Uploaded by Shehzad Qureshi

Final paper answers question 2 and 3 (1)

advertisement
Question 2
Mackerel
a) Risk faced by Mackerel
It is natural to assume that the main objective of a business is the maximisation of shareholder
wealth and in the context of the APV project the main measure of performance will be the profit
made on the contract as this will drive the earnings over which the institutions are concerned.
However, in a decision where there is risk and uncertainty, the company also has to decide on its
appetite for risk. Risk appetite is usually divided into three categories:
• risk averse individuals tend to assume the worst outcome and seek to minimise its effect
• risk seekers are interested in the best outcomes and seek to maximise their returns under
these circumstances
• risk neutral individuals are interested in the most probable outcome
The risks for Mackerel arise from uncertainties in its external environment. The key stakeholders
in this situation are the government (the customer) and Mackerel’s shareholders. The other factor
giving rise to uncertainty is the forecast price of steel, the main raw material in the APV’s
construction.
The shareholders have indicated a concern over earnings volatility and so seem to be risk averse.
This is commercially sensible in a recessionary situation where the company’s survival could be
placed at risk if a large project (such as the APV) were to fail. The project can be seen to be large
for Mackerel as the expected profit is $5m if package 1 is chosen and this is material when
compared to the current operating profit of $20.4m.
A risk averse approach might also be called for where winning the bid could lead to additional
future work so that securing a deal is more important than optimising profit. This appears to be
the case here as the government is the major customer of Mackerel.
The demand level for the APV is also uncertain as the recession could lead to cuts in government
expenditure. Defence spending is often considered more discretionary than spending on public
services (such as pensions) especially if there is not an immediate threat of conflict. Thus, it has
been difficult to predict the probabilities of the different demand levels. Given that there are
significant fixed costs of design and development, these different levels have a material impact
on the return from the project. These problems in quantifying the level of risk will affect the choice
of method of analysing the return from the contract. Mackerel should evaluate the contract using
different methods and come to a conclusion based on the most appropriate one for its objectives
and risk appetite.
A further source of risk is the danger of cost over runs. If successful in its tender, Mackerel will be
working towards a fixed price for the contract ($7.5 m + budgeted variable cost per unit plus 19%).
In the budget, total cost per unit is under $70,000, however, any over runs of actual cost as
compared to budget will reduce the profit margin earned.
Cost per unit
Type 1
Type 2
Type 3
500
62900
65400
67900
750
57900
59567
61233
1000
55400
56650
57900
A major cost risk is the cost of the primary raw material of production (steel). However, this
has been fixed by the forward purchase of the steel for the contract. This has eliminated the risk
of price fluctuations during the contract.
ii)
type 1
type 1
type 1
type 2
type 2
type 2
type 3
type 3
type 3
demand VC
FC
500 23950 7500
750 35925 7500
1000 47900 7500
500 23950 8750
750 35925 8750
1000 47900 8750
500 23950 10000
750 35925 10000
1000 47900 10000
iii)
Maximax
Max
Profit
Type 1
Type 2
Type 3
9101
7851
6601
Maximin
Min
profit
Type 1
Type 2
Type 3
4551
3301
2051
TC
V. REV F.REV
31450 28500.5 7500
43425 42750.75 7500
55400
57001 7500
32700 28500.5 7500
44675 42750.75 7500
56650
57001 7500
33950 28500.5 7500
45925 42750.75 7500
57900
57001 7500
Minimax regret
profit table
Type 1
Type 2 Type 3
500
4550.5 3300.5
2050.5
750 6825.75 5575.8 4325.75
1000
9101
7851
6601
Regret table
Type 1
Type 2 Type 3
500
0
1250
2500
750
0
1250
2500
T. REV
PROFIT Probability
EV
36000.5
4550.5
0.85 3867.925
50250.8 6825.75
0.1 682.575
64501
9101
0.05
455.05 5005.55
36000.5
3300.5
0.25 825.125
50250.8 5575.75
0.5 2787.875
64501
7851
0.25 1962.75 5575.75
36000.5
2050.5
0.2
410.1
50250.8 4325.75
0.5 2162.875
64501
6601
0.3
1980.3 4553.275
1000
Max regret
0
0
1250
1250
2500
2500
To minimise the max regret, Mackerel should choose type 1
Risk seekers and the risk averse will use profit under the different demand scenarios to make the
appropriate choice.
Risk seekers will aim to maximise the possible returns from the different demand scenarios. The
maximax method would be appropriate in this situation and here the company would be advised
to choose design package 1 which will have a maximax profit of $9.1m.
Risk averse decision-makers will aim to maximise the minimum possible returns from the different
demand scenarios. The maximin method would be appropriate in this situation and here the
company would be advised to choose design package 1 which will have a maximin profit of $4.6m.
Pessimistic decision-makers will choose to focus on the lost profit (regret) compared to the best
choice under that demand scenario. They aim to minimise the maximum level of regret that they
can suffer under any demand scenario. This minimax regret method shows the company would
be advised to choose design package 1 which will lead to no regret.
These conclusions should not be surprising as design package 1 has considerably lower fixed costs
and yet is scalable to cope with all levels of demand.
A risk neutral manager does not take an optimistic or pessimistic stance. They will choose the
option that yields the maximum expected value. This method depends on the use of probabilities
for each of the outcomes. The risk manager has attempted to quantify the probabilities of the
different levels of demand given the different design packages employed. It would be wise to
involve both the design and sales teams in these estimates as such estimates are usually highly
subjective, and a broad canvassing of opinion may help to gain more accurate values.
The estimated probabilities allow the calculation of an expected profit for each choice of design
package. The maximum expected profit of $5.6m arises if design 2 is chosen. This is due to the
much greater likelihood of higher demand in that case. Design 3 does not seem to increase the
chances of higher demand sufficiently to outweigh the extra fixed cost of $1.25m compared to
design 2.
iv) Recommendation
In this situation, the choice of method will depend on the risk appetite of Mackerel, whether this
type of decision is likely to be repeated many times and the accuracy of the probability estimates.
As Mackerel shareholders seem risk averse, the profit under the contract is significant compared
to the operating profit of the whole company and the economic environment is difficult so the
low-risk method of maximin seems appropriate. The use of expected values appears questionable
as the probability estimates have not been widely debated and in the current economic
circumstances, the company’s survival may be at risk and so the repeated trials necessary to make
this method valid may not arise.
Design package 1 should be chosen as with unknown probabilities, it carries the least risk. The
company could seek to sharpen the probability estimates and review the implications for company
survival before considering the use of expected values although there is the potential to make an
additional expected profit of $573k if we could justify choosing design 2 over design 1.
The risk over steel prices has been removed by using forward (advance) contracts to cover the
purchase of the material required. As steel is used in many of the company’s products, this should
be investigated as a general risk management technique for the company.
Marking Scheme
i)
ii)
iii)
1 mark per risk identification (1 x 3) and suggestion to overcome it (1 x 3)
12 marks for pay-off table.
1 mark for Maximax
1 mark for maximin
2 marks for expected value
2 marks for minimax regret
4 marks for discussion
iv)
2 marks for JUSTIFIED recommendation
Question 3
Choice of current and proposed performance measures
Current measures
The current measures are all historic, financial ones and so the BSC approach will bring a longer
term view by using non-financial measures which consider those factors which might drive future
growth, for example, those in the learning and growth perspective. The current measures do not
directly link to shareholder value which appears to be the overall aim of the company. A measure
such as economic value added would do this more effectively.
The three measures do give a broad view of financial performance. ROCE is a widely-used measure
which it should be possible to benchmark against competitors. As far as the divisions are
concerned, there is a measure of success in selling through revenue growth, though this may not
be due to only the sales division but also the drugs brought to market by the development
division. Average cost to develop a new drug is a financial measure of the development division’s
performance but this does not measure its aim of innovation in development. Indeed, this
measure may conflict with that aim as cost control of development may hinder innovative
thinking. It would appear more appropriate to have a cost control measure associated with
manufacturing as its goal is to be more efficient. The performance of the manufacturing division
is only measured indirectly through its effect on the financial performance of the company as a
whole.
Consultants’ proposed measures
Monza is planning to implement strategy by innovating drug development, Efficiency in drug
development manufacturing and success in selling their product.
The suggested measures do not seem to deviate much from the existing measures, though there
may be an advantage in this as the new system would be using existing information systems and
known measures in that case. However, this advantage is secondary to the need to find measures
which will drive useful performance in the four perspectives.
The proposed measures from the consultants’ interim report mostly fit within the standard four
perspectives of the BSC, although revenue growth is more appropriate as a measure from the
financial perspective. Customer perspective measures should focus on the strategies which will
achieve success in the eyes of the customers rather than just measuring the results of those
strategies. Examples of this would be measuring the efficacy of the drugs which are developed by
Monza or the reputation of Monza’s medicines among the medical community. Acquisition of
sales to different hospitals via contract can also be measured to increase its sales. This can be
directly linked with the third objective of company.
Taking the others in turn, ROCE does not seem to be directly linked to shareholder value as, for
example, economic value added or net present value would be. ROCE considers the performance
over the whole capital base while the shareholders will be more directly concerned with returns
on their equity investment. As a profit-based measure, ROCE may also be failing to target cashgeneration which is ultimately driving dividend payments and value creation for shareholders.
As already indicated, cost control in business processes is important but other measures of success
such as time to market for the development of new products and quality initiatives should also
be considered.
The fourth perspective is particularly relevant to a high-technology and linked with the first
strategy of Monza where they want to innovate drug development. There will be considerable
competitive advantage in having a highly skilled workforce, however, the measure proposed is
imprecise as it values all training days, whether for knowledge workers or unskilled labourers, as
equally valuable. Measures of the number of innovations within each division may be appropriate
as these will be qualitatively different (new compounds developed, manufacturing quality
improvements and sales techniques/initiatives developed).
Overall, the initial proposed set of measures does appear limited and does not address the overall
aim of Monza or the problem of the narrowness of the existing set of measures.
Note: This is suggested answer. Other relevant justified indicators will earn equal points
Critical evaluation of current performance indicator with JUSTIFIED reasoning
1.5 marks per perspective
Critical evaluation of proposed performance indicators and suggestions with JUSTIFIED
reasoning
1.5 marks per perspective
Connection of proposed KPI with the mission statement
3 marks
No marks will be awarded in case of any recommendation or suggestion without
JUSTIFICATION
Download