12” GAS PIPELINE AKRI – KWALE FOR
AKRI GAS RECOVERY
PROJECT
SCOPE OF WORK
CD-BF
00
28/05/2014
Issued for
Review
Validation
Status
Rev.
Date
Description
EDM
Prepared
by
EDM
Checked
by
C.A
Approved
by
Project name
Company logo and business name
Contractor
Approval
Company
Approval
Company identification
3214.10.GGPD.10909
12” GAS PIPELINE
AKRI – KWALE FOR
AKRI GAS RECOVERY
PROJECT
Contractor logo and business name
Vendor logo and business name
Facility Name
12” AKRI – KWALE GAS PIPELINE
Vendor Identification
Location
Scale
Sheet of Sheets
LAND
n.a.
1 / 43
Plant Area
Supersedes N.
Superseded by N.
Plant Unit
Document Title
Scope of Work
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
2 / 43
REVISION RECORD
0
Rev.
May, 2014
Date
Issued for Review
Reason for Revision
First Issue
Short Description of Changes
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
3 / 43
CONTENTS
1
2
3
4
INTRODUCTION
1.1
Pipeline Component
5
1.2
Definitions and Abbreviations
7
1.3
Route Overview
9
1.4
Pipeline Route Conditions
9
1.5
Environmental Data
9
1.6
Battery Limits
10
1.7
Pipeline Design Parameters
10
DESCRIPTION OF THE WORK
2.1
Engineering
2.2
Construction Hydrostatic Test, Pre-Commissioning, Commissioning
12
and start-up
12
2.3
Particular Requirements of the Work
14
2.4
Parties Involved in the Project
16
ENGINEERING
3.1
Introduction
17
3.2
Basic Design Endorsement
17
3.3
General Engineering Requirements
18
3.4
Specific Engineering Requirements
19
3.5
Final Documentation
21
3.6
Drawings and Documentation’s
21
3.7
Engineering Documents Approval
22
3.8
Computerised Maintenance Systems (CMMS)Data Documentation........24
CONSTRUCTION WORK
4.1
General
25
4.2
Construction Management
26
4.3
Safety
26
4.4
Labour
26
4.5
Tools and Consumables
26
4.6
Mobilisation
27
4.7
Transport of Pipes and Materials from Port of Entry to Storage/Marshalling
Yard
27
4.8
Transport of Pipes and Materials to Work Site
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
27
Company Identification
Contractor Identification
3214.10.GGPD.10909
5
7
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
4 / 43
4.9
Construction Camps
27
4.10
Camp and Field Office Accommodation for COMPANY Personnel
27
4.11
Construction Work
28
4.12
Detailed Work Description
28
STRUCTURAL WORKS
5.1
6
Rev. index.
Trap support design
37
SUPPLY
6.1
COMPANY Supplied Items
40
6.2
CONTRACTOR Supplied Items
40
6.3
Spare Philosophy for Construction
42
STANDARD
7.1
7.2
COMPANY Supplied Items
CONTRACTOR Supplied Items
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
43
43
Company Identification
3214.10.GGPD.10909
1.0
Contractor Identification
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
5 / 43
INTRODUCTION
COMPANY intends to develop and install a new Gas Pipeline of about 15 Km section of NPS 12
Pipeline conveying Gas from Akri Flowstation to Kwale Gas Plant.
This specification defines the technical requirements for the detailed engineering,
procurement, construction, installation, testing and precommissioning of the Gas Pipeline from
Akri Flowstation to Kwale Gas Plant (NPS 12).
A fibre optic cable (FOC), (if applicable), shall be laid in the same trench with the Gas Pipeline.
The FOC shall serve three main purposes:
 Pipeline surveilance (intrusion detection)
 Telecommunication
 Process data retrieval
The Pipeline shall be realised complete with all necessary provisions except Scraper Traps,
etc.
CONTRACTOR will be responsible for the supply of the 12” line pipes and all other materials
required to complete the pipeline system.
CONTRACTOR will be responsible for tie-in (with all required materials) of the new 12” Akri
Gas Pipeline to both ends of the existing 24” River Niger Pipeline crossing.
CONTRACTOR will be responsible for the supply and installation of a new Slug Catcher and
the interconnecting piping, which shall be connected to the existing MP Header in Kwale Gas
Plant. The Sludge Catcher shall be installed in a new location to be acquired by Company.
CONTRACTOR should note that all items/works included in the various Drawings that are not
captured in the Scope of Work shall be his responsibility.
The route, of the pipeline shall be the same with the existing Right of Way of the 10’’ Kwale –
Akri Oil Pipeline.
All permits and Licences regarding Right of Way shall be provided by the COMPANY prior to
mobilisation and during the execution of the works.
The CONTRACTOR will be responsible for all aspects of the work, starting from the
documents provided for in these specifications, the development of all the Engineering
required to complete the works and the procurement of all required fittings and other materials,
including construction and installation on site, testing and precommissioning.
This document therefore defines the Basic requirements for the realisation of the Pipeline
System. Where this specification conflicts with its associated specifications and/or the codes,
standards and associated drawings listed in any part of this document, the CONTRACTOR
shall bring the matter to COMPANY’S attention for resolution and approval in writing. In all
cases, the most stringent requirements shall apply.
Compliance of the CONTRACTOR with the provisions of this specification does not relieve
him of his responsibility to properly install the pipeline, equipment and accessories in order to
meet the specified service conditions and Nigerian codes governing design, fabrication and
health and safety.
The COMPANY reserves the right to supply the detailed specifications for project material
procurement with which CONTRACTOR must comply.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
6 / 43
In the following paragraphs, the term “PIPELINE SYSTEM” refers to the 12” Gas Pipeline AND
the Fibre Optic Cable (FOC), including all pipeline components required to fulfill the objectives
of this project.
Within this context, CONTRACTOR shall perform all activities including all detailed design
engineering, procurement and supply of materials including line pipes, fabrication, supply,
transport, construction, testing and pre-commissioning activities required to achieve the
successful completion of the Work.
The Pipeline shall be realised and connected without interrupting services at Akri Flowstation
and Kwale Gas Plant.
At Akri all new connection lines, shall be designed and constructed by the CONTRACTOR .
Detail engineering, procurement, construction and testing are included in the CONTRACTOR
scope of work.
At Kwale, all new connection lines, Slug Catcher and its accessories shall be placed on a
foundation to be designed and constructed by the CONTRACTOR. Detail engineering,
procurement, construction and testing works are included in the CONTRACTOR scope of work.
On this pipeline section all construction activities, concrete weighing, cable duct laying and
hydraulic testing to be provided by the CONTRACTOR shall be in accordance with specification
as will be provided by the contractor and approved by company or in accordance with any other
specification as may be supplied by the company.
Cable duct shall be waterproofed, closed and able to withstand a 10 meters head of water.
The description of the Work included in this Scope of Work is not an exhaustive detailed
statement of all CONTRACTOR obligations under this Contract. This Scope of Work shall be
read in conjunction with other project and engineering documents, general and discipline
specifications, project drawings and all other documents included in the Contract.
The detailed engineering shall be based on the Basic Design Documents enclosed in the
Contract.
Thus, for the realisation of the Pipeline system Akri -Kwale, the following activities shall be
carried out as a minimum.







1.1
Project Management
Detailed Engineering
Procurement
Construction, Installation and ROW Restoration
Cathodic Protection
Testing and Precommissioning
As Built File
Pipeline Component
The main components of the NPS 12 Gas Pipeline System specific to the Pipeline
Scopes of Work are:
1)
2)
3)
4)
5)
15 km of NPS 12 Pipeline, 3 km of existing NPS 24;
Foundation;
Cathodic Protection (CP) System;
Fibre Optic Intrusion & Leakage Detection System
Slug Catcher
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
7 / 43
The Battery Limits and connecting points are identified accordingly and indicated in
the Basic Design Documents.
PIPELINE SUMMARY
12” PIPELINE
Service
Pipeline Length
Routing
Configuration
Pipe Size
Pipe Material
Pipe Wall Thickness
Pipe Coating
Coating of Field Joints
Pipeline Design Life
Piping Code
Gas
18 Km
On existing Right of Way of 10’’ Kwale – Akri
Pipeline
Buried. No bunding
Normal Areas:
min 1.00 m (T.O.P)
Agricultural Areas: min 1.20 m (T.O.P)
Residential Areas: min 1.20 m (T.O.P)
Swamp and Mangrove Areas: min 1.00 m (T.O.P)
ND 12’’
API 5L X 65 – SMLS
11.1mm/12.7
as
specified
in
3214.10.BGRA.16519
HDPE three layers
Heat shrinkable sleeves (HSS)
Thirty (30) years
- Cross-country pipeline
-
ASME B 31.8
07486.PLI.MEC.SPC Design Criteria For Buried
Pipeline.
-
ASME B 31.8
ASME B 31.3
- Akri and Kwale
1.2
Definitions and Abbreviations
1.2.1
Definitions
COMPANY
Is NAOC who wishes to realise the NPS 12
new Pipeline from Akri - Kwale
COMPANY Representative
means any authority or person appointed in
writing by COMPANY to witness the
manufacturing, fabrication quality control and
inspection of materials and equipment to be
used for the project.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
Engineer
Is the party which carries out all or part of the
design, as specified by COMPANY.
CONTRACTOR
Is the party which carries out part of the
design, procurement, construction activities,
manufactures and/or supplies materials,
equipment and services to perform the
duties as specified by the COMPANY.
The term “CONTRACTOR” shall also apply
to the construction Sub COMPANY selected
by COMPANY for the execution of part of the
Work.
CONTRACT
The entire set of documents enclosed in the
volumes making up the EPC documentation.
INSPECTOR
The authorised person or agent of the
COMPANY assigned to perform inspections.
VENDOR
The COMPANY manufacturing or supplying
a particular product.
SUPPLIER
The COMPANY distributing or selling a
product.
SPECIFICATION
A portion or section of the Tender.
SUBCONTRACTOR
The
COMPANY
retained
by
the
CONTRACTOR to perform specific portions
of the Work.
COMPANY SPECIFICATIONSGuidelines for design and/or realisation
generally based on a clarifying international
standard.
WORK
The complete scope of the work to be
performed as described in this Tender.
WORK SITE
The site or location where the work is to be
performed, including rights-of-way, offices
and shops.
FACILITY
All or any part of the pipeline and associated
equipment.
CONSTRUCTION WORKS
All design and construction activities of
pipeline and related facilities within the
Contractor scope of work.
Filename
The name assigned to each file; it must be in
accordance to the requirements of windows
system dimensions.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
8 / 43
Company Identification
Contractor Identification
3214.10.GGPD.10909
1.2.2
1.3
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
Shall
Is to be understood as mandatory in relation
to the requirements of these specifications.
Should
Indicate a recommendation.
Owners
Company or appointed agent for the service
or building; landowner or respective tenant of
the land or property
Construction Drawings
The applicable Typical, Detail, or Alignment
Sheet drawings as defined in the Contract
Construction Specifications
The applicable specification as defined in the
Contract.
9 / 43
Abbreviations
CP
DF
dmsl
FOC
KP
LLWS
msl
MAOP
NPS
ND
ID
OD
PE
PTS
RoW
SMYS
STS
T/R
WT
NDT
FS
SAP
Cathodic Protection
Design Factor
dimensionless
Fibre Optic Cable
Kilometre Point
Lowest Level Water Spring
mean sea level
Maximum Allowable Operating Pressure
Nominal Pipe Size
Nominal Diameter
Internal Diameter
Outside Diameter
Polyethylene
Pipe Tracking System
Right of Way
Specified Minimum Yield Strength
Scraper Trap Station
Transformer/Rectifier
Line Pipe Wall Thickness
Non Destructive Test
Flow Station
Systems Application Product in Data Processing
PM
OEM
Prevention Maintenance
Original Equipment Manufacturer
Route Overview
The NPS 12 is located in both Imo and Delta States in Nigeria. The starting point is
located at Akri flowstation in Imo State and terminates at Kwale Gas Plant in Delta
State.
The proposed 12” Gas Pipeline from Akri to Kwale follows the existing right-of-way
(ROW) of 10’’ Kwale – Akri Oil Pipeline. Contractor shall be responsible to produce
the Details of pipeline route at his charge.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
1.4
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
10 / 43
Pipeline Route Conditions
The pipeline route is covered by dense tropical vegetation intersected by several river
creeks and swamp areas. The major part of the route is located in mangrove swamp
area which s influenced by tide variation.
CONTRACTOR shall investigate the site to clearly understand the conditions which
may affect the construction activities during the performance of the Work
Contractor shall be responsible to produce the Details of pipeline route at his charge.
1.5
Environmental Data
Location
Country :
State :
Altitude :
Nigeria
Imo & Delta States
sea level
Akri flow station and Kwale Gas Plant are located in NAOC’s OML 60 in the Land
Area of the Niger delta
Climate
Tropical climate, marine-salty environment (Nigeria River Swamp Area).
Air
Absolute minimum temperature
: 16°C
Absolute maximum temperature
: 36°C
Average ground temperature
: 25°C
Design temperature
Dry bulb temperature
: 34°C
Wet bulb temperature
: 28°C
Relative humidity
: 90 to 95%
Maximum humidity
: 99%
Design relative humidity
: 90%
Fine sand presence in atmosphere during 2 months “Armatan” period.
Rainfall
For 60 minutes
For 30 minutes
For 15 minutes
Heavy rain
: 92 mm/h
: 140 mm/h
: 160 mm/h
: storm presence
Sunshine
10/12 hours/day over 12 months. Maximum is June.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
11 / 43
Wind
The highest mean wind velocity at 10 m above ground level is 75 Km/h.
Lightening
High concentration of direct lightening phenomena during seasonal storms.
1.6
Battery Limits
The battery limits of the NPS 12 new Gas Pipeline design is defined in P&ID Nos
3210.10.BPFM.XXXXX.
Contractor to note that the FOC shall be ran along the entire length of the pipeline,
from Akri to Kwale, and terminates appropriately. The FOC shall contain 12 singlemode optical fibers (standard cable length: 3000 m per cable Drum), generally to
comply with suitable ITU-T Recommendations.
Contractor shall also terminate the fibre optic cable (FOC) in COMPANY’s control
equipment located at both ends (Akri and Kwale).
Consequently, Contractor shall note the following:

Akri – Kwale FOC Installation: Contractor shall terminate 6 cores of the
FOC at Telecommunications (TLC) control room at both ends (i.e. at Akri and
Kwale, respectively), while the remaining cores shall be terminated in the
intrusion detection control/monitoring equipment and the plant’s main control
system in the Control room, as applicable.
*Contractor to verify the termination methodology that will realise the main
objectives of the FOC as outlined in Section 1.0.
Consequently, Contractor shall liaise with COMPANY’s FOC end-user departments
(e.g. ICT, Telecommunications, GIS, etc.) for advice, especially as regards the
appropriate interface equipment(s) that may be required, so as to ensure that
termination of the FOC is done properly and effectively to achieve the main
objectives highlighted in Section 1.0 above.
*NOTE: that all interface equipment(s) required by the user-departments for proper
termination of the FOC are also within Contractor’s scope of work.
Pipeline Contractor to note, therefore, that a minimum slack (excess length) of 100m
of fibre optic cable shall be allowed at the cable ends in both flowstations, as much as
is required for proper termination at the receiving control equipment(s). See Doc. No:
3214.10.BISP.26807.
1.7
Pipeline Design Parameters
1.7.1
Pipeline System Design
The primary code applicable to the pipeline system is ASME B31.8, ASME B31.3,
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
Rev. index.
3214.10.GGPD.10909
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
12 / 43
API 1104, and any other code which its application may improve the quality of the
pipeline project.
Other codes and standards listed on Tender Documents shall also be adhered to.
The Pipeline shall be buried along its entire length except for portions located at
launcher and line valve. At these areas, the below and above ground transition shall
be denoted on the P&IDs by the abbreviations UG and AG respectively.
The pipeline shall be designed to be inspected by means of various kinds of pig.
1.7.2
Pipeline Materials
12” Gas Pipeline Akri-Kwale
Steel
Line Pipe Specification
: API 5L Gr. X65 SMLS
Pipeline Diameter and Wall Thickness
1.7.3
Dimensional (Inside) Diameter
: 304.9mm (NPS 12)
WT - ASME B31.8 DF 0.72/0.6
Coating
:11.1mm/12.7mm
External pipe Coating
:3 Layer Polyethylene (2.9mm)
Internal pipe Coating
: not required
Pipeline Design Pressure
12” Gas Pipeline Akri - Kwale
Design pressure
Flange Rating
1.7.4
: 120 barg
: 900 lb
Hydrostatic Test
Hydrostatic test requirements are defined in Technical Specification for Pipeline
Cleaning, Gauging and Hydrotesting Addendum to API Spect 5L No.
3214.10.BTST.16535
1.7.5
De-watering
De-watering requirements are defined
specification No. 3214.10.BTST.16576.
1.7.6
in
the
Pipeline
Start-up
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Pre-Commissioning
Company Identification
Contractor Identification
3214.10.GGPD.10909
Start-up requirements
3214.10.BTST.16576.
are
defined
in
the
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
Project
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
specification
13 / 43
No.
Company Identification
3214.10.GGPD.10909
2
DESCRIPTION OF THE WORK
2.1
Engineering
Contractor Identification
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
14 / 43
CONTRACTOR shall carry out the detailed engineering Work including review and
endorsement of the Basic Engineering, and where applicable or missing information
shall ensure that he embark on some survey to locate or provide such missing
information which he shall submit to the company for review and approval before
apllication, complementary site survey required, detailed design, engineering for
procurement, engineering for construction, pre-commissioning, commissioning and
start-up.
CONTRACTOR shall ensure the technical reviews and approval by COMPANY.
CONTRACTOR shall manage and perform the engineering activities and report to
COMPANY as per the engineering to be developed in accordance with the
requirements of the Contract.
CONTRACTOR shall prepare and submit all engineering documentation to
COMPANY in accordance with the Contract requirements.
CONTRACTOR shall provide the final documentation for the “as built” of the pipeline
and associated facilities consisting of all documents, drawings, calculations, test
report, certificate, procedures for pipeline operation, government filings, and all other
documentation required under the Contract.
2.2
Construction, Hydrostatic Test, Pre-Commissioning, Commissioning and startup
CONTRACTOR shall perform the construction activities in accordance with detail
design engineering documents developed by CONTRACTOR and approved by
COMPANY
CONTRACTOR shall safely connect 12” Line Pipe to the existing 24” Line Pipe at
both ends of River Niger (HDD across the River Niger).
CONTRACTOR shall take over the Site “as is”; the Site being “The RoW allocated by
the COMPANY” and provide areas for material storage, construction camps, offices
and access to the Site locations.
CONTRACTOR shall appoint Safety and Community Relation Managers prior to start
of any work in the Site.
CONTRACTOR shall provide appropriate implementation of Health, Safety, Security
and Environment rules at Site. CONTRACTOR shall make available adequate first aid
materials at Work Site throughout the construction period.
CONTRACTOR shall construct, pre-commission, commissioning and start-up the
Work including unloading, storing, transport, handling, stringing, prefabrication,
installation and erection as required.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
15 / 43
CONTRACTOR shall carry out all work and services and furnish all equipment
materials and tools required to grading, excavating, hauling, handling, welding,
lowering-in, hydrostatic testing works, etc.
CONTRACTOR shall carry out all hot-tapping activities (if applicable) and relevant
services and furnish all equipment, materials and tools required. CONTRACTOR shall
also provide procedure and provision ensure rapid and safe evacuation under
emergency.
CONTRACTOR shall provide construction workforces.
CONTRACTOR shall ensure that the construction Work is carried out in accordance
with drawings and specifications approved by COMPANY for Construction.
CONTRACTOR shall supply, operate and maintain Construction Equipment as
required for the execution of the Work.
CONTRACTOR shall provide material, consumable and facilities to support
Manufacturers/Suppliers specialists during construction, pre-commissioning,
commissioning and start-up.
CONTRACTOR shall manage surplus materials and waste disposal in accordance
with the rules and regulations in force in the Republic of Nigeria, in particular with the
prescribed environmental mitigation measures.
CONTRACTOR shall provide the security (bearing in mind, the present security
suitation in the Niger Delta) and safety services within the Site.
CONTRACTOR shall provide telecommunications, power supply and all other utilities
required at Site.
CONTRACTOR shall manage coordinate and supervise the Work assigned to Sub
CONTRACTOR(s) to ensure the Work is performed within the required schedule, and
the quality requirements of the Contract.
CONTRACTOR shall provide the hydrostatic testing of pipeline, including pre-testing,
pre and post hydrostatic test activities, including filling, cleaning, gauging and calliper
pigging.
CONTRACTOR shall provide the pre-commissioning activities including:
i)
ii)
iii)
iv)
v)
vi)
De-watering (and safe disposal of test water);
CP testing and Commissioning;
Inspecting, testing and pre-calibrating instrumentation, including
instrumentation;
Checking operation of all protection systems;
Purging and leaving pipeline systems under positive pressure;
Disposing of test water and all excess and waste fluids, materials
and equipment as specified in the Contract.
CONTRACTOR shall undertake full responsibility for the commissioning and start-up
of the complete pipeline system of which the 12” Akri - Kwale Gas Pipeline and all its
facilities (Slug Catcher and Valves e.t.c) are integral parts.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
16 / 43
At least 1 month prior to the programmed date for commissioning and start-up,
CONTRACTOR shall submit for the COMPANY approval a detailed procedure and
program. Upon completion of the commissioning and start-up in accordance with the
program and procedures, to the satisfaction of the COMPANY, the taking over of the
pipeline system by the COMPANY shall not relieve the CONTRACTOR in any way
from his obligations to carry out further tests as may be required on the pipeline
system to demonstrate and fulfil his overall responsibility for performance of the
system, regarding the Gas Pipeline 12” Akri – Kwale only
CONTRACTOR shall provide and operate an electronic material traceability with
qualified operator personnel to continuously store and report upon, pipeline data
progress.
CONTRACTOR shall provide qualified surveyors, equipment and helpers for all
topographical survey activities. The CONTRACTOR shall carry out the topographical
survey activities, dimensional measurement and checks before and during
construction and survey all data required for the preparation of the “as built
“documents and for implementation of pipe tracking system.
Contractor shall be responsible for the Restoration of the Pipeline Right of way to the
original condition prior to the commencement of the construction activities.
2.3
Particular Requirements of the Work
2.3.1
Additional surveys.
For the execution of the detailed work, CONTRACTOR shall carry out surveys to
confirm existing survey data and/to obtain additional or new data. Such surveys are
included in CONTRACTOR’s Scope of Work
2.3.2
Interface and Coordination.
Interface with other parties are outlined in Section 2.4 of this document.
2.3.3
Permits
CONTRACTOR shall consider that there may be some existing pipeline and relevant
facilities, along the Pipeline ROW, which may be in operation and as such, all work in
these areas shall require permits from the relevant operating COMPANY.
This requirement is also applicable for all the crossings of existing pipeline, flow line,
cables and other above ground and underground structures.
2.3.4
Tie-ins at Interface Point.
CONTRACTOR shall perform all hot-tapping activities; all flange connections, welds
and test at interface point Battery Limits. Generally, CONTRACTOR shall carry out all
In-plant Piping/Tie-in as detailed in the P&IDs.
2.3.5
Pipeline Work Constraints
The constraints which may affect the project activities are listed here below.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
17 / 43
CONTRACTOR shall take these into consideration and shall take the necessary
provisions in its organisation and planning for the performance of the work.
i)
ii)
iii)
iv)
v)
vi)
vii)
2.3.6
Environmental Constraints;
Archaeological Constraints;
Terrain / Geo-hazard Constraints;
Access Constraints;
Third-party Constraints;
Social Constraints;
Security constraints.
Working in the Vicinity of Existing Pipelines
CONTRACTOR shall place particular emphasis on aspects of the Work relating to the
safety of working in proximity to existing pipelines and services. The Work shall be
carried out under a specific Permit-to-Work system.
CONTRACTOR shall prepare and submit, for COMPANY approval, procedures and
method statements which shall specifically address this aspect.
Notification is required for entry into all Plant areas.
2.3.7
Material Traceability/Pipe Tracking System.
CONTRACTOR shall prepare and issue, for COMPANY approval, a procedure to
operate electronic pipe tracking system together with import, storage, export and
report upon, pipeline data. COMPANY shall approve the structure of the data file in
order to permit the import/export of data between CONTRACTOR and COMPANY.
2.3.8
Extra Works
If deemed necessary, and when required by the COMPANY in writing, the
CONTRACTOR shall provide all the labour and materials necassary for any extra
works required by the COMPANY. Payment will be in accordance with the
CONTRACTOR’ s Price List.
2.3.9
Access by COMPANY Representative
The CONTRACTOR shall grant the COMPANY’ s representative free access to any
location where works described in these specifications are being executed.
2.3.10.
Equipment Nameplates
CONTRACTOR shall provide nameplates for all permanent equipment items installed
during the course of works. All texts shall be submitted to the COMPANY for the
approval prior the manufacture. All instruments, manual valves and other permanent
items shall be provided with Stainless Steel (SS) tag plates by CONTRACTOR as
approved by COMPANY as part of this Scope of Work.
2.3.11
Material Identification
CONTRACTOR shall compile material list for all permanent material (pipes, valves
and fittings, etc.) to ensure traceability and material identification. The list shall
contain, as a minimun, the following details for each item of permanent material:
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909





Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
18 / 43
Stamped Pipe/Fitting number
Cast/Heat number
Painted Serial number
Individual pipe Lenghts
Valve Manufactures
2.4
Parties Involved in the Project
2.4.1
Parties Involved in the Work
The Parties outlined here below, shall be involved in the implementation of the
project:
1)
2)
3)
4)
COMPANY
CONTRACTOR
Sub Contractor (s) including their own Sub Contractor(s)
Manufacturers (s) including their own Sub Contractor(s) Suppliers (as and when
required)
5) Welding Inspectors, anticorrosion Coating Inspectors, Concrete coating
Inspectors, Third Party agencies appointed by CONTRACTOR and approved by
COMPANY to carry out certain inspection and testing as described in the Tender
Documents.
2.4.2
Parties Interfacing with the Work
Responsibility for liaison with third parties for the purpose of obtaining permits shall lie
with CONTRACTOR. COMPANY shall use its best endeavours to help where
possible.
Authority
Feature to be crossed
i)
ii)
Harbour Area
Rivers and Navigable Waterways
Nigeria Port Authority
Ministry of Water Resources in
Imo/Delta State and Port Authority
iii) Federal Ministry of Work & Housing
Chief Engineer in Imo/Delta State
iv) Ministry of Work in the Imo/Delta State
v) N.I.T.E.L. in Imo/Delta State
vi) N.E.P.A.
vii) Other Companies
viii) NAOC operating staff supervisors
2.4.3
Federal Trunk Roads
State Roads
Telephone Cable
Electricity Lines
Pipeline or Other Utilities
Akri Flow station and Kwale Gas Plant
facilities
Other CONTRACTOR at Site
CONTRACTOR shall acquire full knowledge of other CONTRACTOR at Site directly
or indirectly involved in the project and at this effect, shall make all the necessary
provisions in its organisation and planning for the performance of the work
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
3214.10.GGPD.10909
3
ENGINEERING
3.1
Introduction
Contractor Identification
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
19 / 43
Engineering shall include the necessary FEED engineering including design
optimisation and finalisation, detailed engineering including procurement, supply,
construction, pre-commissioning, commissioning and start-up and any other
engineering work that CONTRACTOR may require to comply with the Scope of Work.
CONTRACTOR shall develop the engineering on the basis of the Basic Design
Document included in the Contract.
The detailed engineering shall include but not limited to, the following :






The NPS 12 new Gas Pipeline,
Cathodic protection system,
NPS 12 new Gas Pipeline connections
NPS 12 Gas Pipeline Slug Catcher
Any other work considered necessary by the contractor and approved by
company toward the realization of the oil pipeline project.
The detailed engineering also involves the preparation/development and review of
Technical Specification and Data Sheets for Pipeline Security System, particularly
the Fibre Optic Intrusion & Leakage Monitoring/Detection System.
COMPANY reserves the right to issue to CONTRACTOR additional documentation for
information or clarification purposes, at any time. Such documentation shall not give
rise to any claim whatsoever if the content of such documents does not alter the
CONTRACTOR Scope of Work or if the alteration is of such a nature that is deemed
necessary for the safe operation of the pipeline.
3.2
Basic Design Endorsement
CONTRACTOR recognises that the Basic Design Documents do not define the work
in detail but are fit and sufficient for the purpose they are intended to define the basic
principles and requirements for the reliable performance of the Work.
Before Contract award, CONTRACTOR shall review and control all Basic Design
documents and seek for possible clarification or missing information. The
Endorsement of Basic Design document activity shall be carried out discipline by
discipline and shall include technical meeting with COMPANY, as required.
The endorsement activity shall be substantiated by the issue of the Endorsement
Report, by CONTRACTOR to COMPANY for approval.
The review and endorsement activity shall be considered as an integral part of
CONTRACTOR Scope of Work before Contract award. As a consequence, adaptation
or modification shall require COMPANY approval. Any other work in any way resulting
from such endorsement or otherwise connected there with, shall be considered to be
part of CONTRACTOR’s Scope of Work.
Topographical survey data provided by COMPANY are integral part of Basic Design
documents and as such endorsed by CONTRACTOR. Therefore any claims from
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
20 / 43
CONTRACTOR arising from the lack of knowledge in respect of topographical survey
affecting the work shall not be accepted by COMPANY under any circumstance.
Additional surveys carried out by CONTRACTOR shall be at his own expense as a
part of Scope of Work, subject to the constraint of security and obtaining of relevant
permits.The CONTRACTOR shall carry out a field survey and stake out the route of
the pipeline on the ground. Pipeline alignment stakes shall be placed at close enough
intervals along the pipeline centreline and at every point of intersection of two
tangents, such that the alignment of the pipeline is maintained throughout. In addition,
reference offset markers shall be placed at a distance not exceeding 30 m from the
survey centreline at all stakes. The location, distance and deflection of the offset
markers from the pipeline centreline shall be recorded to permit the re-establishing of
the pipeline stakes. The CONTRACTOR shall survey the route linking up the B.M’s of
the line to the existing trigonometric points. Topographic and detailed surveys shall be
carried out at the following locations:



main roads and major rivers
canals and existing pipeline crossings
particular areas requiring special design activities.
All topographic works shall be in accordance with “Specification for topographical
survey works” (doc. 3214.10.BADG.35888).
3.3
General Engineering Requirements
CONTRACTOR shall prepare all necessary engineering documentation required for
the Work, as specified in the Contract documents.
CONTRACTOR shall perform the detailed engineering in accordance with its own
engineering procedures amended to suit the requirements of Project Coordination
Procedures.
CONTRACTOR’s engineering activities shall generally include but not limited to the
following:
i)
ii)
Prepare drawing list and document index
Implement document control of CONTRACTOR, Sub Contractor and
Manufacturers/Suppliers drawings and documents using a computer
data base in accordance with COMPANY requirements
iii) Prepare QA/QC procedures
iv) Review drawings and documents for safety
v) Prepare data sheets and specifications for material requisition
including line pipes
vi) Provide material take-off and continuous monitoring of material
changes
vii) Carry out preliminary surveys to determine the soil resistivity levels of
different locations.
viii) Carry out protection current calculations, potential attenuation
calculation, groundbed dimensioning & sizing of the feeding system
(transformer/rectifier).
ix) Prepare layouts & drawings of the CPS insulating joints, feeding units
& junction boxes, groundbeds, test points, feeding cable routes.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
21 / 43
x)
Installation details for feeding units, groundbeds, junction boxes, test
points.
xi) Prepare data sheets for all CPS materials.
xii) Evaluate technical inquiries and bids
xiii) Review and approve Manufacturers/Suppliers data and drawings
xiv) Witness and report performance test at Manufacturers/Suppliers shop
xv) Review Manufactures/Suppliers recommended spare parts and
prepare detailed list for two years operations
xvi) Co-ordinate and verify Manufacturers/Suppliers detailed engineering
and documentation
xvii) Prepare document for Sub Contractor(s)
xviii)
Prepare interface documents, review and validate documents
prepared by other Parties and existing drawing as applicable to the
Work.
xix) Prepare and issue all documents and provide assistance required to
allow COMPANY to obtain approval from Authorities at all stage of
design and construction prior to start up of the construction activities.
xx) Provide access to facilities, data tools and results to COMPANY for
carrying out detailed engineering safety and technical audit.
xxi) Prepare final documentation as specified in Section 3.5 and in
accordance with the requirements set forth in the COMPANY’s
CONTRACTOR agreements.
3.4
Specific Engineering Requirements
CONTRACTOR shall implement and complete the Basic Design documents and
prepare all new documents as required to complete the Work.
CONTRACTOR shall prepare and issue detailed engineering material specifications,
construction specification and detailed calculations/analyses related to pipeline
stress, hydraulics, stability, expansion, bends, anchoring forces, anchoring blocks,
hydrostatic testing and depressurisation etc. including program validation reports,
computer print outs and CD as applicable.
Caesar 11 Stress Analysis software shall be used for the stress analysis modelling.
Contractor shall submit stress analysis Model along side the Stress analysis report for
review. All software used shall be the latest version.
CONTRACTOR shall produce all necessary detailed drawings to define the pipeline
and the appurtenances. The drawing shall include but not limited to the following:
i) P & ID’S
ii) Process calculation Report
iii) Typical drawings
iv) Alignment sheets
v) Pipeline General Drawing
vi) Ground profile of pipeline route axis
vii)Cathodic protection system drawings & layouts
viii)
Civil works drawings
-
CONTRACTOR shall prepare detailed calculation/analysis, drawings and procedures
for the pipeline project and all type of crossings, which shall include but not
necessarily be limited to the following. Similarly Design factor to be used for
calculating pipeline wall thickness shall be as per recommendations of Basic
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Engineering
Design
Data
(Design
Premise)
07486.PLI.MEC.SPC Design Criteria For Buried Pipeline.
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
3214.10.BGRA.16519,

Crossings of watercourses
The design shall include topographical survey, soil investigation,
hydraulic study and assessment of impact on the depth of laying
the pipeline in order to define the buoyancy and protective
measures.

Crossings of roads and tracks.
The design shall include topographical survey, soil investigation
and the traffic impact on the depth of laying the pipeline in order to
determine the protective measures.

Crossings of pipelines and flowlines.
CONTRACTOR shall conduct any necessary location survey and
provide temporary protective measures/procedures as required to
perform the Work.

22 / 43
Crossings of electrical cables and conduits
CONTRACTOR shall conduct any necessary location survey and
provide temporary protective measures/procedures as required to
perform the Work.
CONTRACTOR shall develop the detailed engineering and design of a permanent
cathodic protection system.
CONTRACTOR shall develop detailed procedures for the hot-tapping connections (if
applicable).
CONTRACTOR shall develop maintain and submit to COMPANY on a regular basis a
comprehensive list of drawings and documents (Document Register).
CONTRACTOR shall carry out complementary site survey including soil resistivity
survey as required for the detail design, cathodic protection and construction.
CONTRACTOR shall prepare and update during the performance of the work and
shall maintain and submit to COMPANY after completion of the Work a complete set
of “As built” drawings.
CONTRACTOR shall prepare and update during the performance of the work and
shall maintain and submit to COMPANY after completion of the Work all construction
and material line pipe data. The structure of the file data shall be approved by
COMPANY to assure the import in COMPANY’s Pipe Tracking System.
3.5
Final Documentation
The final documentation shall include but not necessarily be limited to:
i)The operating manual
ii)
The safety manual
iii)
Final issue of all pipeline drawings “As built”, documents and
Manufacturers/Suppliers data
iv)
All welding procedures records, certified and complete
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
v)
vi)
vii)
viii)
ix)
x)
3.6
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
23 / 43
All welders qualification records, certified and complete
All welding radiography and all other NDT test records certified
and complete
Final pipeline report showing joint number, length, installation
locations weld number bends, survey record and computation
properly signed and complete and all other data and information
as required by the Contract
Complete data transfer dossier for inclusion (by COMPANY) in the
PTS system
Hydrostatic test certified and completed
Cathodic protection tests record certified and complete.
Drawings and Documentation’s
This paragraph outlines the COMPANY’ s requirements with respect to the project
and final drawings to be supplied by the CONTRACTOR.
It is recommended that a CAD system is used to prepare all drawings. In case of
exceptions to this requirement, the COMPANY shall approve the extent of the CAD
application.
Drawings shall be prepared according to COMPANY standards and CAD
specifications.
The CONTRACTOR is responsible for updating all drawings to “As-Built” status and
signing them off on completion of the construction.
The COMPANY will provide the successful bidder with the COMPANY format sheets,
standard symbology, layering, text and line standards all on floppy disk.
Drawing numbers will be supplied by the COMPANY. All reference drawings and
matchline cross-references shall use COMPANY drawing numbers.
All documentation to be supplied by the CONTRACTOR will be stored on disk file
using the following software:




Drawings
Text documents
Electronics sheets
Calculation Data
Autocad
Microsoft Word
Microsoft Excel
Standards ASCII characters
(Releases to be defined with COMPANY)
3.7
Engineering Documents Approval
All engineering documents shall be approved by COMPANY engineering department
or any other party nominated by COMPANY in writing to the CONTRACTOR. The
approved engineering documents shall be stamped “ Approved for Construction “ and
duly signed by COMPANY QA/QC officer or the equivalent in COMPANY nominated
party. Engineering documents in this instance refer to all documents that involve
review, fabrication or construction and installation.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
3.8
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
24 / 43
Maintenance Engineering(CMMS Data).
Computerized Maintenance Management System Data Documentation
EPC Contractor presents as being competent in providing all maintenance data
required for the proper maintenance of equipment and facilities in the contract.
Company uses Format SAP PM software for the management of maintenance.
Contractor shall provide all the data on the equipment and facilities in this contract
according to Company specifications and SAP PM templates for upload to the
software.
EPC Contractor shall have in his workforce at least one (1) SAP PM Certified
Engineer with a minimum experience of two(2)years. Document on the Certification
and experience are to be provided as proof.
EPC Contractor’s SAP Certified Engineer shall demonstrate competence/ proficiency
in the use of SAP PM and maintenance engineering in carrying out all the under
listed activities.
EPC Contractor shall review the standards listed in conjunction with drawings and
P&IDs ( where available) to understand what is required. The standards are :
27954.MAN.GEN.SDS
Maintenance Management Data from Vendors
& EPC Contractors .
20666.MAN.GEN.SDS
Maintenance Entities Requirement
20198.COO.GEN.SDS
Item Numbering
06215.DOC.GEN.SDS
Facilities Functional Units
20665.MAN.GEN.SDS
Plant Breakdown Specification
Following due diligence, professional ethics, Eni safety standards and anti corruption
ethics, The EPC Contractor shall deliver the CMMS work scope listed below.
The EPC Contractor shall provide electronic manuals from Original Equipment
Manufacturers(OEMs) as a guide to SAP standard texts (i.e. detailed task instructions
for the maintenance of each equipment /items installed)and bills of materials.
The EPC Contractor shall provide relevant Technical Data of each maintenance item
for inclusion in SAP according to Eni standard document no. 20666.MAN.GEN.SDS Maintenance Entities Description.
The EPC Contractor shall provide a Bill of Materials:
Do equipment report (type/class/category, tag number, description, manufacturers
model/type/arrangement number/frame, location, etc) as necessary to identify and
collate the different types of equipment, their numbers and where they are used.
Provide a bill of materials (spare parts list) per equipment, complete with warehouse
management parameters (minimum level, maximum level, reorder level and
estimated annual consumption) per station/plant.
Some maintenance items already have some of this data in SAP, but contractor shall
update existing ones where necessary and provide for the missing ones according to
Eni/NAOC standards.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
25 / 43
Prepare/update bill of materials for each Maintenance Strategy (i.e. maintenance
intervals) and plan, where materials are needed to carry out the job.
The EPC Contractor shall provide for and prepare all the SAP PM Templates that are
necessary for loading additional data into Format SAP PM software, ready for SAP
PM implementation.
Such templates include but may not be limited to the following:
(1)Functional Location Template,
(2)Equipment Template,
(3)Material Bill of Materials,
(4) Bill of Materials Contents,
(5)Measuring Points Template,
(6) Standard Texts Template
(7)Task Lists Template,
(8) Maintenance Items Template,
(9) Maintenance Plans Template and
(10) Objects Lists Template
(11) Equipment life expectancy documentation
4.0
CONSTRUCTION WORK
4.1
General
Construction Works shall be understood as all construction activities including precommissioning, commissioning and start-up, to ensure that the built pipeline is in
conformance with the design, mechanically complete, as per the Contract Documents
and ready for COMPANY taking over.
All construction Works shall comply with approved construction drawings and
specifications and all applicable codes standards and regulations outlined in the
Design Premises Doc. No. 3214.10.BGRA.16519
The construction Work to be performed by CONTRACTOR shall include but not
limited to, clearing and grading of Right of Way, unloading, loading, hauling, storage
and stringing of line pipes and other materials; all ditching, bending, concrete coating
of line pipe, welding of pipe including coating of field joints and coating repairs,
lowering-in and backfilling; tie-in, installing river, creeks and other watercourses
crossings including banks restoration, crossing of roads, pipelines, flowlines, cable
and other buried or above ground structures painting,hot-tapping connections (if
applicable), valves installation, internal pipeline cleaning, hydrotesting and dewatering, gauging and cleaning-up and restoring pipeline Right of Way including
temporary extrawork space; providing the necessary engineering, management,
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
3214.10.GGPD.10909
Contractor Identification
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
26 / 43
supervision, personnel equipment, materials and support facilities and performing all
other works necessary to completely construct the NPS 12 Gas Pipeline in
accordance with the specifications and drawings to be prepared by CONTRACTOR
and approved by the COMPANY and the provisions outlined in Contract.
CONTRACTOR shall furnish all labour, tools supplies, vehicles, construction
equipment construction camps, storage and marshalling yards, laydown yards;
hydrostatic testing and de-watering equipment; gauging and inspection tools and
equipment, welding rods, concrete materials, pipe concrete coating materials, pipe
coating materials for coating of field joint, coating repairs, material for painting,
materials required for bedding and padding of pipeline trench, bank restorations,
materials for maintaining and restoring access roads, culverts; material sacks for
restoration and all other designated materials, equipment, supplies and services
which may be required for performing and completing the Work.
CONTRACTOR shall also manage, plan and coordinate all external interfaces related
to the construction of the pipeline as outlined in Section 2.4 of this document.
4.2
Construction Management
CONTRACTOR shall set up a Project Construction Management team headed by a
Project Site Manager who shall report to CONTRACTOR Project Manager and
provide full construction management at the Work Site. Under the authority of Project
Site Manager CONTRACTOR shall develop and implement an organisation in order
to assure the following:
i)
Safety:
CONTRACTOR shall have a project safety program,
approved by COMPANY
ii) Security: CONTRACTOR shall have a project security program
(considering the present security suitation in the Niger Delta)
approved by COMPANY.
iii) Quality Assurance/Quality Control, according to the requirements of
COMPANY and of the project
iv) Community Relation Management
v) Project Control and Scheduling
vi) Material to cover all aspect related to material receiving, storage and
issuing
vii) Material tracking
viii) Field engineering including:
 Technical supervision
 Engineering follow-on
 Field survey and data collection for “As built”
 Field survey and data collection for the implementation of PTS
i) Material management and control
ii) Transport
iii) Attendance to management and weekly progress report
iv) Monthly measurement and reporting on work progress
v) Management of Sub Contractor(s)
vi) Management of Manufacturer/Supplier at site
vii) Taking measures to protect all adjacent or adjoining property against
damage by construction activities
viii) Management and disposal of construction debris and construction
surplus material
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
27 / 43
ix) Management of changes.
4.3
Safety
CONTRACTOR shall take extra care in conjunction with NAOC safety rules to assure
that the integrity of the existing Pipeline/Flowlines, Environment, Flowstations and
Manifold are maintained throughout the duration of the works.
4.4
Labour
CONTRACTOR shall supply and assign to the site all labour required to perform the
work such as foremen, high skilled, skilled, semi-skilled workers and helpers required
to perform the Work. CONTRACTOR shall also provide all other labour as required to
proper support during the work execution.
4.5
Tools and Consumables
CONTRACTOR shall provide all electrical and air powered machines and hand tools
and all consumables including gasoline, diesel fuel lubricants, gases, welding rods,
test material, miscellaneous hardware and all other tools and consumable required for
the construction activities.
4.6
Mobilisation
CONTRACTOR shall mobilise all equipment, personnel, support facilities,
storage/marshalling yards, construction camps, warehouse, and laydown areas as
required to perform the Work.
4.7
Transport of Pipes and Materials from Port of Entry to Storage/Marshalling Yard
CONTRACTOR shall be responsible for offloading at shipside all pipes bends and
other permanent materials at the port of entry and loading and transporting the
materials to the storage/marshalling or concrete coating yards in accordance with the
requirements of project specifications and the Contract.
4.8
Transport of Pipes and Materials to Work Site
CONTRACTOR shall provide all labour and equipment necessary to load and
transport all pipes and other materials from storage/marshalling or concrete coating
yards to the Work Site. Transport of line pipes, materials, equipment personnel and
others to the Work Site will require CONTRACTOR to furnish adequately sized
terrestrial vehicles (trucks) and barges.
4.9
Construction Camps
CONTRACTOR shall provide temporary construction camps at the Work Sites for the
accommodation of its own
personnel, COMPANY personnel and
Manufacturers/Supplier. The camps shall include medical, catering and laundry
facilities. The camp shall also contain all necessary field office accommodations for
the execution of the work. CONTRACTOR shall be responsible for all rental, utilities,
temporary support facilities, permits, security etc. required to provide a full functional,
operating camp.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
3214.10.GGPD.10909
4.10
Contractor Identification
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
28 / 43
Camp and Field Office Accommodation for COMPANY Personnel
CONTRACTOR shall provide living, office accommodation and transport (i.e. vehicles
and boats) for COMPANY and COMPANY Representative field personnel for the
duration of the installation Works.
The office and accommodation shall be in accordance with COMPANY specification
for office and site accommodation included.
4.11
Construction Work
CONTRACTOR shall be responsible for completing the Scope of work in accordance
with the Contract specification drawings and procedures.
The Work to be performed by CONTRACTOR is to install and test:
i) 15 kilometres approximately of NPS 12, 11.1/12.7mm wall thickness, API
5L-X65 SMLS pipeline and 3 kilometres approximately of NPS 24 (HDD
across river niger), 15.9mm wall thickness, API 5L-X65 SAW pipeline.
ii)
Cathodic protection system
iii) Slug Catcher
4.12
Detailed Work Description
4.12.1
Pipeline
Civil Works
The civil work to be carried out by CONTRACTOR include, but not limited to the
following:
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
xiii)
xiv)
xv)
xvi)
xvii)
Access roads
Pipe storage areas and marshalling yard
Concrete coating of line pipe
Right of Way clearing and grading
Handling of topsoil (if required)
Trenching in dry and swamp and mangrove swamp areas
Trenching at watercourse crossing
Trenching at road and track crossings
Trenching at crossing of buried and above ground existing facilities
Backfilling of pipeline trench in dry and swamp and mangrove
swamp areas
Backfilling of pipeline trench at watercourse crossings
Backfilling of pipeline trench at roads and track crossings
Backfilling of pipeline trench at crossings of buried and above
ground existing facilities
Clearing and restoration of Right of Way
Restoration of watercourses banks
Restoration of roads
Trenches for ancillary and associated works
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
xviii)
xix)
xx)
xxi)
xxii)
xxiii)
xxiv)
xxv)
xxvi)
xxvii)
xxviii)
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
29 / 43
Water drainage and hydraulic defence works
Simple and reinforced concrete foundations and structures
Steel supports and walk way
Installation of line makers
Installation of warning signs
Installation of river crossing signs
Supply of all material for civil works
Clearing and reinstatement of all areas affected by the works
Fencing work.
Anchor block construction
All other works necessary to complete the Work.
Mechanical Work
The mechanical work to be carried out by CONTRACTOR include, but not limited to
the following:
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
Loading transport handling unloading and storing of all material
Stringing of all materials along the working R o W
Bending of pipes
Cleaning and coupling
Welding
Non destructive test NDT(radiographic gamma ray and ultrasonic
test)
Installation of casing pipes and assemblies
Pipe laying in dry areas, swamp areas, mangrove swamp areas,
watercourses crossings
Installation of pipeline fittings
Internal pipeline cleaning, gauging and hydrostatic test
Pipeline de-watering
BENDING
As per Technical Specification for Pipeline Construction.
PIPE LAYING, LINE-UP AND WELDING
As per Technical Specification for Pipeline Construction.
COATING OF FIELD JOINTS
As per Technical Specification for Pipeline Construction.
PAINTING OF ABOVE GROUND INSTALLATION
As per Technical Specification for Pipeline Construction.
The CONTRACTOR shall provide NAOC with all painting procedures in accordance with
Technical Specification for Pipeline Construction.
LOWERING-IN
No pipe shall be lowered into the trench until the trench has been inspected, prepared and
approved for receiving the pipe.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
30 / 43
The CONTRACTOR shall respect the lowering-in procedure as per Technical Specification for
Pipeline Construction.
BACKFILLING AND ROW RESTORATION
The CONTRACTOR shall respect the procedure for pipeline backfilling and clean-up as per
Technical Specification for Pipeline Construction. The contractor, at the end of the construction
exercise shall ensure that the pipeline right of way (ROW) and any other area affected by the
job are restore to there original position before the commencement of the construction activity
CATHODIC PROTECTION SYSTEM
Cathodic protection shall be installed as per Technical Specification for Pipeline Construction
3214.10.BTST.16524, in accordance with 27589.VAR.COR.PRG rev.1 – Guidelines for Design
and Constuction of Cathodic Protection System and with Cathodic Protection System Design
Philosophy, 3214.10.BERV.23854. Cathodic protection system shall consist of :
Permanent CP system
The works to be carried out by CONTRACTOR for the installation of cathodic protection
system include, but not limited to the following:
i) Transformer rectifier Units installation
ii) Impressed Current Anode installation
iii) Impressed Current Anode Ground Beds
iv) Sacrificial Anode installation
v) Sacrificial Anode Groundbed installation
vi) Reference Electrodes installation
vii) Junction boxes installation
viii) Surge Diverters
ix) Connecting cables
x) Tests points
xi) Cable to pipe Connections
Temporary cathodic protection system
CONTRACTOR shall design, supply and install all equipment and material necessary for
temporary cathodic protection.
PIPELINE TESTING & PRECOMMISSIONING
CONTRACTOR shall carry out the testing and precommissioning in accordance with following
Specifications.
3214.10.BTST.16524
3214.10.BTST.16535
3214.10.BTST.16576
Technical Specification for Pipeline Construction
Pipeline Cleaning Gauging, Filling and Hydrotesting
Pipeline precommissionig
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
31 / 43
WORKING ADJACENT TO EXISTING FACILITIES
CONTRACTOR shall place particular emphasis on aspects of the work relating to the safety of
working in proximity to existing pipelines and services and existing facilities in plants areas.
The work shall be carried out under a Permit-to –Work system as specified by the relevant
operating Companies.
CONTRACTOR shall prepare and submit, for Company approval, procedures and method
statements which shall specifically address this aspect.
Notification is required for entry into the Plant areas. At least 2 weeks’ notice or as may be
required, for the scheduled Work is required.
PIPELINE APPURTENANCES
The Pipeline Appurtenances are defined in the Technical Specification for Pipeline
Construction.
The Pipeline Appurtenances shall be realised in accordance with the detailed design and
Technical Specification for Pipeline Construction.
a)
Isolating joints
Isolating joints shall be located as indicated in the project drawings and installed as per
Technical Specification for Pipeline Construction.
b)
Pipeline markers and warning signs
As per Technical Specification for Pipeline Construction procedures.
AS-BUILT AND REQUIRED DOCUMENTATION
The CONTRACTOR shall prepare the As-Built File according to approved procedure
INSTALLATION OF FIBRE OPTIC CABLE IN PIPELINE TRENCH
CONTRACTOR shall install the Fibre Optic Cable (F.O.C.) along the pipeline route, between
AKRI and KWALE (refer to FOC Supply & Installation Specification, Doc.No:
3214.10.BISP.26807).
The CONTRACTOR shall provide and shall be responsible for all the following activities:
-
-
The installation of F.O.C. into an excavated trench.
The installation of F.O.C. into steel pipe, installed by CONTRACTOR at road
crossing.
The installation of F.O.C. in HDPE duct installed by CONTRACTOR at
swamp/mangrove areas and river crossing. Contractor to ensure that the HDPE is
supported in-place (tied/attached to the pipeline) to prevent vibrations created by the
water waves.
The final termination of F.O.C at both ends (Akri and Kwale). Refer to Section 1.6
above.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
-
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
32 / 43
The correct use of backfill materials to ensure that the strain limits of the cable are
not exceeded during backfill activities.
The joint, test and commissioning of the complete Fibre Optic Cable to serve the
three functions highlighted in Section 1.0
It is expected that CONTRACTOR will provide suitable equipment for all movements of the
F.O.C., to ensure that no mechanical damage can occur. Contractor is also expected to seek
the support of experienced personnel/sub-contractors when undertaking the aforementioned
operation.
4.12.2 Scraper traps construction work (Not Applicable)
General
Construction Works shall be understood as all construction activities including
pre-commissioning which entails verification of all conformity to ensure that the
built scraper traps are in conformance with the design, mechanically complete
and ready for commissioning as per the Contract Documents.
All construction Works shall comply with approved construction drawings and
specifications and all applicable codes standards and regulations outlined in the
Pipeline Design Premise Doc. No. 3214.10.BGRA.16519
The construction Work to be performed by CONTRACTOR shall include but not
limited to:
Supply all labour, plant, materials, consumables, supervision, fuel, electric
power, tools, equipment, craneage, transport, accommodation and each and
every item necessary for the accomplishment of the Work.
Supply of all materials necessary for the performance of the Work.
Carry out preparatory Work including concrete batching plant establishment and
production of test cubes, welder qualifications, weld procedure specifications
and procedure qualification. All tests, qualifications, procedures and
specifications are for Company review, witness and Approval prior to
commencement of the Work;
Provide setting out, levelling, establishing of temporary bench marks,
monuments and final survey work;
Supply labour and equipment for de-watering, inclusive of treatment and piping
to dispose of water to an approved discharge point adjacent to the Sites limits.
De-watering is Contractor’s responsibility, and CONTRACTOR shall at all times
have suitable equipment on the Site;
Carry out Site preparation including provision for access fence and gates and
any hard standings that may be required to carry out the Work;
Submit samples of items with relevant certificates for Approval prior to use,
including slump and cube tests for concrete as required;
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
3214.10.GGPD.10909
Contractor Identification
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
Carry out all testing as specified. Provide all documentation/certificates to
validate material quality;
Carry out fabrication, erection and hydrostatic testing, and installation of pipe
work, valves, blinds and other in-line items, including installation and removal of
temporary spools in place of those items for activities such as testing and
flushing.
Undertake testing, Pre-commissioning of mechanical, electrical and instrument
systems;
Construct paved areas surrounding scraper traps;
Maintain and keep clean temporary and permanent roads and paving;
Provide all environmental control and mitigation measures to meet noise, air
emission water and waste discharge, etc, requirements and principles
described within the Contract;
Clean up Sites to satisfaction of Company. Dispose of building/construction
waste as the Work proceeds in accordance with the requirements of the HSE
section of the Contract;
Remove all temporary access and all other Temporary Works including fencing
and gates and re-instate to original condition or better.
CONTRACTOR shall also manage, plan and coordinate all external interfaces
related to the construction of the scraper traps and associated facilities.
Equipment, Machinery and Packages
The CONTRACTOR shall provide for the installation of equipment, machinery and
packages, including in detail:
-
Materials handling and all transportation to the site of installation
Setting down on prepared supports and foundations
All levelling and necessary alignment
Final hydrostatic testing, flushing and cleaning
Internal and external cleaning, flushing, air drying of piping after hydrostatic
testing
Installation and removal of temporary equipment, supports and scaffolding for
installation and testing purposes
Supply and fixing of anchor bolts
Painting touch-up
Protection against possible mechanical damage and against dust, humidity and
rust.
Swamp area crossings
Pipe laying of sections of the line running through swamp areas, where the load
bearing capacity of the ground is insufficient for the passage of works plant, shall be
carried out according to the detailed design and Technical Specification for Pipeline
Construction.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
33 / 43
Company Identification
3214.10.GGPD.10909
Contractor Identification
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
34 / 43
The CONTRACTOR shall carry out supplementary investigations, in addition to those effected
during the design phase, in order to define the construction criteria, the plant to use and the
detailed work programme.
In case, the Right-of-Way can first be improved by means of tree trucks or other low density
material suitable for the purpose. In this case, the CONTRACTOR shall submit a detailed
report to the COMPANY prior to commencing the work.
Two methods may be considered for the installation of pipelines in swamps:

The flotation method, where the pipeline is laid from a barge moving through a
channel cut along the right of way.

The push-pull method, where the ditch is dug by a lightweight track-driven machine
and the pipeline , fitted with buoyancy tanks if necessary, is pulled along the ditch
and sunk. This method is preferred in environmentally sensitive areas.
Coating and Painting
CONTRACTOR shall provide coating and painting as follows:
i)
ii)
iii)
iv)
Coating of field joint with heat shrinkable sleeves
Repairs of line pipe coating at concrete coating yard and at site
Coating/repair the coating of fitting
Painting of a/g piping and steel structures.
CONTRACTOR shall provide and maintain all material and equipment necessary for
the sandblasting, coating and painting of piping, pipe supports and steel structures.
Concrete Coating
CONTRACTOR shall provide materials and carry out the concrete coating of line
pipes for the swamp, mangrove swamp and watercourse crossings.
Hydrostatic Test
CONTRACTOR shall perform the hydrostatic test of the pipeline.
CONTRACTOR shall provide all necessary manpower, construction tools and
equipment necessary to perform this activity.
Dewatering
CONTRACTOR shall perform the de-watering of the pipeline.
CONTRACTOR shall provide all necessary manpower, construction tools and
equipment necessary to perform this activity.
Pre- Commissioning
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
35 / 43
CONTRACTOR shall perform the pre-commissioning of the pipeline.
CONTRACTOR shall provide all necessary manpower, construction tools and
equipment necessary to perform this activity.
Commissioning and start-up
CONTRACTOR shall perform the commissioning and start-up of the pipeline.
CONTRACTOR shall provide all necessary manpower, construction tools and
equipment necessary to perform this activity.
Hot tapping connection (If Applicable)
CONTRACTOR shall perform all hot tapping connection of the pipeline.
CONTRACTOR shall provide all necessary manpower, construction tools and
equipment necessary to perform this activity.
4.12.3
Cathodic Protection System
Permanent CP system
CONTRACTOR shall design, supply and install all equipment and material necessary
for cathodic protection.
5.0 PROJECT MANAGEMENT
5.1
Project Management
The CONTRACTOR shall perform all the Project Management services necessary for the
execution of the Project.
The CONTRACTOR shall appoint a capable and experienced Project Manager who will have
authority to act on behalf of the CONTRACTOR and be responsible for the overall direction,
co-ordination, control and performance of the Project activities.
The CONTRACTOR shall perform all activities necessary for implementation of the works
including the following:
-
Project supervision and control
Contract administration
Quality Assurance & Quality control
Planning & Scheduling
Project reporting
Invoice administration
Change in work administration
Issue and distribution of documents and correspondence to the COMPANY as per
contractual requirements in the English language
5.2)
Project Co-ordination and supervision
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
3214.10.GGPD.10909
Contractor Identification
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
36 / 43
The CONTRACTOR shall provide all the plans and procedures required or necessary to
ensure the following:
-
-
Ensure open communication lines with the COMPANY, Vendors, subcontractors and
other parties which the COMPANY may call upon to participate in the execution of
the works.
Provide the COMPANY with all the information requested in order to allow the
COMPANY to evaluate the performance of the CONTRACTOR, his Vendors and
subcontractors.
Ensure the proper co-ordination within the CONTRACTOR’s organisation for the
orderly and smooth development of the activities.
Provide for the required manpower in order to meet any and/or all the scheduled
work targets.
Conduct regular and programmed weekly and monthly meetings with the COMPANY
to discuss the status of the various phases of the works and methods for
resolving any difficulties encountered or foreseeable, and any other aspects of the
work. Issue minutes promptly after each meeting.
Evaluate all Works performed by Vendors and CONTRACTOR’s key personnel.
Inspection
The CONTRACTOR shall inspect and test all work as required by the drawings and
specifications and in line with good working practice and sound workmanship. He shall
maintain proper inspection and control of the work executed on-site in order to ensure a good
standard of workmanship at all times and compliance with all designs, standards,
specifications and codes.
The CONTRACTOR shall also provide services as and when required by the COMPANY's Site
Inspectors, and shall comply with all requirements imposed by them with respect to the issuing
of inspection certificates for all items.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
37 / 43
STRUCTURAL WORKS
6.1
Trap Support engineering (Not Applicable)
CONRACTOR shall carry out detailed engineering for the traps at Akri flowstation and
Kwale Gas Plant respectively, as indicated in the lunching & receiving trap area
layouts.
Engineering shall include the necessary FEED engineering including design
optimisation and finalisation, detailed engineering including procurement, supply,
construction, controls, testing and any other engineering work that CONTRACTOR
may require to comply with the Scope of Work.
CONTRACTOR shall develop the engineering on the basis of the Basic Design
Document included in the Contract, and shall design structures to take care of all
dead, live, test, impact, vibration, pipe expansion, thermal and friction, bundle pull,
wind, trasportation, lifting and erection loads and forces.
Engineering shall be in accordance with “Design specification for civil/structural works
(doc. No. 3214.10.BASP.33001)
CONTRACTOR shall prepare all necessary engineering documentation required for
the Work, as specified in the Contract documents.
CONTRACTOR shall perform the detailed engineering in accordance with its own
engineering procedures amended to suit the requirements of Project Coordination
Procedures.
CONTRACTOR’s engineering activities shall generally include but not limited to the
following:
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
Prepare drawing list and document index
Implement
document
control
of
CONTRACTOR,
Sub
CONTRACTOR drawings and documents using a computer data
base in accordance with COMPANY requirements
Prepare QA/QC procedures
Review drawings and documents for safety
Prepare data sheets and specifications for material requisitions
Provide material take-off and continuous monitoring of material
changes
Coordinate and verify Sub CONTRACTOR detailed engineering
and documentation
Prepare document for Sub Contractor(s)
Prepare and issue all calculation associated drawing.Provide
assistance required to allow COMPANY to obtain approval from
Authorities at all stage of design and construction prior to start up
of the construction activities.
Provide access to facilities, data tools and results to COMPANY for
carrying out detailed engineering safety and technical audit.
Prepare final documentation.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
6.2
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
Trap Support Construction (Not Applicable)
CONTRACTOR shall provide all necessary civil, structural and earth works
for the realisation of the platforms.
All works shall be conforming to the latest requirement of standards,
specifications and local related statutory regulation.
All material shall be from new stock.
All erection shall be supervised by competent trained personal fully
experienced in erecting structural steelwork.
CONTRACTOR shall provide erection method statement and all documents
shall be submitted for approval by COMPANY prior to commencement of
field work.
Procurement and erection works shall be in accordance with followings
project specifications:
3214.10.BAST.33004
3214.10.BAST.33003
3214.10.BASG.33007
3214.14.BAST.33011
General Specification for Structural
Steelwork Material and Fabrication
Specification for Concrete Works
General Earthworks Specification
Specification for Structural Steelwork
Erection
6.3 Structural Pipe Supports
CONTRACTOR shall provide the COMPANY with a detailed engineering
and construction procedure for all necessary pipe supports.
In particular the work to be performed shall include, but not be limited, to
the following:
a) Prefabrication in accordance with piping sketches and relevant standard
specifications
b) Materials handling and transport of prefabrication pieces from the place
of storage to the site.
c) Erection of pipe supports, ladders, walkways, etc. including partial
fabrication of any scaffolding as required, and testing, according to
drawings, standards and specifications.
6.4 Surface Preparation and Painting
Unless otherwise stated, all the aboveground pipeline section and all
aboveground supports shall be painted.
The CONTRACTOR shall provide:
a) Supply of paint products, blasting and cleaning materials, consumables
and any relevant equipment required for their application.
b) Painting (according to the relevant specifications and standards),
including:
 Collection from storage, handling and transport to the site of all painting
materials
 All sandblasting and cleaning of surfaces to be painted
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
38 / 43
Company Identification
Contractor Identification
3214.10.GGPD.10909


Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
Painting
Touch-up as required
6.5 Anchor Blocks
If piping stess analysis indicates that anchor blocks are required to restrict
above ground pipe movement, which may occur due to pressure and
temperature changes in the pipeline, specially designed anchor flanges
encased in concrete anchor blocks shall be installed underground on the
main line, before the pipeline is brought above ground.
CONTRACTOR shall provide:
a) Supply reinforcing steel, concrete works and materials, etc., handling
and transport of prefabricated pieces from the place of storage to the
site.
b) Construct concrete structures, foundations, piling, as required.
c) Supply and installation of anchor bolts (where required).
d) Erection of all necessary scaffolding (where required)
e) Supply and erection of structural steel.
f)
Grouting.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
39 / 43
Company Identification
3214.10.GGPD.10909
7
SUPPLY
7.1
COMPANY Supplied Items
Contractor Identification
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
40 / 43
The line pipe shall be supplied by the CONTRACTOR. Also, the coating of the line
pipe shall be the responsibilty of the Contractor, as coating is part of the scope of
work.
7.2
CONTRACTOR Supplied Items
All materials required to realise the project shall be supplied by the CONTRACTOR.
The CONTRACTOR shall be responsible for the overall procurement philosophy and
timely delivery of quipment and material to the construction site, within the project
schedule.
The CONTRACTOR shall assure the maximun possible standardization when
purchasing the various items appertaining to each plant system. The utilization of the
COMPANY’S List of Supplier shall be mandatory.
The M.T.O. attached to the tender documents shows indicatevily the materials,
regarding pipeline system, to be procured, CONTRACTOR shall perform the detail
engeeniring and provides for the final list of materials and quantities.
CONTRACTOR shall also procure all items and materials regarding all platforms such
as: steel pipes, pressings, beams, floor supports, grid floor pannels, handrailings and
all other permanent and consumable materials required to complete the work.
The Procurement activities to be developed by the CONTRACTOR shall include, but
shall not be limited to, the following:
- Section and submission to the COMPANY for approval of the list of
SUBCONTRACTORS that the CONTRACTOR proposes to utilize for the project.
- Identification and quantity calculations of equipments and materials to be
purchased, including spare parts.
- Material and equipment requisition preparation.
- Issue of inquires to Suppliers/SUBCONSTRUCTORS.
- Issue of purchase orders.
- Expediting of purchase orders.
- Factory inspection.
- Supply of test certificates and conformity certificates.
- Clearance of all the material and equipment through costums.
- Trasport to work site.
7.3 PROCUREMENT
The CONTRACTOR shall procure all items and materials necessary for the works, according
to the specifications provided or stated and/or the requirements listed below.
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
41 / 43
Line pipes
The 12” Line Pipes shall be supplied by Contractor
The characteristics of the Line Pipes supplied by Contractor shall be as follows:








Total length:
Pipe length (average):
Manufacture:
Nominal diameter:
Constant internal diameter:
Wall thickness:
Material:
Coating:
15,000 metres
12.2 m
SMLS
12”
304.9mm
11.1 mm/ 12.7
API 5L – X65
Coating of line pipes shall be
Contractors scope of work.
The technical characteristics and quantity of line pipes to be used for L.R. Bends shall be in
accordance with project data Sheet .
Flanges and fittings
The CONTRACTOR shall supply all flanges and fittings (Elbows, Bends, Reducers, Insulating
Joints, etc.) necessary for the works. In all cases these shall conform to the rating and
standards of the pipeline system.
Bends
All pipeline bends shall be produced by induction bending. Minimum bend radius shall be 5D
(where D is the pipe O.D.). All bends shall be supplied with straight tangent ends at least 500
mm in length. Bends shall comply with requirements of 20337.SLI.SPM.FUN. and project
specification 3214.10.BTST.16528.
Fibre Optic Intrusion Detection System
The CONTRACTOR shall supply the Fibre Optic Intrusion & Leakage Detection System
(complete with fibre optic cable, interface control equipment, accessories, etc.) in accordance
with project specifications and standards.
Pipeline Instrumentation
The CONTRACTOR shall supply all instruments required for the complete installation of the
pipeline (including instrumentation for the launching and receiving traps, Shut-Off Valve,
pressure switches, etc), in accordance with Project requirements and Specifications.
Warning Tape
The CONTRACTOR shall supply PWC warning tape, the tape shall be in accordance with the
project specification.
7.4
Spare Philosophy for Construction
Spare quantities are defined as follows:
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
Description
Line pipe
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
Spare quantities
3% of total length
Line pipe for bends
3% of total length – 10 m min.
L.R. Bends
Min. No. 1 =90°
Casing Pipe
5% of total length – 10 m min.
Casing collar spacer
5% of the total number – min. 2
Casing end seal
5% of the total number – min. 2
Bulk materials
1 piece min. for each size and w.t.
Heat shrinkable Sleeves
8.1
42 / 43
10 % of the total number
INTERNATIONAL STANDARDS
The latest editions of the following International Standards are to be considered as an integral
part of these Specifications;
Mechanical
ASME VIII
ANSI
API
ASTM
AWS
NACE
PFI
MSS
American Society of Mechanical Engineers
American National Standards Institute
American Petroleum Institute
American Society for Testing Materials
American Welding Society
National Association of Corrosion Engineers
Pipe Fabrication Institute
Manufacturers Standardisation Society
Piping
ANSI
ASTM
AWS
NACE
American National Standards Institute
American Society for Testing Materials
American Welding Society
National Association of Corrosion Engineers
Instrumentation & Electrical
AGA
CENELEC
IEC
NEMA
American Gas Association
European Committee for Electrotechnical Standardisation
International Electrotechnical Commission
National Electrical Manufacturers Association
Structural
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.
Company Identification
Contractor Identification
3214.10.GGPD.10909
AWS
Rev. index.
Sheet of Sheets
Validity
Status
Rev. No.
CD-BF
00
American Welding Society
Civil
ACI
BSI
American Concrete Institute
British Standards Institute
Surface Preparation & Painting
SIS
SSPC
Svensk International Standards
Structural Steel Painting Council
Safety & Firefighting
NFPA National Fire Protection Agency
Quality Systems
ISO
International Standardisation Organisation
8.2
COMPANY SPECIFICATIONS AND STANDARDS
In addition to what listed in Section regarding “PIPELINE MATERIALS” the following ENI
standards shall be applied in the execution of the works unless otherwise stated in this
document:
1) 06746.PLI.GEN.SPC Technical Specification for Pipelines and Flowlines
Engineering
2) 20368.PIP.MEC.FUN Carbon Steel Piping Welding
3) 00300PLI.COR.SDS
Transportation and Gathering Pipeline Dielectric Joints
for Pipeline Isolation
5) 07493.SLI.NAV.SPC
For Submarine Pipeline Welding Fittings
General Specifications:
- 310520-SG-10
Management
Contracts
Specification for Strategic Supply
- 310520-SG-02
Management Specification for EPC/EPIC Contracts
Data file: 331685937.doc
This document is property of ENI S.p.A. who will safeguard rights according to the civil and penal provision of the law.