See discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/366237375 Short Circuit Analysis for Effective Relay Coordination in Nigerian Port Authority, Rivers state Article · December 2022 DOI: 10.5281/zenodo.7431713 CITATIONS READS 0 90 2 authors, including: Kingsley Okpara Uwho Rivers State University of Science and Technology 12 PUBLICATIONS 7 CITATIONS SEE PROFILE All content following this page was uploaded by Kingsley Okpara Uwho on 13 December 2022. The user has requested enhancement of the downloaded file. Journal of Emerging Trends in Electrical Engineering Volume 4 Issue 3 DOI:https://doi.org/10.5281/zenodo.7431713 Short Circuit Analysis for Effective Relay Coordination in Nigerian Port Authority, Rivers state Kingsley Okpara Uwho*, Hachimenum Nyebuchi Amadi, Promise Obire Department of Electrical Engineering, Rivers State University, Port-Harcourt, Nigeria *Corresponding Author E-Mail Id: kingsley.uwho@ust.edu.ng ABSTRACT This study seeks to address the poor order of operation of relays in Nigerian Ports Authority (NPA) for effective relay coordination. NPA is fed from Marine Base distribution substation of 2 X 15MVA, 33kV. Short circuit analysis is used and Inverse Definite Minimum Time (IDMT) for prompt response of the relay and hence, the circuit breakers. Modelling and simulation of the network is carried out using Electrical Transient Analyzer (ETAP 19.0.1) using data obtained from the Port-Harcourt Electricity Distribution Company and the Transmission Company of Nigeria. The outcome of the analysis shows that in the existing case, the order of tripping of the primary feeder relays with their respective backup is wrong.When a 3-phase fault is initiated on the existing NPA feeder, the order of time of operation in response to fault is 82.9ms, 137ms, 213ms and 110ms, with the sequence from feeder breaker 33kV to line breaker, 33kV control panel breaker and then to 11kV incomer control breaker. The improved case gives an order of 226ms, 343ms, 411ms and 420ms. 420ms.The existing case means that fault occurs in the order of 1,4,3,2. This negates the right sequence, which is 1,2,3,4. Proper and effective relay coordination is necessary because it protects both the equipment connected in the network and the personnel working on such equipment from danger. Keywords: Circuit breaker, distribution network, nigerian ports authority, short circuit analysis, relay coordination. INTRODUCTION The sole work of a protective relay in a network is to foresee a fault and therefore energize the breaker to open the circuit as fast as possible. Directional over current relays have been used most often as an economic means for the protection of subtransmission and distribution networks or sometimes, as secondary protection of transmission system [1]. The setting of over current relays must meet all likely networks prone to faults. Time and current settings are mostly used. Over current relays have current setting multipliers within 50 – 200% in steps of 25% called the plug setting. The plug setting is dependent on the minimum fault HBRP Publication Page 1-9 2022. All Rights Reserved current and the maximum load current [2]. The reliability of a power network is largely dependent on an efficient protection scheme for it disconnects only the faulty part of a system while supply continues in the rest part of the system. Primary and secondary protections are employed in every power network for a proper relay coordination. In a situation where the primary protection fails to act, the back protection should as a matter of fact acts to save the network from a total collapse [3]. Over current relays act when the load current is more than the preset number. The duty of the TSM of the relay is to determine the time required for the relay to energize the circuit breaker while Page 1 Journal of Emerging Trends in Electrical Engineering Volume 4 Issue 3 DOI:https://doi.org/10.5281/zenodo.7431713 the plug setting dictates the current needed for the relay to pickup [4]. The coordination of an over current relay is set up at the design stage as a result of the fault current calculation. To clear off a fault properly within a given time, a relay must network with other protective relays found at adjacent buses [5]. The Resistance of a conductor is given as SHORT CIRCUIT ANALYSIS Short circuit analysis is used to determine the magnitude of the short circuit current that the system is able to yield and compares the magnitude of the circuit current with the interrupting rating of the over current protective device [6]. The following are the model equations (β¦) (2.1) Whereπ is conductor resistivity at a given temperature in β¦/m π is conductor length in meter A is conductor cross-section area in m² Cross - sectional area (A) is given: Then calculation of diameter becomes d = 2r (2.2) (2.3) From equation (3.3), radius can be evaluated as r = Per kilometer reactance of one phase can be evaluated as: Xo = 0.1445log10 ( ) + 0.0157 (2.4) DGMD- Geometric mean distance between the line conductors and ‘r’ is taken as radius of the conductors. Also, determination of line reactance X is given as: X= π₯β πβ (2.5) Thus, the distributed series impedance becomes: Zβ = R + jX (2.6) Also, the equivalent admittance which is a measure of how easily a circuit or device will allow the flow of electric current, can be represented by: Zβ = Y = = G + jB (2.7) From the above equation (2.7) G= and (2.8) (2.9) If transmission line constants for the route length πβ ππππβ are known, then transmission line constants referred to base MVA in p.u can be evaluated as: HBRP Publication Page 1-9 2022. All Rights Reserved Page 2 Journal of Emerging Trends in Electrical Engineering Volume 4 Issue 3 DOI:https://doi.org/10.5281/zenodo.7431713 Z1P.U = (2.10) For a known source Impedance and Base MVA, source impedance becomes: Source Impedance = (2.11) Total fault impedance at Marine Base 2×15MVA, 33/11kv injection substation in p.u can be evaluated as: ZF = ZS + Z1+Zt ( Zt= Zp.u = ) (2.12) (2.13) For a 3 phase 11kv line fault at the injection substation, Fault MVA = (2.14) Fault current at Marine Base injection substation can be determined as: Fault current= √ (2.15) Where VL-L = Line -Line Voltage MATERIALS AND METHOD Materials Materials employed for this analysis are obtained from the Port Harcourt Electricity Distribution Company (PHEDC) and the Transmission Company of Nigeria (TCN) and are tabulated in table 3.1 Table 1: Data for Calculations and Simulation from PHEDC and TCN[7]. S/N 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Parameter Route length of 33kv line Maximum load on 33kv line T1B 30MVA Impedance at Transmission station T1 15MVA Impedance at Marine Base Injection Substation T2 15MVA Impedance at Marine Base Injection Substation Peak load on Churchill 11kv Feeder Peak load on NPA 11kv Feeder Peak load on Station Road 11kv Feeder Peak load on Amadi North 11kv Feeder Conductor Size Conductor type Cable size CTRs Incomer CTRs Outgoing Base MVA Relay Type Conductor Resistivity at 32 ° 33kv line spacing HBRP Publication Page 1-9 2022. All Rights Reserved Assumptions 4.5km 15.3MW 12.5% 10.52% 10.6% 2.8Mw (168Amps) 2.7MW (162Amps) 3.5MW(210Amps) 3.3 MW (198Amps) 150mm sq. AAC 240mm sq. 1250-800/1 600-300/1 100 Schneider O/C and E/F Relay 2.83×10-8 3ft= 914.4mm Page 3 Journal of Emerging Trends in Electrical Engineering Volume 4 Issue 3 DOI:https://doi.org/10.5281/zenodo.7431713 Method Short circuit analysis and Inverse Definite Minimum Time (IDMT) are used for effective coordination. Electrical Transient Analyzer Program (ETAP 19.0.1) is used for the modelling and simulation. NPA Feeder Relay 7 – NPA Feeder Protective Relay Maximum load of NPA 11kV feeder = 162Amps TMS = 0.081 (Simulated Set Value) Taking time difference between two Relays as 100ms CT Ratio = 600/1A PS = 40% Curve Type: Standard Inverse Fault current (ETAP) on NPA Feeder = 4.494kA PSM = = = 18.725 T= T= = 188ms Relay 4: T2 11kV Incomer Relay Time of operation of Relay 2 = 100 + 188 = 288ms If = 3.505KA PSM = = = 7.3 0.288= TMS = 0.083 MS Relay 2: T2 33kV Control Panel Relay Time of Operation of Relay 3 = 100 + 288 = 388ms If = 1.168kA PSM = = = 6.49 0.388= TMS = 0.1 MS RESULTS AND DISCUSSION Relay Coordination on 33/11kV NPA Feeder (Existing Case) HBRP Publication Page 1-9 2022. All Rights Reserved Page 4 Journal of Emerging Trends in Electrical Engineering Volume 4 Issue 3 DOI:https://doi.org/10.5281/zenodo.7431713 Fig. 1: Circuit Breaker Tripping Sequence for Fault on NPA Feeder (Existing case). Figure 1 clearly shows the order of tripping sequence for a 3-phase simulated fault of the existing case injected on NPA feeder. The tripping sequence is in the order of: Feeder circuit breaker, 33KV line Breaker, 33KV Control Panel Breaker, 11KV Incomer Breaker. This response to fault violates the right order of operation. CB7 – NPA CB4 – T2A 11KV INCOMER CB3 - 33KV CONTROL PANEL CB1 - 33KV LINE BREAKER Table 2: Relay response sequence with time of operation for Existing Case. Table 2 represents the operation of relays with its associated circuit breakers and the corresponding tripping time (ms) for 3phase fault on NPA feeder of the existing HBRP Publication Page 1-9 2022. All Rights Reserved case. There is a clear violation of relay response to fault when compared with the proper sequence. Page 5 Journal of Emerging Trends in Electrical Engineering Volume 4 Issue 3 DOI:https://doi.org/10.5281/zenodo.7431713 Improved Relay Coordination TRIPPING SEQUENCE ON NPA FEEDER (EXISTING CASE) 250 213 TIME (ms) 200 137 150 100 50 110 82.9 1 4 NPA T2A 11KV INCOMER 3 2 33KV CONTROL PANEL 33KV LINE BREAKER 0 TRIPPING SEQUENCE TRIPPING SEQUENCE TIME (ms) Fig. 2: Graph showing Sequence of Circuit Breaker Operation for Fault on NPA Feeder (Existing case). Figure 2 represents a graph of the various circuit breaker tripping sequence with its associated time of operation in response to a 3-phase fault on NPA feeder of the existing case. Fig. 3: Circuit Breaker Tripping sequence for Fault on NPA Feeder (improved case). Figure 3 explains the simulated sequence of tripping for a 3-phase fault on NPA 11kV outgoing feeder for the modified or new case. This mode of operation shows HBRP Publication Page 1-9 2022. All Rights Reserved the right order, which is from Feeder Circuit Breaker to 11kV Incomer Breaker to 33kV Control Panel Breaker and to 33kV line Breaker. Page 6 Journal of Emerging Trends in Electrical Engineering Volume 4 Issue 3 DOI:https://doi.org/10.5281/zenodo.7431713 Table 3: Relay response be sequence with time of operation (improved Case). Table 3 represents the operation of relays with its associated circuit breakers and the corresponding tripping time (ms) for the improved case for a 3-phase fault on NPA feeder. TIME (ms) TRIPPING SEQUENCE ON NPA FEEDER (NEW CASE) 600 343 411 420 400 226 200 1 2 3 4 NPA T2A 11KV INCOMER 33KV CONTROL PANEL 33KV LINE BREAKER 0 TRIPPING SEQUENCE TRIPPING SEQUENCE TIME (ms) Fig. 4: Graph showing Sequence of Circuit Breaker operation for fault on NPA feeder (improved case). Fig. 4 shows a graph of the numerous circuit breaker tripping sequence with its associated time of operation in response to a 3-phase fault on NPA feeder for the improved case. Table 4: Comparison of Existing and Improved Relay Coordination on NPA Feeder. Comparison of Existing Case With New Case on NPA Feeder Feeder Tripping Sequence Time (ms) EXISTING NEW NPA 1 82.9 226 T2A 11KV Incomer 2 137 343 33KV Control Panel 3 213 411 33KV Line Breaker 4 110 420 Table 4 clearly shows the difference between the existing and improved case regarding sequence of operation of various circuit breakers to fault on NPA 11kV outgoing feeder HBRP Publication Page 1-9 2022. All Rights Reserved Page 7 Journal of Emerging Trends in Electrical Engineering Volume 4 Issue 3 DOI:https://doi.org/10.5281/zenodo.7431713 COMPARISON BETWEEN EXISTING CASE WITH NEW CASE 420 411 450 400 343 TIME (ms) 350 300 250 226 213 200 150 100 137 110 82.9 50 0 NPA T2A 11KV INCOMER 33KV CONTROL PANEL 33KV LINE BREAKER TRIPPING SEQUENCE TRIPPING SEQUENCE EXISTING NEW Fig. 5: Graph Comparing Sequence of Circuit Breaker Operation for fault on NPA Feeder (Existing case vs improved Case). Fig 4 represents the different behaviour of circuit breakers in response to a 3-phase fault on NPA feeder when comparing existing with improved case. Table 5: Relay Operating time for fault on NPA feeder. Relay Time Operations (Sec) Relay Theoretical Calculations / (SOP) 0.081 (1) Relay 7 0.083 (2) Relay 4 0.1 (3) Relay 2 0.34 (4) Relay 1 ETAP Modified Network/ (SOP) 0.08 (1) 0.082 (2) 0.09 (3) 0.34 (4) Table 5 shows a clear similarity between manually calculated relay response time with simulated time for a 3phase fault on NPA 11kV feeder for both existing and modified cases. CONCLUSION A reliable and efficient system is the aim of every designer. An efficient relay operation prevents downtimes and guarantees the safety of personnel on site. The relay coordination of NPA has been improved as the right order of tripping has been corrected and is now from Feeder Circuit Breaker to 11kV Incomer Breaker to 33kV Control Panel Breaker and then to HBRP Publication Page 1-9 2022. All Rights Reserved ETAP Existing Network/ (SOP) 0.082 (1) 0.11 (4) 0.09 (3) 0.19 (2) Curve Type SIT SIT SIT Definite Time 33kV line Breaker, which means 1,2,3 and 4. REFERENCES 1. Noghabi, A. S., Sadeh, J., & Mashhadi, H. R. (2009). Considering different network topologies in optimal overcurrent relay coordination using a hybrid GA. IEEE Transactions on Power Delivery, 24(4), 1857-1863. 2. So, C. W., & Li, K. K. (2000). Overcurrent relay coordination by evolutionary programming. Electric power systems research, 53(2), 83-90. 3. Alam, M. N., Das, B., & Pant, V. (2015). A comparative study of metaheuristic optimization approaches Page 8 Journal of Emerging Trends in Electrical Engineering Volume 4 Issue 3 DOI:https://doi.org/10.5281/zenodo.7431713 for directional overcurrent relays coordination. Electric Power Systems Research, 128, 39-52. 4. Hussain, M. H., Musirin, I., Rahim, S. R. A., Abidin, A. F., & Azmi, A. (2013). Optimal overcurrent relay coordination using particle swarm optimization. In 2013 International Conference on Electrical, Control and Computer Engineering,(InECCE 2013) (Vol. 2013, pp. 42-47). 5. Razavi, F., Abyaneh, H. A., AlDabbagh, M., Mohammadi, R., & Torkaman, H. (2008). A new comprehensive genetic algorithm method for optimal overcurrent relays coordination. Electric Power Systems Research, 78(4), 713-720. 6. Horsfall, D. J., Idoniboyeobu, D. C., Ahiakwo, C. O., & Braide, S. L. (2021). Relay Coordination Analysis in SPDC Forcados Distribution Network for Operation, Planning and Future HBRP Publication Page 1-9 2022. All Rights Reserved View publication stats Expansion. Journal of Newviews in Engineering and Technology (JNET), 3(4). 7. Obire, P., Idoniboyeobu, D. C., & Braide, S. L. Protective Relay Coordination in an Injection Substation Using Short Circuit Analysis. International Journal of Advances in Engineering and Management (IJAEM), 4(8), 753-763. Cite as: Kingsley Okpara Uwho, Hachimenum Nyebuchi Amadi, & Promise Obire. (2022). Short Circuit Analysis for Effective Relay Coordination in Nigerian Port Authority, Rivers state. Journal of Emerging Trends in Electrical Engineering, 4(3), 1–9. https://doi.org/10.5281/zenodo.74317 13 Page 9