12 OCT 2020 GRID MAINTENANCE Title: Procedure Index Number: Procedure for Services to lend the Spare Store Material to NG contractors Revision Number: Page Number: 00 2 of 6 4. PR-GM-1470-002 DEFINITION 4.1. Definitions of Terms/Phrases 5. SRP Service Requesting Party S/R Service Request SP Service Provider RESPONSIBILITIES 5.1 Manager Projects Department: (SRP) will send the request to Manager AMD (SP). Service Request (S/R) shall be furnished by indicating clearly about the quantity and other technical detail of the required material. 5.2 Maintenance Department Manager: The concerned Maintenance department manager is the authority responsible for recommending to lend materials or not, in coordination with store officials. 5.2 Contractor: a person or firm that undertakes a contract to provide materials or labor to perform a service or do a job. 6. PROCEDURES 6.1 Projects Department Manager will send the contractor’s request to concerned AMD manager. 6.2 Request will be evaluated by consultation of store staff based on remaining quantity and other technical aspects. 6.3 After evaluation, service request will be either approved or rejected. 6.4 In the case of disapproval, contractor will be informed accordingly through Projects Department. 6.5 In the case of request approval, a material handover form/agreement will be prepared by clearly indicating quantity, other technical specs and material return date. Policies and Procedures Management System Website: http://ngridsa-apps/amas/ TP-NG-6250-001-005 GRID MAINTENANCE Title: Procedure Index Number: Procedure for Services to lend the Spare Store Material to NG contractors Revision Number: Page Number: 00 3 of 6 6.6 PR-GM-1470-002 After the request approved from the authorized persons, a copy of it will be sent to the concerned store and the applicant. 6.7 Prepared agreement will be signed by representative of the contractor or the receiver of the material. 6.8 7. Service provided. RETURN OF BORROWED MATERIAL 7.1. Contractor is responsible to return the material with same quantity and same technical specification as borrowed from store. 7.2. Contractor should test all returned material before received by store. 7.3. By the review of inventory reports, store officials make sure that the account / accounts balance represents the value of the borrowed materials and have not been returned to the company. 7.4. In case the materials were not returned back by the contractor with in the specified time, the concern AMD shall send a reminder to Projects Department requesting to expedite the return the materials by their contractors. 7.5. If returned material is deviated from issued material, a statement of deviation will be prepared based on manufacturer's data and use of material. 7.6. In case the borrowed materials are not returned, NG has the right to implement penalty to contractors who have not returned the borrowed Policies and Procedures Management System Website: http://ngridsa-apps/amas/ TP-NG-6250-001-005 GRID MAINTENANCE Title: Procedure Index Number: Procedure for Services to lend the Spare Store Material to NG contractors Revision Number: Page Number: 00 4 of 6 PR-GM-1470-002 materials. Implementation of penalty will be processed through concerned Projects Department (SRP) 7.7. The cost of materials that have not been returned shall be calculated according to the current market price or price in the store inventory system, whichever is higher. Policies and Procedures Management System Website: http://ngridsa-apps/amas/ TP-NG-6250-001-005 GRID MAINTENANCE Title: Procedure Index Number: Procedure for Services to lend the Spare Store Material to NG contractors Revision Number: Page Number: 00 5 of 6 PR-GM-1470-002 8. FLOWCHART Title: Procedure for Services to lend the Spare Store Material to NG contractors Asset Maintenance Department Service Requesting party (SRP) Service Provider (SP) start 6.1 Service request subm itted 6.2 Evaluate the Service Request 6.3 Request Approved 6.4 Confirm the acceptance No Yes 6.5 Prepare Agreement 6.6 Identification of Store 6.7 Signed agreement 6.8 Service Provided Phase End Policies and Procedures Management System Website: http://ngridsa-apps/amas/ TP-NG-6250-001-005 GRID MAINTENANCE Title: Procedure Index Number: Procedure for Services to lend the Spare Store Material to NG contractors Revision Number: Page Number: 00 6 of 6 PR-GM-1470-002 9. REFERENCES Index/Reference Number Title 10. REVISION HISTORY Revision Date 00 12 OCT 2020 Description of Modifications/Reasons for Change First issue of this Procedure. This document shall comply in accordance with the existing Company’s Rules and Regulations. Any modifications/discrepancies therein found not conformance shall be declared invalid. For clarification and verification on this document, contact the following: Abdulmalik S. Al-Rajeh Section Head Protection- Riyadh Substation Department Riyadh Grid Maintenance Business Line Extension No. 88375 Email: ASRajeh@ngrid.sa Policies and Procedures Management System Website: http://ngridsa-apps/amas/ TP-NG-6250-001-005