TEST 1 1. A long-term agile project has just reached its midway mark and a new project manager is appointed to take over. Additional to the project manager, a current stakeholder was interchanged with another who has more experience regarding the projects’ technology. What next step should the project manager take? A. Discuss expectations from the stakeholder and revise the engagement plan accordingly. B. Encourage the new stakeholder to convene with the product owner to review pertinent information. C. Notify all stakeholders after revising the project plan with new contents added. D. Hold all upcoming sprint review meetings with the new stakeholder in attendance and revise the project plan. 2. An application developer took a story card to work that read "Customer can pay using credit card". After the implementation, the functionality was rejected because the application could not accept foreign credit cards. What should the project manager have done to avoid this issue? A. Described the user story in more detail. B. Scheduled the user story for the next iteration. C. Performed iterative backlog grooming with the team. D. Gathered more detailed requirement specifications from end users. 3. During release planning, a conflict has been raised about needs that must be prioritized, but the development team is losing focus. In order to get all the stakeholders in the right direction, what conflict resolution technique should the project manager use in this situation? A. Reconcile B. Force C. Collaborate D. Compromise 4. A system integrator is working on multiple projects. The functional manager required the integrator to provide onsite support for another project without consulting other parties impacted by this decision. The impact caused a delay in the scheduled deliveries of project A. What should the project manager of project A do first? A. Check the impact of the delay on schedule and cost B. Make sure that the integrator shares the work schedule with the team C. Meet with stakeholders to agree on a communications management plan D. Inform the customer about the delay and set a new delivery date 5. A project manager is struggling to figure out the performance of the project teams in an agile environment. For the same scope of work, team A has calculated and delivered 100 story points and team B has calculated and delivered 125 story points. Which team is performing better? A. Team A as they have calculated fewer story points than team B. B. Team B as they have calculated more story points than team A. C. The team that completes the most stories selected from the sprint backlog. D. The team with the least amount of defects in their deliverables. 6. A newly formed team has become accustomed to agile practices. The project lead has noticed that while they are performing according to expectations, there is boredom with daily team practices among many of the team members. What should the project lead do in this situation? A. Allow the team to self-organize and have them analyze the situation in their retrospective session and self-correct. B. Challenge the team to find new ways to achieve higher levels of performance to improve the situation. C. Speak with individual team members to determine what they would like to do to improve the situation in the team. D. Have the team inform senior management of the situation and ask for recommendations. 7. A project manager is managing a hybrid project. A stakeholder has directly contacted a team member and has requested a change. Due to the request, the team member was distracted from their work, which caused a loss in productivity. What should the team member do? A. Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the project manager. B. Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the change control board (CCB). C. Inform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity. D. Inform the scrum master so that the change can be discussed directly with the stakeholder 8. The product team is progressing with a prototyping approach to deliver a multiyear business initiative. A few user stories are taking longer to be delivered. What should the project manager do? A. Determine the risks and identify a resolution during the retrospective meeting. B. Determine cross-dependencies and plan a spike in the next sprint. C. Inform stakeholders about the delay during project updates. D. Discover the gaps in the communications management plan and address them accordingly. 9. A project manager in a cross-functional organization needs to inform the department manager of the number and type of resources required, and the length of time they will be needed. What should the project manager use to present this resource information? A. Resource assignments B. Resource histogram C. Responsibility assignment matrix (RAM) D. Project organization chart 10.A project is being audited to ensure compliance with organizational policies. What process is being conducted? A. Audit Schedule B. Plan Quality Management C. Control Quality D. Manage Quality 11.All quality controls have passed, and a project deliverable is ready to be released to the customer. However, a change request to add new quality criteria has been approved. What should the project manager do first? A. Update the project management plan. B. Stop the release of the deliverable to the customer. C. Use the new quality criteria for future deliverables. D. Update the risk register. 12.During a group activity to identify an input to the Plan Procurement Management process, some participants disagree with the ranking of compliance-related items. What tool or technique should the project manager use to resolve this? A. Affinity diagram B. Multicriteria decision analysis C. Nominal group technique D. Brainstorming 13.At which stage in the Tuckman team development model should the project manager put the most focus on increasing team motivation? A. Forming B. Storming C. Norming D. Performing 14.A new graduate recently joined a mature agile R&D team. A mentor, assigned to work with the graduate, is overwhelmed by the extra workload. Team performance and motivation are dropping. How can the project manager help with this situation? A. Maintain a laissez-faire leadership style with the team but use a transactional style to give firm guidance to the graduate. B. Ask the mentor to use a collaborative servant leader approach to perform the usual duties along with the mentor role. C. Cancel the mentor plan and focus on keeping the graduate motivated by learning through an intensive immersion. D. Ask three more team members to share the mentor role in order to reduce the individual mentor workload by 75%. 15.A project team just completed an environmental scan and have uncovered a lot of related hindrances that could potentially affect the project delivery negatively. The project manager is working with the team to understand the details of each identified hindrance and how the hindrances relate to each other, in order to understand the overall complexity of the project. This will enable the team to arrive at a plan that addresses the challenges identified. Which of the following techniques has the project manager used in this instance? A. Pareto analysis B. Critical analysis C. Systems thinking D. Total quality management 16.A project team has successfully completed a project. The same team and 3 other people start another project led by another scrum master. How will the new scrum master lead? A. High directive, high supportive B. Low directive, high supportive C. Low directive, low supportive D. None of the above 17.The project team members are dispersed across different countries. Suddenly, travel restrictions do not allow team members to collocate. When analyzing project risks, which risk analysis tools should the project manager use? (Choose two). A. Risk checklist B. Context diagram C. Meetings D. Data representation E. Diagramming techniques 18.A project manager is working on a complex agile project. The project includes many stakeholders with conflicting priorities. Which two actions should the project manager take to be prepared for negotiations and gain support from all of the stakeholders? (Choose two) A. Allow enough contingency to cope with scope changes. B. Develop a good relationship with the project team. C. Understand the politics and personal interests of the stakeholders. D. Develop a good communications management plan. E. Develop a good risk management plan. 19.A project manager is working on a complex project that has high interest from senior management. There are many stakeholders with competing priorities, which requires significant negotiation skills to overcome rising conflicts. Which two principles should the project manager follow when developing the negotiation strategy? (Choose two). A. Separate the people from the problem. B. Focus on political issues first. C. Focus on management priorities. D. Focus on positions, not interests. E. Delegate the decisions to the team. 20.A project manager is working on a complex project with many stakeholders that have conflicting priorities. Senior management asked the project manager to avoid "noise" because this is a highly political project. The project manager opted to use expert opinion from well-known industry profiles. What did the project manager do to satisfy senior management's request? A. Responded in a friendly manner to senior management B. Appeared to be consistent in the use of words and actions C. Cooperated with senior management to achieve mutual goals D. Took action based on the senior management's power to act 21.A project manager is working on a complex, political project with many stakeholders having conflicting priorities. Senior management asked the project manager to ensure that there was no "noise" regarding the project. During a stakeholder meeting, the project manager asked a series of questions to confirm acceptance for each deliverable before asking for acceptance of the whole project. What did the project manager do to satisfy stakeholders? A. Responded to positive actions of the stakeholders to reward actions B. Acted in a manner that was consistent in the use of words and actions C. Engaged with stakeholders by cooperating toward mutual goals D. Acted based on the power authorized by senior management 22.A project manager is working with a team to develop work packages in a hybrid environment. The project manager noticed a gap in the requirements gathering where important points were missing, which would impact the project timeline. What should the project manager do? A. Meet with the project sponsor to discuss canceling the project. B. Meet with the project sponsor and stakeholders to request a budget increase. C. Meet with the product manager to create a backlog with the missing requirements. D. Evaluate the impact, update the risk register, and present it to the stakeholders. 23.A project manager is leading a project that is vital to their organization and the local environmental and energy authority. During a team meeting to discuss project risks, the team raised a high risk that an important senior manager is not currently involved with project. What four actions should the project manager take to ensure the senior manager becomes involved in the project and to ensure project success? (Choose four) A. Implement regular status reporting B. Escalate this issue to upper management C. Develop a highly detailed project management plan D. Invite the senior manager to daily project meetings E. Expand senior manager involvement F. Implement frequent quality reviews 24.In a retrospective meeting, Alan, the junior of the team is enthusiastic about all the topics being discussed and takes notes of everything, while Walter, the senior, interrupts continuously, shows no interest and complains about not being able to continue with code-development. How would you describe the situation? A. Alan is a Learner and Walter is a Prisoner B. Alan is a Explorer and Walter is a Vacationer C. Alan is a Shopper and Walter is a Rebel D. None of the above 25.A project team decides to document new aspects of a regulation as additional elements in the work breakdown structure (WBS). Which of the following are potential downsides to this approach? (Choose 2). A. Traceability improves but requirements will likely remain fragmented. B. Traceability of requirements becomes more difficult at the project level. C. Some of these requirements may not be completed as part of the project itself. D. Regulatory requirements are not necessarily tied to the scope of the project. E. Splitting the new items takes time and also requires effort to update the WBS. 26.A project manager considers compliance to be part of the organization's process assets. The project team, however, has decided to include compliance as inputs to the relevant processes rather than document these rules as requirements. What is the project manager's compliance responsibility? A. Acts as coordinator for the resources and activities B. Conducts audits for the compliance requirement C. Performs risk analyses of compliance risks D. Changes process assets of the organization 27.During the planning of a project incremental deliveries, the team decides they need a specific experience in one of the deliveries towards the end of the project. What should the project manager do next? A. Enroll the team in a specific training so they can be ready for the needed expertise B. Ask the project sponsor to ensure the availability of the needed resource on the specific time C. Ask the team members to team up and do self-paced learning to acquire the needed expertise D. Define and share work agreement with the needed team to coordinate activities effectively 28.An agile coach is counselling a large software organization which has been using waterfall, and now plans to jump into agile or hybrid method. What would be a project managers suggestion? A. Continue using waterfall, since hybrid does not fit with organizational structure. B. Agile takes time to implement, but is more suitable to implement agile and then move to hybrid C. Team members succeed using hybrid methodologies, for they are already familiar with waterfall D. Hybrid is the more appropriate methodology for software organizations 29.A project manager works for a global company and understands the importance of the requirement management plan. When should the requirement management plan be implemented? A. At the start of the project B. Prior to executing C. After customer contracts signature D. During the planning phase 30.In a critical project to the organization, one of the contractors complains that approvals are lengthy and difficult to handle. The contractor mentioned this as it may affect the project schedule. What should the project manager do next? A. Hire additional resources for the team to mitigate this risk. B. Add this risk to the risk register to be monitored and reviewed. C. Escalate the risk to upper management as critical for timely delivery. D. Discuss this with the team to find options to mitigate the risk. 31.A project manager noticed that one team member is frequently absent from project team meetings. Instead of working on the current project, the team member has been working on a task assigned by their functional manager. What should the project manager do to resolve this issue? A. Discuss the resource allocation with the team member's functional manager. B. Remove the team member from the project team due to their continued absences. C. Record the absences in the team member's performance appraisal. D. Ask another team member for input regarding the issue. 32.During the execution phase of a healthcare IT project, the customer's project manager resigns. The key stakeholders are no longer getting updated information in a timely manner. What should the project manager do next? A. Update the communications management plan. B. Inform the key stakeholders directly. C. Update the project sponsors on the issue. D. Keep sending the information until a response is received. 33.Company A has launched a new strategic project. The goal and scope of the project were loosely defined at the executive committee meeting, and the stakeholders have been appointed. The project manager needs to hold the kickoff meeting. However, most of the stakeholders travel extensively, and the project manager is unable to schedule a meeting when all of the stakeholders will be present. How should the project manager approach the kickoff meeting? A. Hold the kickoff meeting with the available stakeholders and update others later. B. Postpone the kickoff meeting until the stakeholders have returned. C. Schedule one-on-one sessions with the stakeholders before they leave. D. Arrange a virtual team kickoff meeting with the stakeholders. 34.The project manager is responsible for a major project that involves working with many vendors. A key project concern is related to the quality and timely delivery of procured products and services as committed by the vendors. What should the project manager do to ensure that the products meet the quality requirements and are delivered on time? A. Raise an item in the risk register to capture potential impacts related to delays in the procurement of products and services, mitigating the risk of suboptimal quality. B. Conduct procurement performance reviews on a regular basis with all contracted vendors to ensure that products and services are all delivered or will be delivered on time and as per the agreed-upon contract. C. Delegate the management of the procurement process and the interaction with all vendors to the organization's procurement department as they have the tools and means to deal with a large number of vendors. D. Review vendor management plan with all vendors to ensure they are in agreeance with the plan, mitigating the risk of undelivered and low-quality products. 35.A project manager is managing a construction project that is 40% through the execution phase. The project sponsor has asked the project manager to ensure that all key stakeholders are still committed to the project. How should the project manager assess the stakeholders' current engagement levels? A. By reviewing and updating the communications management plan B. By analyzing the most updated issue log C. By asking key stakeholders to submit a signed declaration D. By reviewing the stakeholder engagement assessment matrix 36.A project manager receives an email shortly after the beginning of a sprint. It is from a key stakeholder who is unfamiliar with agile methodologies and has a serious complaint about the work that was just started. The stakeholder insists that one deliverable should be changed. What should the project manager do? A. Address the request at the daily standup and ask for the project team's opinion. B. Alter the backlog to accommodate the change and send a note to the team to start the requested deliverable as soon as possible. C. Schedule a meeting with the stakeholder and product owner to discuss the request. D. Cancel the current sprint, schedule a priority retrospective, and invite the stakeholder to discuss the request. 37.A company is implementing a new computerized system. During project execution, the leader of a department raises a concern that the department's requirements are being completely ignored in the approved project management plan. What should the project manager have done to prevent this issue? A. Managed expectations from stakeholders B. Sought expert judgement in the project scope design C. Involved relevant stakeholders in the project planning D. Developed a change management plan to approve change requests 38.A project is 70% complete. During a product review meeting, a stakeholder complains that additional features should be included. A. Analyze changes with the team and go through the formal change control process. B. Inform the stakeholder that the changes will be applied later as product fixes. C. Update the project management plan with the requested changes and inform relevant stakeholders. D. Submit a change request to the change control board and inform the sponsor about the changes. 39.A project manager is preparing to complete the exit criteria for a major system development project. A risk and compliance stakeholder advises the project manager that the project still needs to complete a new deliverable related to the latest legislation passed by the local government. The requested change will impact the project's release date. A. Meet with the stakeholders and advise them that the request was not part of the exit criteria. B. Submit a change request to the Change Control Board (CCB) for final approval. C. Escalate the issue to the sponsor to avoid delaying the project release date. D. Advise the stakeholder that this request is out of scope and that they will need to raise a change request. 40.A project manager has been informed that the first of several major deliveries from another country will be delayed. These deliveries are on the critical path, and the delay will result in a missed milestone. A. Update the project's lessons learned register and project management plan. B. Revise the project schedule and notify the stakeholders of the delay. C. Register the delay in the issue log and develop an immediate action plan. D. Identify the parties responsible for the delay to issue back charges for their portion. 41.A stakeholder is concerned that the project is falling behind schedule, based on unofficial information from the project team. Although some tasks have slipped, these tasks have free floats; otherwise, the project is on track. The project manager immediately contacted the stakeholder to show and explain the latest project status reports. A. Issue a memo stating that the project status can only be shared through authorized channels. B. Include the stakeholder in the project status mailing list. C. Review the project's communications management plan with the project team and update as necessary. D. Revise the status reports to clearly identify delays that should be acted on. 42.The development phase of a new product has concluded. The validation test is about to start, but the test lead disagrees with the criteria for the test. A. Understand the reason for the disagreement and submit a change request to the change control board if appropriate. B. Implement a plan to change the test criteria so that the validation test can be started as scheduled. C. Keep the validation test criteria unchanged because such changes will impact the project schedule. D. Explain how changes may impact the project and convince the test lead to go along with the original test criteria. 43.A project manager has recently been assigned to an existing multinational project and is not familiar with the key stakeholders. A. Request a meeting with the resource manager. B. Review and update the stakeholder register. C. Ask for the opinion or expert judgment of the sponsor. D. Identify the communications tool and update the plan. 44.An organization is halfway through a five-year project and everything has progressed as scheduled. The latest project assessment indicates that the project will not be in compliance with a recently introduced international regulation. A. Proceed with the project because the new regulation is not part of the initial project requirements. B. Conduct a workshop with the project steering committee to review the new regulation and find a resolution. C. Leverage the contingency reserve to fund the additional tasks required for the new regulation. D. Ask for funds from the management reserve because the new regulation is an unknown risk. 45.A new solution is being deployed in several countries. Country A asked for a change in the solution to comply with its customer market. The project manager for the deployment in Country A accepted the change. When the project manager for the deployment in Country B received the new version of the solution, the tests performed failed because this version is not consistent with Country B's regulations. A. Prevent the changes from being authorized. B. Ensure that all countries align their requirements with Country A. C. Analyze all change requests raised during each country's deployment at a global level prior to implementation. D. Ensure that any country that requested a change pays for any required changes. 46.A project manager is reviewing the project status with the team and identifies that a vendor resource can be released earlier than planned. The project manager reviews the schedule, confirms this change, and informs the vendor. The vendor argues that the resource must stay for a certain period of time. A. Leave the schedule as is since the resource has to stay on. B. Confirm the schedule changes and review them with stakeholders. C. Make preparations to release the resource to the vendor. D. Consult the terms and conditions in the vendor contract. 47.A project to develop a new software program has been delivered. The software has been put into production, but members of the project team are continuously contacted by users asking how to use or report problems, even though the project received administrative closure. A. Include an activity in the project scope that allows the project to support the tool after production release. B. Communicate the project's conclusion with the rest of the organization formally, as per the communications management plan. C. Ensure the final product is transitioned to a different group or organization to take care of the software during its life cycle. D. Ask the team members to stop answering or addressing questions from users and encourage the users to read the documentation instead. 48.The scope of an agile project is finalized, along with compliance requirements. During a regular project review, a stakeholder informs the project manager that changes are proposed to the country's safety legislation which may affect the scope of the project. A. Focus on completing the activities per the product backlog. B. Analyze the impact of the legislative changes. C. Instruct the team to proactively initiate changes in the next sprint based on the proposed legislation. D. Wait for the sponsor to approve the additional budget for the changes in scope. 49.An agile team replaced a key member with a less experienced member. One of the stakeholders is concerned that the project will not be delivered on time because of the new team member. A. Add this concern as a risk in the risk log and escalate it to the project management office (PMO). B. Meet with their functional manager to assess the situation, and obtain guidance on how to proceed. C. Reverse the decision for replacement and bring the former key member back onto the team. D. Assess the impact of this replacement, and make further resource adjustments where necessary. 50.An agile project team member is working on a user story that is overdue. Not having a completed user story is causing a significant delay to a specific functionality and will cause the team to miss the sprint goals. A. Discuss this delay at the next team standup meeting. B. Request additional resources from the sponsor. C. Exclude this functionality in the final product. D. Replace the project team member with a new developer. 51.An agile project is midway through its ten iteration cycles. During the last iteration, the team had to work overtime to accomplish the goal. In the iteration retrospective, the team agreed that they took more time than planned because they did not have the required experience when they executed the assigned tasks for the first time. A. Ask the project sponsor for additional team training. B. Ask the sponsor to approve a change request for more time in future iterations. C. Ask the team to re-assess their effort estimates in the iteration planning session. D. Ask the product owner to reprioritize the product backlog. 52.Project team A is launching a complex program in collaboration with project teams B, C, and D. What should be the priority for project team A's project manager during the early stages of the project? A. Host a team-building event with members from project teams A, B, C, and D. B. Include a metrics dashboard for project teams B, C, and D. C. Establish the same priorities as those of project teams B, C, and D. D. Ask project teams A, B, C, and D to identify critical dependencies, risks, and major milestones. 53.In order to function optimally, a project team should have a project charter that states the vision or purpose of the project and a clear set of working agreements. To achieve this, which question should the project charter answer? A. Why is this project being done? B. Why did the organization prioritize this project? C. What are the key risks and their mitigation? D. Who will be doing the work? 54.An agile team created a risk register for a project. All initial risks were identified using stakeholder interviews, workshops, and information from the project charter. What should the project manager do to manage the risk register and the associated risks for the remaining project duration? A. Assess and prioritize the risks during each sprint retrospective meeting. B. Add risks as an agenda topic in daily standup meetings. C. Update the risk register and review risks with the team on a regular basis. D. Eliminate all project risks using iterative risk management. 55.At daily standup meetings, several team members complain that they cannot concentrate due to a noisy work environment. Who is responsible for solving this problem by creating a more conducive work environment? A. The project sponsor. B. The team members. C. The product owner. D. The project manager. 56.An agile project team is building a website for a client. The client informs the product owner that their company has decided to release the website one month ahead of schedule, in order to take advantage of a business opportunity. What should the project manager have the team do? A. Commit additional resources to complete work a month in advance. B. Meet as a group to assess what is possible to complete by the new timelines. C. Tell the client it is not possible to release the website this early. D. Conduct a retrospective meeting to understand how they could have worked faster. 57.A project team adopted agile practices to meet the business need to develop an application. One of the senior team members inconsistently attends the team meetings, even the daily standup meetings. This senior team member then asks other team members to provide status updates on the senior team member's behalf. What should the project manager do to handle this situation? A. Request the removal of the senior team member due to the participation issues. B. Remind the senior team member to adhere to the team's working agreement. C. Escalate the senior team member's participation to upper management. D. Ask the other team members to cover the tasks assigned to the senior team member. 58.An inexperienced project manager requires HR support for a project. The HR manager hired interns and sent them for training. However, the training did not deliver on the competency-based outcomes. The HR manager is not willing to accept the training costs because the training budget is exhausted. What should the project manager do to resolve the situation? A. Prepare clear training requirements for full-time staff and interns. B. Identify the competency gaps and collaborate with the HR manager for options. C. Communicate training and hiring requirements to the HR manager. D. Analyze the risk, update the risk register, and inform the HR manager. 59.An agile project to implement a new automation process in a factory is underway. The project manager needs a vendor to help with the installation. What should the project manager do before the vendor comes to work with the team? A. Delegate all key decisions to the vendor's team so the project manager does not take any risks. B. Hold an orientation to ensure both parties share the same understanding of project goals and requirements. C. Submit the communication matrix so that all team members and vendors are known. D. Remind the team that the vendor works for them and that the team can make final decisions. 60.A project manager observed that a team member is becoming increasingly disengaged from an ongoing project. What should the project manager do to help ensure participation from this team member? A. Speak to the team member, understand the problem, and ask the team member to work on corrective actions. B. Ask another team member to mentor the disengaged team member. C. Call a team meeting to discuss team engagement expectations. D. Ask the team member to undergo additional training to improve their communication skills. 61.A project manager has created the stakeholder list and is deciding how to distribute information effectively to the customer. What should the project manager do next? A. Meet with all the stakeholders face-to-face on a weekly basis. B. Send updates to all stakeholders, including the customer. C. Perform a stakeholder analysis and prepare a communications management plan. D. Review historical data sent to other customers and follow the same practices. 62.A company has started doing agile projects. The project sponsor is frustrated and does not understand the new requirements gathering process, which seems to be incomplete and moving too fast. What should the project manager do? A. Help the project sponsor understand the different tools and techniques available and why this one was selected. B. Update the stakeholder register to identify the project sponsor as a potential impediment. C. Let the team know that the sponsor is unhappy and switch from iterative planning to predictive planning. D. Pause the project work until the scrum master has a chance to review the complete backlog with the sponsor. 63.An organization is trying to adopt agile approaches to execute projects for their customers. During project planning, the product owner proposed that any release to the customer should be approved by the legal department before it is shipped. The development team is disappointed as it may potentially delay releases and the delivery schedule. Since other departments in the organization do not use agile, what should the project manager's role be as a servant leader? A. Advise senior management to introduce agile to all departments to ensure seamless services to customers. B. Continue with organizational procedures to ensure compliance to policies and avoid creating issues. C. Inform the customer about the organizational procedures and ask them to discuss this with the organization's leadership. D. Work with the legal department and other applicable departments to review the processes that support the project delivery. 64.A team has recently adopted agile and is following a scrum model. There is a conflict between a lead developer and a quality assurance team member regarding their approaches, which is impacting the sprint goals. What should the project manager do to resolve these conflicts? A. Call separate meetings with each team member and suggest that the team members resolve it at their level. B. Analyze the situation and help the team members understand the impact of the conflict. C. Help the team members collaborate and resolve their problem together. D. Discuss the situation in the retrospective session and create an action item. 65.A newly appointed product owner is not sure how to prioritize product specifications and mentions this challenge to the project manager. What should the project manager do to assist the product owner? A. Prioritize product backlog for the product owner. B. Coach the product owner on how to prioritize product specifications. C. Request that the product owner becomes trained in agile methods. D. Ask project team to prioritize product backlog. 66.A project was undertaken to set up a new business function in the company. Several months after completion, the project manager is still handling business operations for the project while working on another project. What should the project manager have done at the beginning of the project to prevent this? A. Ensured that the revision to the organizational structure was a deliverable. B. Included the transition plan as a deliverable in the project closing process. C. Clarified the RACI chart with the project sponsor at the project's onset. D. Ensured that the recruitment process was included in the project management plan. 67.During a retrospective meeting, project team members complain that open issues that were not fixed during the iteration are impacting their velocity. What should the project manager do to improve productivity? A. Ensure team members attend daily standup meetings to discuss the impediments. B. Document the issues in the issue log and wait to solve them at another time. C. Extend the daily standup meetings to discuss the issues in more detail. D. Escalate the issues to the project sponsor to get them solved immediately. 68.During project execution, the audit team determined that critical regulatory requirements are not being met. What should the project manager have done first to avoid this problem? A. Updated the issue log with regulatory requirements. B. Assessed the internal and external regulatory environments. C. Had the audit team review the project management plan. D. Included a member of the audit team on the project 69.A project manager recently took over a project from a project manager who left the company. The new project manager is aware that the previous project manager had a very authoritarian style of management and made all the decisions regarding the project. The new project manager notices that a senior supervisor's morale is low. What should the new project manager do? A. Increase the supervisor's level of authority. B. Identify the cause of the morale issue. C. Modify the role of the supervisor in the project. D. Speak with the supervisor and update the project issue log. 70.A conflict about how to proceed has developed between two team members prior to a release. The team needs to work together to complete the product release. What should the project manager do first to defuse the situation? A. Hire an agile coach to instruct the team members on how to manage their conflict without harming the project. B. Observe the team members' interactions and talk with them about their complaints before applying a conflict resolution technique. C. Set up meetings with both team members and human resource management to remind them of the importance of the next delivery of the product. D. Explain to the team members that they are wasting time engaging in a conflict and not delivering the product functionality. 71.The product owner has asked the project manager and the agile team to demonstrate the completed functionality to key project stakeholders. The project is in its early days and has only completed three iterations of functionality. This is the first time the stakeholders will be exposed to an agile project. What should the project manager do? A. Reinforce with the product owner that it is their role to communicate and manage the stakeholder groups directly. B. Set expectations with the stakeholders regarding what agile is, the approach, and that they will be seeing a small amount of functionality. C. Demonstrate the completed functionality to the stakeholders, along with the user requirements and solution prototypes available. D. Protect the team from distractions by providing a link to the user acceptance test (UAT) environment so the stakeholders can view the functionality directly. 72.A project manager is managing multidisciplinary teams. During the last project review meeting, the project manager realized that there is friction between some of the team members. What should the project manager do next? A. Identify the team members and review their project performance. B. Consult with the sponsor to find replacements for the team members. C. Evaluate the issue and apply conflict resolution techniques. D. Report the issue in the monthly project executive summary. 73.A new project manager joins an existing team. The project manager is made aware that there are strong personalities on the team, which has resulted in management becoming involved to resolve team performance issues. What should the new project manager do when first joining this team? A. Implement the plan that senior management has developed to resolve conflicts on the team. B. Review the team velocity records and observe the team and interactions between the team members. C. Follow the advice of the most vocal team member on how to improve team dynamics. D. Observe the team and determine who should be removed from the team 74.A project manager is planning the next release for the software development team. The team completed two releases to date, and the product backlog for the next release has been confirmed. Which tools should the project manager use to plan the duration for the next release? A. Retrospective notes, product roadmap, and test cases B. Work breakdown structure (WBS), product roadmap, and resource calendar C. Burndown chart, user stories, and retrospective notes D. Business requirements document, product owner calendar, and user stories 75.A project team has just reached a project milestone successfully. The project manager noticed that the team performed extremely well. Which approach should the project manager use to communicate with the team about their performance? A. Avoid communicating anything about their performance as the team is expected to deliver milestones successfully. B. Wait until the end of the project and report to the team what was done well and poorly in each stage. C. Give feedback to the project team regarding their good performance in the next project meeting. D. Disregard what was already done on the project and ask the project team to focus on what is left to be done. 76.In a multidisciplinary project, a project manager is delegating some project management activities to several team members. What should the project manager do? A. Develop a project communications management plan and distribute it to the stakeholders. B. Develop a mentoring plan and include it in the project status report. C. Develop an organizational breakdown structure (OBS) and a work breakdown structure (WBS). D. Develop a responsible, accountable, consult, and inform (RACI) chart. 77.A project team member continues to change a colleague's deliverable during every sprint. The colleague has asked the project manager to intervene. What action should the project manager take to address the concern? A. Speak with the team member to determine the reason for the changes. B. Discuss any lack of quality in the deliverable with the colleague. C. Review the performance of both team members with their functional managers. D. Control the execution and delivery to ensure that the deliverables are not changed 78.A project is following a strategic plan that includes key milestones that have been aligned with stakeholders. As the work is being executed, new tasks arise along with important dependencies that prevent the work from progressing as planned. The team is unable to determine who should make decisions and take actions on the new tasks and dependencies. What will help the project manager resolve this issue? A. Use a RACI chart to facilitate team task accountability. B. Use a Gantt chart to ensure milestones are accomplished. C. Ask the sponsors who has responsibility. D. Use a work breakdown structure (WBS) to ensure requirements are covered. 79.An integrated project delivery requires the development of both hardware and software. The project manager has received a customer-approved Gantt chart for the entire product development, and the customer wants to be involved during project execution. However, the software development team would like to introduce agile methodologies. What should the project manager do? A. Assess the best project methodologies for continued business value. B. Adopt agile sprints to develop the project within the timeframe. C. Advise the team to strictly follow the customer-approved Gantt chart. D. Evaluate customer roles with the project management office (PMO). 80.In a company that recently adopted hybrid practices, a project is struggling to perform as expected. Neither the project manager nor the team members have previous experience with this new approach to project management. To ensure the transition to hybrid practices is producing the desired results, what should the project manager do? A. Take an active role in assigning tasks to team members and follow up with their results. B. Train team members in basic hybrid practices and ensure the team performs coordination meetings. C. Issue performance reports to all team members so they can review and act on them. D. Build a WBS and RACI chart to ensure all aspects of the project are owned and tasks are clear. 81.A project manager is building a project team. All of the project team members have worked together on previous projects. One of the team members is known for challenging most organizational procedures and processes. What should the project manager do first to ensure a smooth project initiation? A. Review the organizational process assets (OPAs) with all team members and establish ground rules. B. Ask the project sponsor to define the ground rules and share them with the team members. C. Ask the project sponsor to replace or remove the troubled team member. D. Set up a meeting with the team members to review the project management plan. 82.A project manager in Location A works with a local team, while developers are in another remote location, and a quality assessor is in yet another remote location. The project manager is aware that these distances mean that the team could struggle with lag when needing to communicate. What could the project manager do to mitigate this issue? A. Increase the number of standup sessions per day. B. Source new team members locally. C. Create a fishbowl window. D. Decrease the need for team communications through backlog grooming. 83.During a one-on-one session, a new team member shared their frustration regarding their inability to successfully complete an assigned task, even after the team member put forth their best effort. What should the project manager do first to address the team member's concerns? A. Encourage the team member to keep working hard on their assignments. B. Identify the root cause for why the team member cannot complete the assigned work and remediate. C. Authorize additional training for the team member during the next month's educational series opportunities. D. Adapt their leadership style based upon the team member's needs 84.The project manager of a new hybrid project is trying to put together the project team. The best candidates for team members are geographically dispersed, so there is a risk that this situation will interfere with the performance of the project. Colocation would increase costs dramatically; and due to severe competition, the company is struggling financially to survive. What should the project manager do? A. Make sure the right tools for virtual collaboration are available for the team. B. Insist on bringing the team together by cutting the budget somewhere else. C. Ask the product owner for additional funds to support colocation. D. Organize the work according to the locations of the team members. 85.Initial training for new software on a project consisting of a DVD to be watched prior to participating in the project was given during the project onboarding. Several team members gave negative training feedback stating they were unprepared to use this new software. What should the project manager have done to ensure proper team member training? A. Test the project team members after they have completed their training. B. Request that the training department find more appropriate courses. C. Ask the team members to learn the required skills from the accompanying software manual. D. Conduct individual and team assessments on their preferred learning method(s). 86.During the last sprint review, the product owner stated that the product does not deliver any value. The project manager believes that the product meets all the provided specifications. The team is confused by the product owner's statement. What should the project manager do when using a hybrid approach? A. Review the project's benefits management plan with the product owner. B. Escalate the matter to the executive board so they can decide on next steps. C. Prioritize the project backlog and ask the development team to fix the issues. D. Ask the product owner to terminate the project as it is no longer aligned to the expected benefits. 87.A project manager is leading a project where a low-level stakeholder has just been promoted to a new position and has now become a high-level stakeholder. What should the project manager update to ensure the proper involvement of this stakeholder to the project? A. Communications management plan B. Stakeholder engagement plan C. Resource management plan D. Risk management plan 88.An agile project team is struggling to keep track of the changes being applied to the product, because its process is cumbersome and error-prone. What should the project manager do to address the issue? A. Clearly assign the responsibility for the process to a single person to ensure accountability in case of failure. B. Use the next retrospective to evaluate the process's effectiveness, and determine if changes are needed. C. Seek the sponsor's approval to stop following this process and assume the risk of eliminating it. D. Secure funds to acquire a software-based solution that can speed up the process and reduce the errors. 89.A project manager working with a culturally diverse team discovers major intra-team conflicts during project execution. What should the project manager do? A. Schedule a project team meeting to understand the conflicts. B. Advise the team members to work harmoniously. C. Update the resource management plan. D. Engage members in team-building activities. 90.A project advisory team is working remotely from the core project team. There is a constant flow of information between these two teams, and both teams approve project documents. Any delays in approvals will result in additional expense. Which practice would assure the project manager that all of the documents are on hand, updated, and approved properly? A. Let the advisory and core teams develop and maintain their own document categorization and naming systems. B. Require each member of the advisory and project teams to maintain updated records. C. Have the sponsor maintain and approve changes within a single document registry. D. Oversee a single document registry and change control system that both teams use. 91.A hybrid project involving many stakeholders is underway. As requested by the project management office (PMO), the project status reports, as well as other project documents, are being stored in a central repository. When reviewing the documents stored in the repository, the project manager discovered that documents were either not updated or were missing. What should the project manager do in this situation? A. Discuss the situation with the project sponsor to reduce the level of documentation. B. Work with the team leaders to update the required project reports C. Stop all project activities until the project documents are updated and uploaded. D. Schedule a knowledge transfer session at the final stage of the project. 92.A project manager is assigned to an ongoing project with virtual team members from different countries who are working remotely in different time zones. The project manager notices that team members are not completing project activities on time and are unable to produce the expected deliverables due to irregular communications. How should the project manager resolve this? A. Provide the team with the deliverable list to guide them. B. Engage with the team members to understand their challenges. C. Organize time management training for the team. D. Take steps to colocate the team in the same office 93.A project manager has completed the project deliverable and has passed the acceptance criteria. Which statement confirms that project benefits have been achieved? A. The deliverable has been approved and value has been confirmed. B. The deliverable solved all of the issues specified by the project sponsors. C. The project has seen some improvements in the ability to make decisions. D. The project was completed on schedule, without any complaints from end users. 94.On an agile project, a team member raises concerns about health and safety issues related to the project deliverable. How should the project manager handle health and safety issues on projects? A. Provide the customer with adequate documentation on health and safety information. B. Send the issue to the health and safety department. C. Design a health and safety policy for the organization. D. Ensure that the necessary health and safety requirements are met in the definition of done (DoD). 95.A major change in a government policy may cause a project's completion date to be delayed. The project is 90% complete. What should the project manager do next? A. Suspend the project until the issue with the government policy is resolved. B. Engage the change control board (CCB) to assess possible impacts to the project. C. Move forward with the project since it is near completion. D. Assign a new completion date for the project and inform stakeholders. 96.A project manager has been assigned to lead a cross-functional project team. During a brainstorming session, the project manager realizes that some team members do not see the need for change, and this is affecting the team's output. What should the project manager do? A. Restate the objectives of the project to the team. B. Ask the project sponsor to review the project charter. C. Engage team members to understand their doubts and get their buy-in. D. End the brainstorming session and adopt interview methods. 97.At what point in an agile project should a project manager engage stakeholders? A. At the start of the project B. At the end of the project C. When challenges are encountered in the project D. Throughout the project life cycle 98.A team is working on a new technology deployment project. This product has never been implemented before so there is no past data or historical records. The team is challenged to provide initial estimations to the client (timelines, cost, and unforeseen product challenges). How should the project manager handle this situation? A. Develop up-front project management plans with a detailed budget. B. Provide guidance on project cost, time, and quality. C. Develop estimations with the team and explain the assumptions to the client. D. Encourage the team to perform retrospectives at intervals. 99.A key stakeholder is upset about the new features in the current iteration for the product. The key stakeholder was unavailable during the last review and did not have the opportunity to provide input. What should the project manager have done to prevent the stakeholder from being upset? A. Waited until all stakeholders approved the change before implementing B. Ensured that updated project information is always accessible to all stakeholders C. Met individually with every stakeholder to avoid disagreement D. Scheduled meetings only when all stakeholders could be present 100. In the middle of an executing an IT project, two project team members discover a new feature that will change the appearance of the product and make it more aesthetically appealing. Excited about the opportunity to add this feature, they approach the project manager to approve this addition to the deliverables, which will increase client satisfaction and possibly increase the company's chances of receiving additional project contracts from the client. How should the project manager respond? A. Approve the idea in order to achieve the projected expectations of the team members. B. Remind team members that, without an approved change request, the focus should be on the agreed scope. C. Get the buy-in of the remaining team members and implement the feature once the team members give their consent. D. Implement the change as soon as possible to improve the possibility for future revenue. 101. A project manager is managing an upgrade from an older system to a new version. Halfway through the upgrade, the older system failed to upgrade and could not be restored. What should the project manager do to manage this situation? A. Abandon the old system and motivate the team to speed up the project as there is nothing more to do. B. Ask for more time to restore the old system while continuing with the project. C. Assess the impact with the functional manager to inform key stakeholders about mitigation plans and seek approval. D. Encourage the team to continue working as the project manager is not responsible for the old system, but keep checking the baseline. 102. Even though the customer is receiving sprint velocity and results reports from the project manager by email, escalations to the project sponsor complaining about project performance are common. What should the project manager do in this situation? A. Involve the customer in the sprint planning and review sessions to agree on release dates. B. Schedule regular sessions with the customer to explain the reports and address feedback. C. Send a document detailing the team capacity and role assignments to the customer. D. Have the technical leader call the customer to explain the technical details about the project issues. 103. There are concerns that a scheduled-for-release product may not meet the agreed-upon end user requirements. How should a project manager avoid this situation in the future? A. Discuss the benefits with the client. B. Ensure there is a product backlog. C. Provide examples of other similar projects. D. Hold a session to review the deliverable in detail. 104. A project manager is assigned to a project in a country where the company has not previously done business. At the beginning of the project, the project manager realizes that there are certain regulatory requirements for which the project team has no experience. What should the project manager do next? A. Assign sufficient budget in case such requirements have to be met. B. Consult with a subject matter expert on how to avoid such requirements. C. Engage a subject matter expert to check if the requirements are relevant to the project. D. Escalate concerns about the requirements to the project sponsor. 105. A team member in a hybrid organization informs the project manager of a new way to execute an activity with a shorter duration. The project manager has not used the new process before, but a trusted team member explains that their previous experience with the process validates the efficacy of the new process. Which two actions should the project manager take? (Choose two). A. Involve the team member's functional manager. B. Postpone the decision until the next sprint. C. Update the work breakdown structure (WBS). D. Assess the impact. E. Communicate the impact with key stakeholders. 106. For the purposes of quality assurance, a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available. Why is an attendance list important? A. It is a document that is registered within the lessons learned register. B. It is a record that shows the number of attendees at the meeting. C. It is standard practice on projects to conduct risk review meetings, however, meeting attendance is optional. D. The attendance list is evidence that risk review meetings were held with the appropriate project team members. 107. A compliance issue was found during the course of a project. This caused an inspection of the product by the internal audit team. As a result, the project fell behind schedule. What should the project manager have done initially to avoid this issue? A. Ensured that compliance requirements were documented. B. Created templates to document compliance. C. Hired a compliance consultant. D. Engaged stakeholders at the beginning of the project. 108. A project manager walked into a project office and found a team member and a supplier representative engaged in a disagreement over a clause in the supply agreement. The project manager invites the supplier for a negotiation with the project team to resolve the conflict. Applying the principles of negotiation, for what should the project manager and team aim? A. Give up the project objective for a win-lose outcome. B. Achieve the project objective for a win-lose outcome. C. Achieve the project objective for a win-win outcome. D. Achieve the project objective no matter what the outcome. 109. As a project is nearing completion, a struggle between the product owner and the project sponsor regarding who owns the benefits derived from the deliverable becomes a matter of litigation. What should the project manager have done to prevent this conflict from happening? A. Identified the project sponsor as a stakeholder at the beginning of the project. B. Develop and approve the project charter jointly with the product owner and the project sponsor. C. Created a detailed work breakdown structure (WBS). D. Identified and captured any potential issues in the issue log. 110. Which one of the following is a best practice to ensure that virtual team meetings are effective? A. Having the meetings recorded for participants who could not attend. B. Work with the virtual team members to determine communications most appropriate for them given their location and participation on the project. C. Prioritizing the agenda with items that require more discussions. D. Assigning a timekeeper and a note taker, alternating for each meeting. 111. A project manager is in the execution phase of a project. A newly identified stakeholder continuously bypasses the project manager to get feedback from the project sponsor directly, thus escalating pressure and frustration for all members of the team. What should the project manager do next? A. Call a project meeting of all stakeholders to discuss the matter and develop a suitable action plan. B. Email the communications management plan to the stakeholder concerned and point out that they did agree to the plan. C. Meet the project sponsor and confirm that the project manager must be the single point of contact. D. Meet with this stakeholder to update the stakeholder engagement plan and to understand their communication needs. 112. In the planning stage of an upgrade project, a project manager benchmarked other recent projects that use the same technology. The project manager discovered that longer-than-planned outages occurred in most of the cases due to frequent maintenance activities. What will be project manager's next step? A. Benchmark projects using other technologies to establish a more objective baseline. B. Compare other similar technologies and recommend implementation of another technology. C. Create a risk item in the risk register and incorporate the thresholds according to the benchmarks. D. Discuss the probable downtime with the sponsor and obtain approval for outages. 113. A distributed team just finished an iteration that completed complex tasks ahead of schedule. During a retrospective, a new member interrupts and asks everyone to reiterate their role and what they have worked on in previous iterations. What should the project manager do? A. Refer the new team member to the project management plan. B. Inform the team member that this would be best handled in another meeting. C. Ask each team member to explain their role and what they worked on in the previous iteration. D. Ask the functional manager of the new team member to review the onboarding process. 114. A risk was identified at the beginning of a project, and a response plan was established. Due to unforeseen circumstances, the situation is much different than the anticipated risk, resulting in an even higher level of risk. The project manager has an idea to address the new risk efficiently, but the response is different from the original risk mitigation plan. What should the project manager do? A. Implement only those responses that are compatible with the risk management plan. B. Update the risk management plan and implement the new response to address the risk. C. Wait until the next progress meeting to get management approval for the new response. D. Implement a contingency response and inform the stakeholders afterward 115. A project manager is responsible for a 12-month waterfall project to create a new product. The project is nine months into execution when a new technology becomes available that would reduce the project costs by 10%. What should the project manager do? A. Update the configuration management plan to include the new technology as part of the design. B. Continue working as planned since the new technology was not part of the project management plan. C. Create a change request to evaluate the feasibility of using the new technology. D. Ask the development team to implement all remaining components with the new technology. 116. A project manager calls a meeting to identify risks for a complicated project. Several subject matter experts are invited to this meeting along with the project team. Why has the project manager invited the subject matter experts? A. Subject matter experts have specialized expertise and can help identify and address high-risk issues. B. Identifying risks in a meeting with subject matter experts makes getting better project resources easier. C. Risks will be easier to accept if the subject matter experts who attended the meeting work together. D. The project manager can leverage subject matter experts' resources to follow up on the identified risks. 117. The Work Breakdown Structure (WBS) of a project has been completely defined based on past project documentations and lessons learned. The team is now preparing the cost estimates. For contingency, the team increased the estimated cost of each activity by the same percentage. This resulted in the total cost exceeding the allocated budget before adding the management reserve. What should the project manager do? A. Request additional budget for the project. B. Reduce the percentage increase to reduce the total cost of the project. C. Recalculate the contingency reserve based on only identified risks. D. Allocate a portion of the contingency reserve to the management reserve. 118. The Quality Management Plan (QMP) calls for regression testing before each product release, but these tests were not included in the Work Breakdown Structure (WBS). What should the project manager do first? A. Submit a change request to add regression testing work packages to the project scope. B. Request extra test resources from the quality assurance functional manager. C. Suggest to the project client that regression testing be removed from the quality requirements. D. Seek approval from the project sponsor to remove regression testing from the Quality Management Plan. 119. A project manager is working with a cross-functional team. From lessons learned, the project manager is aware that this team typically raises additional requirements that are not in the approved scope. What should the project manager do to handle this expected behavior? A. Guide the team to manage scope using standard agile methodology. B. Escalate to senior management and request replacement team members. C. Attend daily standup meetings with the cross-functional team and key stakeholders. D. Explain to the team that requirements cannot be changed unless the budget is not affected. 120. A team member who is unfamiliar with the subject matter is struggling to complete a complex deliverable. What should the agile project manager do to ensure that the team member is able to take on a similar challenge in the future? A. Ensure that the team member receives adequate training and is comfortable with the subject matter. B. Encourage the team member to take on more stories on this subject matter until they are completely comfortable. C. Ask the team member to avoid taking on stories on this subject matter until the person is comfortable with the subject matter. D. Replace the team member with a more experienced team member who will improve the team's velocity. 121. An application developer took a story card to work that read "Customer can pay using credit card". After the implementation, the functionality was rejected because the application could not accept foreign credit cards. What should the project manager have done to avoid this issue? A. Described the user story in more detail. B. Scheduled the user story for the next iteration. C. Performed iterative backlog grooming with the team. D. Gathered more detailed requirement specifications from end users. 122. The sponsor notified the product owner that the budget was approved for a project. However, any additional investment for the project would have to wait until the next fiscal year. The product owner is concerned that this will hold up the project. What should the product owner do? A. Track the budget based on the release plan and show the value to the business. B. Explain that the project is just starting and the budget will need to be adjusted. C. Track the budget based on each sprint and remove nice-to-have deliverables. D. Ensure that the project manager monitors every invoice from the project. 123. A project team has been tasked to build a new product. The team builds the demo first and add features to the initial product. This is an example of what technical practice? A. Test-Driven Development (TDD) B. Continuous Delivery C. Behavior-Driven Development D. Spikes 124. A project manager is managing a hybrid project. A stakeholder has directly contacted a team member and has requested a change. Due to the request, the team member was distracted from their work, which caused a loss in productivity. What should the team member do? A. Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the change control board (CCB). B. Inform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity. C. Inform the scrum master so that the change can be discussed directly with the stakeholder. 125. A project is being executed. The project's life cycle is defined as predictive; however, a major deliverable will be handed over incrementally to the customer. The assigned resources are experienced and reliable and are willing to make decisions that the project manager used to make after each incremental delivery on other projects. What should the project manager do? A. Inform the team that although this is a hybrid environment, the project manager must still be responsible for making decisions. B. Consult the product owner about letting the resources make decisions. C. Support the decisions of the team and transfer the decision making responsibility to them. D. Schedule a steering committee meeting and obtain their approval on the request 126. A new project has high uncertainty in the cost required for completion. What approach should the project manager use to determine the expected costs? A. Analogous estimating B. Statistical techniques estimating C. Parametric estimating D. Three-point estimating 127. All quality controls have passed, and a project deliverable is ready to be released to the customer. However, a change request to add new quality criteria has been approved. What should the project manager do first? A. Update the project management plan. B. Stop the release of the deliverable to the customer. C. Use the new quality criteria for future deliverables. D. Update the risk register. 128. During project closure, the project manager finds it difficult to obtain successful project completion feedback. Some stakeholders disagree with the project's success criteria and have been frustrated with the project from the beginning. To what should the project manager refer to address these concerns? A. Project charter B. Quality management plan C. Scope statement D. Requirements documentation 129. An approved project charter stated that an agile approach must be used. During a lessons learned session, the client indicates that the team was unable to provide reliable cost estimates for the project, and that more time should be allocated to define the scope during the first iteration. What lesson should be captured in the lessons learned repository? A. The client should be exposed to the agile approach in advance to understand the cost estimating process. B. The agile approach should not be used if the client requires reliable cost estimates. C. During the first iteration of a project, time should be allocated to define the scope and ensure that reliable cost estimates are performed. D. Client communications should be included in the daily standups 130. After stakeholder data and information collection is complete, an analysis of the collected data begins. The power/interest scores are plotted for each stakeholder on a set of the axis to provide a visualization of stakeholder power and interest. There are three stakeholders that have low power and low interest. What are the actions for them? A. They must be kept satisfied by ensuring their concerns and questions are addressed adequately. B. They require minimal management effort. C. They must be kept informed and updated on the project. D. They must be kept satisfied, but also actively engaged with and consulted on the project. 131. A project team is faced with deciding on the next steps to take in order to address recently identified tasks schedule delays. The project manager expects team members to make the appropriate decisions for their respectively assigned tasks and proceed to implement them. Which type of leadership style is the project manager using in this instance? A. Democratic B. Autocratic C. Free rein D. Smoothing 132. A project team just completed an environmental scan and have uncovered a lot of related hindrances that could potentially affect the project delivery negatively. The project manager is working with the team to understand the details of each identified hindrance and how the hindrances relate to each other, in order to understand the overall complexity of the project. This will enable the team to arrive at a plan that addresses the challenges identified. Which of the following techniques has the project manager used in this instance? A. Pareto analysis B. Critical analysis C. Systems thinking D. Total quality management 133. A project manager is part of a project management focus group working on implementing project management change measures across the organization so that the benefits of projects can be more effective and successful. Which of the following describes the main process (es) for the focus group to consider in order for effective and successful change to take place within projects in the organization? A. An effective organization change process of projects B. An effective Individual change process of team members C. An effective regulatory change process of the industry D. Both A and B 134. In a Digital Transformation project with a very limited budget, it is needed a mixed profile that dominates the Mainframe and Cloud computing environment. Reviewing the availability of resources the only available is Paredes, who is problematic in dealing with colleagues for personally undermining and not respecting their work. As a Project Manager, what decision would you make: A. Add Paredes to the team and always be on his side as he is a vital resource for the project B. Add Paredes to the team and get involved in the problems he causes to fix them C. Wait 3 months for another resource with the same profile to be released from another project D. Add Paredes and do not take sides in the disagreements among team members 135. A project manager has engaged the sponsor and discussed concerns regarding noncompliance. The project manager understands that this could be a potential audit situation. What should the project manager do? A. Do nothing and continue to work as before since they will be ab audit B. Disengage the noncompliant department. as this is problematic C. Disclose the source of the problem to the auditors and let them decide. D. Gain the commitment and approval from leadership on noncompliance 136. A project vendor has informed a project manager that an outsourced project deliverable will be available 6 months later than the agreed project schedule. The vendor stated that they are focusing on other project deliverables with priority dependencies, and this particular deliverable had no stated dependencies. What should the project manager do to avoid schedule delays in future? A. Monitor the dependencies and respond to challenges. B. Ensure that all new dependencies are finish to start C. Specify any dependencies if they exist. D. Conduct a meeting to inform the customer. 137. A project manager is helping an organization transition from traditional methods to agile. The infrastructure, data warehousing and enterprise architecture teams operate very differently than the application development teams. How should the project manager implement agile in this organization? A. Ask every team in the organization to implement same agile methodology so that one-size-fits-all solution can provide similarity across all teams. B. All each team to decide which agile methodology fits best for them and let them implement different methodologies based on their needs. C. Force the top-down transition approach by asking the CEO to provide support for implementing agile in every team in the organization. D. Ask one team to implement scrum as a pilot so that all other teams in the organization can also implement scrum by learning from this team. 138. An operation support project, though the support work is going smooth, a customer is always complaining that they do not have any visibility on the quality of support work. How should this customers concern be addressed? A. Prepare relevant reports and send to customer on a daily basis and publish the reports on shared folder for future review B. Request customer to appoint a manager from their area to review day-to-day activities and agreements reached during all discussions C. Plan for a recursive governance meeting with customer to present the progress and publish the data in a shared folder for future review D. Inform the customer that every day after the most important discussions have taken place one team member will oversee updating him 139. A project manager is gathering knowledge related to the project and product requirements. Which approaches are classified as explicit knowledge transfer? (Choose 3). A. Creating a user manual with thorough guidance. B. Capturing users' experiences to potentially learn from them. C. Training session arranged by an external company. D. Reading through the project/product documentation and FAQs. E. Engaging in job shadowing activities. 140. In a critical project to the organization, one of the contractors complains that approvals are lengthy and difficult to handle. The contractor mentioned this as it may affect the project schedule. What should the project manager do next? A. Hire additional resources for the team to mitigate this risk. B. Add this risk to the risk register to be monitored and reviewed. C. Escalate the risk to upper management as critical for timely delivery. D. Discuss this with the team to find options to mitigate the risk. 141. What would be the most effective approach to motivate your team members? A. Providing formal awards and recognition to the team. B. Providing financial incentives to all the team members. C. Providing the same incentives to all the team members. D. Providing behavior-specific incentives to team members. 142. A team lead is assigned to an ongoing project. The team members have been working together for a while. How should the team lead start building relationships? A. Distribute tasks and observe the quality of the deliverables. B. Talk about personal preferences and make sure the team understands your approach. C. Ask some team members to share information about other members to become familiar with the team. D. Ask the team members directly about both personal and workrelated matters. 143. One in two dispersed teams fails to reach objectives due to: A. Inability to manage the distributed workforce B. Conflict management C. Team purpose identification D. Distribution of power 144. A new project manager is attempting to enable shared leadership within their virtual team. Which of the following options should the project manager avoid? A. Respect team members’ competencies B. Loosen the reins and avoid the “responsibility trap” C. Encourage leadership behaviors D. Maintain a "natural distance" with the team 145. A project manager in an organization is considering to implement an agile project delivery. The organization has a very strong PMO and very well defined change control process. What should be the main type of change that the project manager can use as a strong argument for agile delivery? A. Unplanned changes, like defects repair because agile improves quality by using incremental delivery B. Planned changes because in agile the team doesn't follow a plan and the approval process is much faster C. Planned changes because in agile the product owner decide priorities, using an ordered list called Backlog D. Unplanned changes, like shifting business expectations because in agile the product owner decide priorities 146. Which of the following is a tactic that a project manager can employ to effectively monitor the impact of the risk on the project while monitoring risks? A. Risk avoidance B. Risk escalation C. Risk acceptance D. Risk reporting 147. During a retrospective meeting, the team realizes that all deliverables were completed according to the specifications provided in the product backlog. However, the number of errors found during testing increased dramatically. What should the project manager do? A. Meet with quality assurance specialists to clarify the issue and seek resolutions. B. Review the risk management plan to determine the mitigation strategy. C. Perform a Monte Carlo analysis to identify possible scenarios and actions. D. Register the risk in the risk register and monitor it during the next iteration. 148. An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures. What should the project manager do to help avoid this situation in the future? A. Ask the project sponsor to approve overtime to compensate for the lack of performance while adjusting the plan. B. Review the velocity of the team over the last several sprints and adjust the plan accordingly. C. Replace junior team members with more experienced ones, and negotiate the project scope to compensate for the budget gap. D. Switch to a Kanban approach to have better control on the planned pace by limiting work in progress. 149. The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a mediumsized project. What tools can be used to provide this information? A. Analysis of the business requirements document B. A release burndown chart C. Story points for the remaining user stories D. Surrogate measurements 150. A transportation company is transforming its operational processes and the main system this company uses to move freight. The scope statement is in place. An iterative delivery approach has been agreed by all stakeholders. What does the project manager need to do next to help the team understand the work that needs to be done? A. Start working on the project management plan with work packages, a detailed schedule, and work assignments for team members. B. Work directly with stakeholders on the work breakdown structure (WBS) and assign tasks with a required timeline for each team member to start the work. C. Work with the team to decompose the scope into a WBS and work packages in order to create required deliverables and timelines. D. Create the requirements management plan to outline how project requirements will be collected, analyzed, and documented, and then assign requirements to team members. 151. A lengthy, ongoing project exhausts a project team. Due to deadline issues, the project manager needs to encourage team members. What should the project manager do? A. Review the project charter and propose extending the project schedule. B. Provide more recognition and rewards to team members. C. Discuss the situation with the team. D. Request additional resources. 152. Due to a recent incident, a dissatisfied stakeholder files a complaint about a project that has been closed. What can the project manager do to help resolve this? A. Execute the relationship management plan. B. Consult with the project sponsor to manage the dissatisfied stakeholder. C. Review the project management information system (PMIS) archives. D. Update the risk register 153. During a project steering committee meeting, the project manager reports that a formerly supportive key team member has become resistant to and negative about changes. Where this information should be captured? A. Responsible, accountable, consult, and inform (RACI) matrix B. Stakeholders engagement assessment matrix C. Risk register and issue log D. Work performance reports 154. A team receives outsourced deliverables and determines that they do not meet the agreed-upon acceptance criteria. What should the project manager reference to verify this with the vendor? A. Procurement management plan B. Request for proposal (RFP) C. Statement of work (SOW) D. Inspections 155. A project must be simultaneously implemented in two countries with a time-zone difference of 11 hours. The project manager must determine a mutually convenient time to provide stakeholders with information on the project's schedule, cost, and performance progress. What should the project manager use to determine this? A. Communication requirements analysis B. Asynchronous brainstorming C. Expert judgment D. Meeting planning skills 156. A project to create a new product is completed and introduced into the market, but sales are much lower than expected. Analysis determines that the product is misaligned with the organization's core competencies. During what activity should this have been discovered? A. What-if scenario analysis B. Business case review C. Strategic performance evaluation D. Scope definition 157. A project is being audited to ensure compliance with organizational policies. What process is being conducted? A. Audit Schedule B. Plan Quality Management C. Control Quality D. Manage Quality 158. A new warehouse facility is under construction. The project manager implements team development efforts such as training that will result in a lower defect ratio. What should the project manager do next? A. Introduce a training program. B. Update the resource management plan. C. Increase quality control reviews. D. Add training costs to the budget 159. A company is using Lean Six Sigma methodology on a project. Midway through the project, an external Lean consultant is invited to conduct an audit to ensure that the methodology is being properly applied. Which process is being employed? A. Manage Quality B. Control Quality C. Perform Qualitative Risk Analysis D. Plan Quality Management 160. An experienced project manager is preparing a kick-off meeting for a new service assessment. A high-level description of the service has been provided. What should the project manager do first? A. Develop the project charter. B. Develop the responsible, accountable, consult, and inform (RACI) matrix. C. Define the project scope statement. D. Create the work breakdown structure (WBS). 161. An issue requires the execution of the project's contingency plan, which impacts the schedule. What should the project manager do? A. Initiate a risk audit. B. Issue a change request. C. Review the cost impact. D. Update the contingency plan 162. A project manager discovers a significant flaw in a major project deliverable. Which project management process is being performed? A. Manage Quality B. Control Quality C. Plan Quality Management D. Statistical Sampling 163. A project manager is creating a software project's quality management plan. While reviewing lessons learned from past, similar projects, the project manager discovers that rework due to quality issues resulted in cost overruns. What should the project manager do to ensure that quality is addressed throughout the software development life cycle? A. Conduct recurring retrospectives to regularly check on the effectiveness of quality processes. B. Assign a resource to focus solely on the project’s quality. C. Ensure that quality is tied to performance reviews. D. Identify new quality policies and procedures for the project. 164. In an agile development environment, when should a risk analysis be performed? A. Before the start of each iteration B. During the daily standup meeting C. In the retrospective meeting D. After every scrum meeting 165. A project manager engaged in the delivery of a global project is in the process of recruiting a project team. After the team is formed, what should the project manager do? A. Send a welcome email and host a team introductory event with the team members so they get to know each other. B. Send a project management plan and charter to team members to familiarize them with project goals and procedures. C. Arrange a meeting for team members to discuss any concerns regarding requirements and project scope. D. Send the team members a survey to learn more about each member, share the results via email. 166. Some team members assigned to a new technology project expressed their lack of knowledge about the technology and the challenges they will face during implementation. What should the project manager do? A. Due to the project due dates, replace the members with more knowledgeable staff. B. Ask the team members to do some research and self-learning efforts about the technology. C. Reallocate the members to work on and complete different tasks for which they have experience. D. Reassure the team members that a training path is in place to learn the new technology 167. A project team is in the process of identifying the benefits associated with two projects in order to choose the one that will deliver more business value. The task at hand involves analyzing which project will help the company meet its compliance and regulatory requirements more easily as well as improve customer satisfaction more. Which of the following best describes the category of the benefits being analyzed in this task? A. Quantitative benefit B. Qualitative benefit C. Quality benefit D. Real benefit 168. What interpersonal skills that a project manager or team needs to monitor stakeholder relationships, evaluate engagement strategies, and modify these approaches as needed? A. Active listening, leadership, and cultural and political awareness B. Coaching, decision making, cultural and political awareness C. Active listening, team building, leadership, and networking D. Networking, influencing, and cultural awareness 169. When managing a strategic project for their organization, what four tools should a project manager use for risk analysis? (Choose four) A. Brainstorming B. Inspection C. Risk checklists D. Product evaluation E. Interviewing F. Decision tree analysis 170. A project is implementing three magnetic resonance imaging (MRI) units for the main hospital. One of the MRI units has passed acceptance testing and the other two are in the build stage. The customer submits a change request to implement a fourth MRI unit. Which technique would produce the most accurate delivery estimate for the additional unit? A. Analogous B. Bottom-up C. Parametric D. Relative 171. In a retrospective meeting, Alan, the junior of the team is enthusiastic about all the topics being discussed and takes notes of everything, while Walter, the senior, interrupts continuously, shows no interest and complains about not being able to continue with code-development. How would you describe the situation? A. Alan is a Learner and Walter is a Prisoner B. Alan is a Explorer and Walter is a Vacationer C. Alan is a Shopper and Walter is a Rebel D. None of the above 172. A project manager has made compliance-related changes by adopting a new project delivery approach. During external validation, an audit revealed that some of the component work did not conform to the organization's standards. What should the project manager have done? A. Executed only compliant deliverables. B. Clarified interpretation of compliance guidelines. C. Translated business requirements to design. D. Researched regulations in the public sector. 173. A project manager is working on a new compliance project that is different from regular projects as it will involve multinational partners and several government departments. The project will result in the adoption of new standards and procedures. What must the project manager do from the onset? A. Ensure that the business requirements are defined and met B. Ensure solution design is available from the start of the project C. Ensure execution and handover are done effectively D. Ensure the interpretation of compliance guidance and validation 174. A project team recently experienced delays due to noncompliance which have made the project schedule less flexible and increased risk to cost and poor quality. The team is brainstorming about ways to avoid this in future. What is most far-reaching implication for the organization if this noncompliance is not resolved? A. Business survival and continuity B. Unhappy clients or end users C. Slower response to system D. Fines and penalties 175. A large infrastructure organization is reviewing and standardizing project tools and techniques. Regarding the question “When should the decision be made to take corrective action?” which process group can this question come from? A. Initiating Process Group B. Planning Process Group C. Executing Process Group D. Monitoring and Controlling Process Group 176. Some of the stakeholders of a project in a financial institution are worried about the project not being well managed. And ask project manager to produce monitoring Which knowledge area out of 9 knowledge areas project manager can skip from Monitoring and Controlling? A. Project Procurement Management B. Project Integration Management C. Project Communication Management D. Project Human Resource Management 177. A project leader is on a very complex project, which is in the middle of a sprint. A stakeholder comes across the project manager and informed them about a requirement and proposed to call a meeting to inform team members. What should the project manager do? A. Call a meeting with the stakeholder and a team member B. Ask the stakeholder to come to the war room and explain the requirement to the team C. Call a meeting with the stakeholder an all team members D. Add to the product backlog to be treated in next iteration 178. A product owner has requested to incorporate embedded functionality for the patient portal in the next sprint. The team decided to perform an Affinity Estimation session to define how much value will be delivered. Which role is responsible to facilitate the session? A. Product Owner B. Scrum Master C. Developer D. Stakeholder 179. Exposing team members to behavioral models helps to obtain a good level of maturity and allows the team to work well together. Using the DISC behavior model, what characteristics best describe the Influence Style? A. Direct, result oriented, firm, can be seen as intimidating B. Outgoing, enthusiastic, optimistic, can be seen as overly optimistic C. Accommodating, patient, humble, tactful, Can be seen as indecisive D. Analytical, reserved, precise, can be seen as halting process 180. A project manager is in a successful automotive company with high quality standards. The project manager needs to ensure that they create a high-quality WBS. Which of the following is not a key characteristic of a high quality WBS? A. Deliverable oriented B. Hierarchical C. The 100% rule D. Customer focused ANSWERS 1. Solution: B. Encourage the new stakeholder to convene with the product owner to review pertinent information. In agile environment, the product owner must work closely with stakeholders, teams, and customers to define the product direction. The project manager's next steps should be to encourage the new stakeholder to convene and engage with the product owner to review pertinent information. The other answer choices are incorrect. These options do not address the key stakeholder which is the product owner in this case. 2. Solution: A. Described the user story in more detail In order to avoid this situation, the user story should have been made available in detail to capture the requirement for foreign credit card acceptance. The other answer choices are incorrect they would not have helped the project manager avoid the situation, rather they are iterative steps in an agile approach. 3. Solution: B. Force If there is a conflict it is the customer's needs that must be prioritized. Everyone in the team must have the same goal: deliver value to the customer. Hence, Force is the right technique. The plan can't afford different solutions that do not deliver value to the customer. 4. Solution: C. Meet with stakeholders to agree on a communications management plan In a hybrid environment, communication problems are the responsibility of the project manager to solve and not the stakeholders. All other options are also valid but on priority communication management plan with stakeholders has to be agreed upon. 5. Solution: C. The team that completes the most stories selected from the sprint backlog. As per Agile, team that completes the most stories from the backlog delivering working software is the performer team. Performance must not be measured just on velocity or story points. 6. Solution: B. Challenge the team to find new ways to achieve higher levels of performance to improve the situation Agile practices always encourages the team to find new ways of working to achieve higher levels of performance. Hence this option is correct. As the team is newly formed, the Project lead is expected to educate the team members on new agile practices with the help from the Scrum Master and not allow the team members to analyze the situation on their own. Hence this option is incorrect. As the team is new, speaking to the individual team members on what they would like to do is inappropriate It is for the Project lead and the Scrum Master to provide enough guidance and motivation to the team members. Hence this option is incorrect. It is expected for the Project lead to go with solutions to the senior management and seek their recommendations. Hence this option is incorrect. 7. Solution: C. Inform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity The team member approaching the Scrum Master is the correct choice, as it is the role of the Scrum Master to make sure that any obstacles and impediments are removed from the team. The Scrum Master should now make sure there is no further loss of productivity to the team through any means in the future. The Scrum Master does not have the authority to discuss the change directly with the stakeholder in Agile Projects. It is the team that is responsible for requirements. Hence this option is not correct. The team member should not be involved in advising the stakeholder on any kind of process related ideas like providing the new requirements directly to the change control board [CCB] or sending the requirements directly to the Project Manager. Hence these two options are incorrect. 8. Solution: B. Determine cross-dependencies and plan a spike in the next sprint Within a complex program/project it’s critical to identify external and internal dependencies and keep a track on them accordingly which is the top priority and focus for the Project Manager. Failure to do so can result in not meeting the objectives. Determining the risks and identifying a resolution, informing stakeholders about the delay, addressing the gaps in communication management are something that can be done in parallel. 9. Solution: B. Resource histogram A resource histogram, by definition defines resource requirements over time. Resource assignments take place once the need for resources has been determined and available resources have been identified. The Project organization chart and Responsibility assignment matrix will not identify the need for resources nor for what duration are they needed. 10. Solution: D. Manage Quality PMBoK Sixth Edition Chapter 8 Section 8.2 states: "Manage Quality is the process of translating the quality management plan into executable quality activities that incorporate the organization's quality policies into the project. The key benefits of this process are that it increases the probability of meeting the quality objectives as well as identifying ineffective processes and causes of poor quality. Manage Quality uses the data and results from the control quality process to reflect the overall quality status of the project to the stakeholders. This process is performed throughout the project. Manage Quality is sometimes called quality assurance, although Manage Quality has a broader definition than quality assurance as it is used in non-project work. In project management, the focus of quality assurance is on the processes used in the project. Quality assurance is about using project processes effectively. It involves following and meeting standards to assure stakeholders that the final product will meet their needs, expectations, and requirements. Manage Quality includes all the quality assurance activities, and is also concerned with the product design aspects and process improvements. Manage Quality work will fall under the conformance work category in the cost of quality framework. The Manage Quality process implements a set of planned and systematic acts and processes defined within the project's quality management plan that helps to: Design an optimal and mature product by implementing specific design guidelines that address specific aspects of the product, Build confidence that a future output will be completed in a manner that meets the specified requirements and expectations through quality assurance tools and techniques such as quality audits and failure analysis. Confirm that the quality processes are used and that their use meets the quality objectives of the project and improve the efficiency and effectiveness of processes and activities to achieve better results and performance and enhance stakeholders’ satisfaction. The project manager and project team may use the organization's quality assurance department, or other organizational functions, to execute some of the Manage Quality activities such as failure analysis, design of experiments, and quality improvement. Quality assurance departments usually have cross-organizational experience in using quality tools and techniques and are a good resource for the project. Manage Quality is considered the work of everybody—the project manager, the project team, the project sponsor, the management of the performing organization, and even the customer. All of these have roles in managing quality in the project, though the roles differ in size and effort. The level of participation in the quality management effort may differ between industries and project management styles. In agile projects, quality management is performed by all team members throughout the project, but in traditional projects, quality management is often the responsibility of specific team members" The distractors are correct. The correct answer is: "Manage Quality" 11. Solution: B. Stop the release of the deliverable to the customer If a new quality change has been approved after the project deliverable is ready, the deliverable will not meet the new quality requirements and should not be released to the customer. The new quality criteria should be used for all deliverables, not only future ones. The risk register would contain risks associated with quality; however, a quality change has been approved. The question did not state a new quality risk has been identified. Updating the project management plan would require an approved change, which may be the case here, but that is not the first thing the project manager should do. 12. Solution C. Nominal group technique expands on brainstorming with voting to rank ideas for prioritization or further brainstorming. It enhances understanding with all individuals, who then vote privately to prioritize the ideas. An affinity diagram classifies ideas but not prioritize them. Multicriteria decision analysis will rand decisions with predefined criteria, which may not exist. 13. Solution: A. Forming The earlier a project manager instills motivation during the forming/develop team stage, the team can collaboratively build on the positive foundation. Forming sets the tone for the duration of the project. Storming phase, team members may be busy with their internal conflicts. Norming Phase, team members may settle down with their conflicts and busy with their priorities of work. Performing phase, the team will perform and deliver the projects. So, it is better to put the focus on increasing team motivation at forming phase. 14. Solution: A. Maintain a laissez-faire leadership style with the team, but use a transactional style to give firm guidance to the graduate The graduate is in need of authoritative and stable guidelines and positive feedback while the team must not lose their autonomy to maintain motivation. Collaborative servant leadership approach is used for increasing team gel and motivation. Without mentor it is difficult to learn through an insensitive immersion. Asking three team members to share the mentor role is not an effective way. 15. Solution: C. Systems thinking The Project manager by looking at the connections between the different hindrances to have a full understanding of the picture used system thinking. Total quality management (TQM) is the continual process of detecting and reducing or eliminating errors in manufacturing, streamlining supply chain management, improving the customer experience, and ensuring that employees are up to speed with training. The Pareto Principle states that 80 percent of a project's benefit comes from 20 percent of the work. Or, conversely, that 80 percent of problems can be traced back to 20 percent of causes. Pareto Analysis identifies the problem areas or tasks that will have the biggest payoff. 16. Solution: D. None of the above Scrum master in agile normally lead like a servant leader. So none of the above is the right answer. 17. Solution: A and E. Risk checklist and diagramming techniques 18. Solution: B and C. Develop a good relationship with the project team and understand the politics and personal interests of the stakeholders. Negotiations, including agreements, require people skills rather than good planning. Although having good Communication and Risk plans as well a clear project schedule may help those are outcomes of the negotiation. Agile is not a silver bullet and it is not always the best option for project delivery. 19. Solution: A and D. Separate the people from the problem and Focus on positions, not interests The most important aspects in negotiations are people, their personalities and interests. Separating the negotiations on the source of conflict rather than personal interests is the main success factor. Delegating is a sign of weakness and although playing politics is an important aspect of project management, the project should put the projects scope above politics. 20. Solution: D. Took action based on the senior management's power to act Use the Law of Authority to establish your own credentials or credibility early in the negotiation process. When establishing your approach or explaining how or why decisions have been made, link your position to known, respected sources in order to garner credibility. 21. Solution: B. Acted in a manner that was consistent in the use of words and actions Law of Commitment and Consistency can be called “Get the other person saying ‘yes,’ immediately.” This occurs when one party asks the other side to make a number of “small” decisions that lead to only one obvious conclusion: to accept the general concession. The approved project charter formally initiates the project. A project charter may still be used to establish internal agreements within an organization to ensure proper delivery under the contract. The Project Manager has to negotiate project agreements. Project Manager has to persuade the Stakeholders and achieve acceptance. The correct answer is: "Acted in a manner that was consistent in the use of words and actions." The Distractors are accepted. 22. Solution: C. Meet with the product manager to create a backlog with the missing requirements. Working in a hybrid environment requires team collaboration to define stories and prioritize them. The project manager should work with the product manager to create a backlog for the missing requirements to minimize project timeline delay. The other answer choices are incorrect. Canceling the project will derail all efforts thus far and a budget increase may not be feasible. 23. Solution: A, C, E and F. Implement regular status reporting, develop a highly detailed project management plan, Expand senior manager involvement and Implement frequent quality reviews. 24. Solution: D. None of the above * Explorers – Are eager to discover new ideas and insights. They want to learn everything they can about the iteration/release/ project. * Shoppers – Will look over all the available information and be happy to go home with one useful new idea * Vacationers – Aren’t interested in the work of the retrospective but are happy to be away from the daily grind. * Prisoners – Feel they have been forced to attend and would rather be doing something else. 25. Solution: A and C. Traceability improves but requirements will likely remain fragmented and some of these requirements may not be completed as part of the project itself. Since the regulatory changes are multiple dimensions (technical, legal, organizational, control) that most likely cannot be managed in a single branch of the WBS. 26. Solution: A. Acts as coordinator for the resources and activities Since the team has decided to include compliance as inputs, it is assumed that project environment is agile based and so, the best action for the Project Manager is to determine the necessary approach and support the team as coordinator. Hence this choice is the correct answer. In an agile environment, the project manager is a servant leader involved in removing obstacles and impediments for the team, and the team performs all development activities. Hence all other options are incorrect. 27. Solution: D. Define and share work agreement with the needed team to coordinate activities effectively An important part during planning phase is indicating how others may interact with the team and define this in a working agreement. Making the team learn or asking the project sponsor to assign resource will lead to delays and/pr deterioration of quality of work. 28. Solution: B. Agile takes time to implement, but is more suitable to implement agile and then move to hybrid 29. Solution: A. At the start of the project The requirements management plan should be implemented at the start of the project not in the planning phase or prior to executing or after customer. 30. Solution: D. Discuss this with the team to find options to mitigate the risk The correct answer is to discuss this with the team to find options to mitigate the risk. The project is critical to the organization; therefore, the team should explore mitigation options. Risk mitigation is a risk response that involves decreasing the probability or impact of a threat. The other answers are incorrect because the team should consider all options before making decisions. Hiring additional resources for the team could potentially increase the project cost and does not guarantee decreased schedule impact. Being that the project is critical to the organization, adding the risk to the risk register for reviewing and monitoring does not address the issue thoroughly and is a slow process. Escalating the risk should only be done if the team fails to find an acceptable solution, if the threat is outside the scope of the project, or if the proposed response would exceed the authority of the project manager. 31.Solution: A. Discuss the resource allocation with the team member's functional manager. The project manager should identify the issues and collaborate with relevant stakeholders to resolve them. The functional manager would be the appropriate stakeholder to discuss resource allocation. The other answer choices are incorrect because they do not focus on the project manager seeking a resolution for the issue, but rather suggest team member removal and responsibility deflection. 32.Solution: A. Update the communications management plan. If there is a change in project stakeholders, the communication plan must be updated immediately. This is what the senior project manager should do next since the customer's project manager has resigned. This way, the customer's replacement project manager will be aware of how to communicate and the key stakeholders will be kept up-to-date on new information. 33.Solution: D. Arrange a virtual team kickoff meeting with the stakeholders. The appropriate response for the project manager, in this case, is to use virtual spaces to make a geographically distributed stakeholder team work together. It is important that all key stakeholders are present because kickoff meetings are held at the outset of a project to formally set expectations, gain a common understanding, and commence work. For this type of project, this will be an ongoing problem and thus it is important that the project manager establishes early on so that geography will not be an issue. Holding the kickoff meeting with available stakeholders is not the correct choice since important information will be addressed and the project can get started. Further, updating others later will only delay the project if they are critical stakeholders. This practice may be expected for all meetings moving forward and does not set a good precedent. Postponing the kickoff meeting is incorrect as this will be an ongoing problem that will not solve itself. It will also delay the project and continue to impact the project. As the stakeholders travel extensively, getting their time for one-onone sessions may not be possible. Even if a one-on-one meeting is possible, it does not replace a kickoff meeting, which is intended to include all key stakeholders. 34.Solution: B. Conduct procurement performance reviews on a regular basis with all contracted vendors to ensure that products and services are all delivered or will be delivered on time and as per the agreed-upon contract. Conducting regular formal reviews is the most proactive option that the project manager can take. This will ensure that quality of the delivered/rendered products and services are as per expectations and in accordance to the signed procurement contract. 35.Solution: D. By reviewing the stakeholder engagement assessment matrix Stakeholder engagement assessment matrix supports comparison between the current engagement levels of stakeholders and the desired engagement levels required for successful project delivery and will be the best tool to assess the stakeholders' current engagement levels. The other answer choices are incorrect. Communications management plan establishes how, when and by whom information of about the project will be administered and disseminated, and doesn't help in assessing the stakeholder engagement level. Issue log is where all the issues are recorded and tracked. It doesn't have stakeholder engagement details. Getting key stakeholders to submit a signed declaration doesn't help in assessing the stakeholders' engagement level. 36.Solution: C. Schedule a meeting with the stakeholder and product owner to discuss the request. The project manager should schedule a meeting with the key stakeholder and the product owner so that the concern can be discussed and addressed. The other answer choices are incorrect. The daily standup meeting is for checking the progress of the sprint and addressing the team member's issues/challenges. Issues with requirements are not discussed in this forum. Altering the backlog is also not an option for the project manager. Backlog is owned by the product owner and only product owner is authorized to make changes to it. Cancelling the current sprint would be a drastic action. 37.Solution: C. Involved relevant stakeholders in the project planning The project manager should involve the relevant stakeholders in the project planning. This will address the issue of requirements not captured in the project management plan. The other answer choices are incorrect. Managing expectation from stakeholder will not help in resolving requirements that are not captured during project planning. Developing a change management plan will not help in resolving requirements that are not captured during project planning. Seeking expert judgement in the project scope design will also not help to get correct requirements captured during project planning. 38.Solution: A. Analyze changes with the team and go through the formal change control process. Before submitting a formal change request, the project manager should analyze the impact of the change with the team. 39.Solution: B. Submit a change request to the Change Control Board (CCB) for final approval. Legislative compliance requirements must be met. Changes pertaining to compliance require the project manager to submit a request and seek approval from the CCB. The other answer choices are incorrect because they do not suggest that the project manager submit a change request or deny the change required by the latest legislation. 40.Solution: C. Register the delay in the issue log and develop an immediate action plan. This is a clear issue and the project manager should document it in the issue log, and then the action plan should be created. The other answers may be required but should come after the action plan is created. 41.Solution: C. Review the project's communications management plan with the project team and update as necessary. The stakeholder was acting on unofficial information. The communication management plan, if created properly, will avoid this situation and ensure that the correct messages are sent to different stakeholders. After addressing the short-term issue, the project manager should address it long-term by reviewing and updating the communication management plan. The other answer choices are incorrect. Issuing the memo and including the stakeholder in the project status mailing list will not solve the incorrect unofficial information from being sent out. Revising the status report is not an appropriate response because the project is still on track. 42.Solution: A. understand the reason for the disagreement and submit a change request to the change control board if appropriate. Test criteria should be aligned and agreed upon by stakeholders, and change request should be made if necessary. It is important for the project manager to understand the reason for the disagreement and submit a change request to the change control board if appropriate. The other answer choices are incorrect. Making a plan to change the test criteria needs to be approved by the change control board before it can be implemented. Keeping the validation test criteria unchanged or going ahead with the original test criteria may affect the quality of the new product. 43.Solution: B. Review and update the stakeholder register. The stakeholder register contains details of the project's stakeholders and provides an overview of their project roles and their attitude toward risk on the project. The project manager should review and update the stakeholder register and begin to build rapport. The other answer choices are incorrect. The resource manager is an individual with management authority over one or more resources, and will not know all project stakeholders; asking for expert judgment of the sponsor will not help the project manager learn about the project stakeholders; updating the communication plan will not allow the project manager to familiarize themselves with the project stakeholders. 44.Solution: B. Conduct a workshop with the project steering committee to review the new regulation and find a resolution. The project manager needs to work with the project steering committee to find a resolution and ensure compliance with the new regulation The other answer choices are incorrect. Proceeding without addressing the new regulation will result in non-compliance upon project completion. The project manager should not ask for new funds or leverage the contingency reserve without getting the approval of the change control board. 45.Solution: C. Analyze all change requests raised during each country's deployment at a global level prior to implementation. Analyzing all change requests raised during each country's deployment at a global level prior to implementation would have helped avoid this situation. The other answer choices are incorrect. Several countries are deploying the same solution, any impact analysis must take into account all the countries and not only the one which raises the request. Changes are acceptable within the project, but they must be managed appropriately. Getting the country to pay for any change request is not the appropriate action. 46.Solution: D. Consult the terms and conditions in the vendor contract. Since there is a contractual disagreement, the project manager should check the contract documentation to confirm the terms and conditions. 47.Solution: C. Ensured the final product is transitioned to a different group or organization to take care of the software during its life cycle. As the project received administrative closure, the project manager should have ensured that all deliverables, including the new software program, be handed over to a different group or organization that will operate, maintain, and support it throughout its life cycle. The other answer choices are incorrect. Asking the team members to stop answering or addressing questions or including the activity to support the tool after production release are not a part of the project closure activities. Communicating to the rest of the organization formally is done only after the project closure is obtained. 48.Solution: B. Analyze the impact of the legislative changes. Proactive monitoring of external situations/happenings is key to embracing changes (which are mandatory or optional) for project success. The project manager should analyze the impact of the proposed legislation. This will be needed by the product owner to prioritize the backlog and raise change (if needed). The other answer choices are incorrect. Focusing only on completing the activities as per backlog will be a risk to the project. If the proposed legislation goes ahead, the project has the risk of being non-compliant. Without proper change approvals, the project manager can't instruct the team to proactively initiate change in the next sprint. Without proper scope change approvals, the additional budget will not be granted. 49.Solution: D. assess the impact of this replacement, and make further resource adjustments where necessary. The project manager should assess the impact of this replacement, and make further resource adjustments where necessary to ensure the project timelines are not affected by this replacement. The team should be fully independent, and be empowered to make their own decisions on their team membership. The other answer choices are incorrect. The options to raise this stakeholder concern as a risk and seeking their functional manager's guidance do not empower the team and do not ensure successful project delivery. The option to reverse the decision would also be counterproductive to the earlier decision taken and further disempower the team. 50.Solution: A. Discuss this delay at the next team standup meeting. The agile team is empowered to discuss and agree on actions to address delays. The only correct option is to discuss this at the next team meeting. The options on requesting additional resources, excluding functionality and even replacing team members should be discussed and agreed as a team first. 51.Solution: C. Ask the team to re-assess their effort estimates in the iteration planning session. The team learns from previous iterations how to do things better. The actions to address any shortcomings are taken as part of the next planning session. The next action should be to assess whether the team now has sufficient experience to perform the tasks within the planned timeframe for the next iteration. The other answer choices are incorrect. The options to seek additional training and reprioritize the product backlog may not affect the team's ability to complete in the next iteration. The option to ask the sponsor to approve delayed timelines is also unnecessary if the team assesses that it now has the necessary experience to complete the next iteration within schedule. 52.Solution: D. Ask project teams A, B, C, and D to identify critical dependencies, risks, and major milestones. Identifying risks early in a project is a critical success factor. With multiple project teams working together, it's important for the project manager to identify dependencies, risks, and milestones and their impact on different projects' critical paths. The other answer choices are incorrect. Hosting a team-building event and having a metrics dashboard are good to have activities, but they are not a priority compared to identifying critical dependencies. Projects would be expected to have different priorities, but project teams should collaborate toward a common outcome for the program. 53.Solution: A. Why is this project being done? Answering why the project is being done would explain the purpose of the project. The other options are less of a priority for addressing the project vision and purpose. 54.Solution: C. Update the risk register and review risks with the team on a regular basis. The correct answer is to update the risk register and review risks with the team on a regular basis. The project manager should update the risk register and review the risks regularly with the team to ensure the mitigations are in place. The other answer choices are incorrect because it is not possible to eliminate all risks; discussing risks in retrospectives and daily standups is not appropriate as those meetings are not meant to discuss risks regularly. 55.Solution: D. The project manager. The project manager is responsible for removing impediments and creating a conducive work environment. A critical role for the project manager is to maximize delivery by removing impediments to their progress. This includes solving problems and removing obstacles that may be hampering the project team’s work. By solving or easing these impediments, the project team can deliver value to the business faster. Projects can be challenging from the perspectives of technical challenges, environmental influences, and interpersonal interactions. Supporting project team members through problem solving and removing impediments builds a supportive culture and leads to a trusting and collaborative environment. 56.Solution: B. Meet as a group to assess what is possible to complete by the new timelines. The project manager should have the team assess the situation to determine whether the project can be delivered earlier. The other answer choices are incorrect. Committing additional resources depends on the team's risk and action assessments; telling the client it is not possible without assessment of the new timeline is not the best strategy; and conducting a retrospective meeting does not help with the current client request. 57.Solution: B. Remind the senior team member to adhere to the team's working agreement. The project manager should remind the senior team member of the team's working agreement and ensure they stick to it. The other answer choices are incorrect. The project manager should first try to resolve this situation with the senior team member. Having other team members cover is also not sustainable and affects team dynamics. Removal requests are a form of escalation, and is done only if the Project Manager is unable to resolve the current issue. 58.Solution: B. Identify the competency gaps and collaborate with the HR manager for options. The best option to resolve the situation is to work with the HR manager to identify the gaps and relevant solutions. All the other options are important but do not work towards a solution for the current situation. 59.Solution: B. Hold an orientation to ensure both parties share the same understanding of project goals and requirements. The best option is to hold an orientation or kick-off meeting where all parties have the same understanding of the work goals, requirements, taxonomy and the general approach, including timelines. It is important to integrate such key partners in your team by providing information, criteria, expectations, and critical items, responsibilities to avoid future issues or impasses. The other options to delegate or retain key decisions are both subjective on the specific scenario and may not be correct in all scenarios. The option to submit the communication matrix to have all parties known is not always required and is not as important as having the orientation meeting. 60.Solution: A. Speak to the team member, understand the problem, and ask the team member to work on corrective actions. Understanding and showing empathy for a disengaged team member is very important for a project manager. The project manager should speak to the team member, understand the problem, and ask them to work on corrective actions to ensure engagement. The other answer choices are incorrect. These options suggest the project manager should take action without first understanding the issue the team member is experiencing. 61.Solution: C. Perform a stakeholder analysis and prepare a communications management plan. The project manager should perform stakeholder analysis, identify all the stakeholders as well as their communication requirements, and prepare the communications management plan. The other answer choices are incorrect. Meeting with all stakeholders face-to-face on weekly basis is a good idea, but it may not be practical. Also that may not be the appropriate method and frequency for all stakeholders. Reviewing historical data is good practice and can guide the project manager, however, project manager will still need to identify all stakeholders of this project & each stakeholder's communication. requirements/preferences. 62.Solution: A. Help the project sponsor understand the different tools and techniques available and why this one was selected. Each agile practitioner is empowered to train and mentor stakeholders in the organization to help them understand the process and participate effectively. The other answer choices are incorrect. A project sponsor cannot be thought of as an impediment on an agile project. This would break the fundamental trust model. It is against the agile principles of selforganization and servant leadership to dictate process without any buy-in from the teams doing the work. Pausing the project is incorrect because it breaks agile process and implies that the entire backlog of work has to be approved ahead of time. This would effectively create a waterfall project without agility or thoroughness. 63.Solution: D. Work with the legal department and other applicable departments to review the processes that support the project delivery. The project manager should work with the legal department and other applicable departments to review the processes that support the project delivery. Servant leaders facilitate and remove organizational impediments and coach teams in agile. The other answer choices are incorrect. Advise senior management..." This option will cause further delays in the project given the time it will take to introduce agile practices to the entire organization. Furthermore, the approach does not focus project effort. "Continue with organizational..." In this case avoiding the issue will not result in resolving the issue which will cause more negative impacts on the project. "Inform the customer..." Transference of responsibility for the issue to the customer is inappropriate as the Project Manager must facilitate and remove obstacles not other stakeholders. 64.Solution: C. Help the team members collaborate and resolve their problem together. Conflict between team members should be dealt with among themselves. The opinions of the team members should be valued and made transparent in the process. The project manager should encourage them to collaborate to solve their issue and should intervene if the conflict cannot be resolved. The other answer choices are incorrect because they do not directly help resolve the conflict. Calling for separate meetings, understanding the impact of the conflict, and discussing in a retrospective meeting delay resolution and don't encourage the team members to unite. 65.Solution: B. Coach the product owner on how to prioritize product specifications. The project manager should coach the product owner on how to prioritize product specifications. Project managers should act as a facilitator, becoming impartial bridge-builders and coaches, rather than making decisions for which others should be responsible. The other answer choices are incorrect. They do not support the idea that the project manager should coach the product owner to fill in missing knowledge gaps. 66.Solution: B. Included the transition plan as a deliverable in the project closing process. The organizational structure would have already been revised as the project manager is currently executing the operations. To enable proper responsibility transfer from the project to the new business function, the recruitment process which is part of transition planning should be included by the project manager at the beginning of the project 67.Solution: A. Ensure team members attend daily standup meetings to discuss the impediments. The project manager should ensure team members attend daily standup meetings to discuss the impediments. Project managers should build their servant leadership skills of facilitation, coaching, and impediment removal. The other answer choices are incorrect. These options suggest documenting the issue and taking action later; extending daily standups which is time-consuming; and escalating the issue and deflecting responsibility to the sponsor. 68.Solution: B. Assessed the internal and external regulatory environments. At the beginning of the project, understand the regulatory requirements based on the type of project and the industry will allow the team to include tasks in the plan geared to meeting the requirements, ensure enough resources are allocated to addressing the requirements and reducing the amount of rework that would result from not doing the assessment. 69.Solution: B. Identify the cause of the morale issue. The new project manager should first gather additional information to identify the root cause of the low morale issue. Hence this option is the correct answer. The other answer choices are incorrect. Increasing the supervisor's level of authority or modifying the role of the supervisor in the project or speaking with the supervisor and updating the project issue log will not improve the senior supervisor's morale. 70.Solution: B. Observe the team members' interactions and talk with them about their complaints before applying a conflict resolution technique. The project manager must first analyze the conflict between the team member before implementing conflict resolution techniques. The other answer choices are incorrect because they promote hiring external resources (agile coach), escalating the issue, and taking action without first assessing the situation. 71.Solution: B. Set expectations with the stakeholders regarding what agile is, the approach, and that they will be seeing a small amount of functionality. Since it is the stakeholder's first time with agile, the project manager should set the stakeholders' expectations on what agile is, the approach (which is that you will deliver the project in small increments that build on all the rest) in the context to what is done 72.Solution: C. Evaluate the issue and apply conflict resolution techniques. Conflict is inevitable in projects, the success of any project manager in managing a team is dependent on how well he manages the conflicts. Conflict resolution has many tools including force /direct or collaborate /problem-solving. The project manager has to evaluate the situation of the given team's matrix and charter to gain insight and use conflict resolution techniques accordingly. 73.Solution: B. Review the team velocity records and observe the team and interactions between the team members. As the new project manager joins the existing team , they should simply observe to understand the dynamics and nature of the existing team. If there is dysfunction, all the more important to observe, and then take action once there is a better understanding of the team. The other answer choices are incorrect. Implementing plans that the project manager is not fully aware of before getting to know the team may have adverse effects; listening to the most vocal team member does not take into account the thoughts of the entire team; and observing the team to remove a member is not the primary goal of the new project manager. 74.Solution: C. Burndown chart, user stories, and retrospective notes The project manager should use the burndown chart, user stories, and retrospective notes for planning the duration of the next release. A burn down chart is a graphical representation of work left to do versus time; user stories provide the customer perspective; and the best predictor of a team's ability to deliver is the velocity from previous sprints, as well as lessons learned (contained in retrospective notes). 75.Solution: C. Give feedback to the project team regarding their good performance in the next project meeting. The project manager should give performance feedback to project team as often as possible, so good work can be enhanced and unacceptable work can be corrected. By providing feedback in the next meeting, the project manager will not delay or withhold feedback like the other answer choices suggest. 76.Solution: D. Develop a responsible, accountable, consult, and inform (RACI) chart. The project manager should develop a RACI chart and share it with project team members and concerned stakeholders. The target is to empower project team members and delegate some project management responsibilities to them to ensure engagement. 77.Solution: A. Speak with the team member to determine the reason for the changes. Understanding the reason for constant changes is the first step the project manager should take in addressing the concerns. Then, the project manager can determine the actions necessary to resolve the conflict. The other answer choices are incorrect. These choices suggest that the project manager should attempt to implement solutions or take action before having an understanding of the issue they are dealing with. 78.Solution: A. Use a RACI chart to facilitate team task accountability. A RACI (responsible, accountable, consult, and inform) chart shows the project resources assigned to each work package. It is used to illustrate the connections between work packages, or activities, and project team members. The other answer choices are incorrect. A Gantt chart shows schedules without assigning responsibility; the sponsors should not need to be consulted if a RACI is in place and agreed; and the WBS does not include the decision-making authority. 79.Solution: A. Assess the best project methodologies for continued business value. Achieving continued business value is more important than choosing to adopt different methodologies. The whole purpose for project management is to execute work that provides identified business value, thus the project manager should assess the best project methodologies for continued business value. 80.Solution: B. Train team members in basic hybrid practices and ensure the team performs coordination meetings. In order for the hybrid transition to be successful, the project manager should ensure team members receive basic training in the hybrid methods being used to strengthen commitment and improve the flow of work. This leads to sound planning and execution in order to deliver features that add value to the customer. The other answer choices are incorrect because they do not address the lack of experience with the new hybrid approach. Training team members is the best way to resolve the issue. 81.Solution: A. Review the organizational process assets (OPAs) with all team members and establish ground rules. Organizational process assets (OPAs) are the plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization. These assets influence the management of the project. The OPAs also include the organization's lessons learned from previous projects and historical information. The project manager should first review the OPAs with all team members and establish ground rules. The other answer choices are incorrect because they either deflect responsibility or happen after ground rules are established. 82.Solution: C. Create a fishbowl window. There are a myriad of tools that project managers can employ to facilitate working with virtual and remote teams. Geographically distributed teams need virtual workspaces. A fishbowl window alleviates lag by providing a long-lived video link that remains open during the workday for a dispersed team. In this way, people can see and engage spontaneously with each other, reducing the collaboration lag otherwise inherent in the geographical separation. 83.Solution: B. Identify the root cause for why the team member cannot complete the assigned work and remediate. Interpersonal and team building skills would need to be applied on this scenario based on the fact the team member is new and the project manager should determine why the team member cannot complete the tasks. The project manager should identify the root cause for why the team member cannot complete the assigned work and remediate. The other answer choices are incorrect. These options suggest the project manager take other actions before understanding the root cause of the issue. 84.Solution: A. Make sure the right tools for virtual collaboration are available for the team. The project manager Ensure virtual team collaboration tools are available is the best way and more economical to make sure the needed collaboration takes place. The other answer choices are incorrect because they suggest colocation or adjusting schedules, both of which may not be feasible moneywise and timewise. 85.Solution: D. Conduct individual and team assessments on their preferred learning method(s). The project manager should conduct individual and team assessments on their preferred learning methods as different project team members will need different training. Individual and team assessment tools give the project manager and the project team insight into areas of strengths, weaknesses, and team preferences. These tools help project managers interact with the team and can provide improved understanding, trust, commitment, and communications among team members and facilitate more productive teams throughout the project. 86.Solution: A. Review the project's benefits management plan with the product owner. "Review the project's benefits management plan with the product owner" is the best choice as a benefits management plan describes how and when the benefits of the project will be delivered and how they will be measured. "Escalate the matter..." is not the best action without looking into the benefits management plan. "Prioritize the project backlog..." This is not an option as it is the last sprint and does not help in the given situation. "Ask the product owner to terminate..." Product Owner alone can't decide to terminate the project, but this action is not the correct option for the given situation. 87.Solution: B. Stakeholder engagement plan The project manager should update the stakeholder engagement plan to ensure proper involvement and reflect changes to the stakeholder community when there are changes to the organization structure or within the industry; when new individuals or groups become stakeholders, current stakeholders are no longer part of the stakeholder community; or the importance of particular stakeholders to the project’s success changes. The other answer choices are incorrect. Communication management plan, risk management plan, and resource management plan do not benefit this scenario. 88.Solution: B. Use the next retrospective to evaluate the process's effectiveness, and determine if changes are needed. The first step for the project manager is to understand the nature and cause of the problem. Using project retrospectives to evaluate project process with the team and come up with better solutions is a good way to implement continuous improvement, as well as keep the team motivated and engaged. The other answer choices are incorrect because they describe action taken to implement solutions, which are premature. 89.Solution: A. Schedule a project team meeting to understand the conflicts. The project manager needs to understand the conflicts and should engage the team in identifying them and developing solutions. The other answer choices are incorrect. Advising the team to work harmoniously, updating the resource management plan, and team building activities does not get to the root of the conflicts nor do they address the issue. 90.Solution: D. Oversee a single document registry and change control system that both teams use. Document control is an important part of project change control. A single document registry will ensure that there is version control and all the documents are accessible to all the stakeholders from a single repository. The project manager should oversee a single document registry and change control system that both teams use. The other answer choices are incorrect. Multiple document registry systems will cause inconsistency, confusion, and delays. It is not the sponsor's role to maintain a document registry. 91.Solution: B. Work with the team leaders to update the required project reports. The first step to address missing or poor documentation would be to correct the deficiency. Then, the project manager should work with the team to ensure that documentation procedures are followed and required project reports are updated. The other answer choices are incorrect. Discussing the problem with the sponsor is not correct, as it is within the project manager's authority to remedy. The project manager does not need to stop all other project activities to address this issue. Project documentation should be updated and knowledge should be transferred throughout the project, not just at the final stage of the project. 92.Solution: B. Engage with the team members to understand their challenges. Engagement with virtual team members is critical to know the issues and challenges team members are dealing with. The project manager can assist to resolve these issues once they are aware of them. The other answer choices are incorrect. They do not assess the problem initially. These steps can be taken after the project manager understands the underlying issues. 93.Solution: A. The deliverable has been approved and value has been confirmed. When the deliverable has been approved and value has been confirmed, this confirms that project the project has met its objective and benefits have been achieved. The other answer choices are incorrect. There is no formal validation. They mention that the deliverable solved the issues, but there is no confirmation of the benefits. 94.Solution: D. Ensure that the necessary health and safety requirements are met in the definition of done (DoD). It is important for the project manager to ensure that the necessary health and safety requirements are included in the DoD and that the project deliverable meets these requirements. The other answer choices are incorrect. Providing the customer with adequate documentation, sending the issue, and designing policies do not specifically ensure that health and safety requirements will be met. 95.Solution: B. Engage the change control board (CCB) to assess possible impacts to the project. It is necessary for the project manager to be proactive in assessing the impact of the policy and addressing the change control board to effect the required changes. This will ensure that the project is completed according to the new schedule. The other answer choices are in correct. The project manager has very little influence of decisions of the government; moving forward with the project with the delay is not appropriate in response to the client; assigning a new completion date is beyond the control of the project manager. 96.Solution: C. Engage team members to understand their doubts and get their buy-in. The scenario clearly indicates their is lack of team member buy-in. Team members either do not see the justification for the project, are uninformed, or feel threatened by the project outcomes. It is important that the PM engages the team members and ensures their buy-in. The other answer choices are incorrect. They do not address the issue of doubt amongst the team members that is affecting project output. 97.Solution: D. Throughout the project life cycle Project managers should actively engage stakeholders throughout the agile project lifecycle. Stakeholders should be engaged at the start and end of a project, and should be aware of issues and challenges encountered during the project. The other answer choices are incorrect. These options suggest stakeholders should only be involved during a certain part of the project instead of throughout the project lifecycle. 98.Solution: C. Develop estimations with the team and explain the assumptions to the client. Due to the lack of historical data, estimations must be created. The project manager should develop estimations with the team and explain assumptions to the client. The other answer choices are incorrect. They do not provide a way for the project manager to handle the situation where estimations and assumptions must be made in a transparent way. 99.Solution: B. Ensured that updated project information is always accessible to all stakeholders It is imperative that stakeholders have updated project information that is accessible. This transparency is necessary to ensure all involved are well aligned about the product outcome. The other answer choices are incorrect. Waiting for the stakeholders to be present or to approve, or meeting with them individually does not avoid disagreement and may cause unnecessary delays. 100. Solution: B. Remind team members that, without an approved change request, the focus should be on the agreed scope. Any changes to already approved project plans must go through the change management process first. Gold plating is not acceptable by PMI standards. The other answer choices are incorrect. Although the project manager is excited about the great opportunity, they cannot approve and implement the change without following the correct procedures to meet the contract requirements. 101. Solution: C. Assess the impact with the functional manager to inform key stakeholders about mitigation plans and seek approval. The project manager should collaborate with the functional expert to agree on the mitigation plan and seek approval from key stakeholders. The other answer choices are incorrect as they suggest abandoning or trying to fix and use the old system, without first assessing the situation. This question and rationale were developed in reference to: PMBOK Guide Sixth Edition (2018) PMI/PMI/Chapter 11: PROJECT RISK MANAGEMENT/445 [Item 11.5.2.6 CONTINGENT RESPONSE STRATEGIES Some responses are designed for use only if certain events occur. For some risks, it is appropriate for the project team to make a response plan that will only be executed under certain predefined conditions, if it is believed that there will be sufficient warning to implement the plan. Events that trigger the contingency response, such as missing intermediate milestones or gaining higher priority with a seller, should be defined and tracked. Risk responses identified using this technique are often called contingency plans or fallback plans and include identified triggering events that set the plans in effect.] 102. Solution: B. Schedule regular sessions with the customer to explain the reports and address feedback. The project manager needs to understand why the customer is escalating even though he is receiving the reports. The best way to address this situation is to schedule regular sessions with the customer to receive feedback and provide more details. The other answer choices are incorrect. These options do not address understanding the main issue the customer is having with project performance, but instead promote agreeing on release dates, sending documents, and involving the technical leader. 103. Solution: D. Hold a session to review the deliverable in detail. In order to prevent this situation in the future, the project manager should hold a session to review the deliverable in detail. It is important to clarify the scope and have stakeholder buy-in. The other answer choices are incorrect. Discussing the benefits with the client occurs in the initial stages; ensuring there is a product backlog does not address the misalignment in requirements; and providing examples of other similar projects does not prevent an issue because each project's deliverables are unique. 104. Solution: C. Engage a subject matter expert to check if the requirements are relevant to the project. The project manager should engage subject matter experts to provide expert judgment to check if the requirements are relevant to the project. The other answer choices are incorrect. Assigning sufficient budget is premature; regulatory requirements cannot be avoided and the project must comply; escalating concerns to the sponsor without first trying to resolve the issue is not good practice. This question and rationale were developed in reference to: PMBOK Guide Sixth Edition (2018) PMI/PMI/4/4.1.2.1 EXPERT JUDGMENT [Item Expert judgment is defined as judgment provided based upon expertise in an application area, Knowledge Area, discipline, industry, etc., as appropriate for the activity being performed. Such expertise may be provided by any group or person with specialized education, knowledge, skill, experience, or training.] 105. Solution: D and E. Assess the impact and Communicate the impact with key stakeholders. In any new and unknown situation, the first thing to do is to assess impact and keep the stakeholder of appraised of any impact. The project manager should assess the impact of the process and communicate with key stakeholders. The other answer choices are incorrect. They may occur after the impact is assessed and the stakeholders are made aware. 106. Solution: D. The attendance list is evidence that risk review meetings were held with the appropriate project team members. The correct answer is the attendance list is evidence that risk review meetings were held with the appropriate project team members. Risk review meetings should be held regularly and attended by appropriate team members as they can contribute adequately to risk identification, assessment, and mitigation. The attendance list is important and reveals evidence of appropriate attendees. The other answer choices are incorrect. A lessons learned register documents a complete phase or project. Knowing the number of attendees does not specify that the appropriate members were in attendance. Attendance at project risk review meetings is not optional for key attendees. 107. Solution: A. Ensured that compliance requirements were documented. It is important that the project manager consider all potential compliance, regulatory and safety requirements at the beginning of the project to ensure the project stays on track, even if the project does not appear to have any. Maintaining these requirements will minimize rework and keep the project on schedule. The other answer choices are incorrect. Engaging stakeholders and hiring a compliance consultant will still require the project manager to ensure that the compliance requirements are captured; creating templates to document compliance is after the fact and does not prevent noncompliance. 108. Solution: C. Achieve the project objective for a win-win outcome. The ultimate goal of a project is to achieve project objective and for a negotiation with a supplier should be a win-win, which makes achieving project goal for a win-win outcome the key. 109. Solution: B. Develop and approve the project charter jointly with the product owner and the project sponsor. Project partnering is a method of transforming contractual relationships into a cohesive, cooperative project team with a single set of goals and established procedures for resolving disputes in a timely and effective manner. The project manager should have developed and approved the project charter jointly with the product owner and project sponsor from the beginning to avoid the conflict. The other answer choices are incorrect. They do not promote project partnering and a collaboration between both parties. This question and rationale were developed in reference to: PMBOK Guide Sixth Edition (2018) PMI/PMI/4.1/75 [Item] | Project Management: A Managerial Approach, 8th Edition (No Date) Jack R. Meredith and Samuel J. Mantel Jr.//4/ [Item commitment to partnering, select subcontractors who will also make such a commitment, engage in joint team-building exercises, and develop a “charter” for the project.] 110. Solution: B. Work with the virtual team members to determine communications most appropriate for them given their location and participation on the project. As a best practice, work with the virtual team members to determine communications most appropriate for them given their location and participation on the project. 111. Solution: D. Meet with this stakeholder to update the stakeholder engagement plan and to understand their communication needs. The project manager should meet with the stakeholder to update the stakeholder engagement plan and to understand their communication needs. Although escalation to the line manager is an option, a project manager is expected to understand the hurdles of dealing with difficult stakeholders. 112. Solution: C. Create a risk item in the risk register and incorporate the thresholds according to the benchmarks. The project manager should create a risk item in the risk register and incorporate the thresholds according to the benchmarks. Risk register updates are the most critical; the other actions listed are less useful for risk mitigation. 113. Solution: B. Inform the team member that this would be best handled in another meeting The best way for the project manager to handle the interruption is to inform the team member that this would be best handled in another meeting, like a backlog refinement for sprint planning, not the retrospective. The other answer choices are incorrect as they suggest that the project manager should accommodate the new team member's question at an inappropriate time. 114. Solution: B. Update the risk management plan and implement the new response to address the risk. The correct answer is to update the risk management plan and implement the new response to address the risk. Throughout the project, the project manager needs to continuously monitor for new, changing, and outdated project risks and changes in the level of overall project risk and update the risk management plan. When a risk level changes it must be reflected in the risk management plan. The other answer choices are incorrect because they are inappropriate ways of managing the situation. The project manager shouldn't implement the response only because it is compatible with the risk management plan, the risk level and impact have changed, and the response should be amended to reflect those changes. Given the elevated risk level, it should be addressed as soon as possible, and the project manager should not wait until the next progress meeting to get management approval for the new response. A contingency response should not be implemented without informing key stakeholders. 115. Solution: C. Create a change request to evaluate the feasibility of using the new technology. Any changes during the project execution need to be raised as a change request. The configuration management plan shouldn't be updated prior any approval. The project team should continue working as planned. The project manager should raise the new technology to the project stakeholders as it introduces benefits to the project with the reduction of project cost by 10%. The project manager shouldn't be asking the development team to implement the new technology without the approval of the stakeholders. 116. Solution: A. Subject matter experts have specialized expertise and can help identify and address high-risk issues. The correct answer is that subject matter experts have specialized expertise and can help identify and address high-risk issues. Subject matter experts are invited to the meeting because they provide functional expertise that will help to quickly identify high-risk areas. Expert judgment is the contribution provided to risk identification based on expertise in a subject area, industry segment, organizational processes, etc. The other answer choices are incorrect because the meeting was called to identify risks, not what may happen after the risk has been identified. When subject matter experts assist in identifying risks, they do not typically provide resources beyond their expertise. The participation of subject matter experts does not necessarily make risks easier to accept nor does it ensure that better resources will be secured. 117. Solution: C. Recalculate the contingency reserve based on only identified risks. Applying the same percentage increase across all activity costs may increase the total cost of a project. It is better to assess the risks of each activity and appropriating the necessary contingency reserve. The other answer choices are incorrect. Requesting additional budget for the project is not correct; reducing the percentage increase before re-evaluating the current cost is not correct; and allocating a portion of the contingency reserve to management reserve is not correct as both serve different purposes in cost estimation. 118. Solution: A. Submit a change request to add regression testing work packages to the project scope. The Quality Management Plan (QMP) drives the quality management processes and regression testing is a part of the QMP. Hence the project manager should submit a change request to add regression testing work packages to the project scope. The other answer choices are incorrect. Requesting extra test resources is something the project manager will do after the change request for the regression testing work packages is approved. Hence this option is not the appropriate answer. Removing regression testing from the quality requirements and QMP is not the right thing to do as it will decrease the quality of the project. 119. Solution: A. Guide the team to manage scope using standard agile methodology. Guiding the team to manage scope by using the standard agile methodology is the best option. Deferring responsibility by escalating to senior management is not an appropriate path to handle the situation. Daily standup meeting would not include additions to currently approved product backlog. Changes to the backlog would be dictated by the product owner after consideration of all constraints, not only the budget. 120. Solution: A. Ensure that the team member receives adequate training and is comfortable with the subject matter. The project manager should provide needed training to address the specific gap where the team member is unfamiliar with the subject matter. The other answer choices are incorrect. Encouraging the team member to take on more or avoid the specific subject matter does not directly address the fact that the team member needs more training on the subject matter. It could also affect the team velocity and quality. Replacing the team member is also incorrect because it would adversely affect the team dynamics, the team member would not improve and grow. 121. Solution: A. Described the user story in more detail In order to avoid this situation, the user story should have been made available in detail to capture the requirement for foreign credit card acceptance. The other answer choices are incorrect they would not have helped the project manager avoid the situation, rather they are iterative steps in an agile approach. 122. Solution: A. Track the budget based on the release plan and show the value to the business 123. Solution: B. Continuous Delivery Continuous delivery technique allow the team to create a demo and continuously make improvements until the product is complete and the client is satisfied. 124. Solution: C. Inform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity The team member approaching the Scrum Master is the correct choice, as it is the role of the Scrum Master to make sure that any obstacles and impediments are removed from the team. The Scrum Master should now make sure there is no further loss of productivity to the team through any means in the future. The Scrum Master does not have the authority to discuss the change directly with the stakeholder in Agile Projects. It is the team that is responsible for requirements. Hence this option is not correct. The team member should not be involved in advising the stakeholder on any kind of process related ideas like providing the new requirements directly to the change control board[CCB] or sending the requirements directly to the Project Manager. Hence these two options are incorrect. 125. Solution: C. Support the decisions of the team and transfer the decision making responsibility to them The servant leader in an Agile or Hybrid environment must empower the team based on its strengths around a purpose/goal and eliminate organizational impediments for delivering results. Hence this option is the correct answer. The team takes decisions in a hybrid environment and is entirely responsible for the project outcome. Hence this option is incorrect. The Product owner being a part of the team should be involved in the decision making process. Hence there is no need for the Project Manager to explicitly inform the Product owner. Hence this option is incorrect. The steering committee does not get involved in trivial issues like approving team for decision making which the team can handle themselves in hybrid projects. Hence this option is incorrect. 126. Solution: D. Three-point estimating Three-point estimating uses the most likely, optimistic, and pessimistic estimates, which improves estimate accuracy for a project with high uncertainty. Analogous estimating uses values from a previous similar project. Since this project has a high level of uncertainty, it can be assumed there is no similar project to compare. Parametric estimating uses a statistical relationship with historical data and is often used in construction. Other statistical techniques are not the best approach for a project with a high level of uncertainty. 127. Solution: B. Stop the release of the deliverable to the customer If a new quality change has been approved after the project deliverable is ready, the deliverable will not meet the new quality requirements and should not be released to the customer. The new quality criteria should be used for all deliverables, not only future ones. The risk register would contain risks associated with quality, however, a quality change has been approved. The question did not state a new quality risk has been identified. Updating the project management plan would require an approved change, which may be the case here, but that is not the first thing the project manager should do. 128. Solution: A. Project charter Project objectives and success criteria should be documented and agreed to in the project charter. Inputs to the project charter also include business documents which would align the project to the business strategy. The quality management plan, scope statement, and requirements documentation would not have the detail to the overall project success criteria. The project charter documents the project success criteria, the approval requirements, and who will sign off on the project. 129. Solution: A. The client should be exposed to the agile approach in advance to understand the cost estimating process Agile environments are subject to high degrees of uncertainty and frequent changes. Only high level cost estimates are needed and they will be adjust with each iteration. The agile approach should be used if it is specified in the charter. Costs and scope changes should be managed with each iteration to comply with the overall project budget. Daily standup are short meetings to review status of tasks and performance of the project. Client communications should not be part of the daily standups. 130. Solution: B. They require minimal management effort Low power and low interest stake holders require minimum management effort. High power and high interest stake holders must be kept satisfied Low power and high interest stake holders must be kept informed and updated on the project 131. Solution: C. Free rein Laissez -faire leadership style leaves the decision up to everyone as in this scenario. Free-rein leadership style is also called as laissez faire leadership style Democratic - This project manager draws on the team members' knowledge and skills and is able to create a group commitment to common goals. Smoothing - resource smoothing is defined as a technique that adjusts the activities of a schedule model so that all requirements for the resources do not go beyond the resource limits already predefined during the planning Autocratic management strictly means the manager makes all the decisions, without involving the team members. 132. Solution: C. Systems thinking The Project manager by looking at the connections between the different hindrances to have a full understanding of the picture used system thinking Total quality management (TQM) is the continual process of detecting and reducing or eliminating errors in manufacturing, streamlining supply chain management, improving the customer experience, and ensuring that employees are up to speed with training. The Pareto Principle states that 80 percent of a project's benefit comes from 20 percent of the work. Or, conversely, that 80 percent of problems can be traced back to 20 percent of causes. Pareto Analysis identifies the problem areas or tasks that will have the biggest payoff. 133. Solution: D. Both A and B For effective change to take place a wholistic view of project processes and how individual team members work need to be considered. An effective organization change process of projects and an effective individual change process of team members can be considered for effective successful change 134. Solution: B. Add Paredes to the team and get involved in the problems he causes to fix them 135. Solution: D. Gain the commitment and approval from leadership on noncompliance "Gain the commitment and approval from leadership on noncompliance" is the best choice as the Project Manager should try to address the noncompliance if known "Do nothing and continue..." is not an acceptable position to be taken by the Project Manager "Disengage the noncompliant department..." is not option, as these non-compliances are to be addressed satisfactorily "Disclose the source..." is not the right choice and let the Audit team decide on the next steps while addressing these kind of issue is the responsibility of a PM 136. Solution: C. Specify any dependencies if they exist Review and update your dependencies list throughout the project. 137. Solution: B. All each team to decide which agile methodology fits best for them and let them implement different methodologies based on their needs 138. Solution: C. Plan for a recursive governance meeting with customer to present the progress and publish the data in a shared folder for future review The relationship between a Project Steering Committee and the Project Manager is analogous to that of a Company Board and the Chief Executive. A Board recruits a Chief Executive and, in partnership with him or her, sets the strategic direction of the company, but the Chief Executive is responsible for the day-to-day running of the company and the results achieved. Similarly, the Project Manager is responsible for the day-to-day running of the project, the goal and cost of which will have been determined by him or her in partnership with the Steering Committee. Like a Company Board, a Project Steering Committee should not be too hands-on. The Project Manager runs the project in accordance with the agreed specification. However, like a Company Board, the Steering Committee should not be too casual, either. Steering Committee members should read the project specification and the Project Manager’s regular reports carefully. Steering Committee meetings should be minuted, and Steering Committee members should sign key documents – specifically, the project specification, the risk management plan (if a separate document) and formal project checkpoint documents (e.g. tollgate decisions). 139. Solution: A, C, and D. Creating a user manual with thorough guidance, Training session arranged by an external company, and Reading through the project/product documentation and FAQs Explicit knowledge transfer results in readily articulated, codified, stored, and accessed information. In this case, it is shared as a manual, training session, documentation, and FAQs. Capturing users' experiences and job shadowing are examples of tacit knowledge. 140. Solution: D. Discuss this with the team to find options to mitigate the Solution: D The correct answer is to discuss this with the team to find options to mitigate the risk. The project is critical to the organization, therefore, the team should explore mitigation options. Risk mitigation is a risk response that involves decreasing the probability or impact of a threat. The other answers are incorrect because the team should consider all options before making decisions. Hiring additional resources for the team could potentially increase the project cost and does not guarantee decreased schedule impact. Being that the project is critical to the organization, adding the risk to the risk register for reviewing and monitoring does not address the issue thoroughly and is a slow process. Escalating the risk should only be done if the team fails to find an acceptable solution, if the threat is outside the scope of the project, or if the proposed response would exceed the authority of the project manager. 141. Solution: D. Providing behavior-specific incentives to team members Employee behavior apart from performance is a key factor for rewarding and recognizing employees. Hence rewarding employees with good behavior is definitely a motivating factor for other team members too and goes a long way in building and retaining a healthy team. Hence this option is the correct answer. Formal awards are related to the power and position of the team member. It does not motivate other team members. Hence this option is incorrect Financial incentives could in fact demotivate the other team members. Hence this option is incorrect. Providing the same incentive to all team members also demotivates the other team members as they will feel that, their talents and performance are not getting recognized properly and even if they do not work properly, they will still get the same incentive as other team members. Hence this is an incorrect option. 142. Solution: D. Ask the team members directly about both personal and work-related matters The indicated approach to build relationship and trust is showing you are interested on the other party. 143. Solution: A. Inability to manage the distributed workforce Research has indicated that one in two dispersed teams has been shown to fail to reach its objectives due to its inability to manage the distributed workforce. 144. Solution: D. Maintain a "natural distance" with the team In many companies, team members report a “natural distance” between the team leader and the team members. Team members feel separated from the team leader, who is often rather seen as management's representative than being a true team member. However, when team leaders interpret themselves as supporting team task accomplishments through their participation in shared leadership, just as any other team member, then team leaders can become more respected and trusted team members themselves. As such, they will be involved in more open communication processes and thus foster the very core purpose of virtual project teams, the integration of team members’ knowledge across distances. In many companies, team members report a “natural distance” between the team leader and the team members. Team members feel separated from the team leader, who is often rather seen as management's representative than being a true team member. However, when team leaders interpret themselves as supporting team task accomplishments through their participation in shared leadership, just as any other team member, then team leaders can become more respected and trusted team members themselves. As such, they will be involved in more open communication processes and thus foster the very core purpose of virtual project teams, the integration of team members’ knowledge across distances. 145. Solution: D. Unplanned changes, like shifting business expectations because in agile the product owner decide priorities Option A ) is incorrect, Agile doesn't focus on improving quality Option B) is incorrect. Agile still needs a plan and although it is likely there is no guarantee that the approvals are faster in Agile Option C) is incorrect. The main reason for using Agile is to 'embrace change', otherwise unplanned changes 146. Solution: D. Risk reporting The correct answer is risk reporting. While monitoring risks, the risk manager collects project performance data, produces performance measures, and reports and disseminates performance information. A risk report is a project document that is developed progressively throughout the risk management processes and summarizes information on individual project risks and the level of overall project risk. The other options are incorrect because they are risk responses, not tactics for monitoring risks. Risk responses are the agreed-upon response actions that are appropriate for the priority of the individual risks and the overall risk. 147. Solution: A. Meet with quality assurance specialists to clarify the issue and seek resolutions This is a quality assurance issue that has already occurred, so it is no longer a risk. The project manager should schedule a meeting with quality assurance specialists to understand the root cause of the large number of errors and seek a resolution. The other answer choices are incorrect as they refer to the issue as a risk. 148. Solution: B. Review the velocity of the team over the last several sprints and adjust the plan accordingly The best indicator of team capacity is the velocity metric and the delivery plan should take that in account prior to any solid commitment 149. Solution: B. A release burndown chart The project manager will need to understand and apply which tools are suitable for certain tasks. Release burndown chart tool provide an indication of the time remaining of the project. 150. Solution: C. Work with the team to decompose the scope into a WBS and work packages in order to create required deliverables and timelines To understand the work, the scope needs to be decomposed into a work breakdown structure with specific work packages included. Then the detailed requirements documentation is completed based on the agreed scope and the WBS. Without the detailed scope statement, it is not possible to proceed with creating a detailed schedule or work assignments . Hence all the remaining options are incorrect. 151. Solution: B. Provide more recognition and rewards to team members More recognition: The project manager notes he needs a way to encourage team members. Recognition is a method to enhance engagement of team members. Extending the schedule: The team is feeling the way they are due to how long the project has gone on. Extending the project further, counters the issue to be addressed. Discuss with the team: The team has make their feelings known and the reason for them. The project manager now need to find a way to encourage and motivate the team members. Additional resources: There is no indication that additional resources are needed or would have a positive impact on the issue at hand. The PM has identified that he needs to find a way to encourage team members. 152. Solution: C. Review the project management information system (PMIS) archives PMBoK Sixth Edition in Chapter 4 states: "4.3.2.2 PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS) The PMIS provides access to information technology (IT) software tools, such as scheduling software tools, work authorization systems, configuration management systems, information collection and distribution systems, as well as interfaces to other online automated systems such as corporate knowledge base repositories. Automated gathering and reporting on key performance indicators (KPI) can be part of this system. 4.3.2.3 MEETINGS Meetings are used to discuss and address pertinent topics of the project when directing and managing project work. Attendees may include the project manager, the project team, and appropriate stakeholders involved or affected by the topics addressed. Each attendee should have a defined role to ensure appropriate participation. Types of meetings include but are not limited to: kickoff, technical, sprint or iteration planning, Scrum daily standups, steering group, problem solving, progress update, and retrospective meetings. 4.3.3.3 ISSUE LOG Throughout the life cycle of a project, the project manager will normally face problems, gaps, inconsistencies, or conflicts that occur unexpectedly and that require some action so they do not impact the project performance. The issue log is a project document where all the issues are recorded and tracked. Data on issues may include: Issue type, Who raised the issue and when, Description, Priority, Who is assigned to the issue, Target resolution date, Status, and Final solution. The issue log will help the project manager effectively track and manage issues, ensuring that they are investigated and resolved. The issue log is created for the first time as an output of this process, although issues may happen at any time during the project. The issue log is updated as a result of the monitoring and control activities throughout the project's life cycle" This question is about an activity to be analyzed after the closure of the project. Therefore, PMIS archives is the correct place to review. The Distractors are correctly defined and are accepted 153. Solution: B. Stakeholders engagement assessment matrix The stakeholder management plan identifies the strategies and actions required to promote productive involvement of stakeholders in decision making and execution. Documenting this detail in an assessment matrix provides for a ready reference to needed detail. A RACI matrix defines the specific roles of individuals, however does not elaborate beyond that. The Risk Register is used to document the risk, including the probability and impact, however is not the means to document specifics of the individual thoughts of team members. . Work performance reports relate to the work itself, not the thoughts or opinions of an individual team member. 154. Solution: C. Statement of work (SOW) Statement of Work(SOW) will contain all the work that needs to be executed for the project to be completed and accepted. Hence this is the correct answer. All other remaining options are irrelevant as Procurement Management Plan will describe how procurement will be done and how vendors will be managed. The Request for Proposal(RFP) describes the project, its goals, and the organization that is sponsoring it and outlines the bidding process and contract terms. Inspections are carried out to identify and correct errors in a completed deliverable. 155. Solution: A. Communication requirements analysis PMBoK Sixth Edition Chapter 12, Section 10.1: " PLAN COMMUNICATIONS MANAGEMENT Plan Communications Management is the process of developing an appropriate approach and plan for project communications activities based on the information needs of each stakeholder or group, available organizational assets, and the needs of the project. The key benefit of this process is a documented approach to effectively and efficiently engage stakeholders by presenting relevant information in a timely manner. This process is performed periodically throughout the project as needed. An effective communications management plan that recognizes the diverse information needs of the project's stakeholders is developed early in the project life cycle. It should be reviewed regularly and modified when necessary, when the stakeholder community changes or at the start of each new project phase. On most projects, communications planning is performed very early, during stakeholder identification and project management plan development. While all projects share the need to communicate project information, the information needs and methods of distribution may vary widely. In addition, the methods of storage, retrieval, and ultimate disposition of the project information need to be considered and documented during this process. The results of the Plan Communications Management process should be reviewed regularly throughout the project and revised as needed to ensure continued applicability. The question is well stated and accepted. The Answer is: "Communications requirements analysis" 156. Solution: B. Business case review PMBoK Sixth Edition states that: "1.2/1.6.6.1 PROJECT BUSINESS CASE The project business case is a documented economic feasibility study used to establish the validity of the benefits of a selected component lacking sufficient definition and that is used as a basis for the authorization of further project management activities. The business case lists the objectives and reasons for project initiation. It helps measure the project success at the end of the project against the project objectives. The business case is a project business document that is used throughout the project life cycle. The business case may be used before the project initiation and may result in a go/no-go decision for the project. A needs assessment often precedes the business case. The needs assessment involves understanding business goals and objectives, issues, and opportunities and recommending proposals to address them. The results of the needs assessment may be summarized in the business case document. The process of defining the business need, analyzing the situation, making recommendations, and defining evaluation criteria is applicable to any organization's projects. A business case may include but is not limited to documenting the following: Business needs: Determination of what is prompting the need for action; Situational statement documenting the business problem or opportunity to be addressed including the value to be delivered to the organization; Identification of stakeholders affected; and Identification of the scope. Analysis of the situation: Identification of organizational strategies, goals, and objectives; Identification of root cause(s) of the problem or main contributors of an opportunity; Gap analysis of capabilities needed for the project versus existing capabilities of the organization; Identification of known risks; Identification of critical success factors; Identification of decision criteria by which the various courses of action may be assessed; 1.4 PROJECT SUCCESS AND BENEFITS MANAGEMENT Projects are initiated to realize business opportunities that are aligned with an organization's strategic goals. Prior to initiating a project, a business case is often developed to outline the project objectives, the required investment, and financial and qualitative criteria for project success. The business case provides the basis to measure success and progress throughout the project life cycle by comparing the results with the objectives and the identified success criteria. Projects are typically initiated as a result of one or more of the following strategic considerations: Market demand, Strategic opportunity/business need, Social need, Environmental consideration, Customer request, Technological advancement, Legal or regulatory requirement, and Existing or forecasted problem. A benefits management plan describes how and when the benefits of the project will be delivered and how they will be measured. Both the business case and the benefits management plan are developed prior to the project being initiated. Additionally, both documents are referenced after the project has been completed. Therefore, they are considered business documents rather than project documents or components of the project management plan. As appropriate, these business documents may be inputs to some of the processes involved in managing the project, such as developing the project charter" The distractors are correct. The answer: "Business Case Review" is correct 157. Solution: D. Manage Quality PMBoK Sixth Edition Chapter 8 Section 8.2 states: "Manage Quality is the process of translating the quality management plan into executable quality activities that incorporate the organization's quality policies into the project. The key benefits of this process are that it increases the probability of meeting the quality objectives as well as identifying ineffective processes and causes of poor quality. Manage Quality uses the data and results from the control quality process to reflect the overall quality status of the project to the stakeholders. This process is performed throughout the project. Manage Quality is sometimes called quality assurance, although Manage Quality has a broader definition than quality assurance as it is used in non project work. In project management, the focus of quality assurance is on the processes used in the project. Quality assurance is about using project processes effectively. It involves following and meeting standards to assure stakeholders that the final product will meet their needs, expectations, and requirements. Manage Quality includes all the quality assurance activities, and is also concerned with the product design aspects and process improvements. Manage Quality work will fall under the conformance work category in the cost of quality framework. The Manage Quality process implements a set of planned and systematic acts and processes defined within the project's quality management plan that helps to: Design an optimal and mature product by implementing specific design guidelines that address specific aspects of the product, Build confidence that a future output will be completed in a manner that meets the specified requirements and expectations through quality assurance tools and techniques such as quality audits and failure analysis, Confirm that the quality processes are used and that their use meets the quality objectives of the project, and Improve the efficiency and effectiveness of processes and activities to achieve better results and performance and enhance stakeholders’ satisfaction. The project manager and project team may use the organization's quality assurance department, or other organizational functions, to execute some of the Manage Quality activities such as failure analysis, design of experiments, and quality improvement. Quality assurance departments usually have cross-organizational experience in using quality tools and techniques and are a good resource for the project. Manage Quality is considered the work of everybody—the project manager, the project team, the project sponsor, the management of the performing organization, and even the customer. All of these have roles in managing quality in the project, though the roles differ in size and effort. The level of participation in the quality management effort may differ between industries and project management styles. In agile projects, quality management is performed by all team members throughout the project, but in traditional projects, quality management is often the responsibility of specific team members" The distractors are correct. The correct answer is: "Manage Quality" 158. Solution: B. Update the resource management plan PMBoK Sixth Edition Chapter 9 states: "9.4.2.6 TRAINING Training includes all activities designed to enhance the competencies of the project team members. Training can be formal or informal. Examples of training methods include classroom, online, computerbased, on-the-job training from another project team member, mentoring, and coaching. If project team members lack the necessary management or technical skills, such skills can be developed as part of the project work. Scheduled training takes place as stated in the resource management plan. Unplanned training takes place as a result of observation, conversation, and project performance appraisals conducted during management of the project team. Training costs could be included in the project budget or supported by the performing organization if the added skills may be useful for future projects. It may be performed by inhouse or by external trainers" The Resource Management Plan as developed now need to be updated with this new training plan as determined by the Project Manager. The correct answer is: "Update the resource management plan" The Distractors are valid and accepted 159. Solution: A. Manage Quality PMBoK Sixth Edition Chapter 8 Section 8.2 Manage Quality states: "The project manager and project team may use the organization's quality assurance department, or other organizational functions, to execute some of the Manage Quality activities such as failure analysis, design of experiments, and quality improvement. Quality assurance departments usually have cross-organizational experience in using quality tools and techniques and are a good resource for the project Project Quality Management processes and the interrelations of these processes in the Project Quality Management Knowledge Area. The Plan Quality Management process is concerned with the quality that the work needs to have. Manage Quality is concerned with managing the quality processes throughout the project. During the Manage Quality process, quality requirements identified during the Plan Quality Management process are turned into test and evaluation instruments, which are then applied during the Control Quality process to verify these quality requirements are met by the project. Control Quality is concerned with comparing the work results with the quality requirements to ensure the result is acceptable. There are two outputs specific to the Project Quality Management Knowledge Area that are used by other Knowledge Areas: verified deliverables and quality reports" Whether it is the internal and/or external auditor the fact is that a continuous audit is required during the various phases of project execution The correct answer is: "Manage Quality" The distractors are correct and valid 160. Solution: A. Develop the project charter PMBoK Sixth Edition Chapter 4 Section 4.1 states: "Develop Project Charter—The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities" The Project Manager should prepare Project Charter before initiating the "Kick-Off" meeting relating to the start of a new project. 161. Solution: B. Issue a change request A contingency plan is a fall back plan in response to a risk. In this case the risk impacts the schedule. The project manager should issues a change request to change the schedule. A risk audit and cost impact review will not address the impact to the schedule. The contingency plan does not need to be updated, it needs to be executed. 162. Solution: B. Control Quality Control quality is the process that records deliverable results and ensure the project outputs are correct. Statistical sampling is not a project management process, it is a tool and technique for control quality. Plan quality management should be done early on in the project, not when evaluating deliverables. Manage quality translates the quality management plan into executable tasks, it does not evaluate project deliverables. 163. Solution: A. Conduct recurring retrospectives to regularly check on the effectiveness of quality processes The PM has identified that quality may be a risk in this project, based on lessons learned from past projects. In developing the quality management plan, the PM should ensure that quality checks are done regularly so that the risk is avoided. The responsibility of managing quality would typically require several skill sets that one person may not have. The team should be involved in quality management. Tying quality to performance reviews will not avoid the same quality issues that have happened in the past. The quality management plan should incorporate the organizations quality policies and procedures. 164. Solution: A. Before the start of each iteration The correct answer is before the start of each iteration. The initial iteration would occur after an initial risk analysis, and that process should be repeated after every subsequent iteration. It is necessary to analyze new and existing risks to thoroughly understand their potential impact on project outcomes while preparing for each iteration. An iteration planning meeting is used to clarify the details of the backlog items, acceptance criteria, and work effort required to meet an upcoming iteration commitment. The other options are incorrect because they are not appropriate times to analyze risks. A daily standup meeting (also referred to as a daily scrum) is a brief collaboration meeting during which the project team reviews its progress from the previous day, declares intentions for the current day, and highlights any obstacles encountered or anticipated. A retrospective meeting in a regularly occurring workshop in which participants explore their work and results to improve both the process and product. These meetings provide an opportunity for the project team to review how it works and to suggest changes to improve processes and efficiency. Retrospectives can be useful for identifying risks. 165. Solution: A. Send a welcome email and host a team introductory event with the team members so they get to know each other A project manager should strive to have team members that know each other in order to collaborate more efficiently. By sending a welcome email and hosting a team introductory meeting, the team members will get to know each other first. The other choices are incorrect because they are not the first step in the process. 166. Solution: D. Reassure the team members that a training path is in place to learn the new technology The project manager is responsible of providing opportunities to hone the skills and knowledge of the team members to increase the mastery of the team performance. Replacing the members with more knowledgeable staff will take time for recruiting and forming the team as well even though asking team members to self-learning may be helpful that is not that effective us instructor lead training Reallocate the members to work on the tasks for which they have experience is not going to help us to implement the project successfully 167. Solution: B. Qualitative benefit Customer satisfaction and compliance both represent non-numerical benefits and hence are qualitative in nature. Quantitative is numerical benefits Quality benefit is the quality of work benefit 168. Solution: A. Active listening, leadership, and cultural and political awareness Active listening, leadership, and cultural and political awareness are the interpersonal skills that a project manager or team needs to monitor stakeholder relationships 169. Solution: A, C, E and F. Brainstorming, Risk checklists, Interviewing and Decision tree analysis The following are the tools used for risk analysis: Brainstorming is to obtain a comprehensive list of individual project risks and sources of overall project risk. Risk checklists are developed based on historical information and knowledge that has been accumulated from similar projects and from other sources of information. Interviewing may be used to generate input for the quantitative risk analysis, drawing on on inputs that includes individual project risks and other sources of uncertainty. Decision tree analysis are used to support selection of the best of several alternative course of action. The following tools are not used for risk analysis: Inspection is examination of a work product to determine whether it conforms to documented standards. Product evaluation is an investigation conducted to provide objective information about the quality of the product or service under test in accordance with the project requirement. 170. Solution: B. Bottom-up Bottom-up estimates are the most accurate, but depend on specific details and historical data. Because the project has delivered a full unit, the actual effort values can be used for the same team. 171. Solution: D. None of the above * Explorers – Are eager to discover new ideas and insights. They want to learn everything they can about the iteration/release/ project. * Shoppers – Will look over all the available information and be happy to go home with one useful new idea * Vacationers – Aren’t interested in the work of the retrospective, but are happy to be away from the daily grind. * Prisoners – Feel they have been forced to attend and would rather be doing something else. 172. Solution: B. Clarified interpretation of compliance guidelines. The project manager should have ensured they understand the compliance guidelines before making compliance-related changes while adopting a new project delivery approach that could pose threats to compliance. The other answer choices are incorrect because they suggest actions that do not promote the specific compliance standards for the project. 173. Solution: D. Ensure the interpretation of compliance guidance and validation Ensure the interpretation of compliance guidance and validation is correct as the government is involved and it will help determine potential threats to compliance. All other options are generic for all projects. 174. Solution: A. Business survival and continuity Business survival and continuity is correct as it is the more far reaching implication, other options are incorrect as these implications are short lived. 175. Solution: D. Monitoring and Controlling Process Group Corrective actions are taken in Monitoring & Control Process Group 176. Solution: D. Project Human Resource Management Test candidates understanding about project management knowledge area. Which particular knowledge area he/she can control and monitor. HR is the one which is handled by a dedicated cross functional team in any organization. where project manager will have influence but not full control. 177. Solution: D. Add to the product backlog to be treated in next iteration As the project team is in a middle of a sprint, any new requirement should be first added to the product backlog and reviewed in the next sprint. Calling a meeting with the stakeholder with a / all team members, getting the stakeholder to explain the requirement in a war room shouldn't be done in the middle of a sprint due to a new requirement. 178. Solution: B. Scrum Master The Scrum Master is the facilitator for all Scrum ceremonies, including estimation events 179. Solution: B. Outgoing, enthusiastic, optimistic, can be seen as overly optimistic 180. Solution: D. Customer focused WBS is used by the project team only and is not usually a deliverable to the customer. PMBoK Sixth Edition Chapter 3 states: "3.5 CREATE WBS Create Work Breakdown Structure (WBS) is the process of subdividing project deliverables and project work into smaller, more manageable components. The key benefit of this process is that it provides a framework of what has to be delivered. This process is performed once or at predefined points in the project. The needs of the project determine which components of the project management plan and which project documents are necessary" WBS is an internal document and not provided to the Customer. Therefore, the correct answer is: "Customer Focused" The Distractors are valid and accepted.