads as per Indian standard codes, the building and structures shall be designed for additional loads due to cranes mono rails equipment (including impact and vibrations if any) platforms etc.., as per actual requirements. Load combinations Load combinations shall be as started in a relevant Indian standard and recommendations and combinations specified by the equipment supply if any. Wind and Earth quack loads Unless otherwise specified wind and earth quack effect on structures on structures shall be analysed based on relevant Indian standard codes and necessary modification factors may be applied according to specific recommendations , if any Dynamic loads Whenever dynamic loads act on a structure the effect same shall be considered in the design along with the static live and wind or earth quack load. Analysis of Structures Frame analysis shall be carried out for all framed structures. All connections shall be moment connections. However bracing may be provided wherever deemed necessary incase of the above. In case of computer aided analysis /designs all relevant backups such as load calculation flow charts , computer dates etc.., shall be furnished . Computer outputs shall be in clear easily understanding able formats and shall be submitted in proper bound volumes. 4.0.0 4.1.0 4.2.0 4.3.0 SITE CLEARANCE, EARTH WORK AND BACK FILLING The specification covers the requirements regarding site clearances, earth work back filling etc. to be done at site. Excavation shall be carried out to true line and levels in all type of soil except hard rock requiring blasting. When hard rock is encountered the surface shall be levelled/benched as directed by the engineer- in- charge All arrangements for drainage to keep the pits dry and required dewatering to be included in the quoted rate. FACT ENGINEERING AND DESIGN ORGANISATION 12FT012/18 QUALITY MANAGEMENT SYSTEM 4.4.0 4.5.0 4.6.0 CIVIL & STRUCTURAL WORKS 12ES001/18 PAGE 5 OF 14 All shoring and strutting required for holding the size of excavation from collapse to be included in the quoted rate Removal of rubbish, slush, etc. from site to be included in the rate. Back filling to be carried out using selected earth from excavation of good sand brought from outside. 5.0.0 FOUNDATIONS This specification covers the requirement governing design of foundations of varies structures. 5.1.0 All designs shall be done based on relevant Indian standard codes. 5.2.0 All foundations shall be done designed to suit the soils conditions. For this purpose the bidder may visit the site and get familiarized with soil conditions by conducting soil exploration work, if necessary. When soil investigation reports are available, the design is to be done as recommended in the report. 5.3.0 All underground pits, slumps, etc, shall be designed to take care of the uplift forces due to buoyancy. 5.4.0 All foundations shall rest on firm original ground. 5.5.0 Unless otherwise recommended in the soil investigation report, all foundations shall extend at least 60 cm below natural ground level. On rock or weather resisting natural ground, removal of top soil may be all that is required. Foundations in any type of soil shall go below the zone significantly weakened by root holes or cavities produced by burrowing animals or worms. 5.6.0 If the sub soil is of aggressive nature sulphate resisting cement shall be used for foundations/ underground structures. 5.7.0 The size, thickness and concrete mix for building and equipment foundations shall be capable to transfer the load on the sub soil. 5.8.0 PCC 1:4:8 shall be used for leveling course, except for liquid retaining structures. The thickness of leveling course shall be 80mm and minimum 150mm thick when used as structural element. Leveling course below liquid retaining structures shall be of 1:3:6 mix 5.9.0 The minimum cover of 75mm shall be provided for foundations pockets to the edge of foundations. 5.10.0 The foundations for machinery and allied equipment shall be designed as recommended by equipment suppliers. Provision for isolation pads, vibration dampeners, bearing pads, springs etc, shall be provided as per equipment manufacturers drawing. 5.11.0 For dynamic loaded foundations grouting shall be with non-shrink, high strength, free flow, cementitious grout like Conbextra GP1, Shrinkkomp, etc. for static loaded foundation, grouting shall be with cement grout or jelly concrete sand grout. 6.0.0 6.1.0 6.2.0 6.3.0 CONCRETE WORKS This specification covers the requirements governing the design of concrete structures for buildings, equipment foundations, storages, chimneys, etc. All design shall be done based on the relevant Indian standard codes. DESIGN CRITERIA All design shall be carried out based on relevant IS codes and sound engineering practices. The structure shall be designed based on the correct evaluation of all loads imposed on the structure. The static equilibrium of the structure must be adequate against the different type of loading. MINIMUM THICKNESS AND DIMENSIONS Minimum thickness of various components of the structure is given below. Floor slabs including slabs on ground 10cms FACT ENGINEERING AND DESIGN ORGANISATION 12FT012/18 QUALITY MANAGEMENT SYSTEM 6.4.0 6.5.0 6.6.0 6.6.1 6.6.2 6.6.3 6.7.0 6.7.1 6.7.2 6.7.3 6.8.0 6.8.1 6.9.0 6.9.1 6.9.2 7.0.0 7.1.0 CIVIL & STRUCTURAL WORKS PAGE 6 OF 14 Column footing 15cms Underground pit slab walls 50cms Minimum dimension of beam / column 200mm Levelling course 80mm Minimum cover reinforcement shall be as per provisions in relevant IS codes. However for works against earth faces, corrosive environment, etc., the cover shall be increased by 30mm than the code provisions. MINIMUM HEIGHT OF PLINTH / PEDESTAL. The minimum height of plinth / pedestal above finished grade or floor level shall be as follows. 1. Building plinth 300mm above nearest road or pavement level 2. Pedestals / encasements for structural columns Open area 300mm Covered area 150mm 3. Pedestals for all equipment Open area as required but not less than 300mm Cover area as required but not less than 150mm 4. Stair pedestal 150mm 5. Ladder pedestal 150mm GROUTING For structural columns as required but not less than 25mm For equipment as required but not less than 25mm The specification for grout shall be either 1:1 cement grout or readymade non shrink grout to suit the type of equipment to be grouted. CONCRETE MIX Levelling course of mix not leaner than1:4:3 shall be provided under foundations other than water retaining structures. M 15 or higher grade concrete shall be used for RCC works. When nominal mix is adapted minimum concrete mix shall be1:2:4. Under any circumstances minimum cement content shall not be less than 330 kg/m^3. Richer concrete mix shall be adopted wherever required to suit the design requirement. REINFORCEMENT RODS The reinforcement rods for concrete shall be as follows. Main bars in columns, footings, Cold twisted steel bars. slabs, foundations, etc. Lateral ties, stirrups, etc Cold twisted steel bars/mild steel bars. Reinforcement for floors Mild steel bars/steel fabric EXPANSION JOINTS Expansion joints in concrete structures shall be provided as per relevant IS code provisions at suitable intervals. Bitumen impregnated fiber boards of approved manufacture as per IS 1838 shall be used as fillers for expansion joints. The gap between the expansion joints shall be thoroughly cleaned and the bitumen fiber boards placed in position as per manufacturer’s specification. The expansion, contraction and construction joints, etc. for water retaining structures shall be provided as per the codal provisions. All water bars specified shall be PVC. STRUCTURAL STEEL WORKS. This specification covers the requirements governing the design of steel structures. All design shall be done based on the relevant Indian standard code. FACT ENGINEERING AND DESIGN ORGANISATION 12FT012/18 12ES001/18 QUALITY MANAGEMENT SYSTEM 7.2.0 7.3.0 7.4.0 7.5.0 7.5.1 7.5.2 7.5.3 7.5.4 7.6.0 7.7.0 7.8.0 7.9.0 7.9.1 7.9.2 8.0.0 8.1.0 CIVIL & STRUCTURAL WORKS PAGE 7 OF 14 MINIMUM THICKNESS OF STEEL For gussets, stiffeners, plate guides, etc. 8mm For base plates 10mm SLENDERNESS AND DEPTH RATIO. The slenderness ratio of main members in tension and compression shall be in accordance with IS 800. The following limiting ratios of depth to span shall be considered as general guide. Trusses 1/10 Rolled beams and girders for ordinary Floors and rafters 1/24 Supporting floor beams for vibrating Machinery 1/15 Roof purlins and girts 1/45 Cable columns 1/30 Gantry girders (rolled sections) 1/15 Gantry girders (built up) 1/12 CONNECTIONS The connections shall be welded as far as possible. Field connections shall be made with black bolts for ladders, hand rail posts, stair stringers removable members and floor plates, platform forming members 200mm and under in size, purlins, girts and minor pipe support members that require not more than three bolts per connection. The minimum size of bolts shall be 16mm unless limited by the size of the connected parts. MATERIAL Unless otherwise specified, steel or hot rolled structural shapes and plates shall conform to IS 226 / 2062. Steel tubes for structural purpose shall conform to IS 1161. High Strength bolts shall conform to IS 3757. Bolts shall conform to IS 1367. ERRECTION LOADS All loads to be carried by the structure or any part if it due to storage or positioning of construction material and erection equipment including all loads due to operation of such equipment shall be considered as erection load. Proper provision shall be made including temporary bracings to take care of stresses due to erection loads. The structure as a whole and all part of the structure in conjunction with temporary bracings shall capable of sustaining this erection load without exceeding the permissible stresses. Dead loads, wind loads and all such parts of live load as would be imposed on the structure during the period of erection shall be taken as acting together with the erection load. TEMPERATURE EFFECTS Expansion and contraction due to changes in temperature on the material of a structure shall become decisive in design and adequate precautions shall be made for such effects. FLOOR COVERING Gratings or chequered plates shall be used for covering .gratings / chequered plates shall be designed for a full live load plus a point load of 500kg minimum. PAINTING, GALVANIZING, FIRE PROOFING All fabricated structural steel, unless galvanized shall receive a shop coat of primer and painted as per specification. Steel which is to be fire proofed (marked FP on design drawings) shall be fabricated unpainted and shall be given a coat of cement wash before encasement in fire proofing material. MASONRY WORKS This specification covers the requirements governing design of masonry structures. FACT ENGINEERING AND DESIGN ORGANISATION 12FT012/18 12ES001/18 QUALITY MANAGEMENT SYSTEM 8.2.0 8.3.0 8.3.1 8.3.2 8.3.3 8.3.4 8.3.5 8.4.0 8.4.1 8.4.2 8.4.3 8.4.4 8.4.5 8.5.0 8.5.1 8.5.2 8.5.3 9.0.0 9.1.0 9.1.1 9.1.2 9.2.0 9.2.1 9.2.2 CIVIL & STRUCTURAL WORKS PAGE 8 OF 14 All design shall be based on relevant Indian standard codes. RANDOM RUBBLE MASONRY The minimum thickness of wall / foundation shall be 38 cms. The thickness shall be determined based on the loading and its slenderness ratio as per the codal provisions. The mortar for the masonry shall be 1:6 cement mortar. All exposed faces of rubble masonry shall be pointed with cement mortar 1:3. Wherever plastering is required the same shall be of cement plaster 1:4 mix, 15 mm thick. BRICK MASONRY The minimum thickness of wall shall be 20cm for load bearing walls and 10cm for partition walls. The thickness shall be determined based on the loading and slenderness ratio as per codal provisions. The mortar for the masonry shall be in cement mortar 1:6 for thickness 20cm and above and 1:4 for thickness 10cm. All fair faces of masonry shall be plastered with cement mortar 1:4 mix 12mm thick and rough surfaces with cement mortar 1:4, 15mm thick. Minimum strength of bricks used shall be of class 35. GENERAL REQUIREMENTS. Points of concentrated stress involved such as corners, openings and interesting where cracking is likely to occur shall be strengthened with steel reinforcement or PCC 1:2:4 mix. The thickness of load bearing walls shall be sufficient at all points to keep the combined stresses due to live, dead and other loads within permissible limits. Where high strength bricks are used richer mix cement mortar shall be used. All doors, windows and ventilator openings shall be provided with RCC lintels of required thickness. ROOFING AND ROOF TREATMENT. This specification covers the specification to be followed for providing roofing ad roof treatments for different structures. ROOFING RCC roof Minimum thickness 10cm and grade M 15. Slope of 1/200 shall be provided for flat roofs. An integral coat of cement plaster in cement mortar 1:3 average 6 mm thickness to be done on the top of slab. AC sheet roofing Unless otherwise mentioned the thickness of roofing sheet shall be 6 mm. Slope of the roof shall not less than 18 degrees. Half round a cave gutter with down shall be provided. Bolts for fixing AC sheets shall be GI with rubber capping to prevent seepage. Wherever necessary specials such as barge board, corner pieces apron piece, north light curve, ventilation curve, etc., shall be provided. Where natural lighting is required not less than 2% of the area shall be provided with translucent FRP sheets (1mm thick). WATER PROOFING OR WEATHER PROOFING. Type 1 Provide six course water proofing treatment using tar felt (type 3, gade1) and residual blown bitumen and provided with 50 mm thick hollow clay tiles set in cement mortar and joints sealed with bitumen compound grade A. Type 2 FACT ENGINEERING AND DESIGN ORGANISATION 12FT012/18 12ES001/18 QUALITY MANAGEMENT SYSTEM CIVIL & STRUCTURAL WORKS 12ES001/18 PAGE 9 OF 14 Water proofing treatment using admixtures like “ALGIPROOF” as per manufacturer’s specification and provided with 50mm thick hollow clay tiles and joints sealed with bitumen sealing compound. 10.0.0 10.1.0 10.1.1 10.1.2 10.2.0 10.2.1 10.2.2 10.2.3 10.3.0 10.3.1 10.4.0 10.4.1 11.0.0 11.1.0 11.2.0 11.3.0 11.4.0 DOORS / WINDOWS / VENTILATORS. This section covers the specification to be followed for various types of Doors, Windows and Ventilators. STEEL DOORS, WINDOWS AND VENTILATORS. This shall be made of standard section conforming to IS 1038 or hollow metal frames sections confirming to IS 4351. Necessary fixtures such as mortice lock for door closers etc shall be provided. For control rooms like MCC, control room, etc., minimum 2 doors shall be provided on opposite sides. ALUMINIUM DOORS, WINDOWS AND VENTILATORS. This shall be made of aluminum box or Z section confirming to relevant IS codes. The sections used shall be of approved brand and design. Necessary fixtures like mortice lock, handles, peg stays, floor spring, etc. shall be provided. For control rooms, MCC and operations area like pump house, compressor house, DG set room etc. glazing provided shall be of 5.5 mm thick wire glass. For air conditioned rooms air lock facility shall be provided if specified. ROLLING SHUTTERS. For storage god owns, ware houses and plants where equipment are to be taken, steel rolling shutters of required size confirming to IS 6248 shall be provided. WOODEN DOORS, WINDOWS AND VENTILATORS. The timber shall be used as specified. Only well-seasoned timber shall be used. The frames shall be of minimum 100 x 70mm. The shutters used shall be one of the followings. 1. Panelled shutters for doors with 100 x 35 mm frames, 18 mm panel and bottom rail with 150x35mm. There shall be a minimum of 5 panels per shutter. 2. Flush door shutter of block board core construction, 35 mm thick with teak veneered face. 3. For windows and ventilators the shutter shall be glazed with 70 x 80 mm frames and 4 mm thick plain or ground glass. When specified, necessary window bars / grills of approved design shall be provided. 4. For toilet PVC doors (PVC frames and shutter) of approved make or steel paneled shutter doors shall be used as specified. FLOORING AND FLOOR FINISHES. This section covers the specification to be followed for different flooring and floor finishes works. Type 1 150 mm thick macadam sub base, over which 150 mm thick PCC 1:3:6 mix finished with 20mm cement mortar 1:3. Type 2 150 mm thick macadam sub base over which 100 mm thick PCC 1:3:6 finished with 25 to 40 mm thick IPS. Type 3 150 mm thick macadam sub base and 100 mm thick RCC floor with reinforcement of 20 kg/m^3 and finished with 6 mm integral coat of cement mortar 1:3. Type 4 150 mm thick PCC 1:4:8 mix, finished with 20 mm thick plastering 1:3 and a floating coat. FACT ENGINEERING AND DESIGN ORGANISATION 12FT012/18 QUALITY MANAGEMENT SYSTEM 11.5.0 11.6.0 11.7.0 12.0.0 12.1.0 12.1.1 12.1.2 12.1.3 12.2.0 12.3.0 12.3.1 12.3.2 12.3.3 12.3.4 12.3.5 12.3.6 12.3.7 12.3.8 12.3.9 CIVIL & STRUCTURAL WORKS PAGE 10 OF 14 Type 5 100 mm thick PCC 1:4:8, finished with 20 mm thick. terrazzo tiles of approved design (minimum mosaic thickness 6 mm) set in cement mortar 1:5, 18 mm thick. Type 6 100 mm thick PCC 1:4:8 finished with 7 mm thick approved brand ceramic tiles set in cement mortar 1:3 and using cement grout and joints finished with tile mate or equivalent. Type 7 100 mm thick PCC 1:4:8 finished with 20 mm thick cement plaster in two coats mixed with red oxide at 3.5 kg/bag of cement and polished. FINISHING WORKS This section gives the specification to be followed fir various finishing works. PLASTERING Type 1 Plastering to brick masonry, minimum 12 mm thick, using cement mortar 1:4. Type 2 Two coats plastering to brick masonry works, minimum 20 mm thick and 3 mm second coat Type 3 Plastering to underside of RCC with cement mortar 1:3, 10 mm thick DADOING 7 mm thick ceramic tile dadoing over plastering for a height of 15 m from floor level using approved brand tile. PAINTING Type 1 Painting with two or more coats of water proof cement paint approved brand and shade over a coat of cement primer. Type 2 Two coat of plastic emulsion paint (medium quality) of approved brand and shade over a coat of primer. Type 3 Two coats of oil bound washable distemper of approved brand and shade over a coat of primer. Type 4 Two or more coats of white washing / color washing with quick lime mixed with strainer. Type 5 Two coats of Zinc chromate primer and two coats of approved quality and shade synthetic enamel paint for steel structure. Type 6 Two coats of Zinc chromate primer and two coats of approved quality and shade chemical resistant enamel paint for steel structures. Type 7 Two coats of Zinc chromate primer and two coats of approved quality and shade chlorinated rubber paint for steel structures including surface preparation by sand blasting / rubbing with emery paper. Type 8 Two coats of approved quality epoxy paint over two coats of primer as per the manufacturer’s specification for steel structure including surface preparation using sand blasting / rubbing with emery paper. Type 9 Two coats of approved quality wood primer and two coat approved quality and shade synthetic enamel paint for wood work including surface preparation. FACT ENGINEERING AND DESIGN ORGANISATION 12FT012/18 12ES001/18 QUALITY MANAGEMENT SYSTEM CIVIL & STRUCTURAL WORKS 12ES001/18 PAGE 11 OF 14 12.3.10 Type 10 Two coats of poly Urethane (clear) mat finish over primer coat as per manufacturer’s specification including surface preparation. 12.4.0 FALSE CEILING 12.4.1 Type 1 False ceiling using 4 mm thick plain AC sheets on steel frame work 12.4.2 Type 2 False ceiling using 4 mm thick plain AC sheet on Aluminum frame work 12.4.3 Type 3 False ceiling using 4 mm thick plain AC sheet on wooden frames 12.4.4 Type 4 False ceiling using 12 mm thick pre laminated phenol formaldehyde bonded particle board. 12.4.5 Type 5 False ceiling using enameled aluminium folded panels 5 mm thick using panel carries panel clips, suspenders etc, of approved make like ‘LUXALOL’ and approved shape. 13.0.0 13.1.0 13.2.0 13.3.0 13.4.0 13.5.0 14.0.0 14.1.0 14.1.1 14.1.2 14.1.3 14.1.4 PROTECTIVE LINING This section covers the specification for various types of protective linings used for different purposes. TYPE 1 40 mm thick acid/alkali resisting lining (class 2) over bitumen primer 10 mm mastic membrane, potassium base silicate cement molten base and joints filled with phenolic resin cement 20 mm depth. Type 2 40 mm thick acid/alkali resisting lining (class 2) over bitumen primer 10 mm mastic membrane, potassium base silicate cement molten base and joints filled with CNSL. Type 3 Epoxy lining 3 mm thick with hardener resin filled mix of approved make as per manufacturer’s specification Type 4 50 mm thick mastic lining over bitumen primer Type 5 Bitumen sand mix lining 25 mm to 50 mm thick using residual blown type bitumen and course sand WATER SUPPLY AND SANITARY WORKS. This section covers the general requirements regarding the design of water supply and sanitary works. WATER SUPPLY All external water lines shall be of HDPE class 4 quality with required fittings laid through trenches with earth cushion. All internal water lines shall be of PVC class 4 quality pipes. Wherever possible internal water lines shall be concealed The size of various pipes shall be designed taking n to account the water required, pressure at supply point, minimum residual pressure at a discharge of (0.35 kg/cm^2), height of building pressure drop due to various losses, etc. The C valve of the pipe may be taken as per supplier’s specification. Isolation valve, gun metal wheel valve, confirming to IS shall be provided for isolating the water mains at branching points and at different floor levels so that repair works can be attended by isolating such portion. FACT ENGINEERING AND DESIGN ORGANISATION 12FT012/18 QUALITY MANAGEMENT SYSTEM 14.1.5 14.1.6 14.2.0 14.2.1 14.2.2 14.2.3 14.2.4 14.2.5 14.2.6 14.2.7 14.2.8 14.2.9 14.2.10 14.2.11 14.2.12 14.2.13 14.2.14 14.2.15 14.2.16 14.2.17 14.2.18 14.2.19 15.0.0 15.1.0 15.1.1 15.1.2 15.1.3 15.1.4 CIVIL & STRUCTURAL WORKS PAGE 12 OF 14 When uninterrupted water supply is not available, overhead water tank (PVC) of required capacity (minimum 1000 liters) shall be provided. Provision of scour, over flow, etc. shall be provided. Where sufficient pressure is not available for water necessary sump tank with pumping arrangement shall be provided with overhead water tank. SEWAGE LINES All sewage lines outside the building shall be of glazed stone ware with a minimum diameter of 100 mm. Inspection chambers with RCC cover slabs shall be provided at all junctions. The outlets for closets and urinals shall be connected to inspection chambers located as close as possible to the building. Building outlets from water closet and urinals only shall be taken to the septic tank. Outlet from washbasins, sinks, bath rooms, etc. shall be connected to the drains through a chamber. When separate drainage scheme is provided all effluents can be connected to the same. All internal outlets of washbasin, closets, sinks, etc. shall be of PVC Class 1 minimum 75 mm. Necessary floor traps, gully traps (PVC shall be provided for all fittings like wash basin, urinal, toilet, bath room, etc.) Necessary ventilation pipe 75 mm dia. PVC with ventilating cowls and mosquito proof net shall be provided. External sewage lines shall be provided with manholes located not more than 30 m and at all junctions/change of directions. When the change of elevation is more than 1.5 m drop man holes shall be provided. Wherever necessary septic tanks of required capacity provided as per the relevant IS codes with provision for soak pit/dispersion trench. All toilet fittings required like water closet, urinals, wash basin, low level flush tank, etc., shall be of approved quality and make vitreous chinaware. Unless otherwise specified all fitting shall be of white colour. Necessary fittings such as pillar cock, stop cock, waste coupling of basin shower heads and connection pipes with nuts shall be of best quality chromium plated brass. Towel rails shall be of anodized aluminium. Wash basin shall be provided with 4 mm thick mirror (size 450 mm x 300 mm) with plywood backing. Soap trays of vitreous china ware to be provided for bath rooms. Urinals shall be of wall mounted front lipped urinal. Where urinal partitions are required it shall be of marble slab 25 mm. The finished floor level of toilet shall be kept 20 mm below the adjoining floor level by providing necessary sunken slabs. ROAD WORK This specification covers the requirement governing the design and specification for roads. All design shall be done based on the relevant Indian standard codes and high way manuals. ROAD DIMENSIONS Width of primary roads : as specified Width of secondary roads : as specified Inside edge turning radius for primary roads : 6500 mm Road camber a IBM road 1/30 to 1/48 FACT ENGINEERING AND DESIGN ORGANISATION 12FT012/18 12ES001/18 QUALITY MANAGEMENT SYSTEM 15.1.5 15.1.6 15.1.7 15.1.8 15.1.9 15.2.0 15.2.1 15.2.2 15.3.0 15.3.1 15.4.0 15.5.0 15.5.1 15.6.0 16.0.0 16.1.1 16.1.2 16.1.3 16.1.4 16.1.5 CIVIL & STRUCTURAL WORKS PAGE 13 OF 14 b Bituminous road 1/48 to 1/60 c Concrete road 1/70 to 1/80 Maximum drop of from centre to edge : 150mm Ruling gradient on plan ground : 1/30 Limiting gradient on plain ground : 1/20 In embankments RCC guards stone 250mm dia shall be provided on either side of the road at minimum spacing of 3 meters. Culverts shall be designed for IRC loading depending on the type of road. WATER BOUND MACADAMSUB BASE (SOILING) In filled up soil and black cotton soil WBM sub base shall be done using 90 mm to 40mm size stone for a thickness of 230 mm In cutting area where soil is loose WBM sub base shall be done using 90mm to 40mm size stone aggregate for a thickness of 150 mm. WBM sub base need not be provided where soil is ordinary rock/ hard laterite/hard rock. WATER BOUND MACADAM BASE COURSE (METALING) Provide and lay water bound macadam base course with stone aggregate 63mm to 40mm including sorting spreading to template and consolidating with road roller complete including spreading and consolidating blinding material 115 mm thick. WBM BASE COURSE (REMATALLING) Provide and lay WBM base course over scarified metalled surface with stone aggregate 50 mm to 20mm size, 75 mm thickness BITUMEN SURFACE FINISHING Bitumen concrete surfacing Provide and lay 50 mm thick bitumen concrete surfacing using stone aggregate 4.8 m³ (60% 25 mm nominal size ) per 100m² and course sand 40% 20mm nominal size per 100 m² and course sand 2.4 m³ per 100m² provided. With host S90/A90 or equivalent bitumen approved quality at 56 kg/m³ of stone aggregate and 128 kg/ m³ of sand over a tack coat of 0.75kg/m³ including finishing, etc. complete. CONCRETE SURFACE FINISH The reinforced cement concrete surfacing shall be done using M15 mix concrete, 150 mm thick. The concrete shall be reinforced using welded fabric if the width of the carriage way is more than 4.5 the concreting shall be done strip viz a longitudinal joints shall be provided in the centre. Along the length of the road joints shall be provided every 15 m. The joints shall be20mm wide and shall be filled with the pre moulded expansion joints strips. A levelling course of 80mmthick shall be provided below the reinforced slab using 1:4:8 concrete mixes. The surface of the road shall be rough finished. BUILDING AND STORM WATER DRAINAGE The rain water collected from the roof shall be connected to the storm water drainage system. Sufficient number of down water pipes shall be provided to drain out the water from the roof depending upon the roof area and intensity of rain fall. The minimum diameter of down water pipes shall be 100mm and shall be of PVC. Drains shall be laid under the building only in unavoidable circumstances. Where it is necessary to lay drain under a building, following conditions shall be satisfied A Pipe shall be of cast iron B The drain shall be laid in a straight line at a uniform gradient C Means of access in the form of materials shall be provided at each and immediately outside the building. FACT ENGINEERING AND DESIGN ORGANISATION 12FT012/18 12ES001/18 QUALITY MANAGEMENT SYSTEM CIVIL & STRUCTURAL WORKS 12ES001/18 PAGE 14 OF 14 16.1.6 All drain pipes shall be designed to discharge three times of the dry weather flow flowing half full with a minimum self-cleaning velocity of 0.75 m/second. 16.1.7 Storm water drains outside the building shall be rubble or brick with 15 mm thick cement plastering of 1:4 mix two coats for rubble masonry and 12 mm thick cement plastering of 1:4 mix two coats for brick masonry drains RCC drains of mix 1:2:4 can also adopted. 16.1.8 Effluent drains shall be suitably lined if required based on process requirement. 16.1.9 The minimum slope of drains shall be 1/300. Cover slabs with adequate thickness and reinforcement shall be provided at road crossing and at places specified to suit project requirement. 16.1.10 Reinforced cement concrete or cast iron pipe of suitable diameter with sufficient earth custom can also be provided depending on the conditions outside the building. 16.2.0 CABLE TRENCHES 16.2.1 Cable trenches shall be provided inside the plant building and outside the plant buildings to suit the Electrical requirements. 16.2.2 The cable trenches are usually constructed either in brick masonry or reinforced cement concrete depending on the size of cable trenches and space availability. For brick masonry cable trenches the bed slab shall be of cement concrete 1:3:6 mix 150mm thick. 16.2.3 For fixing cable racks in cable trenches 150 x 150 x 8 mm thick MS insert plate shall be provided in the side wall of RCC cable trenches in brick masonry cable trenches the insert shall be provided by giving by giving 200 x 200 mm size 16.2.4 Reinforced cement concrete cover slabs or chequered plate of suitable size and thickness shall be provided as specified. 16.2.5 A bed slope of 1/400 provided 17.00 17.1.0 17.2.0 17.3.0 17.4.0 17.5.0 17.6.0 17.7.0 17.8.0 LIQUID RETAINING STRUCTURES This section covers the requirements governing the specifications to be followed for design and construction of liquid retaining structures Design be conforming to IS 3370 Part I to IV (latest) M20 grade concrete with minimum cement concrete of 363 kg/m³ or 1:1 ½:3 nominal mixes shall be used. for tanks resisting on grounds 1:3:6 mix levelling course shall be provided. The provisions regarding expansion joints, construction joints bitumen painting above levelling course etc. shall be made as per code. PVC water bars 230 mm wide shall be used where ever necessary. All embedded parts such as nozzles, pipes, bolts, etc shall be provided at the time of concreting. Plastering with cement mortar 1:4, 10 mm thick mixed with admixtures like impermo, acco proof, etc shall be provided for inside hydro test only. All leaks or wetting noticed during hydro test shall be rectified as per approved methods, using approved materials. FACT ENGINEERING AND DESIGN ORGANISATION 12FT012/18 NOTES:- 32644-13-PS-001 TECHNICAL SPECIFICATION FOR ELECTRICAL INSTALLATION PAGE 1 OF 1 TPS NO. 32644 - 13 - PS - 001 STATUS ENQUIRY ORIGINATING DEPT. R0 COMMITMENT ELECTRICAL P.O / W.O NO. PROJECT Construction of Phosphoric Acid storage tank at Q10 berth W. Island LOCATION WILLINGTON ISLAND CLIENT M/s.FACT-CD PURCHASER M/s.FACT-CD VENDOR 00FT004 / 14 ITEM: SUPPLY AND INSTALLATION OF ELECTRICS 0 06-06-2020 Original issue SM IK IK REV. DATE DESCRIPTION PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION CONTENTS TECHNICAL SPECIFICATION FOR ELECTRICAL INSTALLATION ELECTRICAL DEPARTMENT S.No. 00FT011 / 14 1.0 Doc. No. 32644-13-PS-001 Page 1 of 2 No. of Pages Description Rev. No. with Issue 1 2 3 TECHNICAL DOCUMENTS 1 32644-13-PS-001 SIW Schedule of work- supply and installation of electrics 1 1 2 32644-13-PS-001 SW Scope of work & special requirements 4 0 3 32644-13-PS-001 SPL Specification for erection, testing & commissioning 10 - 4 32644-13-PS-001-INS Scope of Inspection and Tests 4 0 5 00ES001/01 Vendor Data Submission Procedure 3 - 6 32644-13-PS-001-VDI Vendor Data Index 1 7 32644-13-TS-001VDR ELEC Vendor Data Requirements 4 0 8 13ES900/14 Engg Specification – General Requirements for Electrics 4 - 9 32644-13-DA-90001 Data sheet – General Requirements for Electrics 1 0 10 13ES924/14 Engg Specification-Electric for Turnkey Installation 10 - 11 32644-13-DA-924-01 Data Sheet- Turnkey installation 5 0 12 32644-13-TP-924-01 Technical particularsinstallation Electric 6 0 13 13ES906/14 Engg Specification Switchboards – 16 - 14 13ES 930/14 Engineering Specification-Cables 2 - 15. 13ES 911/14 Engg. Specification-Push button station 3 16. 13ES910/14 Engg. Specification-Medium Voltage Induction Motor 6 - 17 13ES914/14 Engg specification for fabrication of cable trays and structural steel 2 0 18 13ES915/14 Engg. Specification – Cabling Installation 4 - 19 13ES916/14 Engg. Specification – Earthing 4 - 20 13ES927/14 Engg. Specification-Lighting Installation 6 - 21 32644-13-PS-001 SV Sub Vendor List 2 0 22 32644-13-PS-001 CS Compliance Statement 1 - 0 06.06.20 REV. DATE ORIGINAL ISSUE DESCRIPTION for Turnkey Medium Voltage SM IK IK PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION 4 ELECTRICAL DEPARTMENT CONTENTS TECHNICAL SPECIFICATION FOR ELECTRICAL INSTALLATION 32644-13-PS-001 Page 2 of 2 2.0 Drawings 1 32644-13-SD-00101 Single Line Diagram of Power Distribution(typical) 1 1 2 32644-13-PL-00501 Overall Power Layout (typical) 1 1 3 32644-13-GE-00251 Typical arrangement of cable riser 1 0 4 32644-13-GE-00252 Typical arrangement of over head cable tray 1 0 5 32644-13-GE-00253 Typical arrangement of earthing junction plate 1 0 6 32644-13-GE-00254 Typical details of buried cables 1 0 7 32644-13-GE-00255 Typical details of cable trench section 1 0 8 32644-13-GE-00256 Earthing connection details(typical) 2 0 9 32644-13-GE-00257 Arrangement of canopies for outdoor devices (Typical) 2 0 10 32644-13-GE-00258 Typical arrangement of copper bonded electrode earth pit 1 0 FACT ENGINEERING AND DESIGN ORGANISATION SCHEDULE OF ITEMS OF WORK ELECTRICAL DEPARTMENT 32644‐13‐PS‐001SIW R0 TECHNICAL SPECIFICATION FOR ELECTRICAL INSTALLATION SL No DESCRIPTION OF ITEM AMOUNT QTY UNIT Rate (₹) 1.0.0 415V,35MVA.TPN, Motor Control Centre(MCC) 2 415V, 4Way 3phase Lighting Distribution board in cast aluminum enclosure, light fittings including all accessories and welding socket outlets 1 LS 1 LS 1 LS 1 LS 4 Local Control Stations for ON/OFF control of MV motors in , weather proof, cast Aluminium enclosure with canopies . Cables and Cabling 5 Earthing and lightning protection 6 GRP/FRP cable trays and structural steel items Excavation and back filling for cable trenches and supply of brick and sand for cable laying purposes. 1 LS 1 LS Miscellaneous items like GI pipes, insulation mats , danger notice plates, resuciation charts cable router marker testing of motors,cutting of roads, concrete, etc 1 LS 7 8 Total Amount(₹) 1 LS NOT TO BE FILLED IN HERE‐‐ ‐‐PRICES TOTAL Say 0 06.06.20 SREENATH.M-DM(Elec) REV DATE PREPARED Page 1 of 1 IGST (₹) ELECTRICAL Supply, Erection, Testing, Commissioning and Handing over of following electrical equipment as per scope of work detailed below. 1 3 Amount (₹) INDULEKHA.K-DGM(Elec) CHECKED INDULEKHA.K-DGM(Elec) APPROVED FACT ENGINEERING AND DESIGN ORGANISATION FACT ENGINEERING AND DESIGN ORGANISATION ELECTRICAL SCOPE OF WORK & SPECIAL REQUIREMENTS 32644-13-PS-001SW R0 Page 1 of 4 DEPARTMENT 1.0 INTRODUCTION 1.1 M/s.Fertilizers and Chemicals Travancore Ltd (FACT) a Govt. of India Undertaking is planning for constructing two numbers of Phosphoric acid tanks and associated facilities at Q10 berth area Willington Island.This requisition is issued for the supply and installation of electrics envisaged for above work 2.0 SCOPE OF WORK 2.1 The scope of work of this requisition covers the design, and detailed engineering, procurement, manufacturing, testing at works, supply, dispatch, storage, handling erection, testing and commissioning of all electrics required for the package, fully conforming to standards and specifications. Scope of work shall also cover preparation and submission of documents and handing over of the installation as per enclosed details, specifications, data sheets, schedule of items of work, drawings, etc. Power supply at 415V,250A,TPN,50Hz will be made available by the client at the existing MCC/ MV Switch board located in the substation building. Further distribution of power supply shall be carried out by the contractor. Cables shall be laid though over head GRP cable trays inside substation building. Cables shall be laid through GRP cable trays wherever pipe supports,building walls etc are available. Cables shall be laid through buried cable trenches wherever pipe bridges are not available. Cables to drive motors shall be taken through GI conduits in paved area.RCC hume pipes shall be used for laying cables at road crossings.MV switch board/MCC under the scope of contactor shall be located in the Heavy equipment workshop.Drive motors for acid transfer pumps and sump pump,feeders for lighting and two numbers of welding socket outlets for tank area etc. shall be fed from above switch board.ON,OFF and trip indications of pumps shall be made available at the existing control room. Bidder shall furnish Load list, single line diagram of power distribution, cable schedule, cable sizing calculations, power layout, earthing layout and lighting layout drawings etc for the approval of consultant/client. All the drawings shall be submitted to Owner/ Consultant for approval. However, approval of the drawing shall not relieve the LSTK contractor from its responsibility of delivering the project as per tender terms & conditions. Weather proof and acid resistant well glass LED type light fittings shall be provided for the stairs and hand rails of tanks.WP and acid resistant type LED flood lights shall be provided on the top of the tanks for illuminating area around dyke wall and roads. Two numbers of copper bonded type earth electrodes shall be provided near heavy equipment workshop for earthing MV switch board and lighting distribution boards.Local Control stations ,drive motors ,Junction boxes etc shall be earthed in duplicate and shall be connected to earthing system . All steel structures, tanks, vessels, pipes, pipe joints, valves etc. shall be earthed against static charge accumulation .Separate earth pits shall be provided for tanks.Earth pits shall be interconnected and shall be connected to nearest existing earth pits using 150 sq.mm PVC covered Aluminium conductor cable. Hoods (using aluminium sheet) shall be provided for drive motors and local control station located in outdoor area as per the drawing enclosed with the tender documents. 2.2 The Electrics include the following but not limited to the following 0 2-6-‘20 ORIGINAL ISSUE SM IK IK REV DATE DESCRIPTION PRPD CHKD APPRD FACT ENGINEERING AND DESIGN ORGANISATION ELECTRICAL SCOPE OF WORK & SPECIAL REQUIREMENTS DEPARTMENT 32644-13-PS-001SW R0 Page 2 of 4 Supply and installation of MV switch boards/MCC. Testing and commissioning of MV motors Supply and installation of Local control stations (push button stations), welding receptacles etc. Supply and installation of 650/1100V,XLPE insulated,PVC sheathed armoured,FRLS aluminium & 650/1100V,XLPE insulated PVC sheathed armoured FRLS copper cables , Earthing and lightning protection Lighting including supply and installation of lighting fixtures, DBs etc. Supply and installation of GRP cable trays and steel structural supports Miscellaneous civil works Supply and installation of miscellaneous items Providing service personnel Preparation of detailed drawings and documents for approval Furnishing vendor drawings for approvals for supply items Preparation of drawings Site test reports Rendering necessary assistance and preparation of documents for statutory approval covering all Electrical installation 2.3 Installation work is inclusive of supply of erection materials, hardware, consumables and sundry items required for the installation. It is the responsibility of the bidder to supply and install all items, that are incidental and necessary for the completion of the installation, whether specifically mentioned or not, so that the installation complies with the standards and regulations specified. 2.4 Associated civil and structural works such as chipping, plastering, grouting, minor brick and concrete works, excavations, fabrication, painting and any other work necessary for completion of the installation shall be included in the scope of work. Separate charges shall not be applicable for the above unless otherwise indicated in Schedule of items of Work. 2.5 The bidder shall furnish all labour (supervisory, skilled, unskilled and administrative), transport vehicles, generator sets, welding machines, gas cutters, erection tools and tackles, cleaners, crimping devices, blow lamp, handling equipment, testing equipment, etc, and any other such equipment necessary for installation, testing and commissioning, at no extra cost to the purchaser. 2.6 It is the responsibility of the bidder to pay wages and salaries to the persons employed and ensure that all labour rules and acts are complied with. Contributions, fees, etc. necessary in this regard shall be paid and the bidder shall maintain all necessary records. 2.7 All consumable materials such as insulation tape, cleaning and paint brushes, welding electrodes, rust preventive materials, jute, cotton waste, hacksaw blades, bolts, nuts, corrosion inhibitive grease, fuel, lubricants, etc and any other material required for carrying out the work shall be included in the scope of the bidder. 2.8 Work shall be started and carried out in accordance with the terms and conditions, approved drawings, specifications and requirements as set forth in this document and instructions of the purchaser or his authorised representative from time to time. 2.9 Where supply of materials are involved, the scope shall include design, manufacture, assembly, testing, and inspection at works, packing and delivery at site. 2.10 Testing and commissioning works include calibration, all pre-commissioning tests, checking of all wiring and connections for power, control, metering, protection, alarm, annunciation, lighting, and earthing. Testing and commissioning of all the equipment covered in this contract shall be carried out as per relevant standards or as directed by the purchaser. 2.11 Bidder shall carry out clearing of all construction waste materials and loose earth, which might FACT ENGINEERING AND DESIGN ORGANISATION ELECTRICAL SCOPE OF WORK & SPECIAL REQUIREMENTS DEPARTMENT 32644-13-PS-001SW R0 Page 3 of 4 have collected in and near the work site consequent to execution of the work under this contract. Also all temporary structures erected by the bidder shall be removed. 3.0 STATUTORY APPROVAL 3.1 It shall be the responsibility of the bidder to ensure that complete installation supplied and/or erected by him fully meets with the relevant standards, Acts, Rules, Regulations, etc applicable. Also it shall be the responsibility of the bidder to obtain approval of statutory authorities like Electrical Inspectorate. 3.2 Preparation of any additional drawings/documents required for obtaining statutory approvals including those of Electrical Inspectorate, Central Electrical Authorities(CEA,Chennai), etc other than what is supplied along with this specification shall be included in the scope of the bidder. Any major deviation in the power distribution scheme envisaged for the project, which may not be acceptable for the statutory bodies, shall be pointed out in the offer submitted. 3.3 Any modification/rectification required by the Purchaser/ Electrical Inspectorate resulting from the improper installation by the bidder or to make the same in full conformity with the relevant standards, Acts, Rules, Regulations, etc applicable for the installation shall be carried out by the bidder, without any extra cost to the Purchaser. 4.0 DRAWINGS AND DETAILS ENCLOSED WITH THE TENDER 4.1 The drawings enclosed are only typical for the guidance of the bidder to formulate the bid and to furnish his rates and prices 4.2 Preparation, completion and handing over the documents and updating the drawings to "AS BUILT" status as per requirement and direction of purchaser/Engineer-In-Charge shall be included in the scope of bidder 4.3 All the available data have been furnished in this requisition. If any other required, the bidder shall obtain the same from purchaser data is additionally 5.0 CONSTRUCTION POWER 5.1 The bidder shall make their own arrangement for construction power, unless otherwise stated elsewhere. 6.0 CONTRACTOR'S LICENSE 6.1 The bidder shall possess a valid and competent Electrical Contractor License (class A)issued by the State Electricity Licensing Board for carrying out electrical installation works in the State where project site is situated. 6.2 True copies of the relevant pages of the Electrical Contractor License possessed by the Bidder shall be furnished along with the technical offer for substantiating the validity and scope of the license. 6.3 The license shall be produced for verification on request by the purchaser. 6.4 All wiremen, electricians, and supervisors engaged by the bidder for the above work shall possess necessary valid license issued by State Electricity Licensing Board. These shall be made available for scrutiny of the Purchaser. 7.0 SPECIAL NOTES 7.1 All exposed MS parts included in the supply scope of the bidder shall be painted with two coats of epoxy based paint over suitable primer at no extra cost to the purchaser. The scope of work shall include painting feeder names, equipment numbers, circuit numbers, etc., with suitable sized characters as directed by the Site-In-Charge on equipment, 7.2 FACT ENGINEERING AND DESIGN ORGANISATION ELECTRICAL SCOPE OF WORK & SPECIAL REQUIREMENTS Page 4 of 4 DEPARTMENT devices associated with this work at no extra cost. shall be supplied free of cost by the bidder. 7.3 32644-13-PS-001SW R0 All materials required for the above All mounting hardwares and external hardwares of electrical item shall be of stainless steel considering installation in corrosive/saline atmospere near sea shore. FACT ENGINEERING AND DESIGN ORGANISATION ELECTRICAL DEPARTMENT SPECIFICATION FOR ERECTION TESTING AND COMMISSIONING 32644-13-PS-001SPL Page 1 of 10 1.0 SCOPE 1.1 This specification covers the engineering requirements for erection/installation, testing and commissioning of electrical equipments/items and its associated works. 2.0 3.0 STANDARDS Erection, testing and commissioning of the equipment covered shall be done as per standard codes of practice and shall comply with requirements of following Indian standards and other relevant standards. Indian Electricity Rules and acts and also to the regulations that are in force at the place of installation. IS:335 : Specification of new insulating oil IS :900 : Code of practice for installation and maintenance of induction motors IS: 1255: Code of practice for installation and maintenance of power cables up to and including 33KV rating IS: 1866: Code of practice for maintenance and supervision of mineral insulating oil In equipment. IS: 5216 : Guide for safety procedures and practices in Electrical work IS: 6792: Method for determination of electric strength of insulating oil. IS: 9124: Code for maintenance and field testing of electrical relays. IS:10028: Code of practice for selection ,installation and maintenance of Transformers-part-2 installation IS:10118:Code of practice for selection ,installation and maintenance for switch gear And control gear-part-3 installation. IS: 13408: Code of practice for the selection, installation and maintenance of Electrical apparatus for use in potentially explosive atmospheres (other than mining application of explosives Processing and manufacture). REFERENCES 3.1 Following documents shall be read in conjunction with this specification: - Scope of work and special requirements - Engineering specification and Data Sheets of General Requirements of Electrics. - Engineering specification and Data Sheets of Cabling and earthing installation, installation of outdoor switchyard equipments. - Engineering specification of Lighting Installation and fabrication of cable trays and structural steel. - Drawing and other documents enclosed with the specification. 4.0 00F121A/14 4.1 GENERAL The erection/installation testing and commissioning shall be carried out in accordance with specifications ,data sheets, drawings, manufacturer’s recommendations, relevant standards or as directed by Owner/Engineer-in-Charge. Requirements regarding erection/installation, testing and commissioning of switch boards, transformers, motors, 0 06.06.2020 REV. DATE ORIGINAL ISSUE DESCRIPTION SM IK PRPD. FACT ENGINEERING DESIGN ORGANISATION IK CHKD. APPRD. ELECTRICAL DEPARTMENT SPECIFICATION FOR ERECTION TESTING AND COMMISSIONING 32644-13-PS-001SPL Page 2 of 10 13F121A/14 push button stations, battery and battery charger etc. are generally explained herein. It is the responsibility of the contractor to supply all equipments, items, accessories, materials, tools, tackles, transporting and lifting vehicles, consumables etc. required for unpacking, checking, transportation, storage, safe custody, installation, erection, testing, commissioning, return of unused equipment/items which are supplied from owner’s stores and handing over of the electrics to the entire satisfaction of the owner. 4.2 The erection scope shall include supply of all hardwares and accessories such as bolts, nuts, washers, gaskets, cable termination accessories, lugs, paint, primer, sand etc. required for completeness of the work. All consumable materials such as insulation tape, cleaning and paint brushes, welding electrodes, rust preventive materials, jute, cotton waste, hack saw blades, bolts, nuts, inhibitive grease, fuel, lubricants, etc. and any other material required in carrying out the work but not for incorporation in to the permanent work, shall also be included in the scope of contractor. 4.3 The equipment/items erected shall be handled with care by experienced riggers under the guidance of a competent supervisor. Proper handling and transporting equipments are to be used and dragging is to be avoided. 4.4 The equipment/items supplied by the Owner shall normally be kept at their stores. The contractor shall inspect these items at the stores by unpacking the containers, if necessary. Damages and short supplied items, if any found shall be reported to the Owners representative in writing prior to taking delivery. The responsibility of safe custody of these items after taking delivery and till handing over shall rest with the contractor. Unused materials and containers shall be returned to the stores. 4.5 The items supplied by the Owner shall be transported from the point of storage to the point of erection/installation using proper capacity transporting vehicles. The scope shall include unpacking the containers, assembling parts, fixing loose items, components, etc. 4.6 Materials supplied by the contractor or issued by the Owner shall be given suitable protection against weather, dust and vermin. In storage places, equipments shall be placed over wooden sleepers to keep them above ground. 4.7 Before carrying out erection/installation works of any item, proper care regarding levelling, alignment, access to working parts, facilities for removing the items for repair, statutory clearance, etc. shall be taken. 4.8 Foundation bolts, nuts, lock nuts, washers, etc. will normally be supplied by the equipment supplier. Any further requirement of these items shall be under the scope of contractor. The equipment shall be installed on the foundation bolts firmly such that there will not be any vibration during operations. 4.9 The push button stations, power junction boxes, switches, isolators, etc. if any, shall be mounted at convenient places like walls, columns, pedestals, cable rack supports, etc. Pedestals where ever required shall be fabricated from the steel sections used for fabrication of cable supports, racks, etc. and installed. 4.10 For mounting of equipment/items on the walls/columns/ supports, suitable MS/GI brackets shall be fixed/ grouted. 4.11 Electrical connections shall be done with great care using spring washers, bimetallic strips, conducting grease , etc. wherever required to ensure good contact without creating undue stresses. Copper busbar joints shall be made after tinning the contact FACT ENGINEERING AND DESIGN ORGANISATION ELECTRICAL DEPARTMENT SPECIFICATION FOR ERECTION TESTING AND COMMISSIONING 32644-13-PS-001SPL Page 3 of 10 13F121A/14 area. Supply of all required accessories or electrical connections shall be included in the contractor’s scope. 4.12 Discrepancies if any found between drawings/statutory requirements and actual conditions at the site, shall be immediately brought to the attention of owners representative. 4.13 If any modification is found required in the wiring or to suit site condition the same shall be carried out as per the instruction of the Engineer-in-Charge without any extra cost. 4.14 All equipments under erection shall be kept properly cleaned and free of dust, vermin, moisture, etc. 4.15 After erection it shall be ensured that no foreign materials, tools or tackles are left in the equipment. All unused cable entries, cutouts, etc. shall be sealed properly. For hazardous area blanking plugs suitable for the area classification applicable shall be used. 4.16 All tests shall be carried out in the presence of Owner’s representative and test shall be recorded on an approved proforma duly certified. The records of all tests shall be submitted to the purchaser’s representatives. 4.17 All interconnected wiring shall be checked thoroughly for correct connection with the wiring, and schematic drawings of the manufacturer and the drawings supplied by owner before energising. 4.18 All power and busbar connection shall also be thoroughly inspected and checked for connections, foreign materials, tightness, etc. before energising the equipments. 4.19 All components within the main equipment shall be tested for proper performance and correct operation before commissioning the equipment. 4.20 All labelling shall be checked for correctness. 4.21 All nuts, bolts, clamps, joints, connections, etc. shall be checked for tightness and tightened wherever required. 4.22 All moving parts shall be checked for its correct movement and proper lubrication. Apply lubrication wherever required. 4.23 All equipment containing liquid shall be checked for correct quantity filling and all gaskets, walls, etc. shall be checked for leak proofness. Oil filling, if found required, shall be done dry and clean oil. Gaskets shall be replaced if found required. The condition of the oil shall be tested in accordance with I.S. 335. 4.24 It shall be ensured that all CT leads are loaded or shorted prior to testing and commissioning. 4.25 Insulation tests shall be carried on all electrical devices, whether specifically mentioned or not, as per this work after properly cleaning these devices. 4.26 All the relays and its settings after commissioning shall be furnished to owner detailing relay type no., panel no. etc. 4.27 In case of any component of an equipment supplied by the owner is found to faulty/unsuitable, the same shall be replaced by the new one issued by owner. 4.28 Parts of relays blocked for transportation should be released manufacturer’s instruction. FACT ENGINEERING AND DESIGN ORGANISATION according to 13F121A/14 ELECTRICAL DEPARTMENT SPECIFICATION FOR ERECTION TESTING AND COMMISSIONING 32644-13-PS-001SPL Page 4 of 10 4.29 All relays, before installation, the rating, range and auxiliary supply voltages for the relay should be checked against drawings/schematic/schedule. 4.30 Relays shall be checked and tested for insulation, pickup value, dropout value, timing, polarity, directional unit sensitivity, stray torque check, slop characteristic, etc. 4.31 Local control stations, Distribution Boards (DBs), welding receptacles, etc. shall be mounted at a height of 1.5M from operational floor, on pedestals/walls/structures etc. by grouting/fixing suitable frames. 4.32 Polarisation test shall be conducted, wherever specified. The polarisation index is the ratio of the 10 minutes resistance value to the 1 minute resistance value. 5.0 CIVIL AND STRUCTURAL WORKS 5.1 Miscellaneous civil works associated with the erection/ installation work such as excavation, dewatering and refilling of earth work for earth pits and cable trench, chipping, grouting, small cutting, etc on floors/walls/columns/structures and bringing back the same to original finish, grouting of supports, providing suitable fixing arrangements for cables, push button stations, DBs etc shall be included in the rates quoted for erection of the respective items, unless specifically excluded in the ‘Schedule of Items of Work’. 5.2 All structural works associated with cabling, earthing, lighting, equipment erection and supporting arrangements shall be included in the scope of the contractor. All the welding and cutting works shall be carried out by certified welders. 5.3 Painting shall be done on all MS materials provided by the contractor such as base channels, frames, supports, pedestals, cable trays/racks/risers, enclosures, boxes, conduits, chequered plates, etc. Before painting the surface should be thoroughly scrapped and cleaned to remove dust, grease, plaster or any other foreign materials. It is the responsibility of the contractor to supply and install all the required materials for painting including paint. 5.4 Cement concrete footing shall be provided for push button stations, cable trays/racks/risers, pedestals, supports, etc. Footing shall be provided using 1:2:4 PCC with 20mm broken stone. It is the responsibility of the contractor to supply and install all materials such as cement, river sand, reinforcement rods, 20 mm broken stone, etc without any extra cost to owner. 5.5 All concrete works and grouting shall be cured for a minimum period of 48 hours. 5.6 Necessary MS plate inserts will generally be provided by the purchaser on walls, concrete slabs, beams columns, etc. Any additional requirement of MS plate inserts, as required by Owner, on walls, concrete slabs, beams, columns, etc shall be under the scope of the contractor. The inserts shall be provided by using MS plates properly hooking using MS rods of sufficient diameter and welding this to the reinforcement rods of concrete slabs, beams, columns, etc., as the case may be. 5.7 Chipping, grouting, etc., as recommended shall be done for completion and installation work on the finished floor, wall, roof, etc. It is the responsibility of the contractor to supply all necessary materials and to bring the disturbed surface to the original finish. 5.8 Touch up painting of scratches found on equipment, other painted metallic surfaces, galvanised structures, etc associated with this work is also included in the scope of the contractor without any extra charge for same. Base steel structures shall FACT ENGINEERING AND DESIGN ORGANISATION ELECTRICAL DEPARTMENT SPECIFICATION FOR ERECTION TESTING AND COMMISSIONING 32644-13-PS-001SPL Page 5 of 10 13F121A/14 be painted with 2 coats of epoxy primer and 2 coats of epoxy paint. 6.0 TRANSFORMERS 6.1 While taking delivery, transformers shall be examined for any sign of damage in transit. Also ensure that all nuts/clamps are tightened properly. Transformers shall be handled carefully. Transportation shall be done either by truck or trailer of sufficient capacity. 6.2 The transformers installation shall be carried out in accordance with IS:10028. Transformer foundation/plinths will be constructed by purchaser/owner. Loose items supplied along with the transformer shall be fixed in position as per manufacturer’s drawings/documents/instruction manuals. 6.3 The transformer shall be transported or erected only with suitable capacity vehicles/equipments. While lifting a transformer, ensure proper balance and that lifting change does not interfere with any part of the transformers. 6.4 The transformer shall never be placed directly on the ground nor left without putting in wheel stoppers. 6.5 The transformer shall be installed on the channels/plates/racks grouted to the floor. 6.6 The transformer shall be levelled, aligned and checked for free movement on the wheels and stoppers shall be fixed to stop further free movement. 6.7 Verify whether all accessories supplied loosely are fitted up as per manufacturer’s recommendations. Fix up loosely supplied CTs, if any as part of REF protection, Earth leakage, etc. while fixing the cooling tubes, ensure that these tubes are flushed with hot oil. 6.8 Whenever blanking plates are removed to fix detached parts such as bushing, components, etc. a new gasket shall be used while fixing the same. 6.9 When the oil is despatched to site separately, it is usually in sealed drums. At the time of filling the oil, it shall be ensured that the oil is filtered, clean and dry. The oil used for filling or topping up shall comply with IS:335. 6.10 The condition of oil should be checked before use. Samples of oil from the transformers should be taken from the bottom of the tank. When samples are taken from drum, they should be taken from the bottom after the oil has been allowed to settle at least for 24 hours. 6.11 Test the oil contained in the transformer and extra oil supplied for topping up for dielectric strength and acidity as described in IS:335 and IS:6792. 6.12 Top of the transformer without the oil getting contaminated with dust and moisture. Oil filling shall be done through the bottom drain valve with all air vents opened to prevent formation of air pockets. The oil shall be filled through a stream line oil filter using flexible metallic hoses. Flow of oil shall be reduced towards the final stage to prevent internal pressure build up. After completion of oil filling, sufficient time shall be allowed for the oil to spread all over and air bubbles to escape. 6.13 Ensure the electrical and earth connection are proper, Whenever gasketted flanges are provided earth connection between flanges shall be provided to by pass fault current flow. 6.14 Ensure that the valves in the oil path are open and drain valves are closed. 6.15 Ensure that Buchholz, temperature and level protections are operative and FACT ENGINEERING AND DESIGN ORGANISATION ELECTRICAL DEPARTMENT SPECIFICATION FOR ERECTION TESTING AND COMMISSIONING 32644-13-PS-001SPL Page 6 of 10 13F121A/14 settings are proper. 6.16 Measure IR values of Transformer windings and control circuits using suitable Megger. 6.17 Identify the vector group of transformer, if necessary. 6.18 Conduct polarity test, insulations test, dielectric test, volume resistivity, acidity and water content test, ratio tests on all tap positions, load tests, magnetic balance test, etc. 6.19 Measure polarisation index for transformers. 6.20 Conduct simulation test on Buchholz, temperature, oil level trip/alarm circuits. 6.21 Verify calibration of temperature and oil level indicators. 6.22 Complete details regarding the preparation of the transformer before initial charging shall be supplied by the transformer manufacturer and design has to be strictly followed by contractor. Transformer rated above 1MVA, when energised for the first time the voltage should be built up gradually. 6.23 After energisation of the transformer, the following observation shall be made/recorded for 24 hours on hour basis at no extra cost. 1. Current and voltage for each phase. 2. Over heating of any part of transformer 3. Abnormal noise or humming 4. Events of alarm and trip 5. No load and magnetising in rush current 6.24 If the transformer oil is found to have poor dielectric strength, the oil shall be dried out as described in IS 10028. Normally the streamline filter shall be used for drying up. The curve, Insulation Resistance and Temperature vs Time shall be furnished. Before drying out check any oil leakage through bushings and radiators, transformer tank is connected to earth temperature indicators are suitably calibrated, capillary tube connection made to respective temperature indicators, etc. The dielectric strength of oil should be tested using a standard oil test kit. The oil should withstand at least 40 KV for one minute with the spear gap of 4mm as per IS:335. If the dielectric strength is less than that specified above, oil should be cleaned, heated, filtered and reconditioned properly till the above result is archived. Charges for filtering specified “schedule of items of work” shall included charges for filtering unit provided by contractor at site. 7.0 SWITCHBOARDS 7.1 The details of switch boards such as, appropriate overall dimension and weight etc. are specified in the “Schedule of items of work”. 7.2 For convenience of packing and transportation, switch boards are sent from manufacturer’s works in convenient shipping sections. Breakable items like meters, relays etc. are sent separately. The contractor shall list out the items received and listing out any damaged or short supplied items and furnish the same to owner/Engineer-in-charge. 7.3 Grouting pockets are generally provided on the respective floors by owner. The channels/bolts shall be rigidly grouted on the pockets of floor by contractor. Necessary chipping, grouting, filling, painting etc. shall also be done by the contractor. Where grouting pockets are not provided by the owner required pockets shall be made by FACT ENGINEERING AND DESIGN ORGANISATION ELECTRICAL DEPARTMENT SPECIFICATION FOR ERECTION TESTING AND COMMISSIONING 32644-13-PS-001SPL Page 7 of 10 13F121A/14 contractor by chipping the floor at no extra cost. 7.4 The switch boards shall be installed on the foundation firmly such that there is no vibration during tripping or closing of breaker/isolating devices. Interconnect the terminals of cubicles/shipping section. Cable glands holes shall be drilled if required. Blocking of moving parts provided for transportation shall be removed. 7.5 Great care shall be taken to ensure that the equipment has been installed correctly and levelled properly before the holding down bolts are grouted to, thereby ensuring correct operation of isolation mechanisms and jointing together the bus bars of the various shipping sections. 7.6 The base channel required for mounting the panels shall be levelled and grouted to the floor by chipping the floor to make a proper bonding surface, if required. 7.7 The switch boards shall be placed on the base channel, assembled, aligned and levelled, so that bus bar jointing, breaker operation, inter-panel bolting, etc., can be carried out freely. The fixing /grouting of the bolt shall be carried out only after alignment and levelling. The foundation bolts shall be either grouted in the pocket holes or tightened to the groove provided on the base channels as per manufactuer’s recommendations. 7.8 Fix all loosely supplied components. Plug cut outs/opening in panels and seal off all gaps by way of vermin proofing. All joints and connections shall be tightened. 7.9 All moving parts where required shall be lubricated. Petroleum jelly shall be applied to all electrical contact surface at connection. 7.10 On no account should a power operated mechanism be operated by power until operation by hand has proved it completely satisfactory. 7.11 While making connection to terminals, care should be taken to avoid undue strain on insulators, bushings, etc. Joints and connections shall be checked for tightness and tightening, if required. During connection, check should be made to ensure that the ratings of current transformers and ratings of meters and relays should match. If required necessary multiplying factor shall be stenciled on meters and adjustment of setting made on the core of instrument transformers. 7.12 Verify name plates, wiring and components with drawings/bill of materials. Discrepancies if any noticed shall be brought to the attention of the Engineer-InCharge. 7.13 Check breaker operation mechanism for proper operation. Circuit breaker mechanism should be checked against manufactures drawing to ensure that the setting at works have not been distorted during transportation. 7.14 Internal cleaning of all panels and chambers of switch board thoroughly with the help of vacuum cleaners and blowers. 7.15 Continuity of wiring, phase sequence and polarity of CTs and PTs shall be checked and verified. 7.16 Wiring shall be checked thoroughly and done, if required, for correct connection with wiring/schematic drawings of manufacturer/purchaser. Minor modifications, if any, required in feeder wiring, providing shorting wires for unused remote stop/interlock terminals etc. as per individual feeder interconnection wiring diagrams shall be done, at no extra cost. FACT ENGINEERING AND DESIGN ORGANISATION ELECTRICAL DEPARTMENT SPECIFICATION FOR ERECTION TESTING AND COMMISSIONING Page 8 of 10 7.17 All components including relays shall be tested for proper performance and correct operation. 7.18 Test continuity, insulation, primary and secondary injection test on metering instruments, protective relays, auxiliary contacts, etc. and calibrate meters according to the instruction of the Engineer-in-Charge. Services of Testing Engineers, if required by owner, shall be made available by contractor without any extra 7.19 Conduct primary injection test on Over current, Earth fault, REF, Differential Protection, etc. 7.20 Conduct simulation tests on all protection, alarm, annunciation, interlock, breaker and motor control circuits. 7.21 Megger test bus bars, breakers, insulators, PTs, control wiring, etc. using suitable meggers. 7.22 High voltage tests on HV breakers and switchboards as per relevant IS. 7.23 If the insulation resistance value of switchboards are found to be lower than acceptable limits dry out the switchboards in accordance with IS 10118 till the IR value improves to safe value. 7.24 Set all the relays properly as per setting furnished by the Engineer-in-Charge. 7.25 Ensure that all the equipment has checked for assembly of circuit breaker and mechanism, alignment of the complete unit, grouting of foundation, fixing of loose instruments, adjustment of circuit breaker, contact travel, connection of interlocks, main circuit and earth connection, wiring, etc. and its insulation thoroughly dried before commissioning and energising. 8.0 MOTORS 8.1 Unless otherwise specified elsewhere, motors will be erected by other agencies. 8.2 Ensure that all accessories supplied along with the motors such as Temperature sensors, Temperature indicators, Speed sensors, limit switches, pressure switches, etc. are properly fixed and Ventilation and Cooling System of the motor are working smoothly. 8.3 Conduct Mechanical and Electrical checks as per IS:900 8.4 As the motors are idle for a long period, the bearing covers should be removed and grease in the housing pressed with thumbs between the racers of the bearing. If the deterioration of greases is found, old grease should be removed and new grease pressed in the bearing housings. 8.5 The contractor shall test the insulation resistance of the motor winding and direction of rotation in the presence of Engineer-in-charge and ensure they are as per requirements. Insulation resistance, currents on coupled and decoupled runs shall be measured and recorded. 8.6 If motors are found to have low insulation value, the following methods shall be adopted as instructed by Engineer-in-Charge, for improving the resistance value. a) By applying low voltage with rotor locked b) By blasting hot air from external source 8.7 13F121A/14 32644-13-PS-001SPL Set right the motor protection relay correctly. FACT ENGINEERING AND DESIGN ORGANISATION 13F121A/14 ELECTRICAL DEPARTMENT SPECIFICATION FOR ERECTION TESTING AND COMMISSIONING 32644-13-PS-001SPL Page 9 of 10 8.8 Run motors on no load for a period of 4 hours or as instructed by the Engineer-InCharge. During no load run record voltage, current, bearing temperatures at one-hour intervals. The starting current shall be also be recorded. 8.9 If the no load runs are found satisfactory, run the motor on load and record observations as mentioned above for 8 hours or as instructed by the Engineer- InCharge. In case of variable speed motors, variation of speed shall be checked and regulation of speed noted. In case of motor operated valves (MOV’s), control panel and all checking, testing, etc. shall be for the total unit as per manufacturer’s instruction manual. 8.10 On completion of installation, the contractor has to submit a completion report as per proforma given in Annexure-E of IS:900. 8.11 Any other test recommended by the manufacturers for special type of equipment like variable speed motors, etc. shall be done. 8.12 All HV motors and MV motors rating 37 KW and above are provided with space heaters, unless otherwise specified. HV motors are provided with main and star terminal boxes. Motors rating 55KW and above are provided with star delta starting/auto transformer starting. 8.13 For special type of equipment like variable speed motors, motor operated valves, etc. any other special test and commissioning by the manufacturers shall be done without extra cost to the owner. 8.14 Polarisation index test shall be conducted on HV motors. 9.0 BUS TRUNKING 9.1 The details of Bus Trunking such as rating, numbers off, etc. are specified in the ‘Schedule of items of work’. The details such as accessories, weight, etc. also specified unless the supply of same is covered in contractor’s scope.. Bus trunking shall be erected, tested and commissioned as per manufactures instruction manual or as directed by their service engineers, as the case may be without any extra cost to owner. 9.2 Bus trunking shall be supported from walls/roof slabs using hanger supports, tie rods, wall brackets etc. Ensure proper supporting and levelling by checking with spirit level and pendulum weight. 9.3 The bus duct shall properly meggered before starting installation. 9.4 Necessary cutout on walls, if required, shall be under the scope of the contractor. After installation bus duct entry shall be completely sealed off. 9.5 Earth loops/earth coupler plates shall be provided between flanges/matting surfaces to allow fault current to freely flow. 10.0 BATTERY SET & BATTERY CHARGERS/UPS SYSTEM 10.1 The battery erection scope shall include assembling the mounting frame, fixing batteries, battery interconnections, etc. 10.2 Each shell shall be inspected for any damage of its positive plates, negative plates, containers, etc. Cell shall be cleaned, properly reused with distilled water. 10.3 All the inter cell/inter tier connections, contact surfaces shall be applied with petroleum jelly. FACT ENGINEERING AND DESIGN ORGANISATION 13F121A/14 ELECTRICAL DEPARTMENT SPECIFICATION FOR ERECTION TESTING AND COMMISSIONING 32644-13-PS-001SPL Page 10 of 10 10.4 The testing and commissioning of the battery set shall include filling of electrolyte, charging discharging, etc. as per manufacture’s recommendations. 10.5 Erection, testing and commissioning of UPS panels, battery charger panels, distribution panels, etc. shall be carried out generally as per the requirements furnished for switch boards. 10.6 Necessary distilled water required during charging to be supplied by the contractor. 10.7 All necessary safety precautions shall be taken while preparing electrolyte, ie. Goggle, rubber, apron, gloves, etc. 10.8 Battery should discharged at specific rate after initial charging and recharge the battery there after. Lamp load/resistance bridge required for discharge shall be under contractor’s scope. Record all battery voltage of each cell, specific gravity, temperature, current during charging/discharging, after final charging the battery shall be put on float charge. All the batteries shall numbered serially on the surface of container with suitable red colour paint./acrylic sheet with black numbers engraved. 10.9 During the period of charging, unit shall not be overloaded and cells must be topped up as often as necessary to prevent the electrolyte falling below. 10.10 The manufacturer will supervise testing and commissioning if so mentioned elsewhere as desired by owner. 11.0 OTHER EQUIPMENTS 11.1 Other equipment such as capacitors, reactors, control panels, push button stations, NGR, EHV switchyard equipments, circuit breakers, Isolators, Current Transformers, Potential Transformers, Lightning Arresters .etc. shall be installed listed and commissioning as per manufacturer’s instructions FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION SCOPE OF INSPECTION AND TESTS (ELECTRICAL) 32644-13-PS-001INS Page 1 of 4 R0 TPS NO: 32644-13-PS-001 ITEM : Construction of Phosphoric Acid storage tank at Q10 W. Island EQPT. NOS.: The following inspection and test shall be conducted and records submitted Sl. No. 1.0 13FT924D/14 2.0 Description Routine tests at Manufacturer’s works on all electrics (Motors, cables,MV Switchboard/ Control panel,LCS etc) as per relevant standards. Physical verification at Manufacturer’s works for compliance with purchase order specifications and approved drawings/ documents Ins./test Reqd. Witness Reqd. Reqd Reqd Reqd Reqd 3.0 Verification of CMRI certificates for electrics of Hazardous area 4.0 Tests at site 4.1 Pre-commissioning tests and commissioning tests as per relevant standards Reqd Reqd 4.2 Insulation Resistance test Reqd Reqd 4.3 Primary and secondary injection tests on CTs and Relays Reqd Reqd 4.4 Checking power, control and earthing system and connections. Reqd Reqd 5.0 Other specific tests 5.1 Checking The Lightning Protection System Reqd Reqd 0 06.06.20 ISSUED FOR ENQUIRY REV. DATE DESCRIPTION Reqd SM SM IK PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION Remarks TECHNICAL PROCUREMENT SPECIFICATION TPS NO. ITEM 32644-13-PS-001 INS SCOPE OF INSPECTION AND TESTS Page 2 of 4 R0 32644-13-PS-001 : MEDIUM VOLTAGE SWITCH BOARDS EQPT. NOS.: The following inspection and test shall be conducted and records submitted Sl. No. Description Ins./test Reqd. Witness Reqd. 1.0 Physical verification for compliance with P.O. spec., scope, approved drawings & BOM Reqd Reqd 2.0 Routine tests Reqd Reqd 2.1 Power frequency Voltage dry tests on main circuits. Reqd Reqd 2.2 Voltage tests on control and auxiliary circuits Reqd Reqd 2.3 Measurement of resistance of main circuit Reqd Reqd 2.4 Mechanical operation test Reqd Reqd 2.5 Tests of auxiliary electrical and pneumatic devices Reqd Reqd 2.6 Verification of wiring Reqd Reqd 2.7 Electrical operation test Reqd Reqd 2.8 Megger test Reqd Reqd 2.9 Safety interlocks and protection against electric shock and short circuits Reqd Reqd 2.10 Verification of CT ratio and polarity of CTs Reqd Reqd 2.11 Verification of nameplate information & marking Reqd Reqd Reqd Reqd Reqd Reqd 2.12 2.13 2.14 Remarks Relay operation tests Primary and secondary injection tests on panels and protective gears Separate testing of breaker operating mechanism and other accessories Type test certificates to be furnished 3.0 Type tests 3.1 Impulse voltage dry test 3.2 Power frequency voltage dry test 3.3 a) Temperature rise tests of Switchboard b) Temperature rise tests of Circuit breaker 0 REV. NO 02.06.2020 DATE ISSUED FOR ENQUIRY DESCRIPTION SM PREPARED FACT ENGINEERING AND DESIGN ORGANISATION IK CHECKED IK APPROVED TECHNICAL PROCUREMENT SPECIFICATION TPS NO. ITEM 32644-13-PS-001 INS SCOPE OF INSPECTION AND TESTS Page 3 of 4 32644-13-PS-001 : MEDIUM VOLTAGE SWITCH BOARDS EQPT. NOS.: The following inspection and test shall be conducted and records submitted Sl. No. Description 3.4 Verification of dielectric properties 3.5 Verification of making and breaking capacity of breaker 3.6 Verification of temp. limits and characteristics of relays 3.7 Short time current tests on main circuits 3.8 Short time current test on earthing circuits 3.9 Mechanical operation test 3.10 Verification of degree of protection Ins./test Reqd. Witness Reqd. FACT ENGINEERING AND DESIGN ORGANISATION Remarks R0 TECHNICAL PROCUREMENT SPECIFICATION 32644-13-PS-001INS SCOPE OF INSPECTION AND TESTS Page 4 of 4 TPS NO.. 32644-13-PS-001 ITEM : MEDIUM VOLTAGE INDUCTION MOTOR EQPT. NOS.: The following inspection and test shall be conducted and records submitted Sl. No. Ins./test Reqd. Witness Reqd. Remarks 1.0 Physical verification for conformity with P.O. specifications and approved drawings 2.0 Routine test (as per IS), including the following: 2.1 Insulation resistance test Reqd 2.2 High voltage test Reqd 2.3 No load running test Reqd 2.4 Locked rotor test Reqd 2.5 Reduced voltage running test at no load Reqd 2.6 Measurement of resistance of windings of stator Reqd 2.7 Open circuit voltage ratio test - 3.0 Type tests Required test certificates shall be furnished 3.1 Dimensional check 3.2 Measurement of stator resistance and rotor resistance 3.3 No load running test at rated voltage 3.4 Open circuit voltage ratio test 3.5 Reduced voltage running test at no load 3.6 Locked rotor test 3.7 Full load running test 3.8 Temperature rise test 3.9 Momentary overload test 3.10 Over speed test 3.11 Tan delta test & polarization index test 3.12 Vibration & noise measurements 3.13 High Voltage test 4.0 Special tests (optional) 0 REV. 13FT910D/14 Description 08.06.20 DATE ORIGINAL ISSUE DESCRIPTION SM Required test certificates shall be furnished - IK PRPD. FACT ENGINEERING AND DESIGN ORGANISATION IK CHKD. APPRD. TECHNICAL PROCUREMENT SPECIFICATION 00ES001 / 01 VENDOR DATA SUBMISSION PROCEDURE PAGE 1 OF 3 SCOPE This document together with “VENDOR DATA REQUIREMENTS (VDR)” defines FEDO’s requirements for vendor drawing and data for any enquiry, work order or purchase order. Bidders unable to comply with these requirements must detail all exceptions in their proposal. The timely delivery of quality drawings and data is as crucial as delivery of the equipment itself and hence the same shall be strictly adhered to after commitment. Failure to provide adequate preliminary data / drawing may render a proposal non-responsive and hence may be rejected. After commitment failure to provide documents as per purchase order may delay progressive payments and adversely affect future invitation to bids. VENDOR DATA REQUIREMENTS (VDR) FEDO will provide a partially completed VDR form along with each enquiry. This form explains group code of the document, quantity of each document required and lead time for submission. Columns are available for the vendor to fill in his deviations, if any, from FEDO’s requirements. The vendor shall forward a filled-in VDR form along with his offer, if he has got any deviation from FEDO’s requirements. In the absence of a filled-in VDR form along with the offer, it will be presumed that the vendor is accepting FEDO’s requirements specified in the VDR. CLASSIFICATION OF DOUCMENTS Documents are classified based on their status and nature of content. Status of documents: Preliminary documents required along with the offer. Documents to be submitted after commitment. Final documents. 3.2.0. The documents are further classified into Groups A,B and C, depending on the nature of the documents as explained below. Group A requirements These documents are urgent in nature and contains information that are required for proceeding with the detailed engineering of surrounding/down stream equipments in the plant and hence are to be submitted on priority basis. Group B requirements These documents are to be reviewed by FEDO for compliance with the purchase order / work order specifications but are not essential for other engineering activities of FEDO. Group C requirements Documents in this group contains data / information / records which are final in nature and that are required for the equipment user and need not be reviewed by FEDO. PRPD.BY: CHKD BY: FACT ENGINEERING AND DESIGN ORGANISATION APPRD BY: ISSUED ON : SEPT 03 TECHNICAL PROCUREMENT SPECIFICATION 00ES001 / 01 VENDOR DATA SUBMISSION PROCEDURE PAGE 2 OF 3 VENDOR DATA INDEX (VDI) Vendor shall forward a filled up and updated VDI along with each vendor data transmittal. VDI shall list out all documents that are being prepared for the particular order, their current revision status and indicate the documents included in the present transmittal. A blank VDI is attached along with this document which shall be used for this purpose. QUALITY OF VENDOR DRAWINGS vendor drawing and data shall be supplied in full size drawings, reproducibles and CDs as specified in the VDR. All drawings / documents shall be clear, legible, right reading and made out of originals prepared in black ink. English language and metric units shall be used for the preparation of all documents. The documents shall be prepared n any of the following standard sizes. A1: 594 mm x 840 mm A2: 420 mm x 594 mm A3: 297 mm x 420 mm A4; 210 mm x 297 mm All documents submitted to FEDO shall be folded into A4 size (210 x 297 mm) except originals/ reproducibles which may be rolled. All reproducibles shall be in high quality polyester films. Soft copies shall be furnished in CD for final drawings/documents. Each drawing / document shall have a title block at the right hand bottom corner with the following information. Name of Vendor. Name of Project, Owner and location. Name of Consultant: FEDO FEDO Purchase Order Number. Equipment name and number. Drawing title. Drawing number, revision and page number. All drawings shall be drawn to some standard scales only and the same shall be indicated in the drawing. The status of the document like “PRELIMINARY, FINAL, FOR REVIEW” etc. shall be stamped on all copies forwarded to FEDO. All documents shall have a block of 100 mm x 100 mm space left vacant for FEDO to put their stamp after review. All drawing/document shall have a revision block explaining revision number, revision description, data of revision, revision authorization etc. When the revised drawings are submitted all currently revised area shall be clearly demarcated by clouding. Any revisions made on other parts of the documenting will not be reviewed by FEDO. When drawings are received back from FEDO with comments, vendor shall incorporate all the comments and resubmit the same. If the vendor is not in a position to incorporate certain comment made by FEDO, then the reason for such deviation shall be highlighted in the forwarding letter to FEDO. FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION 00ES001 / 01 VENDOR DATA SUBMISSION PROCEDURE PAGE 3 OF 3 The respective engineering specification and other purchase order spec. will explain the minimum data / details required in various drawings. In the absence of any such information in the purchase order documents, vendor shall follow the standard good engineering practices in detailing the drawing. CONDITIONS OF FEDO REVIEW FEDO and / or its client reserve the right to review the vendor documents. FEDO’s REVIEW WITH OR WITHOUT COMMENTS OF THE VENDOR DOCUMENTS SHALL NOT RELIEVE THE VENDOR OF RESPONSIBILITY TO COMPLY WITH ALL PURCHASE ORDER TERMS AND CONDITIONS, including all implied requirements relating to fitness for service and good engineering practices. Approval or acceptance does not imply or infer any determination relating to compliance by the vendor with its full responsibilities under the purchase order. FEDO’s comments are limited to identifying requirements within the scope of the purchase order or failure by the vendor to comply with the requirements of purchase order, as revealed by the limited review. Oversights in the above limited review cannot be taken as approval for the vendor to deviate from the purchase order conditions. FEDO reserve the right to point out any such deviations at any stage of the order execution. The vendor shall comply with all such requirements without any price / delivery implications. FEDO review will be authorized by an official stamp as given below, properly filled and signed by the concerned. Comments if any will be indicated in red ink or clouded in the case of copies of commented drawings. Appropriate comment in the ‘comments’ column and ‘status of review’ column will be marked. Comment Status of Review As noted Revise and resubmit for review No comments Proceed as noted and submit revised docs. For records Not reviewed No further review required Forward final docs. as per P.O. All documents received in FEDO shall be dispatched after review within 15 days from the date of receipt. Vendor shall notify FEDO of non receipt of reviewed documents in time immediately, to take corrective actions. The delivery of the equipment shall in no case be linked with the review of the vendor drawings and data by FEDO. It is the sole responsibility of the vendor to execute the job as per the purchase order conditions. If required the vendor shall depute his technical personnel to FEDO after submission of documents for timely finalisation of documents. FACT ENGINEERING AND DESIGN ORGANISATION 32644- 13 - PS - 001 VDI VENDOR DATA INDEX PROJECT: Construction of Phosphoric Acid storage tank at Q10 W. Island PROJECT NO. : 32644 ITEM: Sl. No. Doc. / Drawing No. DATE: Rev. 0 Rev. 1 Rev. 2 Rev. 3 Rev. 4 Rev. 5 Date Date Date Date Date Date Description DATE SIGNATURE FACT ENGINEERING AND DESIGN ORGANISATION R0 VENDOR: P.O NO.: ISSUE NO. 00FT020/14 PAGE 1 OF 1 Relevant to This issue TECHNICAL PROCUREMENT SPECIFICATION 32644-13-PS-001 VDR-ELEC VENDOR DATA REQUIREMENTS Page 1 of 4 PROJECT: Construction of Phosphoric Acid storage tank at Q10 W. Island ITEM: ELECTRICS FOR TURNKEY INSTALLATION CLIENT : M/s. FACT-CD TPS. NO: 32644-13-PS-001 PO NO: ENQUIRY STATUS : COMMITMENT VENDOR: Offer Sl. No. Group code @@ Final After commitment Lead time in weeks Description Qty. Qty. Re qd Qty. @ Agreed Proposed 1.0 A Item wise deviations, if any, from specification. 1S+1P 2.0 A Technical particulars as per prescribed proforma 1S+1P 1S+1P 4 4P+1S 3.0 A Single Line diagram of Power Distribution 1S+1P 1S+1P 4 4P+1S 1S+1P 1S+1P 4 4P+1S 1S+1P 1S+1P 4 4P+1S List of Electrical loads with rating (kW/Amps) and quantity General layout of the system indicating location of all electrics and substation building 4.0 A 5.0 B 6.0 B 7.0 B 8.0 C 9.0 C Power Layout 1S+1P 4 4P+1S 10.0 C Cable Schedule 1S+1P 4 4P+1S 11.0 C Earthing Layout 1S+1P 4 4P+1S 12.0 C Dimensioned GA drawing of individual electrics 1S+1P 4 4P+1S 13.0 C 1S+1P 4 4P+1S 14.0 C 1S+1P 4 4P+1S 15.0 C 1S+1P 4 4P+1S 16.0 C Manufacturer’s Routine test certificates 1S+1P 4 4P+1S 17.0 C Manufacturer’s Type test certificates 1S+1P 4 4P+1S Harmonics calculations for VFD 1S+1P Dimensioned foundation plan showing floor cut outs for cable for major electrical equipments. Technical literature, installation ,operation and maintenance manual of major electrical equipments. 1S+1P 1S+1P Schematic wiring diagram of controls of the ,HV/MV switch boards MCC Schematic wiring diagram of controls and interlocks for HV/MV motors if any Bill of Materials for all electrics indicating make, type, quantity, rating, catalogue ref details etc. Legend: Group code: A-For review and detailed Engineering, B-For review, C- For information and record Document type: R-Reproducible, P-Print, S-Soft copy in properly secured media. Notes: 0 13FT924C/14 REV. 1. @ Vendor shall fill in proposed lead time if different from the required lead time. 2. @@ Each set of final documents shall be submitted in a folder. Two such folders shall be packed and dispatched with the equipment. 06.06.20 DATE Original Issue SM DESCRIPTION FACT ENGINEERING AND DESIGN ORGANISATION IK PRPD. IK CHKD. APPRD. DATA SHEET C 19.0 B 20.0 B CIMFR certificates for electrics in hazardous areas. List of spares for two years trouble free operation of major electrical equipments. Design calculations of Electrical system including cable sizing, earthing, lighting, etc. 1S+1P 13FT924C/14 18.0 32644-13-PS-001 VDR-ELEC VENDOR DATA REQUIREMENTS FACT ENGINEERING AND DESIGN ORGANISATION Page 2 of 4 1S+1P 4 4P+1S 1S+1P 4 4P+1S 1S+1P 4 4P+1S TECHNICAL PROCUREMENT SPECIFICATION Page 3 of 4 R0 PROJECT: Construction of Phosphoric Acid storage tank at Q10 W. Island ITEM: MEDIUM VOLTAGE SWITCH BOARDS CLIENT :M/s FACT-CD TPS. NO: 32644-13-PS-001 STATS : ENQUIRY COMMITMENT P.O. NO.: Offer Sl. No. Grp. code Duly filled in Technical particulars of Medium voltage switch boards , as per format attached Foundation plan, showing cutouts/ floor openings, foundation pockets, etc. along with out line dimensions and static & dynamic loading Dimensioned general arrangement drawing internal & external, including busbar disposition B 2.0 A 3.0 A 4.0 A Sectional view showing fixing details 5.0 A Drawing of Bus trunking flange, with complete dimensions including bolt hole locations & sizes and bus bar arrangement 6.0 A Single line diagram of switch boards 7.0 B 8.0 B 9.0 B 10.0 B 11.0 B 12.0 B Notes: Lead time in weeks Qty. 1.0 Schematic diagram and wiring diagrams (including inter panel wiring diagrams), with ferrule nos, terminal nos, arrangement of terminals, etc. Schedule of materials / components, with quantity, rating, type, make, etc. Relay co- ordination details, with recommended settings, calculation etc Qty. 1S+1P Req d. 1S+1P @ Propd Qty. Agrd. 4 1S+4P 1S+1P 1S+4P 4 1S+1P 1S+1P 1S+4P 4 1S+4P 4 1S+4P 1S+1P 1S+4P 4 1S+1P 1S+4P 4 1S+1P 1S+1P 1S+4P 4 1S+4P 1S+1P Calculation sheet proving busbar capacity 1S+1P Calculation sheet proving capacity of control transformers Certificates / records of routine & type tests conducted as per scope of Inspection and tests @ @@ @@ Final After commitment Description Legend: 13FT906C/14 32644-13-PS-001-VDR VENDOR DATA REQUIREMENTS 1S+1P 1S+4P 4 1S+4P 4 1S+4P 4 Group code: A - For review and detailed Engineering, B - For review, C - For information and record Document type: R -Reproducible, P - Print, S- Softcopy in properly secured media Vendor shall fill in proposed lead time if different from the required lead time. Each set of final documents shall be submitted in a folder. Two such folders shall be packed and despatched with the equipment. 0 02.06.2020 REV.NO. DATE Issued for Enquiry DESCRIPTION SM IK IK PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION 32644-13-PS-001-VDR VENDOR DATA REQUIREMENTS Page 4 of 4 R0 ITEM: MEDIUM VOLTAGE SWITCH BOARDS Offer Sl. No. Description Grp. code Lead time in weeks Qty. 13.0 B Type test certificates of breakers, switches, MCCB etc. 14.0 B Certificate of short circuit rating of breakers 15.0 B 16.0 B 17.0 B 18.0 C 19.0 C 20.0 C 21.0 C 22.0 B Spare parts list 23.0 B Duly filled and signed Compliance statement as per format attached 24.0 B Unpriced copy of price bid 25.0 B Testing procedure for temperature rise test 26.0 C Quality Assuarance Plan (QAP) CPRI test certificate for similar switchboard assembly Test Certificates of brought out items like protective relays, CTs, energy meters, etc. Characteristic curves of fuses and thermal overload relays, with range of adjustment relays. Technical literature / catalogues of relays, MCCB KWH / KW / PF meters, etc. With its wiring diagrams. Technical catalogue & internal wiring diagrams of circuit breakers Technical literature, pamphlets and brochures relating to the various equipment used. Erection , Operation & Maintenance manuals of breakers and complete switchboard @@ Final After commitment Qty. Req d. 1S+1P 1S+1P 4 4 @ Propd Qty. Agrd. 1S+4P 1S+4P 1S+4P 1S+4P 1S+1P 4 1S+1P 1S+4P 1S+4P 4 1S+1P 1S+1P 4 4 1S+4P 1S+4P 1S+4P 1S+1P 1S+1P FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION GENERAL REQUIREMENT OF ELECTRICS 13ES900/14 Page 1 of 4 00FT006 CONTENTS 1.0.0 2.0.0 3.0.0 4.0.0 5.0.0 6.0.0 7.0.0 8.0.0 9.0.0 10.0.0 11.0.0 12.0.0 13.0.0 14.0.0 15.0.0 16.0.0 17.0.0 18.0.0 19.0.0 SCOPE REFERENCE COMPLETENESS OF CONTRACT COMPONENTS AND CONSTRUCTION STANDARDS & REGULATIONS SERVICE CONDITIONS EARTHING POWER SUPPLY DETAILS NAME PLATES PAINTING INTER CHANGEABILITY DANGER NOTICE PLATES TOOLS AND APPLIANCES SERVICES OF MANUFACTURER’S TECHNICAL EXPERTS TRAINING PERFORMANCE OF EQUIPMENT TESTS DOCUMENTS INSTRUCTIONS TO THE BIDDER 1.0.0 SCOPE 1.1.0 This specification covers the general requirements for supply and installation of all electrical items as applicable. 2.0.0 REFERENCE 2.1.0 The following documents shall be read in conjunction with this specification: 2.1.1 Data sheet of General Requirements for Electrics. 2.1.2 Engineering specifications, Data sheets and Technical Particulars of individual equipment / items. 2.1.3 Scope of work, Scope of Inspection and Tests, Special requirements of the project, Vendor Data Requirements, etc attached with the Technical Procurement Specifications. 3.0.0 COMPLETENESS OF CONTRACT 3.1.0 The electrics supplied / installed shall be complete with all accessories for the safe, smooth and efficient operation of the system. Such parts shall be deemed to be within the scope of this specification whether specifically mentioned or not. 4.0.0 COMPONENTS AND CONSTRUCTION 4.1.0 Each and every component shall be of reputed make and be of proven design for best performance, reliability and durability. They shall be brand new. Workman ship shall be of the highest grade and the entire construction shall be in accordance with the best modern engineering practice. 5.0.0 STANDARDS & REGULATIONS 5.1.0 All electrical equipment / installations shall fully comply with the requirements laid down in the following rules / regulations / acts / standards / codes as amended up to date. PRPD. : CHKD. : APPRD. : FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON SEPT 2014 ENGINEERING SPECIFICATION GENERAL REQUIREMENT OF ELECTRICS 5.1.1 Indian Electricity Rules. 5.1.2 Indian Electricity Act. 5.1.3 Indian Electricity Supply Act. 5.1.4 Indian Factories Act. 5.1.5 Fire Insurance Act. 5.1.6 Petroleum Rules. 5.1.7 OISD Standards. 5.1.8 Pollution control norms as per Environmental Regulations. 5.1.9 Standards / regulations of statutory bodies applicable for the place of installation. 13ES900/14 Page 2 of 4 5.1.10 Relevant Indian / International standards and in their absence, the standards of the country of manufacture. Vendor shall furnish all necessary assistance & documents for obtaining approval from statutory bodies. Making whatever additions/ modifications considered necessary by the Electrical Inspectorate and other authorities to bring the equipment / installation in conformity with the above rules, Regulations, acts and standards shall be in the scope of the vendor. 5.3.0 All equipment shall be of tropical design according to relevant Indian / International Standards. 5.4.0 All electrics shall be suitable for the hazardous / non-hazardous area involved and /or specified. Electrics suitable for the hazardous area involved shall be selected as per the relevant Indian Standards and shall be of proven design approved by CIMFR / relevant statutory bodies. In such cases copies of relevant certificates shall be furnished for Purchaser’s approval. 6.0.0 SERVICE CONDITIONS 6.1.0 All equipment shall be suitable for the service conditions specified in the Data sheet of General Requirements for Electrics attached. 7.0.0 EARTHING 7.1.0 Duplicate earthing terminals, suitable for terminating earthing conductors of sizes indicated in the data sheets of individual equipment, shall be provided on the body of the equipment apart from those, if any, provided inside the terminal boxes. 8.0.0 POWER SUPPLY DETAILS 8.1.0 The equipment shall be suitable for the power system details furnished in the Data sheet of General Requirements for Electrics unless otherwise specified in the data sheets of individual equipment. 8.2.0 The equipment shall perform satisfactorily even with variation in supply voltage and frequency as detailed in the data sheets. The equipment shall operate at the specified rating without exceeding the permissible temperature rise as per the relevant I.S. in spite of the variation in supply voltage and frequency. 00FT006 5.2.0 FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION GENERAL REQUIREMENT OF ELECTRICS 13ES900/14 Page 3 of 4 9.0.0 NAME PLATES 9.1.0 Necessary nameplates, conforming to standards, giving relevant details of the equipment, shall be provided on individual equipment. Any additional details shall also be indicated in the nameplate, if so specified in the specifications / data sheets of individual equipment. 10.0.0 PAINTING 10.1.0 Unless otherwise specified in the specifications / data sheets of individual equipment / items, painting procedure described in this clause shall be adopted. 10.2.0 All exposed metal parts shall be subjected to at least the following pretreatment before painting to suit the material and environment involved. 10.2.1 De-greasing. 10.2.2 Rust removing. 10.2.3 Phosphating/ equivalent chemical treatment. 10.2.4 Giving two coats of corrosion resistant primer suitable for final coating. 10.3.0 Two coats of anticorrosive painting shall be given after the above process so as to render the materials suitable for the highly corrosive environment specified. 10.4.0 Final Colour and finish of the equipment shall be Dark Admiralty Grey (shade no: 632) as per IS: 5 unless otherwise specified in the data sheet for individual equipment/item. 10.5.0 Vendor shall furnish detailed painting procedure proposed, along with the bid. 11.0.0 INTER-CHANGEABILITY 11.1.0 All similar parts shall be inter-changeable with each other. 12.0.0 DANGER NOTICE PLATES 12.1.0 Danger Notice plates conforming to IS: 2551 and other statutory requirements shall be affixed on equipment wherever required. 13.0.0 TOOLS AND APPLIANCES 13.1.0 The vendor shall supply one set of special tools and appliances that may be required for carrying out the maintenance, special inspection etc. of the equipment offered, without any extra cost. 13.2.0 Vendor shall also furnish list of tools and appliances required for the maintenance of different equipments. 14.0.0 SERVICES OF MANUFACTURERS’ TECHNICAL EXPERTS 14.1.0 Services of the manufacturer’s technical experts shall be made available to the Purchaser, if found necessary, during erection, testing, and commissioning and during the guarantee period. 00FT006 15.0.0 TRAINING 15.1.0 The vendor shall render all facilities free of cost for imparting training to purchaser’s technical personnel at manufacturer’s works, if required, for the proper assembly, installation, testing, commissioning, operation and maintenance of the equipment supplied. The travel and living expenses of the personnel deputed for training will be borne by the Purchaser. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION GENERAL REQUIREMENT OF ELECTRICS 13ES900/14 Page 4 of 4 16.0.0 PERFORMANCE OF EQUIPMENT 16.1.0 Duly filled in Technical Particulars of individual equipment / item shall be furnished as per formats attached. Performance figures of the equipment as per Technical Particulars furnished along with the offer shall be guaranteed. 17.0.0 TESTS 17.1.0 All the tests specified in Scope of Inspection & Tests attached along with the Technical Procurement Specification shall be performed. 18.0.0 DOCUMENTS 18.1.0 Drawings and documents shall be furnished as per Vendor Data Requirements (VDR) attached with Technical Procurement Specification. 19.0.0 INSTRUCTIONS TO THE BIDDER 19.1.0 All the drawings and documents as per Vendor Data Requirements shall be furnished along with the offer. Offers without these details will be treated as incomplete and are liable for rejection. 19.2.0 In the absence of clearly spelt-out item wise deviations from purchaser’s specification, it will be presumed that the equipment offered are in conformity with the specification. 00FT006 19.3.0 The Vendor shall supply all equipments and items of make specified in the vendor list attached with the specification. The Vendor shall obtain Purchaser’s approval before placement of purchase order for electrical items / components wherever makes are not specified in the respective data sheets. FACT ENGINEERING AND DESIGN ORGANISATION Page 1 of 1 1.0 Project Construction of Phosphoric Acid storage tank at Q10 W. Island 2.0 Owner FACT-CD 3.0 Location Willington Island, Kochi 4.0 Service conditions 4.1 Altitude < 1000m above mean sea level 4.2 Humidity Min 64% 4.3 Humidity max. 93% 4.4 Humidity design 100% at 40 C 4.5 Ambient temperature C-Min. 4.6 0 19.2 0 34.3 0 Ambient temperature C-Max. 4.7 Ambient temperature C-Design 40 4.8 Rain fall – Max . Record in an hour 40mm 4.9 Rain –fall Max record in 24 Hours 169.5mm 5.0 Environment Coastal area. Presence of salts and corrosive gases 6.0 Wind velocity for structural design 124 km/h 7.0 Seismic factor for design Within seismic Zone 3 as per IS 1893 8.0 Soil data 8.1 Soil resistivity 8.2 Type of soil (hard / loose) 9.0 Power system 9.1 Voltage (V) & Variation (± %) 433V +/- 10% 9.2 Frequency (Hz) & Variation (± %) 50Hz +/- 5% 9.3 No of phases Three 9.4 No. of wires Four 9.5 Fault level (MVA) 31/15 9.6 Method of neutral earthing Solid earthing 0 06-06-20 REV. DATE R0 0 PROJECT Construction of Phosphoric Acid storage tank at Q10 W. Island CLIENT FACT-CD P.O. NO. 13FT900A/14 32644-13-DA-90001 GENERAL REQUIREMENT FOR ELECTRICS DATA SHEET SM PRPD. IK IK CHKD. APPRD. VENDOR ENGINEERING SPECIFICATION 13ES924/14 ELECTRICS FOR TURNKEY INSTALLATION Page 1 of 10 CONTENTS 1.0.0 2.0.0 3.0.0 4.0.0 5.0.0 6.0.0 7.0.0 8.0.0 9.0.0 10.0.0 11.0.0 12.0.0 13.0.0 14.0.0 15.0.0 16.0.0 SCOPE REFERENCE STANDARDS GENERAL REQUIREMENTS MOTORS VARIABLE SPEED DRIVES M.V.SWITCHBOARDS/ MOTOR CONTROL CENTRES (MCC) LOCAL CONTROL STATIONS CABLES AND CABLING EARTHING SAFETY ITEMS HAZARDOUS AREA CLASSIFICATION FOR SELECTION OF ELECTRICS ERECTION, TESTING AND COMMISSIONING APPROVAL FROM ELECTRICAL INSPECTORATE LIGHTING MAKE OF ELECTRICAL EQUIPMENT/ ITEMS 1.0.0 SCOPE 1.1.0 This specification covers the requirements for design, engineering, supply, receiving materials at site, inspection at site, storage, transportation at site, erection, testing and commissioning of all electrics required for the safe, efficient and smooth running of the turnkey installation / package. 2.0.0 REFERENCE 2.1.0 The following documents shall be read in conjunction with this specification 2.1.1 2.1.2 2.1.3 Engineering specification and Data Sheet of General Requirements for Electrics Data Sheet of Electrics for Turnkey Installation. Technical Particulars of Electrics for Turnkey Installation. 3.0.0 STANDARDS. 3.1.0 Requirements laid down in the latest revisions of the following Indian Standards and other relevant standards shall be strictly adhered to. IS: 325 IS/IEC:60034 IS/IEC:60947 IS: 8623 IS: 1248 Three phase Induction Motors. Rotating Electrical Machines. Low voltage switchgear and control gear. Low voltage switchgear and control gear assemblies Direct acting indicating analogue Electrical measuring instruments and accessories IS: 2705 Current transformers. IS: 13703 Fuses for voltages not exceeding 100V AC or 1500V DC IS: 10118 Code of practice for selection, installation and maintenance of switchgear and control gear. IS: 732 Code of practice for electrical wiring installation. IS: 694 PVC insulated cables for working voltage upto and including 1100 volts. IS: 1554 PVC insulated (Heavy duty) Electric cables. IS: 3043 Code of practice for earthing. IEC:62305-P-1 to 4 Protection against lightning. IS: 7689 Guide for control of undesirable static electricity. PRPD. : CHKD. : APPRD. : 00FT001 FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON SEPT 2014 ENGINEERING SPECIFICATION IS: 5571 IS: 5572 00FT001 IS:12615 ELECTRICS FOR TURNKEY INSTALLATION 13ES924/14 Page 2 of 10 Guide for selection of electrical equipment for hazardous areas. Classification for hazardous areas (other than mines) for installations.- Part 1 - Areas having flammable gases and vapors. Energy Efficient Induction Motors- Three Phase Squirrel cage electrical 4.0.0 GENERAL REQUIREMENTS 4.1.0 The scope of work for electrics shall be complete in all respects and shall include necessary Medium Voltage switchboards / Motor Control Centres, Motors, Local Control Stations, Cables, Earthing Materials, Safety items and interlocks, Cabling, Earthing, Lighting, etc. required for the installation, as specified in the data sheets. 4.2.0 The Purchaser will be providing adequate power supply at 415 Volts, 50 Hz, 3 phase and neutral A.C. to the MV switch boards / Motor control centres provided by the vendor. The incoming cables shall be connected to the MV Switchboard / MCC by the purchaser. Voltage and frequency variation shall be +10%and +5%, unless otherwise specified in the Data Sheet. 4.3.0 For Motors/Equipments suitable for voltage rating above 415Volts, purchaser will arrange power supply through purchaser’s circuit breakers. Necessary power cabling upto the motors /equipments and control cabling upto the local control stations of motors as well as termination of the above cables at both ends shall also be arranged by the purchaser in such cases. The interconnecting cabling for protection/ alarm required, between HV motors and purchaser’s HV switch board is included in the scope of purchaser. 4.4.0 The purchaser will be terminating the main earth bus at single point within battery limit (size and material of main earth bus shall be as per Data Sheet). Further earthing within battery limit shall be included in the scope of the vendor. 5.0.0 MOTORS. 5.1.0 All drive motors required for the system shall be included in the scope of the vendor unless otherwise specified in the Data Sheet. 5.2.0 Motors shall be suitable for the voltage ratings indicated in the Data Sheet and shall conform to the following specifications. 5.2.1 Motors provided shall have adequate performance characteristics such as starting torque pull out torque, etc. and rating for meeting the driving and starting duty of the driven equipment. 5.2.2 All motors shall be squirrel cage induction type with insulation Class B / F with temperature rise limited to Class B and totally enclosed fan cooled enclosure with IP 55 / IPW55 degree of protection; except in cases of special types of motors such as slip- ring motors, variable speed motors, etc. required to meet special drive requirements, and environmental conditions. In all such cases, motors with necessary special features shall be provided and approval for the same shall be obtained from the purchaser. Degree of protection for the enclosure shall be as specified in the Data Sheet. 5.2.3 Motors shall be provided with 240V,50Hz, single phase anti- condensation heaters, if so specified in data sheet and shall be wired up to separate terminal box with cable glands suitable for the cable sizes specified in Data Sheet. 5.2.4 Motors shall be provided with terminal boxes (where in all six winding ends are brought out), cable glands, etc. suitable for the type and sizes of cables selected by vendor. In addition, the motor shall have the largest terminal box possible in the frame size. 5.2.5 All motors are envisaged to be started on Direct-On-Line unless otherwise specified in the Data Sheet. 5.2.6 All motors shall be suitable for number of starts specified in the Data Sheet. FACT ENGINEERING AND DESIGN ORGANISATION 00FT001 ENGINEERING SPECIFICATION ELECTRICS FOR TURNKEY INSTALLATION 13ES924/14 Page 3 of 10 5.2.7 Motor frame sizes shall be in accordance with IEC recommendations / relevant Indian Standards. 5.2.8 For unidirectional motors, the direction of rotation shall be clearly marked on the body of the motor. 5.2.9 Motors shall have a starting time, which is less than hot locked rotor withstand time of motor by at least two seconds at the rated conditions of voltage and frequency specified with driven machine coupled. 5.2.10 Motors shall be suitable for starting at 80% of the rated voltage against torque speed characteristics of the driven equipment. 5.2.11 The terminal box of Medium Voltage motors shall be capable of withstanding the calculated fault level in terms of the let through energy of combination starter unit at the place of installation. 5.2.12 An indelible warning inscription shall be provided on the motor to indicate that switching of anticondensation heater supply shall also be ensured before carrying out any work on the motor. 5.3.0 In addition to the above requirements high voltage motors shall conform to the following: 5.3.1 Ensure that starting current is not more than 600% of full load current at rated voltage and frequency. 5.3.2 All the six winding ends shall be brought out and marked, three to one terminal box for power supply connections and three to another terminal box on the opposite side for star connection. Further main terminal box shall be phase segregated type and terminal boxes shall be suitable for system fault level for 0.25 seconds or as indicated in the Data Sheet. 5.3.3 If temperature detectors / oil level indicators etc. are provided as per Data Sheet, the same shall be wired upto a terminal box with cable gland suitable for the cable sizes indicated in the Data Sheet. 5.3.4 Additional protection features such as zero speed switches for loads with high starting time, embedded resistance temperature detectors for windings and bearings, oil temperature detectors and level indicators (with alarm and trip contacts) for oil lubricated bearings etc. shall be provided, if specified, in the Data Sheet. For resistance type winding / bearing temperature detectors suitable temperature scanner / monitoring relays with alarm and trip contacts shall be provided, in a weather proof enclosure, if specified in the data sheet. 6.0.0 VARIABLE SPEED DRIVES 6.1.0 The Variable Speed Drive System shall be suitable for the load characteristics and operation duty of the driven equipment, the equipment shall be suitable for continuous operation. 6.2.0 The converter design shall impose minimum harmonics on the electrical power system in accordance with the relevant standards and shall be acceptable to the Owners electrical network. 6.3.0 The Converter Vendor shall advise the percentage of current harmonics over the full range of frequencies. Filters shall be fitted within the converter to minimise harmonic currents. 6.4.0 The converter shall incorporate a programmable microprocessor based control system allowing updating / modifying of the logic functions of the converter by a simple programme procedure using a control panel keypad/ and panel display. 6.5.0 The converter shall be provided with self-check facilities including failure reporting and signalling. The programme shall be protected against loss of supply voltage with back-up for the programme memory and the fault diagnostic and indication shall be equipped with a memory function to retain information with regard to tripping of the Converter. FACT ENGINEERING AND DESIGN ORGANISATION 00FT001 ENGINEERING SPECIFICATION ELECTRICS FOR TURNKEY INSTALLATION 13ES924/14 Page 4 of 10 6.6.0 If requested in the requisition, the converter shall be able to communicate with a remote control/diagnostic system by means of a serial communication interface 6.7.0 The converter shall accurately control the driven equipment speed and torque of any standard induction motor and shall be suitable for pump, fans, mixers, agitator applications etc., as specified in the requisition. 6.8.0 A reference signal of 4mA shall correspond with the minimum operational speed and the reference signal of 20mA shall correspond with the maximum speed. 6.9.0 The Variable Speed Drive System shall be capable of running through voltage dips of up to 20% and equipped with an automatic restart facility which will restart the system with voltage dips greater than 20% less than 4 seconds. Restart shall only take place with voltage recovery greater than 90%. Upon restart the converter shall be capable of synchronising onto rotating motor “flying restart” and develop full acceleration torque. 6.10.0 If the speed exceeds 105% of the maximum operational speed the VSDS shall trip, if the speed reduces to 95% of minimum speed for more than 10 seconds the VSDS shall trip. The converter shall have available critical speed function where it is necessary to avoid certain speeds due to mechanical resonance problems. 6.11.0 Speed control will be carried out either manually for maintenance, or automatically via 4-20mA signal from the process control. 6.12.0 Depending on operational requirements the motor start/stop will be either carried out manually by push buttons or automatically via the process control system. 6.13.0 Emergency stop located at each motor shall trip the supply contactor, removal of power by an emergency shall not cause damage. All stop buttons shall operate at all times. 6.14.0 When the converter is switched on, the drive shall breakaway at a minimum frequency consistent with the slip of the motor. Once motor rotation is established the drive shall ramp up to the set point speed at a controlled rate. Set point speed having been established, change of set point speed shall also be at a controlled rate superimposed on the rate of change demanded by the operator or controller. 6.15.0 During all starting operations, the rate of increase of torque, up to the maximum limited by the protection, shall also be at a controlled rate. The drive shall be suitable for a "windmilling" start with the motor being rotated by the driven equipment in either direction. 6.16.0 Programmable converter relay outputs shall be included with volt free contacts for control and alarm functions. 6.17.0 VFD’s shall comply with IEEE 519 for total harmonic distortion calculation and measurement. If harmonic filters are required to meet this specification, the VFD manufacturer must provide the filter and is fully responsible for the design, manufacturing and installation of the filter as an integral part of the VFD package. 6.18.0 The variable frequency drive shall provide near sinusoidal voltage and current waveforms to the motor at all speeds and loads. Output current THD shall be less than 5%. Standard induction or synchronous motors shall not require derating or upgraded turn-to-turn insulation and shall not require additional service factor. 6.19.0 Variable frequency drive induced torque pulsations to the output shaft of the mechanical system shall be less than 1% to minimize the possibility of exciting a resonance. 7.0.0 M.V. SWITCHBOARDS / MOTOR CONTROL CENTRES (M.C.C.) FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 13ES924/14 Page 5 of 10 7.1.0 The control gear for all Medium Voltage loads shall be housed in centralized MCC's installed in a suitably located electrical room. 7.2.0 MCC's shall be rated for minimum 25 MVA symmetrical fault level with switch fuse/ MCCB incomers and shall conform to the following stipulations: 7.2.1 Number of MCCs shall be selected in such a way to limit the incomer rating to 630 Amps, unless otherwise specified in the Data Sheet. 7.2.2 MCC shall be of self-standing, dust, damp and vermin proof construction in fully compartmentalized cubicle type execution. The MCC shall be single / double front, draw out / non draw-out type as specified in Data Sheet. The enclosure shall be of folded sheet steel construction. Thickness of sheet steel shall not be less than 2 mm except for certain non load bearing members like instrument mounting plates, partitions, doors, etc. for which a minimum thickness of 1.6 mm shall be ensured. 7.2.3 The construction of MCC shall be in such a way that each vertical row of modules shall have separate vertical bus bars, vertical bus bar chamber and cable alleys. The width of the cable alley shall be sufficient to accommodate all the cables and shall have free access for cable terminations and in any case shall not be less than 150 mm. 7.2.4 For draw out type MCC the following stipulations shall also be adhered to: (i) Power and control contacts shall be of fully draw out, self aligning type which get automatically disconnected when the module is withdrawn. A distinct and stable “TEST” position for each module shall be provided. Test push button for checking the control circuitry shall be provided, if specified in Data Sheet. Identical feeder types shall be interchangeable with each other. Also all modules shall carry labels identifying KW rating & type of control wiring. Necessary earthing arrangements shall be provided for the draw out module in TEST and SERVICE positions. (ii) (iii) (iv) 00FT001 ELECTRICS FOR TURNKEY INSTALLATION 7.2.5 The bus bar supports shall be of non-hygroscopic glass reinforced plastic material with anti-tracking features. 7.2.6 Bus bars shall be provided with insulating sleeves and bus bar joints shall be shrouded. 7.2.7 MCC including dropper bus bars to each module shall be rated for the minimum symmetrical short circuit level of 25 MVA at 415V. 7.2.8 MCC shall be provided with incoming feeders comprising of suitably rated AC 22 duty switch fuse units/ Moulded Case Circuit Breakers, voltmeter with 3 way and off selector switch & fuses (connected on the incoming cable side) , CT fed ammeter with necessary CTs & 3 way and off selector switch and CT operated KWh meter. CTs & meters shall be of accuracy class 1.5 and meters shall be of size 96mm x 96mm. 7.2.9 Outgoing motor starter feeders shall comprise of suitably rated AC 23 duty load break switches/MCCBs, HRC fuses, 100% capacity AC 3 category Air break contactors and bimetal overload relays. Feeder switches shall have AC 23 rating corresponding to the full load current of the motors connected. Rating of load break switch shall not be less than the rating of the HRC fuses. 7.2.10 The bi-metal overload relays shall be manual / auto reset type as specified in the data sheet. For manual reset type, reset push button shall be provided on the door. These relays shall have single phasing protection feature. If built-in feature is not available, separate current operated type single phasing preventor shall be provided. 7.2.11 Overload relays for motor of blowers, fans, agitators, compressors, crushers & mills shall be of heavy-duty - delayed action type to allow more starting time. FACT ENGINEERING AND DESIGN ORGANISATION 00FT001 ENGINEERING SPECIFICATION ELECTRICS FOR TURNKEY INSTALLATION 13ES924/14 Page 6 of 10 7.2.12 Ammeters shall be provided for outgoing feeders, if so specified in the Data Sheet. 7.2.13 CTs of ratio and VA capacity suitable to connect remote ammeters (in one phase) shall be provided for all motor feeders of 15 kW and above unless otherwise specified in the Data Sheet. Secondaries of these CTs shall be of 1A rating. Minimum VA capacity shall be 7.5 and class of accuracy 1.5 unless otherwise specified in Data Sheet. 7.2.14 Control supply for the motor starters shall be 110V AC, 50 Hz, single phase AC unless otherwise specified in Data Sheet. In case of 240 V control supply, each circuit shall be provided with individual control fuses and links. 7.2.15 For control voltages less than 240 volts separate control transformers (cast resin insulated type) for each modules or common for each bus section shall be provided as specified in the Data Sheet. In case common control transformer for each bus section is envisaged, it shall have adequate capacity and provisions to feed entire control loads of both bus sections of switchboard, when required. The control transformer shall have +5% taps on primary side and with center tap of secondary winding earthed & having fuse protection on primary side and double pole MCB on secondary side. Common control transformers shall also have suitable switch fuse unit on primary side and additional tapping of +2.5% on secondary side. It shall be ensured that control supply of each feeder gets isolated automatically when power supply to that particular feeder is switched off. 7.2.16 If anti-condensation heaters are provided for motors, provision shall be made to feed the same through isolator with HRC fuse protection/ MCB and NC contact of Main contactor of respective motor starter. 7.2.17 All power and control fuses shall be of the HRC link type, with operation indicators. 7.2.18 In each motor feeder module, at least one Normally Open and one Normally Closed auxiliary contact shall be wired up to the terminal block as spare. The terminal block shall have at least 10% spare terminals, subject to a minimum of two. 7.2.19 All feeders controlled by contactors shall be provided with OFF buttons. Indicating lamps and Reset button shall be provided, if specified, in the Data Sheet. 7.2.20 Providing pressure switches, limit switches, safety switches etc. wherever required for the safety of the equipment and facilitating interlocking shall be the responsibility of the supplier. Interlock defeat switches, as required shall be provided on the control panel (where such panels are provided) or on local control station near the motor and not on the MCC. 7.2.21 All outgoing switch fuse feeders shall be provided with AC 22 load break switch, HRC fuses and neutral link. 7.2.22 The incomer switch fuse unit shall have single phasing annunciators wired up to a terminal block, if so specified in the Data Sheet. 7.2.23 In MCCs having two incomers each shall be of 100% capacity. between incomers / bus coupler to prevent paralleling. 7.2.24 Facility shall be provided for padlocking feeder switches in the OFF position. 7.2.25 Necessary switch-to-door interlock shall be provided in all compartments so that the door of a compartment can be opened only when the switch is in OFF position. 7.2.26 Space heater/ anti condensation heaters (suitable for 240 V, single phase AC) shall be provided for each vertical panel if so specified in the Data Sheet. For double front MCC's space heaters shall be provided on both fronts. Space heaters shall be controlled through isolator with HRC fuse protection / MCB, thermostat etc. FACT ENGINEERING AND DESIGN ORGANISATION Interlocks shall be provided 00FT001 ENGINEERING SPECIFICATION ELECTRICS FOR TURNKEY INSTALLATION 13ES924/14 Page 7 of 10 7.2.27 Continuous earth bus of 70 sq. mm. bare Copper Conductor, or 120 sq. mm. bare Aluminium conductor or 240 sq. mm. GI strip or as specified in the Data Sheet shall be provided for the entire length of the MCC. Duplicate earth terminals shall be provided for external connection. 7.2.28 Maximum allowable current density for bus bar sizing shall be 1.25 Amps/ sq. mm for copper or 0.78 Amps /sq. mm for Aluminium. 7.2.29 Horizontal busbars shall be of uniform cross section throughout the length of the switchboard. Vertical busbars of all vertical panels of the switchboard shall also be of uniform cross section. 7.2.30 Power wiring shall be carried out with PVC insulated, stranded copper / aluminium conductors of 650 Volts grade having adequate current carrying capacity. Minimum size of conductor for power wiring shall be 4Sq.mm copper. Control wiring shall be carried out with 650 V grade, PVC insulated, copper conductor of size not less than 2.5 Sq.mm. 7.2.31 For draw out MCC, provision of control supply in the test position of draw out modules shall be available. In draw out switchboards with module control supply, required test control supply feeder (complete with switch fuse/ and test control supply transformer with double pole MCB on secondary, centre tap of secondary winding earthed, etc. as in clause 6.2.15 above), associated test supply bus / wiring, etc. shall be provided. 7.2.32 The feeder arrangement shall be such that the operating height (ie. operating handle, switches, push buttons, etc.) lies within 1828 mm, but above 300mm, from the floor level. 7.3.0 MOULDED CASE CIRCUIT BREAKERS 7.3.1 Where moulded case circuit breakers are used for feeder circuit protection, rating and characteristics shall be chosen in such a way as to ensure proper discrimination with other upstream and downstream protective devices within the assembly. 7.3.2 The MCCB should be current limiting type with trip time of less than 10 milli second under short circuit conditions. The MCCB should be either 3 or 4 poles as specified in data sheet. 7.3.3 MCCB shall comply with the requirements of the relevant standards IS13947 – Part 2 and should have test certificates for Breaking capacities from independent test authorities CPRI / ERDA or any accredited international lab. 7.3.4 MCCB shall comprise of Quick Make -break switching mechanism, arc extinguishing device and the tripping unit shall be contained in a compact, high strength, heat resistant, flame retardant, insulating moulded case with high withstand capability against thermal and mechanical stresses 7.3.5 The breaking capacity of MCCB shall be as specified in the schedule of quantities. The rated service breaking capacity (Ics) should be equal to rated ultimate breaking capacities (Icu). MCCB’s for motor application should be selected in line with Type-2 Co-ordination as per IS 13947-2. The breaker as supplied with ROM should meet IP54 degree of protection. 8.0.0 LOCAL CONTROL STATIONS 8.1.0 Each motor shall be provided with a local control station near motor. The enclosure shall be of Cast Iron or Cast Aluminium construction with IP-55 / IPW 55 degree of protection, as specified in the Data Sheet. 8.2.0 Local control stations for M.V motors shall be provided with ‘ON’ push button (Green) and 'OFF' push button (Red). 8.3.0 Local control station for H.V Motors shall be provided with 'ON' push button (Green), 'OFF' push button (Red), Ammeter and five numbers Indication lamps. (viz 'ON'-Red , 'OFF'-Green, 'Tripped on fault' - Amber, 'Ready for start' -Clear, 'Space heater ON' - Yellow.). FACT ENGINEERING AND DESIGN ORGANISATION 00FT001 ENGINEERING SPECIFICATION ELECTRICS FOR TURNKEY INSTALLATION 13ES924/14 Page 8 of 10 8.4.0 For all motors of 15 kW and above or as specified in Data Sheet, suitable ammeters shall be provided in the local control stations. Ammeters shall have an accuracy class of 1.5 unless otherwise specified in Data Sheet and shall have a suppressed end scale to suit the starting current. 8.5.0 The OFF push button shall be lockable with a pad-lock in pressed 'OFF' position. 8.6.0 If starting of motors / equipment are envisaged from more than one location or Auto / manual operation is envisaged, necessary Local - Remote or Auto-Manual switches shall be provided either in the Local Control Station or in the Instrument Control panel, if any. Stop facility shall be available from any location irrespective of the position of selector switches. 8.7.0 All spare contacts shall be wired up to the terminal block. The terminal block shall have 10% spare terminals subject to a minimum of two. 8.8.0 Nameplates in white perspex acrylic sheet with letters engraved in black shall be provided for each control station indicating the service. 8.9.0 Circuit breaker contactors controlling motor feeders shall have rating at least 125% of the maximum continuous rating of connected motors. 9.0.0 CABLES AND CABLING. 9.1.0 All power cables shall be PVC insulated, armoured and PVC sheathed with Aluminium conductor unless otherwise specified in Data Sheet. 9.2.0 All control cables shall be PVC insulated, armoured and PVC sheathed with Copper conductor .The control cable shall be laid segregated from the power cables. 9.3.0 The sizes of cables shall be so chosen that they are rated to carry the full load current continuously after allowing for necessary derating factors for the service conditions of installation, and also that the voltage drop in cables does not exceed 3% for full load running. For motor starting, voltage drop up to 15% shall be permitted. 9.4.0 M.V power cables of 400 sq mm and above shall be laid with a clearance of 70 mm in between and shall be clamped individually. Other cables can be laid touching and clamped in groups. 9.5.0 Cables shall be clamped at every 1500 mm interval on the horizontal trays / racks and at 750 mm interval on the vertical trays / risers, at 400 mm interval for cables laid on walls, columns and other structural works, and at bends and take off points. 9.6.0 A clearance equal to one diameter of the bigger cable shall be maintained between two adjacent power cables buried underground and no such clearance need be provided for control and lighting cables. 9.7.0 All fixing materials shall be given coatings of anticorrosive paint. Cable tags made of Aluminium sheet shall be provided at every 10M interval. The purchaser will furnish the identity numbers of cables after submission of the cable schedule by the supplier. All the cable racks in trenches and overhead structure shall be bonded for continuity. 9.8.0 Selection of the size of cables for motors shall be done from the table indicated in the Data Sheet. However, higher sizes may be used if warranted by voltage drop consideration in individual cases. 9.9.0 Wherever cables pass through masonry or concrete work, they shall be taken through suitable PVC / GI pipes. For road crossing suitable GI or concrete pipe shall be provided. 9.10.0 After drawing the cables in GI / PVC pipes, the ends shall be sealed with cable compounds. 9.11.0 The size and minimum number of cores in control cables shall be as specified in the Data Sheet. FACT ENGINEERING AND DESIGN ORGANISATION 00FT001 ENGINEERING SPECIFICATION ELECTRICS FOR TURNKEY INSTALLATION 13ES924/14 Page 9 of 10 9.12.0 Type of cabling shall be overhead / buried in ground / through pipes / through permanently constructed trenches with RCC / CI chequered plate covers as specified in Data Sheet. 10.0.0 EARTHING. 10.1.0 All electrical equipment shall be provided with duplicate earthing in conformity with relevant standards / regulations applicable. The main earth bus shall be of bare / insulated aluminium or copper or galvanized iron strip as specified in the Data Sheet and earthing of individual equipment shall be done with conductors of type, sizes & material specified in the Data Sheet. 10.2.0 Earthing cables / strips shall be taken along with the power cables on the cable trays / racks / risers / GI pipes / non-metallic pipes or buried. Earthing cables shall be clamped at intervals same as that of power cables. Bare earthing strips shall be clamped at 3000 mm interval on horizontal trays / racks, 1500 mm interval on vertical trays / risers, 800 mm interval on walls, columns, and at bends / take off points. 10.3.0 Metallic cable trays / risers shall be earthed at both ends. Electrical continuity of earthing throughout the tray shall be ensured. 10.4.0 Earthing of equipment, vessels, pipe lines etc. if required towards protection against static electricity, shall be done in conformity with relevant standards / regulations applicable. 10.5.0 Earthing system for protection of building and structures against lightning shall be provided if so specified in Data Sheet in conformity with relevant standards / regulations applicable. 11.0.0 SAFETY ITEMS 11.1.0 Safety items required as per statutory regulations such as danger notice plates, rubber mat in front of switch boards, fire extinguishers, resuscitation charts and fire buckets shall be supplied by the vendor, if specified in Data Sheet. 12.0.0 HAZARDOUS AREA CLASSIFICATION FOR SELECTION OF ELECTRICS. 12.1.0 All electrics and their installation shall be suitable for the hazardous/ Non-hazardous area involved and / or specified in the Data Sheet. Electrics suitable for the hazardous area involved shall be selected as per the relevant Indian Standards and shall be of proven design approved by CIMFR / relevant statutory bodies. In such cases copies of relevant certificates shall be furnished for Purchaser’s approval. 13.0.0 ERECTION, TESTING AND COMMISSIONING. 13.1.0 Supply of all erection materials required for the erection of electrical equipments supplied by vendor shall be the responsibility of the vendor. These items shall include all accessories for cable-jointing, cable terminations/ cable tray/ racks, supporting steel structures, pipes, clamps, bricks, sand, cement, rubble, compression type cable glands, insulating materials etc. Necessary grouting, fixing etc. also shall be arranged by the vendor. 13.2.0 It shall be the responsibility of the vendor to supply and install all items that are incidental and necessary for the completion of the installation, whether specifically mentioned or not, so that the installation complies with relevant standards and regulations, at no extra cost to the purchaser. 13.3.0 Commissioning works includes all precommissioning tests, checking of all power, control & earthing connections, testing and commissioning of all equipment / system supplied, erected and / connected by the vendor, as per relevant standards and as directed by purchaser. 13.4.0 The electrical installation work shall be carried out only through a contractor possessing valid and competent electrical contractors license issued by the State Electricity Licensing Board for carrying out electrical installation work in the place of installation. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION ELECTRICS FOR TURNKEY INSTALLATION 13ES924/14 Page 10 of 10 All equipments which do not come under a roof shall be provided with weather proof features, and be suitably protected using hoods /canopies 14.0.0 APPROVAL FROM ELECTRICAL INSPECTORATE. 14.1.0 It shall be the responsibility of the vendor to ensure that the complete installation supplied and / or erected by him fully meets with relevant standards / Acts / rules / Regulations applicable and duly got approved by statutory authorities like Electrical Inspectorate. 14.2.0 Any modifications / rectification required by the owner / Electrical Inspectorate resulting from improper installation by the vendor or to make the same in full conformity with the relevant standards / Rules / Acts / Regulations applicable for the installation shall be carried out by the vendor without any extra cost to the purchaser. 15.0.0 LIGHTING. 15.1.0 If lighting is included in the scope of the vendor, the same shall conform to specifications for the lighting installation attached. 16.0.0 MAKE OF ELECTRICAL EQUIPMENT / ITEMS 16.1.0 Make of Electrical equipment / items shall be as specified in Data Sheet / Sub vendor list attached. 16.2.0 Approval shall be got from the Purchaser for the individual makes of the different electrical items, wherever makes are not specified in the Data Sheet, before placement of purchase order. 00FT001 13.5.0 FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION ELECTRICS FOR TURNKEY INSTALLATION -DATA SHEET 32644-13-DA-92401 Page 1 of 5 1.0 Power supply voltage (clause 4.2.0/ 4.3.0) 1.1 All Electrics shall be suitable for corrosive atmosphere due to the presence of acid 2.0 MOTORS 2.1 Scope of supply of vendor (clause 5.1.0) 2.2 kW range and voltage ratings of motors (clause 5.2.0) R0 1. 415V± 10%, 50 Hz ±5%, 3 Phase & neutral AC at the substation Squirrel cage induction motors –energy efficient –class IE3 a) Type of motor Squirrel cage induction motor –energy efficient b) Motors of rating upto and including 150kW 415V ± 10%, 50 Hz ±5%, 3 Phase AC c) Motors of rating above 150kW upto and including 1000 kW 3.3kV ± 10%, 50 Hz ±5%, 3 Phase AC 2.3 Class of Insulation (Clause 5.2.2) Class F with temperature rise limited to Class B 2.4 Degree of Protection (Clause 5.2.2) a) IP55 for Indoor b) IPW55 weatherproof for Outdoor 2.5 Enclosure for (Clause 5.2.2 a) Non Hazardous area Shall be suitable for corrosive atmosphere(phosphoric acid) b) Hazardous area NA 2.6 Anti condensation heaters (Cl. 5.2.3) Required for motors of rating 37 KW & above 2.7 Method of Starting (Clause 5.2.5) Direct On Line or VFD as per the process requirement 2.8 Number of Starts (Cl. 5.2.6) 2.9 a) Number of consecutive cold starts 3 b) Number of consecutive hot starts 2 c) Number of equally spaced starts/hr. 4 Fault withstand time at terminal box 50kA a) Starting Current (Cl. 5.3.1) As per IS b) Main terminal box (Phase segregated) (Cl. 5.3.2) Required c) Star terminal box (Cl. 5.3.2) Not Required d) Zero speed switches for motors of high starting time required. (Cl. 5.3.2) e) Winding temperature detectors (Cl. 5.3.3)RTD Not Required f) Bearing Temperature detectors (Cl. 5.3.3) RTD Not Required PROJECT Phosphoric Acid Tank CLIENT M/s.FACT-CD 13FT924A/14 P.O. NO. 0 08-06-‘20 SM IK IK REV. DATE PRPD. CHKD. APPRD. VENDOR FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION DATA SHEET g) Oil temperature detectors (Cl. 5.3.3) Not Required h) Oil level indicator (Cl, 5.3.3) Not Required i) Temperature scanner / Monitoring relays with alarm and trip contacts for winding/bearing RTD Not Required j) Foundation bolts for motors Required 32644-13-DA-92401 Page 2 of 5 R0 3.0 MV SWITCHBOARDS / MOTOR CONTROL CENTRES (MCC) 3.1 Incomer rating 200A MCCB 3.2 Number of Incomers in each MCC One (one from Client’s switchboard at substation) Multi-Function meters shall be provided for incomer. 3.3 Enclosure IP 52 3.4 Number of Bus coupler in each MCC - 3.5 Type of MCC (Clause 6.2.2) a) Single front b) Draw out 3.6 Cable entry Bottom 3.7 Material of Bus bars PVC sleeved Aluminium/ Copper 3.8 Test Push Button (Cl. 6.2.4) Not Required (but test facility for control circuit required) 3.9 Type of overload relay reset (Clause 6.2.10 & 6.2.19) Thermal overload(bimetal) relay -manual with reset button. CT operated motor protection relay shall be provided for motor feeders 22kW and above 3.10 Ammeters for outgoing feeders (Clause 6.2.12) 3.11 13FT924A/14 ELECTRICS FOR TURNKEY INSTALLATION a) For Switch fuse/ MCCB feeders Not Required b) For motor feeders Required Current transformer for remote ammeter (Cl.6.2.13) a) For motor feeders Required for motors of rating 15kW and above b) Class of Accuracy 1.5 3.12 Control supply (Cl. 6.2.14) 110V AC 3.13 Control voltage Transformer (Cl. 6.2.15) Required for each module 3.14 Indication lamps on Motor feeders (Clause 6.2.19) a) Motor ON (red) Required b) Motor OFF (Green) Required c) Overload Tripped (Amber) Required d) Voltage rating for indication lamps 110V AC, with LED lamps. 3.15 Short circuit rating of MCCB 50KA for 1 sec 3.16 Single phasing annunciator for incomer (Cl. 6.2.22) Thermal bimetallic overload relays provided for motor feeders shall have integral / built in single phasing preventing feature 3.17 Panel anti-condensation heaters (Clause 6.2.26) Required FACT ENGINEERING AND DESIGN ORGANISATION ELECTRICS FOR TURNKEY INSTALLATION TECHNICAL PROCUREMENT SPECIFICATION DATA SHEET 32644-13-DA-92401 Page 3 of 5 R0 3.18 Earth bus for MCC(Clause 6.2.27) Suitable for 50kA/1sec 3.19 Other requirements 3.20 Type of motor starter 1) Outgoing feeders as required for the acid pumping system including lighting and one numbers welding socket outlets. Spare feeders minimum one number for each rating shall be provided. All out going feeders shall be SFU type. DOL type. SFU shall be provided for all motor feeders as overload protective device. Type of co-ordination between contactor, overload protective device and short circuit protective device shall conform to Type II as per relevant standards. ON,OFF and trip indications of pumps shall be made available at the existing control room. Note: Incomer feeder for the MCC shall be made available by the client at the outgoing feeder of existing MV switch board located in the substation building.MCC for phosphoric acid tanks shall be located in heavy equipment work shop building. Cables and cabling from substation building to Heavy equipment workshop shall be included the scope of work of contractor. 4.0 LOCAL CONTROL STATIONS (Required for motors ) 4.1 Material of construction (Clause 7.1.0) 4.2 Enclosure and degree of protection (Cl. 7.1.0) Cast Aluminium a) Non Hazardous IP 55 weather proof for outdoor b) Hazardous NA 4.3 Ammeter (Cl. 7.4.0) Required for motors rated 15KW and above 4.4 Accuracy class (Cl.7.4.0.0) Class 1.5 4.5 Local/Remote selector switch shall be provided 4.6 Indication lamps – cluster type LED lamps Not required 4.7 Foundation bolt for LCS Required 5.0 CABLES & CABLING 5.1 Type of cable and material of conductor (Cl. 8.1.0 & 5.2.4) a) Power cables - MV Aluminium conductor with XLPE insulated ,PVC inner sheathed,armoured PVC FRLS outer sheathed for cable sizes above 4sqmm. Cable sizes 4sqmm and below shall be Copper conductor, XLPE insulated, PVC inner sheathed armoured PVC FRLS outer sheathed as per IS:7098 b) Control cables Copper conductor with XLPE insulation, PVC inner sheathed, armoured, PVC outer sheathed FRLS type as per IS:7098 All cables for Instrumentation interface shall be stranded 1.5Sq.mm copper cable. 13FT924A/14 5.2 Table of minimum cable sizes of Power cables (Cl. 8.8.0) Vendor shall provide adequate cable sizes to limit the running voltage drop to 3%).Sizes indicated are for Aluminium cables .Equivalent size of copper cable can be provided. Motors ≤ 3.7 kW 1 # of 3 x 4 sq.mm Cu Motors>3.7kW ≤7.5 kW 1 # of 3 x 6 sq.mm .Al Motors>7.5kW ≤11 kW 1 # of 3 x 10 sq.mm Motors>75kW ≤90 kW 1 # of 3 x 240 sq.mm Motors>11kW ≤15 kW 1 # of 3 x 16 sq.mm Motors>90kW ≤110 kW 1 # of 3 x 300 sq.mm FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION 5.3 5.4 ELECTRICS FOR TURNKEY INSTALLATION DATA SHEET 13FT924A/14 Page 4 of 5 R0 Motors>15kW ≤22 kW 1 # of 3 x 25 sq.mm Feeders 32A 4 x 10 sq.mm Al. Motors>22kW ≤30 kW 1 # of 3 x 35 sq.mm Feeders 63A 3.5 x 35 sq.mm Al Motors>30kW ≤37 kW 1 # of 3 x 50 sq.mm Feeders 100A 3.5 x 70 sq.mm Al. Motors>37kW ≤45 kW 1 # of 3 x 70 sq.mm Feeders 200A 3.5 x 240 sq.mm Al. Motors>45kW ≤55 kW 1 # of 3 x 95 sq.mm Feeders 250A 3.5 x 400 sq.mm Al. Motors>55kW ≤60 kW 1 # of 3 x 150 sq.mm Feeders 400A 2RX3.5 x 240 sq.mm Al. Motors>60kW ≤75 kW 1 # of 3 x 185 sq.mm Feeders 800A 4RX3.5 x 400 sq.mm Al. Minimum sizes of control cables (Cl. 8.11.0) a) Size in sq.mm 2.5 b) Minimum No. of cores for MV Motors (for LCS) As reqd. with 1 core, spare c) Minimum No. of cores for HV Motors ( for LCS) - d) Interlock/ Interconnection cables to control panels/ eqpt etc. Upto 7 core – 1 core spare, More than 7 core – 2 cores spare Type of cabling (Cl. 8.12.0) a) MV equipment 1) Cabling inside substation building through over head GRP cable trays. 2) 6.0 EARTHING 6.1 Main incoming earth bus (Cl. 4.3.0) 6.2 Plant main earth bus if any (Cl. 9.1.0) 6.3 Equipment earthing (Cl. 9.1.0)-Type & material 6.4 Equipment earthing (Cl. 9.1.0)-Table of minimum sizes 6.5 32644-13-DA-92401 MCC / Switchboards, fuse/ current limiting type MCCB protected 2R 120sq.mm Al. cable Motors ≤ 30KW & local control stations 2Rx16 sq.mm Al Motors >30KW, ≤37KW 2Rx35 sq.mm Al Motors >37KW, ≤55KW 2Rx50 sq.mm Al Motors >55kW, ≤65kW 2Rx 70Sq.mm Al Motors>65kW, ≤75kW 2Rx120Sq.mm Al Motors rated 75 KW and above 2Rx150Sq.mm Al Size of static earthing minimum (Cl. 9.4.0) Cabling outdoor area - through over head GRP cable trays where pipe bridges/supports are available.Cables shall be laid through GI pipes in paved area.In other area where pipe bridges are not available cables shall be laid through buried trenches.RCC hume pipes shall be provided for road crossings * Vendor to furnish Static Earthing of Process equipment/Tanks 16 sq mm Aluminium cable FACT ENGINEERING AND DESIGN ORGANISATION 1Rx120Sq.mm Al cable. TECHNICAL PROCUREMENT SPECIFICATION 6.6 ELECTRICS FOR TURNKEY INSTALLATION DATA SHEET Lightning protection (Cl. 9.5.0) 32644-13-DA-92401 Page 5 of 5 R0 - Two numbers of earth pits( Maintenance free copper bonded earthing electrodes approved by Kerala state Electrical Inspectorate, comprising of 3 m long, dia. not less than 17 mm, earth electrode of low carbon steel with 250 micron copper bonding on outer surface and having terminals to connect the conductor) shall be provided for earthing MCC . Local Control stations ,drive motors ,Junction boxes etc shall be earthed in duplicate and shall be connected to earthing system . All steel structures, tanks, vessels, pipes, pipe joints, valves etc. shall be earthed against static charge accumulation. Separate earth pits shall be provided for tank earthing .Inter connection of earth pits 13FT924A/14 with the nearest existing earth pit at two points shall be carried out with 150sq.mm PVC covered Al. cable 7.0 SAFETY ITEMS (CLAUSE 10.0.0) 7.1 Danger Notice plates Required 7.2 CO 2 Fire Extinguisher (4.5kg) Required 7.3 Insulation mat in front of MCC/ switchboards 1.1 kV grade insulation mat as per IS 15652:2006 of thickness not less than 2.5 mm and 1000 mm width shall be provided 7.4 Fire buckets ( 1 gallon) - 7.5 Resuscitation charts Required 8.0 Area Classification (Cl. 11.0.0) Safe area 9.0 Weatherproof protection (hood) for outdoor equipment (Clause 12.5.0) Motors & PB stns. Required with Aluminium sheet 10.0 Responsibility of getting approval from Electrical Inspectorate (Cl. 13.1.0) Vendor shall be responsible for getting approval from Electrical Inspectorate(CEA) 11.0 Lighting (Clause 14.0.0) Well glass , acid resistant ,weather proof LED type light fittings shall be provided at srairs and hand rails of tanks. Weather proof ,acid resistant LED type flood light fittings shall be provided at the top of the tanks for illumination of dyke wall area and nearby roads . 12.0 Painting (Deviations if any on those specified in 13ES900) Epoxy painting 13.0 MAKE (Cl. 15.0.0) Refer sub vendor list (Electrical) 14.0 OTHER REQUIREMENTS FACT ENGINEERING AND DESIGN ORGANISATION ELECTRICS FOR TURNKEY INSTALLATION TECHNICAL PARTICULARS 1.0 MOTORS 1.1 Make 1.2 Equipment No. / Name 1.3 Type of Motor 1.4 Motor rating 1.5 Speed in RPM (Syn.) 1.6 Frame size 1.7 1.9 Class of Insulation Enclosure, Degree of Protection & Type of cooling Direction of rotation 1.10 Full load current (Amps) 1.11 Starting Current (%FLC) 1.12 Slip (Percentage) at Full load 1.13 Efficiency (%) and power factor 1.8 32644-13-TP-924-01 Page 1 of 6 a) At full load b) AT ¾ load c) At ½ Load 1.14 Locked rotor withstand time a) Hot (seconds) b) Cold (seconds) 1.15 Starting time of motor on DOL with driven equipment coupled a) At 100% voltage 1.16 1.17 b) At 80% voltage Minimum voltage required for starting with the equipment and corresponding starting time Allowable number of starts with driven equipment coupled a) Consecutive cold starts b) Consecutive Hot starts 1.19 c) Equally spaced starts/Hr. Guaranteed temperature rise under worst conditions of voltage and frequency Speed Vs. Torque curve 1.20 Current Vs. time curve 1.21 Current Vs. Speed curve Thermal withstand characteristics (hot & cold) Start withstand time 1.18 1.22 1.23 PROJECT Phosphoric Acid tank CLIENT M/s.FACT-CD P.O. NO. VENDOR 13FT924B/14 REV. DATE PRPD. CHKD. APPRD. FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PARTICULARS ELECTRICS FOR TURNKEY INSTALLATION a) Hot (seconds) 1.25 b) Cold (seconds) Margin between starting time and locked Rotor withstand time hot (Clause 5.3.1 of 13ES924) CIMFR Certificate (for Flame-proof motors) 1.26 Bearings 1.24 a) Drive end bearing No. & type b) Non-drive end bearing No. & type c) Make of bearings 1.27 Lubricant a) Make b) Type c) Lubrication Schedule of motor 1.28 Weight of Motor 2.0 LOCAL CONTROL STATIONS 2.1 Maker’s Name 2.2 Works at which units will be fabricated 2.3 Material of construction 2.4 Enclosures & Degree of protection 2.5 Technical details, leaflets etc 2.6 Standards applicable 2.7 Ammeter range & Accuracy class 2.8 CIMFR certificate for flame proof equipment 2.9 Type of Local control stations 3.0 CABLES 3.1 Make 3.2 Type & Material Power Cable Control cable 3.3 Standards applicable Power cable 13FT924B/14 Control cable 4.0 EARTHING CONDUCTORS 4.1 Make 4.2 Type & Material 4.3 Standards applicable 5.0 OTHER DETAILS FACT ENGINEERING AND DESIGN ORGANISATION 32644-13-TP-924-01 Page 2 of 6 TECHNICAL PARTICULARS ELECTRICS FOR TURNKEY INSTALLATION 6.0 MOTOR CONTROL CENTRES 6.1 Number of MCCs 6.2 Incomer Rating 6.3 Maker’s name 6.4 Works at which the boards will be fabricated 6.5 Type of switchboards 6.6 Max. Temperature rise over ambient 6.7 Sizes of phase and neutral bus bars of the following ratings along with supporting calculations a) 100A b) 200A c) 400A d) 630A 6.9 e) 800A Short time (1 sec.) rating of bus bars in KA(Rms) Type, make, ratings/range/ratios and relevant details of individual components 6.10 Technical details, leaflets and type test certificates for the following items. 6.8 a) Heavy duty type switches b) Air Break contactors (Power &Auxiliary) c) HRC link type fuses (Power and Control) d) Bus bars e) Current transformers f) Bimetallic thermal overload relays g) Meters h) Indicating lamps i) Timers 6.11 6.12 6.13 j) Single phasing annunciators Overall dimensions in mm of each switchboard Weight of each switchboard in Kg. (Dynamic loading if any shall be furnished) Material and area of cross section of conductors of a) Bus bars to switch of each rating b) Switch to fuses of each rating 6.14 13FT924B/14 32644-13-TP-924-01 Material and voltage class (grade) of insulation of above conductors if insulated FACT ENGINEERING AND DESIGN ORGANISATION Page 3 of 6 ELECTRICS FOR TURNKEY INSTALLATION TECHNICAL PARTICULARS 6.15 Motor KW/ Fdr. rating Full Load Amps Module size Type AC22 rating (A) AC23 rating (A) Page 4 of 6 COMPONENT / FEEDER DETAILS HRC Fuse Switch/MCCB 32644-13-TP-924-01 Thermal rating (A) Let through energy Contactor Type Thermal rating (A) AC3 rating (A) 1sec. Rating (A) 0.25 0.37 1.2 0.55 1.6 0.75 1.8 1.1 2.6 1.5 3.5 2.2 5.0 3.7 7.5 5.5 11 7.5 14 9.3 19 11 21 15 28 18.5 35 22 40 30 55 37 66 45 80 55 100 75 135 90 165 110 200 132 230 150 275 13FT924B/14 Switch fuse/MCCB feeder 63 100 200 250 400 630 FACT ENGINEERING AND DESIGN ORGANISATION Over load relay range (A) Size of wire used in modules Power Control Rating of terminals in Amps. Drawout Fixed Outgoing TECHNICAL PARTICULARS ELECTRICS FOR TURNKEY INSTALLATION 7.0 VARIABLE FREQUENCY DRIVES 7.1 Make 7.2 Model Number 7.3 Country of manufacture 7.4 Type of reference 7.5 Standards to which the VVFD conforms to 7.6 Weight 7.7 Drive type 7.8 Dynamic Response a) Speed fluctuation band b) Speed recovery time after 100% torque step c)Type of feed-back for speed control d)Speed control accuracy 7.10 Waveform distortion factor (% harmonics) in output / input waveform (Number of harmonics and magnitude of each harmonic generated shall be furnished) Rating expressed at (torque) 7.11 Speed control range 7.12 Overload capacity 7.13 Rating declared at (temp.) 7.14 Switching frequency at declared rating 7.15 Overload capability of converter 7.9 a) 115% In( for variable torque) for 7.16 Overall efficiency of drive (excl. motor) at a) 100% load b) 75% load c) 50% load 7.17 Overall power factor of drive (excl. motor) at a) 100% load b) 75% load 13FT924B/14 c) 50% load 7.18 Control mode 7.19 Acceleration time (Adjustable) 7.20 Deceleration time (Adjustable) 7.21 Operation mode 7.22 Speed reference signal 7.23 Braking 7.24 Frequency setting 7.25 Communication protocols 7.26 PID function 7.27 Type of power converter 7.28 Type of cooling system provided 7.29 Type of output filter provided FACT ENGINEERING AND DESIGN ORGANISATION 32644-13-TP-924-01 Page 5 of 6 TECHNICAL PARTICULARS 7.30 ELECTRICS FOR TURNKEY INSTALLATION Panel Construction a)Material of construction b)Thickness c)IP Rating 7.31 Cooling i) Type ii) Redundancy in cooling units 7.32 7.33 7.34 Panel space heater rating Maximum noise level from the drive at 1meter distance Dimensions a) Length b) Height c) Depth 13FT924B/14 d) Weight of cubicle 7.35 Earth bus 7.36 Size 7.37 Minimum fault current capacity FACT ENGINEERING AND DESIGN ORGANISATION 32644-13-TP-924-01 Page 6 of 6 ENGINEERING SPECIFICATION MEDIUM VOLTAGE SWITCH BOARDS 13ES906/14 Page 1 of 16 CONTENTS 1.0.0 2.0.0 3.0.0 4.0.0 5.0.0 6.0.0 7.0.0 8.0.0 9.0.0 10.0.0 11.0.0 12.0.0 13.0.0 14.0.0 15.0.0 16.0.0 17.0.0 18.0.0 19.0.0 20.0.0 21.0.0 22.0.0 23.0.0 24.0.0 25.0.0 26.0.0 27.0.0 SCOPE REFERENCES STANDARDS SERVICE CONDITIONS CONSTRUCTION&GENERAL REQUIREMENTS BUS BARS FEEDER ARRANGEMENT CABLE COMPARTMENTS CABLE TERMINATION WIRING INSULATION EARTHING NAME PLATE MOULDED CASE CIRCUIT BREAKERS FEEDER LOAD-BREAK SWITCHES MINIATURE CIRCUIT BREAKERS FUSES STARTER-CONTACTORS OVERLOAD RELAYS CURRENT TRANSFORMERS RELAYS CONTROL TRANSFORMERS INDICATING INSTRUMENTS INDICATING LAMPS, PUSH BUTTONS, CONTROL SWITCHES, ETC ANTI-CONDENSATION HEATERS DRAWOUT SWITCHBOARDS MEDIUM VOLTAGE CIRCUIT BREAKERS 1.0.0 SCOPE 1.1.0 This specification covers the general requirements for design, manufacture, testing and supply of Medium Voltage Switch boards like Power Control Centres (PCC), Motor Control Centres (MCC), Power cum Motor Control Centres (PMCC), Auxiliary switch boards, Lighting Switchboards, etc. 2.0.0 REFERENCES 2.1.0 Following documents shall be read in conjunction with this specification: 2.1.1 Engineering specification and Data sheet of General requirements for Electrics 2.1.2 Data sheet of Medium Voltage Switchboards 2.1.3 Technical Particulars of Medium Voltage Switchboards 3.0.0 STANDARDS 3.1.0 Requirements laid down in the latest revisions of the following Indian Standards and other relevant standards & regulations shall be strictly adhered to: IS: 8623(Part I) IS/IEC60947-1 IS/IEC60947-3 00FT001 PRPD.: Specification for Low- Voltage Switchgear & Control gear Assemblies Low voltage switch gear and control gear :part 1-General rules Low voltage switch gear and control gear :part 3-Switches, disconnectors,Switch disconnectors and fuse combination units CHKD.: APPRD.: ISSUED ON: SEPT 2014 FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION MEDIUM VOLTAGE SWITCH BOARDS 13ES906/14 Page 2 of 16 IS: 5578 IS: 11353 Guide for marking of insulated conductors Guide for uniform system of marking and identification of conductors and apparatus terminals IS: 10118 Code of practice for selection, installation, and maintenance of switchgear and control gear IS: 13118 Circuit breakers IS:13703 Specification of low voltage fuses for voltages not exceeding 1000V-AC or1500V-DC IS:13947:part4:sec:1 Specification for low voltage switchgear and control gear -Part 4;Contactors and motor starters-Sec-1:Electro mechanical contactors and motor starters IS: 2705 Current Transformers IS: 4201 Application guide for CTs IS: 3231 Electrical relays for power systems protection IS: 3842 Application guide for electrical relays for ac systems IS:13947:part5:sec:1 Specification for low voltage switchgear and control gear -Part 5-control circuit devices and switching elements-sec1:Electromechanical control circuit devices IS:8828 Electrical accessories- Circuit breakers for over current protection for house hold and similar installations 00FT001 IS: 1248 IS: 13010 IS: 13779 IS: 8530 IS: 14415 IS: 14390 IS: 14372 IS: 1901 IS: 2551 IS: 732 IS: 900 IS: 3043 Direct acting electrical indicating instruments A C watthour meters class 0.5,1.0 and 2.0- Specification AC static watthour meter ,class 1.0 and 2.0- specification Maximum demand indicators , class 1.0 Volt ampere hour meter for restricted power factor range- specification Volt ampere reactive hour meter, class 3.0 Volt ampere hour meter for full power factor range Visual indicator lamps Danger notice plates Code of practice for electrical wiring installations Code of practice for installation and maintenance of induction motors Code of practice for earthing 4.0.0 SERVICE CONDITIONS 4.1.0 The equipment shall be designed to operate satisfactorily at rated load under the service conditions and power supply conditions specified in the data sheet of “ General requirements for electrics” and data sheet of “Medium voltage switch boards”. 5.0.0 CONSTRUCTION & GENERAL REQUIREMENTS 5.1.0 All switchboards shall comply with the requirements of IS:8623 applicable for Low-Voltage Switchgear and control gear assemblies. 5.2.0 The switchboard shall be of folded sheet steel construction, fully compartmentalized, floor mounted, free standing type and dust, damp &vermin proof. The degree of protection shall be as specified in the data sheet. Vertical units shall be assembled to form a continuous line up of uniform height and front line up. 5.3.0 Thickness of sheet steel shall not be less than 2 mm except for certain non load bearing members like instrument plates, partitions, doors, etc. for which a minimum thickness of 1.6 mm shall be ensured. 5.4.0 Doors and openings shall be provided with neoprene gaskets. All hardware shall be corrosion resistant. 5.5.0 All doors shall be hinged at one end and shall be bolted (knob type) on other end. All hinges shall be of concealed design for elegant appearance. FACT ENGINEERING AND DESIGN ORGANISATION 00FT001 ENGINEERING SPECIFICATION MEDIUM VOLTAGE SWITCH BOARDS 13ES906/14 Page 3 of 16 5.6.0 Adequate lifting facilities shall be provided on each section. Lifting eyes may be of removable/foldable design. When removed, these shall not leave any openings on the boards. 5.7.0 All barriers used shall be manufactured from non-inflammable material. 5.8.0 Bus bars shall be housed in separate metallic compartment (horizontal bus bar chamber & vertical bus bar chamber) and shall be accessible for inspection only with special tools. 5.9.0 Individual feeder modules shall be housed in independent and separate enclosed compartments separated from each other by metallic barriers. Each vertical row of modules shall have independent vertical bus bars, vertical bus bar chambers, and cable alleys. 5.10.0 The design of the switchboard shall be such as to allow for extension of vertical panels at both the ends. The ends of the busbars shall be suitably drilled and the side covers of the horizontal bus bar chambers at extreme ends shall be provided with opening, which shall be covered with a gasketted plate screwed to the panel. 5.11.0 In the case of single front panels without rear access (as specified in the data sheet), access to all components, cable connections, bus bars, etc. shall be from the front only. 5.12.0 The equipment shall be designed to ensure complete safety during operation, inspection, connection of cables, relocation of outgoing circuits and maintenance even with the bus bar system energized. Features which prevent shorting of power and / or control terminals due to accidental dropping of maintenance tools etc., inside the switchboard shall be provided. Checking and removal of components shall be possible without disturbing adjacent components. All auxiliary equipment / components shall be easily accessible. 5.13.0 All exposed live terminals in the cable alley and incomer terminals inside modules shall be covered or shrouded to prevent accidental contact. 5.14.0 The incoming power connection shall be through bus trunking or cables as specified in the data sheet. Ample space for connection of these cables / bus trunking shall be provided. 5.15.0 For lighting and auxiliary switchboards, the neutral conductors & bus bars shall have the same current carrying capacity as that of the phase conductors & busbars. 5.16.0 Mechanical castle key interlocks and electrical interlocks shall be provided between the incomers and bus couplers to prevent paralleling of incoming feeders, if specified in the data sheet. 5.17.0 Necessary foundation bolts, nuts and washers shall be supplied along with the equipment. 5.18.0 For additional / special requirements of Drawout switch boards (non breaker panels) refer clause 24.0.0 and for requirements of Circuit breaker panels refer clause 25.0.0below. 5.19.0 Temperature rise test if specified (in Scope of inspection and tests / Data sheet), shall be conducted on one unit of each type of MV switchboard, before despatch. Test shall be conducted for the specified full load rating of the bus bars. Test shall be done for both power and neutral bus in both horizontal and vertical bus bar system. Diversity factor given in Table 1 of IS:8623 shall not be applicable. Tests shall comply with he requirements of IS:8623,Clause 8.2.1, verification of temperature rise limits. Testing procedure to be adopted shall be furnished in the bid. Bus bar o temperature rise shall be limited to 40 C. Tests shall be conducted in the presence of FEDO/ owner representatives. 6.0.0 BUS BARS 6.1.0 Busbars shall be of high conductivity aluminum/copper as specified in the data sheet. Insulating sleeves complete with necessary joint shrouds shall be provided for bus bars, if specified in the data sheet. FACT ENGINEERING AND DESIGN ORGANISATION 00FT001 ENGINEERING SPECIFICATION 13ES906/14 MEDIUM VOLTAGE SWITCH BOARDS Page 4 of 16 2 2 6.2.0 Maximum allowable current density for busbars shall be 1.25 A/mm for copper and 0.78 A/mm for Aluminium. 6.3.0 The horizontal and vertical bus bars shall be rated for the same fault level specified in the data sheet. 6.4.0 Horizontal busbars shall be of uniform cross section throughout the length of the switchboard. Vertical busbars of all vertical panels of the switch board shall also be of uniform cross section. 6.5.0 The bus bars and bus bar supports shall withstand the dynamic, thermal & magnetic stresses and strains due to the maximum short circuit current corresponding to the fault level indicated in the data sheet, without any deformation, deterioration or damage. 6.6.0 Rigid insulating barriers / protection guards /wire meshes shall be provided between the group of live bus bars and other parts, so as to eliminate danger to personnel due to accidental contact. 6.7.0 The bus bar supports shall be of non-hygroscopic material with anti tracking features to prevent flashovers. These shall have high tracking index and be mechanically strong. Hylam is not acceptable. 6.8.0 Appropriate identification shall be provided on the busbars for distinguishing the various phases, neutral and control / auxiliary buses. 7.0.0 FEEDER ARRANGEMENT 7.1.0 Feeder module / compartment sizes shall be integral multiples of one or two basic sizes. 7.2.0 Indicating lamps, meters and push buttons shall be mounted flush with the front-hinged cover. 7.3.0 The control components, except those coming on doors, shall be mounted on a base plate, fixed on the frame of the module. 7.4.0 The incoming feeder shall be arranged preferably in the middle of each group of feeders, in such a way that loads are distributed equally on either side. 7.5.0 The feeder arrangement shall be such that the operating height (ie. operating handle, switches, push buttons, etc.) lies within 1828 mm, but above 300mm, from the floor level. 8.0.0 CABLE COMPARTMENTS 8.1.0 Cable compartments / cable alleys shall be provided for easy termination of all incoming and outgoing cables. The width of this cable alley shall be sufficient to accommodate all the cables and shall have free access for cable terminations and in any case shall not be less than 150mm. Cable alleys shall be provided with suitable doors. It shall be possible to carry out maintenance work safely on cable connections to anyone circuit, with the bus bars and adjacent circuit live. 8.2.0 Adequate supports and facilities for clamping shall be provided for cables, wherever necessary. 8.3.0 A horizontal wire way, extending over the entire length, shall be provided at the top / bottom for inter panel wiring. 8.4.0 Removable gland plates, having a minimum thickness of 2mm, shall be provided. Gland plates for glanding for single core cables shall be made of nonmagnetic material. 8.5.0 Cable glands shall be supplied loose along with the equipment for fixing them at site, if specified in the data sheet. 9.0.0 CABLE TERMINATION 9.1.0 All terminal blocks shall have adequate current carrying capacity, heavy duty & break resistant. FACT ENGINEERING AND DESIGN ORGANISATION 00FT001 ENGINEERING SPECIFICATION MEDIUM VOLTAGE SWITCH BOARDS 13ES906/14 Page 5 of 16 9.2.0 Terminals shall be compact and shall have high dielectric strength so as to prevent flashover and have thermal strength to prevent deterioration. All terminals shall be mounted on aluminium rails, with provision for addition of terminals. 9.3.0 Direct conductor termination type terminals of approved make will be acceptable up to 10mm size. Bolted type terminals with crimping type lugs shall be provided for all cable connections greater than 2 10mm . 9.4.0 Sufficient clearances shall be available between terminals when terminal lugs are fitted to them. 9.5.0 Not more than two wires (one incoming & one outgoing) shall be connected per terminal. 9.6.0 Minimum 10% spare terminals shall be provided on each control terminal block, subject to a minimum of two. 9.7.0 Shorting links shall be provided for CT terminals. 9.8.0 Identification numbering / lettering shall be provided for each terminal. 9.9.0 Necessary hardware required for cable termination like nuts ,bolts, washers, spacers etc. for incoming and outgoing feeder shall be fitted and supplied. 10.0.0 WIRING 10.1.0 The switchboard shall be completely pre-wired and ready for external connections at site. 10.2.0 All control wiring shall be carried out through common wire ways. These shall not cross the bus bar chamber. All control wiring shall be easily accessible for maintenance. 10.3.0 Necessary colour codes shall be adopted for power and control wiring for easy identification. 10.4.0 Power wiring shall be carried out with PVC insulated, stranded copper conductors of 650 Volts grade 2 having adequate current carrying capacity. Minimum size of conductor for power wiring shall be 4mm copper. 10.5.0 Control wiring shall be carried out with 650 V grade, PVC insulated, copper conductor of size not less 2 2 than 1.5 mm . Circuits involving current transformers shall have 2.5mm ,1100 V grade conductors. 10.6.0 Wiring shall be terminated in easily accessible terminal blocks. The wires shall be arranged neatly and the two ends of each wire and terminal block shall bear identification number/letter using unbreakable ferrules. 10.7.0 Control wiring wherever terminated shall be in single layer formation. 10.8.0 All inter panel control wiring shall be taken through PVC sleeves and this shall be done by the switch board manufacturer with the identification of wires and terminals for interconnection. 11.0.0 INSULATION 11.1.0 All insulating materials shall be non-hygroscopic, mould proof and treated with suitable varnishes. Hylam shall not be used. 12.0.0 EARTHING 12.1.0 A continuous earth bus as specified in the datasheet shall be provided for the entire length of the switchboard. 12.2.0 A minimum of 2 terminals shall be provided on the bus for external connection to earth grid. 2 FACT ENGINEERING AND DESIGN ORGANISATION 00FT001 ENGINEERING SPECIFICATION MEDIUM VOLTAGE SWITCH BOARDS 13ES906/14 Page 6 of 16 12.3.0 All panels shall be properly connected to the earth bus. 12.5.0 All non-current carrying metallic parts of the equipment shall be earthed. 12.6.0 All hinged doors and covers shall be provided with suitable flexible earthing connections. 13.0.0 NAME PLATE 13.1.0 A nameplate with the switchboard designation shall be fixed at the top of the central panel. Separate nameplates, giving feeder designation shall be provided on each compartment. 13.2.0 Necessary functional nameplate shall be provided for each component such as lamps, PBs, relays, switches, etc. mounted on the panel front. 13.3.0 Nameplates shall be of Non corrosive metal like stainless steel with letters engraved in it. 13.4.0 The component nos. shall be painted / suitably identified inside the panel at appropriate points to give a permanent marking. 14.0.0 MOULDED CASE CIRCUIT BREAKERS 14.1.0 Where moulded case circuit breakers are used for feeder circuit protection, rating and characteristics shall be chosen in such a way as to ensure proper discrimination with other upstream and downstream protective devices within the assembly. 14.2.0 The MCCB should be current limiting type with trip time of less than 10 milli second under short circuit conditions. The MCCB should be either 3 or 4 poles as specified in data sheet. 14.3.0 MCCB shall comply with the requirements of the relevant standards IS13947 – Part 2 and should have test certificates for Breaking capacities from independent test authorities CPRI / ERDA or any accredited international lab. 14.4.0 MCCB shall comprise of Quick Make -break switching mechanism, arc extinguishing device and the tripping unit shall be contained in a compact, high strength, heat resistant, flame retardant, insulating moulded case with high withstand capability against thermal and mechanical stresses 14.5.0 The breaking capacity of MCCB shall be as specified in the schedule of quantities. The rated service breaking capacity (Ics) should be equal to rated ultimate breaking capacities (Icu). MCCB’s for motor application should be selected in line with Type-2 Co-ordination as per IS 13947-2. The breaker as supplied with ROM should meet IP54 degree of protection. 15.0.0 FEEDER LOAD BREAK SWITCHES 15.1.0 The switches shall be of air break type, AC22 /AC23 utilization category as per IS. MinimumAC22 rating of the switch used shall be 63 A. 15.2.0 The switches shall have a quick-make, quick-break, fault-make, load-break mechanism operated by an external insulated earthed handle, complete with ON-OFF position indicator/ dial plates. 15.3.0 Load break switches of motor starter feeders shall have AC23 rating corresponding to full load current of the motor connected. Also theAC22 rating of the switches used shall not be less than the rating of the HRC fuses in the feeder. 15.5.0 The switch fuse feeders shall be provided with load break switches of AC22 utilization category. 15.6.0 Bolted type removable copper links of adequate size shall be provided for neutral, in all incomer feeders and outgoing feeders with TPN switch fuse units. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION MEDIUM VOLTAGE SWITCH BOARDS 13ES906/14 Page 7 of 16 15.7.0 The cubicle door shall be interlocked with the switch mechanism so that the door cannot be opened unless the switch is in the OFF position. 15.8.0 Padlocking facility in OFF position shall be provided for feeder switches. 15.9.0 In the event of an independent control circuit supply to the coils of the contactors, the main switch shall be provided with necessary auxiliary contacts to disconnect this control supply as well, when the switch is turned to ‘OFF’ position for isolating the main supply. 16.0.0 MINIATURE CIRCUIT BREAKERS (MCB) 16.1.0 Miniature Circuit Breaker shall comply with IS-8828. Miniature circuit breakers shall be quick make and break type for 240/415 VAC 50 Hz application with magnetic thermal release for over current and short circuit protection. 16.2.0 The breaking capacity shall not be less than 10 KA at 415 Volts AC. MCB’s shall be DIN mounted. The MCB shall be Current Limiting type (Class-3). MCB’s shall be C Type as per their Tripping Characteristic curves defined by the manufacturer, unless otherwise specified in the data sheet. 16.3.0 The MCB shall have the minimum power loss (Watts) per pole defined as per the IS/IEC and the manufacturer shall publish the values. MCB shall ensure complete electrical isolation & downstream circuit or equipment when the MCB is switched OFF. 16.4.0 The housing shall be heat resistant and having high impact strength. The terminals shall be protected against finger contact to IP20 Degree of protection. All DP, TP, TPN and 4 Pole miniature circuit breakers shall have a common trip bar independent to the external operating handle. 00FT001 17.0.0 FUSES 17.1.0 All fuses shall be HRC link type , suitable for industrial application conforming to IS: 13703 Part II. 17.2.0 Selection of fuses for motor feeders shall be as per IS: 900. 17.3.0 All power and control fuses shall be provided with distinct operation indicators, to show whether they have operated or not. 17.4.0 For all fuses provided in the fuse holders, necessary viewing aperture shall be provided on the fuse holder for locating the blown out fuses. 17.5.0 Fuse holders and fuse bases shall be made of unbreakable non-inflammable and non-hygroscopic material, preferably of phenolic mouldings. 17.6.0 Fuse pullers of different sizes required for inserting and removing HRC fuses shall be supplied for each switchboard. 18.0.0 STARTER-CONTACTORS 18.1.0 Starter contactors shall be electromagnetic, air break type, suitable for uninterrupted duty and of AC3 / AC4 utilization category as specified in data sheet, conforming to relevant standards. 18.2.0 The operating coil shall be vacuum impregnated, with special varnish, to remove all traces of air and moisture. Alternatively, it can be of resin cast material as well. 18.3.0 The holding coils shall be rated for the control voltage specified in the data sheet. 18.4.0 If specified in data sheet, the holding coils shall be provided with delayed (up to 5 seconds) under voltage release features. 18.5.0 Contactors shall preferably have switching position operation indicator. FACT ENGINEERING AND DESIGN ORGANISATION 00FT001 ENGINEERING SPECIFICATION MEDIUM VOLTAGE SWITCH BOARDS 13ES906/14 Page 8 of 16 18.6.0 A minimum of 1 N/O and 1 N/C spare auxiliary contacts, in addition to those required for control circuits, shall be available for each contactor. (If necessary, add on blocks or auxiliary contactor can be provided.) 18.7.0 Wherever control voltage is DC, necessary series economy resistors shall be provided in the control circuits, to reduce the DC load on the battery / rectifier. 18.8.0 Type of co-ordination between contactor, overload protective device and short circuit protective device shall conform to Type II as per relevant standards. 19.0.0 OVERLOAD RELAYS 19.1.0 All overload relays shall be designed to nullify the effects on settings due to changes in ambient temperature and humidity and they shall have adjustable accurately calibrated settings. 19.2.0 Overload protection shall be available for all the phases. 19.3.0 The over load relay shall be manual / auto reset type as specified in the data sheet. For manual reset type, reset knob / push button shall be provided on the cubicle door, if specified in the data sheet. 19.4.0 Overload relays shall be either direct connected or CT operated, depending on the rating of motor. In the case of CT operated relays, cast resin insulated CTs shall be included in the scope of supply of vendor. 19.5.0 Thermal bimetallic overload relays provided for motor feeders shall have integral / built in single phasing preventing feature. If built in feature is not available, separate current operated type single phasing preventor shall be provided. 19.6.0 If separate single phasing preventor (SPP) is provided, the same shall be fail safe type and shall function without any external power supply. In case of failure of internal wiring, the relay shall trip the motor. The SPP shall be suitable for protection of the nonreversible as well as reversible motors. 19.7.0 Thermal over load relays for motor feeders of blowers, fans, agitators, crushers, compressors and mills shall be of heavy duty, delayed action type to allow for more starting time. If required heavyduty overload relays are not available, necessary bypass contactor & timer arrangement circuit shall be provided to allow for more starting time. 19.8.0 Contactor and overload relay shall be selected so as to withstand the let through energy of the connected HRC fuse and MCCB’s in the feeder, and consequent thermal and dynamic effects. 20.0.0 CURRENT TRANSFORMERS 20.1.0 Current Transformers (CTs) shall be of cast resin insulated type, and shall conform to relevant standards like IS: 2705 & IS: 4201. 20.2.0 Ratings of CTs provided shall match the specific requirements of the meters and protective relays involved. 20.3.0 CTs provided in circuit breaker panels shall withstand the maximum short circuit current for a minimum of 1 second. However for motor feeders the minimum duration can be 0.6seconds. 20.4.0 Separate CTs / cores shall be used for metering and protection. Dual purpose CTs are not acceptable. 20.5.0 CTs for metering purposes shall have adequate capacity to cater for 130% of full load conditions. Metering CTs shall have an Instrument Security Factor not more than 5 and an accuracy class not more than 1.5 unless otherwise specified. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION MEDIUM VOLTAGE SWITCH BOARDS 13ES906/14 Page 9 of 16 20.6.0 CTs for protection purposes shall have sufficient accuracy, burden and accuracy limit factor for necessary coordination / discrimination for clearing faults. Accuracy limit factor for protection CT shall not be less than 10 and accuracy class shall be 5 P. CTs for differential / REF protection shall be of class ‘PS’. 20.7.0 All CT terminals and terminals to remote meters shall be provided with links to facilitate shorting as and when required. 20.8.0 CTs shall be provided with polarity markings adjacent to terminals, both for primary and secondary. These shall be legible even after years of service. 20.9.0 1 No. current transformer with 1 Amp secondary rating shall be provided for each motor feeder having a motor rating of 15 KW and above, unless otherwise specified in the data sheet, for remote ammeter. Burden of this CT shall be sufficient to compensate for the lead burden and for the burden of remote ammeter. As per data sheet, if same CT is used for local and remote meters, it shall have adequate burden to meet the total requirement. 00FT001 20.10.0 If standby earth fault protection (earth leakage protection) and / or restricted earth fault protection are provided on incoming breaker panels, one number ground CT with suitable VA and ratio for standby earth fault protection and one number ground CT with suitable ratio, knee point voltage and exciting current for restricted earth fault protection, shall be supplied loose, per incomer, in weatherproof enclosure fitted with cable glands. 21.0.0 RELAYS 21.1.0 Relays shall conform to IS 3842 & IS 3231. 21.2.0 Protective relays shall be flush mounted drawout type. The type and manufacture of the relays shall be approved by the buyer. 21.3.0 All relays shall have hand reset type operation indicators and initiating contacts. Indicators shall be visible from front side of the panel. It shall be possible to reset them without opening the relay case. 21.4.0 Protective relays shall be suitable for the CT secondary current. 21.5.0 The relay shall have provision for insertion of test plug at the front for testing and calibration purposes. It shall be possible to test the relays without disconnecting the wiring and without withdrawing the relay. The insertion of the test plug shall automatically short circuit the CTs and permit extension of external power supply to the relay. 21.6.0 Circuit breaker feeders with protective relays shall be provided with high speed master tripping relay of the lock out type with hand reset feature and coil cut off contact. 21.7.0 It shall be ensured, by checking with the relay manufacturer, that with the accuracy limit factor of current transformer provided, the thermal withstand capability of relays will not get exceeded for the fault level prescribed. 21.8.0 If composite motor protection relays are prescribed in the data sheet for motor feeders, thermal withstand characteristics of motors will be furnished on receipt from motor manufacturer. Selection of most suitable version of motor protection relay based on the motor characteristics, to provide adequate protection to the motor, shall be the responsibility of the switchboard supplier. Necessary application checks shall be carried out by vendor in consultation with the relay manufacturer and recommended settings along with calculations shall be submitted. 21.9.0 Vendor shall furnish complete relay coordination details applicable. This is required to check the adequacy of CT ratios, VA ratings, relay types and characteristics, etc. and to determine the optimum settings to be adopted for ensuring selectivity and backup protection. While selecting the settings, manufacturing tolerances of devices shall be considered. Settings for all adjustable devices shall be FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION MEDIUM VOLTAGE SWITCH BOARDS 13ES906/14 Page 10 of 16 00FT001 tabulated. Graphs shall also be drawn to match motor characteristics with motor protection relay characteristics. 22.0.0 CONTROL TRANSFORMERS 22.1.0 Control transformer shall be provided on each module unless otherwise specified in the datasheet, wherever control voltage specified / required is different from the mains voltage. 22.2.0 Control transformer shall be cast resin-insulated type. 22.3.0 Control transformer shall have ± 5% voltage tappings on the primary side and with center tap of secondary winding earthed. Where common control transformer is specified in data sheet for bus section additional tappings of ± 2.5% shall also be provided. 22.4.0 All Control transformers shall have HRC fuse protection on primary side and double pole MCB on secondary side. Where common control transformer’s are specified in the data sheet for bus section, suitable switch fuse unit shall be provided on the primary side. 22.5.0 Control transformer provided in individual module shall have adequate capacity to feed the control loads of the feeder as well as the inrush VA of the contactors & relays of the feeder. 22.6.0 Where common control transformers are specified in the data sheet for each bus section, each unit shall have adequate capacity to feed all control loads (including those of spare panels) of particular bus section and any one of the adjacent bus sections as well as the inrush VA of contactors & relays applicable. In the event of failure of the control transformer of one bus section, control transformer feeding any one of its adjacent bus sections shall be capable of feeding the same also, in addition to its own loads, by temporary interconnection. 22.7.0 Where control transformers are provided bus section wise, the compartment housing the control transformer shall preferably be located towards the bottom of the switchboard, to facilitate maintenance and replacement. 22.8.0 Wherever module control transformers are envisaged in draw out switchboards, a separate control transformer (complete with switch fuse on primary, double pole MCB on secondary and centre tap of secondary winding earthed) for test supply shall be provided along with associated wiring and accessories. 22.9.0 Where common control transformers are provided, the control supply to module shall get automatically isolated when the feeder switch is switched OFF. 23.0.0 INDICATING INSTRUMENTS 23.1.0. Meters shall be flush mounted and of a type and make approved by the buyer. 23.2.0 All meters shall be square type of size 96mm x 96 mm unless otherwise specified in the datasheet. Dials shall be white with black numerals and letters. 23.3.0 A moving iron voltmeter having a range of 0-500Volts AC shall be provided, along with a suitable selector switch, to read all line to line voltages on the incoming side of incoming feeders. The selector switches shall have 3 way and OFF positions. Necessary facia plates to denote switch positions shall be provided. Necessary control fuses shall be provided in the voltmeter circuit. 23.4.0 Voltmeter shall be of Class 1.5 accuracy as per IS and shall have suppressed scale for the lower values in the range. 23.5.0 Ammeters shall be of accuracy Class 1.5 as per IS unless otherwise specified. 23.6.0 Ammeter having suitable range shall be provided along with ammeter selector switch to read line currents in the incomer feeders. The selector switches shall have 3 way and OFF position. Necessary FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION MEDIUM VOLTAGE SWITCH BOARDS 13ES906/14 Page 11 of 16 facia plates to denote switch positions shall be provided. These ammeters shall have approximately uniform scale up to about full load current and suppressed end scale from 100% to at least for 150% full load. 23.7.0 Ammeter, if provided for motor feeders as per data sheet, shall have suppressed overload range (cramped end scale), to read the starting current of 600-800% and 200-400% of normal full load current of motors for DOL starting and for star delta starting respectively. 23.8.0 A red mark shall be provided on the ammeter dial, corresponding to the full load current. 23.9.0 All ammeters shall be operated through current transformers and not directly connected. Calibration of the ammeters shall tally with the ratio of the current transformers. 23.10.0 Cushion stoppers and zero correction screws shall be provided for all meters. 23.11.0 Energy meter, kilowatt meter and power factor meter, if provided as per data sheet, shall be operated through current transformer only. The rating shall correspond to full load requirements. The multiplication factor, if any, shall be furnished and exhibited by the side of the meter. 23.12.0 All lighting feeders shall be provided with CT operated ammeter with selector switch and energy meter suitable to measure unbalanced loads on a 3-phase 4 wire system. 23.13.0 All selector switches shall be of rotary type, spring loaded and of robust construction. The operating handle of these switches shall be knob type and of black colour. 23.14.0 Digital type meters shall be provided wherever specified in the data sheet. 00FT001 23.15.0 All auxiliary equipment such as shunts, transducers, CTs, VTs, etc. that are required shall also be included in the supply of the switchboard. 24.0.0 INDICATING LAMPS, PUSH BUTTONS, CONTROL SWITCHES, ETC. 24.1.0 INDICATING LAMPS 24.1.1 Indicating lamps shall be of long life LED type and shall be indigenously available.. 24.1.2 Necessary preventive measures shall be ensured to avoid any malfunction of the connected circuit in the case of any fault in the indicating LED’s. 24.1.3 All signaling lamps must have clarity of colour .The colour shall be in LED and not as an applied coating 24.1.4 Necessary protective fuses shall be provided for the lamp circuit in breaker feeders with shunt trip arrangements. 24.2.0 PUSH BUTTONS 24.2.1 Number of PBs like START, STOP, REVERSE etc. required are given in the data sheet. Colour of push buttons knobs shall be as per relevant IS. 24.2.2 All push buttons shall have 1 N/O + N/C contacts, unless otherwise required. 24.2.3 All push buttons shall be provided with legend plates to identify the function or operation. 24.3.0 Local / Remote change over switch shall be provided, if specified in the data sheet, when starting is envisaged from more than one location. 24.4.0 All Control switches shall be preferably of rotary type with operating knob. They shall have proper designation plates. FACT ENGINEERING AND DESIGN ORGANISATION 00FT001 ENGINEERING SPECIFICATION MEDIUM VOLTAGE SWITCH BOARDS 13ES906/14 Page 12 of 16 25.0.0 ANTICONDENSATION HEATERS 25.1.0 Anti condensation heater of adequate capacity, rated for 240 V AC, shall be provided in every vertical panel, in easily accessible position. For double front switchboards, heaters shall be provided on both the fronts. 25.2.0 Necessary two pole ONOFF switch with HRC fuse & neutral link (or two pole MCBs) shall be provided for each anti condensation heater circuit along with suitable thermostat for automatic temperature control. 25.3.0 Heater supply to individual panel heaters in each bus section shall be availed through a separate switch fuse feeder complete with suitably rated two pole switch, HRC fuse, neutral link, associated heater supply bus/wiring, etc. 25.4.0 Wiring of anti condensation heaters shall be isolated or separately bundled from other internal wiring , preferably using a different colour. 25.5.0 If anti condensation heater is specified in data sheet, space heater supply shall be taken from the outgoing end of motor isolator and shall be wired through an MCB and separate auxiliary contactor, coil supply of it shall be through the NC contact of the main contactor. 26.0.0 DRAWOUT SWITCHBOARDS 26.1.0 The feeders shall be fully draw out type. 26.2.0 All draw out modules shall have distinct and stable TEST position, SERVICE position & ISOLATED (WITHDRAWN) position. 26.3.0 All power contacts (both on bus bar side and cable side) shall be of fully draw out, self aligning, plug in design, which get automatically disconnected when the draw out module is withdrawn from the connected (SERVICE) position. Removable male and female contacts preferred. 26.4.0 Wiring for neutral may be in the fixed portion of the compartment. Where neutral connection is required for control purposes within the module, they shall be through draw out contacts providing full draw out facility. 26.5.0 All control contacts also shall be fully draw out self aligning type which get automatically connected/ disconnected depending on the circuit requirements, when draw out module is withdrawn to TEST / ISOLATED positions. 26.6.0 Manual plug-in plug-out arrangement for control contacts is not acceptable. 26.7.0 The design of the contacts shall be such as to increase the contact pressure during starting and shortcircuiting conditions. 26.8.0 Necessary separation barriers shall be envisaged between pairs of power contacts to prevent flashovers. 26.9.0 Draw out arrangement shall be designed in such a way that withdrawing and plugging in of the trolley are achieved with smooth and reliable operation and without causing any damage or thrust to the plug in type contacts. 26.10.0 Withdrawable trolley/ chassis shall be preferably with screw cranking arrangement and/or guide vanes, such that trolley movement is positively guided and self aligning type. The trolley must move on low friction rolling mounts. 26.11.0 Trolley pad locking switch and latch /trolley clamping captive screw shall be provided for the fully inserted position. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION MEDIUM VOLTAGE SWITCH BOARDS 13ES906/14 Page 13 of 16 26.12.0 There shall be positive indication for the various positions of the trolley. 26.13.0 Wiring for components within the draw out module shall be identical in layout, ferrule numbering, sequencing of secondary isolating contacts, colouring etc. to achieve maximum interchangeability. 26.14.0 In the case of double front panels, the module trolleys shall be interchangeable from one front to another front in such a manner that direction of rotation of motors are kept unaltered. Such interchanging shall not require rearranging /connecting cables. 26.15.0 Identical feeder types shall be interchangeable with each other. Also all modules shall carry labels identifying KW rating & type of control wiring 26.16.0 Necessary earthing arrangements shall be provided for the truck in the‘ TEST’ and‘ SERVICE’ positions. The earth connection shall make before the main power and control contacts make and break after the power and control contacts are disconnected. Earthing connection through manual plug & socket connection will not be acceptable. 00FT001 26.17.0 Provision of control supply in the test position of draw out modules (feeders which require control supply) shall be available. In draw out switchboards with module control supply, required test control supply feeder, associated test supply bus/ wiring, etc. shall be provided. 27.0.0 MEDIUM VOLTAGE CIRCUIT BREAKERS 27.1.0 GENERAL & CONSTRUCTIONAL FEATURES 27.1.1 Circuit Breakers, if any, shall conform to IS: 13118. 27.1.2 All CBs shall be suitable for uninterrupted duty as per IS. 27.1.3 CBs provided for control of motors, capacitors, etc. shall be suitable for the specific duty involved. 27.1.4 If different ratings of circuit breakers are used in the switch board, they shall preferably belong to the same family. The individual units of same ratings in a continuous switchboard shall be interchangeable. 27.1.5 Circuit breaker enclosure shall be same as that of main equipment. 27.1.6 Circuit breaker shall be of forward draw out construction. The cradle shall be so designed and constructed as to permit the smooth withdrawal and insertion of the breaker into it. The movement shall be free of jerks, easy to operate and shall preferably be on steel balls / rollers and not on flat surfaces. Horizontal draw out type truck is preferred. 27.1.7 Each CB shall be housed in a separate compartment and shall be enclosed on all sides. Adequate provision shall be made for escape of hot gases by providing louvers. The louvers shall be covered with perforated sheets and shall be so located as to direct the hot gases away from the operating personnel. Multi-tier arrangement can be provided, if adequate space for maintenance is ensured. 27.1.8 Sheet steel barriers shall be fitted between the tiers in a vertical section and between two vertical sections in the breaker compartment. 27.1.9 The hinged lockable door of the draw out type of CB shall not form an integral part of the draw out portion, so that entry of foreign materials / things into the cubicle is not possible when the CB is drawn out. 27.1.10 The door shall be of such a design that it shall allow the breaker to be kept withdrawn up to the ‘TEST’ and ‘ISOLATED’ positions with the CB door closed. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION MEDIUM VOLTAGE SWITCH BOARDS 13ES906/14 Page 14 of 16 27.1.11 The CB door shall be interlocked with the breaker positions such that: a) The door cannot be opened unless the breaker is in ISOLATED position and b) The breaker cannot be racked into the SERVICE position unless the door is closed. 27.1.12 The following four positions of the CB shall be distinctly marked and locking arrangements shall be made: a) SERVICE position: The main disconnecting contacts shall be fully gripped on both sides, namely the bus bar side and the load side (both main and secondary isolating contacts in service). b) Test position: The truck shall be perfectly isolated from the live busbars in order to test for proper performance (main isolating contacts separated and secondary isolating contacts in service / test position). c) ISOLATED position: It shall be able to withdraw the truck from the cubicle for inspection and maintenance (both main and secondary isolating contacts isolated). d) MAINTENANCE position: It shall be possible to draw out / take out the circuit breaker fully outside the cubicle for maintenance purposes. 27.1.13 The above first three positions of the CB shall be positive, achieved only through the turning /racking motion of the draw out mechanism and not by trial and error. There shall be an indicator clearly showing the first three positions listed above, and the same shall be visible from the front without opening the front door. 27.1.14 It shall not be possible to close the CB unless it is positively in one of the following positions: a) Truck in ‘SERVICE’ position b) Truck in ‘TEST’ position c) When the truck is in completely ‘ISOLATED’ position. 27.1.15 The interlocks mentioned above are the minimum requirement. Manufacturers shall include any other safety interlocks, which may be required by the particular design feature of the switchgear offered. 27.1.16 Necessary earthing arrangements shall be provided for the truck in the‘ TEST’ and‘ SERVICE’ positions. The earth connection shall make before the main power and control contacts make and break after the power and control contacts are disconnected. Earthing connection through manual plug & socket connection will not be acceptable. 27.1.17 Separate and adequate accommodation shall be provided for instruments / meters, indicating lamps, auxiliary contactors, timers, control fuses, CTs, VTs, protective and auxiliary relays, auxiliary switches, control transformers if any, etc. These shall be easily accessible for testing and maintenance, without any danger of accidental contact with live parts of the CB. All the above accessories, bus bar connections, wire ways, cable space, painting and other general requirements of CB shall conform to relevant clauses mentioned elsewhere in this specification. 00FT001 27.1.18 Truck/trolley shall be provided for handling the circuit breaker 27.2.0 CIRCUIT BREAKER CONTACTS 27.2.1 CB contact assemblies shall include easily replaceable arcing contacts. Main current carrying contacts shall be of low resistance, arc resistant and adjustable to compensate wear. 27.2.2 Contact fingers shall be spring loaded to reduce contact bounce. 27.2.3 The isolating contacts shall be self-aligning and able to carry rated short circuit current, without any tendency for the contacts to ‘blowoff’. FACT ENGINEERING AND DESIGN ORGANISATION 00FT001 ENGINEERING SPECIFICATION MEDIUM VOLTAGE SWITCH BOARDS 13ES906/14 Page 15 of 16 27.2.4 In case of air circuit breakers, the arc chutes shall be removable for routine inspection of the contacts. 27.2.5 In case of air break contacts, the arcing contacts shall have anti-sticking and burn resistant properties. 27.2.6 Wiring and termination of secondary isolating contacts shall be interchangeable in all identical breakers. 27.3.0 OPERATING MECHANISM 27.3.1 It shall be possible to close and trip the circuit breaker without opening the CB compartment door. The operating handle and the mechanical trip push button shall be at the front of the breaker and integral with it. Arrangements with operating handle fitted on the door independently of the breaker, and connected through a set of links to the breaker, are not acceptable. 27.3.2 CB shall be fitted with hand / direct motor / motor charged spring / solenoid closing mechanism, as specified in the data sheet. Whatever be the mode of operation of the breaker, it shall have hand closing provision to be operated in emergencies and during testing. 27.3.3 Operating mechanism shall be mechanically and electrically trip free in all positions of CB. 27.3.4 It shall be possible to mechanically trip the CB mechanism by a distinctively marked push button. 27.3.5 In “manually operated breaker”, the design of the handle and operating mechanism shall be such as not to require large open slots in the front door for the movement of the handle. Manual closing mechanism shall be of independent manual type. 27.3.6 In “electrically operated breakers”, remote closing facility shall be provided. The type of electrically operated mechanism and the voltage of operation shall be as indicated in the data sheet. 27.3.7 The breaker shall be provided with suitable anti pumping feature to ensure that it does not reclose automatically after a tripping, even if the closing impulse is maintained. 27.3.8 When the breaker is in the closed position, a closing operation of an initiating control device shall not result in further operation of the breaker closing mechanism or discharging of the closing spring. 27.3.9 Closing of CB shall be prevented, unless the spring is fully charged. 27.4.0 OTHER REQUIREMENTS 27.4.1 The auxiliary wiring between the switchgear receptacle and the truck unit shall be established by means of a plugging / sliding unit, consisting of minimum 10 pairs of contacts rated for 10A, 650V grade, which get automatically disconnected when the drawn out module is withdrawn from the test position. 27.4.2 A mechanical ON-OFF indicator, appropriately marked, shall be provided at the front of the CB. 27.4.3 A mechanical interlock shall be provided between the circuit breaker and isolator, if any, directly connected to CB to prevent operation of the isolator when the CB is in closed position. 27.4.4 The closing coils and other auxiliary devices shall operate satisfactorily at all voltages between85110% of the rated control voltage specified in the data sheet. Trip coils shall operate satisfactorily at all voltages between70-110% of the rated trip voltage mentioned in the data sheet. 27.4.5 Auxiliary power supply for control, indication and space heaters shall be as indicated in the datasheet. For auxiliary power supply, necessary control switch fuse / MCB of required ratings shall be provided, unless otherwise specified in the data sheet. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 13ES906/14 Page 16 of 16 Releases: Releases shall be provided, if specified in the data sheet. Type of releases provided and their characteristics shall be furnished by the vendor. If provided, the releases shall have the following features: a) The overload release shall be provided with a setting range of 70% to 110% of the breaker rated current or as specified in the data sheet. b) The short circuit release shall be provided with minimum two settings corresponding to 750% and 1000% of the rated current, with adjustable time delay range of 25ms to350 ms or as specified in the data sheet. c) Earth fault releases shall be provided with a setting range of 10% to 40% of the rated current, or as specified in the data sheet. d) In PCCs/ PMCCs, where two breakers are connected in series they shall be fitted with releases permitting discrimination. 00FT001 27.4.6 MEDIUM VOLTAGE SWITCH BOARDS FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION Page 1 of 2 1.0.0 2.0.0 3.0.0 4.0.0 5.0.0 6.0.0 7.0.0 8.0.0 CONTENTS SCOPE REFERENCE STANDARDS GENERAL CONSTRUCTIONAL REQUIREMENTS DRUM LENGTHS TOLERANCES METHOD OF INSTALLATION CABLE DRUMS 1.0.0 SCOPE 1.1.0 This specification covers the requirements for design, manufacture, testing at Works and supply of cables. 2.0.0 REFERENCE 2.1.0 The following documents shall be read in conjunction with this specification. 2.1.1 Engineering specification and Data Sheet of General requirements for Electrics 2.1.2 Data sheet of Cables 2.1.3 Technical particulars of Cables 3.0.0 STANDARDS 3.1.0 Cables shall comply with the requirements laid down in the latest issues of following standards wherever applicable along with other related standards. IS 694 PVC Insulated Cables for working voltage up to and including 1100V IS 1554 (Part I & II) PVC Insulated (Heavy Duty) Electric Cables IS 7098 (Part I & II) Cross-linked Polyethylene Insulated PVC Sheathed Cables IS 10418 Drums for Electric Cables IS: 5831 PVC insulation and sheath of Electric Cables. IS:8130 Conductors for insulated Electric cables and flexible cords. IS:3975 Mild steel wires strips and tapes for armouring of cables. IS: 10810 (part 41) Methods of test on cables. Mass zinc coating on steel armour. IS:209 Zinc ingot IS:3961(Part 2) Recommended current rating for cables. Part 2: PVC insulated and PVC sheathed heavy duty cables IS:10810(part 58) Oxygen index test IS:10810( Part 61) Flame retardant test. IS:10810( Part 62) Fire retardant test for bunched cables. IS:13573 Joints and terminations for Polymeric cables for working voltages from 6.6kV upto and including 33kV performance requirements and type tests IEC60331 Fire resisting characteristics of Electric cables IEC-60332-2 Test on Electric cables under fire conditions-Part: 2 Test for vertical flame propagation for a single small insulated wire or cable IEC-60332-3 Test on Electric cables under fire conditions-Part: 3 Test for vertical flame spread of vertically mounted bunched wires or cables IEC-60502 Extruded solid dielectric insulated power cables for rated voltages from 1kV upto 30kV IEC- 540&540A Test methods for insulation and sheath of electric cables and cords. ASTM: D2863 Standard method of flammability of plastics using oxygen index method. PRPD. : CHKD. : APPRD. : FACT ENGINEERING AND DESIGN ORGANISATION 00FT006 13ES930/14 CABLES ISSUED ON SEPT 2014 13ES930/14 ENGINEERING SPECIFICATION CABLES Page 2 of 2 ASTM: D2843 4.0.0 4.1.0 Outer sheath of all PVC and XLPE cables shall be black in colour and minimum oxygen index shall 0 be 29 at 27±2 C. Suitable chemicals shall be added into PVC compound of the outer sheath to protect the cable against rodent and termite attack. 4.2.0 All cables covered in this specification shall be flame retardant (FR) unless specified otherwise in data sheet. The outer sheath of PVC and XLPE cable shall posses flame propagation properties meeting requirements as per the IS:10810(Part 62). 4.3.0 Sequential marking of the length of the cable in metres shall be provided on outer sheath at every one meter interval. This embossing/engraving shall be legible and indelible. 5.0.0 DRUM LENGTHS 5.1.1 5.1.2 Unless otherwise specified in the Data Sheet of Cables, Cables shall be supplied in standard drum lengths as follows: Medium Voltage power cables upto and including 6Sq.mm - 1000metres Medium Voltage power cables from 10Sq.mm to 400Sq.mm - 500 metres 5.1.3 Control cables upto and including 27 Core- 1.5Sq.mm/ 2.5sq.mm - 1000 metres 5.1.4 5.1.5 3.3/6.6/11kV(E) 3.3/6.6/11kV(E) upto3x400 sq.mm Upto 1x630Sq.mm - 500 metres 1000 metres 5.1.6 5.1.7 33kV (E) 33kV(E) Upto 3x400Sq.mm Upto 1x400Sq.mm - 250 metres 1000 metres 5.2.0 Cable quantities less than one full standard drum length shall be supplied in single length. 5.3.0 Specific requirements if any, regarding drum lengths / single lengths etc. indicated in the data sheet shall be complied with. 6.0.0 6.1.0 TOLERANCES Drum lengths: Maximum tolerances permissible on the drum lengths shall be +5% or -2%, when more than one drum length is ordered. 6.2.0 Ordered quantity: Maximum tolerances permissible on the total ordered quantity item wise shall be + 2% or -2%. 7.0.0 METHOD OF INSTALLATION 7.1.0 The cables are proposed to be laid on overhead racks exposed to weather or on racks in the cable trenches or buried directly in ground. The supplier shall furnish the rating factors for the different methods of installation. 8.0.0 CABLE DRUMS 8.1.0 Cable drums are proposed to be stored in the OPEN store yard where it will be exposed to rain, sun and other climatic variations. The wooden drums shall not deteriorate and collapse during the storage for at least two years. PVC /Rubber end cap shall be supplied free of cost for each drum with a minimum of eight per thousand meter length. The ends of the cables shall be properly sealed with caps to avoid ingress of water during transportation and storage. 8.2.0 00FT006 Standard Test Method for Density of Smoke from the Burning or Decomposition of Plastics IEC: 60754-1 Test on gases evolved during combustion of materials from cables – Part 1: Determination of the halogen acid gas content GENERAL CONSTRUCTIONAL REQUIREMENTS FACT ENGINEERING AND DESIGN ORGANISATION 13ES911/14 ENGINEERING SPECIFICATION PUSH BUTTON STATION Page 1 of 3 CONTENTS 1.0.0 2.0.0 3.0.0 4.0.0 5.0.0 6.0.0 7.0.0 8.0.0 9.0.0 10.0.0 SCOPE REFERENCE STANDARDS GENERAL DESCRIPTION CONSTRUCTION WEATHER PROOFING PUSH BUTTONS INDICATING LAMPS AMMETERS NAME PLATE 1.0.0 SCOPE 1.1.0 This specification covers the requirements for design, manufacture, testing and supply of push button stations. 2.0.0 REFERENCE 2.1.0 2.1.1 2.1.2 2.1.3 The following documents shall be read in conjunction with this specification. Engineering specification and and Data Sheet of General requirements for electrics Data sheet of Push button station. Technical particulars of Push button station. 3.0.0 STANDARDS 3.1.0 All push button stations shall comply, wherever applicable, with the latest issues of the following standards and other relevant standards. IS: 2419 Indicating instruments IS: 1248 Direct acting electrical instruments IS: 1901 Indicating Lamps IS/IEC60079-11 Electrical apparatus for explosive gas atmospheres: part 11-Equipment protection by intrinsic safety"I" IS:13947 Specification for low voltage switchgear and control gear IS: 7118 Direction of movement of control devices IS/IEC60947-1 Low voltage switch gear and control gear :part 1-General rules 4.0.0 GENERAL DESCRIPTION 4.1.0 Push button stations shall be designed in such a way that the equipment unit is suitable for mounting on pedestal as well as on wall/surface. Fixing screws with cadmium / nickel plating shall be supplied with each unit. 4.2.0 Push button stations for hazardous area shall be of a design for which approval has been obtained from the Central Mining and Research Institute, Dhanbad, for use in the division of hazardous area specified. The details of such approval shall be given on the name plate. The approval / certification shall be relevant and valid. 4.3.0 All materials shall be selected, fabricated and painted to withstand / resist the environmental and service conditions specified in Data sheet of General requirements for electrics, attached. 5.0.0 CONSTRUCTION 5.1.0 Material of construction of enclosure shall be as specified in the data sheet such as cast iron / cast aluminum alloy / higher impact strength glass polyester material. If aluminum is used it shall be copper free. The glass polyester if used shall not get affected due to ultra violet rays over its life span. 00FT001 PRPD. : CHKD. : APPRD. : FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON: SEPT 2014 00FT001 ENGINEERING SPECIFICATION 13ES911/14 PUSH BUTTON STATION Page 2 of 3 5.2.0 The enclosure shall be as specified in the data sheet, like IP55 / IP55 weather proof (IP55WP) / flame proof (FP) / flame proof weather proof (FPWP). 5.3.0 Compression type cable glands suitable for the cable sizes given in the data sheet shall be provided. 5.4.0 Cable glands provided for flameproof push button stations shall be flameproof double compression type, approved by C.M.R.I., Dhanbad. 5.5.0 All necessary terminals shall be wired up to a terminal block for easy connection of external cables. The terminals shall be suitable for connection of 2.5mm2 copper conductor unless otherwise specified in the data sheet. 5.6.0 The cable entry shall be from the bottom unless otherwise specified in the data sheet. 5.7.0 The pushbutton station shall have four legs for mounting. The lugs shall be offset, so that the rear surface of the unit stays at least 5mm away from the surface. On lugs two holes shall be circular and two oblong, to facilitate correct positioning of the unit. 5.8.0 20% of the terminals with a minimum number of two shall be provided as spare. 5.9.0 All components shall be base mounted unless otherwise specified in the data sheet. 5.10.0 All hardware such as nuts, bolts, washers etc. shall be nickel / cadmium plated SS. 5.11.0 Two Nos. external earth terminals shall be provided on the body of the push button station. 5.12.0 The push button station shall be wired as per requirement specified in the data sheet / typical drawings attached. 5.13.0 The internal wiring shall be carried out using PVC insulated multi strand copper wires of 1.5mm2 unless otherwise specified in the data sheet. 5.14.0 Warning inscriptions “Isolate elsewhere before opening” shall be prominently marked on the top of the push button station. 6.0.0 WEATHER PROOFING 6.1.0 Push button stations specified with weatherproof enclosures shall be suitable for outdoor operation and shall subject to direct sun and rain without further protection like canopy, hood etc. 7.0.0 PUSH BUTTONS 7.1.0 Number of push buttons like ‘ON’, ‘OFF, ‘REVERSE’ etc. required are specified in the data sheet. 7.2.0 Number of Normally Open (N/O) contacts and Normally Closed (N/C) contacts to be actuated by each push button are indicated in the data sheet. Push buttons shall be momentary actuated type unless otherwise indicated in data sheet. 7.3.0 Push buttons shall have padlocking facility for the ‘OFF’ position (lockable in the pressed ‘OFF’ position). The locking links shall be of simple but robust and rigid construction. It shall not be possible to lock in the normal position of ‘OFF’ button. 7.4.0 Push button unit shall be rated for 10 A, 500 V unless otherwise specified in the data sheet. 7.5.0 Auto - manual / local- remote selector switches shall be knob type having stay put type contacts of same rating as that of push buttons and shall have distinct ‘OFF’ position unless otherwise specified in the data sheet. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 13ES911/14 PUSH BUTTON STATION Page 3 of 3 INDICATING LAMPS 8.1.0 Indicating lamps shall be provided if specified in the data sheet. 8.2.0 Indicating lamps shall be of long life LED type and shall be indigenously available. 8.3.0 Indicating lamps for “SPACE HEATER ON” indication shall be rated for 240V, single phase AC unless otherwise specified in the data sheet. 8.4.0 Lamps must have the clarity of colour. Lamps shall be so designed to prevent glare from the bulb and shall permit visibility from all directions. 9.0.0 AMMETERS 9.1.0 The ammeters in the push button stations shall be moving iron type with Class-1.5 accuracy conforming to IS:1248, suitable for 1A secondary current of Current Transformer. The burden shall not exceed 3 VA. The normal range shall be suitable for full load current of motors as indicated in the data sheet. The exact ranges/scales shall be furnished along with the order. The ammeter shall have compressed end scale (suppressed overload range) for at least 6 to 7 times the values of normal range. Cushioned stoppers shall be provided at the end of scale to stop the pointer during starting kicks. Full load shall be indicated on the scale with a red mark. 9.2.0 The size of the ammeter shall be 72 x 72 mm2 unless otherwise specified in the data sheet. 10.0.0 NAME PLATE 10.1.0 Name plates in white Perspex acrylic sheet engraved in black / stainless steel plate with 5 mm letters as specified in the data sheet, shall be provided, indicating the service. 10.2.0 The function of each push button /lamp /switch shall be clearly marked below the respective components in anodized aluminum plate having letters of a minimum 3mm height unless otherwise specified in the data sheet. 10.3.0 Nameplates shall be fastened by SS screws only. 00FT001 8.0.0 FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 13ES910/14 MEDIUM VOLTAGE INDUCTION MOTOR Page 1 of 6 CONTENTS 1.0.0 2.0.0 3.0.0 4.0.0 5.0.0 6.0.0 7.0.0 8.0.0 9.0.0 10.0.0 11.0.0 12.0.0 13.0.0 14.0.0 15.0.0 16.0.0 17.0.0 18.0.0 19.0.0 20.0.0 21.0.0 22.0.0 SCOPE REFERENCES STANDARDS GENERAL REQUIREMENTS STARTING CURRENT AND TORQUE NUMBER OF STARTS INSULATION CONSTRUCTION VENTILATION BEARINGS AND LUBRICATION WEATHER-PROOFING TERMINAL BOXES AND TERMINATIONS EARTHING NAME PLATES LIFTING FACILITIES COUPLINGS ANTICONDENSATION HEATERS PROTECTION RECIPROCATING COMPRESSOR FACTOR MOTOR SUPPLIED AND ORDERED ALONG WITH THE DRIVEN MACHINE ADDITIONAL ACCESSORIES / REQUIREMENTS DESPATCH 1.0.0 SCOPE 1.1.0 This specification covers the general requirements for design, manufacture, testing and supply of medium voltage induction motors. 2.0.0 REFERENCE 2.1.0 2.1.1 2.1.2 2.1.3 The following documents shall be read in conjunction with this specification. Engineering specification and Data Sheet of General requirements for electrics Data sheet of Medium Voltage Induction Motors Technical particulars of Medium Voltage Induction Motors 3.0.0 STANDARDS 3.1.0 All motors shall comply, wherever applicable, with the latest issues of the following Indian Standards and other relevant standards. IS: 325 IS: 1231 IS: 1271 IS/IEC60079-0 IS/IEC60079-1 IS/IEC60079-2 IS/IEC60079-7 IS/IEC60079-15 IS: 2223 00FT006 PRPD. : 3 Phase Induction Motors Dimensions of 3 phase foot mounted Induction Motors Classification of insulating materials Electrical apparatus for explosive gas atmospheres: part 0-General requirements Electrical apparatus for explosive gas atmospheres: part 1-Flame proof enclosures ”d” Electrical apparatus for explosive gas atmospheres: part 2-Pressurized enclosures ”p” Electrical apparatus for explosive gas atmospheres: part 7-Increased safety”e” Electrical apparatus for explosive gas atmospheres: part 15-construction test and marking for type of protection "n" Dimensions of flange mounted AC Induction Motors CHKD. : APPRD. : FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON SEPT 2014 ENGINEERING SPECIFICATION IS: 2253 IS: 2254 IS: 4029 IS: 4691 IS: 4722 IS: 4728 IS: 4889 IS: 6362 IS: 6381 IS: 7389 IS: 8789 IS: 12065 IS: 12075 00FT006 IS: 12615 13ES910/14 MEDIUM VOLTAGE INDUCTION MOTORS Page 2 of 6 Designations for types of construction and mounting arrangements of rotating electrical machines Dimensions of vertical shaft motors for pumps Guide for testing three phase induction motors Degrees of protection provided by enclosure for rotating electrical machinery Rotating electrical machines Terminal markings and direction of rotation for rotating electrical machinery Methods of determination of efficiency of rotating electrical machines Designation of methods of cooling of rotating electrical machines Construction and testing of electrical apparatus with type of protection"e" Pressurized enclosures of electrical apparatus for use in explosive atmospheres Values of performance characteristics for 3 phase induction motors Permissible limits of noise levels for rotating electrical machines Mechanical vibration of rotating electrical machines with shaft heights from 56 & higher measurement, evaluation and limits of vibration severity Energy efficient motors 4.0.0 GENERAL REQUIREMENTS 4.1.0 All machines shall be continuous maximum rated (Class S1 as per IS:325) under the operating conditions specified in the data sheet, and shall be suitably protected for operation under the service conditions stated in data sheet. 4.2.0 Motors for hazardous areas shall be of a design for which approval has been obtained from the Central Mining and Research Institute (CMRI), Dhanbad, for use in the particular hazardous area specified. All motors approved as above, shall have a separate nameplate carrying the details of such approval, fixed on the body adjacent to the main nameplate. The approval / certification shall be latest/relevant. 4.3.0 The motor coupled to its driven machine shall start and operate successfully under full load even if the voltage at the motor terminals is lowered to 80% of rated voltage for 30 seconds. 4.4.0 Critical speeds should be either well below or well above the normal running speeds of the motor. 4.5.0 Slip at rated load shall not exceed 3% at rated voltage and frequency. 4.6.0 The motors shall be liberally designed as regards their pullout torque, pullout voltage and their ability to ride through voltage dips during system disturbances. They should, if required, be suitable for automatic restart under full load after a momentary lack of supply voltage, with the possibility of the restored supply voltage being out of phase with respect to the motor residual voltage. The extent to which the motor has to withstand out of phase residual voltage (in percentage) shall be as specified in the data sheet. 5.0.0 STARTING CURRENT AND TORQUE 5.1.0 All motors are envisaged to be started direct on line across full line voltage unless otherwise specified in the data sheet. The rotor shall be squirrel cage type unless otherwise specified in the data sheet. The rotor shall be dynamically balanced with fan and half key on the rotor shaft. 5.2.0 The starting characteristics of the machine shall be carefully selected as to: 5.2.1 Satisfy the torque requirements of driven machine, even where reduced voltage starting is specified in the data sheet. 5.2.2 Have starting time which is less than locked rotor withstand time (hot) of the motor by at least two seconds, at the rated conditions of voltage and frequency specified, with driven machine coupled. 5.2.3 Ensure that starting current is not normally more than 600% of full load current at the rated voltage and frequency (subject to IS tolerance) unless otherwise specified in the data sheet. FACT ENGINEERING AND DESIGN ORGANISATION 00FT006 ENGINEERING SPECIFICATION 13ES910/14 MEDIUM VOLTAGE INDUCTION MOTORS Page 3 of 6 5.2.4 Ensure that accelerating torque is not too large to cause stressing of the transmission elements and the driven machine 5.2.5 Ensure that motor is suitable for starting at 80% of the rated voltage against torque speed characteristics of the driven equipment. 6.0.0 NUMBER OF STARTS 6.1.0 The motor shall be suitable for the number of starts specified in the data sheet. If nothing is specified in data sheet, then the motor should be suitable for Direct-on-line starting with minimum number of starts stated below: a) Three successive cold starts b) Two successive hot starts c) Four uniformly spaced starts per hour 7.0.0 INSULATION 7.1.0 Insulation class shall be class F with temperature rise limited to class B 7.2.0 Motor winding shall be done using copper conductor only 7.3.0 The winding shall be tropicalised. 7.4.0 All windings shall be treated with humidity, acid and alkali resisting protective coating like epoxy gel to withstand service conditions in an industrial atmosphere described in data sheet. 8.0.0 CONSTRUCTION 8.1.0 The motor shall be able to withstand the corrosive atmosphere mentioned in data sheet. External screws and bolts shall be protected particularly against corrosion by passivation. 8.2.0 The enclosure shall be provided with the required degree of protection, viz IP 55 (Indoor) / IPW55 (Outdoor) / Flameproof / Flameproof weatherproof, etc. as specified in the data sheet. 8.3.0 Vibration and noise levels shall not exceed those given in the relevant IS. 8.4.0 Motor frame sizes shall be in accordance with IEC recommendation in the absence of Indian Standards. For a particular motor, required frame sizes as per IS / IEC or higher frame size shall only be supplied. 8.5.0 The shaft shall be generously proportioned for transmitting continuous full load torque and any specified overload or duty, which may be created by the driven machine. In designing the motor shaft and bearing systems, the manufacturer shall take full account of the characteristics, thrust, shaft system and bearing system of the driven machine and also the type of coupling proposed, so as to give a completely satisfactory shaft and bearing system. 8.6.0 The motors shall be suitable for connecting capacitor at the motor terminals, if required in data sheet. Rating of capacitor shall be as indicated in the data sheet. If there is any limitation/ inadequacy with regard to the rating of the capacitor that can be connected to the motor, the findings shall be clearly substantiated in the Technical Particulars. 8.7.0 Condensate drains shall be provided where water may collect. Drain holes shall also be provided, wherever required. 8.8.0 Foundation rails if any, foundation bolts, nuts; washers, etc. shall be supplied. 8.9.0 All motors shall be capable of standing idle for long periods without damage to the bearings. FACT ENGINEERING AND DESIGN ORGANISATION 00FT006 ENGINEERING SPECIFICATION 13ES910/14 MEDIUM VOLTAGE INDUCTION MOTORS Page 4 of 6 9.0.0 VENTILATION 9.1.0 Motors shall be self-ventilated. 9.2.0 Materials of construction of fans, tubes, etc. used shall be suitable for the environment specified in the data sheet. 9.3.0 Motors shall be bi-directional, i.e. suitable for rotation in clockwise and anti-clockwise directions. 10.0.0 BEARINGS AND LUBRICATION 10.1.0 The bearings shall be of reputed manufacturer and of a type interchangeable with bearings from other makes. 10.2.0 The method and type of lubrication shall be selected by the manufacturer and shall be suitable for the rating (kW), speed and duty involved. 10.3.0 Excess grease escape devices shall be provided. 10.4.0 Grease migration to winding shall be prevented. 10.5.0 Necessary grease nipples for online lubrication from outside shall be provided for both Drive End and Non-Drive End bearings. Whenever grease nipples are provided, these shall be associated, where necessary, with appropriately located relief devices to ensure passage of grease through the bearings. 10.6.0 Name and grade of lubricant shall be given in the motor nameplate. 10.7.0 Lubrication schedule for the motors shall be indicated in the nameplate or shall be furnished separately in the maintenance manual. 10.8.0 Details of bearing shall be furnished in the test certificates, to facilitate ordering of spares. 11.0.0 WEATHERPROOFING 11.1.0 If Outdoor service is specified in the data sheet, the motors shall be suitable for operation in direct sun and rain, without further protection (like canopy, hood, etc.) from weather. However, vertical motors shall be provided with a hood over the fan cover, as an integral part of the motor. 12.0.0 TERMINAL BOXES AND TERMINATIONS 12.1.0 The motors shall be complete with compression type cable glands suitable for the armoured PVC /XLPE main power cables, as specified in the data sheet. 12.2.0 All the six winding ends shall be brought out and marked to one terminal box for power supply connections. 12.3.0 The terminal boxes shall be suitable for the system fault level for 0.25 seconds or as indicated in data sheet. The terminal boxes shall be amply sized to accommodate the cable sizes specified in data sheet. The terminal box shall be provided with pressure relief device if necessary. 12.4.0 It shall be possible to rotate the terminal box in steps of 90 degrees to enable cable entry from any direction. 12.5.0 Live terminals shall be insulated from the frame with material resistant to tracking. FACT ENGINEERING AND DESIGN ORGANISATION 00FT006 ENGINEERING SPECIFICATION 13ES910/14 MEDIUM VOLTAGE INDUCTION MOTORS Page 5 of 6 12.6.0 Flameproof double compression type cable glands shall be provided for flameproof motors approved by CMRI, Dhanbad. 12.7.0 For anti-condensation heater, thermistor, etc. separate terminal boxes shall be provided, with cable glands, suitable for the cable sizes specified in data sheet. These terminal boxes shall be flame proof for flameproof motors. 12.8.0 Main terminal box shall be located on the right hand side of the motor, when viewed form its drive end, unless otherwise specified in the data sheet. 12.9.0 In case star delta starting is envisaged / capacitors are to be connected to the motor terminals, the terminal box shall be of special design by which sufficient creepage space between terminals is available. The terminal box shall be provided with two / three sets of cable glands as specified in the Data Sheet. 13.0.0 EARTHING 13.1.0 All motors shall have two suitable earth studs, capable of withstanding the fault level, integral to the motor frame for motor earthing. The studs should be adequate for accepting lug of the earthing conductor size specified in the data sheet. 14.0.0 NAME PLATES 14.1.0 Two stainless steel nameplates shall be supplied and fastened by SS fasteners. In addition to the data required to be furnished on the name plate as per IS, locked rotor current, temperature rise, type of enclosure, direction of rotation (if unidirectional), weight, grade of lubricant, bearing sizes and ambient temperature for which the motor is designed shall also be indicated. 14.2.0 A stainless steel warning label with indelible red inscription shall be provided on the motor to indicate that isolation of main power supply alone is not sufficient and that space heater supply shall also be isolated before carrying out any work on the motor. 15.0.0 LIFTING FACILITIES 15.1.0 Provision for lifting the motor shall be provided on the motor. 16.0.0 COUPLINGS 16.1.0 The motor shall be supplied with bare, single shaft extension and key. The couplings shall be supplied and fitted by the driven machine supplier. 17.0.0 ANTICONDENSATION HEATERS 17.1.0 The motors of rating 37 KW and above shall be provided with anti condensation heaters to prevent condensation when the motor is kept idle for long periods. The anti-condensation heaters shall be rated for single phase 240 V, 50 Hz. power supply, unless otherwise specified in the data sheet. 18.0.0 PROTECTION 18.1.0 Embedded temperature detectors or thermistors, hot air thermostats, etc. shall be provided in the motor if specified in the data sheet. Where thermistors are provided, thermistor control relay shall be supplied loose in a suitable weatherproof enclosure of cast aluminium. 19.0.0 RECIPROCATING COMPRESSOR FACTOR 19.1.0 Supplier of motors for driving reciprocating compressors shall liaise with the purchaser and the compressor manufacturer to ensure that the compressor factor chosen is sufficient to have a satisfactory degree of current pulsations. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 13ES910/14 MEDIUM VOLTAGE INDUCTION MOTORS Page 6 of 6 MOTOR SUPPLIED ALONG WITH THE DRIVEN MACHINE 20.1.0 When a motor is supplied as a combined unit with the driven machine, the driven machine supplier shall ensure proper co ordination in the selection of motor and its characteristics. The driven machine supplier is also responsible for the suitability of the motor for the equipment and shall guarantee a reasonable defect liability period. 20.2.0 The driven machine supplier shall also ensure the correctness of the motor test certificates, suitability of couplings etc. 21.0.0 ADDITIONAL ACCESSORIES / REQUIREMENTS 21.1.0 The motors shall be provided with additional accessories / requirements, if any, specified in the data sheet 21.2.0 Where any special requirement such as degree of protection to enclosures, thermal cutout, special cable boxes, extra starting torque, supply of half coupling, etc. are specified, these details shall be clearly recorded in the test certificates or in an attached supplement. 22.0.0 DESPATCH 22.1.0 Before despatch, opening in the motor like cable entry should be sealed to prevent entry of moisture and dust during transit and storage. 00FT006 20.0.0 FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION FABRICATION AND INSTALLATION OF CABLE TRAYS AND OTHER STRUCTURALS FOR ELECTRICS 13ES914/14 Page 1 of 2 CONTENTS 1.0.0 2.0.0 3.0.0 4.0.0 5.0.0 SCOPE REFERENCE STANDARDS AND REGULATIONS STANDARD REQUIREMENTS GENERAL REQUIREMENTS 1.0.0 SCOPE 1.1.0 This specification covers the standard requirements for fabrication and installation of cable trays/ racks /risers, frames, supports etc. as per drawings / data sheet enclosed for supporting the electrical items like cables, push button stations, distribution boards, switch boards, lighting fixtures, etc. 1.2.0 Supply of required steel sections for fabrication of the above structures shall be included in the scope of the contractor, only if specifically indicated in the data sheet / price data sheet. 1.3.0 The scope shall also include painting of all mild steel structurals installed as per this specification. 2.0.0 REFERENCE 2.1.0 The following documents shall be read in conjunction with this specification. 2.1.1 Engineering specification and Data Sheet of General requirements for Electrics 2.1.2 Data sheet of Fabrication and Installation of cable trays and other structurals for Electrics 3.0.0 STANDARDS AND REGULATIONS 3.1.0 Fabrication, installation and painting of cable trays/racks / risers, supports, frames, etc. shall be as per standard codes of practice and shall fully comply with the requirements of the Indian Electricity Rules & Acts and also to the Regulations / Standards that are in force at the place of installation. 3.2.0 The steel sections supplied if any, shall confirm to relevant Indian standards. 4.0.0 STANDARD REQUIREMENTS 4.1.0 CABLE TRAYS 4.1.1 Cable trays shall be ladder type, fabricated using mild steel sections as per typical drawings applicable, unless otherwise specified in the data sheet. 4.1. 2 The cable trays are to be connected at joints & bends and fixed to the tray supports by welding/ bolting as specified in the data sheet / drawings. 4.2.0 CABLE TRAY SUPPORTS / RISERS/ CABLE RACKS 4.2.1 The cable trays shall be supported at proper intervals by tray supports / risers as per typical drawings applicable. The cable tray supports / risers with necessary cross arms shall be fabricated using MS sections as per the drawings applicable. 00FT001 PRPD. : CHKD. : APPRD. : FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON SEPT 2014 ENGINEERING SPECIFICATION FABRICATION AND INSTALLATION OF CABLE TRAYS AND OTHER STRUCTURALS FOR ELECTRICS 13ES914/14 Page 2 of 2 Wherever cable racks (direct cable supports without cable trays) are envisaged the same shall be fabricated using suitable MS sections as indicated in the drawings / data sheet. These cable racks shall be made continuous by running a suitable MS section welded to all the racks. 4.3.0 PEDESTALS / FRAMES / SUPPORTS 4.3.1 Pedestals, frames, supports, etc. required for mounting of push button stations, panels, switch boards, fire buckets, distribution boards, light fixtures etc. shall be fabricated, if required, using suitable mild steel sections and fixed at relevant places indicated in the drawings. 4.4.0 PAINTING 4.4.1 All fabricated mild steel sections shall be treated properly for removal of rust, dirt, dust, grease etc. before application of primer. After completion of surface cleaning, all MS surfaces shall be applied with a coat of primer suitable for anti corrosive paint specified in the data sheet. Two coats of anticorrosive paint shall be applied over the primer coat. The required quantity of primer and paint shall be supplied by the contractor. 4.4.2 The two coats of paint shall preferably be of two different shades. 5.0.0 GENERAL REQUIREMENTS 5.1.0 The cable trays/racks / supports/ risers have to be fabricated considering the sizes of cable trenches, number and size of cables proposed in the route, etc, wherever detailed drawings are not furnished. 5.2.0 The owner will provide necessary embedded M.S. plate inserts for welding cable racks / supports, etc. at fixed intervals on the walls of the cable trenches, below the roofs, on the walls, columns, beams, etc. wherever cable route has been finalized by him or if the contractor informs such requirements in advance/before commencement of civil works, to the owner. However, wherever M.S. plate inserts are not available, the contractor shall provide the same for fixing of cable racks / supports, etc. with necessary chipping and replastering the surface concerned. 5.3.0 Where more than one layer of cable trays/ racks are used the spacing between them shall be 150 mm or more depending on the cable sizes. 5.4.0 Necessary holes (with threads wherever necessary) on the steel sections required for fixing of bolts, nuts etc. for cable clamping and mounting of equipment shall be provided before welding and fixing the same. 5.5.0 The welding shall be carried out as per standard codes of practice. All joints shall be full welded. 5.6.0 The contractor shall supply all the necessary consumables including welding rods, gas, etc. and make his own arrangement for welding equipment. 00FT001 4.2.2 FACT ENGINEERING AND DESIGN ORGANISATION 13ES915/14 ENGINEERING SPECIFICATION CABLING INSTALLATION Page 1 of 4 00FT001 CONTENTS 1.0.0 2.0.0 3.0.0 4.0.0 5.0.0 6.0.0 SCOPE REFERENCE STANDARDS AND REGULATIONS STANDARD REQUIREMENTS GENERAL TESTING OF CABLES 1.0.0 SCOPE 1.1.0 This specification covers the standard requirements for erection, testing and commissioning of cabling installation as per the drawings, specification, data sheets and other details enclosed. 1.2.0 Supply of required cables shall also be included under the scope, only if specifically indicated in the data sheet for cabling. 1.3.0 The term cable shall mean power / control / lighting cable for this specification. 2.0.0 REFERENCE 2.1.0 The following documents shall be read in conjunction with this specification. 2.1.1 Engineering specification and Data Sheet of General requirements for Electrics 2.1.2 Data sheet of Cabling installation. 3.0.0 STANDARDS AND REGULATIONS 3.1.0 Cabling installation shall be carried out in accordance with the latest editions of relevant Indian Standards and the installation shall fully comply with the requirements of the Indian Electricity Rules & Acts and other Statutory Regulations that are in force at the place of installation. 4.0.0 STANDARD REQUIREMENTS 4.1.0 HANDLING & LAYING OF CABLES 4.1.1 When unloading cable drums, they shall be carefully lifted and placed on the ground. For removing the cable from the drums, the drum should be properly mounted on jacks on a cable wheel, making sure that the spindle is strong enough to carry the weight without bending and that it is lying horizontally in the bearings so as to prevent the drum creeping to the one side or the other while it is rotating. The drums should be carefully rolled down from a suitably arranged ramp or rails in the direction of arrow marked on the drum. Under no circumstances should a drum be dropped to the ground as the shock may cause heavy damages to the inner layers of cable. 4.1.2 On transporting over a long distance from stores to work spots, the drums should be placed on cable drum wheels strong enough to carry the weight of the drums which are pulled by means of ropes, or alternatively they may be placed on a trailer or a vehicle with a low loading platform for transporting to the destination. 4.1.3 Cable rollers shall be used for laying of cables and cables shall be properly handled while laying to avoid any damages. 00FT001 PRPD. : CHKD. : APPRD. : FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON SEPT 2014 00FT001 ENGINEERING SPECIFICATION 13ES915/14 CABLING INSTALLATION Page 2 of 4 4.1.4 Cables shall be cut to required lengths only after assessment of correct lengths required by actual measurement at site. The contractor shall ensure that wastage of cables is minimum by resorting to most economical cable cutting schedules prepared by the contractor. 4.1.5 The cables shall be laid on trays, racks, risers, walls, structures, etc. and in trenches as shown in the Power lay out (cable layout) drawings. 4.2.0 CLAMPING 4.2.1 Power and Control cables shall be properly segregated while doing the laying and clamping. 4.2.2 MV power cables of 400 sq.mm and above and H.V. cables shall be laid with a clearance of 70mm in between and shall be clamped individually. Other cables can be laid touching and clamped in groups. 4.2.3 Cables shall be clamped at every 1500mm interval on the horizontal trays / racks and at 750mm interval on the vertical trays/ risers, bends, at take off points, and at 400mm interval for cables laid on walls, columns and other structural works. 4.2.4 Cables leading to cable box of an equipment shall be supported at a distance of 450mm from cable gland / cable box. 4.2.5 Cables shall be clamped only after the cables are neatly laid, dressed and kept in position. 4.2.6 Types of cable clamps, fixing bolts / nuts / washers and materials of cable clamps shall be as specified in the data sheet for cabling. 4.3.0 CABLES IN PIPES 4.3.1 Wherever cables are taken through GI pipes, suitable bushes shall be provided at both ends to avoid sharp edges of the pipes damaging the cables. 4.3.2 Wherever cables pass through masonry or concrete work, they shall be taken through suitable PVC / GI pipes. For road crossings GI/ Hume pipes of suitable size shall be provided. 4.3.3 After drawing the cables in the GI / PVC pipes, the ends shall be sealed with cable compound. 4.4.0 CABLE LAYING DIRECT IN GROUND 4.4.1 For laying cables direct in ground, suitable trenches shall be excavated in the soil to the required sizes and at location shown in drawings attached / applicable. Cables shall be laid directly in the excavated trench on the sand bed. After laying cables as per cable/ power layout drawings, the excavated trenches shall be back filled with layers of sand, well burnt bricks and riddled soil respectively as shown in the cross sectional details given in the drawings attached. 4.4.2 A clearance equal to one diameter of the bigger cable shall be maintained between two adjacent power cables buried underground and no such clearance need be provided for control and lighting cables, unless otherwise specified in the data sheets / drawings. 4.4.3 There shall not be any cross over of cables when laid in the ground. 4.4.4 Inspection chambers constructed from brick and masonry complete with suitable RCC slab cover shall be provided for all power and control cable joints in the through run of the cables. Jointed cable shall be looped in the inspection chamber to provide extra length of cable for the purpose of rejoining in future in case original cable joint fails. Cable identification tags shall be provided inside the cable chamber. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 13ES915/14 CABLING INSTALLATION Page 3 of 4 4.4.5 Wherever buried cable enters the building the same shall be taken through PVC / GI pipes embedded at the entry portion. After taking cables through the above pipes, the same shall be sealed by using suitable compound so as to avoid ingress of water. 4.4.6 Necessary cable marker plates made out of Cast iron shall be fixed at every 15Metres interval and at all bends along the route of buried cable trench at central line of the trench. Voltage rating of the cables shall be engraved on the marker plates. 4.4.7 The depth of cable laying shall be as per clause 6.3.2 of IS:1255 4.4.8 The minimum segregation for direct buried cables from other services shall be as given in the table below:MINIMUM CLEARANCE 11/66kV Circuits 6.6kV Circuits 415V Circuits 240V Circuits Instrument, communication and other low signal cables. 4000mm 1250mm 750mm 500mm 600/1000V cables 300mm 300mm None None All piped services below ground and Hot pipe services above ground 500mm 300mm 300mm 300mm 4.5.0 LAYING OF SINGLE CORE CABLES 00FT001 While designing layout with single core cable installations following factors shall be considered 4.5.1 Cables shall be laid as a general practice in trefoil formation touching each other or flat formation with spacing as per requirement. 4.5.2 When cables are laid in a flat formation, the individual cable fixing clamps, and spacers shall be of non magnetic material. 4.5.3 As a general practice, the sheath of single core cables shall earthed to keep sheath at earth potential. However depending on the current the cable has to carry, the feeder length and permissible sheath potential, various methods of sheath bonding are employed, viz. single point bonding, bonding at middle, sectionalised bonding etc., for which cable manufacturers recommendations shall be followed. 4.6.0 4.6.1 CABLE JOINTING During the preliminary stage of laying the cable, consideration should be given to proper location of the joint position so that when the cable is actually laid, the joints if any, are made in the most suitable places. Joints shall not be made at passageways and at road crossings. 4.6.2 In cable trenches or in any other cable route where there are two or more cables laid together, the joints, if any shall be arranged to be staggered by two or more metres so as to reduce the possibility of one joint failure affecting the other. 4.6.3 Before jointing is commenced the insulation resistance of both section of the cable to be jointed shall be measured using suitable megger. 4.6.4 In jointing of armoured PVC cables, hot pouring compound shall not be used. Only cold sealing compound shall be used. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 13ES915/14 CABLING INSTALLATION Page 4 of 4 Individual conductors in cables shall always be jointed number-to-number or colour to colour of the insulation over the conductors. 4.6.6 All materials required for cable jointing such as jointing kit, compounds, insulation tapes, cable lugs, glands, fittings etc. and other consumable materials shall be supplied by the contractor wherever necessary. 4.7.0 CABLE TERMINATION 4.7.1 Cable glands necessary for cable termination on the equipment will be supplied along with equipment. However, the contractor shall supply suitable glands for all other requirements. 4.7.2 Wherever necessary holes are not drilled on the gland plate of the switch boards or on the cable boxes of the equipment for fixing of cable gland, suitable holes shall be drilled at convenient locations by the contractor for fixing the cable glands. 5.0.0 GENERAL 5.1.0 Lighting cables shall be installed in compliance with engineering specification for lighting installation also, if attached. 5.2.0 The armour of the PVC-A-PVC cables shall be effectively earthed at both end terminations through separate earthing of cable glands. 5.3.0 As far as possible, joints at intermediate points in the through run of the cable should be avoided. 5.4.0 The power, control and lighting cables shall be provided with identification tags fixed to them at every 10 m interval. The tags shall be made from full hard aluminum discs not less than 3mm, thick and of size 50mm x 75mm for all cables of size 400mm2. and above and proportionately smaller sizes of tags ( but 3mm thick ) for all other sizes of cables. Tags shall have 4 holes, 2 holes on either side for tying around the cable by using suitable binding wire. The cable numbers assigned in the cable schedule and circuit numbers for lighting distribution cables shall be punched on these tags. 6.0.0 TESTING OF CABLES 6.1.0 All cables shall be tested before and after jointing/ termination as per relevant Indian Standards. Jointing/termination shall be redone, if found unsatisfactory without any extra cost to the owner. 6.2.0 All cables shall be megger tested, and H.V. cables shall be pressure tested (HV dielectric test) in addition to megger test, before commissioning. 6.3.0 The cable cores should be tested for continuity, absence of cross phasing, insulation resistance to earth and insulation resistance between conductors. 6.4.0 All tests shall be carried out in the presence of owner’s representatives and tabulations of observations shall be furnished. 6.5.0 The contractor shall make his own arrangement for necessary testing meters and equipments. 00FT001 4.6.5 FACT ENGINEERING AND DESIGN ORGANISATION 13ES916/14 ENGINEERING SPECIFICATION EARTHING Page 1 of 4 CONTENTS 1.0.0 2.0.0 3.0.0 4.0.0 5.0.0 6.0.0 7.0.0 8.0.0 SCOPE REFERENCE STANDARDS AND REGULATIONS STANDARD REQUIREMENTS LIGHTNING PROTECTION EARTH PITS JOINTS / TERMINATIONS TESTING OF EARTH CONDUCTORS/ ELECTRODES. 1.0.0 SCOPE 1.1.0 This specification covers the standard requirements for supply of earthing materials and accessories and erection, testing and commissioning of Earthing system, as per the drawings and data sheets for earthing. 1.2.0 If design of earthing system is also included in the scope of vendor, the same shall be as per details in the Data sheet of Earthing and relevant design calculations shall be furnished by vendor for purchaser’s approval. 2.0.0 REFERENCE 2.1.0 The following documents shall be read in conjunction with this specification. 2.1.1 2.1.2 2.1.3 Engineering specification and Data Sheet of General requirements for Electrics Data sheet of Earthing Technical particulars of Earthing 3.0.0 STANDARDS AND REGULATIONS. 3.1.0 Earthing shall be carried out in accordance with the latest edition of following standards and shall fully comply with the requirements of the Indian Electricity Rules , Indian Electricity Act, Petroleum rules (where applicable), and also to the Regulations laid down by CEA/ Electrical Inspectorate, OISD, Central/state/ local/ insurance authorities, that are in force at the place of installation. IS: 3043 IS: 7689 IS: 2309 Code of practice for Earthing Guide for control of undesirable static electricity Protection of Buildings and allied structures against Lightning- Code of practice IS: 732 Code of practice for Electrical wiring installations OISD110 Recommended practices on Static Electricity OISD 147 Inspection and safe practices during Electrical installations OISD149 Design aspect for safety in Electrical system OISD173 Fire prevention and protection system for Electrical installations OISD180 Lightning Protection Where conflict exists between standards and codes, the more stringent shall govern. 4.0.0 STANDARD REQUIREMENTS 4.1.0 Duplicate earthing (two separate and distinct connection with the earth) shall be employed for all electrical equipments. The plant earthing system shall have an earthing network with required number of earth electrodes connected to it. The following shall be earthed: System Neutral Current and potential transformer secondary neutral. PRPD. : CHKD. : APPRD. : 00FT001 FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON SEPT 2014 ENGINEERING SPECIFICATION 00FT001 13ES916/14 EARTHING Page 2 of 4 Metallic non-current carrying parts of all electrical apparatus such as transformers, Switchgears, motors, lighting/power panels, terminal boxes, control stations, lighting fixtures, receptacles etc. Steel structures, loading platform etc. Cable trays and racks, lighting mast and poles. Storage tanks, spheres, vessels, columns and all other process equipment. Electrical equipment fencing ( e.g transformer yard etc.) Cable shields and armour. Flexible earth provision for wagon,truck. Pump handling Hydrocarbon if it’s base plate is separate from motor’s base plate. Turbo driven pump handling Hydrocarbon. 4.2.0 Earthing cables / strips shall be taken along with the power cables on the cable trays / racks / risers. All earthing shall be done on the body of the equipment and not on the detachable part. 4.3.0 Earthing cables shall be clamped at every 1500mm. interval on the horizontal trays / racks, 750mm interval on vertical trays / risers, 400mm interval on walls / columns / on structural using spacers, and at bends / take off points. Bare earthing strips shall be clamped at 3000mm interval on horizontal trays / racks, 1500mm interval on vertical trays / risers, 800mm interval on walls / columns, and at bends / take off points. 4.4.0 Metallic cable trays / risers shall be earthed in duplicate. Continuity of earthing throughout the tray shall be ensured. GI strips, if used for cable tray earthing, shall not be welded to trays, to prevent corrosion. 4.5.0 Wherever insulated earth conductors are taken out from the cable trenches, walls / through floor, etc. they shall be taken through non-metallic or GI pipes. In the case of bare earth conductors, non-metallic pipes shall be used. 4.6.0 Wherever earth conductor crosses the road, it shall be taken through GI pipes / non-metallic pipes / formed cable trenches. In the case of bare earth conductors metallic pipes shall not be used. 4.7.0 At all terminations of earth conductors on equipment, sufficient length shall be left for easy movement of the equipment from its position for alignment purposes. 4.8.0 Wherever not detailed, the route of the conductor and location of the earth pit shall be arranged, so as to avoid obstructions, crossing, etc. according to convenience at site and shall be got approved by the Engineer in charge at site or his representative. 4.9.0 Wherever required, earthing cables / strips shall be buried along with power cables. 4.10.0 Earthing cables / bare earth strips used for interconnection of earth pits, run as ring main shall be buried in ground at a depth of 500 mm below finished grade level. 4.11.0 Wherever looping earth connections are envisaged between motor and local push button stations, the same shall be done using common lug at motor end as shown in IS: 3043. 4.12.0 Unless adequately connected to earth elsewhere, all utility and process pipelines should be bonded to a common conductor by means of earth bars or pipe clamps and connected to the earthing system at a point where pipelines enter or leave the hazardous area except where conflicting with the requirements of cathodic protection. 4.13.0 Steel pipe racks in the process units and offsite area shall be earthed at every 25 metres. FACT ENGINEERING AND DESIGN ORGANISATION 00FT001 ENGINEERING SPECIFICATION 13ES916/14 EARTHING Page 3 of 4 4.14.0 Tanks, piping and process vessels and equipment containing flammable liquids or gas shall be earthed by a connection to the earth network, or by bonding to an earthed metal structure for protection against static electricity. 4.15.0 The sheath of single core cables shall earthed to keep sheath at earth potential. However depending on the current the cable has to carry, the feeder length and permissible sheath potential, various methods of sheath bonding are employed, viz. single point bonding, bonding at middle, sectionalised bonding etc., for which cable manufacturers recommendations shall be followed. 5.0.0 LIGHTNING PROTECTION 5.1.0 Lightning protection shall be provided for the equipment, structures and buildings as per the requirements of IS: 2309. 5.2.0 An independent earthing network shall be provided for lightning protection and this shall be bonded with the main earthing network below ground, minimum at two points. 5.3.0 Lightning protection for the plant structures, storage tanks and columns in the hydrocarbon industry shall be carried out as per OISD 180. 5.4.0 An earth electrode should be connected to each down conductor. Each of these earth electrode should have a resistance not exceeding the product given by 10 Ohm multiplied by the number of earth electrodes to be provided. The whole of lightning protective system including any earth ring shall have a combined resistance to earth not exceeding 10 ohm without taking account of any bonding. 6.0.0 EARTH PITS 6.1.0 The arrangement of earth pit shall be as given in IS: 3043 unless otherwise specified in the data sheet. Necessary provisions for terminating main earth conductors on to the earth electrodes shall be ensured. 6.2.0 All accessories required for the earth pits such as electrodes, clamps, clips, bolts, nuts, washers, GI pipes, funnel, valve and the masonry works of the pits including supply of necessary materials, cement and excavation and refilling of soil for providing earth pits shall come under the scope of the contractor. 6.3.0 Water supply for watering of earth pits will be given by Purchaser at one point. Common valve for isolating and 1" distribution pipe to earth pits shall be provided by the contractor. Individual taps shall be provided for each earth pit, if specified in the data sheet. 7.0.0 JOINTS / TERMINATIONS 7.1.0 The joints of bare earth strip shall be bolted/ riveted / brazed / welded as stipulated in IS: 3043. All such joints shall be given necessary coatings of suitable compound to prevent corrosion. 7.2.0 In the case of PVC insulated earth conductors proper joints shall be made and the entire joint shall be fully sealed by suitable compound so that no metallic part is exposed. 7.3.0 Crimping type of lugs shall be used for termination of earth conductors. However in the case of bigger size of earth conductors where crimping type of terminations are not feasible, soldering type of lugs may be used. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 13ES916/14 EARTHING Page 4 of 4 The contractor shall make his own arrangement for the necessary equipment, drilling / welding machines and all other tools and tackles which are necessary for completing the installation. 8.0.0 TESTING OF EARTH CONDUCTORS / ELECTRODES. 8.1.0 All earth conductors shall be tested before and after jointing / termination as per relevant Indian Standards. Jointing / termination shall be redone, if found unsatisfactory, without any extra cost to the purchaser. 8.2.0 Earth pits shall be checked & tested for proper connections / terminations. 8.3.0 Each Earth electrode shall be tested as per relevant Standards and results tabulated. 8.4.0 Effective resistance of the earthing system shall be tested and tabulated. 8.5.0 All tests shall be carried out in the presence of Engineer -in- charge or his representative and tabulations furnished. 8.6.0 The contractor shall make his own arrangement for the meters and equipments necessary for the testing. 00FT001 7.4.0 FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 13ES927/14 LIGHTING INSTALLATION Page 1 of 6 CONTENTS 1.0.0 2.0.0 3.0.0 4.0.0 5.0.0 6.0.0 7.0.0 SCOPE REFERENCE STANDARDS & REGULATIONS GENERAL REQUIREMENTS WIRING EARTHING TESTING 1.0.0 SCOPE 1.1.0 This specification covers the general requirements for erection, testing and commissioning of lighting system as per the Schedule of items of work/ drawings/ documents/ data sheets and general conditions of contract, including supply of required materials and accessories. 2.0.0 REFERENCE 2.1.0 The following documents shall be read in conjunction with this specification. 2.1.1 2.1.2 2.1.3 Engineering specification and Data Sheet of General requirements for Electrics. Data sheet of Lighting Installation Technical particulars of Lighting Installation 3.0.0 STANDARDS 3.1.0 Lighting installation shall fully comply with the requirements of the Indian Electricity Rules, Regulations, Acts and other statutory regulations that are in force in the place of installation and also carried out in accordance with the latest editions of relevant Indian Standards, particularly the following. IS: 732 IS: 6665 IS: 3043 IS: 1554(Part I) IS: 694 IS: 1293 IS: 3854 IS: 371 IS: 2412 IS: 3837 IS: 3480 IS: 3419 IS: 9537(Pt II &III) IS: 1332 IS: 2193 IS: 2713 IS: 2551 IS:4736 IS:14768 OISD 149 PRPD. : Code of practice for electrical wiring installations Code of practice for industrial lighting Code of practice for earthing PVC insulated (Heavy duty) electric cable. PVC insulated cables Plugs & socket outlets Switches for domestic and similar purposes Ceiling roses Link clips for electrical wiring Accessories for rigid steel conduits for electrical wiring Flexible steel conduits for electrical wiring Fittings for rigid non-metallic conduits Conduits for electrical installations Precast reinforced concrete street lighting poles Precast prestressed concrete street lighting poles Tubular steel poles Danger notice plates Hot dip Zinc coatings on mild steel tube Conduit fittings for Electrical installations Design aspect for safety in Electrical system CHKD. : APPRD. : 00FT006 FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON SEPT 2014 00FT006 ENGINEERING SPECIFICATION LIGHTING INSTALLATION 13ES927/14 Page 2 of 6 4.0.0 GENERAL REQUIREMENTS 4.1.0 Scope of work shall include installation of lighting fixtures, fans, plug socket outlets, distribution boards (DB) etc. with all associated accessories and materials required to make the installation complete in all respects even in cases when such items are specifically not mentioned. Cost of all such miscellaneous items shall be included in the price of installation quoted, unless specifically excluded from the scope. 4.2.0 All items shall be of makes specified in the data sheet. Wherever makes are not specified, the items offered shall be of reputed make and got approved by purchaser/ engineer in charge at site, before ordering. 4.3.0 Wherever cables/ wires are to be passed through masonry works, road crossings, cement floors etc. they shall be protected by taking through GI pipes/ conduits (metallic/ PVC). After wiring up, the walls, floorings etc. shall be restored to the original condition. 4.4.0 All exposed metal parts are to be coated with primer and paint as specified in the data sheet. 4.5.0 Utmost care shall be taken to avoid scratches kinks and cuts on the conductor while transporting the wires/ cables to site during installation. Suitable inhibiting grease shall be liberally applied to bare Aluminium conductors, before connecting them up. 4.6.0 The junction boxes, cable end boxes etc. wherever provided shall have sufficient wiring space in relation to the size of cable/ wire specified. Items supplied shall be complete with cable glands, cable boxes, conduit entries, terminals etc. and other accessories, which are necessary for the satisfactory installation/ operation of the lighting system. 4.7.0 Cables to and from lighting switchgear/ distribution board shall be laid in trenches/ racks/ trays available along with power cables. In other areas cables shall be clamped properly on steel surface using MS spacers. (MS spacers shall be welded to the surface). On concrete surface cable shall be directly clamped. Cables leaving or entering cable trenches other than buried shall be taken through GI pipes to 1.2m above ground/ floor level. The cables taken over walls/ columns/ racks shall be properly clamped using Aluminium clamps of 16SWG sheet, with width varying from 12.5 to 25mm. 4.8.0 The contractor should possess a contractor’s license (valid up to date) issued by the State Electricity Licensing Board. The work should be got carried out only by licensed wireman under the supervision of licensed supervisors. 4.9.0 Wooden materials shall be coated with good quality varnish. 4.10.0 Sufficient number of earth pits shall be provided if found necessary or if specified in the drawing/data sheet and interconnected so as to have the resistance of the earthing installation within the limits as per relevant Indian Standard. 4.11.0 All distribution boards shall be marked LIGHTING or POWER as the case may be and also marked with the voltage and number of phases of the supply. Each DB shall be provided with the drawing giving details of each circuit with its control, the current rating of the circuit, the rating of the fuse elements/ MCBs and all-important details given in the circuit diagram. The drawing shall be made on durable material like PVC and pasted inside the front cover of the DB. 4.12.0 Locations of lighting fixtures, ceiling fans, plug sockets etc. shown in the drawing are indicative. They shall be located to suit the site conditions subject to the approval of purchaser’s engineer in charge. 4.13.0 All switches and plug socket outlets shall be mounted at a height of 1.5m above floor level unless otherwise specified in the drawing. FACT ENGINEERING AND DESIGN ORGANISATION 00FT006 ENGINEERING SPECIFICATION LIGHTING INSTALLATION 13ES927/14 Page 3 of 6 4.14.0 All emergency DBs shall have the words “ Emergency AC/ DC” (as the case may be) painted on it in large letters in RED paint. Emergency lighting fixtures shall be marked “E” in RED. 4.15.0 Serial numbers if any allotted to each DB in the drawing shall be painted on it in RED for emergency DBs and in WHITE for other DBs. 4.16.0 Respective circuit numbers shall be painted on the lighting fixture at a conspicuous place if so specified in the data sheet. 4.17.0 All fuses shall be of HRC type unless otherwise specified in the drawing/ data sheet. 4.18.0 The scheme followed for circuit numbering is as given below unless otherwise specified. 4.18.1 4.18.2 4.18.3 First two digits indicate the serial number of the DB Third digit indicates the serial number of the circuit (way) in each phase. The letter after the digit indicates the phase of the circuit. 4.19.0 DBs, main switches etc. shall be mounted on painted MS angle frames or MS boxes. 4.20.0 Where ceiling fans are provided, lighting fixtures shall be suspended by means of conduits such that the fan blades and lighting fixtures are at the same level. 4.21.0 On walls/ columns/ handrails, lighting fixtures shall be mounted on suitable GI pipes/ MS angle frames. On ceilings the fixtures shall be mounted on suitable MS brackets, wooden blocks etc. 4.22.0 Fan hooks shall be provided on RCC slabs/beams by chipping the concrete and hooking to the reinforcing rod if indicated in the drawing. The slab /beam surface shall be restored to the original condition after providing the hook. 4.23.0 Similar parts of all switches, lamp holders, distribution fuse boards, ceiling roses brackets, pendants, fans and all other fittings shall be so chosen that they are of the same type and interchangeable in each installation. 4.24.0 Lighting installation in oil and gas installations shall be as per OISD 149. 4.25.0 Aviation warning lights shall be in accordance with the convention of the International Civil Aviation Organisation (ICAO) Publication Annex 14 and to Indian standards, together with the approval of the local aviation authority. 5.0.0 WIRING 5.1.0 GENERAL 5.1.1 Looping back system of wiring shall be adopted. Looping of cables shall be carried out only from control gears / junction boxes / ceiling roses and not from lighting fixtures. 5.1.2 Control switches and plug socket outlets shall be mounted on painted MS box / PVC box as indicated in the data sheet. Front plate of these boxes shall be of the material specified in the data sheet. 5.1.3 Junction boxes shall be of PVC/ painted MS box/ cast aluminium as specified in the data sheet. 5.1.4 Flush type ceiling roses shall be provided if indicated in the drawings. Ceiling roses shall have terminals for connecting 3-core cable. 5.1.5 More than two wires shall not be connected to a terminal of ceiling rose/ switch/ plug socket outlet etc. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION LIGHTING INSTALLATION 13ES927/14 Page 4 of 6 The number of stranded conductor cables drawn into or laid into an enclosure of a wiring system shall be such that no damage is caused to the cable or to the enclosure during their installation.The maximum number of stranded conductor cables that can be drawn through a conduit shall be as per IS:732 5.2.0 CABLE WIRING 5.2.1 Use 1.1kV grade heavy duty PVC-A-PVC Aluminium/ Copper cable of size and number of cores indicated in the drawing for circuit mains (ie. from DB to control gear/ junction box of the first point in the circuit) and distribution (ie from control gear/ junction box of the first point to the control gear/ junction box of the adjacent point in the circuit and so on). 3 core 1.5 sq mm PVC insulated and sheathed unarmoured stranded copper cable shall be used for connecting fans / non flameproof lighting fixtures to the control gear/ junction box. In the case of flameproof lighting fixtures 1.5 sq mm PVC-A-PVC copper cable shall be used. 5.2.2 In the case of street light fixtures mounted on concrete/ steel poles, wiring from DB to the junction box provided at the bottom of the pole and looping back to the junction box of the adjacent pole in the circuit shall be done using 1.1kV grade PVC-A-PVC Aluminium/ Copper cable of size indicated in the drawing. The incoming cable shall be connected to a terminal block to be provided in the junction box by the contractor. Wiring from the terminal block to the lamp shall be done through a 2A HRC fuse using 3core 1.5 sq mm PVC insulated and sheathed stranded copper cable. (The third core is used for earthing the fixtures) 5.2.3 240V, 15/5A, 3 pin plug socket outlets shall be wired using 1.1kV grade 3 core PVC-A-PVC Aluminium/ Copper cable of size indicated in the drawing. 5.2.4 Armoured cables shall be terminated using flameproof cadmium plated brass cable glands in the case of flameproof equipment and ordinary cable glands in the case of non flameproof equipment. 2 Crimping type tinned copper lugs shall be used for conductors of 6mm and above. 5.2.5 Lighting cables shall be identified by providing tags (Aluminium discs 3mm thick) at 10m intervals. Circuit numbers indicated in the circuit diagram shall be punched on these tags. 5.3.0 CONDUIT WIRING 5.3.1 Rigid/ flexible PVC conduits or rigid steel conduits or rigid flow-coat metal conduits with ISI mark and of suitable sizes shall be used as specified in the data sheet. 5.3.2 Use PVC insulated single core Aluminium/ Copper cable of size and number of cores indicated in the drawing for circuit mains (ie. from DB to control gear/ junction box/ ceiling rose of the first point in the circuit) and distribution (ie from control gear/ junction box of the first point to the control gear/ junction box/ ceiling rose of the adjacent point in the circuit and so on). Use 3 core PVC insulated and sheathed unarmoured 24 strand (each strand having 0.2mm dia. minimum) copper cable for connecting lighting fixture/fan to ceiling rose. 5.3.3 240V, 15/5A, 3 pin plug socket outlets shall be wired using single core PVC insulated Aluminium/ Copper wires of sizes specified in the drawing. 5.3.4 Circuits of different phases shall not be drawn in the same conduit. However balanced 3-phase circuit and neutral can be drawn in the same circuit. 5.3.5 The entire system of metallic conduit work, including the outlet boxes and other metallic accessories, shall be mechanically and electrically continuous by proper screwed joints, or by double check nuts at terminations. The conduit shall be continuous when passing through walls or floors. 00FT006 5.1.6 FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION LIGHTING INSTALLATION 13ES927/14 Page 5 of 6 TRUNKING CABLE MANAGEMENT SYSTEM 5.4.1 Adaptable trunking shall be used for power cables and data cables to run parallel in two different compartments with partition. 5.4.2 PVC insulated cables and / or other approved insulated cables to IS: 694-1990 shall be used in this type of work. 5.4.3 Preferred size of the mini trunking (Casing wiring) should be 25x16 mm, 32x16 mm, 40x25 mm, 40x40 mm and for adaptable trunking it should be 100x34 mm or 100x50 mm or 160x50 mm or 200x50mm for making upto four isolated compartments. 5.4.4 Trunking should be equipped with rail on its surface on which clip-on partition can be clipped which should accept frames/plates for wiring devices upto 6/8 modules. 5.4.5 The mini trunking and adaptable trunking shall be of the same material, viz. either PVC or anodized aluminium in extruded sections. 5.4.6 The mini trunking shall have a square or rectangular body. The trunking cover shall be “CLIP-ON” type with double grooving in the case of PVC wire-ways, and CLIP-ON type for the metallic wire ways. All surfaces shall have smooth finish inside and outside. The top of the side walls of the body shall be suitable for the above types of fixing arrangement of trunking. PVC trunking or Aluminium trunking should have uniform thickness throughout its length and shall be of factory finish. The thickness of the mini trunking & adaptable trunking shall be 1mm minimum. 5.4.7 The mini trunking and adaptable trunking shall be fixed by means of suitable screws to approved type of asbestos or fiber fixing plugs, at intervals not exceeding 60 cm for all sizes for mini trunking. In case of Adaptable trunking, the screwing distance shall be such that the weight of the trunking & cable hold firmly on the wall or ceiling. On either side of the joints, the distance of the fixing arrangement shall not exceed 15 cm from, the joint. 6.0.0 EARTHING 6.1.0 All DBs shall be provided with an earth bus of the same size in addition to three buses for the phases and one for the neutral, which shall be connected in duplicate to the main earthing system using PVC insulated/ bare Aluminium/ Copper conductor of size indicated in the data sheet. 6.2.0 All DBs and main switches shall be earthed in duplicate using PVC insulated/ bare Aluminium/ Copper conductor of size indicated in the data sheet. 6.3.0 Lighting fixtures, E point of plug socket outlets, control switches junction boxes etc. shall be earthed using conductors specified in data sheet. 6.4.0 Where 3 core cables are specified for wiring, the third core shall be used for earthing. 6.5.0 All earth wires shall be connected to the main earthing system. If earth pits are provided specifically for the lighting installation in the drawings, they shall be interconnected using conductors specified in the data sheet and also linked to the main earth system. 6.6.0 A protective (earth continuity) conductor shall be drawn inside conduits and trunking for earthing of all metallic boxes of the installations as well as for connections to the earth pin of the socket outlets. 00FT006 5.4.0 FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION LIGHTING INSTALLATION 13ES927/14 Page 6 of 6 7.0.0 TESTING 7.1.0 The following tests shall be conducted satisfactorily, by the contractor at his own cost, in the presence of the purchaser’s representative; test results shall be submitted and results got approved. Insulation test Earth resistance test Earth continuity test Continuity test. Operation of ELCB. 00FT006 7.1.1 7.1.2 7.1.3 7.1.4 7.1.5 FACT ENGINEERING AND DESIGN ORGANISATION 00ft024/14 TECHNICAL PROCUREMENT SPECIFICATION SUB VENDOR LIST (ELECTRICAL) FOR PHOSPHORIC ACID STORAGE TANK 32644-13-PS-001 SV Page 1 of 2 R0 5.4 INDUCTION MOTORS – LV (415 V) (SAFE / HAZARDOUS AREA) 1 ASEA BROWN BOVERI LTD. INDIA 2 FUJI ELECTRIC SYSTEMS CO. LTD. JAPAN 3 SIEMENS LTD. INDIA 4 TOSHIBA CORPORATION JAPAN 5.6 HT / LT POWER & CONTROL (11 KV, 6.6 KV & 415V) POWER CABLES 1 NICCO CORPORATION LIMITED INDIA 2 TORRENT CABLES LIMITED INDIA 3 UNIVERSAL CABLES LTD. INDIA 5.8 SWITCHBOARDS – LV (415 V) (MCC / PCC / PMCC) 1 ABB LTD. INDIA 2 LARSEN & TOUBRO LTD. INDIA 3 SIEMENS LTD. INDIA 5.17 FLAMEPROOF / HOSEPROOF LOCAL CONTROL STATION, JUNCTION BOX, LIGHTING FITTING, PLUG, SOCKET, HAND LAMP, ACCESSORIES LIGHTING, DISTRIBUTION BOARD & CONTROL PANEL 1 BALIGA LIGHTING EQUIPMENTS LTD. INDIA 2 FCG FLAMEPROOF CONTROL GEARS PVT. LTD. INDIA 3 FLAMEPROOF EQUIPMENTS PVT. LTD. INDIA 4 R. STAHL INDIA/GE RMANY 5.18 STREET / FLOOD LIGHTING FIXTURES 1 PHILIPS INDIA LTD. 5.19 LIGHTING POLES 1 BAJAJ ELECTRICALS LTD. INDIA 2 CROMPTON GREAVES LIMITED INDIA 3 PHILIPS INDIA LTD. INDIA 5.20 FLAMEPROOF / HOSE PROOF INDUSTRIAL LIGHTING FIXTURES 1 BALIGA LIGHTING EQUIPMENTS LTD. INDIA 2 FCG FLAMEPROOF CONTROL GEARS PVT. LTD. INDIA 3 FLAMEPROOF EQUIPMENTS PVT. LTD. INDIA 0 06-06-2020 Original issue REV. DATE DESCRIPTION INDIA SM IK IK PREPARED CHECKED APPROVED FACT ENGINEERING AND DESIGN ORGANISATION 00ft024/14 TECHNICAL PROCUREMENT SPECIFICATION SUB VENDOR LIST (ELECTRICAL) FOR PHOSPHORIC ACID STORAGE TANK 32644-13-PS-001 SV Page 2 of 2 R0 4 R. STAHL 5.23 DISTRIBUTION BOARDS 1 CONTROLS & SWITCHGEAR CO. LTD. INDIA 2 ELECMECH CORPORATION INDIA 3 INTRELEC INDIA 4 LOTUS POWERGEAR PVT. LTD. INDIA FACT ENGINEERING AND DESIGN ORGANISATION INDIA/GERMANY 32644-13-PS-001CS PROCUREMENT SPECIFICATION COMPLIANCE STATEMENT PAGE 1 OF 1 TPS No. 32644-13-PS-001 We state that our Quotation No……….……………….………….. is in full compliance with the documents issued against the Enquiry No. …………….………………..….. except for the deviations listed below. LIST OF DEVIATIONS S. No. Description Reasons for Deviation Name of Vendor: 00FT014/14 Date: Name & Designation FACT ENGINEERING AND DESIGN ORGANISATION Seal & Signature R I 4 3 I 2 AT SUB-STATION FROM ElllSlllG MCC MCC � ---� 'JIJ0/1A v� (LOCAlED IN HEAVY EQUIPMENT WORKSHOP) 1 A c:..:J D D I� 415V, 200A, 35MVA,(llj � 3Ph+N 50Hz BUS )i - � )i )i )i 1 � 1' �I � 1 2 4 3 5 ' )i )i )i )i ,, ;f :-(A) ,_ Ct;� FEEDER No. ' �h� h . ,' . , 1 � )i 6 @ 7 � ,__ B 9 10 z "T Q. :, Ill � "' Q PANEL DESIGNATION (NAME PLAlE DATA) (!) Zc Cf S'MTCH FUSE/ MCCB RATING (A) CT RATIO (METERING) CT RATIO PROlECTION) CT RATIO iREF ) . CT RATIO (STAND-BY E/F) PO'IIER CABLE (Runs.lt'=exSizel (XI.PE AL) COllR(1 CABLE (P'it-A-PI/C . Cu ) (Runs I Core x Size so.mm) SP CE HEAlER CABLE ARunsA#-PI/C CoreCu.)x Size sq.mm) il"it - < :, Q. Q. 0:: � z < I!: 0:: L,J � �!li: <!>O L,J 0:: 32 63 - - - 200 32 63 - 200 200/1 Bi Q. ::E Bi ii! - - - - 0 2::: -fl- B � ~-E3- - � z < I!: < - - - (!)� �� < Bi !!l:;!5 Bi L,J 0:: - - - L,J 0:: 63 32 63 32 - EXPLANATION SYMBOL � � MAGNETIC A CONTACroR, MICRO PROCESSOR :i� PROT. REIAY I VJ 3 PHASE SQUIRREL CAGE INDUC110N MOTOR MINIAl\JRE CIRCUIT BREAKER I!'!] � � HRC FUSE CURRENT lRANSFORMER ji SWITCH FUSE CABLE TERMINAllON "11'14 -,!,- ........ EXPLANATION INDICAllON IAIIPS VOI.TMEIER PUSH BUTTON STATION WITH ON OFF BIITTON & AMMEIER AMMEIER SELECTOR SWRCH B VOLTMEIER SELECTOR SWITCH MULTI AJNCllON MEIER E:ARTH CONNECTION DRAW OUT F£Al\JRE ,__ PROJECT NAME: 1 EW PA TANK A T Q10 BERTH-W.ISLAND 0 PRELIMINARY DESCRIPTION SC ALE: -- A NO. r-.......... r-0 0 0 0 C ,__ t- 'v 0:: - - - - LEGEND SYMBOL L,J :, L,J 0:: :JIil FEEDER RATING MOTOR RATING (k C < Q. ::E :, Q. ,_ "'� I Q. ::E ::E IK SM Soman DRAWN CHKD SINGLE LINE DIAGRAM (TYPICAL) 4 I KERALA 3 - 0 A DRG. NO. 32644-13-SD-00 101 REV. FACT ENGINEERING & DESIGN ORGANISATION UDYOGAMANDAL 32644 03.06.'20 TITLE APPRD. DATE SHEET 1 OF 1 I CLIENT: M/s. FACT-CD PROJECT NO: 2 l�-•=-•I•JI 1 8 9 10 11 12 6 7 3 4 5 2 H H GN I� i}•� Jj_ I � _I c'lff _ll'-IE 0·1::, [[Vi' ::_,L '.�ii.i)j_;j_j_,'i G 11,,�i//'' I111- l -iCL :_1·,_1/ J,---::n- u =·E 5, 6 A \1\ �. Q TT77:'/ f1,,1HCr1 I L 1 PN \' J !m� ,J:, G I c::: WALK WAY CUM PIPE BRIDGE l� J.5M WIDE' C C ' ' 1"1 IC) -� s� - r,-1 ,, , ,, o/R1: _ c -Tn -JliL □ □ 1/ /,_L:10,J ,,k,,H,LIr 1!/[_,,< :; la� l_ F ')�; I'/i,,..,/, ,..._ I '":1 C.UJ ·- / . // , '"!' /;;•--:• ,, ,1, , c'./.-•:;J-i-[- � ,W-T' __ -� -'.,i:.P:��== Jl 21.7 1-,,5 1� , _ 0 ,� B B J '/r'?1',gi � � □ _k_ [ -'°'� � ·:�:.: 1.3 l_,r "J" SY" :, ''":)§'· IN-IK1IIA&i;:- � � 1 �f f· 0 \,,,£ :t)l,.J!,,1;:;,i,,.•,.);' ""' i�r,\'·1c,,0 ;;,�, I I SULPH. ACID LINE FROM SHIP � >\1 __ c,, I '//l "(> s:·_;;'f_;::;.,;, j/i(l'i, /iif/.J/' :r'Q \; , m ;j3':f1;:_I :';'f/i ,-_:_�1::,-.,.;':;', 'ti □ #.O;·,,-�J,,r=��=�:_:�_:;;-=_:;;_:;;_._:Jtl,k""�::1t:=��::::::::== ===== . 1 1 __. _.�,/J,._,,,,/,_,;.•,,"-;.,,1iflJ..i:•,:;;.,�I N PC, NTTO BAR<iE ='""' � � � 'i ",�1 ✓',- 'f;c ;;c�q1, U� 1ii,,. 'It= 1 ii✓ �;cc/<, • I "I �C =====�-- -- :.:-::. ..: - . . •,;.'6:,--.-}a�'#/ ,I_' / /L-••��� •/ \;.. •'.C/ ,,,,,_,"<§'';/&. -·�- . ,..iliWf ... \!;, 'f"'</!: i_i}•;!?,•,c:--,... V •. ,,_,__, F' I'l = �,-;1___,.,_,,., ;_:4,1:1f!·---- ,,w ,,. '" , , 1 ?\9i '.<')1 "*-',_"-� ,•.:-:,""" ,,.,.:·_ '!::..... ,..... -I/vi<>-_ : ·-f�, " <. ,..:;,.,,, > '\¾ 1 ,-; �-11--c::r--. ·-c::::,. ,,,: .. . ,,, o-.· <:t�l�; "\-, -,::1, 'iJ .;,;/Ji/;/::mf: 18 - � ·;;,<_ -----�---,-ii::::; u,!-.1J;)'>;,,, /'!/,c<i11t!,s,� ' !!fiJJff!W:£!!lfl;?::t,:z, \ �� g' &,$' �,, 1f'., o/ ,,._., � _,.-,11,,-,,, � ' ; '7"' \�·::'-'�(, ;;'.;'';;;7, !;. ; " i. E 'ii/i-ii/!!0;-;.;'_'ooou i'm'll t,,�iri ��"' N • .; , 1 ),; �[L•,:_, w� ·1'#.1�¾·,'�10":ii/j -,-�{7_/ ·,�•-;'t..'_/1 J1_-- - f�(:,-)-,-� -'!.�Ir:7 -/ ,1.lL__ _/-, 1 : 1 1"-//- 111-.=J -/ l-,:,r . �) , ·--------- � ,- 2; l I , . ,'. - . ,,--; 0?_,�;?; \ J ·- 1zf�t<h (Cb ✓ � I , �'.? -- --,,,��-:,�- 7T7'"'''1'c ------ . . 'lie TR'·_ ·•_ E_'.::_i II./(;,,.:,,, -·pF·_ ,-, C•01· ,I' I' . ; ,-_LJl·'.I __,I O • p , •. -----1--< 'I llt ,,,- ---c;i;- 'Ij:11,, , : .. .;, ,fr .. . � 1 • .• • • • "· , i/ii/•. , ---���tR1' --iftP1"= rn1'"'0 :GE,sw J,jJr·•·:,;�Ji:-:',:,1{ -. "<., ' t�c1(0'7ff';, :,�. . .� z ,J. .. ' !$://,:c-,"l1/iilli;?f, J' .,1 ' ,!:"",, ,--,, b:2.C'1 � iii -:--- , � , 1- l '!<-1-'' �'<9 \ts-'.:o� <t ' i < �- . . ---.. ' - �R I JI:[ \ CiC!CCO •= » e'l', , 25 77 205 ::i":,/-'11-.1(1 1J --,_:� cc , .- ,, \s;, ,,, Cl C cc L L \ I �-I \ ----���,,.-:_- ��: I - cii� / • '<>--�;;-11:_ ,,•_ 1; L_.,. .,,,_; . ;,�:: '-"_ 1�/1 > �6Ji ·::. �- �'<- '<t; � Jpp.-,,:r:;i2 :c�:-i-N.I WAL: -, ,c C CO -• 0 • • ;· ·• •' ,;,;, - --�� - PCAD I'' 1''111- - - , ' '-. 7;_. ·,- - ·, <• - <§'<o/ l ...., .L ..._._.::_..::':'':;'_1_.11(1! ___ ,-tJ!iicXR,iei'tl\ - LES 81PllU &.: � �- F f-­ c /"" - -- I � I ��-- F,-,u � � ·--! - -r· _='FT."'.ll·-.111·-.IC 'il'A I w ·,r-.,, ;_--; "le,";-' 11 i;?-, Ui 11 ·';['ii,n , 111_·i·i ! 1 L�1l:, '"" iz-;; - 1- , ✓- 22.0·=1 n Id F,_�'.'{ b}i ,�,-,,;� � ' <§' "> +- I ' PROPOSEDDR/,ni-t»/ ' 2 7 1 J� ��=:·:��.�:..,,r'--�t :\ :;: • · 7 : ; : { 2-., � ;xw�-·r:· ,t;tifrit&ff,21wM·.; . •.., . ·. .. - � :';'-· )ABLc '.i _ol: KRIF J : 1, � I ]11,i : 1 .1 . .:�n. :,.�__··>J,- �� •' ',:;- · D , 'P"'-t r-ft "' �·--,�/ · c1· .-Lha ··-, fJ � .IT-' ,_ ..,,r -1-,r-ll.Jlh-.-,,. -J :1' T,"':01!f[7::_-� ;,:u- i,' II .. _ , -,- . ' •:, .I I j 1- � / e,-_. _ , _ · ,,-•cF,, c,cH-.H::l I ,,-.,,T PIP="· Tu-,--;,- --:, _ __,-- . .L_ /;--� / Ll:.: . / ' [ "-;' _; . :, i-,- �-U_-'-/];;J__/_-.�,.:.,_ � ,RIED Jt•.JUl '\ -=-----,__ r;,:-)ul--.JD I: 11-'/i'c::,,sl�::::HBD/\=-.'D :�'c;::,T;�T_f'i ccTfc;_,r; �'!;'ET:G�,c.,! · .._'r' � -- '., '• ,. •.·,, r· ' ,· ,., " - -1 r· , l �'-"" 3c '--I , -� ,'-] 113989 ) � r-1.t[ I �J ') ) '�•••·�'1138 ]r-r l el;c/--1 S -• 9 �.. >l L <--1 >� ', J--1,- / -_-1 ;_- cf'�� [,.i r o -� ' ' -1__, 'C--1 C ,"r-1--,HL ::;1 ,- JURIE[1 /� ,-L! ,: t[,ck ck JcJI I, 0 ,",--' r-!.. 1 � � l, ; � i 1 � r cl< ',/,, ! ,,:•• !� lF::�/L 1-::..._s, _;,__, ' '.:Ail FS I< C/',3_E TG.�: ·:.1_. -,r-,:._; I I) 01··. 1_1·1,<� � :-:-c---;c;�='f7"'.T)'"'° RCA; r · , , ,--• I I � --1 '----1 1=:_ (=:: , .. /--,� --1� ...___/ .J � r-�, �--1 - ,___ -�[}- �2'�¥,;1};i_{,i:�:li:f{1\¾\!l!iz{◊rfl:{i;rrJ _., .,, ,s,· " ---�""'\ ,/'.; �:Jh. 4 1 � l'el _-.J L &f-----=-- l':1 �� ::-1 c. c'...4 - �� " - - -- -.--�-,_ - -- /1 '; � 'c.. � � � (). I�� -"- '' : ,;:;; <§'' ; " ')<oro \)\)/ '¾\.'<\: E .,�·· , ,1·•) n I "' ' ti ''' ' '' ',I- - -�- -',_ fi11,,/1111w11./;j ),,_ id�r ! ,;'.} In··· -S � �-;�,.,;:� I I I I I I -- 1:, s-, �?---- 1- ''////.'//,,,, - •; "I I I I I I :J '' i _,_ £>!-/ _0,'--':�\�-= �_,;-,.,[_ 0Yl. -•1rn .JIID�, -- 1 � ,R()lJIJn _ _ _ 1 • ft--- ..I II /<. CJ D t:w 'iii;,;, //,I('', " L,_ ,, - '., '-... C C LEGEND: NOTE: CABLES IN CABLE TRAY □ N PIPE BRIDGE/ BUILDING \,/ALLS/DYKE \,/ALL, ETC. -----·----· I. CABLES BURIED UNDER GROUND ALL DIMENSI□ NS ARE IN METER CABLES THROUGH G.I PIPE BURIED UNDERGROUND B B A THIS DRAWING IS THE PROPERTY OF FACT ENGINEERING AND DESIGN ORGANISATION AND IS TO BE USED ONLY FOR THE PURPOSE OF WHICH IT WAS LENT AND MUST NOT BE USED IN ANY WAY DETRIMENTAL TO THE INTEREST OF THE COMPANY AND IS SUBJECT TO RETURN ON DEMAND SCALE I 1:750 nRAWN -· .. Soman DATE I I I II I I I I I I I I CHE�:KED -DESIGNED I PRELIMINARY -- 05.06.'20 12 I 11 I 10 I 9 I a I 7 I 6 I s 4 ENGINEERING & DESIGN ORGANISATIOl'-1 II FEDO THE FERTILISERS AND CHEMICALS TRAVANCORE LTD 11� KERALA UDYOGAMANDAL PROJECT NO: 32644 OVERALL POWER LAYOUT (TYPICAL) SM DATE CHECKED APPROVED CHECKED REVISED PARTI CULARS ZONE NO c!; >--- - - - - - - - - - - - - - - - - ----< TITLE DRAWING NO :....__---1-________________ --:-_______________--t---'-----'----------------------------�--�--��--�-- ---1-e---....:c.c:...._c:.::....:..c.:.· ° CLIENT ---ED I IK APPRuv REVISION REFERENCE DRAWING M / s FACT CD � 0 FACT OF1 DRG. N0.32644-13-PL-00 501 2 A 0 REV. 4 2 3 / Cl z I <C u :::iE -w D □ 0:: z 0 0 LLz 0:: w::::> (/) 1-­ o a..w 65x65x6 MS 0:: 0:: AN GLE/ =>o a.. 1-STEEL ROD w 1-ON BOTH SIDES F �-, @1500 IN TERVA o:: m O::::> LL (I) i D RUN G GRP CABLE TRAY W '.'.:j� Zo Oz o<C w>­ (1) z ::::> <( wa.. m :::iE C 0 0u I-(/) w J g N RUN G 50x50x6 MS SUPPORT AN GLE C ELEVATION TYPE - A - i!: Cl LL SLAB/ BEAM/STRUCTURE �o z 1-0 (/) �� W <C (/) 1-- z� <C GRP CABLE TRAY t, w I g§ 1-z 1:2 t, vi <i! w1-­ Cl z 0W z:::i!E <( a:: 1-W t, ZCl B a::>w<( �:!: 0>­ Zz W<( 65x65x6 MS AN GLE WELDED TO IN SERTS @1500 IN TERV GRP CABLE TRAY 0 0 N RUN G GRP CABLE TRAY B RUN G RUN G 0� / �Cl w LL (I) O::::> >-w I-- m 0:: w1-­ a.. o oz 0:: I-­ a.. (/) w::::> :::iE i!:Cl (I) �� 0 0 N 50x50x6 MS SUPPORT AN GLE TYPE - B TYPICAL ARRANGEMENT OF GRP CABLE TRAY SUPPORTS t---+--------+------+---+---1---------< PROJECT NAME: NEW PA TANK AT Q10 BERTH- W. ISLAND PROJECT NO: 32644 04.06.'20 TITLE TYPICAL ARRANGEMENT OF 0 PRELIMINARY IK SM ,i1' . . H PR A E E N I P N N A T R RIP C C D D D D K O O S _DAT_ __, � � � � _ _ _ _ _ _ _ _ W_ _ _ _ _ _ _ � __ __ � ,_ �� A 0 A OVERHEAD CABLE TRAY � _J SCALE: N TS SHEET 1 OF 1 1---------------------<-....____. DRG. NO. 32644-13-GE-00 252 REV. CLIENT: M/s. FACT-CD �i " i!:t:: � " 0 gLL FACT ENGINEERING & DESIGN ORGANISATION KERALA UDYOGAMANDAL 11 ��r1=1:i1t1,1 tL """_1 0 a�---------.------------.---------�--------� 4 3 2 4 3 2 BOLT & NUT �------------------�--�---� FOR FIXING JUNCTION PLATE \ a::z f2 0 wz en a:: D ELEYAIIQN �� a:: a:: ::, (}_Q 1w I­ IO 1w MAIN EARTH CONDUCTOR. g§� LL vl EARTH CONDUCTORS TO EQUIPMENTS IN PLANT �en zClz w<C en>=>z ALUMINIUM PLATE oo we'.: CD::::; C 1- C 0 00 �� I-Cl LL 0 �o zl- Qf{J !;;i: a:: en� -z �c.,w a::1I 0 zo c., Ivi ...J �� z CABLE LUG ow z::::; <( a:: c., l:;j ZCl B a:: w� !z!s: >c:, z z W<( '----�------' � MAIN EARTH CONDUCTOR. t;� �Cl w LL en O=> �w CD a:: W1(1-Q Oz a:: (}_ en I- 0 EARTH CONDUCTORS BOLT, NUT, FLAT WASHER AND SPRING WASHER 1. 100x6mm ALUMINIUM PLATE (THE CROSECTIONAL AREA OF THE PLATE SHALL BE GREATER THAN THAT OF THE MAIN EARTH CONDUCTOR). LENGTH OF THE PLATE SHALL BE DECIDED TO SUIT THE NUMBER OF CONNECTIONS AT SITE. 2. AFTER FIXING, THE OUT SIDE SURFACE OF THE BOLTS, NUTS, AND WASHERS AND THE PLATE SHALL BE COVERED WITH BITUMIN/GRASE /EPOXY PANIT. l---+--------+----+---+---+------1 PROJECT NAME: NEW PA TANK AT Q10 BERTH-W. ISlAND w::i �::::; en c �� 0 PRELIMINARY DESCRIPTION SCALE: NTS !z NO. � s:w A <( ...J a:: oen ::/,,,,,,_,, SM DRAWN CHKD � iili r-- CLIENT: M/s. FACT-CD �t: � r-0 t0 PROJECT NO: 32644 IK 04.06.'20 TITLE TYPICAL ARRANGEMENT OF EARTHING APPRD. DATE A _ N _ _CT_ IO _ N _ _PLA_TE _ ____+--'----lo SHEET 1 OF 1 1------JU DRG. NO. 32644-13-GE-00 253 REV FACT ENGINEERING & DESIGN ORGANISATION UDYOGAMANDAL KERALA ii ii •I•ll IIM�·tL-- -. QL..---------�--------�---------�-----------' 4 3 B TO EQUIPMENTS IN PLANT 2 4 3 2 RCC COVER SLAB . · . .. . . 4 . .. .. . . . . . · ••· . • :. "' . • ... �:- . ·:� _· . _..,_ ·:.,. ·· ·. ·-�•- · :_: � __..;. .--:.:1__ _· .· ...-. - --·� · .· :_ -� - . . · . 4 .: ..... . ._·4•_ D w 0 LO N ------- i!: GRP CABLE TRAY (TYP) 0 LO N ------- C C 0 LO N 0 0 .•... LI-; . • ·_ _. �.: · ·. · .. · .. .4· . · I. •"" : · . .. · . . ·, -· • . . . 4 . - • .� � . . ... . : . ·.; · . . . . _ .. • . . ,. ·� .... ; : :.• � .. ....·· . . .. • 4 .. . · . �. -� 4 ·.. : . · ·· • :., . .. · . ., . • . . . •. : _. 4 ··· . � :_ , .4 _ _ - 60x8 mm MS FLAT INSERTS AT 1000 INTERVALS. • .. · . • . .I WIDTH "W" 50x50x6 M.S. ANGLE ·--·< ._. . �. ,, ·1 OF WIDTH OF SL.NO. SIZE IN mm (WxD NO. TRAY TIERS* 1. 1000 X 1000 4 600 2. 750 X 750 3 450 3. 600 X 600 2 300 B NOTE:1. BOTTOM LAYER FOR 600x600 & 300x300 TRENCHES SHALL BE OF FULL WIDTH. *2. NO OF TIERS SHALL BE AS PER THE LAYOUT DRAWINGS 3. CABLE TRAY SHALL BE BOLTED TO 50x50x6 ANGLE SUPPORTS. t---+--------+-----+--+-SM DRAWN CHKD PROJECT NAME: ---+-----1 NEW PA TANK AT Q10 BERTHW. ISLAND IK 04.06.'20 APPRD. DATE SHEET 1 OF 1 TITLtcABLE TRENCH SECTIONAL DETAILS (TYPICAL) 4 KERALA 3 O A DRG. NO. 32644-13-GE-00 255 REV. FACT ENGINEERING & DESIGN ORGANISATION UDYOGAMANDAL PROJECT NO: 32644 2 11��••••I•ll tL -_ 4 3 2 D a::z o e z wa:: (/) a:� a::a:: ::::, Cl...10 w :r: II- Ei3 a::CD ---:, O LL. PUSH BUTTON STATION ____, � '.'.:j (/) z­ oo oz w<C (l)>::::,z <( WCl... CD::::? C 0 00 1- C �� lo LL. �o zig[{] a:: � (/)� -z e>w a:: :r: 01o z1c, (/) ....J W<( 01z ow z::::!!: <( i:i:: c,w zo B i:i:: w� �3: 0>zz W<( �- FROM MAIN EARTH RING B EARTHING ARRANGEMENT FOR MOTORS WITH P.B. STATION EARTH LOOPED TO MOTOR EARTH STUD. (PROVIDE DUPLICATE EARTHING) t.,� �o w LL.(/) 0:::J �w a::CD Wf­ Cl...Q O a::z Cl.. I- 1---+----------+---+-----+---+--------t PROJECT NAME: 1---+----------+---+-----+---+--------tNEW PA TANK AT Q10 BERTH-W. ISLAND w::::, �::::? �� <C c, O PRELIMINARY DESCRIPTI ON � !z: A NO. 3:w <( ....J a:: 0(1) � � r--. �t: � r--. 0 0 :1DRAWN SM CHKD SCALE: NTS PROJECT NO: 32644 IK 04·06-'20 TITLE EARTHING CONNECTION APPRD. DATE 0 A SHEET 1 OF 2 1-----------------+--� DETAILS (TYPICAL) DRG. NO. 32644-13-GE-00 256 REV. CLIENT: M/s. FACT-CD FACT ENGINEERING & DESIGN ORGANISATION IIAA�,i lL !l•I•ll ..... - KERALA UDYOGAMANDAL 0 o�----------------------------------� 4 3 2 3 4 2 1----PUSH BUTTON STATION o:::z �o D FROM MAIN EARTH RING z w 0::: (/) �� 0:::0::: ::> a.o 1w F0 w �a3 LL� ADAPTOR BOX (IF ANY) '.'.:i (/) z­ oo z o<C w (/)>­ ::> z wi:t CD:::i,; C 0 0 1-0 �� lo LL C JUNCTION PLATE �o zlQ[:3 0::: (/)� '< -z �ow 0::: I 01- t5� cii_J EARTH CONDUCTOR �� z ow z::::;; <( ii:: c.,t:;:i zo B ii:: B EARTHING ARRANGEMENT FOR MOTORS WITH ADAPTOR BOX & P.B. STATION EARTH CONDUCTOR LOOPED TO JUNCTION PLATE (PROVIDE DUPLICATE EARTHING) w� �:,\:: 0>­ zz W<( 0� i'.;:o w LLC/l O::> �w 0::: CD Wt0.Q Oz 0::: a.1(/) W::> F:::i!: 1---+---------+----+---+-----+-----t PROJECT N AME: 1---+---------+----+---+-----+--___,NEW PA TANK AT Q10 BERTH-W. ISLAND !� s_M ___ 1K---+_04.o _ _ 20 TITLE _ s:__, _ ____:1,___ _ _1M_N 1A_ RY ,_o--+-P R_ EL NO. D ES C R IPTIO N DRAWN CHKD PPRD. DATE A A 0 A DETAILS (TYPICAL) SHEET 2 OF 2 ---------------+--'---t SCALE: NTS �� 0: �z i PROJECT NO: 32644 EARTH ING CONNECTION DRG. NO. 32664-13-GE-00 256 -----------------�---------r■��i==i=iiiia---1 h OC/l <C � :,\:: r-- 0 REV CLIENT: M/s. FACT-CD ��:c�A�A��!� EERING & DESIGN ORGANIS ���� 11��-i!l•I•ll O'---------�--------�-------�------------' 4 3 2 4 3 2 2 mm THICK AL. SHEET WITH 25x3 M.S FLAT FOR REINFORCEMENT D z o:: �o wz 0:: (/) �� 0:: 0:: :::, a..o 1w I­ I U 1-w 0::' CD O LL ul 25x3 M.S.FLAT WITH 10 ¢ BOLT HOLE �(/) zoo oz w<C (/) >­ :::, z wi:i: CD ::ii: C 0 0 I-(_) C �� lo LL �o zig[{] �o:: (/)� -z �- C.!>W 0::I CANOPY 0 1- 6� ii'i ....J W<( 01z ow z:::i: <( a:: (.!) ti zo B a:: w� �3: 6 >­ zz W<( NOTES:1. AFTER FABRICATION THE STRUCTURALS SHALL BE PAINTED WITH EPOXY PAINT WITH B SUITABLE PRIMER. 2. THE SIZE OF THE CANOPY SHALL BE SUCH THAT THERE WILL BE A MINIMUM CLEARANCE OF t3� �o 10 mm FROM THE EQUIPMENT ON ALL SIDES. w LL (I) 0::J �w 0::CD Wf0..Q Oz 0:: a.. I- (/) w:::, t---+--------t-----+---+-----+-----1 PROJECT NAME: t---+--------t-----+---+-----+-----1 NEW PA TANK AT Q10 BERTH-W. ISLAND �::ii: �� <C O P RELIMINA RY C.!> � !z A NO. DESCRIPTI ON 3:w <( SCALE: NTS 0:: ....J 0(1) � CLIENT: t.1/s. FACT-CD � " �t:: :!DRAWN SM CHKD PROJECT NO: 32644 IK 04.06.'20 TITLE APPRD. DATE TYPICAL ARRANGEMENT OF CANOPIES -�F�O�R�O�U�TD�O�O�R�D�E�V�IC�E�S--t------'-----i O A SHEET 1 OF 2 t-- DRG. NO. 32644-13-GE-00 257 REV. z" FACT ENGINEERING & DESIGN ORGANISATION 0 � UDYOGAMANDAL KERALA o�---------r-------------,------------,---------� 4 3 2 3 4 2 HANDLE 2mmTHICK ALUMINIUM SHEET WITH 25x3 MS FLAT FOR REINCEFORMENT. / A D C 100x100x10 MS FLAT WITH 1Qq; BOLT HOLE. 25x25X5 MS ANGLE (BENT TO SHAP . L_J HOOD FOR MOTOR L_J L_J B NOTES:1. AFTER FABRICATION THE HOOD SHALL BE PAINTED WITH EPOXY PAINT WITH SUITABLE PRIMER. 2. THE SIZE OF THE HOOD SHALL BE SUCH THST THERE WILL BE A CLEARANCE OF THE MINIMUM 30mm FROM THE MOTOR, ON ALL SIDES. VIEW FROM A +---+----------+---+-----+---+------< PROJECT NAME: +---+----------+---+-----+---+------< NEW PA TANK AT Q10 BERTH-W. ISLAND SM :1DRAWN CHKD IK 04.06.'20 TITLE APPRD. DATE TYPICAL SHEET 2 OF 2 4 3 PROJECT NO: 32644 ARRANGEMENT OF CANOPIES FOR OUTDOOR DEVICES 0 A DRG. NO. 32644-13-GE-00 257 REV. 2 TECHNICAL PROCUREMENT SPECIFICATION PAGE 1 OF 1 TPS No. Sl. R0 32664-14 -PS-001 Doc. No. Description No. 00FT011/00 32664-14 -PS-001 INDEX No. of pages Rev. No. with issue 1 32664-14-PS-001 SW INST SCOPE OF WORK 1 1 0 2 32664-14-PS-001 SIT INST SCOPE OF INSPECTION AND TESTS 2 0 3 32664-14-PS-001 VDR INST VENDOR DATA REQUIREMENTS 4 0 4 32664-01 -PS-001 SPL INST SPECIAL REQUIREMENT OF THE PROJECT 3 0 5 32664-14-PS-001 SV INST ATTACHMENTS SUB VENDOR LIST 3 0 1 14ES008/15 30 0 2 32664-14-CL-00001 1 0 3 2 1 0 6/6/2020 FOR COMMENTS DCK MKZ REV. DATE DESCRIPTION PRPRED CHKED FIELD INSTRUMENT ERECTION SPECIFICATION OVERALL CABLE LAYOUT FACT ENGINEERING AND DESIGN ORGANISATION 2 3 4 MS APRVD INSTRUMENTATION DEPARTMENT SCOPE OF WORK 32664-14 -PS-001 SW INST Page 1 of 1 PROJECT: NEW PA TANK AT WI CLIENT: FACT-CD FACT ITEM: INSTRUMENTATION SYSTEM FOR NEW PA TANK AT WI STATUS ENQUIRY/ COMMITMENT PO NUMBER The scope of work include the following Description Sl.No 1. 2. Supply of hardware (Field instruments, Erection material, Spares) Inspection, testing and quality assurance services 3. Erection, integration to o existing facility and commissioning 4. Documentation Required Remarks 14FT660/15 Note:- The above mentioned scope is only for preliminary understanding only. only Detailed scope is mentioned in subsequent documents and attachments of this tender document. 0 REV 06/06/20 DATE FOR CLIENTS COMMENTS DESCRIPTION DCK PRPD FACT ENGINEERING AND DESIGN ORGANISATION MKZ CHKD MS APPRD R0 INSTRUMENTATION DEPARTMENT 32664-14-PS-001 SIT INST Page 1 of 2 R0 SCOPE OF INSPECTION AND TESTS PROJECT: NEW PA TANK AT WI ITEM : As indicated below EQPT NO. The following inspection and test shall be conducted and records to be submitted Sl.No 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 Inspection. Required RADAR LEVEL TRANSMITTERS/ LEVEL SWITCH Visual inspection Dimensional inspection Performance test accuracy Material test certificate Certificate for electric code Hydraulic test Weather proof certificate SIL certificate W&M India certificate IBR certificate (If applicable- for guided wave) Functional test- Alarm contacts, communication with host/ accessories etc Witness Reqd $ $ $ $ $ $ $ - $ $ $ * * $ * - $ * $ $ $ $ $ $ $ $ $ $ $ * Remarks 5.0 CABLES Visual inspection Dimensional inspection Performance/ insulation resistance Routine tests as per national/ international standard referred in the data sheet/ QAP Type test report 1.0 2.0 3.0 4.0 5.0 6.0 ELECTRICAL FITTINGS AND JUNCTION BOXES Visual inspection Dimensional inspection Certificate for electrical code Weather proof certificate Type test report Routine test $ $ $ $ $ $ $ $ * * * $ 1.0 PRESSURE GAUGES Calibration Certificate $ * 0 06/06/20 FOR COMMENTS DCK MKZ MS REV DATE DESCRIPTION PRPD CHKD APPRD 1.0 2.0 3.0 4.0 14FT942/15 Description FACT ENGINEERING AND DESIGN ORGANISATION INSTRUMENTATION DEPARTMENT Sl.No 2.0 3.0 32664-14-PS-001 SIT INST Page 2 of 2 R0 SCOPE OF INSPECTION AND TESTS Description Material Test certificate (For diaphragm seal, thermowell) Weatherproof certificate Inspection. Required $ $ Witness Reqd * Remarks * $ - Manufacturer shall conduct their standard inspection as part of their 'quality assurance' program and shall furnish inspection reports for review. If required, witness inspection will be conducted by purchaser's representative. *Report review 14FT942/15 Note –1 ID of ferrule by GO/NOGO gauge, pipe thread by plug and ring gauge, interchangeability of ferrule nut. Note-2 Also ferrule tightening test to be carried out. 0 06/06/20 FOR COMMENTS DCK MKZ MS REV DATE DESCRIPTION PRPD CHKD APPRD FACT ENGINEERING AND DESIGN ORGANISATION INSTRUMENTATION DEPARTMENT PROJECT: CLIENT: ITEM: STATUS PO NUMBER NEW PA TANK AT WI M/s FACT- CD Package items ENQUIRY/ COMMITMENT OFFER SL GRP. DESCRIPTION NO CODE 14FT910/15 A 32664-14-PS-001 VDR INST Page 1 of 4 R0 VENDOR DATA REQUIREMENTS QTY AFTER COMMITMENT Lead Time In Weeks QTY Req. Prop Agrd FINAL 1P+1S 2 3P+1S QTY From package vendor 1. B Deviation list 1P+1S 2. C 3. B 4. B Documents and drawings index Bidder’s checklist- Filled ( If attached with tender) Control system Architecture 5. B Instrument schedule 6. B Spare parts list 1P+1S 6 3P+1S 7. B Instrument specifications 1P+1S 4 3P+1S 8. B 9. B 1P+1S 4 3P+1S 10. B 1P+1S 4 3P+1S 11. B Instrument design philosophy Instrument installation diagram (loop schematic diagram) Instrument location & cable panel arrangement/wiring drawings Bill of material 1P+1S 4 3P+1S 12. B 13. B 1P+1S 8 3P+1S 14. B 1P+1S 6 3P+1S 15. B 1P+1S 4 3P+1S Control panel & inter lock panel arrangement/wiring drawings. Marshalling box(termination box) drawings Junction box schedule/ connection drawings Cable schedule 0 06/06/20 FOR COMMENTS DCK MKZ MS REV DATE DESCRIPTION PRPD CHKD APPRD FACT ENGINEERING AND DESIGN ORGANISATION INSTRUMENTATION DEPARTMENT VENDOR DATA REQUIREMENTS 16. B Interlock scheme &write up 17. B Control room layout 18. B IO List of PLC 19. B Grounding details 20. B Air distribution drawings 21. B 22. B 23. B 24. B 25. C 26. C 27. C Instrument hookup drawings (Process Hookup, Electrical hookup, Pneumatic Hookup) Instrument/ junction box installation drawings with supports and canopy Test procedures for instrument, lines etc Pre-commissioning and commissioning checklist, Procedure etc Loop folders (All connected drawings of every instrument loop in a folder in a dedicated CD/DVD) All documents and drawings in CDs/DVDs (Editable copy) As built drawings 32664-14-PS-001 VDR INST Page 2 of 4 R0 1P+1S 6 3P+1S 1P+1S 6 3P+1S 1P+1S 6 3P+1S 1P+1S 10 3P+1S 1S 2$ 1S 1P+1S 4$ 3P+1S Group code: A- For review and detailed engineering, B- For review, C- For information and record document type: RReproducible, PPrint, MMicrofilm SSoft (CD/DVD) $Counts from Date of Startup 14FT910A/15 Notes: @ Vendor shall fill in proposed lead-time if different from the required lead-time. @@ Each set of final documents shall be submitted in a folder. Two such folders shall be packed and dispatched with the equipment. FACT ENGINEERING AND DESIGN ORGANISATION INSTRUMENTATION DEPARTMENT VENDOR DATA REQUIREMENTS SL GRP. DESCRIPTION NO CODE B AFTER COMMITMENT QTY Lead Time In Weeks Req Prop Agrd FINAL QTY 1P+1S 12 3P+1S 1P+1S 12 3P+1S 1P+1S 12 3P+1S 1P+1S 14 3P+1S 1P+1S 14 3P+1S 1P+1S 14 3P+1S 1P+1S 12 3P+1S 1P+1S 1P+1S 14 2BD M 2BD M 12 (1) 3P+1S 3P+1S 2BD M 2BD M 2BD M 3P+1S 18 B Vendor data requirement from instrument manufactures Manufactures catalogue with model code no. Manufactures technical specification indicating range, material, utility requirements Quality assurance plan FAT/ SAT Procedure for DCS/PLC Control valve sizing & noise level calculations Thermowell wake frequency and sizing calculation Flow element sizing Dimensioned outline drawings for instruments/ Junction boxes, panel etc Control panel/ interlock panel drawings Wiring drawings Control panel/ interlock panel detail fabrication drawing Termination, wiring & power supply distribution drawings Instrument assembly drawing Performance curves/test certificates Third party (IBR, CMRS etc) certificates Detailed spare parts manual Operation, installation, maintenance, service manual for each instrument Material test report 19 C Weather proof Certificates 1P+1S 20 C Hydro test certificates, Leakage test certificates 1P+1S 1. C 2. B 3. B 4. B 5. B 6. B 7. B 8. B 9. B 10 B 11 B 12 B 13 B 14 B 15 C 16 C 17 C 14FT910A/15 OFFER QTY 32664-14-PS-001 VDR INST Page 3 of 4 R0 1P+1S 1P+1S 1P+1S 1P+1S FACT ENGINEERING AND DESIGN ORGANISATION 3P+1S 3P+1S 3P+1S 3P+1S 3P+1S INSTRUMENTATION DEPARTMENT VENDOR DATA REQUIREMENTS General Arrangement drawings of panels 22 C All documents and drawings in CD (1)-dispatched along with instrument/ system BDM- Before dispatch of material 32664-14-PS-001 VDR INST Page 4 of 4 R0 21 B 1S 4$ 1S 14FT910A/15 Note: All the above indicated submission time is typical and shall be optimized (Early submission) to complete the project within time schedule indicated in NIT if required. FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION 32664-01-PS-001 SPL (INST) R0 Page 1 of 3 1.0. INTRODUCTION M/s FACT intends to install two nos of new Phosphoric acid Tanks at Willington Island, Kochi at its existing raw material handling site on LSTK basis. The following covers the special requirements and scope of work related to instrumentation for the project. 2.0. DEFINITIONS Client/ Owner PMC LSTK Vendor 3.0. 3.1. 3.2. 3.3. 3.4. 3.5. 4.0. 4.1. 4.2. 14FT660/15 SPECIAL REQUIREMENT OF THE PROJECT (INSTRUMENTATION) 0 REV M/s FACT CD M/s FEDO Lump sum Turn Key LSTK Contractor / its sub contractor as the case may be SCOPE OF WORK The contractor’s scope of work is inclusive of but not limited to the following: Design and detailed engineering of total instrumentation required for the tank and its interfacing to existing control room. Supply of instrument erection material like cable tray, cable, cable glands, junction box, structural steel, consumables etc, erection, commissioning. Testing, calibration, painting etc. Documentation and as built preparation Scope of anticipated work with quantity is detailed in instrumentation schedule of work. Note that being a LSTK work, the work mentioned in schedule of work is to be treated for reference.. Major items and services only are listed in this document. The supply, erection and integration of instrumentation for the safe operation of the system shall be in the scope of the LSTK contractor. FACILITY DESCRIPTION As part of the new Tanks, one no of radar type level transmitter shall be mounted on each tank. These transmitters shall be interfaced to a local field indicator also supplied by the Radar OEM and shall be wired in series to the control room wiring. Necessary looping shall be implemented in a junction box. All these level instrument shall be connected to a single junction box and wired till control room through overhead cable tray routed alongside the pipe rack for 06/06/20 DATE FOR COMMENTS DESCRIPTION DCK PREPARED FACT ENGINEERING AND DESIGN ORGANISATION MKZ CHECKED MS APPROVED TECHNICAL PROCUREMENT SPECIFICATION 4.3. 5.0. 5.1. 5.2. 5.3. 5.4. 5.5. 5.6. 5.7. 5.8. 5.9. 14FT660A/15 5.10. 5.11. 5.12. SPECIAL REQUIREMENT OF THE PROJECT (INSTRUMENTATION) 32664-01-PS-001 SPL (INST) Page 2 of 3 R0 acid pipelines. Necessary structural work shall be included in scope of instrumentation. New Junction box and cable tray work is included in scope of contractor. Note that, existing cable tray shall be used wherever it is available to control room in cable route as indicated in cable routing drawing. GENERAL All the cables inside the dyke wall shall be routed at an elevation greater than the height of dyke wall. For this purpose, concrete footing and additional structural work if required shall be included in scope of work. Vendor shall supply all instruments and erection material from attached vendor list only. Supply of material from any other vendor is subject to PMC/ Owner approval. Vendor shall submit QAP, test certificates of all instruments and erection material as per vendor data requirements for PMC approval. Vendor shall execute all site related jobs as per sound engineering practice and to the satisfaction of site in charge of client/PMC. All instruments and junction boxes shall be protected against direct sunlight and rain by installing canopies of 20 AWG aluminium sheet. Instrument and junction box tag numbers shall be painted on support. All steel structural’s used for instrument/junction box/cable tray shall be painted. Cables shall be tagged with SS plates. General instrument erection guide lines are attached in 14ES010/15. Irrelevant sections in the document may be ignored. Relevant erection tools of good quality and repute shall be provided to workers during instrument erection. All the instruments supplied shall be covered under guarantee/ warrantee for a period of 12 months from the date of erection or 18 months from the date of supply. Contractor shall maintain good cleanliness at site during instrument erection. All scrap or waste materials shall be disposed to designated scrap yard at site. If there is any conflict in the specifications or in scope of work, PMC’s authorised site engineer shall be consulted for the resolution and his decision shall be final and binding on contractor. If necessary bidder shall conduct site visits for data collection before quoting. Mandatory Instrument spares are also included in the instrument schedule of work. Commissioning spares shall be included in contractor scope for FACT ENGINEERING AND DESIGN ORGANISATION TECHNICAL PROCUREMENT SPECIFICATION 5.13. 14FT660A/15 6.0. 6.1. SPECIAL REQUIREMENT OF THE PROJECT (INSTRUMENTATION) 32664-01-PS-001 SPL (INST) Page 3 of 3 R0 replacements if any due to damage/ maintenance requirements arising out of pre-commissioning/ commissioning activities. Main cable routing drawing is attached in 32664-14-CL-00001. All minor cable routing including the cable laying from tank side indicator to JB, Instrument to JB are also in the scope of contractor. Junction box and tank side indicator shall be mounted in easily accessible locations at 1.5m height. CLIENT’S OBLIGATION The control room receiver instruments shall be supplied and erected by the client (Push button, Lamps, Recorders or display units etc.). The contractor scope is limited to cabling to control room, glanding, termination, testing (in coordination with client) etc FACT ENGINEERING AND DESIGN ORGANISATION DATA SHEET 32664-14-PS-0001 SV INST PAGE 1 OF 3 SUB VENDOR LIST R0 The make of instrumentation items shall be as per the following list. a. GENERAL INSTRUMENTS CONSORTIUM b. H GURU INSTRUMENTS (SI) P LTD c. MANOMETER (INDIA) PVT LTD d. ODIN INDIA PRIVATE LIMITED PRESSURE & DIFFERENTIAL e. PREMIER INSTRUMENTS & CONTROLS PRESSURE GAUGES LTD f. BLUE BELLS CONTROL SYSTEMS PVT LTD g. WIKA INSTRUMENTS (I) PVT. LTD. h. WAAREE INSTRUMENTS LTD. i. BUDENBERG GUAGE CO. LTD. a. KEI INDUSTRIES LTD. b. ASSOCIATED CABLES PVT LTD, MUMBAI c. GENERAL INSTRUMENTS CONSORTIUM d. UNIVERSAL CABLES LTD. CABLES e. TOSHNIWAL CABLES f. POLYCAB WIRES PVT. LTD. g. DELTON CABLES LTD. h. BROOKS CABLE WORKS LTD. a. CHEMTROLS SAMIL (INDIA) PVT LTD b. GENERAL INSTRUMENTS CONSORTIUM SWITCHES-LEVEL (FLOAT TYPE) c. INSTRUMENTATION LTD d. MOTOYAMA ENGINEERING WORKS LTD 14FT703/15 e. TRANSDUCERS & CONTROLS P LTD 4 NEW PA TANK AT WI PROJECT 3 2 1 0 REV CLIENT P.O. NO 06/06/20 DCK MKZ DATE PRPD CHKD MS APPRD VENDOR FACT ENGINEERING AND ORGANISATION M/s FACT CD DATA SHEET LIST OF SUB VENDORS FOR PACKAGE INSTRUMENTS 32644-14-PS-0001 SV INST PAGE 2 OF 3 R0 f. TOKYO KEISO CO LTD g. ISA CONTROLS FRS LTD h. SAKURA ENDRESS C/o ITOCHU CORPORATION i. MAGNETROL INTL INC j. LEVCON CONTROLS PVT. LTD. k. PEPPERL+FUCHS INDIA PVT LTD a. ENDRESS + HAUSER (I) PVT LTD b. EMERSON PROCESS MANAGEMENT (INDIA) PVT LTD c. MAGNETROL INTL INC LEVEL TRANSMITTER GUIDED WAVE/NON CONTACT TYPE RADAR d. KHRONE-MARSHALL PVT LTD e. ABB LIMITED f. HONEYWELL AUTOMATION INDIA LIMITED g. YOKOGAWA INDIA LIMITED h. SIEMENS Ltd a. BALIGA LIGHTING EQUIPMENTS PVT LTD b. CROMPTON GREAVES LTD c. EX-PROTECTA JUNCTION BOX d. FLEXPRO ELECTRICALS PVT LTD e. FLAMEPROOF EQUIPMENTS PVT LTD f. FLAMEPACK (MANIPAL) g. ALSTOM T&D INDIA LIMITED a. BLUE STAR LTD b. ALWAYE ENGINEERING WORKS c. INDIANA GRATINGS PVT LTD 14FT703A/15 CABLE TRAY d. STEELITE ENGINEERING LTD e. VENUS STEEL PRODUCTS f. VINAY STEEL SYSTEMS g. CHELUR CORPORATION FACT ENGINEERING AND ORGANISATION DATA SHEET LIST OF SUB VENDORS FOR PACKAGE INSTRUMENTS 32644-14-PS-0001 SV INST PAGE 3 OF 3 R0 a. FCG FLAMEPROOF CONTROL GEARS PVT. LTD b. FLEXPRO ELECTRICAL PVT LTD c. EXPROTECTA CABLE GLAND d. BALIGA LIGHTING EQUIPMENTS PVT LTD e. MULTI PRESSINGS 14FT703A/15 h. CEAG FLAMEPROOF CONTROL GEARS(P) LTD FACT ENGINEERING AND ORGANISATION ENGINEERING SPECIFICATION 1.0.0 2.0.0 3.0.0 21.0.0 22.0.0 23.0.0 24.0.0 PART C – JOB COMPLETION REQUIREMENTS COMPLETION OF ERECTION JOB COMMISSIONING AND START –UP BILL OF QUANTITIES AND MATERIALS 7.0.0 8.0.0 9.0.0 10.0.0 11.0.0 12.0.0 13.0.0 14.0.0 15.0.0 16.0.0 17.0.0 18.0.0 19.0.0 20.0.0 25.0.0 26.0.0 27.0.0 28.0.0 PART D- PROCEDURES AND STANDARDS GENERAL REQUIREMENTS AND RECOMENDEDATION FOR PIPE WELDING SPECIFICATION FOR PAINTING WORK INSPECTION AND TEST PROCEDURE FOR INSTRUMENT INSTALLATION WORK. APPLICABLE STANDARDS 1.0.0 1.1.0 1.2.0 1.3.0 1.4.0 1.5.0 1.6.0 1.7.0 29.0.0 30.0.0 31.0.0 PRPD BY: PART E- ATTACHMENTS DRAWINGS-ANNEXURE I SCHEDULE OF WORK – ANNEXURE II ITEMS TO BE SUPPLIED BY CONTRACTOR- ANNEXURE III CHKD BY: Page 1 of 30 NOTE: The description under scope of supply will be general in nature and covers most of the prevalent types of instruments, some of which may not be required for this particular project. Hence only the applicable items shall be referred to. For actual list of instruments, refer schedule of work. CONTENTS PART A – GENERAL SCOPE OF WORK CONTRACTOR’S OBLIGATIONS OWNER’S SUPPLY PART B- TECHNICAL REQUIREMENTS INSTRUMENT INSTALLATION ONLINE INSTRUMENTS FIELD MOUNTED PRIMARY MEASURING INSTRUMENTS FIELD MOUNTED TRANISMITTERS FIELD MOUNTED CONTROLLER FIELD MOUNTED GAUGES FIELD MOUNTED SWITCHES ANALYSERS MISCELLANEOUS INSTRUMENTS JUNCTION BOXES, PDB’S, MB’S CONTROL PANELS FABRICATION WORK AND MOUNTING OF INSTRUMENTS GENERAL NOTES FOR INSTRUMENT PIPING AND TUBING GENERAL NOTES ON TERMINATION ELECTRICAL INSTALLATION AND GROUNDING GENERAL NOTES ON CABLE TRAY, DUCTS AND CONDUIT INSTALLATION CIVIL WORKS CALIBRATION AND FUNCTIONAL CHECK TESTING AND LOOP CHECKING 4.0.0 5.0.0 6.0.0 14 ES008 /15 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION PART A- GENERAL SCOPE OF WORK The scope of work shall include but not be limited to: Unpacking, checking, cleaning and withdrawal of instruments, instrument accessories and erection materials at owner’s stores and /or from places of storage anywhere within the boundary wall of project and existing factory. Return of leftover materials to owner’s stores. Transportation and handling of instruments, instrument accessories and erection materials at owner’s stores and /or from places of storage anywhere within the boundary wall of project to work site and /or contractors stores. Installation of field mounted instruments such as pressure/vacuum gauges, dial thermometers, pressure switches, blind switches, manometers, differential pressure indicators, local flow indicators/ recorders, local indicating controllers, flow transmitters, pressure transmitters differential pressure transmitters, temperature transmitters, rotameters etc. Installation of vessel mounted instruments such as level gauge glass, magnetic level gauges, bi-colour level gauges, torque tube level instruments, level switches, dial thermometers, pressure gauges etc. Installation of instruments on vendor’s equipment such as Speed Indicators, Speed Controllers, Vibration/Axial Displacement/ axial Thrust Monitoring Systems, Ammeters, Anti surge Controls etc. Supervision of installation of on-line instrument (by other contractors) such as Orifice Flow Element, Control Valves, PD/ Turbine Meters, Rotameters etc. Installation of analytical instruments such as Infrared Analysers, Paramagnetic Analysers, Thermal conductivity Analysers, NOX analyser, H2S analysers, silica analysers, Density Analysers, PH APVD BY FACT ENGINEERING AND DESIGN ORGANISATION ISSUED ON: ENGINEERING SPECIFICATION 1.8.0 1.9.0 1.10.0 1.11.0 1.12.0 1.13.0 1.14.0 1.15.0 1.16.0 1.17.0 1.18.0 14 ES008 /15 1.19.0 1.20.0 1.21.0 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION analysers, Electrical Conductivity Analysers, Dissolved Oxygen analysers, Online gas Chromatographs, oxygen analysers etc Installation of miscellaneous instruments such as Belt weighers, flame safe guard instruments, pneumatic change over switches, air sets, thermocouple assemblies, thermo resistance assemblies, purge type liquid level measuring systems, volume tanks for double acting piston actuators etc. Installation of local panel mounted instruments such as receiver indicators, indicating controllers, pneumatic/ electronic receiver recorders, manual loaders, ratio control stations, computing/ selector relays, temperature indicators/ recorders, receiver switches, alarm annuciators, timers, analyser recorders, etc. Interconnecting field & panel mounted instruments. Cutting gasket of various materials to suitable sizes and fixing the same along with the fitting or flanged connections. Any modifications jobs during installation of instruments. Erection and interconnection of control panels, cubicle boards, control desks etc. locally and in the control rooms. Fabrication and installation of frames, supports, mounting stands, clamps, brackets, cable racks, cable tray and bends, tees and crossings etc. for the racks and trays. Fabrication and installation of instrument protective boxes (Canopy). Laying and supporting of cable tray and ducts. Laying and supporting of instrument air headers and distribution lines. Laying and support of multi run tubing and single run tubing on racks and their termination. Laying and support of multicore and single pair electrical cables, multicore and single pair compensating cable and any other special cables on racks/ trays and their terminations. Fabrication, laying and supporting of impulse piping and sample lines for analyzer and for laboratory. Fixing in position electrical junction boxes, distribution boxes and relay boxes- in the field and behind the control panel-, 1.22.0 1.23.0 1.24.0 1.25.0 1.26.0 1.27.0 1.28.0 1.29.0 1.30.0 1.31.0 1.32.0 2.0.0. 2.1.0 2.2.0 Page 2 of 30 conduit pipes, fittings and flameproof boxes. Any civil job involved in the installation of supports, mounting stands, control panels, junction boxes, relay boxes, air piping, tubes etc. Cleaning and blowing of main air header and distribution lines, pneumatic tubing, impulse piping and sample lines for analysers etc. Testing of main air header distribution lines, pneumatic tubing etc, for any leakage and proper connections. Hydraulic/ pneumatic testing of impulse piping and sample lines. Testing of electrical cables, compensating cables, and special cables for proper connections, continuity and insulation, together with other contractors as required. Testing of complete instrument loops for proper connections and functioning, together with automation contractor. Steam tracing of impulse lines wherever necessary and final connections to steam jacketed instruments. Piping connections for internal washing of instruments and purging of instrument casing. Cleaning and painting of frames, supports, clamps, mounting stands and racks etc, as per painting specifications. Testing, calibration and functional checking of all the instruments and accessories. TIG welding, stress relieving and dye penetrant tests wherever required. Welding of IBR impulse pipes (CS), SS316 and 316L impulse pipes. Sealing of cable entries into control panels /room after laying of all cables and tubes. CONTRACTOR’S OBLIGATIONS The contractor’s obligations shall include: Arrangement and supply of required tools and tackles such as electric welding sets, gas welding sets, gas cutting sets, hydro testing pumps, trailer, forklifts, crane, jumbo trucks, pipe and tube benders, drilling equipments, multi-meters, ferrule printers etc and all other tool necessary for the installation of instrument according to good international practice. Arrangement and supply of consumables like welding electrodes, industrial gases, cleaning fluids such as kerosene, insulation tapes, sealing compounds, all clamping materials for cable/tube trays FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 2.3.0 2.4.0 2.5.0 2.6.0 2.7.0 2.8.0 2.9.0 2.10.0 14 ES008 /15 3.0.0 3.1.0 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION and racks, impulse piping and air header such as bolts, nuts, M.S. clamps (straight pin type)/ U type lugs of 1.5 mm Sq./ 2.5mm Sq. size in required quantity, SS/ aluminium tag plates, PVC cable marking ferrules etc. and all other consumables necessary for execution of the job. Arrangement and supply of testing equipments and other instruments such as dead weight tester (weight in kg/cm .Sq) manometer, portable pneumatic /electronic calibrator, standard test gauge, thermocouple test kit, D.C potentiometer, whetstone bridge, decade resistance box, temperature bath with thermostatic control, oscilloscope, telephone sets, signal generator, megger, vacuum pump, hydraulic pump avometer, digital multimeter, testing /calibrating facilities for panel mounted indicators, recorders, controllers, computing relays, counters, turbine flow meters, transmitters , electro pneumatic converters etc. Planning and maintaining of all activities of the contract as per PERT chart approved by owner. Arranging staff like supervisory staff, skilled and unskilled labour forces etc as required for timely completion of the entire job. Maintaining records on daily basis of all the works as per approved schedule, calibration and inspection reports as per the advice of OWNER. Making arrangements for distribution of electricity and water from supply point to work spots. Co-ordination with other contractors’ works as required by OWNER to complete the instrument erection work. Security arrangement for contractor’s office and stores to ensure safety of all equipments and all free issue materials supplied by the OWNER. Clearing of site after completion of work. Return of OWNER’S surplus and free supply materials and other excess materials included in work order to OWNER after accounting. OWNER’S SUPPLY Owner’s obligations shall include: Supply of all pipes, pipe fittings, cable trays and ducts, valves, flanges, junction boxes, control panels, gauge boards two core and multi-core control/ power/ shielded cables, three core and multicore resistance thermometer cables, single 3.2.0 3.3.0 3.4.0 4.0.0 4.1.0 4.2.0 4.3.0 4.4.0 Page 3 of 30 pair and multipair compensating cables two core and multi-core electrical/ electronic cables etc (except those included in contractor’s scope.) Supply of all pneumatic, electrical, electronic and analytical instruments, special sampling systems, resistance thermometers, dial thermometers, thermocouples, bimetallic thermometers, thermo wells, all the switches for alarm and shutdown, pressure and vacuum gauges, air filter regulators, solenoid valves, output gauges, analyzer cabinets etc except those included in the contractor’s scope. Supply of water free of cost and electricity on chargeable basis. Cranes, jumbo trucks, forklifts etc will be spared by the owner on chargeable basis (only if available) otherwise contractor has to make his own arrangements. PART B- TECHNICAL REQUIREMENTS INSTRUMENT INSTALLATION The instrument contractor shall ensure that the instruments are received in good condition and shall report defect if any to the engineer in charge. The contractor will be responsible for safety of all instruments thereafter till the commissioning of the plant. Any loss or damage of instruments while in his custody shall be chargeable to the contractor. Contractor shall be responsible for supply and cost of all replacement material and labour necessary to rectify faults which occur during instrument installation or testing period due to reasons such as falls or due to faulty work man ship or faulty material in the contractor’s supply. All the instruments are to be checked for their calibration prior to installation in the field and shall be corrected for any calibration misalignments that would have occurred during transportation or subsequent handling. All the installation works shall be done as per released construction drawings, instrument installation drawings and manufacturer’s instruction manuals that will be supplied after the contract is finalized. If the area in which the installation are to be carried out are partially hazardous [as per area of classification] and partially FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 4.5.0 5.0.0 5.1.0 5.1.1. 5.1.2. 5.1.3. 5.1.4. 5.1.5. 5.1.6. 5.2.0 5.2.1. 5.2.2. 14 ES008 /15 5.2.3. 5.2.4. 5.2.5. 5.2.6. 5.2.7. 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION general purpose then the instrument erection contractor shall execute all the electrical works in accordance with applicable codes of Indian standards for electrical installation and owners safety regulations. Contractor shall handover/ report all faulty instruments or any defects found, which may arise due to design omission or discrepancies, which would impede the proper functioning of instruments/ system must be brought to the notice of engineer in charge without undue delay. ONLINE INSTRUMENTS Instrument contractor shall supervise and ensure correct installation of on-line instruments, by piping contractor. It will be the responsibility of the instrument contractor to see that the following are accomplished as per specifications and drawings. FLOW TUBES (Venturi, nozzle etc) The flow tube shall be installed in pipeline with arrow aligned in the direction of flow. The straight pipe lengths adjacent to flow tube shall conform to vendor drawings /standards. Tapping & fittings shall be as specified in the instrument process piping drawings. Measurements of I.D, length shall be done in order to ensure that correct unit is installed for each line. Change in I.D if any, shall be reported to site Engineer. Ensure that no weld deposit is projecting inside the pipeline. Gasket used shall be that specified for duty and shall not project inside the pipe beyond the limits specified by standards. ORIFICE PLATE Orientation of tapping & necessary straight length upstream and down stream of orifice. Proper gasket (gasket shall not project inside the pipe and shall be within the limit specified in orifice plate specification.) Proper direction of orifice plate. No weld materials shall project inside the pipeline near the orifice. Location of tapping shall be at proper distance from orifice plate. Correct orifice plate /unit is installed for each line. The drain/ vent hole in the orifice plate shall be located as per specification. 5.2.8. 5.3.0 5.3.1. 5.3.2. 5.3.3. 5.4.0 5.4.1 5.4.2 5.4.3 5.4.4 5.4.5 5.4.6 5.5.0 5.5.1 5.5.2 5.5.3 5.5.4 Page 4 of 30 Concentricity of orifice bore with pipe I.D. shall be ensured. INTEGRAL ORIFICE TRANISMITTERS Transmitters shall be installed in coordination with piping contractor with correct flow direction along with the straight pipe pieces adjacent to flow transmitter. In the case of pneumatic transmitter, connect receiver gauge and air set with proper air and signal tubing. Tubing wherever required shall be done with necessary slopes as stipulated in the installation standards. In the case of electronic transmitters, twisted pair screened armored cable /cables as specified shall be glanded and terminated as per termination details. ROTAMETER, PURGE ROTAMETER & ROTAMETER TRANISMITTER Contractor shall supervise &ensure the following while piping is in progress. Verticality of meter The float which is removed for the purpose of transportation shall be kept in position before installation. Proper gaskets are used. Rotameter scale clearly visible from the operation platform. Reducer pairs supplied with meter to be installed by piping contractor shall be supervised by instrument contractor. After installation, proper air & signal connections shall be made through junction box & to control room. [tubing &tube connections are covered separately in section 16.0.0] Air set if supplied loose shall be installed as per instrument pneumatic diagram. TURBINE /MAGNETIC /VORTEX/ POSITIVE DISPLACEMENT/ ULTRASONIC/ MASS FLOW METER The flow meter is to be mounted, wired and tubed as mentioned below: Flow meter shall be installed, in coordination with the piping contractor, on pipeline with arrow aligned in the direction of flow. The straight pipe lengths adjacent to flow meter shall be 10xD upstream 5xD downstream or as recommended by the manufacturer. Care shall be taken to ensure correct alignment of flow meter with in mating pipe work. Electrical connection from the flow meter to the secondary instruments shall be FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 5.5.5 5.5.6 5.6.0 5.6.1 5.6.2 5.6.3 5.6.4 5.6.5 5.6.6 5.6.7 5.6.8 5.6.9 14 ES008 /15 5.6.10 5.7.0 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION made. Do not run the signal leads in the same conduit/ tray as that for power supply. [Cable wiring & conduit work are covered separately] The complete installation shall be carried out in accordance with the instruction manual supplied by vendor. The flow meter shall not have any strain on its body from adjacent pipes. CONTROL VALVES, DAMPERS, PRESSURE REDUCING VALVES, DESUPERHEATERS The instrument contractor shall ensure the following while the control valve is being installed by the piping contractor. Control valve is installed in the correct direction. The control valve is not under mechanical strain after erection. Proper gaskets are used for the purpose. In the case of butterfly valve the vane shall not be obstructed by any piping parts and shall be free to rotate. The air supply to the control valve and the signal line from the respective controller to the valve positioners /valve shall be made by the instrument contractor. Signal tubing, instrument piping etc are covered separately. For valves with air filter set and positioner, contractor shall ensure that the valve positioner & the associated linkages are physically and functionally in good condition. When solenoid valve is mounted on the valve, the air connections would be provided by the valve supplier. Contractor shall give all electrical connections through required fittings. Instrument contractor shall ensure the proper installation of the pressure control valve by piping contractor with respect to direction and other aspects for control valves. The backpressure tappings from the downstream/ upstream piping shall be properly connected by the instrument contractor. Calibration of control valve shall include all testing and calibration of all the accessories such as limit switches, continuous position feedback etc. MOTOR OPERATED VALVES The instrument contractor shall ensure proper installation of motor operated valve while it is being erected by piping contractor. The electrical connections 5.8.0 6.0.0. 6.1.0. 6.1.1. 6.1.2. 6.1.3. 6.2.0. 6.2.1. 6.2.2. 6.2.3. 6.3.0. 6.4.0. Page 5 of 30 will be provided by the electrical contractor. Instrument contractor shall ensure that proper earthing of the valve body is made by the electrical contractor before commencing any work on the valve. Also instrument contractor shall ensure proper functioning of limit switches, open, close commands, continuous position feedbacks, other contacts if any. SOLENOID VALVES Work involves installation of solenoid valve on pneumatic signal lines to control valve/ damper actuator, and termination of electrical cables. All necessary electric & pneumatic connections shall be done by instrument contractor, [tubing & wiring conduit work etc are covered separately under sec. 16.0.0& 17.0.0]. FIELD MOUNTED PRIMARY MEASURING ELEMENTS ANNUBAR FLOW ELEMENTS/ PITOT TUBE Elements shall be so installed that it can be inserted or withdrawn from the pressurized pipe lines under flow conditions without interruption of service. Annubar installation shall be as per instrument process piping drawings and instruction manual supplied by the vendor. All the process piping connections shall be given by the contractor [piping covered under 16.0.0]. TEMPRATURE ELEMENTS [T/C & RTD] T/C shall be installed at proper locations along with specified thermo well. T/W shall be screwed or flanged type and shall be adequately tightened with use of proper gasket, nuts & bolts, which will be supplied by the owner. Each T/C shall be connected by proper signal /extension cable using proper glands from individual temperature element to junction boxes.[cables are included separately under 18.0.0] MULTIPLE T/C ASSEMBLIES Work involved is same as above. RTD ELEMENTS [FOR BEARING TEMPRATURE] R.T.D elements are already wired up to local junction boxes by the equipment vendors. Contractor shall connect these from junction boxes through the multicore leads with the corresponding instrument point. [The cabling is included separately FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 6.5.0. 7.0.0. 7.1.0. 7.2.0. 7.2.1. 14 ES008 /15 7.2.2. 7.3.0. 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION under 18.0.0]. The RTD elements are already installed on machinery / equipment. In case these instruments are not installed by the vendor in the field, instrument contractor shall arrange to install these instruments as per 6.0.0. VIBRATION PROBES, AXIAL DISPLACEMENT PROBES & DRIVE SPEED PROBES All the probes are already mounted on the machinery /equipment by the vendor and wired up to junction box and terminated. Instrument contractor shall provide the electrical connection from the junction box to control panel. In case these were not installed by the vendor in the field, instrument contractor shall arrange to install these probes as per drawings. FIELD MOUNTED TRANISMITTERS PNEUMATIC D/P TRANISMITTER FOR FLOW, LEVEL, DENSITY ETC Mounting of differential pressure transmitters, air filter regulator, locally fabricated suitable stands /supports, tubing them from the first isolation valves with the 3 valve manifold, giving necessary slopes as stipulated in the installation diagrams. Provide air supply using 6mm OD SS tubes; connect ¼” OD copper tube [output], to a receiver gauge or to the secondary local instrument or to junction box as the case may be. Install air filter set. [Tubing, process piping supports etc are covered separately under sec 16.0.0]. LEVEL TRANISMITTERFLANGE MOUNTED FLUSH /EXTENDED DIAPHRAM TYPE Mounting of the transmitter on the vessel nozzle /isolation valve using proper nuts, bolts, gaskets, receiver gauge, air set and pneumatic tubing shall be installed as per 7.1.0. FLUSH /EXTENDED DIAPHRAM TYPE WITH REMOTE SEAL–FOR LEVEL AND DENSITY Work involved is identical to item 7.1.0 except that instead of impulse tubing, capillary tubing with flanged diaphragm to be mounted on to the vessel nozzle/ isolation valves the capillary tube shall be supported properly. GAUGE/ ABSOLUTE PRESSURE TRANISMITTERS 7.4.0. 7.4.1. 7.4.2. 7.4.3. 7.4.4. 7.4.5. 7.5.0. 7.6.0. 7.7.0. 7.8.0. 7.8.1. 7.8.2. 7.8.3. Page 6 of 30 The work involved is identical to item 7.1.0 except that there will be only one impulse tapping. DISPLACEMENT TYPE LEVEL TRANISMITTERS WITH AIR SET The displacement type level transmitters with air set shall be fitted in such a way that it is subjected to minimum vibration The installation shall be carried out using necessary pipes, isolation valves & other fittings as specified in the instrument process piping drawings. Connections of air supply lines- free of oil, water &dust -at constant pressure of 1.4 kg/cm.sq. Calibration &checking should be carried out in co-ordination with piping group. [Installation of valves, pipes& tube are covered in section 16.0.0]. The air filter set shall be installed as specified in instrument pneumatic tubing diagram. ELECTRONIC TRANISMITTERS The details in item 7.1.0 to 7.4.0 under pneumatic transmitters will be applicable to electronic transmitters except that cabling is involved instead of tubing. ELECTRO MECHANICAL LEVEL TRANISMITTERS Mounting the instrument on the vessel nozzle/ flange using proper gaskets, nuts, bolts and connecting the power /signal cables. RADIO ACTIVE LEVEL TRANISMITTERS Installation of the radioactive source, line detector and point detectors as per the details provided by the manufacturer and strictly following the government regulations. TANK LEVEL TRANISMITTERS (FLOAT AND TAPE TYPE) Installation of float and tape, guide wires, protector pipe with V– seal and mounting the transmitter on suitable supports. The protector pipe shall be properly supported and signal cable shall be terminated. TEMPRATURE TRANISMITTERS The installation shall be carried out as per instruction manuals of vendors. The thermo well with bulb shall be fixed [screwed or flanged] on the pipeline using proper thread sealant or nut, bolt, gaskets as the case may be as per 6.2.2. Integral type temperature transmitters shall be mounted on the thermo well FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 7.8.4. 8.0.0. 8.1.0. 8.2.0. 8.3.0. 9.0.0 9.1.0 14 ES008 /15 9.2.0 9.2.1. 9.2.2. 9.2.3. 9.2.4. 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION head. Signal Cable shall be glanded and terminated. Remote mounted transmitter shall be separately mounted on a pedestal with proper accessibility and the cable to temperature element and signal cable to control room shall be glanded and terminated to the transmitter. FIELD MOUNTED CONTROLLERS INDICATING CONTROLLERSPNEUMATIC The work involves mounting the transmitter/ controller on proper support Suitable piping connections, air supply connections, and signal lines shall be provided as specified to correct final control element. The piping & tubing shall be as specified in the process piping diagrams. [The details for supports tubing’s &piping are covered under 16.0.0]. DISPLACEMENT TYPE LEVEL TRANISMITTER + CONTROLLER WITH AIR SET Work involved is a combination of 7.4.0 and 8.1.0. ELECTRONIC CONTROLLERS Field mounted electronic controllers are either mounted inside local control rooms or in local control panel. The installation of the controller inside the room shall be in a panel with suitable size cut out. The panel cutting and complete installation and wiring of the controller shall be as per manufacturer’s instruction manuals and shall be done by the contractor. Wherever local panel mounted controllers are used, mounting of the panel on its foundation, purging connections, all wring and termination, canopy for the local panel etc will be in contractor’s scope. FIELD MOUNTED GAUGES PRESSURE GAUGES Installing pressure gauge using suitable connecting tubes /vent/ drain/valves /etc from the first isolation valve provided on ducts/ pipes/ vessels/ pumps etc. MANOMETER Scope includes: The installation of instruments with proper supports. Filling with proper manometer fluid. Connecting all the piping and valves as per the drawings. Providing final connections using a flexible hose. Page 7 of 30 (The details for piping fittings and valves are covered separately.). 9.3.0 LEVEL GAUGE [REFLEX TYPE] Each level gauge shall be fitted with a pair of gauge cocks, the piping connections & fittings shall be carried out as per the instruction given by the supplier and as per the instrument installation diagram. 9.4.0 MAGNETIC LEVEL GAUGES Work involved is same as item 9.3.0 except that care shall be taken to handle it properly so that the magnetic float is not damaged. 9.5.0 BOILER LEVEL GAUGES 9.5.1 The high pressure level gauge shall be fitted with proper gaskets & weather proof one end open hood and suitable illuminator. 9.5.2 Process piping connections & complete installation shall be in accordance with instruction manual supplied by vendor. Supply using cables shall be connected to the illuminator from the near by switch provided by the electrical contractor. [The details for piping and fixing valves conduit &wiring etc. shall be covered separately.] 9.6.0 BOILER LEVEL GAUGE WITH REMOTE INDICATION 9.6.1 This shall include the erection of condensate chamber. 9.6.2 Process connections &complete installation should be carried out in accordance with instruction manual supplied by the vendor, while piping work is in progress. 9.7.0 TANKAGE SYSTEMS 9.7.1. ELECTRONIC TANK GAUGING SYSTEM 9.7.1.1. The tankage system, including servo and radar type level instruments with associated instruments such as pressure /single element temperature transmitter/ multiple temperature element transmitters, tank side indicators, junction boxes etc shall be mounted and wired as per vendor’s installation manual and wiring drawings. 9.7.1.2. Connection to control room and commissioning of the system shall be under the supervision of the tank gauging vendor. 9.7.1.3. The control room panel erection, necessary inter-panel wiring, cold loop checking of field cables etc of the system is also under the scope of the vendor. FACT ENGINEERING AND DESIGN ORGANISATION 14 ES008 /15 ENGINEERING SPECIFICATION 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION 9.7.2. FLOAT AND TAPE METHOD 9.7.2.1. Contractor shall ensure that the instrument is located in an easily accessible place. Location shall also be such that ambient temperature is within the specified limits as given by the vendor. 9.7.2.2. For float and tape measurement, contractor shall install measuring tape, float, protector pipe, local indicator and supports as per hookup drawings or vendor drawings. 9.7.2.3. Contractor shall fix the channel steel or pipe vertically, which does not bend due to its weight, under the sidewall of tank, for accurate measurements. 9.7.2.4. The float and tape shall not be subjected to sudden, abnormal vibrations, due to a violent stream of feed fluid or while erecting the same. 9.8.0 DIAL TYPE INDICATING THERMOMETERS The work involves installing of thermometers and thermo-wells (threaded or flanged) on pipes/ vessels using proper nuts, bolts &gaskets provided by piping group. The threaded thermo well shall be fitted using Teflon tapes or pipe ‘dopes’ as the case may be. 9.9.0 TEST THERMOWELLS Mounting of thermo well on the pipes/ vessels using proper nuts, bolts and gaskets 9.10.0 DIFFRENTIAL PRESSURE INDICATOR Work involved is same as per 9.1.0 except that there are two tapping. 9.11.0 THERMOMETER –CAPILARY TYPE Work involved is same as per 9.7.0, except that the capillary tube shall be supported by tray / structural. 10.0.0. FIELD MOUNTED SWITCHES 10.1.0. RECIEVER PRESSURE SWITCH (PNEUMATIC) The pressure switches shall be mounted on suitable supports. Necessary pneumatic tubing and electrical connections shall be made. The pneumatic signal shall come from corresponding transmitter. [Pneumatic tubing and electrical wiring are covered separately under 16.0.0 & 17.0.0] 10.2.0. DIRECT CONNECTED PRESSURE SWITCH 10.2.1. Work involved is same as 10.1.0 but impulse tubing shall be connected from pipelines /vessels using proper isolation 10.2.2. 10.3.0. 10.4.0. 10.5.0. 10.6.0. 10.7.0. 10.8.0. 10.9.0. 11.0.0. 11.1.0. 11.1.1. 11.1.2. 11.1.3. Page 8 of 30 valves instead of pneumatic copper tubing from transmitters. Pressure switches shall be installed rigidly to avoid vibration. DIRECT CONNECTED DIFFRENTIAL PRESSURE SWITCH Work involved is same, as 10.2.0 except that impulse tubing shall be provided. DIRECT CONNECTED LEVEL SWITCH [INTERNAL/ EXTERNAL/ FLOAT TYPE] Scope includes the installation of level switches on vessel, making necessary electrical connections using armored cable [scope for wiring is covered separately under 16.0.0& 17.0.0]. LEVEL SWITCH TUNING FORK TYPE, PADDLE TYPE, CAPACITANCE TYPE [WITH OR WITHOUT EXTERNAL CHAMBER] Scope of work is same as item 10.4.0 TANK LEVEL SWITCHES [FLOAT AND TAPE TYPE] Installation of float, tape and guide wires, mounting the switch on the vessel flange, connecting the cable and termination. TEMPRATURE SWITCH The scope of work includes mounting temperature switch with thermo well on the vessel/ pipe line, cabling and termination etc. DIRECT CONNECTED FLOW SWITCH Scope of work includes, mounting the flow switch on the pipe line, cabling and termination. LIMIT SWITCH Electrical connection to be made to the limit switches mounted on control valves, actuators etc. ANALYSERS Manufacturer’s instruction manuals shall be strictly followed for proper installation and functioning of analyser. PH ANALYSERS IMMERSION TYPE Mounting the electrode with holder using the mounting hardware provided, installing the analyser transmitter and JB on 2” pipe pedestal and termination. FLOW THROUGH TYPE Contractor shall supervise and ensure the proper installation of the electrode chamber on the pipe line by piping group. Analyser transmitter and JB shall be mounted on 2” pipe pedestal and the air supply tubing, cabling and termination shall be done. PH- ANALYSER, CABINET MOUNTED FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 11.2.0. 11.2.1. 11.3.0. 11.4.0. 11.5.0. 11.6.0. 14 ES008 /15 11.7.0. 11.8.0. 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION Installation of the analyser cabinet, air supply tubing, interconnecting cabling and termination. CONDUCTIVITY ANALYSERS Contractor shall supervise and ensure the proper installation of the electrode chamber on the pipe line by piping group. Analyser transmitter and JB shall be mounted on 2” pipe pedestal and the interconnecting cabling and termination shall be done. CONDUCTIVITY ANALYSER WITH SAMPLING RACK Installation of the analyser sampling rack, impulse tubing for sample inlet and outlet/ drain, cooling water inlet and outlet, interconnecting cabling and termination etc shall be done. DISSOLVED O2 ANALYSERS Mounting the electrode with holder using proper support, installing the analyser amplifier and JB on 2” pipe pedestal, mounting the power supply converter and inter connecting cabling and termination etc. PROCESS TITRATORS Installation of the process titrators inside the local control room and the connected cabling and tubing/ piping, as per installation details provided by the manufacturer shall be done. DENSITY ANALYSER (VIBRATION TYPE) Mounting the analyser sampling rack and cabling and termination etc shall be done. DENSITY ANALYSER (FLOAT TYPE) Contractor shall supervise and ensure the proper installation of the density analyser on the pipe-line by piping group. Pneumatic to electronic converter shall be mounted on 2” pipe pedestal, air supply /signal tubing, cabling and termination etc to be done. MOISTURE ANALYSERS The analyser probe shall be mounted on the flange provided on the pipe line using proper gasket, nuts and bolts which will be supplied by the owner. The signal cable shall be connected to the probe and terminated. OLEUM ANALYSER Work involved is same as item 11.7.0. In addition to the above, contractor shall mount the analyser transmitter and junction box on suitable support in the 11.9.0 11.10.0 11.11.0 11.12.0 11.13.0 11.14.0 11.15.0 12.0.0 12.1.0 12.1.1. 12.1.2. 12.1.3. 12.1.4. 12.2.0 Page 9 of 30 field, and inter-connecting cable to be terminated. TERMAL CONDUCTIVITY ANALYSER Installation of the sampling cabinet, analyser cabinet at locations shown in the layout drawings, connecting the sample tubing as per the drawings, and terminating the cables etc shall be done. Manufacturer’s instruction manuals shall be strictly followed for the installation and functioning of the analyser. INFRARED ANALYSERS. Work involved is same as item 11.9.0 PARA MAGNETIC O2 ANALYSERS Work involved is same as item 11.9.0 NOX ANALYSERS Work involved is same as item 11.9.0 SO2 ANALYSER Work involved is same as item 11.9.0 ZIRCONIA PROBE FOR O2 ANALYSER Work involved is same as item 11.8.0 ONLINE GAS CHROMATOGRAPHY Work involved is same as item 11.9.0 MISCELLANEOUS INSTRUMENTS HYDROCARBON DETECTOR The scope includes fixing of the detector on a pedestal downstream of local wind direction such that the gases to be detected are facing to the element. The installation of canopy shall not keep the wind away from the detecting assembly. The associated cabling and termination shall be as per the drawings released by FEDO. The elevation of the detector shall be such that for detection of heavier gases (Compared to air) the instrument shall be located above the point of leak source. Similarly, for detection of lighter gases, the instrument shall be mounted below the point of leak source. Where line of sight gas detectors are specified, their installation, alignment etc shall be strictly as per vendor’s instruction manual. For transmitterreceiver type or transmitter-reflector type instrument, the line of view shall be free of obstructions and frequent passage ways of man/ machinery. The cabling of both the transmitter and receiver will be in the scope of the contractor. For detection of toxic gases, the instrument shall be located as near to the point of source as possible for faster detection of leaks. HEAT/ SMOKE DETECTOR FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 12.2.1. 12.3.0 12.1.1. 12.1.2. 12.1.3. 12.4.0 12.2.1. 12.2.2. 12.5.0 12.3.1. 12.3.2. 12.3.3. 12.3.4. 12.6.0 12.4.1. 14 ES008 /15 12.4.2. 12.4.3. 12.7.0 12.5.1. 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION These types of instruments are normally located inside buildings. The installation of these instruments shall be as per relevant NFPA standards. The scope shall be generally same as in 12.1.0 except that these instruments are either ceiling/ wall mounted. FLAME DETECTORS Fixing the detecting element in such a way that direct flame and heat will not damage the instrument. Mounting the preamplifier/ relay units inside a dust tight metal enclosure or local panel supplied by others. Interconnecting cabling between the detecting element and the relay. VANE ACTUATORS Supervision of installation of the vane actuator carried out by mechanical contractor and to ensure that the same installed as per manufacturer’s recommendations. Termination of tubing and wiring on to the positioners, air set, I/P converter etc of the actuator. SUCTION PYROMETERS To install the suction pyrometer assembly on to the flange nozzle of the furnace using proper gaskets, bolts and nuts, supplied by the owner. This is to be connected by proper compensation/ extension cable up to the junction box. Provide necessary tubing with required fittings for air connection to the ejector of the suction pyrometer. Cabling for suction pyrometer will be similar to thermocouple. ACTUACTOR OF CONTROLLED VOLUME PUMPS The control volume pump will be installed by machinery contractor. Instrument contractor shall supervise the installation work and ensure that the same is installed as per manufacturer’s instructions/ recommendations. Provide the termination of signal cable (4-20 mA signals) and also tubing for all connection to the positioners unit and the actuator. Generally the scope of work will be similar to control valve. OPERATION BOX This is required for the local operation of bagging machines etc. This houses the push buttons and lamps required for the operation of bagging machine. 12.5.2. 12.8.0 12.9.0 13.0.0 13.1.0. 13.1.1. 13.1.2. 13.1.3. 13.1.4. 13.1.5. 13.2.0. Page 10 of 30 Instrument erection contractor shall install the operation box properly on a suitable structure nearby using brackets if required. Provide termination of all incoming and out going cables to the operation box as per the wiring scheme of bagging machine supplier. MOTION DETECTOR This is Small electronic instrument provided with mounting socket, similar to a relay. Contractor shall mount the motion detector inside a housing provided by purchaser and terminate all incoming and outgoing cables as per manufacturer’s wiring scheme. I/P CONVERTERS + POSITIONERS & E/P POSITIONERS Mounting I/P converters on separate supports wherever necessary, making the electrical and pneumatic connections. JUNCTION BOXEs, PDBs, MBs ELECTRICAL JUNCTION BOXES, PDB’S, MB’S AND TERMINATION BOXES Fabrication of necessary supports and welding it on the available structures or grouting on to the floor including the civil work connected with it. Mounting the junction box, connecting the individual cables and multicore cable using cable glands and terminating the wires. All the electrical wires shall be identified using the cable marking ferrules. For termination boxes, only one cable entry and outlet is required. All other holes shall be blinded with suitable plugs. Where cable runs are underground, junction boxes, marshalling boxes etc shall be mounted above grade at convenient height for easy access. If the wiring is over-head, JBs/ PDBs/ marshalling boxes shall be mounted a few feet above grade for easy access. Care shall be taken to ensure safe working conditions. Where wiring must enter the top of JBs/ PDBs/ marshalling boxes, it shall be brought near the bottom of the box and then back up to terminals. Forming a drip loop near the bottom of the JBs/ PDBs/ marshalling boxes. JBs/ PDBs/ Marshalling boxes shall be mounted suitably such that they do not hinder works like movement of personal around the plant, removal of equipments like heat exchanger shell tubes .etc. RTD JUNCTION BOXES FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 13.3.0. 13.4.0. 13.5.0. 14.0.0 14.1.0. 14.2.0. 14.3.0. 14 ES008 /15 14.4.0. 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION Work involved is same as item 13.1.0 TERMOCOUPLE JUNCTION BOXES Work involved is same as item 13.1.0, except that compensating cables are used instead of electrical cables. A.C. POWER DISTRIBUTION BOXES Work involved is same as item 13.1.0, except that the distribution box houses isolation switches and fuse units for distributing 110VAC power to field instrument. ENCLOSURE FOR INTRINSIC SAFE BARRIERS Work involved is same as 13.1.0, except that the contractor shall mount I.S barriers inside the enclosure and the incoming and outgoing cables are to be glanded and terminated. CONTROL PANELS The control panel is pre-wired, and pretubed, all the wire and tubes being terminated to the respective terminal blocks, and bulkheads respectively. Instrument contractor shall undertake the installation of panels, mounting the instruments on the panel and execute all the termination of wiring & tubing at the back of the panel. Instrument erection contractor’s scope shall include but not be limited to the transportation, calibration / testing, loopchecking etc, of all the panel mounted instruments. However, if the contractor has to under take some of wiring and tubing which are found necessary at a later stage for which they have to indicate the cost of the wiring / tubing per meter basis the materials will be supplied by the purchaser. The local control panels shall be mounted as per instrument location and cable routing diagrams, IADs/ GADs. All the wires and tubes shall be terminated as per instruction manual from manufacturer. Foundation for panels and racks shall meet the requirements of the equipment vendor’s specifications. Panel shall be located to allow easy access and operation and to permit operator to survey the maximum panel area, panels shall be arranged and located for easy reading, servicing and maintenance of equipments and panels/ cubicles. Air purging shall be used whenever necessary for environment reason as well as electrical safety. Panels shall be removed from racks only 15.0.0 15.1.0 15.1.1. 15.2.0 15.2.1. 15.2.2. (a) (b) (c) (d) (e) (f) Page 11 of 30 when ready for installation. Hooks shall be used while lifting and moving the panel. Welding shall not be done on the panel at site for supports etc. Panels shall not be used as earth as it may damage the electronic instrument. Proper earthing for the panel shall be provided separately; otherwise it shall be connected to the main earth of the plant. FABRICATION WORK AND MOUNTING OF INSTRUMENTS FABRICATION WORK. Instrument contractor shall fabricate different steel structures supplied to him as per drawings. Unit rates shall be applicable as shown in bid item. Minor civil works like chipping, grouting, etc, shall form part of fabrication job. Consumables like welding rods and gas shall be included in the fabrication cost. INSTRUMENT AIR LINES Piping contractor will terminate main instrument air header lines on the pipe bridge with first isolation valve for branch lines for instrument air distribution. The fittings will be welded type and pipes will be galvanized carbon steel type. Contractor’s scope includes installing, testing and commissioning of these lines. 316L PIPES /316SS PIPES, CARBON STEEL PIPES Welding of instruments’ impulse lines using pipes shall be done by qualified welders as per the standard welding procedure. NOTES ON MOUNTING OF INSTRUMENTS Mounting of all accessories of fieldmounted instruments such as manifolds, air sets, condensate pots etc wherever applicable, are included in the installation of the instruments and no extra shall be paid for their accessories. No field mounted instrument shall be installed with support from impulse piping/ signal lines. Hand rails shall never be used for mounting or supporting instruments. Instruments shall be mounted on pedestal fabricated using base plate and 2” pipe of about 1.5meter height. All field mounted instruments shall be mounted at grade or on platform. If pedestal is installed at paved area, it shall be fixed to the concrete paving with anchor bolts FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 14 ES008 /15 (g) 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION If ground is unpaved, a concrete base shall be provided for the pedestal. Pedestals mounted on the top of platforms or process piping shall be removable. (h) The instruments shall be mounted on pedestals using “U” clamps, nuts and bolts or as per installation drawings given by engineering department or vendor. (i) Pedestal shall be painted to protect from corrosive atmosphere and weather conditions. 16.0.0. GENERAL NOTES FOR INSTRUMENT PIPING AND TUBINGS 16.1.0. The sizes of the piping /tubing and also their materials of construction are decided by the designer of the instrumentation and control system. 16.2.0. Instrument tubing (mainly SS) shall be cut using only the standard cutter. Use only fine sand–paper for polishing the outer edge of the tubes after cutting. Never use a file or grinder. Any burr or scratch will not make a good tight–fit when joining the tube with compression type couplings. After tightening, softly remove the joint and inspect for the uniform closure of the ferrule on the fitting. 16.3.0. Where tubing is adjacent, clearance between them near the coupling portion shall be at least 10cm for easy maintenance. 16.4.0. The pipes shall be supported on angles using proper U-clamps. 16.5.0. Pipe lines (for impulse lines) shall be bent only after sand filling and heating and using a bending tool, otherwise, it will kink and become weak. 16.6.0. Always avoid sharp bends. Use only smooth bends wherever necessary. 16.7.0. Give proper support for the piping for drawing out purpose. 16.8.0. When using pipe connector or couplings, adequate space for spanner head shall be provided. 16.9.0. When brazing or welding two pipe ends, care shall be taken to see that the adjacent pipes/ vessels are not affected by this heating. 16.10.0. For ‘reference drawings’ list refer to document control index. 16.11.0. All instruments on instrument piping details and other instrument drawings are shown symbolically. For true picture and location of connection refer to vendor’s drawings. Page 12 of 30 16.12.0. Instrument connection block valves on lines, orifice flanges, vessels and equipment are to be in accordance with the specification of the line, vessels or equipment to which they connect and that are furnished by the piping division. 16.13.0. Field contractor shall relieve strain from all connections by properly supporting all pots, leads and instruments. Refer to “typical instrument support details” and standard drawings attached. 16.14.0. Instrument pressure leads and flow meter leads are to be sloped 1 in 12 minimum in horizontal runs, except that long pressure instrument leads carried on racks through the yard may be run horizontally, but without pockets, together with pneumatic leads. 16.15.0. When a pressure lead rises above the pressure connection and the instrument it serves a minimum slope of approximately 1 in 12 from high point of the lead toward the pressure connection and the instrument must be maintained. 16.16.0. ‘Field’ contractor shall provide sufficient flexibility for pressure leads and pneumatic leads to allow for thermal expansion of vessels, lines or equipment to which they connect. 16.17.0. Use bends in all pressure leads and keep threaded joints to a minimum. 16.18.0. Bends in tubing for pneumatic leads are to be kept to the absolute minimum required. 16.19.0. All pressure leads and pneumatic leads to and from instruments are to be thoroughly cleaned of burrs and foreign matter before being put into operation. 16.20.0. All pressure/ level instruments in wet service are to be corrected for liquid head pressure. 16.21.0. Instruments, instrument pressure leads, flow meter leads and pneumatic leads shall not be mounted on, nor supported from platforms, railings, steel supports, equipment and process or utility lines that are subject to abnormal vibrations, particularly vibrations caused by reciprocating machines, unless absolutely necessary. Additional bracing and / or supports shall be provided for instrument and instrument leads to assure rigidity under such abnormal conditions. 16.22.0. Where rack is not provided, pneumatic leads [generally 3 or less] shall, be strapped to air headers or branches. FACT ENGINEERING AND DESIGN ORGANISATION 14 ES008 /15 ENGINEERING SPECIFICATION 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION 16.23.0. Elevation shown in instrument locations and air supply header drawings are to bottom of piping unless otherwise noted. 16.24.0. The quantities given in the bill of materials for pipes and tubes are for straight pieces only. Installation of fittings like elbows, tees, valves condensate pots etc. shall be included in the cost of erection and no separate charges will be applicable for these items. 16.25.0. Locations and facing of instruments shall be adhered to as closely as possible. 16.26.0. Air supply piping will be supported on existing steel. ‘Field’ contractor shall provide additional steel wherever required. 16.27.0. ‘Field’ contractor shall provide all materials required for mounting and supporting instruments, Instrument pots, piping etc. Refer to “typical instrument support details” drawings. 16.28.0. Unless otherwise noted, pedestal type mounted transmitters, indicators, recorders and controllers shall be located with the center line of the instrument 1.3M above grade or platform. 16.29.0. All elevations given are based on the grade elevation indicated on the lay out drawings. 16.30.0. All tube fitting shall be used as specified in instrument hook up &layout drawings. The contractor shall ensure material, dimension and physical condition of all items before putting them into service. 16.31.0. For D/P transmitters with capillary extension, the capillary tube shall be insulated using glass wool with aluminum cladding as indicated in the instrument application diagrams. 16.32.0. Welding as per the standard procedure /specifications shall be followed. Any pre heating/ post-weld heat treatment shall be done wherever required as per standards. 16.33.0. All pipe lines shall be thoroughly checked for cleanliness and moisture before and after installation. 16.34.0. After testing, all C.S pipes shall be epoxy painted. 16.35.0. The take off points shall be from top of the header. 16.36.0. While brazing or welding two pipe ends, care shall be taken to see that adjacent pipes /vessels do not get affected due to heating. 16.37.0. Even when dryers are supplied to keep the air dry, a drain shall be installed at Page 13 of 30 low point(s) in the system to provide drainage. 16.38.0. No bends, scratches or cuts shall be made on any of the enclosed tubes, as these will be points of potential failure. 17.0.0 GENERAL NOTES ON TERMINATION, ELECTRICAL INSTALLATION AND GROUNDING 17.1.0 TERMINATION 17.1.1 Wires of cable shall be cut as it comes off the reel at location free from sharp objects. 17.1.2 Jacket shield material shall be terminated without cutting insulation underneath. If no pair jackets is used and pair are individually shielded then insulating tape or sleeving shall be applied to exposed shielded in order to protect accidental grounds. 17.1.3 All cable ends shall be protected against moisture entry prior to connecting the cables to its permanent terminations. 17.1.4 Stripping of insulations from wire shall be done without cutting the conductor. Standard stripping tools of proper design shall be used. 17.1.5 Screws shall be torqued adequately to get good contact with wires inserted under the screw. 17.1.6 Proper compression of terminal screws shall be done to prevent corrosion which may later cause poor continuity, galvanic, or rectification action .High qualityterminal strips and insulating materials shall be used. 17.1.7 All wires or leads terminated at connection shall have sufficient slack to reduce the effect of vibrations. 17.1.8 Necessary cable supports shall be provided to avoid having cable weight support from wire terminations. 17.2.0 ELECTRICAL INSTALLATION 17.2.1 The equipment erection and their installation shall confirm to the latest Indian electricity rules and Indian Factories Act, as regards safety, earthing and other essentials provisions specified therein form installation and operation of the electrical part of the instrumentation loop. 17.2.2 Fittings switches, distribution boards, junction boxes etc for electrical lines shall be installed at places indicated in drawings. 17.2.3 The cable termination shall be done using solderless crimping type closed eyelet connectors [contractor’s supply]. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 17.2.4 17.2.5 17.2.6 17.2.7 17.2.8 17.2.9 17.2.10 17.2.11 17.2.12 17.2.13 14 ES008 /15 17.2.14 17.2.15 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION Cables carrying 110 volts or above shall not run in same conduit, metal or PVC ducting, trunking or trays as cables carry lower voltage. Cables carrying alternative current shall not be run in the same conduit, metal or PVC ducting trunking or trays, as cables carrying direct current unless agreed to the owner in writing. There shall be a minimum separation of 200mm between trays carrying these signals. Laying of earth, conductors fixing on cable duct /tray structural, clamping/ jointing by brazing wherever necessary, testing and commissioning including supply of earth conductors, crimping lugs, bolts, nuts, washers etc and supply and installation of earth pits as per drawings. Where cables are run through pipes, the entry to and exit from pipes shall be smooth and free from burrs. Cables shall be pulled into such pipes in such a way that there is no damage to the cable. Where space is left in pipes for cables to be pulled in at a later date, a galvanized draw wire of adequate size shall be left in the pipes. There shall be no intermediate joints in any cable. Joints shall be made only at terminals in instruments or approved equipment. Temperature compensation cables, alarm and trip system wires shall be run in conduit or on cable tray as specified on drawings. Elevations shown for horizontal conduit /tray runs are the elevations of the platforms, steel or piping from which these are to be supported. Contractor shall provide any additional supports if required. Vertical conduit /tray runs at structures shall be supported from ladders unless otherwise noted. Location and elevation of conduit /cable tray run may be changed when necessary to avoid interference. Cables shall be located at minimum distance of 300 mm from hot piping or equipment. Vents and drains shall be furnished at high and low points in conduit runs. Conduit shall be sloped towards drain fittings. Page 14 of 30 17.2.16 All sealing fittings shall be dammed with fiber and filled with sealing compound after wiring is completed. 17.2.17 The 24V/ 110V alarm, control and instrument power wiring shall be run in conduit/ cable trays from local instruments to centrally located terminal boxes. Wires shall be copper single conductor, PVC insulated rated 600 V. 17.2.18 Conduits/ cable trays in main runs shall be supported on a suitable steel rack. 17.2.19 Minimum size of conduit shall be 20 mm and that of cable tray shall be 50mm. 17.2.20 All the spares wire shall be tagged and placed in convenient place or terminated suitably. 17.2.21 All cables shall be tagged with Aluminium laminating plates at every 30m, at every crossings (Pipe bridges/ walls) etc. 17.3.0 GROUNDING 17.3.1 All exposed metallic parts that could become energized with hazardous potentials shall be reliably connected to the equipment grounding circuits. 17.3.2 On complex inter-connected instrumentation networks caution shall be exercised when grounding the circuit to ensure that multiple grounds are not established. 17.3.3 Cable screen shall be earthed at only one point near the control room. 17.3.4 All instrument grounds shall be checked for same potential if tying between instrument circuit grounds to the same earth electrode beds that are used for power grounding is done. 17.3.5 All the spares conductors in a multicore cable shall be grounded to avoid induction of large voltage surges on signal circuits when near by lightning strikes occur. 17.3.6 Shields or signal wires shall never be left unconnected, grounded indiscriminately, connected to their signal pair at two more points or tied to other signal leads. 17.3.7 Instruments, junction boxes, cable gland plates shall be properly earthed whenever applicable. 18.0.0 GENERAL NOTES ON CABLES ON TRAYS, DUCTS AND CONDUIT INSTALLATION 18.1.0 Changes in direction of cable trays/ cable ducts shall be achieved by use of cable tray bends and tee pieces or by efficient clampings. For cable trays, generally available supports will be used for routing. But whenever it is not available. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 18.2.0 18.3.0 18.4.0 18.5.0 18.6.0 18.7.0 18.8.0 14 ES008 /15 18.9.0 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION Contractor shall make necessary supports for routing the cable trays/ cables ducts Main cables shall be laid through cable ducts. Contractor shall provide proper covers after installation of all the cables inside the duct. In case of new cables are laid in existing ducts, contractor shall uncover and re-fix the covers as necessary. All pneumatic tubing and electrical cables shall be clamped on the cable tray at intervals of not more than 500mm. Grease shall be applied to all machine bolts before tightening. Necessary grease shall be supplied by contractor. Cable tray &cable ducts shall be fixed on structural supports fabricated at site by contractor. Contractor shall fabricate at site, suitable bends, tees, crossings etc and shall supply/ fabricate required clamps from sheets/ strips for the trays and ducts wherever required according to the routing requirement. The cables taken along trays /angles alone will have to be clamped. The cable inside the duct shall be neatly arranged. This shall also include laying under ground cables through the trench wherever required. The quantity given in the bill of materials for cable trays, cable conduits and cable ducts are for straight pieces only. Installation of fittings like bends, tees, reducers etc shall be included in the cost of erection and no separate charges will be applicable for these fittings. Fire resistant materials/ coatings as specified shall be applied on the cable trays/ ducts at locations where fire proofing is required. Trays are not designed as walkways or hoisting beams and persons shall be advised not to use them as such. All runs of ducting and conduits shall be mechanically and electrically continuous. Running threads shall be secured by lock nuts. Underground conduit banks which cross beneath roadways, railways or other areas subject to heavy loading or having poor soil conditions shall be adequately supported or the envelope reinforced using concrete cover slabs to prevent shearing, crushing or damage from uneven settlement. Page 15 of 30 18.10.0 All underground runs in process plants shall be clearly marked for run location and identified using pointer marks and service identification signs as per the installation standards. 18.11.0 Cable conduit shall be supported from at least every 1.5 meters. Supports shall be tack welded to conduits. 18.12.0 Conduits shall not be supported from piping -that may have to be replaced or removed for inspection-, or from high temperature piping. 18.13.0 Conduit runs shall be solidly connected to assure continuity in their entire length. Ground jumbers shall be installed where physical condition cast any doubt as to the required electrical continuity. 18.14.0 All underground conduits shall be arranged in banks and should have protection and identifying concrete envelop. 18.15.0 Conduit banks shall be installed about 2 feet below grade, 12” below drainage ditches in process areas, or below the frost line, whichever is deeper. 18.16.0 The ends of cables shall be properly sealed before pulling, to prevent moisture and damaging substances from entering. 18.17.0 Cables normally shall be pulled directly from a shipping reel placed on a cable puller into position in the tray. Cables shall be taken out from drums using cable puller only, to avoid twisting and subsequent damage of outer sheath of cable. The cable puller shall be either fabricated or supplied by the contractor. Small, cables (2’and smaller in diameter), can be laid with a basket grip. The pulling tension shall not exceed the cable manufacturer’s recommendations. Pulley, rollers, etc shall be used to guide the cables into positions in the tray. 18.18.0 Specific care shall be taken while installing special cables like co-axial cables as electrical characteristics may change due to improper handling. 18.19.0 Care shall be taken to see that there are no kinks or loops that may scrape the edges of conduit fittings, cover plate surfaces and edges etc and result in damaged insulation and even broken wire. 18.20.0 Covers on tray shall be used to prevent accumulation of dirt, debris, snow, ice, etc. 18.21.0 A minimum of 5 feet clearance shall be present between noise generating FACT ENGINEERING AND DESIGN ORGANISATION 14 ES008 /15 ENGINEERING SPECIFICATION 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION equipments and cable tray on which signal cables will be laid. 18.22.0 Cable trays shall be run with the breadth of the tray in a vertical plane. Where FEDO’s site engineer agrees that a vertical run is not possible, a short horizontal section shall be used, but the run shall revert to the vertical plane at the nearest point. 18.23.0 The contractor’s scope shall include cable laying harnessing/ dressings, clamping on trays, making Aluminium tags with cable numbers punched on the cable before entering the instruments, junction boxes or control room. The tags may be tied to the cable using PVC insulated GI/ SS wires. PVC marking ferrules [contractor’s scope of supply], shall be used at the termination end of the cables. All single /multi-core tubing/ cables connecting the field instruments /junction boxes with bulk heads/ junction boxes of control panel are to be laid on cable trays and properly clamped at intervals not exceeding 1000mm on horizontal runs and 300mm on vertical runs. 19.0.0 CIVIL WORKS All civil works such as grouting, chipping of the wall /concrete floor as required for some fixtures of instrument, cable racks, instrument pedestal etc will have to be undertaken by the contractor. All the chipped areas shall be re-plastered to attain the same finish as before. For opening up walls at any place, prior permission shall be obtained & the same shall be closed neatly after completion of said work to the same specification & finish as before such a work was undertaken. 20.0.0 CALIBRATION AND FUNCTIONAL CHECK Instrument contractor shall possess all relevant test instruments and shall test the installation in the following manner in the presence of site engineer. 20.1.0 All pneumatic signal lines shall be disconnected and blown through with instrument air. 20.2.0 The signal lines shall be blanked off and pressurized pneumatically using bubble bottle to 1.5Kg/cm2. The bubble rate after pressurizing shall be less than 1 bubble in ten minutes. 20.3.0 All instrument air mains shall be isolated from the instrument and pressure 20.4.0 20.5.0 20.6.0 20.7.0 20.8.0 20.9.0 20.10.0 20.11.0 20.12.0 20.13.0 20.14.0 20.15.0 Page 16 of 30 pneumatically 1.5 times maximum working pressure and isolated from the source of pressure. The pressure shall not fall by more than 0.1Kg/cm2 in ten minutes. All the impulse lines shall be isolated from the instrument, and hydraulically tested to 1.5 times the working pressure and isolated from the source of pressure. The pressure shall not fall by more than 0.1kg/cm2 in ten minutes. All the installation will have to be checked and tested by the method of simulation for working of entire Instrumentation loop and its circuits to include the relevant, primary, secondary and control elements. All RTD electric and electronic instrument wiring shall be tested for resistance between conductors and earth for 500V DC. These tests shall be carried out with all conductors disconnected except from the test instruments. The insulation resistance shall not be less than 10 mega ohms. Transmitter’s connections to the correct receiver and polarity shall be checked. Controller connections to their correct control devices shall be checked. Correct connection of pneumatic and electric switches shall be checked. Correct operation of alarms and functioning of interlocks shall be checked. This testing shall be in coordinate with site engineer. The written results /certificates of all tests [loop tests and group tests] shall be approved by site engineer in writing. Reasonable evidence of the satisfactory conditions of the test equipment shall be provided, if required. All errors of faulty workmanship regarding the installation discovered during the testing shall be corrected. All pneumatic, electro-pneumatic and electronic transmitters, indicators and recorders shall be calibrated, taking eight check points throughout the instrument range. Four each shall be taken on the upscale run and downscale run. Contractor shall have signal sources and other precision calibration equipments for all pneumatic and electronic instruments as per the instrument list given. The ranges of the instrument shall be set as per the specifications. The instrument shall have required characteristics throughout their range as per FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 20.16.0 20.17.0 a. b. c. 20.18.0 20.19.0 a. b. c. d. e. 20.20.0 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION specifications within the tolerance. Any deviations shall be brought to the notice of engineer in-charge. Contractor shall undertake any minor repairs of instruments found necessary, as part of calibration work. However such work may be under taken only with consent of the engineer in –charge. Precaution shall be taken to see that no instrument is subjected to overloading or unwanted signal is supplied to the instrument. Calibration work shall be undertaken only after studying the instruction manuals and other special instructions from manufacturer’s regarding each instrument. NOTE: All hydraulic test fluid shall be drained off from the impulse line when hydraulic test is over. All impulse line shall be blown off using instrument air before testing. For float type level instrument the test pressure shall be the rated pressure. Procedure for testing and checking of instruments is provided in Annexure-B. To identify the stage of inspection done, small label with different colour shall be attached on the field instrument as follows:Bench calibration Pressure test flushing of impulse line Electrical test (megger continuity etc.) Blowing in air supply. Loop checking. SMART transmitters shall be configured using HART calibrator. All functionality to be simulated and verified, prior to taking up installation/ put up with plant. 21.1.5. Wire to wire and wire to ground resistance shall normally not exceed 10Mohms in most applications. 21.1.6. The shield drain shall also be tested for accidental shorts or grounds as just another conductor requiring high resistance to ground. 21.1.7. Grounding circuits shall be tested for resistance low enough to operate overcurrent devices incase a ground fault occur within the instrument. 21.1.8. Instrument erection shall be considered 100% complete only after all the checks as indicated below are complete. 21.1.9. All instrument loops are to be checked for compliance of the installation drawings. Wherever possible signals are to be simulated at the transmitter end and shall be followed at the indicator / controller/ alarm/ interlock components up to the final control element. Loop check shall be carried out by simulation of signals from transmitter end at minimum four points, 25%, 50%, 75% and 100%, all defects such as leaks at the instrument process piping / tubing, instrument air lines/ fittings etc insulation/ connection faults at electrical wirings shall be rectified to the satisfaction of the owner. All the calibration variations, misalignment of linkages of final control element are to be rectified. 21.1.10. All the joints in the air lines and pneumatic signal lines are to be tested for leaks using soap solution. All checking shall be done as per the general notes on wiring & tubing. 22.0.0. 21.0.0. 21.1.0. 21.1.1. 21.1.2. 14 ES008 /15 21.1.3. 21.1.4. TESTING AND LOOP CHECKING TESTING For analog instruments testing of wires shall be done after installation to verify freedom from grounds. After all connections are given the complete loop shall be checked for satisfactory performance. Where meggers are used, care shall be taken not to use a voltage in excess of the insulations rated voltage. While testing the wires, all the instruments shall be disconnected to avoid damage to the instruments. Page 17 of 30 a. b. c. PART C- JOB COMPLETION REQUIREMENTS COMPLETION OF ERECTION JOB The completion of the entire job on instrumentation will be considered in following three major stages and the payment will be accordingly made subject to the other commercial terms. 60% of the job will be considered completed when erection of the instrument material is mechanically completed. 20% of the job will be considered completed on completion of checking and calibration of individual instruments. 20% of the job will be considered completed after loop checking of instruments. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 14 ES008 /15 22.1.0. 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION MATERIAL RECONCILATION/ WASTE ALLOWANCE The contractor shall plan and execute the work in such a manner that wastage of materials shall be limited to minimum. The contractor should take precaution to ascertain the actual route and lengths required before laying of cables and tubes so that the lengths of cut pieces are kept to the minimum possible and not exceed 0.5% of total Qty, for cables and SS tubes. As far as possible, total wastage /scrap which cannot be accounted for in receipt, consumption return statement should not exceed following % allowances item wise. Items supplied by the owner as free issue shall be returned to store with proper return notes. He shall also furnish reconciliation statement for their material supplied to him. The Work will be deemed incomplete without submission of proper material reconciliation report. The responsibility of submitting ‘material reconciliation report’ without any delay towards the end of the job lies solely with the contractor. The statement prepared by the contractor with proper references of receipts, dates etc should be submitted which will be verified for the total quantum of job carried out and materials / items installed. After checking the three statements with due allowances for wastage /scrap, material statements can be accepted by FEDO/ OWNER/ CLIENT. This marks the completion of the job and final payment will be made only after this activity is completed. Allowances for unaccountable wastage for various categories of material will be as given below Item N oLength of S.S. pipes, t tubes alloy steel pipes. e Electrical cables (3 meter : per length of cables or which ever is less) f C.S pipes, Aluminium o trays r Structural material wValves, pipe fittings acompression fittings sglands etc. t Nut, bolt, gasket material a 22.2.0. 23.0.0. 24.0.0. 24.1.0. 24.1.1. 24.1.2. 24.1.3. % allowances 0.5% 2% 24.1.4. 24.1.5. 1% 2% nil 24.1.6. Page 18 of 30 Note: for wastage over and above the figures indicated, contractor will be charged at the cost of price +overheads + taxes. QUANTITY VARIATION Quantities indicated in the bill of quantities are tentative and are likely to vary subsequently. The unit rates shall remain firm for any variations in the scope of work to an extent of +/–25% of total contract value. COMMISSIONING AND START UP For commissioning and start up contractor shall deploy qualified skilled, semi skilled and unskilled personal at the rates quoted under schedule of labour rates. The approximate number of personal that would be required is also indicated in the schedule of labour rates. The owner will have option to engage partially, fully or additional personals as required by him and the contractor shall provide the personal at the rate indicated. Actual requirement will be intimated to the contractor at least 15 days in advance. These rates shall be applicable for any additional work done on ”labour supply basis” for the entire period of erection. BILL OF QUANTITIES AND MATERIALS RATES The rates for installation of instrumentation shall be included for: Handling, Transportation, care and protection of owner issued equipment and materials from owner’s stores to contractor’s stores or point of installation. All installation works, fixing and testing. Maintaining proper inventory of owner supplied equipments and materials and returning all surplus equipment and materials to stores of owner, after completion of work. Provision of adequate and proper storage for owner’s equipment and materials. Provision of complete instrument workshop with testing and calibration equipments. Provision of all installation equipments, tools, scaffolding, workshop, offices and any other equipments and /or appliances necessary to complete the installation, in accordance with the specifications. 2% FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 24.1.7. 24.1.8. 24.2.0. 24.2.1. 24.2.2. 25.0.0. 25.1.0. 25.1.1. 25.2.0. 25.2.1. a) b) c) 14 ES008 /15 d) 25.3.0 25.3.1 a) 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION All consumable materials other than those separately enumerated in the bid items. Removal, re-calibration and reinstallation of instrument as required during pre commissioning. MEASUREMENT As far as possible, all measurement for payment shall be taken from” good for construction drawings ‘released for construction and schedules provided by owner. Only the items listed in the schedule shall be measured for payment. All other labors and activities necessary to complete the installation shall be deemed included in the items in the schedule. Note. For measurement & billing refer formats 25FT407& 25FT408. PART D-PROCEDURES AND STANDARDS GENERAL REQUIREMENTS AND RECOMMENDATIONS FOR PIPE WELDING SCOPE This specification covers the requirements and recommendations for welding procedure qualification test and welder’s performance qualification test of piping/ instrumentation structural work. REFERENCES The following codes, standards and specification in the latest editions as of now shall form a part of this specification unless otherwise mentioned. ANSI/ASME B31.3 ASME CODE SECTION IX “SPECIFICATION FOR FABRICATION AND INSTALLATION OF STEEL PIPING”. “PIPING MATERIAL CLASSIFICATION” WELDING PROCEDURE GENERAL TABLE-1 includes the several kinds of welding procedure. The contractor or sub contractor who will do the actual welding work for piping shall select the applicable welding procedure for each kind of pipe welding from table-1. After that the contractor or sub contractor shall prepare the detailed WPS and procedure Qualification record (PQR) in accordance with ASME CODE SECTION IX and obtain the written approval from b) 25.3.2 a) b) c) d) e) f) g) 25.3.3 a) b) c) Page 19 of 30 Owner prior to the commencement of any welding work. If the contractor or sub contractor wants to use other welding procedures not listed in the table-1 the contractor or sub contractor shall submit the detailed WPS and PQR to owner and get the approval before use. WELDING PROCEDURE FOR CARBON STEEL All pressure retaining welds and attachment welds to the pressure retaining part shall be made by SHIELDED METAL ARC WELDING (SMAW) using low hydrogen type electrode AWSE 7018 except root pass. Root pass of girth butt weld and branch connection weld, where the complete penetration is required shall be made by GAS TUNGESTON ARC WELDING (GTAW) process or SMAW process. For GTAW, filler metal shall comply with AWS ER70S-2, 3, 6 or ER70S-G (TGS50, KOBE STEEL LTD.). For SMAW, electrodes shall comply with ASW E6010. For small diameter piping (2” & smaller), all GTAW process may be used for all passes. End preparation and root gap shall be in accordance with Fig.327.3.1 of ANSI/ASME B31.3. In case of ASW E 6010 for root pass, minimum 80 degC pre-heating is required for the thickness 1/2” and over. Weld progression for vertical position shall be uphill. When post weld treatment (PWHT) is necessary from the fluid service requirement PWHT conditions shall be as follows. MATERIAL : Carbon steel. HOLDING TEMPRATURE : 625+/25 degC HOLDING TIME : Min 1 Hr. Welding procedure for C-1/2Mo Steel (piping material service class). Root pass of girth butt weld and branch connection weld where the complete penetration is required shall be, made by GTAW process. Filter pass and cover pass shall be made by GTAW or SMAW. GTAW filler metal shall comply with ASW ER80S-D2 or ER80S-G (TGS-M, KOBE STEEL LTD.). For SMAW, electrode shall comply with AWS E7016-AI, low FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION d) e) f) 25.3.4 a) b) c) hydrogen type electrode. E7010-AI type (high cellulose type)) shall not be used. For small diameter piping (2”&under), all GTAW process is preferable. End preparation and root gap shall be in accordance with FIG 327.3.1 of ANSI/ ASME B31.3. Weld progression for vertical position shall be uphill. Welding procedure for austenitic stainless steel, SS TP–304, 304L, 316L, 316SS. Root pass of girth butt weld and branch connection weld where the complete penetration is required shall be made by GTAW process. Root pass by SMAW process shall be prohibited. Filler pass and cover pass shall be made by GTAW or SMAW. For small diameter piping (2” &under), all GTAW process is preferable. Accepted filler metal and electrode shall be as follows: Piping material TP304 Filler metal (GTAW) AWSER 308 TP304L AWSER 308L AWSER 316L AWS ER 316 TP316L 316SS 14 ES008 /15 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION Electrode (SMAW) AWSE 30816 AWSE 308L16 AWSE 316L16 AWSE 316L10 Notes: 1. For welding electrodes AWSE 308L16, the maximum carbon content shall be 0.03% (extra low carbon type). At the time of purchasing these welding materials, maximum carbon content shall be specified, because maximum carbon content of normal AWS E308L-16 and AWS E316L-16 is 0.04%. 2. The following are the acceptable materials which comply with the above requirement. AWS Trade name & class Manufacturer E308L-16 NC38EL(K.S.L),WEL 308 ELC(N.W.R)(K.S.L— KOBE STEEL LTD) E316L-16 d) e) f) g) 25.3.5 a) b) c) d) e) f) g) Page 20 of 30 NC36EL (K.S.L), WEL 316 ELC (NWR) (NWR— NIPPON WELDING ROD CO., LTD.). End preparation and root gap shall be in accordance with FIG.327.3.1 of ANSI/ ASME B31.3. Weld progression for vertical position shall be uphill. Internal back shielding with pure argon gas (min 99.9%) shall be required during the welding. Back shielding with nitrogen gas shall not be permitted. Maximum inter-pass temperature during welding shall be 150 degC. Welding procedure for dissimilar metals. Root pass of girth butt weld and branch connections weld where the complete penetration is required shall be made by GTAW process. Root pass by SMAW process shall be prohibited. Filler pass and cover pass shall be made by GTAW or SMAW. For small diameter piping (2” & under), all GTAW process is preferable. Acceptable filler metals and electrodes for various combinations of base metals shall be as follows. Piping C/S S.S S.S SS material 304 304L 316L ER 309 C/S ----- E309-16 S.S 304 ---------ER308 E308-16 SS.304L ----------------------ER308 L E308L -16 S.S --------------316L NOTE: for E308L-16 max. Carbon Content shall be 0.03 % (extra low carbon). See note 1 of 25.3.4. End preparation and root gap shall be in accordance FIG 327.3.1 of ANSI/ ASME B31.3. Weld progression for vertical position shall uphill. Internal back shielding with pure argon gas (min.99.9%) shall be required during the welding. Back shielding with nitrogen gas shall not be permitted. Maximum interpass temperature during welding shall be 150 degC. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION h) 25.4.0 25.4.1. 25.4.2. 25.5.0 25.5.1 14 ES008 /15 25.5.2 25.5.3 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION Welding between galvanized carbon steel or zinc rich primer coated carbon steel and stainless steel shall be prohibited to avoid the zinc embitterment crack on the weld and heat affected zone (HAZ). WELDING PROCEDURE QUALIFICATION TEST All welding procedure used for the instrument piping construction works shall be qualified or shall have been qualified by the contractor or subcontractor as his responsibility in accordance with ASME CODE SECTION IX and the requirements herein before the commencement of any welding work. If the contractor or sub contractor does not have the procedure qualification records (PQRs) for the applicable welding procedure specifications (WPSs) according to these specification requirements, he shall carry out the welding procedure qualifications tests and shall submit the complete documents as “WPSs & PQRs to owner for approval. TABLE –2 “ STANDARD PROCEDURE FOR WELDING PROCEDURE QUALIFICATION TEST” are the sample of procedure qualification test for each welding procedure listed in TABLE -1 The contractor or sub contractor may modify the test procedure as far as the requirements of ASME CODE SECTION IX and this specification are kept. WELDER PERFORMANCE QUALIFICATION TESTS All welders and welding operators engaged in this job are required to pass the performance qualification test in accordance with ASME CODE SECTION IX. The contractor or sub contractor shall be wholly responsible for qualifying each welder and welding operator has enough skill to make the sound welds by using the welding procedure to be used for this job. TABLE-3: STANDARD PROCEDURE FOR WELDER PERFORMANCE QUALIFICATION TEST” are the sample of performance qualification test for each welding procedure listed in TABLE –1. The contractor or subcontractor may modify the test procedure as far as the requirements of ASME CODE SETCTION IX and the specification are kept. 25.5.4 25.5.5 26.0.0 26.1.0 26.2.0 26.2.1. 26.2.2. 26.3.0 26.3.1 26.3.2 26.3.3 26.3.4 26.3.5 a. b. c. d. e. f. 26.4.0 26.5.0 26.5.1 a) Page 21 of 30 Visual inspection during welding and after welding is very important. Therefore the competent welding inspector or welding supervisor who has enough experience for visual inspection of weld shall witness the weld test and judge his capability before guided bend test or radiographic examination. GTAW welder who passed the carbon steel weld shall not be qualified for stainless TIG welding, even if the No. of ASME CODE SECTION IX is same, but not vise versa. SPECIFICATION FOR PAINTING WORK SCOPE This specification covers the general requirements for painting of instruments /accessories; steel structure’s and instrument piping. REFERENCE The requirement given in the following specification in the manner and to thee extend indicated therein. I.S for surface preparation. SURFACES TO BE PAINTED AND SURFACES NOT TO BE PAINTED The following surfaces shall be painted in accordance with the painting classes of this specification; carbon steel instrument accessories. Steel supporting structures. Carbon steel instrument impulse piping. Other surfaces which are required to be painted for any specified reason. However the following shall not be painted:Nonferrous metal, stainless steel or other high alloy steel. Name plates or identification tags. Valve stems or other machined contact surfaces. Galvanized surfaces. Insulation covers. Plastic. PAINTING CLASSES The materials or paints specified in the CLASSES A to E are selected on the basis of service conditions. Refer to Annexure-1 for details. PREPRATION OF SURFACES General requirements. The surface shall be prepared to dry metal after removing rust ,oil, grease, dust , stain, or other extraneous matter by manual or mechanical cleaning such FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION b) c) d) e) f) 26.5.2 a) b) c) 26.6.0 26.6.1 26.6.2 14 ES008 /15 26.6.3 26.7.0 26.7.1. 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION as wire brushing grinding ,power brushing ,etc. Wet surfaces due to rain fall, dew-drop and frost etc shall be thoroughly wiped with rags and dried before each painting. Cleaning of wet or soiled surfaces shall be done immediately before application of paint in such a manner that adjacent wet paint surfaces are not damaged by the cleaning operation. Drying of wet surfaces may be expedited by blowing warm air. The painted /primed surfaces shall be dry and clean before application of subsequent coats. Deposits on the primed /painted surface must be cleaned before the application of the next coat. If the painted surfaces are exposed to rain while painting is in progress, the effected paint shall be entirely removed and be repainted after making the surface clean. Cleaning of surfaces. Cleaning of rolled steel surfaces shall be carried out in the manner that all crevices, corners and edges of sharp steel, joints of steel plates ,especially around bolt heads ,welds beads etc. may be cleaned. Cleaned surfaces shall not be damaged by unnecessary tapings, etc. Where sand blasting is required, the same shall be carried out to SA21/2 grade the sand blasted surfaces shall be painted with in 6 hours after sand blasting. STORAGE OF PAINTING MATERIALS Paints, varnishes, thinners or other volatile and inflammable painting materials shall be stored on a 150mm thick layer of sand in well ventilated and detached storage sheds. Fire extinguishers or sufficient amount of sand shall be placed where readily accessible in case of fire. ‘No Smoking “ And Other Suitable Warnings Signs , Such as “No Open Flames”,” Danger”, “Storage Of Inflammable Materials “ etc shall be posted , around storage sheds. MIXING AND THINNING Mixing and thinning shall be done only at well ventilated places where there are no open flames. MIXING Whenever mixing of base paint and additives are involved, such mixing shall 26.7.2. 26.8.0 26.8.1 a) b) c) d) e) 26.8.2 a) b) c) d) 26.9.0 26.9.1 Page 22 of 30 be done strictly as per manufacturer’s specification/ recommendations. As far as practical, quantity of mixing shall be sufficient to cover the given section or entire surface of the specific colour. Thinning whenever required shall be strictly as per recommended ratio. PAINTING General requirements. Painting on instrument equipment /accessories and piping shall be done at plant site or at shop as required. Painting shall be performed only in favorable weather conditions. Paintings shall not be performed in rainy, damp, windy, dusty, weather or on the day of such unfavorable weather is predicted. During painting, adjacent surface shall be properly protected from paint splashes. If blemishes or damages occur by accident, they shall be thoroughly cleaned, repaired or replaced. Upon completions of paintings work, all staging, scaffolding, paint containers, etc, shall be removed from the job site and the, premise shall be left clean. Caution signs of “wet paint” shall be posted around the areas where readily visible, until the paint has completely dried. Methods of application. Painting shall be generally performed by hand brush method. Spray method may be adopted for surfaces likes that of control panels for specified reasons. Whenever hand brush method is employed for painting, painting shall be done in alternate directions from vertical to horizontal or from horizontal to vertical and shall be applied to all edges, corners, crevices, joints, intersections etc. If brush marks, drags, adhesions of brushes bristles, dust or blemishes occur, the surfaces shall be lightly sand papered before further coats are applied. All surfaces that are inaccessible after installation and assembly except for contact surfaces, shall be painted twice that is after first coat, the same is repeated again. The second and final coats are also repeated in same manner. PRECAUTIONS Open flames, smoking exposed elements or sources of ignition of any and shall be FACT ENGINEERING AND DESIGN ORGANISATION 14 ES008 /15 ENGINEERING SPECIFICATION 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION strictly prohibited in area where painting is being performed 26.9.2 During painting operation and for a sufficient time thereafter, welding or open flame work shall be prohibited in the adjacent area. 26.9.3 “No Smoking” and other warning panels to read “Caution” “No open flames” etc shall be posted in all areas where and while painting is performed. The sign shall remain posted for a sufficient time after painting has been completed. 26.9.4 Hand lamps, flash lights etc which will cause a fire shall be handled carefully. 26.9.5 Inflammable liquids with a flash point below 40 deg C shall not be used for cleaning purpose. 26.9.6 Where it is practicable, adequate ventilation shall be provided to reduce the concentration of harmful vapours in the atmosphere. Otherwise workmen shall wear vapor-proof mass, rubber gloves etc for protection when he has to work in a badly ventilated place. 26.10.0 INSPECTION 26.10.1. Finished surfaces shall be uniform and smooth, free from mass of drops, ridges, waves, laps, wrinkles, brush marks, and other defects. 26.10.2. Finished surfaces shall be of uniform colour that presents good appearance, without spots, stains, and discolorations. 26.10.3. Inconspicuous parts, such as the corner of build up members, around bolts, undersides and backsides of pipelines, pipe bends and valves etc shall be closely checked so that they may not be left unpainted. 26.10.4. Paint colours for identification purposes of piping shall be checked for correct colour application, if required. 26.10.5. Defective surfaces, if any, shall be cleaned and repainted. 26.10.6. Additional requirements. a) Any imperfect or damaged layer shall be repainted before the next layer is applied. b) The field welding for damaged layer shall be repaired before the next layer is applied. c) Bolts and nuts shall be provided with the relevant priming coat immediately after mounting. d) Places where field welds are to be provided a section of 50 to 500 mm shall remain unpainted on both sides 26.11.0 TABLES Page 23 of 30 The tables for class-A to E are given in annexure-A. 27.0.0 27.1.0 27.1.1. 27.2.0 27.3.0 27.3.1. a) b) c) d) 27.3.2. 27.4.0 27.4.1 a) b) c) d) e) 27.4.2 INSPECTION AND TEST PROCEDURE FOR INSTRUMENT INSTALLATION WORK SCOPE This specification covers the procedure for inspection and test of instruments installation work. REFERENCE GENERAL Inspection and tests shall be performed for the following work items: Instrument pressure piping Instrument electrical wiring and temperature wiring. Instrument signal air tubing. Instrument supply air piping Test reports shall be prepared for all tests and be submitted to CONSULTANT/ OWNER immediately after tests are completed Typical report forms will be furnished along with the erection tender or the same may be requested by the contractor to FEDO site in-charge. INSPECTION AND TEST – INSTRUMENT PRESSURE PIPING Instrument pressure lead lines between the process isolating valves and the instruments to which they are connected shall be tested. Prior to the test, the following items shall be inspected visually: Whether instruments are correctly installed according to the P&ID. Whether the upstream and downstream connections of the instruments pressure leads line for differential pressure type instrument is correct. Whether adequate slope is provided to instrument pressure lead line. Whether sufficient supports are provided to instrument pressure lead line. Whether correct materials of the correct rating are used for instrument pressure lead lines. TESTING DESCRIPTION Instruments with an operating pressure less than 40kgf/cm2g shall be pneumatically tested. Instruments with an operating pressure equal to or more than 40kgf/cm2g shall be hydrostatically and pneumatically tested. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 1. a. b. c. 14 ES008 /15 2. a.) b.) c.) 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION Unless otherwise specified, test shall be performed with instrument connected to the line. Hydrostatic test Test fluid: water. Test pressure. Normally operating pressure x1.5 or 90% of the maximum allowable pressure of instrument (in the case of pressure instrument, its measuring range), which ever lower. Test procedure (see Annexure C) After closing the process isolation valves and opening the equalizing valve, if installed, fresh water shall be fed into the pressure lead line. Details are as follows: Step 1Close valves 1, 2, and 8 Open valves 3, 4, 5, 6, and 7 Pump enough water and pressurize system up to test pressure. Step 2Close valves 6, 7 Open valve 8 Confirm that pressure gauge indication does not decrease during 3 minutes. Step 3Close valves 8 Open valves 1, 6 and 7 Then pump enough water to confirm that valve 1 is not blocked. Step 4Close valve 1 &Open valve 2. Then pump enough water to confirm that valve 2 is not blocked Step 5 Close valves 1, 2, 3, and 5 Open valves 4 Pneumatic test Test fluid: Air, N2 gas or inert gas. Test pressure 7 kgf/cm2g or 90% of the maximum allowable pressure of the instrument (in the case of pressure instruments its measuring range), which ever lower, with a minimum test pressure of 1kgf/cm2g. If instrument is not durable to1 kgf/cm2g, test shall be performed with instrument disconnected from the line. Test procedure (see Annexure D) After closing the process isolating valves and opening the equalizing valve, if installed, test fluid shall be fed into the a) b) c) 27.5.0 27.5.1. a) b) c) 27.5.2. Page 24 of 30 pressure lead line. Details are as follows: Step 1Close valves 1 .2 Open valves 3, 4, 5, and 6 Pressurize system up to the test pressure. Step 2 Close valve 6 Confirm that there is no leak by pouring soap water on each connection. Step 3 Open valves 1 Confirm that valve 1 is not blocked Step 4 Close valve 1 Pressurize system again and open valve 2 to confirm that valve 2 is not blocked Step 5 Close valves 1, 2, 3, and 5 Open valve 4 Notes:The analyser pipeline shall be tested by disconnecting the lead line from instrument. The test procedure shall be the same as that with process pipeline. Test may be performed separately or together with the test for process piping or equipment. All instrument piping systems shall be cleaned by blowing air or flushing water before and or after the test, all joints which are defective shall be repaired immediately and shall be re-tested by the original test method. INSTRUMENT ELECTRICAL WIRING AND PENETRATING WIRING GENERAL Continuity, identification and cable insulation resistance test shall be performed. Prior to the test, the following shall be inspected visually: Whether instruments are correctly installed according to the P&ID. Whether wire marking and/ or colour coding at terminals are correct. Whether sealing compound or packing is provided as specified at entry of each instrument. TEST PROCEDURE STEP.1. Continuity and identification of each wire and continuity of shield wire shall be inspected between the field instrument terminals and the control FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION a) b) c) 27.6.0 27.7.0 27.7.1. 27.7.2. 14 ES008 /15 27.7.3 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION panel board terminals by using a telephone, a buzzer, or other suitable means. STEP.2. Insulation resistance test shall be performed by using a 500 V or 1000V Megger. In this case, the wire shall be disconnected from the terminal both at the field and the control panel. The minimum resistance value shall be as follows Line to line Line to ground All min 10Mohm Line to shield. STEP.3. the electricity charged in the wire by the insulation resistance shall be discharged by grounding the wire and then the wire shall be connected firmly to its terminal. INSTRUMENT SIGNAL TUBING Continuity, identification and leak test shall be performed as per the instruction of FDEO site-in-charge. Prior to test, a visual inspection shall be made as to whether instruments are correctly installed according to the P&ID. INSTRUMENT SUPPLY AIR PIPING GENERAL Pneumatic test and air blowing of the supply air piping system shall be performed between the first take off valve on the main air header and instruments. Prior to the test, visual inspection shall be made as to whether instruments are correctly installed according to the P&ID. TEST FLUID AND PRESSURE Test fluid shall be free of oil, dry air or N2 gas. Test pressure for air supply pipe from main header first take–off valve to individual instrument air regulators shall be equal to main air header operating pressure. Short length of air tubes between instrument and its air regulator shall be tested by the set pressure of the air regulator. TEST PROCEDURE STEP 1. Air blowing of the system shall be performed by disconnecting air tube at the inlet of the air regulator and opening the shutoff valve. Air blowing shall be done by opening and closing the shut off valve for a minimum of five times until the air system is confirmed to be clean. STEP 2 the air tube shall be connected again and the shutoff valve shall be opened to pressurize the system. All a) b) 27.8.0 28.0.0 28.1.0 29.0.0 30.0.0 Page 25 of 30 joints and connections shall be tested with soap solution to facilitate the detection of leaks. Note: Test may be performed separately or together with the test main air header. All joints & connections found to be defective shall be repaired immediately and shall be re-tested by the original test method. CONFIGURATION OF SMART FIELD INSTRUMENTS Normally HART/ FOUNDATION FIELD BUS/ PROFIBUS –DP based SMART field instruments are used. The HART configuration shall be used for verifying / configuration/ calibration checks for tag no, range, engineering units, LRV, URV, alarm settings ,functional blocks, configuration output function, trouble shooting etc. This is applicable with respect to all SMART field instruments, communicating with DCS/ PLC/ SCADA system. Re-ranging, download/ upload from DCS/ SCADA, point data base verification etc shall be carried out for each tag/ transmitter. Cold loop check and hot loop check shall be carried out. Diagnostic functions and communication shall be verified. Also any other functionality required /specified shall be configured. APPLICABLE STANDARDS API-RP-550- Installation of refinery instruments & control system ISA Standard- Standard & practices for installation OTHER STANDARDS Inspection & test procedure for instrument installation work General requirement and recommendation for pipe welding Installation standards for instrumentation PART E - ATTACHMENTS DRAWINGS - ANNEXURE I The drawings issued for Instrument erection are attached in Annexure I. The drawings provided are only typical and covers almost all type of instruments. All the required drawing will be issued before start of work or progressively during erection. Modification/ deviation (If any) in the drawings shall be informed to engineering department for approval. SCHEDULE OF WORK - ANNEXURE II FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION The schedule of work is attached in Annexure - II. The instrument contractor shall follow standard erection procedure and maintain good quality of work. The wastage of material shall be limited to minimum as possible. ITEMS TO BE SUPPLIED BY CONTRACTOR - ANNEXURE III The list of items to be supplied by the contractor is attached in Annexure-III. The instrument contractor shall supply Page 26 of 30 the specified items purchased from standard suppliers/ sub-vendors approved by FEDO / OWNER. The items supplied shall be inspected for damages and compliance with specifications given by the engineering department. Any damage and unacceptable variation shall be recorded (Refer 25 FT 403) and brought to the notice of concerned Engineer- in- charge. 14 ES008 /15 31.0.0 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION Page 27 of 30 ANNEXURE-A PAINTING SPECIFICATION-SELECTION OF CLASS Table 1-Painting classes SERVICE CONDITION SCOPE OF APPLICATION Ambient. Temp up to 65 deg C. Chemical splashing area, mild acid/ alkaline atmosphere. Saline atmosphere General use for surfaces 65 deg C to 120 deg C Chemical splashing area particularly Urea, acid/ alkaline atmosphere. Highly corrosive area particularly urea and abrasive environment subject to wind /dripping etc General use for epoxy coatings Highly corrosive and abrasive areas Chemical splashing areas including fluorine Surface at sub zero temperatures 120 to 400 deg C A At field Before shipment at shop B At field Before shipment at shop C At field D Before shipment at shop 14 ES008 /15 At field Before shipment at shop E At field Primer Primer First finish coat Second finish coat Primer Primer First finish coat Second finish coat Primer Primer First finish coat Second finish coat Primer Primer First finish coat Primer Primer First finish coat Second finish coat CLASS A B Instrument accessories such as condensate pots, air headers, instrument pedestals, impulse piping, steel structures etc. Mechanical power tool cleaning /wire brushing C D E 1. DETAILED SPECIFICATION OF PAINTING CLASSES CLA Painting Process SS Before shipment at shop SURFACE PREPARATION Paint No. of Coats Red oxide zinc chromate primer to IS -2074 -DoSynthetic enamel to IS-2932 or Aluminium paint to IS-2339 1 Film thick/co at 20 1*/2 1 20 15 1 1 15 25 1*/2 1 25 25 1 1 25 25 1*/2 1 1 1 25 40 40 25 1*/2 1 1 25 40 25 1*/2 1 1 25 20 20 -DoRed oxide zinc chromate primer chlorinated rubber based -DoChlorinated rubber finished-un modified -DoEpoxy red oxide zinc phosphate primer -DoEpoxy finish paint -Do2 pack polyurethane primer -Do2 pack polyurethane finish Heat resistant silicone / aluminium paint -Do-Do-Do- (*) Where primer is applied before shipment, one coat instead of two coats shall be applied. FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION Page 28 of 30 ANNEXURE-B CALIBRATION METHODS Pressure vacuum gauge Pressure gauge Receiving instrument (pneumatic) Receiving instrument (electronic.) Receiving pressure switch Receiver switches Electronic switch. Dial thermometer & temperature transmitter Temperature switches Vibration /axial displacement system Dead weigh tester and vacuum gauge test Pneumatic rig Using test rigs with accurate gauge Using electronic calibrator &test rig Hydraulic/ pneumatic tester Pneumatic test rig Signal generator Temperature bath with standard thermometer Multivolt source or resistance source Bently Nevada testing equipment Control valve Pneumatic /electric test rig Controller Electronic& pneumatic rigs Potentiometer/ decade resistance box Temperature indicator Differential pressure transmitters Hg manometer E/P transducer ANALYSERs O2, H2, CO2 etc. Zero /span gas &output meter Solution & output meter By comparing with Hg manometer -Do-DoCheck the operation using Multi-meter -Do-DoChecked at various temperature Checked increasing and decreasing the value This to be calibrated as per manufacturer’s instruction. If contractor does not have the instrument, he shall do this on sub contractor under his responsibility by BN Indian agent. Lubricated stored &checked for smooth operation & hysteresis I/P SOV, limit switch, valve opening &closing time etc to be checked. Manufacturer’s instruction manuals Calibration to be checked giving known input of T/C or resistance and comparing output standard curves. Output shall be measured using master output gauge. Checking shall be done by feeding input from field calibrator & noting the output reading. Calibration shall be checked using zero &span gases &noting the output meter. Using these std. solution & output meter, calibration to be checked. 14 ES008 /15 PH, conductivity dissolved O2 Hydraulic or pneumatic rig output meter (elect or pneumatic) Field calibrator standard gauge for Hg manometer. By comparing with master gauge FACT ENGINEERING AND DESIGN ORGANISATION ENGINEERING SPECIFICATION 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION 14 ES008 /15 ANNEXURE-C HYDROSTATIC TEST ARRANGEMENT FACT ENGINEERING AND DESIGN ORGANISATION Page 29 of 30 ENGINEERING SPECIFICATION 14ES008/15 FIELD INSTRUMENT ERECTION SPECIFICATION 14 ES008 /15 ANNEXURE-D PNEUMATIC TEST ARRANGEMENT FACT ENGINEERING AND DESIGN ORGANISATION Page 30 of 30