REAFFIRMATION WITH EDITORIAL REVISION February 2011 Process Industry Practices Insulation PIP INSH1000 Hot Service Insulation Materials and Installation Specification PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process industry facilities, this Practice has been prepared from the technical requirements in the existing standards of major industrial users, contractors, or standards organizations. By harmonizing these technical requirements into a single set of Practices, administrative, application, and engineering costs to both the purchaser and the manufacturer should be reduced. While this Practice is expected to incorporate the majority of requirements of most users, individual applications may involve requirements that will be appended to and take precedence over this Practice. Determinations concerning fitness for purpose and particular matters or application of the Practice to particular project or engineering situations should not be made solely on information contained in these materials. The use of trade names from time to time should not be viewed as an expression of preference but rather recognized as normal usage in the trade. Other brands having the same specifications are equally correct and may be substituted for those named. All Practices or guidelines are intended to be consistent with applicable laws and regulations including OSHA requirements. To the extent these Practices or guidelines should conflict with OSHA or other applicable laws or regulations, such laws or regulations must be followed. Consult an appropriate professional before applying or acting on any material contained in or suggested by the Practice. This Practice is subject to revision at any time. © Process Industry Practices (PIP), Construction Industry Institute, The University of Texas at Austin, 3925 West Braker Lane (R4500), Austin, Texas 78759. PIP member companies and subscribers may copy this Practice for their internal use. Changes or modifications of any kind are not permitted within any PIP Practice without the express written authorization of PIP. Authorized Users may attach addenda or overlays to clearly indicate modifications or exceptions to specific sections of PIP Practices. Authorized Users may provide their clients, suppliers and contractors with copies of the Practice solely for Authorized Users’ purposes. These purposes include but are not limited to the procurement process (e.g., as attachments to requests for quotation/ purchase orders or requests for proposals/contracts) and preparation and issue of design engineering deliverables for use on a specific project by Authorized User’s client. PIP’s copyright notices must be clearly indicated and unequivocally incorporated in documents where an Authorized User desires to provide any third party with copies of the Practice. PRINTING HISTORY October 1997 Issued October 2005 Complete Revision August 2007 Editorial Revision February 2011 Reaffirmation with Editorial Revision Not printed with State funds Process Industry Practices Page 2 of 34 REAFFIRMATION WITH EDITORIAL REVISION February 2011 Process Industry Practices Insulation PIP INSH1000 Hot Service Insulation Materials and Installation Specification Table of Contents 1. Introduction................................. 4 1.1 Purpose ............................................. 4 1.2 Scope ................................................. 4 2. References .................................. 4 2.1 Process Industry Practices ................ 4 2.2 Industry Codes and Standards .......... 4 3. Definitions ................................... 5 4. Requirements.............................. 5 4.1 Project Scope .................................... 5 4.2 Materials ............................................ 5 4.3 Storage and Handling of Insulation Materials ............................................ 6 4.4 Installation Requirements .................. 6 4.5 Quality Plan...................................... 15 4.6 Inspection ........................................ 16 4.7 Repairs ............................................ 16 Process Industry Practices Data Forms INSH1000-D1 – Documentation Requirements Sheet The following data forms shall be part of this Practice only if indicated on the purchaser’s completed Documentation Requirements Sheet. INSH1000-D2 – Hot Service Insulation System Project-Specific Requirements INSH1000-D3 – Extent of Hot-Service Insulation INSH1000-D10 – Calcium Silicate Insulation System for Pipe and Equipment INSH1000-D11 – Expanded Perlite Insulation System for Pipe and Equipment INSH1000-D12 – Mineral Wool Preformed Pipe Sections Insulation System INSH1000-D13 – Mineral Wool Board Insulation System for Equipment INSH1000-D14 – Mineral Wool Blanket Insulation System for Pipe and Equipment INSH1000-D15 – Glass Fiber Preformed Pipe Sections Insulation System INSH1000-D16 – Glass Fiber Board Insulation System for Equipment INSH1000-D17 – Glass Fiber Blanket Insulation System for Pipe and Equipment Page 1 of 16 PIP INSH1000 REAFFIRMATION WITH EDITORIAL REVISION Hot Service Insulation Materials and Installation Specification February 2011 INSH1000-D18 – Cellular Glass Block and Fabricated Sections Insulation System INSH1000-D19 – Polyisocyanurate Insulation System INSH1000-D20 – Ceramic Fiber Blanket Insulation System INSH1000-D21 – Glass Fiber Needled Blanket Insulation System INSH1000-D22 – Flexible Elastomeric Cellular Thermal Insulation System for Pipe and Equipment INSH1000-D23 – Rigid Cellular Phenolic Thermal Insulation System for Pipe and Equipment INSH1000-D24 – User-Defined Thermal Insulation System for Pipe and Equipment INSH1000-F1 – Calcium Silicate Insulation for HC ASTM C533 Type I (inches) INSH1000-F2 – Calcium Silicate Insulation for PP ASTM C533 Type I (inches) INSH1000-F3 – Calcium Silicate Insulation – Combined Table ASTM C533 Type I (inches) INSH1000-F4 – Cellular Glass Insulation for HC ASTM C552 (inches) INSH1000-F5 – Cellular Glass Insulation for Pp ASTM C552 (inches) INSH1000-F6 – Cellular Glass Insulation – Combined Table ASTM C552 (inches) INSH1000-F7 – Fiberglass Insulation for HC ASTM C547, Type 1 / C612, Type I (inches) INSH1000-F8 – Fiberglass Insulation for PP ASTM C547, Type 1 / C612, Type I (inches) INSH1000-F9 – Fiberglass Insulation – Combined Table ASTM C547, Type 1 / C612, Type I (inches) INSH1000-F10 – Mineral Wool Insulation for HC ASTM C547, Type II or III / C612, Type IVB (inches) INSH1000-F11 – Mineral Wool Insulation for PP ASTM C547, Type II or III / C612, Type IVB (inches) INSH1000-F12 – Mineral Wool Insulation – Combined Table ASTM C547, Type II or III / C612, Type IVB (inches) INSH1000-F13 – Expanded Perlite Insulation for HC ASTM C610 (inches) INSH1000-F14 – Expanded Perlite Insulation for PP ASTM C610 (inches) INSH1000-F15 – Expanded Perlite Insulation – Combined Table ASTM C610 (inches) Process Industry Practices INSH1000-F16 – Polyisocyanurate for HC ASTM C591, Type II or IV (inches) INSH1000-F17 – Polyisocyanurate Insulation for PP ASTM C591, Type II or IV (inches) INSH1000-F18 – Polyisocyanurate Insulation – Combined Table ASTM C591, Type II or IV (inches) INSH1000-F19 – Elastomeric Foam Insulation for HC ASTM C534, Grade 3 (inches) INSH1000-F20 – Elastomeric Foam Insulation for PP ASTM C534, Grade 3 (inches) INSH1000-F21 – Elastomeric Foam Insulation – Combined Table ASTM C534, Grade 3 (inches) INSH1000-F22 – Phenolic Foam Insulation for HC ASTM C1126, Type III, Grade 1 (inches) INSH1000-F23 – Phenolic Foam Insulation for PP ASTM C1126, Type III, Grade 1 (inches) INSH1000-F24 – Phenolic Foam Insulation – Combined Table ASTM C1126, Type III, Grade 3 (inches) INSH1000-F25 – User-Defined Insulation for HC (inches) INSH1000-F26 – User-Defined Insulation for PP (inches) INSH1000-F27 – User-Defined Insulation – Combined Table (inches) INSH1000-FM1 – Calcium Silicate Insulation for HC ASTM C533 Type I (mm) INSH1000-FM2 – Calcium Silicate Insulation for PP ASTM C533 Type I (mm) INSH1000-FM3 – Calcium Silicate Insulation – Combined Table ASTM C533 Type I (mm) INSH1000-FM4 – Cellular Glass Insulation for HC ASTM C552 (mm) INSH1000-FM5 – Cellular Glass Insulation for PP ASTM C552 (mm) INSH1000-FM6 – Cellular Glass Insulation – Combined Table ASTM C552 (mm) INSH1000-FM7 – Fiberglass Insulation for HC ASTM C547, Type 1 / C612, Type I (mm) INSH1000-FM8 – Fiberglass Insulation for PP ASTM C547, Type 1 / C612, Type I (mm) INSH1000-FM9 – Fiberglass Insulation – Combined Table ASTM C547, Type 1 / C612, Type I (mm) INSH1000-FM10 – Mineral Wool Insulation for HC ASTM C547, Type II or III / C612, Type IVB (mm) INSH1000-FM11 – Mineral Wool Insulation for PP ASTM C547, Type II or III / C612, Type IVB (mm) Page 2 of 16 PIP INSH1000 REAFFIRMATION WITH EDITORIAL REVISION Hot Service Insulation Materials and Installation Specification February 2011 INSH1000-FM12 – Mineral Wool Insulation – Combined Table ASTM C547, Type II or III / C612, Type IVB (mm) INSH1000-FM13 – Expanded Perlite Insulation for HC ASTM C610 (mm) INSH1000-FM14 – Expanded Perlite Insulation for PP ASTM C610 (mm) INSH1000-FM15 – Expanded Perlite Insulation – Combined Table ASTM C610 (mm) INSH1000-FM16 – Polyisocyanurate for HC ASTM C591, Type II or IV (mm) INSH1000-FM17 – Polyisocyanurate Insulation for PP ASTM C591, Type II or IV (mm) INSH1000-FM18 – Polyisocyanurate Insulation – Combined Table ASTM C591, Type II or IV (mm) INSH1000-FM19 – Elastomeric Foam Insulation for HC ASTM C534, Grade 3 (mm) INSH1000-FM20 – Elastomeric Foam Insulation for PP ASTM C534, Grade 3 (mm) INSH1000-FM21 – Elastomeric Foam Insulation – Combined Table ASTM C534, Grade 3 (mm) INSH1000-FM22 – Phenolic Foam Insulation for HC ASTM C1126, Type III, Grade 1 (mm) INSH1000-FM23 – Phenolic Foam Insulation for PP ASTM C1126, Type III, Grade 1 (mm) INSH1000-FM24 – Phenolic Foam Insulation – Combined Table ASTM C1126, Type III, Grade 3 (mm) INSH1000-FM25 – User-Defined Insulation for HC (mm) INSH1000-FM26 – User-Defined Insulation for PP (mm) INSH1000-FM27 – User-Defined Insulation – Combined Table (mm) Process Industry Practices Page 3 of 16 PIP INSH1000 REAFFIRMATION WITH EDITORIAL REVISION Hot Service Insulation Materials and Installation Specification February 2011 1. Introduction 1.1 Purpose This Practice provides requirements for materials and installation of hot service insulation systems on the external surfaces of piping and equipment, ambient to 649°C (1200°F). 1.2 Scope This Practice describes requirements for hot service insulation materials and accessories, storage and handling of materials, insulation application, extent of insulation, and documentation. Comment: Use of this Practice for contractual purposes requires the purchaser to make specific choices and to assemble additional supporting documents. Listing of or reference to supporting documents within this Practice does not imply suitability for specific designs. 2. References Applicable parts of the following Practices, industry codes and standards, and references shall be considered an integral part of this Practice. The edition in effect on the date of contract award shall be used, except as otherwise noted. Short titles are used herein where appropriate. 2.1 Process Industry Practices (PIP) – PIP INTG1000 – Insulation Inspection Checklist 2.2 Industry Codes and Standards American Petroleum Institute (API) – API 521 – Guide for Pressure-Relieving and Depressuring Systems American Petroleum Institute American Society for Testing and Materials (ASTM) – ASTM C450 – Prefabrication and Field Fabrication of Thermal Insulating Fitting Covers for NPS Piping, Vessel Lagging, and Dished Head Segments – ASTM C692 – Test Method for Evaluating the Influence of Thermal Insulation on the External Stress Corrosion Cracking Tendency of Austenitic Steel – ASTM C795 – Specification for Wicking-Type Thermal Insulation for Use over Austenitic Stainless Steel – ASTM C871 – Chemical Analysis of Thermal Insulation Materials for Leachable Chloride, Fluoride, Silicate and Sodium Ions Process Industry Practices Page 4 of 16 PIP INSH1000 REAFFIRMATION WITH EDITORIAL REVISION Hot Service Insulation Materials and Installation Specification February 2011 3. Definitions owner: Party who owns the facility wherein the insulation system will be used purchaser: Party who awards the contract to the supplier. The purchaser may be the owner or the owner’s authorized agent. supplier: Party responsible for providing the insulation materials and installing the insulation system 4. Requirements 4.1 Project Scope 4.1.1 Documents required to define the scope of the work are listed on Purchaser’s Data Sheet PIP INSH1000-D1. 4.1.2 Project specific insulation on piping and equipment shall be in accordance with Purchaser’s Data Sheet PIP INSH1000-D2. This data sheet describes the surfaces to be insulated and the materials to be used. 4.1.3 The extent of insulation is listed on Purchaser’s Data Sheet PIP INSH1000-D3. 4.1.3.1 This data sheet defines the extent of insulation by surface or component for each insulation type code required for the project. 4.1.3.2 The extent of equipment insulation may also be defined by the purchaser for individual items. 4.2 4.1.4 Insulation materials shall be in accordance with Purchaser’s Data Sheets PIP INSH1000-D10 through PIP INSH1000-D23 as required in accordance with Purchaser’s Data Sheet PIP INSH1000-D1. These data sheets define requirements for specific insulation materials and accessories. 4.1.5 Systems requiring additional insulation specifications beyond Practices shall be covered by purchaser’s documentation. Materials 4.2.1 Insulation and accessory materials shall be furnished in accordance with the requirements of this Practice, including the specific class, grade, or type. 4.2.2 Asbestos shall not be used as a component in the manufacture of insulation and accessory materials. 4.2.3 Materials shall be new and shall be used before the expiration date. 4.2.4 Sealant, mastics, and adhesives shall be supplied in factory-sealed containers. 4.2.5 Multilayer calcium silicate and expanded perlite pipe insulation shall be ordered factory-nested. Process Industry Practices Page 5 of 16 PIP INSH1000 REAFFIRMATION WITH EDITORIAL REVISION Hot Service Insulation Materials and Installation Specification February 2011 4.2.6 All materials shall be qualified for use on austenitic stainless steel in accordance with ASTM C795. 4.2.6.1 If requested, test reports shall be furnished. 4.2.6.2 A chemical analysis shall be provided in accordance with ASTM C871 for all materials. This chemical analysis shall not vary by more than 50 percent from the chemical analysis of the production lot tested in accordance with ASTM C692. 4.2.7 Use of materials other than those specified in this Practice requires prior written approval of the purchaser. 4.2.8 Requests for substitutions of materials shall be included as an alternate in the proposal. 4.2.9 Requests for substitutions of materials after contract award are not permitted. 4.2.10 All mastics, cements, adhesives, caulks, labels, marking pens, and tapes that come in contact with stainless steel shall have a maximum leachable chloride content of less than 50 ppm, when tested in accordance with ASTM C871. 4.2.11 Use curved segments, beveled lags and V-grooved materials manufactured to specific inside diameters that assure complete inside and outside diameter closure. 4.2.12 Fabricated insulation shall conform to with ASTM C450 and the Adjunct. 4.3 4.4 Storage and Handling of Insulation Materials 4.3.1 From delivery to the installed finished product, insulation materials shall at all times be protected from the elements and have adequate drainage. 4.3.2 Insulation materials shall be handled and stored in accordance with the manufacturer’s printed recommendations. 4.3.3 Mastics, adhesives, and sealers that are exposed to temperatures outside the recommended temperature ranges during storage shall be removed from the site and replaced with new material. 4.3.4 Materials that have exceeded shelf life and dates shall be removed from the site and replaced with new material. Installation Requirements 4.4.1 General 4.4.1.1 All materials shall be stored, mixed, thinned, and applied in accordance with the manufacturer’s printed instructions. 4.4.1.2 All conflicts between this Practice and the manufacturer’s printed instructions shall be brought to the attention of the purchaser for resolution. 4.4.1.3 Authorization to proceed with application of insulation shall be obtained in writing from the purchaser. Process Industry Practices Page 6 of 16 PIP INSH1000 REAFFIRMATION WITH EDITORIAL REVISION Hot Service Insulation Materials and Installation Specification February 2011 4.4.1.4 Unless otherwise specified, insulation shall not be applied until completion of the following has been verified: a. Required hydrostatic and/or pneumatic pressure testing b. Application of required substrate protective coating systems, including touch-up of previously applied coatings c. Installation and testing of required tracing systems d. Cleaning of surfaces that require insulation 4.4.1.5 Temporary terminations of installed insulation shall be adequately protected at all times. 4.4.1.6 All insulation shall be smooth and free from cracks, voids, gaps and depressions greater than 3 mm (1/8 inch). 4.4.1.7 All cracks, voids, gaps, and depressions in the insulation greater than 3 mm (1/8 inch) shall be refitted and not filled. 4.4.2 Insulation Layering 4.4.2.1 Unless otherwise specified by purchaser, piping and equipment insulation shall be applied as a multiple layer for operating temperatures of 316 °C (600 °F) and higher. 4.4.2.2 Personnel protection insulation shall be applied as a double layer for thicknesses greater than 100 mm (4 inches). 4.4.2.3 If applying single-layer insulation, other than hinged pipe covering, the circumferential butt joints of each half section shall be staggered. 4.4.2.4 If applying double-layer or multiple-layer insulation, each succeeding layer shall be staggered to the longitudinal and circumferential joint of the layer beneath. All joints of all layers shall be staggered. 4.4.2.5 Each layer of double-layer or multiple-layer insulation shall be held in place separately. 4.4.3 Insulation Securement 4.4.3.1 Except as modified in accordance with 4.4.3.2, insulation up to 300 mm (12 inches) O.D. shall be held in place with 1.3 mm (0.050 inch) diameter Type 304 stainless steel tie wire. 4.4.3.2 Cellular glass and polyisocyanurate foam insulation up to 300 mm (12 inches) O.D. may be held in place with fiberglass reinforced pressure-sensitive tape. 4.4.3.3 Insulation 300 mm (12 inches) O.D. to 600 mm (24 inches) O.D. shall be held in place with 13 mm (0.5 inch) wide by 0.50 mm (0.020 inch) thick Type 304 stainless steel bands and wing seals. Process Industry Practices Page 7 of 16 PIP INSH1000 REAFFIRMATION WITH EDITORIAL REVISION Hot Service Insulation Materials and Installation Specification February 2011 4.4.3.4 Insulation above 600 mm (24 inches) O.D. shall be held in place with 19 mm (0.75 inch) wide by 0.50 mm (0.020 inch) thick Type 304 stainless steel bands and wing seals. 4.4.3.5 All cut ends of wire shall be embedded into the insulation. 4.4.4 Metal Jacketing 4.4.4.1 If fire protection is required in accordance with API 521, stainless steel jacketing shall be installed on equipment and piping. 4.4.4.2 If aluminum jacketing is provided on lines with an operating temperature exceeding 400 °C (750 °F), stainless steel jacketing shall be used at points of contact with insulated surface. 4.4.4.3 Exposed edges of metal jacketing shall be machine-bent or rolled to eliminate sharp edges. 4.4.5 Metal Jacketing Securement 4.4.5.1 Metal jacketing to 600 mm (24 inches) O.D. shall be held in place with 13 mm (0.5 inch) wide by 0.50 mm (0.020 inch) thick Type 304 stainless steel bands and wing seals. 4.4.5.2 Metal jacketing above 600 mm (24 inches) O.D. shall be held in place with 19 mm (0.75 inch) wide by 0.5 mm (0.020 inch) thick Type 304 stainless steel bands and wing seals. 4.4.5.3 Jacket banding shall be spaced on maximum 300 mm (12 inch) centers. 4.4.6 Screws 4.4.6.1 Screws shall be self-drilling No. 8 by 13 mm (1/2 inch) stainless steel, with elastomeric washers. 4.4.6.2 Screw heads shall be hex, Phillips recessed round, round, hex-slotted, or pan type. 4.4.7 Insulation System Expansion Provisions 4.4.7.1 Expansion joints shall be provided for rigid insulation materials on all piping and horizontal equipment in accordance with Table 1. 4.4.7.2 Expansion joints shall be provided below insulation supports on vertical piping, except if above an elbow at the bottom of a pipe run or directly above the pipe flanges. 4.4.7.3 The expansion joint spacing shown in Table 1 shall be the maximum distance allowable between restraint points in the insulation system. Comment: Restraint points are typically pipe supports, pipe fittings, branch connections, flanges, and valves. Process Industry Practices Page 8 of 16 PIP INSH1000 REAFFIRMATION WITH EDITORIAL REVISION Hot Service Insulation Materials and Installation Specification February 2011 Table 1 – Expansion Joints Expansion Joint Spacing, mm (feet) Operating Temperature Range °C (°F) Horizontal Piping and Equipment (Note 1) Vertical Piping Up to 38 (100) 18000 (60) 18000 (60) (18000) 39 to 93 (101 to 200) 18000 (60) 9000 (30) 94 to 149 (201 to 300) 9000 (30) 4500 (15) 150 to 204 (301 to 400) 4500 (15) 4500 (15) 205 to 260 (401 to 500) 3600 (12) 3600 (12) 261 to 371 (501 to 700) 2700 (9) 2700 (9) 372 to 482 (701 to 900) 1800 (6) 1800 (6) 483 to 649 (901 to 1200) 1200 (4) 1200 (4) 4.4.7.4 If piping runs have distances between insulation restraint points that exceed those shown in Table 1, insulation expansion joints located approximately midway between the restraint points shall be provided. 4.4.7.5 Expansion joints shall not be required for personnel protection insulation or fibrous insulation on horizontal equipment and piping. 4.4.7.6 Fibrous insulation shall be compressed during installation to ensure that circumferential joints are tightly butted together. 4.4.7.7 Except as modified in accordance with 4.4.7.8, expansion joints shall be provided beneath all insulation support rings on vertical equipment and piping, except for the bottom support ring. 4.4.7.8 Expansion joints should not be provided beneath the insulation support ring if the support is immediately above an elbow or flange. 4.4.7.9 Insulation expansion joints shall be installed in all layers of multiple-layer insulation. 1. Joints in horizontal piping and equipment shall be staggered between layers. 2. Joints installed below insulation supports on vertical piping and equipment shall not be staggered. 4.4.7.10 Insulation expansion joints shall be 25 mm (1 inch) wide and packed tightly with mineral fiber blanket insulation compressed a minimum of 50 percent. Process Industry Practices Page 9 of 16 PIP INSH1000 REAFFIRMATION WITH EDITORIAL REVISION Hot Service Insulation Materials and Installation Specification February 2011 4.4.7.11 Insulation bands securing rigid insulation on equipment in hot service shall incorporate 100 mm (4 inch) long, flat expansion springs in accordance with Table 2. 4.4.7.12 Insulation bands securing fibrous insulation on equipment in hot service shall not require expansion springs. 4.4.7.13 Bands securing equipment insulation weather jacketing in hot service shall incorporate 4-inch (100-mm) long, compression spring assemblies in accordance with Table 2. Table 2 – Expansion Spring Requirements Equipment O.D. mm Normal Operating Temperature Number of Expansion Devices per Band inches C F 750 & under 30 & under up to 649 up to 1200 none ≤204 ≤400 none >750 to 1800 >30 to 72 205 to 649 401 to 1200 1 ≤204 ≤400 none 205 to 427 401 to 800 1 428 to 649 801 to 1200 2 ≤204 ≤400 none 205 to 649 401 to 1200 1 per 9 m (30 ft) of band ≤66 ≤150 none >1800 to 3000 >3000 to 3600 >72 to 120 >120 to 144 >3600 4.4.8 >144 Pipe Insulation Supports in Vertical Piping 4.4.8.1 If specified by purchaser, vertical piping insulation supports shall be furnished shop-installed by the piping fabricator. 4.4.8.2 If additional vertical piping insulation supports are required, bolt-on supports shall be furnished and field-installed. 4.4.8.3 Design of vertical pipe insulation supports shall be provided in the proposal, and shall be subject to review and approval by purchaser. 4.4.8.4 Location of pipe insulation supports in vertical piping shall consider: a. Maximum spacing of supports shall be the same as specified in Table 1 for expansion joints in vertical pipe insulation. b. Insulation supports shall be provided above all flanged connections. Process Industry Practices Page 10 of 16 PIP INSH1000 REAFFIRMATION WITH EDITORIAL REVISION Hot Service Insulation Materials and Installation Specification February 2011 c. Supports above flanged sections shall be located a minimum one stud bolt length plus 25 mm (1 inch) from the back face of the top flange. d. Insulation supports shall be provided above elbows and tees, if the vertical or diagonal run length is equal to or greater than the maximum spacing allowed in Table 1 for expansion joints in vertical pipe insulation. e. If required above elbows or tees, supports shall be located 150 mm (6 inches) from the pipe-to-fitting weld. 4.4.8.5 Supports shall provide adequate clearance for the installation of required electric or steam tracers. 4.4.9 Piping Insulation 4.4.9.1 Insulation for fittings, flanges, and valves shall be fabricated in accordance with ASTM C450 and the Adjunct. 4.4.9.2 Molded insulation fitting covers shall be used, subject to the operating temperature limits of the molded cover material. 4.4.9.3 Socketweld or threaded valves, ells, tees and other fittings shall be insulated with strips of glass fiber-needled blanket, wrapped around the valve or fitting and secured with wire. 4.4.9.4 Valve insulation shall be terminated directly below the packing gland flange and packing follower. 4.4.9.5 Insulation material shall not be applied between the pipe and tracer, except if spacers to prevent local overheating of the pipe are specified. 4.4.10 Equipment Insulation 4.4.10.1 Equipment with vessel shell diameters of 900 mm (36 inches) or less shall have shell insulation extended to cover the heads. 1. Each head shall be blocked in with an insulation disc, fabricated or cut to match the inside diameter of the insulation. 2. Nominal disc thickness shall be the thickness required for the shell. 4.4.10.2 Unless specified otherwise, all exposed heads exceeding 900 mm (36 inches) shall be insulated with block insulation. 1. Block insulation shall be installed full thickness and fit to follow the curvature of the head. 2. As an alternate to shop-fabricated segments, heads shall be insulated with field fit block if approved by the purchaser. 3. Scored or V-grooved block shall not be permitted. Process Industry Practices Page 11 of 16 PIP INSH1000 REAFFIRMATION WITH EDITORIAL REVISION Hot Service Insulation Materials and Installation Specification February 2011 4.4.10.3 Unless specified otherwise by purchaser, vertical equipment support legs, lugs, and saddle supports for horizontal equipment shall not be insulated. 4.4.10.4 Insulation on skirt-supported vertical vessels shall be extended past the bottom tangent line, down the exterior surface of the skirt to the bottom insulation support ring. 4.4.10.5 Vessels having skirt inside diameters exceeding 1200 mm (48 inches) shall have the corresponding inside skirt surface insulated. 4.4.10.6 Equipment nozzles connected to bare piping shall have the equipment insulation system terminated on the nozzle and finished with a metallic cover. 4.4.10.7 For insulation of vessel shells, rigid pipe sections or rigid curved radius segments shall be utilized up to the maximum commercially available size. 4.4.10.8 Beveled block insulation for vessel shells shall be used only if shell diameters exceed the commercially available size of curved radius segments. 1. Edge beveling of the block shall be in accordance with ASTM C450 and the Adjunct. 2. Bevels shall be applied to either one or both block edges. 4.4.10.9 Scored block insulation shall not be an acceptable substitute for beveled lags or curved radius segments. 4.4.10.10 Code or other nameplates shall not be covered by insulation. 4.4.11 Machinery Insulation 4.4.11.1 Machinery, such as pumps and turbines, shall be insulated with removable/reusable insulation covers, as designated in PIP INSH1000-D2. 4.4.11.2 If required by purchaser, machinery, such as pumps and turbines, shall be insulated with insulating and finishing cement. 4.4.11.3 Before applying insulating and finishing cement, a layer of 25 mm (1 inch) hexagonal chicken wire mesh or expanded metal lath shall be wrapped around the equipment item to be insulated with a 25 mm (1 inch) overlap at all edges and secured with wire. 4.4.11.4 All cut wire ends shall be turned in so as not to protrude through the finished surface. 4.4.11.5 The insulating and finishing cement shall be mixed and applied according to the manufacturer's recommendations. 4.4.11.6 Insulating and finishing cement shall be applied to the same thickness as the adjoining insulation. Process Industry Practices Page 12 of 16 PIP INSH1000 REAFFIRMATION WITH EDITORIAL REVISION Hot Service Insulation Materials and Installation Specification February 2011 4.4.12 Insulation Types ET and ST 4.4.12.1 If insulation design and installation is included with the electrical tracing system design and installation subcontract, alternate insulation materials and thicknesses, and combinations thereof, shall be utilized, provided the intent of the specification is satisfied. Such alternates shall be approved by the purchaser. 4.4.12.2 Jacketing for insulation on electrical traced piping shall be installed with bands only. Comment: Screws and rivets can damage the electrical tracing and shall not be acceptable fasteners for any jacketing installed to finish insulation on electrically traced piping. 4.4.12.3 Screw and rivet fasteners can however be used in the fabrication of removable insulated covers for use over electrically traced piping components. 4.4.12.4 Unless required for personnel protection, tube tracer unions located outside of the pipe or equipment insulation shall not be insulated. 4.4.12.5 Unless required for personnel protection, tracer expansion loops located outside of insulation shall not be insulated. 4.4.12.6 If required for personnel protection, insulation for tracer loops shall be installed in accordance with the following: a. The tracer shall be wrapped with 3 mm (1/8 inch) thick fiberglass tape, using a 50 percent overlap to provide a 6 mm (1/4 inch) thickness. b. The fiberglass tape shall be secured with wire on 150 mm (6 inch) centers. c. The outer surface of the fiberglass tape shall be finished with weather barrier mastic, without reinforcing membrane, applied to a nominal dry film thickness of 2 mm (1/16 inch). 4.4.12.7 Pipe insulation shall be oversized, unless otherwise agreed with purchaser. 4.4.12.8 Grooving or deforming of the insulation to accommodate heat tracing is prohibited. 4.4.12.9 Oversized insulation shall be installed such that the insulation is not loose on the piping. 4.4.13 Insulation Finish 4.4.13.1 Weather jacketing shall be fitted tightly around vessel and piping attachments that pass through the weather jacketing. 4.4.13.2 RTV silicone sealant shall be applied to the extent necessary to prevent the entrance of water around penetrations through the weather jacketing. Process Industry Practices Page 13 of 16 PIP INSH1000 REAFFIRMATION WITH EDITORIAL REVISION Hot Service Insulation Materials and Installation Specification February 2011 4.4.13.3 Circumferential and longitudinal laps in weather jacketing shall be overlapped 50 mm (2 inches) to 75 mm (3 inches). 4.4.13.4 Unless otherwise specified, insulation surfaces that have not been finished with metal jacketing shall be weatherproofed with membrane-reinforced weather barrier mastic. 1. The membrane-reinforced mastic shall extend under the adjoining metal jacketing for a distance of 75 mm (3 inches) minimum. 2. The membrane-reinforced mastic shall also extend onto uninsulated projections a minimum of 75 mm (3 inches). 4.4.13.5 Weather barrier mastic shall be applied by trowel or brushed on large surfaces and by brush or glove on small surfaces. 4.4.13.6 Two coats of weather-barrier mastic shall be applied in accordance with the material manufacturer's instructions and the following: a. Substrate temperatures shall be within the application temperature range established by the material manufacturer. b. Substrate temperature shall be above dew point temperature at the time of application and until the mastic has dried. c. Substrate shall be dry if the mastic is applied. d. Substrate shall not be subject to freezing temperatures within 24 hours of application. e. If weather barrier mastic is scheduled for application over dusty surfaces, the surface shall be primed with suitable primer, as recommended by the weather barrier mastic manufacturer. f. Weather barrier mastic shall not be thinned. g. Reinforcing membrane shall be applied while first coat is still tacky. h. Membrane shall be embedded in first coat of mastic, without wrinkles, so that mastic comes up through the open mesh. i. Membrane seams shall be overlapped 50 mm (2 inches). j. The second coat of mastic shall be applied before the first coat dries. k. All outside corners of insulation shall be rounded and the weather barrier mastic provided with a double layer of reinforcing membrane. 4.4.13.7 After drying, the membrane reinforced weather barrier mastic shall be inspected for imperfections (i.e., cracks, pinholes, openings, or exposed reinforcing membrane). Such imperfections shall be repaired with the same material as originally applied. Process Industry Practices Page 14 of 16 PIP INSH1000 REAFFIRMATION WITH EDITORIAL REVISION Hot Service Insulation Materials and Installation Specification February 2011 4.4.14 Corrosion Monitoring Inspection Ports 4.4.14.1 Corrosion monitoring inspection ports shall be installed at locations designated by Owner. 4.4.14.2 Ports shall be positioned so that the inspection point is in the center of the opening. 4.4.15 Protection of Installed Insulation 4.4.15.1 Installed insulation shall have the required permanent protection or temporary protection applied before the conclusion of work on that day. 4.4.15.2 Installed insulation shall have temporary protection applied if rain or other forms of atmospheric moisture can damage the insulation during each work shift. 4.4.16 Wet Insulation 4.4.16.1 Insulation that becomes wet shall be removed and replaced with dry insulation. 4.4.16.2 Wet insulation shall be discarded. 4.4.17 Work Area Housekeeping 4.4.17.1 Insulation materials shall be handled and disposed of in accordance with applicable federal, state, and local laws and regulations. 4.4.17.2 Insulation-related materials, such as mastics, shall be handled and applied with care to prevent splattering on adjacent facilities, such as concrete foundations, paving, structural steel, equipment, piping, gauge glasses, instruments, machined surfaces, valve stems, and packing. 4.4.17.3 All mastic over-spray and splatter shall be removed immediately. 4.4.17.4 Flammable materials shall be stored away from ignition sources such as welding operations. 4.4.17.5 Debris from insulation application work shall be removed from the work area on a regular basis and placed in containers at the end of the workday. 4.5 Quality Plan A quality plan shall be provided with the proposal that includes the following: a. Quality assurance, quality control, and inspection criteria b. A method of providing the purchaser with verifiable evidence that all aspects of quality are accepted and found acceptable by the supplier’s inspector during the course of the insulation work c. All elements identified by PIP INTG1000 Process Industry Practices Page 15 of 16 PIP INSH1000 REAFFIRMATION WITH EDITORIAL REVISION Hot Service Insulation Materials and Installation Specification February 2011 d. Inspection hold points as necessary to assure work can be properly inspected before any additional work is performed that could obscure defective materials or installation 4.6 Inspection 4.6.1 All materials, fabrication, and installation work is subject to inspection by the purchaser or the owner. 4.6.2 The purchaser's inspector shall review the quality procedures to verify the following information: a. Quality procedures are appropriate for the work scope being performed and have been approved by purchaser. b. The approved quality procedures have been implemented and are being administrated by the quality personnel. 4.7 4.6.3 Items that are not in accordance with the purchase order shall be subject to rejection. 4.6.4 Rejected material, fabrication, or installation work shall be replaced at no cost to purchaser. 4.6.5 Unless otherwise specified, INTG1000 shall be used for inspection documentation. Repairs 4.7.1 Damage to installed insulation shall be promptly reported to the purchaser. The report shall include the location and nature of the damage. 4.7.2 Damage to insulation weather jacketing shall be repaired immediately if the damage can result in additional damage to the insulation due to water leakage into the system. 4.7.3 Damage to the integrity of weather jacketing applied over calcium silicate shall be of prime concern and shall be given top repair priority. 4.7.4 If permanent repair is not immediately practical, temporary repair of damaged weather jacketing shall be required. 4.7.5 Damaged insulation shall be replaced if the nature of the damage will adversely affect the thermal performance of the system. 4.7.6 Any disputes regarding the need for replacement of insulation shall be referred to the purchaser for resolution. Process Industry Practices Page 16 of 16 ASSOC. PIP: INSH1000 DOCUMENTATION REQUIREMENTS SHEET HOT SERVICE INSULATION MATERIALS AND INSTALLATION NO. DATE REVISION DESCRIPTION PROJECT NO. PIP INSH1000-D1 PAGE 1 OF 4 FEBRUARY 2011 BY CHECKED APPROVED DATE NOTES PROJECT DOCUMENT NO. FACILITY NAME LOCATION NUMBER INEG1000 INEG2000 INTG1000 INSH1000-D2 INSH1000-D3 TITLE INSULATION DESIGN GUIDE GUIDELINES FOR USE OF INSULATION PRACTICES INSULATION INSPECTION CHECKLIST HOT SERVICE INSULATION SYSTEM PROJECT-SPECIFIC REQUIREMENTS EXTENT OF HOT-SERVICE INSULATION INSH1000-D10 YES INSH1000-D11 YES INSH1000-D12 YES INSH1000-D13 YES INSH1000-D14 YES INSH1000-D15 YES INSH1000-D16 YES INSH1000-D17 YES INSH1000-D18 YES INSH1000-D19 YES INSH1000-D20 YES INSH1000-D21 YES INSH1000-D22 YES INSH1000-D23 YES YES YES YES YES YES YES SELECTED MATERIALS SYSTEM DATA SHEETS NO CALCIUM SILICATE INSULATION SYSTEM FOR PIPE AND EQUIPMENT NO EXPANDED PERLITE INSULATION SYSTEM FOR PIPE AND EQUIPMENT NO MINERAL WOOL PERFORMED PIPE SECTIONS INSULATION SYSTEM NO MINERAL WOOL BOARD INSULATION SYSTEM FOR EQUIPMENT NO MINERAL WOOL BLANKET INSULATION SYSTEM FOR PIPE AND EQUIPMENT NO GLASS FIBER PERFORMED PIPE SECTIONS INSULATION SYSTEM NO GLASS FIBER BLOCK AND BOARD INSULATION SYSTEM NO GLASS FIBER BLANKET INSULATION SYSTEM NO CELLULAR GLASS BLOCK AND FABRICATED SECTIONS INSULATION SYSTEM NO POLYISOCYANURATE INSULATION SYSTEM NO CERAMIC FIBER BLANKET INSULATION SYSTEM NO GLASS FIBER NEEDLED BLANKET INSULATION SYSTEM NO FLEXIBLE ELASTOMERIC CELLULAR THERMAL INSULATION SYSTEM FOR PIPE AND EQUIPMENT NO RIGID CELLULAR PHENOLIC THERMAL INSULATION SYSTEM FOR PIPE AND EQUIPMENT NO NO NO NO NO NO REV ASSOC. PIP: INSH1000 DOCUMENTATION REQUIREMENTS SHEET HOT SERVICE INSULATION MATERIALS AND INSTALLATION PROJECT NO. PROJECT DOCUMENT NO. FACILITY NAME LOCATION INSH1001-F1 YES INSH1001-F2 YES INSH1001-F3 YES INSH1001-F4 YES INSH1001-F5 YES INSH1001-F6 YES INSH1001-F7 YES INSH1001-F8 YES INSH1001-F9 YES INSH1001-F10 YES INSH1001-F11 YES INSH1001-F12 YES INSH1001-F13 YES INSH1001-F14 YES INSH1001-F15 YES INSH1001-F16 YES INSH1001-F17 YES INSH1001-F18 YES INSH1001-F19 YES INSH1001-F20 YES INSH1001-F21 YES INSH1001-F22 YES INSH1001-F23 YES INSH1001-F24 YES INSH1001-FM1 YES INSH1001-FM2 YES INSH1001-FM3 YES INSH1001-FM4 YES SELECTED INSULATION THICKNESS TABLES CALCIUM SILICATE INSULATION FOR HC (INCHES) NO CALCIUM SILICATE INSULATION FOR PP (INCHES) NO CALCIUM SILICATE INSULATION – COMBINED TABLE (INCHES) NO CELLULAR GLASS INSULATION FOR HC (INCHES) NO CELLULAR GLASS INSULATION FOR PP (INCHES) NO CELLULAR GLASS INSULATION – COMBINED TABLE (INCHES) NO FIBERGLASS INSULATION FOR HC (INCHES) NO FIBERGLASS INSULATION FOR PP (INCHES) NO FIBERGLASS INSULATION – COMBINED TABLE (INCHES) NO MINERAL WOOL INSULATION FOR HC (INCHES) NO MINERAL WOOL INSULATION FOR PP (INCHES) NO MINERAL WOOL INSULATION – COMBINED TABLE (INCHES) NO EXPANDED PERLITE INSULATION FOR HC (INCHES) NO EXPANDED PERLITE INSULATION FOR PP (INCHES) NO EXPANDED PERLITE INSULATION – COMBINED TABLE (INCHES) NO POLYISOCYANURATE INSULATION FOR HC (INCHES) NO POLYISOCYANURATE INSULATION FOR PP (INCHES) NO POLYISOCYANURATE INSULATION – COMBINED TABLE (INCHES) NO ELASTOMERIC FOAM INSULATION FOR HC (INCHES) NO ELASTOMERIC FOAM INSULATION FOR PP (INCHES) NO ELASTOMERIC FOAM INSULATION – COMBINED TABLE (INCHES) NO PHENOLIC FOAM INSULATION FOR HC (INCHES) NO PHENOLIC FOAM INSULATION FOR PP (INCHES) NO PHENOLIC FOAM INSULATION – COMBINED TABLE (INCHES) NO CALCIUM SILICATE INSULATION FOR HC (MM) NO CALCIUM SILICATE INSULATION FOR PP (MM) NO CALCIUM SILICATE INSULATION – COMBINED TABLE (MM) NO CELLULAR GLASS INSULATION FOR HC (MM) NO PIP INSH1000-D1 PAGE 2 OF 4 FEBRUARY 2011 ASSOC. PIP: INSH1000 DOCUMENTATION REQUIREMENTS SHEET HOT SERVICE INSULATION MATERIALS AND INSTALLATION PROJECT NO. PROJECT DOCUMENT NO. FACILITY NAME LOCATION INSH1001-FM5 YES NO INSH1001-FM6 YES NO INSH1001-FM7 INSH1001-FM8 INSH1001-FM9 YES YES YES NO NO NO INSH1001-FM10 YES NO INSH1001-FM11 YES NO INSH1001-FM12 YES NO INSH1001-FM13 YES NO INSH1001-FM14 YES NO INSH1001-FM15 YES NO INSH1001-FM16 YES NO INSH1001-FM17 YES NO INSH1001-FM18 YES NO INSH1001-FM19 YES NO INSH1001-FM20 YES NO INSH1001-FM21 YES NO INSH1001-FM22 YES NO INSH1001-FM23 YES NO INSH1001-FM24 YES NO YES YES YES YES YES YES YES NO NO NO NO NO NO NO INIH0001 INIH0002 INIH0003 YES YES YES NO NO NO INIH0004 YES NO INIH0006 INIH0007 INIH0009 YES YES YES NO NO NO INIH0010 YES NO CELLULAR GLASS INSULATION FOR PP (MM) CELLULAR GLASS INSULATION – COMBINED TABLE (MM) FIBERGLASS INSULATION FOR HC (MM) FIBERGLASS INSULATION FOR PP (MM) FIBERGLASS INSULATION – COMBINED TABLE (MM) MINERAL WOOL INSULATION FOR HC (MM) MINERAL WOOL INSULATION FOR PP (MM) MINERAL WOOL INSULATION – COMBINED TABLE (MM) EXPANDED PERLITE INSULATION FOR HC (MM) EXPANDED PERLITE INSULATION FOR PP (MM) EXPANDED PERLITE INSULATION – COMBINED TABLE (MM) POLYISOCYANURATE INSULATION FOR HC (MM) POLYISOCYANURATE INSULATION FOR PP (MM) POLYISOCYANURATE INSULATION – COMBINED TABLE (MM) ELASTOMERIC FOAM INSULATION FOR HC (MM) ELASTOMERIC FOAM INSULATION FOR PP (MM) ELASTOMERIC FOAM INSULATION – COMBINED TABLE (MM) PHENOLIC FOAM INSULATION FOR HC (MM) PHENOLIC FOAM INSULATION FOR PP (MM) PHENOLIC FOAM INSULATION – COMBINED TABLE (MM) HOT INSULATION INSTALLATION DETAILS PIPING – GENERAL ARRANGEMENT PIPING – LAYERED INSULATION PIPING – VERTICAL INSULATION SUPPORT SINGLE LAYER PIPING – VERTICAL INSULATION SUPPORT MULTI-LAYER PIPING – FLANGE INSULATION PIPING – INSULATION CONNECTIONS REMOVABLE AND REUSABLE INSULATION – FLEXIBLE VALVE COVER PIP INSH1000-D1 PAGE 3 OF 4 FEBRUARY 2011 ASSOC. PIP: INSH1000 DOCUMENTATION REQUIREMENTS SHEET HOT SERVICE INSULATION MATERIALS AND INSTALLATION PROJECT NO. PROJECT DOCUMENT NO. FACILITY NAME LOCATION INIH0011 INIH0050 YES YES NO NO INIH0051 YES NO INIH0052 INIH0053 INIH0054 YES YES YES NO NO NO INIH0055 INIH0056 YES YES NO NO INIH0059 INIH0060 INIH0061 INIH0062 INIH0063 YES YES YES YES YES NO NO NO NO NO INIH0064 YES YES YES YES YES YES YES YES YES YES NO NO NO NO NO NO NO NO NO NO NOTES: PIPE SUPPORTS VERTICAL VESSELS WITH OUTSIDE DIAMETERS OVER 36” (915) VERTICAL VESSELS WITH OUTSIDE DIAMETERS 36" (915) AND LESS VESSEL COMPOSITE TYPE 1 VESSEL COMPOSITE TYPE 2 VERTICAL VESSEL BOTTOM HEAD INSULATION TOP/HORIZONTAL HEAD NOZZLES VESSEL STIFFENER INSULATION DETAIL TYPICAL CLIP DETAILS NOZZLE FLASHING LAP SEAM DETAILS HORIZONTAL VESSELS APPLICATION OF METAL GORES ON HORIZONTAL VESSEL HEADS HORIZONTAL HEAT EXCHANGERS PIP INSH1000-D1 PAGE 4 OF 4 FEBRUARY 2011 ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D2 HOT SERVICE INSULATION SYSTEM PROJECT-SPECIFIC REQUIREMENTS NO. DATE REVISION DESCRIPTION BY FACILITY NAME LOCATION SERVICE OR ITEM DESCRIPTION NOTES: PAGE 1 OF 1 FEBRUARY 2011 CHECKED PROJECT NO. PROJECT DOCUMENT NO. “TYPE” CODE OPERATING TEMP. °C (°F) MATERIAL THICKNESS TABLE SPECIAL REQUIREMENTS APPROVED ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D3 PAGE 1 OF 3 FEBRUARY 2011 EXTENT OF HOT-SERVICE INSULATION NO. DATE FACILITY NAME LOCATION REVISION DESCRIPTION BY CHECKED APPROVED PROJECT NO. PROJECT DOCUMENT NO. INSULATION REQUIREMENTS FOR PIPING AND EQUIPMENT (NOTE: PROJECT PIPING AND EQUIPMENT INSULATION SPECIFICATIONS MAY MODIFY THESE REQUIREMENTS.) SJ - STEAM JACKETED PF - PREVENTION FROM FREEZING HC - HEAT CONSERVATION HT - HOT FLUID TRACED PP - PERSONNEL PROTECTION PS - PROCESS STABILITY HJ - HOT FLUID JACKETED FP - FIRE PROTECTION INSULATION ET - ELECTRIC TRACED ST - STEAM TRACED HC PS PP [1] ET, ST, SJ, ITEMS AMB – 649°C AMB – 649°C 61°C – 649°C HT, HJ, & PF (AS REQUIRED BY (AMB TO 1200°F) (AMB TO 1200°F) (141°F – 1200°F) THE PURCHASER) YES YES [4] YES STRAIGHT OR BENT PIPE, SOCKETWELD, THREADED, OR BUTTWELD PIPE FITTINGS. SOCKETWELD, THREADED, OR BUTTWELD VALVES NO [4 NO [4 [4] YES [2, 5] PIPE UNIONS NO [4 NO [4 NO NO [2] STEAM TRAPS, RELATED STRAINERS YES [5] NO [2, 5] [4] YES [5] FLANGED PIPE FITTINGS, FLANGED VALVES (EXCLUDING RELIEF AND CONTROL VALVES), FLANGE ORIFICE SETS, PIPING FLANGES CONNECTED TO EQUIPMENT NOZZLES AND FLANGED SPECIAL ITEMS (I.E., STRAINERS) NO NO NO NO PIPE TRUNNIONS, PIPE SUPPORT CLAMPS, AND HANGER RODS NO NO NO YES PRIMARY PIPING FOR INSTRUMENT CONNECTIONS, SAMPLE PIPING, VENT AND DRAIN PIPING NO NO NO NO ROTATION JOINTS, SLIDE VALVES OR OTHER ITEMS IN WHICH INSULATION CAN INTERFER WITH NORMAL OPERATION NO [4] NO [4] NO YES [5] EXPANSION JOINTS ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D3 PAGE 2 OF 3 FEBRUARY 2011 EXTENT OF HOT-SERVICE INSULATION FACILITY NAME LOCATION PROJECT NO. PROJECT DOCUMENT NO. INSULATION REQUIREMENTS FOR PIPING AND EQUIPMENT (NOTE: PROJECT PIPING AND EQUIPMENT INSULATION SPECIFICATIONS MAY MODIFY THESE REQUIREMENTS.) SJ - STEAM JACKETED PF - PREVENTION FROM FREEZING HC - HEAT CONSERVATION HT - HOT FLUID TRACED PP - PERSONNEL PROTECTION PS - PROCESS STABILITY HJ - HOT FLUID JACKETED FP - FIRE PROTECTION INSULATION ET - ELECTRIC TRACED ST - STEAM TRACED HC PS PP [1] ET, ST, SJ, ITEMS AMB – 649°C AMB – 649°C 61°C – 649°C HT, HJ, & PF (AS REQUIRED BY (AMB TO 1200°F) (AMB TO 1200°F) (141°F – 1200°F) THE PURCHASER) NO NO NO YES INSTRUMENTS AND ASSOCIATED TUBE NO NO NO NO RELIEF VALVES NO [2, 5] NO [2, 5] YES [5] CONTROL VALVES [4] N/A VESSELS, SHELL AND HEAD SURFACES NO [2, 5] NO [2, 5] [4] N/A VESSEL HAND HOLES NO [2, 5] NO [2, 5] [4] VESSEL MANWAYS NO NO N/A VESSEL INSTRUMENT TRIM YES YES [4] N/A HEAT EXCHANGER SHELL AND INTEGRAL SHELL COVER SURFACES YES [5] YES [5] [4] N/A HEAT EXCHANGER FRONT AND REAR HEADS, INCLUDING CHANNEL BARRELS, COVERS, AND BONNETS (EXCLUDING FLANGED JOINTS) NO [2, 5] NO [2, 5] [4] N/A HEAT EXCHANGER FLANGED JOINTS NO NO N/A N/A COMPRESSORS YES [5] YES [5] N/A BLOWERS, FANS YES [3, 5] YES [3, 5] N/A N/A TURBINE DRIVERS NO [4] NO [4] N/A INTERNALLY INSULATED ITEMS ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D3 PAGE 3 OF 3 FEBRUARY 2011 EXTENT OF HOT-SERVICE INSULATION FACILITY NAME LOCATION PROJECT NO. PROJECT DOCUMENT NO. HC PS ET ST ITEMS INSULATION REQUIREMENTS FOR PIPING AND EQUIPMENT (NOTE: PROJECT PIPING AND EQUIPMENT INSULATION SPECIFICATIONS MAY MODIFY THESE REQUIREMENTS.) SJ - STEAM JACKETED PF - PREVENTION FROM FREEZING HEAT CONSERVATION HT - HOT FLUID TRACED PP - PERSONNEL PROTECTION PROCESS STABILITY HJ - HOT FLUID JACKETED FP - FIRE PROTECTION INSULATION ELECTRIC TRACED STEAM TRACED HC PS PP [1] ET, ST, SJ, AMB – 649°C AMB – 649°C 61°C – 649°C HT, HJ, & PF (AS REQUIRED BY (AMB TO 1200°F) (AMB TO 1200°F) (141°F – 1200°F) THE PURCHASER) NOTES: 1. PERSONNEL PROTECTION (PP) SHALL BE PROVIDED TO 7 FT (2100 mm) ABOVE GRADE OR PLATFORMS AND 3 FT (900 mm) HORIZONTALLY FROM THE PERIPHERY OF PLATFORMS, WALKWAYS, OR LADDERS. 2. INSULATE OR GUARD ONLY IF REQUIRED FOR PERSONNEL PROTECTION. 3. INSULATION SHALL BE FURNISHED BY EQUIPMENT MANUFACTURER. 4. PROVIDE REMOVABLE METAL GUARDS OR SUITABLE PERSONNEL BARRIERS IF REQUIRED FOR PERSONNEL PROTECTION. 5. REMOVABLE / REUSABLE COVERS SHALL BE PROVIDED, UNLESS OTHERWISE INDICATED BY PURCHASER. ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D10 CALCIUM SILICATE INSULATION SYSTEM FOR PIPE AND EQUIPMENT NO. DATE PAGE 1 OF 2 FEBRUARY 2011 REVISION DESCRIPTION BY FACILITY NAME LOCATION CHECKED APPROVED PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Calcium silicate preformed pipe sections, curved segments and flat block shall conform to ASTM C533, Type 1. Beveled lags shall be used in the size range in which curved segments are not commercially available. The material shall be continuously identified throughout to indicate that the product does not contain asbestos. APPROVED MANUFACTURERS MANUFACTURER BRANDNAME MANUFACTURER BRANDNAME ACCESSORY DESCRIPTION METAL JACKETING All jacketing shall be furnished with integral, continuously heat-sealed Polysurlyn moisture barrier. Aluminum jacketing for piping and equipment shall be stucco-embossed finish, except for head segments, fitting and valve covers shall be smooth finish. Metal jacketing on vertical equipment 1200 mm (48 in.) and larger in diameter shall be aluminum sheets, 0.6 mm (0.024-in.) thick with 32 mm (1-1/4-in.) pitch corrugations. Corrugated jacketing shall be approximately 825 mm (33-in.) to 1200 mm (48-in.) wide by 3000 mm (10-ft) long. The length of corrugated jacketing shall be modified to minimize waste and cutting. Metal jacketing on horizontal equipment 1200 mm (48 in.) and larger in diameter shall be aluminum 0.6 mm (0.024-in.) thick. Metal jacketing on vessels less than 1200 mm (48 in.) in diameter, and all piping, shall be aluminum, 0.5 mm (0.020-in.) thick and machine-rolled for circumferential fit. Stainless steel jacketing, if required, shall be 0.25 mm (0.010-in.) thick. FABRICATION ADHESIVES Water based, sodium silicate fibrous adhesive suitable for brush or trowel application. MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D10 CALCIUM SILICATE INSULATION SYSTEM FOR PIPE AND EQUIPMENT FACILITY NAME LOCATION PAGE 2 OF 2 FEBRUARY 2011 PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Calcium silicate preformed pipe sections, curved segments and flat block shall conform to ASTM C533, Type 1. Beveled lags shall be used in the size range in which curved segments are not commercially available. The material shall be continuously identified throughout to indicate that the product does not contain asbestos. APPROVED MANUFACTURERS MANUFACTURER BRANDNAME MANUFACTURER BRANDNAME ACCESSORY DESCRIPTION EXPANSION JOINT MATERIAL Expansion joint material for application to 538ºC (1000ºF) shall be a 80 to 192 kg/m³ (5 to 12 lb/ft³) nominal density Type E glass fiber blanket in mat form without the use of resinous or organic binders. Expansion joint material for application at temperatures exceeding 538ºC (1000ºF) shall be ceramic-free needled silica fiber in mat form. FASTENERS All banding shall conform to ASTM A167 and A480/A480M and be furnished deburred. Banding seals shall conform to ASTM A167. Crimp seals are required for securing banding to expansion springs. Tie wire shall conform to ASTM A167 and A580/A580M. Tie wire shall be 1.3 mm (0.050 in.) minimum diameter. Glass filament tape shall be 25 mm (1 in.) wide with pressure-sensitive adhesive. Sheet metal screws shall be No. 8 by 13 mm (1/2 in.) long, austenitic stainless steel, Type "A" or "AB" point, with either slotted hex head or slotted pan head. MISCELLANEOUS ACCESSORIES Expansion springs for insulation shall be 100 mm (4 in.) long flat springs. Expansion springs for jacketing shall be compression spring assemblies. Woven fiberglass tape shall be 3 mm (1/8 in.) thick, plain-weave, and suitable for application to 538°C (1000°F). Metal sealant shall be RTV silicone, aluminum or gray color, suitable for continuous service to 204°C (400°F) and intermittent service to 260°C (500°F). MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D11 EXPANDED PERLITE INSULATION SYSTEM FOR PIPE AND EQUIPMENT NO. DATE REVISION DESCRIPTION PAGE 1 OF 2 FEBRUARY 2011 BY FACILITY NAME LOCATION CHECKED APPROVED PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Expanded perlite preformed pipe sections, curved segments and flat block shall conform to ASTM C610. Beveled lags shall be used in the size range where curved segments are not commercially available. Premolded elbow fitting covers are permitted. APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER BRAND NAME ACCESSORY DESCRIPTION METAL JACKETING All jacketing shall be furnished with integral, continuously heat-sealed Polysurlyn moisture barrier. Aluminum jacketing for piping and equipment shall be stucco-embossed finish, except for head segments, fitting and valve covers shall be smooth finish. Metal jacketing on vertical equipment 1200 mm (48 in.) and larger in diameter shall be aluminum sheets, 0.6 mm (0.024-in.) thick with 32 mm (1-1/4-in.) pitch corrugations. Corrugated jacketing shall be approximately 825 mm (33-in.) to 1200 mm (48-in.) wide by 3000 mm (10-ft) long. The length of corrugated jacketing shall be modified to minimize waste and cutting. Metal jacketing on horizontal equipment 1200 mm (48 in.) and larger in diameter shall be aluminum 0.6 mm (0.024-in.) thick. Metal jacketing on vessels less than 1200 mm (48 in.) in diameter, and all piping, shall be aluminum, 0.5 mm (0.020-in.) thick and machine-rolled for circumferential fit. Stainless steel jacketing, if required, shall be 0.25 mm (0.010-in.) thick. FABRICATION ADHESIVES Water based, sodium silicate fibrous adhesive suitable for brush or trowel application. MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D11 EXPANDED PERLITE INSULATION SYSTEM FOR PIPE AND EQUIPMENT FACILITY NAME LOCATION PAGE 2 OF 2 FEBRUARY 2011 PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Expanded perlite preformed pipe sections, curved segments and flat block shall conform to ASTM C610. Beveled lags shall be used in the size range where curved segments are not commercially available. Premolded elbow fitting covers are permitted. APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER BRAND NAME ACCESSORY DESCRIPTION EXPANSION JOINT MATERIAL Expansion joint material for application to 538ºC (1000ºF) shall be a 80 to 192 kg/m³ (5 to 12 lb/ft³) nominal density Type E glass fiber blanket in mat form without the use of resinous or organic binders. Expansion joint material for application at temperatures exceeding 538ºC (1000ºF) shall be ceramic-free needled silica fiber in mat form. FASTENERS All banding shall conform to ASTM A167 and A480/A480M and be furnished deburred. Banding seals shall conform to ASTM A167. Crimp seals are required for securing banding to expansion springs. Tie wire shall conform to ASTM A167 and A580/A580M. Tie wire shall be 1.3 mm (0.050 in.) minimum diameter. Glass filament tape shall be 25 mm (1 in.) wide with pressure-sensitive adhesive. Sheet metal screws shall be No. 8 by 13 mm (1/2 in.) long, austenitic stainless steel, Type "A" or "AB" point, with either slotted hex head or slotted pan head. MISCELLANEOUS ACCESSORIES Expansion springs for insulation shall be 4 in. (100 mm) long flat springs. Expansion springs for jacketing shall be compression spring assemblies. Woven fiberglass tape shall be 1/8 in. (3 mm) thick, plain-weave, and suitable for application to 1000°F. Metal sealant shall be RTV silicone, aluminum or gray color, suitable for continuous service to 400°F (204°C) and intermittent service to 500°F (260°C). MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D12 MINERAL WOOL PREFORMED PIPE SECTIONS INSULATION SYSTEM NO. DATE REVISION DESCRIPTION PAGE 1 OF 2 FEBRUARY 2011 BY FACILITY NAME LOCATION CHECKED APPROVED PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Mineral wool preformed pipe sections shall conform to ASTM C547, Type II or Type III. Premolded ells and other prefabricated fitting covers are permitted. Mineral wool pipe sections cut from board stock are not permitted. Mineral wool pipe insulation fabricated with fibers oriented perpendicular to pipe surface is not permitted. Type II – Molded, for use to °C °F Grade A – Requires No Heat-Up Schedule YES NO Type III – Precision V-Groove, for use to °C °F Grade B – Heat-Up Schedule Is Required YES NO kg/m³ lb/ft³ Maximum Shot Content In Accordance With ASTM C-1332: % Specified Density: APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER BRAND NAME ACCESSORY DESCRIPTION METAL JACKETING All jacketing shall be furnished with integral, continuously heat-sealed Polysurlyn moisture barrier. Aluminum jacketing for piping and equipment shall be stucco-embossed finish, except for head segments, fitting and valve covers shall be smooth finish. Metal jacketing on vessels less than 1200 mm (48 in.) in diameter, and all piping, shall be aluminum, 0.5 mm (0.020-in.) thick and machine-rolled for circumferential fit. Stainless steel jacketing, if required, shall be 0.25 mm (0.010-in.) thick. FABRICATION ADHESIVES FACINGS Neoprene-based contact cement Facing shall be as agreed between the purchaser and manufacturer. MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D12 MINERAL WOOL PREFORMED PIPE SECTIONS INSULATION SYSTEM FACILITY NAME LOCATION PAGE 2 OF 2 FEBRUARY 2011 PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Mineral wool preformed pipe sections shall conform to ASTM C547, Type II or Type III. Premolded ells and other prefabricated fitting covers are permitted. Mineral wool pipe sections cut from board stock are not permitted. Mineral wool pipe insulation fabricated with fibers oriented perpendicular to pipe surface is not permitted. Type II – Molded, for use to °C °F Grade A – Requires No Heat-Up Schedule YES NO Type III – Precision V-Groove, for use to °C °F Grade B – Heat-Up Schedule Is Required YES NO kg/m³ lb/ft³ Maximum Shot Content In Accordance With ASTM C-1332: % Specified Density: APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER BRAND NAME ACCESSORY DESCRIPTION EXPANSION JOINT MATERIAL Expansion joint material for application to 538ºC (1000ºF) shall be a 80 to 192 kg/m³ (5 to 12 lb/ft³) nominal density Type E glass fiber blanket in mat form without the use of resinous or organic binders. Expansion joint material for application at temperatures exceeding 538ºC (1000ºF) shall be ceramic-free needled silica fiber in mat form. FASTENERS All banding shall conform to ASTM A167 and A480/A480M and be furnished deburred. Banding seals shall conform to ASTM A167. Tie wire shall conform to ASTM A167 and A580/A580M. Tie wire shall be 1.3 mm (0.050 in.) minimum diameter. Glass filament tape shall be 25 mm (1 in.) wide with pressure-sensitive adhesive. Sheet metal screws shall be No. 8 by 13 mm (1/2 in.) long, austenitic stainless steel, Type "A" or "AB" point, with either slotted hex head or slotted pan head. MISCELLANEOUS ACCESSORIES Woven fiberglass tape shall be 3 mm (1/8 in.) thick, plain-weave, and suitable for application to 538°C (1000°F). Metal sealant shall be RTV silicone, aluminum or gray color, suitable for continuous service to 204°C (400°F) and intermittent service to 260°C (500°F). MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D13 MINERAL WOOL BOARD INSULATION SYSTEM FOR EQUIPMENT NO. DATE PAGE 1 OF 2 FEBRUARY 2011 REVISION DESCRIPTION BY FACILITY NAME LOCATION CHECKED APPROVED PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Mineral wool board shall conform to ASTM C612, Type IVB. kg/m³ lb/ft³ Maximum Shot Content In Accordance With ASTM C-1332: Specified Density: APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER ACCESSORY DESCRIPTION METAL JACKETING All jacketing shall be furnished with integral, continuously heat-sealed Polysurlyn moisture barrier. Aluminum jacketing for piping and equipment shall be stucco-embossed finish, except for head segments, fitting and valve covers shall be smooth finish. Metal jacketing on vertical equipment 1200 mm (48 in.) and larger in diameter shall be aluminum sheets, 0.6 mm (0.024-in.) thick with 32 mm (1-1/4-in.) pitch corrugations. Corrugated jacketing shall be approximately 825 mm (33-in.) to 1200 mm (48-in.) wide by 3000 mm (10-ft) long. The length of corrugated jacketing shall be modified to minimize waste and cutting. Metal jacketing on horizontal equipment 1200 mm (48 in.) and larger in diameter shall be aluminum 0.6 mm (0.024-in.) thick. Metal jacketing on vessels less than 1200 mm (48 in.) in diameter, and all piping, shall be aluminum, 0.5 mm (0.020-in.) thick and machine-rolled for circumferential fit. Stainless steel jacketing, if required, shall be 0.25 mm (0.010-in.) thick. FABRICATION ADHESIVES Neoprene-based contact cement % BRAND NAME MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D13 MINERAL WOOL BOARD INSULATION SYSTEM FOR EQUIPMENT FACILITY NAME LOCATION PAGE 2 OF 2 FEBRUARY 2011 PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Mineral wool board shall conform to ASTM C612, Type IVB. kg/m³ lb/ft³ Maximum Shot Content In Accordance With ASTM C-1332: Specified Density: APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER ACCESSORY DESCRIPTION EXPANSION JOINT MATERIAL Expansion joint material for application to 538ºC (1000ºF) shall be a 80 to 192 kg/m³ (5 to 12 lb/ft³) nominal density Type E glass fiber blanket in mat form without the use of resinous or organic binders. Expansion joint material for application at temperatures exceeding 538ºC (1000ºF) shall be ceramic-free needled silica fiber in mat form. FASTENERS All banding shall conform to ASTM A167 and A480/A480M and be furnished deburred. Banding seals shall conform to ASTM A167. Crimp seals are required for securing banding to expansion springs. Sheet metal screws shall be No. 8 by 13 mm (1/2 in.) long, austenitic stainless steel, Type "A" or "AB" point, with either slotted hex head or slotted pan head. MISCELLANEOUS ACCESSORIES Expansion springs for jacketing shall be compression spring assemblies. Metal sealant shall be RTV silicone, aluminum or gray color, suitable for continuous service to 204°C (400°F) and intermittent service to 260°C (500°F). % BRAND NAME MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D14 MINERAL WOOL BLANKET INSULATION SYSTEM FOR PIPE AND EQUIPMENT NO. DATE REVISION DESCRIPTION PAGE 1 OF 2 FEBRUARY 2011 BY FACILITY NAME LOCATION CHECKED APPROVED PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Mineral wool blanket shall conform to ASTM C592, Type II. Facings shall be supplied as indicated. Inside Face: Hex Mesh Metal Lath Material: Stainless Steel Galvanized Outside Face: Hex Mesh Metal Lath Material: Stainless Steel Galvanized kg/m³ lb/ft³ Maximum Shot Content In Accordance With ASTM C-1332: % Specified Density: APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER ACCESSORY DESCRIPTION METAL JACKETING All jacketing shall be furnished with integral, continuously heat-sealed Polysurlyn moisture barrier. Aluminum jacketing for piping and equipment shall be stucco-embossed finish, except for head segments, fitting and valve covers shall be smooth finish. Metal jacketing on vertical equipment 1200 mm (48 in.) and larger in diameter shall be aluminum sheets, 0.6 mm (0.024-in.) thick with 32 mm (1-1/4-in.) pitch corrugations.Metal jacketing on vessels less than 48 inches (1200 mm) in diameter, and all piping, shall be aluminum, 0.020-inch (0.5-mm) thick and machine-rolled for circumferential fit. Corrugated jacketing shall be approximately 825 mm (33-in.) to 1200 mm (48-in.) wide by 3000 mm (10-ft) long. The length of corrugated jacketing shall be modified to minimize waste and cutting. Metal jacketing on horizontal equipment 1200 mm (48 in.) and larger in diameter shall be aluminum 0.6 mm (0.024-in.) thick. Metal jacketing on vessels less than 1200 mm (48 in.) in diameter, and all piping, shall be aluminum, 0.5 mm (0.020-in.) thick and machine-rolled for circumferential fit. Stainless steel jacketing, if required, shall be 0.25 mm (0.010-in.) thick. MANUFACTURER BRAND NAME BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D14 MINERAL WOOL BLANKET INSULATION SYSTEM FOR PIPE AND EQUIPMENT FACILITY NAME LOCATION PAGE 2 OF 2 FEBRUARY 2011 PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Mineral wool blanket shall conform to ASTM C592, Type II. Facings shall be supplied as indicated. Inside Face: Hex Mesh Metal Lath Material: Stainless Steel Galvanized Outside Face: Hex Mesh Metal Lath Material: Stainless Steel Galvanized kg/m³ lb/ft³ Maximum Shot Content In Accordance With ASTM C-1332: % Specified Density: APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER SEALANT Metal sealant shall be RTV silicone, aluminum or gray color, suitable for continuous service to 400°F (204°C) and intermittent service to 500°F (260°C). FASTENERS All banding shall conform to ASTM A167 and A480/A480M and be furnished deburred. Banding seals shall conform to ASTM A167. Sheet metal screws shall be No. 8 by 13 mm (1/2 in.) long, austenitic stainless steel, Type "A" or "AB" point, with either slotted hex head or slotted pan head. BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D15 GLASS FIBER PREFORMED PIPE SECTIONS INSULATION SYSTEM NO. DATE REVISION DESCRIPTION PAGE 1 OF 2 FEBRUARY 2011 BY FACILITY NAME LOCATION CHECKED APPROVED PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Glass fiber preformed pipe sections shall conform to ASTM C547, Type I. Premolded ells and other prefabricated fitting covers are permitted. Glass fiber pipe sections cut from board stock are not permitted. Glass fiber pipe insulation fabricated with fibers oriented perpendicular to pipe surface is not permitted. Grade A – Requires No Heat-Up Schedule Grade B – Heat-Up Schedule Is Required APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER BRAND NAME ACCESSORY DESCRIPTION METAL JACKETING All jacketing shall be furnished with integral, continuously heat-sealed Polysurlyn moisture barrier. Aluminum jacketing for piping and equipment shall be stucco-embossed finish, except for head segments, fitting and valve covers shall be smooth finish. Metal jacketing on vessels less than 1200 mm (48 in.) in diameter, and all piping, shall be aluminum, 0.5 mm (0.020-in.) thick and machine-rolled for circumferential fit. FACINGS Facing shall be as agreed between the purchaser and manufacturer. EXPANSION JOINT MATERIAL Expansion joint material for application to 538ºC (1000ºF) shall be a 80 to 192 kg/m³ (5 to 12 lb/ft³) nominal density Type E glass fiber blanket in mat form without the use of resinous or organic binders. MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D15 GLASS FIBER PREFORMED PIPE SECTIONS INSULATION SYSTEM FACILITY NAME LOCATION PAGE 2 OF 2 FEBRUARY 2011 PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Glass fiber preformed pipe sections shall conform to ASTM C547, Type I. Premolded ells and other prefabricated fitting covers are permitted. Glass fiber pipe sections cut from board stock are not permitted. Glass fiber pipe insulation fabricated with fibers oriented perpendicular to pipe surface is not permitted. Grade A – Requires No Heat-Up Schedule Grade B – Heat-Up Schedule Is Required APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER BRAND NAME ACCESSORY DESCRIPTION FASTENERS All banding shall conform to ASTM A167 and A480/A480M and be furnished deburred. Banding seals shall conform to ASTM A167. Tie wire shall conform to ASTM A167 and A580/A580M. Tie wire shall be 1.3 mm (0.050 in.) minimum diameter. Glass filament tape shall be 25 mm (1 in.) wide with pressure-sensitive adhesive. Sheet metal screws shall be No. 8 by 13 mm (1/2 in.) long, austenitic stainless steel, Type "A" or "AB" point, with either slotted hex head or slotted pan head. Woven fiberglass tape shall be 3 mm (1/8 in.) thick, plain-weave, and suitable for application to 538°C (1000°F). MISCELLANEOUS ACCESSORIES Metal sealant shall be RTV silicone, aluminum or gray color, suitable for continuous service to 204°C (400°F) and intermittent service to 260°C (500°F). Fabrication adhesive shall be neoprene-based contact cement. MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D16 GLASS FIBER BOARD INSULATION SYSTEM FOR EQUIPMENT NO. DATE PAGE 1 OF 2 FEBRUARY 2011 REVISION DESCRIPTION BY FACILITY NAME LOCATION CHECKED APPROVED PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Glass fiber board shall conform to ASTM C612, Type II, Grade A, Category 2. kg/m³ lb/ft³ Specified Density: APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER ACCESSORY DESCRIPTION METAL JACKETING All jacketing shall be furnished with integral, continuously heat-sealed Polysurlyn moisture barrier. Aluminum jacketing for piping and equipment shall be stucco-embossed finish, except for head segments, fitting and valve covers shall be smooth finish. Metal jacketing on vertical equipment 1200 mm (48 in.) and larger in diameter shall be aluminum sheets, 0.6 mm (0.024-in.) thick with 32 mm (1-1/4-in.) pitch corrugations. Corrugated jacketing shall be approximately 825 mm (33-in.) to 1200 mm (48-in.) wide by 3000 mm (10-ft) long. The length of corrugated jacketing shall be modified to minimize waste and cutting. Metal jacketing on horizontal equipment 1200 mm (48 in.) and larger in diameter shall be aluminum 0.6 mm (0.024-in.) thick. Metal jacketing on vessels less than 1200 mm (48 in.) in diameter, and all piping, shall be aluminum, 0.5 mm (0.020-in.) thick and machine-rolled for circumferential fit. FABRICATION ADHESIVES Neoprene-based contact cement BRAND NAME MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D16 GLASS FIBER BOARD INSULATION SYSTEM FOR EQUIPMENT FACILITY NAME LOCATION PAGE 2 OF 2 FEBRUARY 2011 PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Glass fiber board shall conform to ASTM C612, Type II, Grade A, Category 2. kg/m³ lb/ft³ Specified Density: APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER ACCESSORY DESCRIPTION EXPANSION JOINT MATERIAL Expansion joint material for application to 538ºC (1000ºF) shall be a 80 to 192 kg/m³ (5 to 12 lb/ft³) nominal density Type E glass fiber blanket in mat form without the use of resinous or organic binders. FASTENERS All banding shall conform to ASTM A167 and A480/A480M and be furnished deburred. Banding seals shall conform to ASTM A167. Crimp seals are required for securing banding to expansion springs. Sheet metal screws shall be No. 8 by 13 mm (1/2 in.) long, austenitic stainless steel, Type "A" or "AB" point, with either slotted hex head or slotted pan head. MISCELLANEOUS ACCESSORIES Expansion springs for jacketing shall be compression spring assemblies. Metal sealant shall be RTV silicone, aluminum or gray color, suitable for continuous service to 204°C (400°F) and intermittent service to 260°C (500°F). BRAND NAME MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D17 GLASS FIBER BLANKET INSULATION SYSTEM FOR PIPE AND EQUIPMENT NO. DATE REVISION DESCRIPTION PAGE 1 OF 2 FEBRUARY 2011 BY FACILITY NAME LOCATION CHECKED APPROVED PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Glass fiber blanket shall conform to ASTM C592, Type I. Blanket is not furnished with facings. kg/m³ lb/ft³ Specified Density: APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER ACCESSORY DESCRIPTION METAL JACKETING All jacketing shall be furnished with integral, continuously heat-sealed Polysurlyn moisture barrier. Aluminum jacketing for piping and equipment shall be stucco-embossed finish, except for head segments, fitting and valve covers shall be smooth finish. Metal jacketing on horizontal equipment 1200 mm (48 in.) and larger in diameter shall be aluminum 0.6 mm (0.024-in.) thick. Metal jacketing on vessels less than 1200 mm (48 in.) in diameter, and all piping, shall be aluminum, 0.5 mm (0.020-in.) thick and machine-rolled for circumferential fit. SEALANT Metal sealant shall be RTV silicone, aluminum or gray color, suitable for continuous service to 204°C (400°F) and intermittent service to 260°C (500°F). FASTENERS All banding shall conform to ASTM A167 and A480/A480M and be furnished deburred. Banding seals shall conform to ASTM A167. Sheet metal screws shall be No. 8 by 13 mm (1/2 in.) long, austenitic stainless steel, Type "A" or "AB" point, with either slotted hex head or slotted pan head. MANUFACTURER BRAND NAME BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D17 GLASS FIBER BLANKET INSULATION SYSTEM FOR PIPE AND EQUIPMENT FACILITY NAME LOCATION PAGE 2 OF 2 FEBRUARY 2011 PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Glass fiber blanket shall conform to ASTM C592, Type I. Blanket is not furnished with facings. kg/m³ lb/ft³ Specified Density: APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER ACCESSORY DESCRIPTION MANUFACTURER BRAND NAME BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D18 CELLULAR GLASS BLOCK AND FABRICATED SECTIONS INSULATION SYSTEM NO. DATE REVISION DESCRIPTION PAGE 1 OF 2 FEBRUARY 2011 BY FACILITY NAME LOCATION CHECKED APPROVED PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Cellular glass block and fabricated sections shall conform to ASTM C552, Grade 1, Types 1, 2, and 3, including annexes, and be fabricated to the dimensions of ASTM C450. Gypsum cement shall be used for fabrication. APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER BRAND NAME ACCESSORY DESCRIPTION METAL JACKETING All jacketing shall be furnished with integral, continuously heat-sealed Polysurlyn moisture barrier. Aluminum jacketing for piping and equipment shall be stucco-embossed finish, except for head segments, fitting and valve covers shall be smooth finish. Metal jacketing on vertical equipment 1200 mm (48 in.) and larger in diameter shall be aluminum sheets, 0.6 mm (0.024-in.) thick with 32 mm (1-1/4-in.) pitch corrugations. Corrugated jacketing shall be approximately 825 mm (33-in.) to 1200 mm (48-in.) wide by 3000 mm (10-ft) long. The length of corrugated jacketing shall be modified to minimize waste and cutting. Metal jacketing on horizontal equipment 1200 mm (48 in.) and larger in diameter shall be aluminum 0.6 mm (0.024-in.) thick. Metal jacketing on vessels less than 1200 mm (48 in.) in diameter, and all piping, shall be aluminum, 0.5 mm (0.020-in.) thick and machine-rolled for circumferential fit. Stainless steel jacketing, if required, shall be 0.25 mm (0.010-in.) thick. LAMINATION / FABRICATION ADHESIVE Gypsum cement (asphalt is not permitted) MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D18 CELLULAR GLASS BLOCK AND FABRICATED SECTIONS INSULATION SYSTEM FACILITY NAME LOCATION PAGE 2 OF 2 FEBRUARY 2011 PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Cellular glass block and fabricated sections shall conform to ASTM C552, Grade 1, Types 1, 2, and 3, including annexes, and be fabricated to the dimensions of ASTM C450. Gypsum cement shall be used for fabrication. APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER BRAND NAME ACCESSORY DESCRIPTION EXPANSION JOINT MATERIAL Expansion joint material for application to 538ºC (1000ºF) shall be a 80 to 192 kg/m³ (5 to 12 lb/ft³) nominal density Type E glass fiber blanket in mat form without the use of resinous or organic binders. FASTENERS All banding shall conform to ASTM A167 and A480/A480M and be furnished deburred. Banding seals shall conform to ASTM A167. Crimp seals are required for securing banding to expansion springs. Tie wire shall conform to ASTM A167 and A580/A580M. Tie wire shall be 1.3 mm (0.050 in.) minimum diameter. Glass filament tape shall be 25 mm (1 in.) wide with pressure-sensitive adhesive. Sheet metal screws shall be No. 8 by 13 mm (1/2 in.) long, austenitic stainless steel, Type "A" or "AB" point, with either slotted hex head or slotted pan head. Expansion springs for insulation shall be 100 mm (4 in.) long flat springs. MISCELLANEOUS ACCESSORIES Expansion springs for jacketing shall be compression spring assemblies. Woven fiberglass tape shall be 3 mm (1/8 in.) thick, plain-weave, and suitable for application to 538°C (1000°F). Metal sealant shall be RTV silicone, aluminum or gray color, suitable for continuous service to 204°C (400°F) and intermittent service to 260°C (500°F). MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D19 PAGE 1 OF 2 FEBRUARY 2011 POLYISOCYANURATE INSULATION SYSTEM NO. DATE REVISION DESCRIPTION BY FACILITY NAME LOCATION CHECKED APPROVED PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Rigid, cellular polyisocyanurate block and fabricated sections shall conform to ASTM C591, Grade 2, Type II or IV, and be fabricated to the dimensions of ASTM C450. Type II– 40 kg/m³ (2.5 lbs/ft³) Minimum Density Type IV– 32 kg/m³ (2.0 lbs/ft³) Minimum Density APPROVED MANUFACTURERS MANUFACTURER BRANDNAME MANUFACTURER BRANDNAME ACCESSORY DESCRIPTION METAL JACKETING All jacketing shall be furnished with integral, continuously heat-sealed Polysurlyn moisture barrier. Aluminum jacketing for piping and equipment shall be stucco-embossed finish, except for head segments, fitting and valve covers shall be smooth finish. Metal jacketing on vertical equipment 1200 mm (48 in.) and larger in diameter shall be aluminum sheets, 0.6 mm (0.024-in.) thick with 32 mm (1-1/4-in.) pitch corrugations. Corrugated jacketing shall be approximately 825 mm (33-in.) to 1200 mm (48-in.) wide by 3000 mm (10-ft) long. The length of corrugated jacketing shall be modified to minimize waste and cutting. Metal jacketing on horizontal equipment 1200 mm (48 in.) and larger in diameter shall be aluminum 0.6 mm (0.024-in.) thick. Metal jacketing on vessels less than 1200 mm (48 in.) in diameter, and all piping, shall be aluminum, 0.5 mm (0.020-in.) thick and machine-rolled for circumferential fit. FABRICATION ADHESIVE Solvent-borne adhesive. MANUFACTURER BRANDNAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D19 PAGE 2 OF 2 FEBRUARY 2011 POLYISOCYANURATE INSULATION SYSTEM FACILITY NAME LOCATION PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Rigid, cellular polyisocyanurate block and fabricated sections shall conform to ASTM C591, Grade 2, Type II or IV, and be fabricated to the dimensions of ASTM C450. Type II– 40 kg/m³ (2.5 lbs/ft³) Minimum Density Type IV– 32 kg/m³ (2.0 lbs/ft³) Minimum Density APPROVED MANUFACTURERS MANUFACTURER BRANDNAME MANUFACTURER BRANDNAME ACCESSORY DESCRIPTION EXPANSION JOINT MATERIAL Expansion joint material for application to 538ºC (1000ºF) shall be a 80 to 192 kg/m³ (5 to 12 lb/ft³) nominal density Type E glass fiber blanket in mat form without the use of resinous or organic binders. FASTENERS All banding shall conform to ASTM A167 and A480/A480M and be furnished deburred. Banding seals shall conform to ASTM A167. Tie wire shall conform to ASTM A167 and A580/A580M. Tie wire shall be 1.3 mm (0.050 in.) minimum diameter. Glass filament tape shall be 25 mm (1 in.) wide with pressure-sensitive adhesive. MISCELLANEOUS ACCESSORIES Sheet metal screws shall be No. 8 by 13 mm (1/2 in.) long, austenitic stainless steel, Type "A" or "AB" point, with either slotted hex head or slotted pan head. Metal sealant shall be RTV silicone, aluminum or gray color, suitable for continuous service to 204°C (400°F) and intermittent service to 260°C (500°F). MANUFACTURER BRANDNAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D20 CERAMIC FIBER BLANKET INSULATION SYSTEM NO. DATE PAGE 1 OF 1 FEBRUARY 2011 REVISION DESCRIPTION BY FACILITY NAME LOCATION APPROVED PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Ceramic fiber blanket shall conform to ASTM C892, Type II. kg/m³ lb/ft³ Nominal Density: APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER ACCESSORY CHECKED DESCRIPTION BRAND NAME MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D21 GLASS FIBER NEEDLED BLANKET INSULATION SYSTEM NO. DATE REVISION DESCRIPTION PAGE 1 OF 1 FEBRUARY 2011 BY FACILITY NAME LOCATION CHECKED APPROVED PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Type “E” glass fiber needled blanket shall be constructed of mechanically needled, textile glass fiber mat without binder. Insulation shall be suitable for continuous service at 649°C (1200°F), and shall have a nominal density of 128 kg/m³ (8 lb/ft³). APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER BRAND NAME ACCESSORY DESCRIPTION MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D22 FLEXIBLE ELASTOMERIC CELLULAR THERMAL INSULATION SYSTEM FOR PIPE AND EQUIPMENT NO. DATE REVISION DESCRIPTION PAGE 1 OF 1 FEBRUARY 2011 BY FACILITY NAME LOCATION CHECKED APPROVED PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Flexible elastomeric cellular thermal insulation shall conform to ASTM C534, Grade 3, Type I (tubular) and Type II (sheet). APPROVED MANUFACTURERS MANUFACTURER BRANDNAME MANUFACTURER BRANDNAME ACCESSORY NONMETALLIC JACKETING DESCRIPTION Liquid-applied coating and reinforcing membrane, as recommended by manufacturer. Sheet material, thickness and composition as recommended by manufacturer. ADHESIVES Application adhesives shall be as recommended by manufacturer. MANUFACTURER BRANDNAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D23 RIGID CELLULAR PHENOLIC THERMAL INSULATION SYSTEM FOR PIPE AND EQUIPMENT NO. DATE REVISION DESCRIPTION PAGE 1 OF 2 FEBRUARY 2011 BY FACILITY NAME LOCATION CHECKED APPROVED PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Rigid cellular phenolic thermal insulation shall conform to ASTM C1126, Type III, Grade 1. Facings shall be supplied as indicated. APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER BRAND NAME ACCESSORY DESCRIPTION METAL JACKETING All jacketing shall be furnished with integral, continuously heat-sealed Polysurlyn moisture barrier. Aluminum jacketing for piping and equipment shall be stucco-embossed finish, except for head segments, fitting and valve covers shall be smooth finish. Metal jacketing on vertical equipment 1200 mm (48 in.) and larger in diameter shall be aluminum sheets, 0.6 mm (0.024-in.) thick with 32 mm (1-1/4-in.) pitch corrugations. Corrugated jacketing shall be approximately 825 mm (33-in.) to 1200 mm (48-in.) wide by 3000 mm (10-ft) long. The length of corrugated jacketing shall be modified to minimize waste and cutting. Metal jacketing on horizontal equipment 1200 mm (48 in.) and larger in diameter shall be aluminum 0.6 mm (0.024-in.) thick. Metal jacketing on vessels less than 1200 mm (48 in.) in diameter, and all piping, shall be aluminum, 0.5 mm (0.020-in.) thick and machine-rolled for circumferential fit. FABRICATION ADHESIVE Solvent-borne adhesive. MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D23 RIGID CELLULAR PHENOLIC THERMAL INSULATION SYSTEM FOR PIPE AND EQUIPMENT FACILITY NAME LOCATION PAGE 2 OF 2 FEBRUARY 2011 PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: Rigid cellular phenolic thermal insulation shall conform to ASTM C1126, Type III, Grade 1. Facings shall be supplied as indicated. APPROVED MANUFACTURERS MANUFACTURER BRAND NAME MANUFACTURER BRAND NAME ACCESSORY DESCRIPTION EXPANSION JOINT MATERIAL Expansion joint material for application to 538ºC (1000ºF) shall be a 80 to 192 kg/m³ (5 to 12 lb/ft³) nominal density Type E glass fiber blanket in mat form without the use of resinous or organic binders. FASTENERS All banding shall conform to ASTM A167 and A480/A480M and be furnished deburred. Banding seals shall conform to ASTM A167. Tie wire shall conform to ASTM A167 and A580/A580M. Tie wire shall be 1.3 mm (0.050 in.) minimum diameter. Glass filament tape shall be 25 mm (1 in.) wide with pressure-sensitive adhesive. Sheet metal screws shall be No. 8 by 13 mm (1/2 in.) long, austenitic stainless steel, Type "A" or "AB" point, with either slotted hex head or slotted pan head. MISCELLANEOUS ACCESSORIES Metal sealant shall be RTV silicone, aluminum or gray color, suitable for continuous service to 204°C (400°F) and intermittent service to 260°C (500°F). MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D24 USER-DEFINED INSULATION SYSTEM FOR PIPE AND EQUIPMENT NO. DATE REVISION DESCRIPTION PAGE 1 OF 2 FEBRUARY 2011 BY FACILITY NAME LOCATION CHECKED APPROVED PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: MANUFACTURER ACCESSORY METAL JACKETING NON-METALLIC JACKETING FABRICATION ADHESIVE EXPANSION JOINT MATERIAL APPROVED MANUFACTURERS BRAND NAME MANUFACTURER DESCRIPTION BRAND NAME MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 DATA SHEET PIP INSH1000-D24 USER-DEFINED INSULATION SYSTEM FOR PIPE AND EQUIPMENT FACILITY NAME LOCATION PAGE 2 OF 2 FEBRUARY 2011 PROJECT NO. PROJECT DOCUMENT NO. INSULATION SPECIFICATION: MANUFACTURER ACCESSORY FASTENERS MISCELLANEOUS ACCESSORIES APPROVED MANUFACTURERS BRAND NAME MANUFACTURER DESCRIPTION BRAND NAME MANUFACTURER BRAND NAME ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F1 CALCIUM SILICATE INSULATION FOR HC ASTM C533 Type I (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 801 to 850 851 to 900 901 to 950 CHECKED APPROVED 951 1001 1051 1101 1151 to to to to to 1000 1050 1100 1150 1200 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F2 CALCIUM SILICATE INSULATION FOR PP ASTM C533 Type I (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 801 to 850 851 to 900 901 to 950 CHECKED APPROVED 951 1001 1051 1101 1151 to to to to to 1000 1050 1100 1150 1200 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F3 CALCIUM SILICATE INSULATION – COMBINED TABLE ASTM C533 Type I (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 801 to 850 851 to 900 901 to 950 CHECKED APPROVED 951 1001 1051 1101 1151 to to to to to 1000 1050 1100 1150 1200 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F4 CELLULAR GLASS INSULATION FOR HC ASTM C552 (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F5 CELLULAR GLASS INSULATION FOR PP ASTM C552 (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F6 CELLULAR GLASS INSULATION – COMBINED TABLE ASTM C552 (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F7 FIBERGLASS INSULATION FOR HC ASTM C547, Type 1 / C612, Type I (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 801 to 850 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F8 FIBERGLASS INSULATION FOR PP ASTM C547, Type 1 / C612, Type I (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 801 to 850 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F9 FIBERGLASS INSULATION – COMBINED TABLE ASTM C547, Type 1 / C612, Type I (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 801 to 850 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F10 MINERAL WOOL INSULATION FOR HC ASTM C547, Type II or III / C612, Type IVB (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 801 to 850 851 to 900 901 to 950 CHECKED APPROVED 951 1001 1051 1101 1151 to to to to to 1000 1050 1100 1150 1200 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F11 MINERAL WOOL INSULATION FOR PP ASTM C547, Type II or III / C612, Type IVB (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 801 to 850 851 to 900 901 to 950 CHECKED APPROVED 951 1001 1051 1101 1151 to to to to to 1000 1050 1100 1150 1200 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F12 MINERAL WOOL INSULATION – COMBINED TABLE ASTM C547, Type II or III / C612, Type IVB (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 801 to 850 851 to 900 901 to 950 CHECKED APPROVED 951 1001 1051 1101 1151 to to to to to 1000 1050 1100 1150 1200 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F13 EXPANDED PERLITE INSULATION FOR HC ASTM C610 (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 801 to 850 851 to 900 901 to 950 CHECKED APPROVED 951 1001 1051 1101 1151 to to to to to 1000 1050 1100 1150 1200 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F14 EXPANDED PERLITE INSULATION FOR PP ASTM C610 (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 801 to 850 851 to 900 901 to 950 CHECKED APPROVED 951 1001 1051 1101 1151 to to to to to 1000 1050 1100 1150 1200 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F15 EXPANDED PERLITE INSULATION – COMBINED TABLE ASTM C610 (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 801 to 850 851 to 900 901 to 950 CHECKED APPROVED 951 1001 1051 1101 1151 to to to to to 1000 1050 1100 1150 1200 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F16 POLYISOCYANURATE FOR HC ASTM C591 (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °F to 150 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F17 POLYISOCYANURATE FOR PP ASTM C591 (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °F to 150 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F18 POLYISOCYANURATE – COMBINED TABLE ASTM C591 (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °F to 150 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F19 ELASTOMERIC FOAM INSULATION FOR HC ASTM C534 (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °F to 150 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F20 ELASTOMERIC FOAM INSULATION FOR PP ASTM C534 (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °F to 150 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F21 ELASTOMERIC FOAM INSULATION – COMBINED TABLE ASTM C534 (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °F to 150 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F22 PHENOLIC FOAM INSULATION FOR HC ASTM C1126 (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °F to 150 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F23 PHENOLIC FOAM INSULATION FOR PP ASTM C1126 (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °F to 150 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F24 PHENOLIC FOAM INSULATION – COMBINED TABLE ASTM C1126 (Inches) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °F to 150 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F25 PAGE 1 OF 1 FEBRUARY 2011 USER-DEFINED INSULATION FOR HC (Inches) FACILITY NAME: PROJECT NO.: LOCATION: PROJECT DOCUMENT NO.: INSULATION: NO. Pipe Size or O.D. (NPS) (in.) DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 801 to 850 851 to 900 901 to 950 CHECKED APPROVED 951 1001 1051 1101 1151 to to to to to 1000 1050 1100 1150 1200 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F26 PAGE 1 OF 1 FEBRUARY 2011 USER-DEFINED INSULATION FOR PP (Inches) FACILITY NAME: PROJECT NO.: LOCATION: PROJECT DOCUMENT NO.: INSULATION: NO. Pipe Size or O.D. (NPS) (in.) DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 801 to 850 851 to 900 901 to 950 CHECKED APPROVED 951 1001 1051 1101 1151 to to to to to 1000 1050 1100 1150 1200 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-F27 PAGE 1 OF 1 FEBRUARY 2011 USER-DEFINED INSULATION - COMBINED TABLE (Inches) FACILITY NAME: PROJECT NO.: LOCATION: PROJECT DOCUMENT NO.: INSULATION: NO. Pipe Size or O.D. (NPS) (in.) DATE to 150 REVISION DESCRIPTION 151 to 200 201 to 250 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in inches. 251 to 300 301 to 350 351 to 400 BY 401 to 450 451 to 500 501 to 550 Operating Temperature, °F 551 601 651 701 751 to to to to to 600 650 700 750 800 801 to 850 851 to 900 901 to 950 CHECKED APPROVED 951 1001 1051 1101 1151 to to to to to 1000 1050 1100 1150 1200 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM1 CALCIUM SILICATE INSULATION FOR HC ASTM C533 Type I (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 426 to 450 451 to 475 476 to 500 501 to 525 CHECKED 526 to 550 551 to 575 576 to 600 APPROVED 601 to 625 626 to 650 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM2 CALCIUM SILICATE INSULATION FOR PP ASTM C533 Type I (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 426 to 450 451 to 475 476 to 500 501 to 525 CHECKED 526 to 550 551 to 575 576 to 600 APPROVED 601 to 625 626 to 650 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM3 CALCIUM SILICATE INSULATION – COMBINED TABLE ASTM C533 Type I (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 426 to 450 451 to 475 476 to 500 501 to 525 CHECKED 526 to 550 551 to 575 576 to 600 APPROVED 601 to 625 626 to 650 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM4 CELLULAR GLASS INSULATION FOR HC ASTM C552 (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM5 CELLULAR GLASS INSULATION FOR PP ASTM C552 (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM6 CELLULAR GLASS INSULATION – COMBINED TABLE ASTM C552 (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM7 FIBERGLASS INSULATION FOR HC ASTM C547, Type 1 / C612, Type I (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 426 to 450 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM8 FIBERGLASS INSULATION FOR PP ASTM C547, Type 1 / C612, Type I (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 426 to 450 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM9 FIBERGLASS INSULATION – COMBINED TABLE ASTM C547, Type 1 / C612, Type I (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 426 to 450 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM10 MINERAL WOOL INSULATION FOR HC ASTM C547, Type II or III / C612, Type IVB (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 426 to 450 451 to 475 476 to 500 501 to 525 CHECKED 526 to 550 551 to 575 576 to 600 APPROVED 601 to 625 626 to 650 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM11 MINERAL WOOL INSULATION FOR PP ASTM C547, Type II or III / C612, Type IVB (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 426 to 450 451 to 475 476 to 500 501 to 525 CHECKED 526 to 550 551 to 575 576 to 600 APPROVED 601 to 625 626 to 650 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM12 MINERAL WOOL INSULATION – COMBINED TABLE ASTM C547, Type II or III / C612, Type IVB (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 426 to 450 451 to 475 476 to 500 501 to 525 CHECKED 526 to 550 551 to 575 576 to 600 APPROVED 601 to 625 626 to 650 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM13 EXPANDED PERLITE INSULATION FOR HC ASTM C610 (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 426 to 450 451 to 475 476 to 500 501 to 525 CHECKED 526 to 550 551 to 575 576 to 600 APPROVED 601 to 625 626 to 650 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM14 EXPANDED PERLITE INSULATION FOR PP ASTM C610 (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 426 to 450 451 to 475 476 to 500 501 to 525 CHECKED 526 to 550 551 to 575 576 to 600 APPROVED 601 to 625 626 to 650 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM15 EXPANDED PERLITE INSULATION – COMBINED TABLE ASTM C610 (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 426 to 450 451 to 475 476 to 500 501 to 525 CHECKED 526 to 550 551 to 575 576 to 600 APPROVED 601 to 625 626 to 650 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM16 POLYISOCYANURATE FOR HC ASTM C591 (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °C to 75 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM17 POLYISOCYANURATE FOR PP ASTM C591 (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °C to 75 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM18 POLYISOCYANURATE – COMBINED TABLE ASTM C591 (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °C to 75 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM19 ELASTOMERIC FOAM INSULATION FOR HC ASTM C534 (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °C to 75 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM20 ELASTOMERIC FOAM INSULATION FOR PP ASTM C534 (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °C to 75 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM21 ELASTOMERIC FOAM INSULATION – COMBINED TABLE ASTM C534 (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °C to 75 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM22 PHENOLIC FOAM INSULATION FOR HC ASTM C1126 (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °C to 75 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM23 PHENOLIC FOAM INSULATION FOR PP ASTM C1126 (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °C to 75 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM24 PHENOLIC FOAM INSULATION – COMBINED TABLE ASTM C1126 (mm) FACILITY NAME: PROJECT NO.: LOCATION: NO. Pipe Size or O.D. (NPS) (in.) PAGE 1 OF 1 FEBRUARY 2011 PROJECT DOCUMENT NO.: DATE REVISION DESCRIPTION BY Operating Temperature, °C to 75 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 CHECKED APPROVED ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM25 PAGE 1 OF 1 FEBRUARY 2011 USER-DEFINED INSULATION FOR HC (mm) FACILITY NAME: PROJECT NO.: LOCATION: PROJECT DOCUMENT NO.: INSULATION: NO. Pipe Size or O.D. (NPS) (in.) DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 426 to 450 451 to 475 476 to 500 501 to 525 CHECKED 526 to 550 551 to 575 576 to 600 APPROVED 601 to 625 626 to 650 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM26 PAGE 1 OF 1 FEBRUARY 2011 USER-DEFINED INSULATION FOR PP (mm) FACILITY NAME: PROJECT NO.: LOCATION: PROJECT DOCUMENT NO.: INSULATION: NO. Pipe Size or O.D. (NPS) (in.) DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 426 to 450 451 to 475 476 to 500 501 to 525 CHECKED 526 to 550 551 to 575 576 to 600 APPROVED 601 to 625 626 to 650 ASSOC. PIP: INSH1000 INSULATION THICKNESS TABLE PIP INSH1000-FM27 PAGE 1 OF 1 FEBRUARY 2011 USER-DEFINED INSULATION - COMBINED TABLE (mm) FACILITY NAME: PROJECT NO.: LOCATION: PROJECT DOCUMENT NO.: INSULATION: NO. Pipe Size or O.D. (NPS) (in.) DATE to 75 REVISION DESCRIPTION 76 to 100 101 to 125 1/2 3/4 1 1-1/2 2 3 4 6 8 10 12 14 16 18 20 24 30 36 48 Flat NOTES: 1. Thicknesses are in mm. 126 to 150 151 to 175 176 to 200 201 to 225 BY 226 to 250 251 to 275 Operating Temperature, °C 276 301 326 351 376 401 to to to to to to 300 325 350 375 400 425 426 to 450 451 to 475 476 to 500 501 to 525 CHECKED 526 to 550 551 to 575 576 to 600 APPROVED 601 to 625 626 to 650